WEST DUNBARTONSHIRE COUNCIL 
Report by Chief Officer - Resources 
Infrastructure, Regeneration & Economic Development Committee:
2 November 2022
___________________________________________________________________
Subject: Infrastructure, Regeneration & Economic Development Budgetary
Control Report 2022/23 to Period 5 (31 August 2022)
1. Purpose
1.1 This report provides an update on the financial performance to 31 August
2022 of those services under the auspices of the Infrastructure, Regeneration
& Economic Development Committee (IRED).
2. Recommendations
2.1 Members are asked to:
i) note the contents of this report showing the revenue budget forecast to
overspend against budget by £0.454m (3.53%) at the year-end, of
which £0.030m is COVID-19 related, therefore the non-covid variance
is currently projected at £0.424m adverse, and
ii) note the net projected annual position in relation to relevant capital
projects which is highlighting a projected variance of £14.567m
(30.57%) due to slippage of £12.820m (26.91%) and an underspend of
£1.747m (11.99%).
3. Background
Revenue
3.1 At the meeting of West Dunbartonshire Council on 9 March 2022, Members
agreed the revenue estimates for 2022/23. A total net budget of £12.819m
was approved for IRED services. Since then there have been various
adjustments and some services have moved outwith the IRED remit and the
revised budget is therefore now £12.876m, as follows:
£m
Starting Position 12.819
Cost of Living Allocation 0.057
Revised  Budget 12.876
ITEM 11

Page 2

3.2 Due to the current financial challenges facing the Council, recruitment
restrictions have been implemented, and the filling of vacancies is subject to
active review. For variances linked to this action (beyond the budgeted
turnover targets), in year savings through not filling vacancies, will be
removed from services and held in a central code. This will result in a number
of favourable service variances being removed from services and held
centrally. This will have no impact on the overall projected outturn of the
Council, just on how that outturn is reported. Several service areas, including
those covered by this report, have still to have a final position agreed with the
Chief Officer, so have not been centralised as at period 5, meaning any
favourable variances in relation to their vacancies are still being reported
within the service figures. However this will be updated in future budget
control reports.
3.3 With vacancy savings being removed from service budgets and transferred to
a central budget, other projected overspends identified within services are
now more clearly reported. This demonstrates that, if the Council were only to
meet the budgeted turnover level of vacancies there would be a far more
significant overspend which highlights the extent to which the Council cannot
afford to operate with its current full establishment. 
3.3 The current pay award for staff from 1 April 2022 has been agreed recently.
Any cost beyond the increase assumed in the budget will be required to be
funded. Scottish local authorities are working with CoSLA and the Scottish
Government to ensure adequate funding is available. For the purposes of this
report, it is assumed that the pay award budgeted is adequate and anything
beyond that budgeted will be fully funded.
Capital
3.4 At the meeting of Council on 9 March 2022, Members also agreed the
updated 10 year General Services Capital Plan for 2022/2023 to 2031/2032. 
The next three years from 2021/22 to 2023/24 have been approved in detail
with the remaining years being indicative at this stage. The total project life
budget approved for projects that have either commenced or are due to
commence in that period total £179.698m.
4. Main Issues
Revenue Budget
4.1  The current budgetary position is summarised in Appendix 1.  A more detailed
analysis by service is given in Appendix 2. It should be noted however that
this assumes a 2% pay award. In light of the most recent pay award
negotiations it is likely that the actual pay award will be higher than 2%. Based
on the current offer being negotiated which is around 5% the increase in cost
would be an additional revenue cost of  £0.887m and capital cost of £0.103m
giving an overall additional cost of £0.990. Of this £0.756m will be covered by
additional Scottish Government funding leaving a balance of £0.230m
unfunded of which £0.171m is revenue and £0.069 is capital.

Page 3

4.2 Of the 13 services monitored 7 are showing either a favourable or nil variance,
with 6 services showing an adverse variance. Comments are shown in
Appendix 3 when there are projected net annual variances greater than
£0.050m and also where the net variance is below £0.050m but there are
offsetting variances of over £0.050m within the service.  
4.3 Appendix 1 shows the probable outturn for the services at £13.330m. As the
annual budget is £12.876m there is currently a projected adverse variance for
the year of £0.454m, of which £0.030m is COVID-19 related, therefore the
non-covid variance is currently projected at £0.424m adverse.
4.4 Officers will continue to manage the budgets as closely as possible
throughout the year and it is hoped that by tight budgetary control expenditure
may be brought in on line.
Capital Budget
4.5 The overall programme summary report is shown in Appendix 4. Information
on projects in the red category for probable underspends or overspends in-
year and in total is provided in Appendices 5 together with additional
information on action being taken to minimise or mitigate slippage and/or
overspends where possible and detail on projects within the green category
are shown in Appendix 6.The analysis shows that for the in-year planned
spend there is currently a projected in-year variance of £14.567m of which
£12.820m relates to project slippage and an in-year underspend of £1.747m.
Officers review regularly the in-year position to consider options to maximise
the effective use of capital resources
4.6 From the analysis within the appendices it can be seen that there are six
project with forecast slippage over £0.500m, as listed as follows:
Project Slippage £m
Vehicle Replacement 2.217
Vehicle Replacement Strategy 1.000
New West Bridgend Community
Centre 1.063
LUF 5.203
Clydebank Can on the Canal 0.657
Viresco 0.750
5. People Implications
5.1 There are no people implications.

Page 4

6. Financial Implications
6.1 Other than the financial position noted above, there are no financial
implications of the budgetary control report. Officers are currently reviewing
budgets and projections with a view to improving the position by financial year
end and progress will be highlighted in future reports to committee.
7. Risk Analysis
7.1 The present variances should be viewed in the knowledge that there are a
number of variable factors which could arise between now and 31 March and
which could affect the year end results for both the revenue and capital
budgets.
8. Equalities Impact Assessment (EIA)
8.1 The report is for noting and therefore no Equalities Impact Assessment was
completed for this report.
9 Consultation
9.1 The views of both Finance and Legal services have been requested on this
report and both have advised there are neither any issues nor concerns with
the proposal. As the report is for noting no further consultation is envisaged.
10. Strategic Assessment
10.1 Proper budgetary control and sound financial practice are cornerstones of
good governance and support Council and officers to pursue the five strategic
priorities of the Council’s Strategic Plan. This report forms part of the financial
governance of the Council. This report is for noting and, therefore, does not
directly affect any of the strategic priorities.
Laurence Slavin
Chief Officer  – Resources
Date:  11 October 2022
Person to Contact: Jackie Thomson - Business Unit Finance Partner, 16
Church Street, Dumbarton, G81 1QL.
e-mail jackie.nicol-thomson@west-dunbarton.gov.uk
Appendices: Appendix 1 - Summary Budgetary Position (Revenue)
Appendix 2– Detailed Budgetary Position (Revenue)
Appendix 3 – Variance Analysis (Revenue)

Page 5

Appendix 4 – Budgetary Position (Capital)
Appendix 5 – Variance Analysis Red Status (Capital)
Appendix 6 - Variance Analysis Green (Capital)
Background Papers: None
Wards Affected: All