WEST DUNBARTONSHIRE COUNCIL 
Report by the Economic Development Manager 
Infrastructure, Regeneration & Economic Development Committee 
27 September 2022 
Subject: Development Strategy for the Artizan Centre     
1 Purpose 
1.1 The purpose of this report is to update Members on the progress made on the
Artizan Centre proposals. It seeks approval for delivery of short term
improvements, and for further work required to progress the redevelopment. 
2. Recommendations 
2.1 It is recommended that Committee:
• Notes the progress made on Artizan Centre proposals
• Authorises procurement and delivery of Phase 1 short term
improvements including  the following:
o Relocation of tenant(s) (6 months)
o Demolition of the rear Artizan units (refer to Appendix 2) (10
months)
o Design and delivery of temporary and permanent landscaping
(12-15 months)
o Development of meanwhile uses on newly vacated land (12-15
months)
o Property improvements including external and internal works (6-
15 months)
o Further detailed feasibility and market studies (3-12 months)
• Authorises procurement and development of detailed feasibility studies
to inform medium and long term development strategy
• Notes that the existing tenants will continue to be supported as part of
the strategy.

Page 2

3. Background 
3.1 Like many town centres nationally, Dumbarton town centre has been shaped
by a number of factors over the recent years, including the ongoing trend of
internet shopping and retail parks as well as most recently, the impact of the
pandemic. The decline of retail in town centres is predicted to continue,
requiring intervention, to reimagine and repurpose how town centres are used
and perceived. 
3.2 West Dunbartonshire Council successfully applied to the UK Government for
Levelling up Fund (LUF) monies to tackle the decline of the town centre and
deliver three key projects in Dumbarton: Glencairn House; Connecting
Dumbarton and the acquisition, part-demolition and costs towards the
redevelopment of the Artizan Centre. The Artizan Centre has now been
purchased by the Council and this presents a unique and exciting opportunity
to redefine the Dumbarton Town Centre (Appendix 1). £5.375 million
(excluding optimism bias) of LUF funding remains to be spent by March 2025
to support the redevelopment of the Artizan site in line with the LUF
outcomes. 
3.3 A team of consultants was appointed to carry out a feasibility study and
prepare a development strategy for the site. Their work has not yet concluded
however it has informed the first stages outlined in this report and will inform
later stages which will be brought back to a future IRED. The consultancy is
almost complete but additional specialist feasibility and design work is
required to make recommendations on detailed long term proposals. 
3.4 The community have a central role to play in shaping the future of their town
centre. A number of consultation events engaging the local community took
place in early 2022, and an online survey was also published. People were
asked how they feel about the Artizan and the town centre, what their
aspirations are and what changes they would like to see introduced. Separate
consultation events were held with external and internal stakeholders.
3.5 Community opinion clearly highlighted the importance of putting the heart
back in the town centre and having a clean welcoming environment. Desire
for vibrant shops, enhanced food and beverage offer, quality public and green
spaces and need for improvements to the built environment featured
frequently in the comments, which informed the progress so far and will shape
the long term development strategy. 
4. Main Issues 
4.1 The overarching objective of the Artizan redevelopment is regeneration of the
Dumbarton Town Centre which seeks to balance the need for economic

Page 3

regeneration, place making and design quality, with the requirement for sound
asset management. A high quality redevelopment of this large and prominent
site would be transformational for the entire town centre and, by extension, for
the whole of Dumbarton. It has a potential to create a lively, welcoming public
space for the community in the heart of the town centre, correct the economic
blight caused by long term vacancies and disrepair, and attract footfall and
spend from both locals and visitors. By projecting a more confident image of
Dumbarton it could generate a momentum for the town to establish itself as
an attractive place to live, work, visit and invest. 
4.2 Artizan Centre has a number of well-established businesses and an active
frontage along the High Street, while the rear part of the centre is mostly
vacant, some buildings are in need of significant repairs and many of the
existing shop units do not meet the needs of the commercial and retail market
requirements. The “Railway to Rock” route connecting the Railway Station
and the Rock and Castle runs through the site and the High Street units are
within the Town Centre Conservation Area. A number of key opportunities and
challenges were identified by the consultants and these will be addressed
through the redevelopment.  They include but are not limited to: 
• Retention of the existing retailers which bring footfall into the town
centre. 
• Reduction of the number of retail units to align with current market
trends.
• Integration of the Denny Theatre and Concord Community Centre into
the redeveloped centre. These well-used facilities can help support
active use of the area and support development of evening uses.   
• Introduction of new green spaces and public realm and square within
the town centre
• Delivery of a development that would enhance the town and become a
focal point of a 20 minute neighbourhood where daily services can be
accessed within a 20 minute walk. 
• New housing to bring more people into the town centre. 
• Any new development should consider the  context of the Town Centre
Conservation Area
• Further evidence is required regarding car parking/ sustainable
requirements within the Town Centre. 
4.3 Local Development Plan 2 (as amended, 2020) shows Artizan Centre as
located within the identified town centre boundary. The Development Strategy
for the town centre supports mixed use development and improvements to the
Artizan Centre. Dumbarton Policy 1 supports a more diverse and vibrant town
centre and encourages a range of uses, where these accord with Policy SC2
– SC2 identifies core town centre areas (Artizan sits within this) and supports
use classes 1, 2, 3, 7, 11 and public houses. Revised urban strategy (2014)
identifies the Artizan Centre as a possible Large Project. The strategy
identifies the Artizan Centre as having a negative impact on parts of the town

Page 4

centre and states the Council will support incremental change or radical
redevelopment. Main uses in this area (including introduction of a traditional
grid pattern to area to north) would be retail, office, some residential, leisure,
food and drink and other appropriate town centre uses. 
4.4 It is considered that a mix of uses within the future redeveloped Artizan
Centre would bring vibrancy back into the town centre and help sustain high
levels of footfall. The uses could include:
• Active frontages on the ground floor – retail or community uses that
create a reason to visit and spend time in the town centre and increase
dwell time
• Housing – different tenure mix to repopulate the town centre, bring
additional footfall and vibrancy and contribute to delivery of 20 minutes
neighborhood principles
• Public spaces and connections - green and sustainable public realm,
facilitating community participation and involvement, creating
opportunities for active travel and connecting Denny Theatre with the
Artizan site, and the Railway to Rock connectivity route.
• A new  development – focal point to increase footfall and create a
strong focal point within the site 
4.5 The Council is committed to sustainable regeneration of the Artizan site and
delivering the vision of a more active and vibrant town centre. While long term
(next 2-8 years) development options are being explored, much of which will
stretch beyond the Levelling Up Fund timescale and will need to be self-
sustaining, we plan to focus on a number of short term improvements (Phase
1) which can be delivered within the next 12 – 15 months. 
4.6 Phase 1 focuses on small scale early interventions and on setting the
direction of travel for long term redevelopment. It will address urgent and
priority requirements, and establishing a high standard of design and delivery. 
Proposed Phase 1 deliverables and activities include the following:
• Relocation of tenant(s) (6 months)
• Demolition of the rear Artizan units (refer to Appendix 2) (10 months)
• Design and delivery of temporary and permanent landscaping including
extension of the Connecting Dumbarton to link the Railway with the
River (12-15 months)
• Development of meanwhile uses on newly vacated land to animate and
bring more activity to the town centre and make best use of vacant
land, and opportunities presented (12-15 months)
• Property improvements including external and internal works (6-15
months)

Page 5

• Further detailed feasibility and market studies to determine feasibility of
a possible future new development, housing and other new uses on
site (3-12 months) 
4.7 An important consideration is that disruption and impact on current tenants is
minimised. The early demolition works will focus on the area of the Artizan to
the rear and west block with the highest number of vacant units and act as a
catalyst for future improvements. 
4.8 New permanent and temporary landscaping will be delivered within the site as
to improve the environment for the users. This could include public
greenspace on newly vacant land, public realm improvements, temporary or
permanent connection with Denny Theatre and a cycle route connecting the
Railway and the River Leven, along the Railway to Rock connectivity spine. 
Meanwhile uses can be introduced to animate and bring more activity to the
town centre and make best use of vacant land. Proposed meanwhile uses
could include introduction of short term community uses and pop-up shops to
vacant units (if available) or outdoor community or commercial events. 
4.9 Specialist consultants will be commissioned to undertake detailed feasibility
studies and market research to inform next phases of the development. The
studies would include:
• A feasibility study and market research to determine feasibility of an
anchor development
• A feasibility study and market research to determine future new uses
on the vacant plots including possible new retail and housing 
4.10 A deliverable and feasible long term vision for the site will be developed
following completion of detailed feasibility and market research studies and
discussions with partners. A number of options will be explored and proposals
will be brought back to a future IRED Committee. 
4.11  Parking remains an important factor of any new development. It will be
necessary to set out how future demand for parking in Dumbarton Town
Centre can be managed, and how an approach to parking can contribute to
the wider policy aims of changing behaviours, reducing dependency on the
car and encouraging alternative ways to access the town centre including
public transport, walking and cycling.. 
4.12 The support of existing retailers, businesses, community planning partners the
community and community-led organisations that already do much to
contribute to the vitality of the town centre will be important in delivering the
vision for Dumbarton. A robust communication and engagement plan will be
produced to ensure that our ambitions for the town are properly conveyed and
that existing stakeholders in the town centre benefit from the vision.

Page 6

4.13 A successful redevelopment of the Artizan site would contribute to the delivery
of national policy priorities including 20 minute neighbourhoods, carbon
reduction, place making and community empowerment. 
5. People Implications 
5.1 Delivery of the vision will require commitment from various Council services
and the utilisation of existing staff resources.  The cross-Service collaboration,
particularly across Regeneration, Planning, Asset Management and
Roads/Transportation and partnerships with external partners will continue. 
6. Financial & Procurement Implications 
6.1 Funding from the Levelling Up Fund must be drawn down by March 2025. A
monitoring and spending plan has been established with Central Government,
to agree a project spend timeframe. To comply with requirement of the fund,
continuous progress must be demonstrated. Delays could reduce the funding
currently available. The LUF grant itself does not commit the Council to fund
any specific component, however, to make best use of resources it is
recommended Phase One proposals proceed. 
6.2 A proportion of the £5.375m available in the Artizan budget will be spent on
Phase One works and activities. Any remaining funds will go towards enabling
future long term development(s) on site, subject to approval by a future IRED
Committee. 
7. Risk Analysis 
7.1  If the LUF grant is not drawn down within the timescales required (March
2025), or grant conditions are not met, there is a risk that not all the funding
will be made available resulting in the further delays and deterioration of
Dumbarton town centre. 
8.       Equalities Impact Assessment 
8.1 An assessment has been carried out. The redevelopment of the Artizan has
relevance to a number of equality groups, and positive impacts were identified
for each.

Page 7

9.     Environmental Sustainability 
9.1     In line with the Council’s Climate Change Strategy, there will be ‘zero carbon’
approach proposals emerging from the Artizan Vision. This will make a
positive contribution to environmental sustainability. In particular additional
greening of the centre and contributions towards a 20 Minute Neighbourhood.
.
10.   Consultation 
10.1 As indicated above there has been extensive consultation on the future of the
Artizan Centre. The views expressed in those engagement events have
informed plans for the short term interventions and will help shape the long
term strategy. Further individual and group consultations will take place during
the next stages. This work will continue, to help ensure confirmed
development will solidify the town as the heart of the community. 
11. Strategic Assessment 
11.1 The vision will support Council’s strategic priorities to:
• improve economic growth;
• improve environmentally sustainable infrastructure; and
• improve the wellbeing of communities. 
Chief Officer:  
Service Area:  Regulatory & Regeneration  
Date:   September 2022  
________________________________________________________________ 
Person to Contact: Gillian McNamara, Economic Development Manager Tel:
0777 442 8294  
gillian.mcnamara@west-dunbarton.gov.uk 
Appendices:  Appendix 1 - Artizan Redevelopment Area 
Appendix 2 - Artizan demolitions Phase 1
Appendix 3 – Equality Impact Assessment

Page 8

Background Papers:  IRED Report 10 June 2021 Levelling Up Fund and
Community Renewal Fund – Proposed Bids
IRED Report 15 September 2021 New Regeneration
Officer Post (LUF) (Fixed Term) 
Wards Affected:  Dumbarton