WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
1
Project Life Financials 83 0 0% 83 0 0%
Current Year Financials 83 0 0% 83 0 0%
Project Description
Project Manager Steven Milne/ John McKenna
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-23 31-Mar-23
2
Project Life Financials 20 13 66% 20 0 0%
Current Year Financials 7 0 0% 7 0 0%
Project Description
Project Manager Steven Milne/ John McKenna
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-23 31-Mar-23
3
Project Life Financials 290 63 22% 290 0 0%
Current Year Financials 216 0 0% 216 0 0%
Project Description
Project Manager Steven Milne/ John McKenna
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-23 31-Mar-23
30 June 2022
Budget Details
Project Life Financials
Spend to Date Variance
Mitigating Action
None available at this time.
Anticipated Outcome
Physical works being carried out by 31/3/23.
Replace existing main hall Air Handling unit at Clydebank Town Hall
Replace existing main hall Air Handling unit at Clydebank Town Hall.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Works are integrated with the new Baths refurbishment. Await design proposals from Vital for approval. Works to be complete by 31 March 2023
to compliment the district heating installation.
Leisure Energy projects - air handling units, upgrade lighting, circulating pumps, and draught proofing
Measures to be installed at both Meadow Centre & Vale of Leven Swimming Pool; new pool hall Air
Handling Units, upgrade lighting, circulating pumps Vale of Leven Swimming Pool, internal and external
lighting and draught proofing.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Works to be passed to Consultancy Services and meeting to be arranged.
Main Issues / Reason for Variance
Further works ordered. Expect full spend by 31 March 2023.
Mitigating Action
None required.
Anticipated Outcome
Delivery of project with full budget spend.
Replace failed heating controls/valves & recommission
Replace failed heating controls/valves & recommission.
Planned End Date Actual End Date
Mitigating Action
All works to be complete in one tender package.
Anticipated Outcome
All works to be completed next financial year 2023/24.

Page 2

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2022
Budget Details
Project Life Financials
Spend to Date Variance
4
Project Life Financials 85 55 64% 85 (0) 0%
Current Year Financials 30 0 0% 27 (3) -10%
Project Description
Project Manager Steven Milne/ John McKenna
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-23 31-Mar-23
5
Project Life Financials 16 14 85% 16 0 0%
Current Year Financials 2 0 0% 2 (0) 0%
Project Description
Project Manager Steven Milne/ John McKenna
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-23 31-Mar-23
6
Project Life Financials 50 0 0% 50 0 0%
Current Year Financials 50 0 0% 50 0 0%
Project Description
Project Manager Steven Milne/ John McKenna
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-23 31-Mar-23
Automatic Meter Readers - Water
Automatic Meter Readers.
Planned End Date Forecast End Date
Water Meter Downsize
Water Meter Downsize.
Main Issues / Reason for Variance
Water meter works to be carried out in the last quarter of the year. Previous works with electricity meter supplier did not meet expectations. Await
resolutions before issuing further orders.
Mitigating Action
None required.
Anticipated Outcome
All works to be completed 2022/23.
Anticipated Outcome
Delivery of project within budget.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Project integrated with Water AMR project. All works to be carried out in the last quarter of the year. Expect full spend.
Mitigating Action
None required
Mitigating Action
None available at this time.
Anticipated Outcome
Works complete 2022/23
Lighting upgrades to LED in schools and Corporate buildings
Upgrade lighting in schools and corporate buildings.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Initial building surveys being carried out with layout of existing lighting. Expect full spend depending on access restrictions and availability of DLO
to carry out the work.

Page 3

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2022
Budget Details
Project Life Financials
Spend to Date Variance
7
Project Life Financials 2,188 58 3% 1,651 (538) -25%
Current Year Financials 1,651 58 4% 1,450 (201) -12%
Project Description
Project Manager Gillian McNamara/ Michael McGuinness
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-23 31-Mar-24
8
Project Life Financials 9,782 4,928 50% 9,797 15 0%
Current Year Financials 2,223 30 1% 2,075 (148) -7%
Project Description
Project Manager Gillian McNamara/ Michael McGuinness
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-24 31-Mar-24
9
Project Life Financials 1,166 1,023 88% 1,166 0 0%
Current Year Financials 143 0 0% 143 0 0%
Project Description
Project Manager Gillian McNamara/ Michael McGuinness
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-23 31-Mar-23
Planned End Date Forecast End Date
Main Issues / Reason for Variance
LED budget is invested across our town centres and strategic sites and is used to develop and implement projects as well as providing match
funding to lever in external funding. During 2022/2023 the key projects to be developed and delivered include a contribution towards Smollett
Fountain public realm, enabling works at Mitchell Way subject to the timescale of the developer, development costs associated with Dumbarton
Waterfront, the Arc of Attraction Strategy and in Clydebank implementation of the Development Framework and delivery of the Activities Centre.
Many regeneration projects are subject to factors outwith Council control and close monitoring of the programming is required. A contingency is
included for increasing costs and new funding opportunities.
Mitigating Action
None available at this time.
Regeneration/Local Economic Development
Budget to facilitate the delivery of Regeneration throughout West Dunbartonshire, aligned to the Economic
Strategy. External funding will be sought to maximise opportunities for redevelopment of these sites.
Town Centre Fund
Scottish Government funding to help improve local town centres.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
The remaining Town Centre Fund will be spent on the Smollett Fountain public realm works which will be completed by the end of the financial
year.
Main Issues / Reason for Variance
The remaining Regeneration Fund projects are Dumbarton Waterfront Path; the contribution towards the costs of Glencairn House; Connecting
Dumbarton; and the Scottish Marine Technology Park at the former Carless site. As Levelling Up Fund is programmed to be spent before
Regeneration Fund for Glencairn House and Connecting Dumbarton, it is not anticipated that any Regeneration Fund will be spent on these
projects during this financial year and will be carried forward. Spend against The £2.0m Clyde Mission funding for SMTP will continue during the
financial year 2022/2023 before an agreement is reached on the £2.0m of Regeneration Fund investment. Dumbarton Waterfront Path will be
developed according to landowner timescales, and only some spend is anticipated this year.
Mitigating Action
Programme management approach to delivery.
Anticipated Outcome
Progress towards delivery of planned projects from Economic Development Strategy and Charrette Action Plans albeit later than originally
anticipated.
Anticipated Outcome
Improved town centres and strategic sites across West Dunbartonshire.
Regeneration Fund
Funding to implement major regeneration projects linked to community charrettes. 
Planned End Date Forecast End Date
Mitigating Action
None available at this time.
Anticipated Outcome
Regenerated Town Centres.

Page 4

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2022
Budget Details
Project Life Financials
Spend to Date Variance
10
Project Life Financials 1,456 139 10% 1,456 0 0%
Current Year Financials 1,317 0 0% 1,112 (205) -16%
Project Description
Project Manager Gillian McNamara/ Michael McGuinness
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-23 31-Mar-23
11
Project Life Financials 747 0 0% 747 0 0%
Current Year Financials 747 0 0% 747 0 0%
Project Description
Project Manager Gillian McNamara/ Michael McGuinness
Chief Officer Peter Hessett
Project Lifecycle 31-Dec-22 30-Jun-23
12
Project Life Financials 125 56 45% 125 0 0%
Current Year Financials 69 0 0% 69 0 0%
Project Description
Project Manager Gillian McNamara/ Michael McGuinness
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-23 30-Jun-23
Anticipated Outcome
Place-based improvements that advance Scottish Government's priorities of 20 min neighbourhoods and carbon zero.
Clydebank Can On The Canal
New activities centre in Clydebank Town Centre.
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
The budget includes a £0.641m contribution to Titan Boulevard at Queens Quay and £0.441m towards implementation of Alexandria Masterplan
projects.
Mitigating Action
Programme involves  expenditure over a number of projects led by different services. Regular reporting between services will help early
identification of risk.
Place Based Investment Programme
Scottish Government Funding to establish a Place-Based Investment Programme to ensure that all place
based investments are shaped by the needs and aspirations of local communities.
Mitigating Action
None available at this time.
Anticipated Outcome
Successful LUF applications that meet UK Government's over-riding objective of Levelling Up and transformational regeneration.
Levelling up
Successful LUF applications that meet UK Government's over-riding objective of Levelling Up and
transformational regeneration.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
This capacity funding was awarded by UK Government to assist with development of LUF bids. WDC has been awarded a grant from LUF
Round 1 and the capacity funding will be used in part to produce Artizan Centre redevelopment options. The balance will be used for
Roads/Transportation to develop a major transportation bid for LUF2.
Main Issues / Reason for Variance
Kier is appointed to design and deliver the Activities Centre at Clydebank Town Centre. Design of the project is underway and a commencement
date for construction is to be confirmed however this will be later than anticipated due to some administrative delays.
Mitigating Action
None available at this time.
Anticipated Outcome
New community-run activities centre in Clydebank Town Centre.

Page 5

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2022
Budget Details
Project Life Financials
Spend to Date Variance
13
Project Life Financials 21,578 21,628 100% 21,748 170 1%
Current Year Financials 120 0 0% 120 0 0%
Project Description
Project Manager Patricia Rowley/ Craig Jardine
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-23 31-Mar-23
14
Project Life Financials 11,100 0 0% 11,100 0 0%
Current Year Financials 3,600 0 0% 3,600 0 0%
Project Description
Project Manager Patricia Rowley/ Craig Jardine
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-24 31-Mar-24
15
Project Life Financials 34,050 2,726 8% 34,049 (1) 0%
Current Year Financials 986 46 5% 986 (0) 0%
Project Description
Project Manager Patricia Rowley/ Craig Jardine
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-27 31-Mar-27
Main Issues / Reason for Variance
Consultancy costs financed by income received
Mitigating Action
None required
Anticipated Outcome
Consultancy costs for District Heating
District Heating
Consultancy Costs for District Heating
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Regular updates are provided at every Council meeting and monthly Project Board meetings and to City Deal.  The main issues contained within
the new Council's approved Outline Business Case are still valid, which include Exxon's remediation strategy, land transfer arrangements and
issues relating to adjoining owners.  WDC Consultants are monitoring the remediation process to ensure compliance with specification, also
Esso are independently monitoring the remediation works.  Final Business Case submission is November 2022. Through the Scape framework
we are working closely with Balfour Beatty to achieve a formal pre construction agreement to allow the detailed design works to commence and
the full construction programme to be developed. Agreements in principle are progressing with third party land owners.
Mitigating Action
None required.
Mitigating Action
None available at this time.
Anticipated Outcome
Project will be delivered on budget.
Exxon City Deal
As part of the City Deal project the WDC Exxon site at Bowling regeneration with alternative A82 route
included.
District Heating Network Expansion
District Heating Network Expansion.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Network expansion to GJNH (Golden Jubilee National Hospital) will commence pending approval to proceed by the GJNH Board. 
Anticipated Outcome
Delivery of the project on time and within the increased budget.

Page 6

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2022
Budget Details
Project Life Financials
Spend to Date Variance
16
Project Life Financials 8,535 124 1% 8,535 (0) 0%
Current Year Financials 1,715 5 0% 1,715 0 0%
Project Description
Project Manager Sharon Jump/ Craig Jardine
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-25 31-Mar-25
17
Project Life Financials 1,912 124 7% 1,912 0 0%
Current Year Financials 1,912 124 7% 1,912 (0) 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-23 31-Mar-23
18
Project Life Financials 350 9 3% 350 0 0%
Current Year Financials 0 0 0% 0 0 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-24 31-Mar-24
Depot Rationalisation
Depot Rationalisation.
Main Issues / Reason for Variance
Works progressing.
Mitigating Action
None available at this time.
Anticipated Outcome
Full budget spend anticipated and request for FY22/23 acceleration of budget received.
Anticipated Outcome
Project business case will be brought back to project board and Council.
Building Upgrades and H&S - lifecycle & reactive building upgrades
Lifecycle and reactive building upgrades.
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Design Team have been appointed to develop feasibility options for the DRP Project, currently in stage 1 of this phase reviewing service
requirements.  The conclusion of the feasibility report will provide input for the options appraisal exercise.  The intention would be to bring a
business case to the IRED Committee in November 2022.
Mitigating Action
None available at this time.
Mitigating Action
None available at this time.
Anticipated Outcome
To deliver new sports changing facility.
New Sports Changing Facility Dumbarton West (Old OLSP site) 
New Sports Changing Facility Dumbarton West (Old OLSP site) 
Planned End Date Forecast End Date
Main Issues / Reason for Variance
The budget for this project has been rephased to FY 2023/2024.

Page 7

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2022
Budget Details
Project Life Financials
Spend to Date Variance
19
Project Life Financials 150 16 11% 150 0 0%
Current Year Financials 134 0 0% 134 (0) 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-21 31-Mar-23
20
Project Life Financials 750 664 89% 750 0 0%
Current Year Financials 86 0 0% 86 (0) 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-22 31-Mar-23
21
Project Life Financials 2,375 87 4% 2,375 (0) 0%
Current Year Financials 1,090 3 0% 1,090 (0) 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-22 31-Mar-24
Holm Park & Yoker Athletic FC
Develop a new 3G pitch to act as a home venue for Clydebank FC with extensive community access.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Project now complete awaiting invoices.
Main Issues / Reason for Variance
Project had been delayed due to a number of COVID-19 related issues and utilities issues.  Unit is now in production but delay to site due to the
utility disconnection and demolition works. 
Mitigating Action
None available at this time.
Anticipated Outcome
To deliver new sports changing facility.
New Sports Changing Facility at Lusset Glen in Old Kilpatrick
New Sports Changing Facility at Lusset Glen in Old Kilpatrick
Planned End Date Forecast End Date
Anticipated Outcome
New build community facility.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Planning Permission received and currently working on internal room layouts to confirm overall budget required to complete project.  Previous
delays, include application for planning permission which Officers elongated due to requirement to go to design panel, and delays in additional
information being able to be provided to Planning due to site visits not being able to be carried out because of COVID-19 restrictions.  Currently
room layouts are being discussed with the group, this will then allow a review of costs to minimise the additional budget required to complete the
Mitigating Action
None available at this time.
Mitigating Action
None available at this time.
Anticipated Outcome
Project delivered on budget.
New Westbridgend Community Centre
New Westbridgend Community Centre

Page 8

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2022
Budget Details
Project Life Financials
Spend to Date Variance
22
Project Life Financials 150 0 0% 150 0 0%
Current Year Financials 150 0 0% 150 0 0%
Project Description
Project Manager Michelle Lynn
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-25 31-Mar-25
23
Project Life Financials 78 0 0% 78 0 0%
Current Year Financials 78 0 0% 78 0 0%
Project Description
Project Manager Martin Feeney
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-22 31-Mar-23
24
Project Life Financials 45 0 0% 45 0 0%
Current Year Financials 45 0 0% 45 0 0%
Project Description
Project Manager Martin Feeney
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-22 31-Mar-23
Changing Places Toilet Provision
Changing places toilet provision in four public buildings - Balloch bus stance toilets, Concord Community
Centre, Dalmuir Community Centre and Clydebank East Community Centre.
Planned End Date Forecast End Date
Mitigating Action
None available at this time.
Anticipated Outcome
Project delivered within budget.
Elevated Platforms (Building Services)
Elevated Platforms (Building Services).
Purchase of 3 Welfare Units
At Council meeting on 30th August 2017 it was agreed to purchase 3 Welfare Units as a spend-to-save
proposal.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Welfare Units will be purchased by the end of the financial year.
Main Issues / Reason for Variance
Plans have been prepared and projects will be progressed by the end of the financial year.
Mitigating Action
None available at this time.
Anticipated Outcome
Project delivered within budget.
Anticipated Outcome
Project delivered within budget.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
It is anticipated that spend will be achieved by the end of the financial year 2022/2023.
Mitigating Action
None available at this time.

Page 9

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2022
Budget Details
Project Life Financials
Spend to Date Variance
25
Project Life Financials 405 2 0% 405 0 0%
Current Year Financials 405 2 0% 405 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
26
Project Life Financials 472 406 86% 472 0 0%
Current Year Financials 66 0 0% 66 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
27
Project Life Financials 1,726 1,718 100% 1,726 0 0%
Current Year Financials 13 5 38% 13 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
Main Issues / Reason for Variance
Projects are currently being developed to deliver better access in our parks, cemeteries and open spaces. Full budget spend anticipated in
2022/23.
Mitigating Action
None required at this time.
Anticipated Outcome
Better access with parks, cemeteries and open spaces.
Public non-adopted paths and roads
Upgrades to drainage and lighting to enhance the lifespan of paths and roads within  facilities in public
parks, cemeteries and civic spaces.
Planned End Date Forecast End Date
Anticipated Outcome
Budget to be vired to Posties Park Project.
Environmental Improvement Fund
This fund has been created to deliver environmental improvement projects for communities throughout West
Dunbartonshire.
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
This fund has now closed. Funding to be vired to Posties Park project.
Mitigating Action
None required
Community Sports Fund
Match funding of up to 75% for local sports clubs to develop business cases to improve facilities.
Main Issues / Reason for Variance
Remaining budget rephased from 2021/22 to progress with tree planting in 2022/23 in line with the Councils Climate Change and Biodiversity
action plans.  Full budget spend anticipated.
Mitigating Action
None required at this time.
Anticipated Outcome
Improvements to the environment of West Dunbartonshire.

Page 10

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2022
Budget Details
Project Life Financials
Spend to Date Variance
28
Project Life Financials 50 37 73% 50 (0) 0%
Current Year Financials 13 0 0% 13 (0) 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
29
Project Life Financials 220 214 97% 220 0 0%
Current Year Financials 7 0 0% 7 (0) 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 03-Apr-21 31-Mar-22
30
Project Life Financials 200 0 0% 200 0 0%
Current Year Financials 30 0 0% 30 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
31
Project Life Financials 581 59 10% 581 (0) 0%
Current Year Financials 122 0 0% 122 (0) 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-22 31-Mar-22
Mitigating Action
None required at this time.
Anticipated Outcome
Sustainable burial environment for local residents.
Kilmaronock Cemetery Extension
Extension of existing cemetery at Kilmaronock. 
Planned End Date Forecast End Date
Main Issues / Reason for Variance
This budget will be used to develop an area of the existing Cemetery for additional burials.  Project scope has now been developed and will be
tendered under the minor civils framework.  Budget spend anticipated in 2022/23.
Main Issues / Reason for Variance
Project works complete.  Retentions to be paid in 2022/23.
Mitigating Action
None required at this time.
Anticipated Outcome
New all weather tennis courts.
Sports Facilities Upgrades - Argyll Park - Construction of 3 All Weather Tennis Courts
Project is part of wider investment in sporting facilities and is dependent on match funding from Sports
Scotland. Agreement in principle to wider WDC strategic priorities.
Planned End Date Actual End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Consultant and design team fees for resurfacing of 3G pitch at East End Park.
Mitigating Action
None required.
East End Park Resurfacing
Resurfacing of 3G pitch at East End Park.
Main Issues / Reason for Variance
Development of play areas to improve accessibility and inclusiveness of play areas throughout West Dunbartonshire.
Mitigating Action
None required at this time.
Anticipated Outcome
Renewal of play parks
Anticipated Outcome
Resurfacing of 3G pitch at East End Park.
Play Parks Grant Funding
Renew and replace play park equipment
Planned End Date Forecast End Date

Page 11

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2022
Budget Details
Project Life Financials
Spend to Date Variance
32
Project Life Financials 210 0 0% 210 0 0%
Current Year Financials 10 0 0% 10 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 30-Nov-23 30-Nov-23
33
Project Life Financials 25 0 0% 25 0 0%
Current Year Financials 25 0 0% 25 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
34
Project Life Financials 102 0 0% 102 0 0%
Current Year Financials 102 0 0% 102 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
Balloch Mountain Bike Track
Develop a mountain bike skills trail at Balloch Castle Country Park.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Design fees to develop Mountain bike skills trail in Balloch country park. Project to commence April 2023 and works to be complete by November
2023.
Anticipated Outcome
Large bins provided for high traffic areas
Knowes Nature Reserve
Nature resource for Faifley Community
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Supply and install extra large litter bins as a pilot project within hotspot problem areas. Project is due to commence August 2022 and completion
is anticipated by March 2023.
Mitigating Action
None required at this time.
Mitigating Action
None required at this time.
Anticipated Outcome
Mountain bike track
Large bins for high traffic areas (pilot)
Supply and install extra large litter bins as a pilot project within hotspot problem areas.
Main Issues / Reason for Variance
Funding received from Nature Restoration Fund to build nature resource for Faifley community. Project due to commence 1st April 2022 and
completion anticipated by November 2022.
Mitigating Action
None required at this time.
Anticipated Outcome
Nature resource for Faifley Community

Page 12

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2022
Budget Details
Project Life Financials
Spend to Date Variance
35
Project Life Financials 740 350 47% 350 (390) -53%
Current Year Financials 390 0 0% 0 (390) -100%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Jul-22 31-Jul-22
36
Project Life Financials 683 0 0% 566 (117) -17%
Current Year Financials 683 0 0% 566 (117) -17%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
37
Project Life Financials 203 0 0% 107 (96) -47%
Current Year Financials 107 0 0% 107 (0) 0%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
Mitigating Action
None required at this time.
Anticipated Outcome
To provide people of West Dunbartonshire additional space to help adhere to social distancing guidelines.
Spaces for People
Funding has been awarded from Sustrans to assist with social distancing measures required as a result of
the COVID-19 pandemic.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
The programme is now complete and there will be no further expenditure.
Main Issues / Reason for Variance
To develop projects including Balloch Park Phase 2, and other projects principally around National Cycle Network 7 and further pedestrian
dropped kerbs
Mitigating Action
None required at this time.
Anticipated Outcome
To improve connectivity and enhanced Cycling routes within West Dunbartonshire.
Cycling, Walking and Safer Streets
Introduction of enhanced walking routes and traffic calming schemes to introduce safer streets within West
Dunbartonshire.
Planned End Date Forecast End Date
Mitigating Action
None required at this time.
Anticipated Outcome
To improve Footways in West Dunbartonshire.
Footways/Cycle Path Upgrades
Renewal and/or enhancement of failed footpaths/cycle paths through West Dunbartonshire.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Projects and locations still to be decided.

Page 13

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2022
Budget Details
Project Life Financials
Spend to Date Variance
38
Project Life Financials 200 0 0% 5 (195) -97%
Current Year Financials 5 0 0% 5 0 0%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
39
Project Life Financials 60 55 91% 60 0 0%
Current Year Financials 5 0 0% 5 0 0%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
40
Project Life Financials 314 215 68% 314 (0) 0%
Current Year Financials 100 0 0% 100 (0) 0%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Budget to be used for retention payment from last years surfacing of Dumbarton East footways.
Mitigating Action
None required at this time.
Additional Pavement Improvements
Extra funding to accelerate pavement maintenance and improvements across West Dunbartonshire.
Turnberry Homes - traffic calming/ management at Turnberry housing development off Castle Road
Funding has been received from Turnberry Homes and will be used to introduce traffic calming and traffic
management measures to mitigate the impact of additional traffic accessing the housing development off
Castle Road, Dumbarton.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Consultation completed 2021/2022 and speed humps will be installed prior to 31 March 2023.
Anticipated Outcome
To improve Footways in West Dunbartonshire.
Anticipated Outcome
To provide Electric Vehicle Charging points within West Dunbartonshire.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Charging points to be installed at Moss O' Balloch park by the end of this financial year.
Mitigating Action
None required at this time.
Mitigating Action
None required at this time.
Anticipated Outcome
Traffic calming to be installed in Dumbarton East.
Electrical Charging Points - Rapid Charge
Funding has been awarded from Transport Scotland for the Installation of electrical charging points

Page 14

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2022
Budget Details
Project Life Financials
Spend to Date Variance
41
Project Life Financials 1,257 0 0% 1,257 0 0%
Current Year Financials 1,257 0 0% 1,257 0 0%
Project Description
Project Manager Raymond Walsh/ Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
42
Project Life Financials 500 0 0% 500 0 0%
Current Year Financials 500 0 0% 500 0 0%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
43
Project Life Financials 149 0 0% 149 0 0%
Current Year Financials 149 0 0% 149 0 0%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
Flood Risk Management
Enhancement of drainage infrastructure to ensure compliance with Flood Risk Management Act 2009.
Planned End Date Forecast End Date
Mitigating Action
None required at this time.
Anticipated Outcome
Projects should be complete within budget.
Infrastructure - Flooding
Essential renewal of failed drainage assets to minimise flood risk within West Dunbartonshire.
Flood Prevention
Various flood prevention projects.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Plans are under consideration by officers.
Main Issues / Reason for Variance
A detailed design for Gruggies Burn will be undertaken by the end of the financial year.
Mitigating Action
None required at this time.
Anticipated Outcome
Project should be complete within budget.
Anticipated Outcome
Intention is to complete works within budget.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Small value projects to tackle flooding events in various areas
Mitigating Action
None required at this time.

Page 15

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2022
Budget Details
Project Life Financials
Spend to Date Variance
44
Project Life Financials 800 181 23% 800 0 0%
Current Year Financials 620 0 0% 620 0 0%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
45
Project Life Financials 1,627 5 0% 1,075 (552) -34%
Current Year Financials 1,627 5 0% 1,075 (552) -34%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
46
Project Life Financials 3,444 7 0% 3,444 0 0%
Current Year Financials 3,444 7 0% 3,444 (0) 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
Main Issues / Reason for Variance
Awaiting outcome of Scottish Government & SEPA deliberations, however officers are hopeful full budget spend can be incurred by the end of
the financial year.
Mitigating Action
None required at this time.
Anticipated Outcome
Project should be completed within budget.
River Leven Flood Prevention Scheme
River Leven Flood Prevention Scheme.
Planned End Date Forecast End Date
Mitigating Action
None required at this time.
Anticipated Outcome
Improve accessibility to Public Transport and improve journey time reliability.
Strathclyde Partnership for Transport - Bus, cycling and walking infrastructure improvements & Park and Rides
Strathclyde Partnership for Transport - Bus, cycling and walking infrastructure improvements.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Work will be undertaken during this financial year for A8014 Kilbowie Rd, A814 Congestion Measures, Balloch Station Park & Ride and Bus
Infrastructure Improvements. All of these projects will be undertaken by Roads Services.
Main Issues / Reason for Variance
Roads Operations are progressing an extensive surfacing program and have a number of schemes to be completed by the end of the financial
year.
Mitigating Action
None required at this time.
Anticipated Outcome
Intention is to complete various surfacing works by the end of March 2023.
Infrastructure - Roads
Infrastructure - Roads.
Planned End Date Forecast End Date

Page 16

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2022
Budget Details
Project Life Financials
Spend to Date Variance
47
Project Life Financials 12 0 0% 12 0 0%
Current Year Financials 12 0 0% 12 (0) 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
48
Project Life Financials 97 35 36% 97 (0) 0%
Current Year Financials 55 0 0% 55 (0) 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
49
Project Life Financials 15,053 421 3% 15,053 (0) 0%
Current Year Financials 1,524 0 0% 1,524 0 0%
Project Description
Project Manager Sharron Worthington
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
Street lighting and associated electrical infrastructure
WDC is responsible for the maintenance of 18,000 street lighting columns and associated illuminated signs
and bollards.  This budget is required for this infrastructure.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Budget will be used for any service work carried out by Scottish Power before or after column replacement works.
Anticipated Outcome
Intention is to complete works within budget.
Gruggies Burn Flood Prevention
Commission of Gruggies Flood Prevention Scheme.
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
This budget will be utilised for depot rationalisation works during the financial year.
Mitigating Action
None available at this time.
Mitigating Action
None available at this time.
Anticipated Outcome
Intention is to complete works within budget.
Depot Improvement Works
Improvement of WDC Roads Depot.
Main Issues / Reason for Variance
Budget to be used for a detailed design for Gruggies Burn.
Mitigating Action
None available at this time.
Anticipated Outcome
Project should be completed within budget.

Page 17

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2022
Budget Details
Project Life Financials
Spend to Date Variance
50
Project Life Financials 2,325 1,007 43% 2,325 0 0%
Current Year Financials 693 0 0% 693 (0) 0%
Project Description
Project Manager Sharron Worthington
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-26 31-Mar-26
51
Project Life Financials 2,325 0 0% 2,325 0 0%
Current Year Financials 0 0 0% 0 0 0%
Project Description
Project Manager Sharron Worthington
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-26 31-Mar-26
52
Project Life Financials 4,300 3,802 88% 4,300 (0) 0%
Current Year Financials 498 0 0% 498 (0) 0%
Project Description
Project Manager Sharron Worthington
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-22 31-Mar-22
Mitigating Action
None required at this time.
Anticipated Outcome
To provide an improved A813.
A813 Road Improvement Phase 2
A813 Road Improvement Phase 2.
A813 Road Improvement Phase 1
A813 Road Improvement Phase 1.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Plans have been developed for carriageway widening and footway and cycleway construction between Strathleven and Lions Gate.  There are
ongoing discussions with Aggreko and other land owners in regards to access and land acquisition with construction commencing during
2022/2023.
Main Issues / Reason for Variance
Works substantially complete. Additional works as a compensation event due to start on Wallace street in July 2022.
Mitigating Action
None required at this time.
Anticipated Outcome
Project should be completed within budget enhancing the A814 through Clydebank.
Anticipated Outcome
To provide an improved A813.
Clydebank Charrette, A814
Clydebank Charrette, A814
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
These works are not due to commence until Phase 1 has been completed.
Mitigating Action
None required at this time.

Page 18

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2022
Budget Details
Project Life Financials
Spend to Date Variance
53
Project Life Financials 3,930 3,846 98% 3,846 (84) -2%
Current Year Financials 84 0 0% 0 (84) -100%
Project Description
Project Manager Cameron Muir
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-22 31-May-21
54
Project Life Financials 1,039 650 63% 1,039 (0) 0%
Current Year Financials 117 6 5% 117 (0) 0%
Project Description
Project Manager Cameron Muir
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
55
Project Life Financials 80 0 0% 80 0 0%
Current Year Financials 40 0 0% 40 0 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Works to Renton footbridge are now complete and work will commence on the other bridges.
Mitigating Action
None available at this time.
Mitigating Action
None required.
Anticipated Outcome
To provide an improved Lomond Bridge.
Protective overcoating to 4 over bridges River Leven
To overcoat 4 bridges over River Leven.
A811 Lomond Bridge
Upgrade of Lomond Bridge.
Planned End Date Actual End Date
Main Issues / Reason for Variance
Works to Lomond Bridge were completed May 2021. No further costs expected.
Main Issues / Reason for Variance
New Plant to be purchased
Mitigating Action
None required.
Anticipated Outcome
To purchase equipment.
Anticipated Outcome
To upgrade bridges within West Dunbartonshire.
Roads Plant
Purchase of Roads plant and equipment.
Planned End Date Forecast End Date

Page 19

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2022
Budget Details
Project Life Financials
Spend to Date Variance
56
Project Life Financials 350 0 0% 350 0 0%
Current Year Financials 350 0 0% 350 0 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
57
Project Life Financials 300 0 0% 300 0 0%
Current Year Financials 300 0 0% 300 0 0%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
58
Project Life Financials 1,000 0 0% 1,000 0 0%
Current Year Financials 1,000 0 0% 1,000 0 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
Footway Resurfacing (RAMP)
Footway resurfacing
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Projects and locations to be decided.
Anticipated Outcome
To upgrade traffic signals.
Roads improvements
Various road improvement projects
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Projects and locations to be decided.
Mitigating Action
None required.
Mitigating Action
None required.
Anticipated Outcome
Resurface footways.
Traffic Signal Upgrades
Upgrade Traffic Signals
Main Issues / Reason for Variance
Projects and locations to be decided.
Mitigating Action
None required.
Anticipated Outcome
Improvements to roads

Page 20

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2022
Budget Details
Project Life Financials
Spend to Date Variance
59
Project Life Financials 100 0 0% 100 0 0%
Current Year Financials 100 0 0% 100 0 0%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
60
Project Life Financials 1,000 0 0% 1,000 0 0%
Current Year Financials 1,000 0 0% 1,000 0 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
61
Project Life Financials 30 0 0% 30 0 0%
Current Year Financials 30 0 0% 30 0 0%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
62
Project Life Financials 400 0 0% 400 0 0%
Current Year Financials 400 0 0% 400 0 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-22 31-Mar-23
Mitigating Action
None required.
Anticipated Outcome
Renewal of street signage.
Pavement improvements
Various pavement improvement projects.
Street sign renewal
Renewal of street signs
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Projects and locations to be decided.
Main Issues / Reason for Variance
Expenditure on water safety equipment will be made as required throughout the year.
Mitigating Action
None required
Anticipated Outcome
Water safety equipment as required.
Anticipated Outcome
Improvement to pavements.
Water Safety
To develop Water Safety Policy & enhance water safety equipment in WDC
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Projects and locations to be decided.
Mitigating Action
None required.
Main Issues / Reason for Variance
Delivery expected by September 2022 and full budget spend expected before the end of the financial year.
Mitigating Action
None available at this time.
Anticipated Outcome
Project delivered within  budget.
Purchase of gritters
Purchase of gritters.
Planned End Date Forecast End Date

Page 21

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2022
Budget Details
Project Life Financials
Spend to Date Variance
63
Project Life Financials 1,980 0 0% 1,980 0 0%
Current Year Financials 180 0 0% 45 (135) -75%
Project Description
Project Manager Kenny Lang
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
64
Project Life Financials 160 0 0% 160 0 0%
Current Year Financials 80 0 0% 80 0 0%
Project Description
Project Manager Kenny Lang
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
65
Project Life Financials 1,150 1,124 98% 1,150 (0) 0%
Current Year Financials 26 0 0% 26 0 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-22 30-Apr-22
Waste Transfer Station
The design, development and construction of a recycling and bulk waste transfer facility that will ensure all
recycling material can be sorted and disposed off appropriately to ensure compliance with landfill ban in
2025.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Consultant project nearing completion and spend will be made thereafter.
Anticipated Outcome
Project delivered within  budget.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Compactors have now been delivered.
Mitigating Action
None Required.
Mitigating Action
None Required.
Anticipated Outcome
Project delivered within budget.
Replacement of compactors at Dalmoak civic amenity site
The purchase of 2 compactors for the Council civic amenity site at Dalmoak.
Mitigating Action
None required.
Anticipated Outcome
To create new community facilities with additional space for early years provisions.
Dalmonach CE Centre
To create new community facilities with additional space for early years provisions.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Project complete and final account to be agreed.