West Dunbartonshire Council · 17 August 2022
Back to Infrastructure, Regeneration & Economic Development Committee — 17 August 2022 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Supplementary
Agenda
Infrastructure, Regeneration and
Economic Development
Committee
Date: Wednesday, 17 August 2022
Time: 10:00
Format: Hybrid meeting
Contact:   Email: committee.admin@west-dunbarton.gov.uk
Dear Member
ITEMS TO FOLLOW
I refer to the agenda for the above Meeting of the Infrastructure,
Regeneration and Economic Development Committee which was issued on 4
August 2022 and now enclose copies of the reports relating to Items 6, 14
and 16, which were not available for issue at that time. 
Yours faithfully
PETER HESSETT
Chief Executive
Page 53

Page 2

Note referred to:-
6 ROADS & NEIGHBOURHOOD DELIVERY PLAN 2021/22    57- 70
– YEAR END PROGRESS
Submit report by the Chief Officer – Roads & Neighbourhood, providing the
year-end progress of the 2021/22 Delivery Plan. 
14 SUBLEASE OF 3 BIRCH ROAD AND 1 OVERBURN  71 - 74
AVENUE, BROADMEADOW INDUSTRIAL ESTATE, 
DUMBARTON           
Submit report by the Chief Officer – Supply, Distribution and Property, seeking
approval of the Committee that the Council grant consent for the sublease of
3 Birch Road and 1 Overburn Avenue, Broadmeadow Industrial Estate,
Dumbarton. 
16 INFRASTRUCUTRE, REGENERATION & ECONOMIC            75 - 115 
DEVELOPMENT BUDGETARY CONTROL REPORT 
2022/23 TO PERIOD 3 (30 JUNE 2022) 
Submit report by the Chief Officer – Resources, providing an update on the
financial performance to 30 June 2022 of those services under the auspices
of the Infrastructure, Regeneration & Economic Development Committee. 
Page 54

Page 3

Distribution:- 
Councillor Craig Edward 
Councillor David McBride (Chair)
Councillor Jonathan McColl
Councillor Michelle McGinty
Councillor John Millar 
Councillor Lawrence O’Neill (Vice Chair)
Councillor Lauren Oxley
Councillor Chris Pollock
Councillor Martin Rooney
Councillor Gordon Scanlan
Councillor Clare Steel
Councillor Sophie Traynor 
All other Councillors for information 
Chief Executive
Chief Officer – Regulatory and Regeneration
Chief Officer – Supply, Distribution and Property
Chief Officer – Roads and Neighbourhood 
Date of issue:  11 August 2022
Page 55

Page 4

Page 56

Page 5

WEST DUNBARTONSHIRE COUNCIL
Report by Chief Officer – Roads & Neighbourhood (Shared Service)
Committee: Infrastructure, Regeneration and Economic Development
Committee: 17 August 2022
Subject: Roads & Neighbourhood Delivery Plan 2021/22 Year End progress
1 Purpose
1.1 This report provides members with the year-end progress of the 2021/22
Delivery Plan. 
2 Recommendations
2.1 It is recommended that Committee notes the year-end position for 2021/22.
3 Background
3.1 Each Chief Officer develops an annual Delivery Plan which sets out actions to
help deliver the Strategic Plan and address the performance challenges and
service priorities identified in the planning process. The Plan also provides an
overview of services and resources, including employees and budgets, sets
out the performance indicators (PIs) for monitoring progress and considers the
relevant risks
3.2 Progress is reported to this Committee twice yearly, at mid-year and year-end.
4. Main Issues
2021/22 Year-end Performance
4.1 The 2021/22 Delivery Plan was presented to IRED Committee on 12 May
2021 and mid-year progress reported on 17 November 2021.
4.2 Full details of year-end progress are set out at Appendix 1 and summarised
below.
4.3 Of the 21 actions set out in the plan, 14 have been completed in year as
planned and seven were outstanding. Incomplete actions relate to the
following and will be carried forward and completed in 2022/23:
 Deliver new gymnasium, changing facilities and all weather running
track
 Review business plans to align activities, identify opportunities to
reduce duplication, an identify learning opportunities (under R&N
services collaborative programme)
ITEM 6
Page 57

Page 6

 Finalise the delivery of a suitable new allotment site with provision for
40 traditional plots 
 Continue to work collaboratively with Argyll & Bute and Inverclyde
Councils to develop a best value proposal for procuring the reception,
transportation, treatment and compliant disposal of biodegradable
municipal waste
 Produce a business case for the development of a waste transfer
station within Council’s boundary
 Complete phase 1 of the Fit for Service review of waste services
 Produce a revised service delivery model that reflects the changes in
quantities of plastic and glass collections due to the introduction of a
national deposit return scheme. 
4.4 Data is available for eight of the 16 PIs set out in the plan. Five met or
exceeded targets (green), one narrowly missed target (amber) and two were
further adrift of targets (red). The latter relate to the following, both of which
were impacted by an increase in waste; 
 Tonnage of biodegradable municipal waste landfilled 
 Percentage of total household waste that is recycled 
4.5 Five performance indicators showed improvement in both the short and long
term trend and one showed improvement in the short trend. 
4.5  The full set of PIs will be reported through the Council’s annual performance
reporting process later in 2021/22. 
4.6 Quality standards were set out in the 2021/22 Delivery Plan to help define
what service users can expect to receive, and remind both the organisation
and employees of the challenges and obligations they face in delivering best
value services. Of the ten PIs measuring quality standards, six met or
exceeded targets (green) two narrowly missed target (amber) two were further
adrift of the targets (red). Full details are set out in Appendix 2. 
5 People Implications 
5.1 There are no direct people implications arising from this report. 
6 Financial & Procurement Implications 
6.1  There are no direct financial or procurement implications arising from this
report. 
7 Risk Analysis 
7.1  Failure to deliver on the actions assigned to the service may have a direct
impact on the delivery of the Council’s Strategic Plan. It is essential that
remedial action is taken to ensure strategic delivery plans achieve the
commitments detailed and approved. 
Page 58

Page 7

8 Equalities Impact Assessment 
8.1  An EIA is not required with this report, however screening and impact
assessments will be carried out on specific activities as required. 
9 Consultation 
9.1  The delivery plans were developed through consultation with officers from the
strategic service areas. 
10 Strategic Assessment 
10.1  The Delivery Plans set out actions to support the successful delivery of the
strategic priorities of the Council. 
Chief Officer: Gail McFarlane 
Service Area:  Roads & Neighbourhood 
Date:   17 August 2022
________________________________________________________________ 
Person to Contact:  Karen Connelly    
karen.Connelly@west-dunbarton.gov.uk 
Appendices:  Appendix 1: R&N Delivery Plan 2021/22 - Year-end
Progress; 
Appendix 2: R&N Quality Standards 2021/22 - Year-end
Progress 
Background Papers:  2021/22 R&N Delivery Plan Report – IRED Committee,
12 May 2021  
2021/22 R&N Delivery Plan Mid-year Report – IRED
Committee, 17 November 21 
Wards Affected:  All
Page 59

Page 8

Appendix 1 - R&N Year End Delivery Plan 2021/22
2. Supported individuals, families and carers living independently and with dignity
Improved wellbeing
Action Status Progress Due Date Note Owner
Deliver new gymnasium, changing facilities and all
weather running track 31-Mar-2022
This action had not progressed as planned, pressures due to the
pandemic caused delays in completion which is expected in the
first half of 22/23. This action will carried forward to 22/23.
Ian Bain
3. Meaningful engagement with active, empowered and informed citizens who feel safe and engaged
Fully consulted and involved citizens who are able to make full use of the Community Empowerment Act
Performance Indicator
2020/21 2021/22
Owner
Value Status Value Target Short Trend Long Trend Note
% of adults satisfied with parks and
open spaces 86.5% N/A N/A 80% N/A N/A 2020/21 data for LGBF indicators will be
available in the first quarter of 2023
following publication by the Improvement
Service.
Ian Bain
% of adults satisfied with refuse
collection 82.63% N/A N/A 91% N/A N/A Kenny Lang
Page 60

Page 9

Performance Indicator
2020/21 2021/22
Owner
Value Status Value Target Short Trend Long Trend Note
% of adults satisfied with street
cleaning 68.9% N/A N/A 82% N/A N/A Ian Bain
5. Efficient and effective frontline services that improve the everyday lives of residents
A committed and skilled workforce
Action Status Progress Due Date Note Owner
Ensure working groups within R&N comprising
workforce representatives and Trade Unions address
operational concerns
31-Mar-2022
The working groups have been established and are developing
and reviewing risk assessments across the Roads Service. The
risk assessments have been updated to reflect social distancing
requirement and will continue to be reviewed and updated
through these established groups as restrictions change.
Gail Macfarlane
Ensure team meetings continue to take place virtually
as a result of the pandemic 31-Mar-2022
The team meetings are in place and continue on a virtual basis.
As the restrictions ease the meeting will move to a face to face
basis.
Gail Macfarlane
A continuously improving Council delivering best value
Action Status Progress Due Date Note Owner
Review business plans to align activities, identify
opportunities to reduce duplication, an identify learning
opportunities (under R&N services collaborative
programme)
31-Mar-2022
Due to the pandemic the majority of work was done on a reactive
basis, which was undertaken on a fully collaborative basis.
Business plans are under review for the new financial year to
Gail Macfarlane
Page 61

Page 10

Action Status Progress Due Date Note Owner
identify sharing opportunities such as joint procurement
exercises. Action carried forward to 2022/23.
Risk Description Current
Assessment Target Assessment Date Reviewed Note Owner
COVID-19 impact on Roads &
Neighbourhood Protection
Roads & Neighbourhood is faced with
significant demands for protection in
relation to additional and constant
changing legislation and guidelines,
PPE requirements, supply chain, cost
of PPE and ensuring workforce safety.
31-Mar-2022
In areas of front line dependency,
resilience measures have been
identified. Adequate PPE is available and
provided as required in addition strong
protocols are in place and with the
continued rollout of the vaccine the
likelihood of this risk is reduced.
Contingency measures can be put in
place if required for key service activity.
No change to risk matrix
Gail Macfarlane
COVID-19 impact on Roads &
Neighbourhood Service
Delivery
Roads & Neighbourhood is faced with
significant delivery demands in relation
to moving services online, disruption,
reduction and quality.
31-Mar-2022
As a predominantly front line service,
limited activities require to be on line
and those that do are now in place.
Whilst most services area at full
operational, with the continued
uncertainty regarding the easing of
restrictions including isolation
requirements this risk will remain at the
same status until the stability is
sustained.
No change to risk matrix
Gail Macfarlane
COVID-19 impact on Roads &
Neighbourhood Workforce
Roads & Neighbourhood is faced with
significant workforce demands in
relation to absence, reduction,
recruitment and wellbeing.
31-Mar-2022
The service has reviewed and updated
risk assessments to reflect current
restrictions and movement restrictions
PPE is available as required to ensure
workforce safety. With the continued
uncertainty regarding the easing of
restrictions including isolation
requirements this risk will remain at the
same status until the stability is
sustained.
No change to risk matrix
Gail Macfarlane
Page 62

Page 11

Sustainable and attractive local communities
Performance Indicator
2020/21 2021/22
Owner
Value Status Value Target Short Trend Long Trend Note
Tonnage of biodegradable municipal
waste landfilled 27,208 17,263 13,300
Whilst this figure is higher than target, we
continue to make incremental improvements
each quarter, with a significant improvement
since previous year.  There has been an
increased in the overall tonnage collected
which continues to impact on this indicator.
Kenny Lang
% Residents satisfied with roads
maintenance 46% 38% 41.5% Based on the LGBF comparative data Liam Greene
Cost of parks & open spaces per
1,000 population £
£42,733
.00 N/A N/A £41,500.00 N/A N/A
2020/21 data for LGBF indicators will be
available in the first quarter of 2023
following publication by the Improvement
Service.
Ian Bain
Net waste collection cost per
premises £50.60 N/A N/A £55.80 N/A N/A Kenny Lang
Net waste disposal cost per premises £132.20 N/A N/A £134.00 N/A N/A Kenny Lang
Net cost of street cleaning per 1,000
population £
£21,734
.00 N/A N/A £21,500.00 N/A N/A Ian Bain
Road maintenance cost per kilometre
£
£13,622
.00 N/A N/A £14,000.00 N/A N/A Liam Greene
Street Cleanliness Index - % Clean 84.9 94.1% 93 Target exceeded. Ian Bain
% of Class A roads that should be
considered for maintenance
treatment 10-12
26.9% 19.5% 24% Target exceeded.
Liam Greene
% of Class B roads that should be
considered for maintenance
treatment 10-12
19% 18.9% 24.5% Target exceeded.
Liam Greene
% of Class C roads that should be
considered for maintenance
treatment 10-12
27% 26.9% 30% Target exceeded.
Liam Greene
Page 63

Page 12

Performance Indicator
2020/21 2021/22
Owner
Value Status Value Target Short Trend Long Trend Note
Percentage of unclassified roads that
should be considered for
maintenance treatment
40.8% 33.4% 37% Target exceeded.
Liam Greene
% of total household waste that is
recycled 34.2% 37% 60%
Year-end target significantly missed
with shows low improvement in recycling
figures, but indicates that we are moving
towards a period of stability, and working
towards, minimising waste to landfill. The
impact of additional waste through residual
collections has impacted on our recycling
rate. Work is underway to educate the
community and help deliver change, and
allow WDC to meet our recycling objectives.
Kenny Lang
Action Status Progress Due Date Note Owner
Finalise the delivery of a suitable new allotment site
with provision for 40 traditional plots 31-Mar-2022
The overall delivery of this project has been delayed due to
Covid-19.  Draft plans have now been developed and the project
will be progressed in 22/23.  Action carried forward to 2022/23.
Ian Bain
Implement the Food Growing Strategy action plan for
West Dunbartonshire 31-Mar-2022 Action completed successfully. Ian Bain
Review the local bio diversity action plan in prep for
developing new plan in 22/23 31-Mar-2022 Action completed successfully. A new plan will be developed in
22/23. Ian Bain
Improve and increase local plant and animal species
diversity, including greenspaces, parks and wider
landscapes
31-Mar-2022
Action completed successfully. An audit of existing species has
been completed as planned and additional areas have been
developed that will increase species diversity.
Ian Bain
Explore alternative methods of weed control 31-Mar-2022
Trials of alternative non chemical methods of weed control have
taken place. No suitable alternative has been identified and
further trials will continue into 22/23.
Ian Bain
Continue to collaborate with the Scottish Government
to identify opportunities for the transition to electric
fleet and installation of electric charging points
31-Mar-2022
Action completed successfully. 7 charging points installed over
2021/22 with funding secured for an additional 2 in 2022/23. The
team have also participated in workshops with the GCR to
investigate future needs and opportunities for investment.
Liam Greene
Roll out the installation of electric vehicle charging
points at key car parks 31-Mar-2022 Action completed successfully. Liam Greene
Page 64

Page 13

Action Status Progress Due Date Note Owner
Develop and implement active and sustainable travel
routes to support a change in travel behaviour 31-Mar-2022 Action completed successfully. Active travel officer now recruited
and developing active travel routes. Liam Greene
Progress the Gruggies Burn flood alleviation scheme 31-Mar-2022 Action completed successfully. Roads Capital team progressing
with site investigation works to finalise design. Liam Greene
Review the proposed actions and interventions arising
from the River Leven flood study 31-Mar-2022 Action completed successfully. Report currently with SEPA and
await feedback on next steps and prioritisation. Liam Greene
Participate in the Loch Lomond flood study 31-Mar-2022 Action completed successfully. The service continues to
participate and liaise with National Park team as required. Liam Greene
Continue to work collaboratively with Argyll & Bute and
Inverclyde Councils to develop a best value proposal for
procuring the reception, transportation, treatment and
compliant disposal of biodegradable municipal waste
31-Mar-2022
This action is progressing and will continue over to 2022/23, the
action will not be completed until around the same time as the
landfill ban 2025.
We will continue to liaise with key stakeholders to agree our
approach, a draft proposal will be prepared and timelines agreed
for our procurement exercise in advance of the current contract
expiry.
Kenny Lang
Produce a business case for the development of a
waste transfer station within Council’s boundary 31-Mar-2022
This action will continue over to 2022/23.Waste services will
review the development of the first stage business plan with the
consultants within 6 months and will report outputs to senior
management thereafter.
Kenny Lang
Complete phase 1 of the Fit for Service review of waste
services 31-Mar-2022
This action is progressing and will continue over to 2022/23, we
have engaged with key stakeholders, to agree our approach. The
next steps include, Design approach and timelines for activity
including communications thereafter roll out changes/
improvements.
Kenny Lang
Produce a revised service delivery model that reflects
the changes in quantities of plastic and glass collections
due to the introduction of a national deposit return
scheme.
31-Mar-2022
This action is progressing and will continue over to 2022/23.
The Deposit return scheme has been delayed until August 2023.
We continue to work internally towards the new deadline.
Kenny Lang
Review the composition of the vehicle fleet and ensure
the conversion from the current diesel powered fleet to
a low /zero CO2 emissions fleet is implemented in a
planned and sustainable way (via Fleet Strategy)
31-Mar-2022
All milestones have been completed, and Fleet services are
working towards a more sustainable fleet solution. Regular
meetings with services users have been established, to discuss
individual requirement and work towards a greener tomorrow.
Kenny Lang
Review the implications of the Transport (Scotland) Act
2019 in relation to pavement parking and develop an
action plan in response to the requirement to enforce
it, reflecting Scottish Government guidance
31-Mar-2022 Action completed successfully. Action plan prepared. Liam Greene
Page 65

Page 14

Risk Description Current
Assessment Target Assessment Date Reviewed Note Owner
Challenge to delivery of burial
and cremation services
A number of factors may impact on
ability to deliver these services.  For
example a pandemic would create
significant immediate demand on
services.
31-Mar-2022
There is a high likelihood of increased
deaths in winter 2021 due to Covid-19
and influenza. However, we have well-
rehearsed measures in place to deal
with the challenges this will present.
No change to risk matrix
Ian Bain
Impact of major adverse
weather incidents on services
A significant period of adverse weather
may result on failure to deliver key
operational functions of E&N services
31-Mar-2022
The Business Continuity Plan would
come into effect in the event of a major
adverse weather incident.
No change to risk matrix
Ian Bain;
Kenny Lang
Failure to maintain road
network during adverse
weather
A significant period of adverse weather
may result in failure to deliver key
operational functions of R&T services
and other Council services.
31-Mar-2022
Status maintained. Cyclical maintenance
undertaken to mitigate any risk.
No change to risk matrix.
Liam Greene
Failure to manage and
maintain the road network
effectively
Failure to manage and maintain the
road network effectively will have an
adverse impact on user safety, traffic
movement, air quality, economic
growth and reduce access to facilities
and amenities. The Council’s
reputation as a place to live and work
with access to employment, education,
leisure and health opportunities would
be adversely affected.
31-Mar-2022
The service continued to address urgent
defects throughout the pandemic. As
restrictions have eased the full roads
service delivery has recommenced.
No change to risk matrix.
Liam Greene
Inability to deliver priority
services as a result of fuel
shortages
A fuel shortage would significantly
impacting on our ability to provide
priority service across West
Dunbartonshire.
31-Mar-2022
Council participates in the Scottish
Government Liquid Fuels Framework
and contributes to the work of the
Scottish Government Fuel Resilience
Group. There are no issues with fuel at
this time.
No change to risk matrix.
Kenny Lang
Page 66

Page 15

Risk Description Current
Assessment Target Assessment Date Reviewed Note Owner
Councils Assets
Risk: That the Council's assets and
facilities are not fully fit for purpose
with consequent adverse impact on
our ability to deliver efficient and
effective services. Assets included in
this assessment are; the Council’s
property portfolio, housing stock,
roads and lighting, fleet and open
space
31-Mar-2022
The current plan will continue into
2022/23. The new 5 year Corporate
Asset Management Strategy and
Property Action Plan will be developed in
2022/23 to ensure it meets the
aspirations of the new Strategic Plan.
No change to risk matrix.
Craig Jardine;
Michelle Lynn;
Gail
Macfarlane;
Alan Young
Action Status
Overdue
Completed
PI Status
Significantly Missed Target
Narrowly Missed Target
Met or Exceeded Target
Long Term Trends
Improving
No Change
Getting Worse
Short Term Trends
Improving
No Change
Getting Worse
Risk Status
Alert
High Risk
Warning
Page 67

Page 16

OK
Page 68

Page 17

Appendix 2 - R&N Quality Standards 2021/22
Quality Standards 2021/22
Fleet & Waste
Performance Indicator
2020/21 2021/22
Owner
Value Status Value Target Short Trend Long Trend Note
Percentage of missed bins collected
within 3 working days of being
reported
100% 98.5% 100% Kenny Lang
WM5: Percentage of abandoned
vehicles that require to be removed
by the council that are removed
within 14 days
100% 100% 100% Target achieved. Kenny Lang
Greenspace
Performance Indicator
2020/21 2021/22
Owner
Value Status Value Target Short Trend Long Trend Note
Percentage of offensive graffiti
removed within 24 hours of being
reported
100% 100% 100% Target achieved. Ian Bain
Percentage of non-offensive graffiti
removed within 5 working days of
being reported
100% 100% 100% Target achieved. Ian Bain
Page 69

Page 18

Roads & Transportation
Performance Indicator
2020/21 2021/22
Owner
Value Status Value Target Short Trend Long Trend Note
Percentage of emergency road
related defects repaired within 2
hours of being reported
100% 100% 100% Target achieved. Liam Greene
Percentage of serious road related
defects repaired within 2 working
days of being reported
86.1% 85.1% 100%
Adrift of target Reduction in available
resources and backlog of works impacted
response times. Additional resources and
working practices will be reviewed to bring
service levels back in line
Liam Greene
Percentage of non-serious road
related defects repaired within 7
working days of being reported
78.2% 72.2% 100%
Target not achieved. Reduction in available
resources and backlog of works impacted
response times. Additional resources and
working practices will be reviewed to bring
service levels back in line
Liam Greene
Percentage of routine road related
defects repaired within 28 working
days of being reported
46.7% 38.8% 100%
Target not achieved. Reduction in available
resources and backlog of works impacted
response times. Additional resources and
working practices will be reviewed to bring
service levels back in line
Liam Greene
RL2: Percentage of all traffic light
repairs completed within 48 hours 98.6% 100% 100% Improved performance from previous year.
Target achieved. Liam Greene
RL3: Percentage of all street light
repairs completed within 7 days 100% 99% 99%  Target achieved. Liam Greene
PI Status
Significantly Missed Target
Narrowly Missed Target
Met or Exceeded Target
Long Term Trends
Improving
No Change
Getting Worse
Short Term Trends
Improving
No Change
Getting Worse
Page 70

Page 19

WEST DUNBARTONSHIRE COUNCIL
Report by Chief Officer: Supply, Distribution and Property
Infrastructure Regeneration and Economic Development Committee:
17 August 2022
___________________________________________________________________
Subject:   Sublease of 3 Birch Road and 1 Overburn Avenue, Broadmeadow 
Industrial Estate, Dumbarton
1. Purpose
1.1 The purpose of this report is to seek the approval of the Committee that the
Council grant consent to approve for the sublease of 3 Birch Road and 1
Overburn Avenue, Broadmeadow Industrial Estate, Dumbarton.
2. Recommendations
2.1      It is recommended that the Committee:
(i) Approve the sublease of the 1 Overburn Avenue from Aggreko to
Complete Paving Requirements (Scotland) Limited (SC236251) with a
rental of £45,000pa for remainder of lease, which is for a further 76
years.
(ii) Approve the sublease of the 3 Birch Road from Aggreko to HBR
Dumbarton Limited (SC405581) with a rental of £21,750pa for
remainder of lease, which is for a further 77 years.
(iii) Authorise the Chief Officer, Supply, Property and Distribution to
conclude negotiations.
(iv) Authorise the Chief Officer, Regulatory and Regeneration to conclude
the transaction on such conditions as considered appropriate.
3. Background
3.1 The sites are wholly owned by West Dunbartonshire Council and are classed
as Common Good ground, these site must stay within West Dunbartonshire
Council ownership.
3.2 Dumbarton District Council entered into the lease with Aggreko for 3 Birch
Road on November 1st August 1990 for a period of 109 years.
ITEM 14
Page 71

Page 20

3.3 West Dunbartonshire Council entered into the lease with Aggreko for 1
Overburn Avenue on 28th November 1998 for a period of 100 years.
3.4 The sites are currently occupied by Aggreko on long leases, however due to
Aggreko having their new unit located at Lomond gate the sites at Birch Road
and Overburn Avenue are now surplus to their requirements. 
3.5 Two local companies have approached Aggreko looking to expand their
business within the Dumbarton area and are keen to sublease the sites from
Aggreko, to enable business expansion.
4. Main Issues
3 Birch Road
4.1 The site is let to Aggreko for a term of 100 years with 77 years remaining.
4.2 Aggreko have been approached by HBR Dumbarton Limited to sublease the
site at 3 Birch Road.
4.3 HBR Dumbarton Limited are a local company who specialises in mechanical,
accident repair and recovery. Along with specialising in body work, powder-
coating and alloy restoration. They are a local business who have been
operating within Dumbarton for 11 years, growing a successful business.
1 Overburn Avenue
4.4 The site is let to Aggreko for a term of 100 years with 76 years remaining.
4.5 Aggreko have been approached by CPR (Scotland) Limited to sublease the
site at 1 Overburn Avenue.
4.6 CPR (Scotland) Ltd are a Resurfacing and Civil Engineering Contractor who
have been trading within West Dumbarton for a period of 21 years, with their
business successfully growing over the years. CPR are now looking to
expand their business further.
4.7 Should either company cease trading then Aggreko would be liable for the
remainder of the term of the lease thus the Council would not be at any
detriment.
4.8 Both leases have been subject to recent rent reviews and this is reflective in
the current rental figure and upward only rent reviews will take place every 5
years.
Page 72

Page 21

5. People Implications
5.1 There are no significant people implications other than the legal department
documentation to conclude the subleases.
6. Financial and Procurement Implications
6.1 The Council will benefit from a continued rental for a period of 76/77 years
with 5 yearly upward only rent reviews.
6.2 The rental values reflect current market rents, which have been agreed as of
this year.
6.3 There are no procurement implications arising from this report.
7. Risk Analysis
7.1 As with any transaction of this nature there is a risk of the sublease not
proceeding due to issues which arise during the due diligence process and
the site will fall back to the responsibility of Aggreko for the remainder of the
leases.
8. Environmental Sustainability
8.1 We are keeping industrial businesses located within an area which is classed
for industrial use.
9. Equalities Impact Assessment (EIA)
9.1 An Equality Impact Assessment is not applicable for the purpose of this
report.
10. Consultation
10.1 Consultations of other departments are not applicable for the purpose if this
report.
11. Strategic Assessment
11.1 By agreeing to this proposal the Council will benefit in terms of receiving an
ongoing rental for a further period of 76/77 years with upwards only rent
reviews. 
Page 73

Page 22

11.2 The sub leases would enable two local companies to expand their business’
providing more jobs within the local community thus contributing to the
Council’s strategic priority for a strong local economy and improved job
opportunities.
Angela Wilson
Chief Officer: Supply, Distribution and Property
Date: 2 August 2022
Person to Contact: Michelle Lynn, Asset Coordinator.
Email: michelle.lynn@west-dunbarton.gov.uk
Cassie McAteer, Estates Surveyor. 
Email: cassie.mcateer@west-dunbarton.gov.uk
Appendices: None
Background Papers:  None
Wards Affected: Ward 3
Page 74

Page 23

WEST DUNBARTONSHIRE COUNCIL 
Report by Chief Officer - Resources 
Infrastructure, Regeneration & Economic Development Committee:
17 August 2022
___________________________________________________________________
Subject: Infrastructure, Regeneration & Economic Development Budgetary
Control Report 2022/23 to Period 3 (30 June 2022)
1. Purpose
1.1 This report provides an update on the financial performance to 30 June 2022
of those services under the auspices of the Infrastructure, Regeneration &
Economic Development Committee (IRED).
2. Recommendations
2.1 Members are asked to:
i) note the contents of this report showing the revenue budget forecast to
overspend against budget by £0.486m (4.00%) at the year-end, of
which £0.064m is COVID-19 related, therefore the non-covid variance
is currently projected at £0.422m adverse;
ii) note the net projected annual position in relation to relevant capital
projects which is highlighting a projected variance of £1.962m
(1.09%) due to slippage of £1.971m (1.10%) and an underspend of
£0.009m (0.001%).
iii) note the progress on efficiencies incorporated into budgets for 2022/23;
and
iv) note the projects to be accelerated.
3. Background
Revenue
3.1 At the meeting of West Dunbartonshire Council on 9 March 2022, Members
agreed the revenue estimates for 2022/23. A total net budget of £12.891m
was approved for IRED services.
Capital
3.2 At the meeting of Council on 9 March 2022, Members also agreed the
updated 10 year General Services Capital Plan for 2022/2023 to 2031/2032.
The next three years from 2021/22 to 2023/24 have been approved in detail
with the remaining years being indicative at this stage. The total project life
budget approved for projects that have either commenced or are due to
commence in that period total £179.698m.
ITEM 16
Page 75

Page 24

4. Main Issues
Revenue Budget
4.1  The current budgetary position is summarised in Appendix 1.  A more detailed
analysis by service is given in Appendix 2. Of the 13 services monitored 7 are
showing either a favourable or nil variance, with 6 services showing an
adverse variance. Comments are shown in Appendix 3 when there are
projected net annual variances greater than £0.050m and also where the net
variance is below £0.050m but there are offsetting variances of over £0.050m
within the service.
4.2 Appendix 1 shows the probable outturn for the services at £13.305m. As the
annual budget is £12.819m there is currently a projected adverse variance for
the year of £0.486m, of which £0.064m is COVID-19 related, therefore the
non-covid variance is currently projected at £0.422m adverse.
4.3 Officers will continue to manage the budgets as closely as possible
throughout the year and it is hoped that by tight budgetary control expenditure
may be brought in on line.
Capital Budget
4.4 The overall programme summary report is shown in Appendix 4. Information
on projects in the red category for probable underspends or overspends in-
year and in total is provided in Appendices 5 together with additional
information on action being taken to minimise or mitigate slippage and/or
overspends where possible and detail on projects within the green category
are shown in Appendix 6.The analysis shows that for the in-year planned
spend there is currently a projected in-year variance of £1.962m of which
£1.971m relates to project slippage and an in-year underspend of £0.009m.
Officers review regularly the in-year position to consider options to maximise
the effective use of capital resources
4.5 From the analysis within the appendices it can be seen that there is one
project with forecast slippage over £0.500m, as listed as follows:
Project Name
Slippage
(£m)
Bus Cycling and Walking Infrastructure 0.552
5. People Implications
5.1 There are no people implications.
6. Financial Implications
6.1 Other than the financial position noted above, there are no financial
implications of the budgetary control report. Officers are currently reviewing
Page 76

Page 25

budgets and projections with a view to improving the position by financial year
end and progress will be highlighted in future reports to committee.
7. Risk Analysis
7.1 The present variances should be viewed in the knowledge that there are a
number of variable factors which could arise between now and 31 March and
which could affect the year end results for both the revenue and capital
budgets.
7.2 Assumptions around service demand and timing of nationally agreed changes
through the phasing out of lockdown change regularly and therefore there is a
significant risk that the projected year end budgetary position will change from
that reported.
8. Equalities Impact Assessment (EIA)
8.1 The report is for noting and therefore no Equalities Impact Assessment was
completed for this report.
9 Consultation
9.1 The views of both Finance and Legal services have been requested on this
report and both have advised there are neither any issues nor concerns with
the proposal. As the report is for noting no further consultation is envisaged.
10. Strategic Assessment
10.1 Proper budgetary control and sound financial practice are cornerstones of
good governance and support Council and officers to pursue the five strategic
priorities of the Council’s Strategic Plan. This report forms part of the financial
governance of the Council. This report is for noting and, therefore, does not
directly affect any of the strategic priorities.
Laurence Slavin
Chief Officer  – Resources
Date:  21 July 2022
Person to Contact: Jackie Thomson - Business Unit Finance Partner, 16
Church Street, Dumbarton, G81 1QL.
e-mail jackie.nicol-thomson@west-dunbarton.gov.uk
Appendices: Appendix 1 - Summary Budgetary Position (Revenue)
Appendix 2– Detailed Budgetary Position (Revenue)
Page 77

Page 26

Appendix 3 – Variance Analysis (Revenue)
Appendix 4 – Budgetary Position (Capital)
Appendix 5 – Variance Analysis Red Status (Capital)
Appendix 6 - Variance Analysis Green (Capital)
Background Papers: None
Wards Affected: All
Page 78

Page 27

WEST DUNBARTONSHIRE COUNCIL APPENDIX 1
REVENUE BUDGETARY CONTROL 2022/23
IRED SUMMARY
MONTH END DATE 30 June 2022
Total Budget
2022/23
Spend to
Date 2022/23
Forecast
Spend
2022/23
Annual
RAG
Status
Net Variance
Attributable
to Covid
Underlying
Variance
Excluding
Covid
£000 £000 £000 £000 % £000 £000
(266) (11) (206) 60 -23%  0 60
(592) (149) (493) 99 -17%  0 99
610 234 610 0 0%  0 0
2,933 842 3,013 80 3%  0 80
7,503 1,876 7,503 0 0%  0 0
187 (10) 168 (19) -10%  0 (19)
(193) (113) (230) (37) 19%  0 (37)
(1,031) (154) (991) 40 -4%  0 40
7,978 1,862 8,199 221 3%  221
(2,315) (198) (2,313) 2 0%  69 (67)
245.55 437 208 (38) -15%  (5) (32)
Depots 0 61 0 0 0%  0 0
(2,239) 1,662 (2,162) 78 -3%  0 78
12,819 6,339 13,305 486 4%  64 422
Transport, Fleet & Maintenance Services
Service / Subjective Summary Annual Variance 2022/23
Corporate Asset Maintenance
Consultancy Services
Roads Services
Grounds Maintenance & Street Cleaning Client
Outdoor Services
Burial Grounds
Crematorium
Waste Services
Corporate Assets /Capital Investment Programme
Economic Development
Ground Maintenance & Street Cleaning Trading A/c
Total Net Expenditure
Page 79

Page 28

WEST DUNBARTONSHIRE COUNCIL APPENDIX 2
REVENUE BUDGETARY CONTROL 2022/23
IRED COMMITTEE DETAIL
PERIOD END DATE 30 June 2022
PERIOD 3
Actual
Outturn
2021/22
Total
Budget
2022/23
Spend to
Date 2022/23
Forecast
Spend
2022/23
RAG
Status
£000 £000 £000 £000 £000 %
18,274 Employee 19,032 4,391 19,201 170 1% 
3,921 Property 3,392 370 3,485 93 3% 
4,547 Transport and Plant 4,571 543 4,736 164 4% 
10,643 Supplies, Services and Admin 11,744 1,453 10,753 (991) -8% 
9,414 Payments to Other Bodies 9,369 2,095 9,357 (12) 0% 
390 Other 557 0 557 0 0% 
47,189 Gross Expenditure 48,666 8,851 48,090 (576) -1% 
(32,144) Income (35,846) (2,512) (34,785) 1,062 3% 
15,046 Net Expenditure 12,819 6,339 13,305 486 4% 
£000 £000 £000 £000 £000 %
2,006 Employee 1,676 426 1,706 30 2% 
57 Property 49 12 49 0 0% 
59 Transport and Plant 67 17 67 0 0% 
1,329 Supplies, Services and Admin 3,070 183 1,980 (1,090) -36% 
0 Payments to Other Bodies 0 0 0 0 0% 
0 Other 0 0 0 0 0% 
3,451 Gross Expenditure 4,862 638 3,802 (1,060) -22% 
(3,648) Income (5,128) (649) (4,008) 1,120 22% 
(197) Net Expenditure (266) (11) (206) 60 -23% 
£000 £000 £000 £000 £000 %
1,721 Employee 1,758 396 1,719 (39) -2% 
93 Property 81 0 84 2 3% 
1,919 Transport and Plant 2,068 93 2,218 150 7% 
509 Supplies, Services and Admin 567 19 567 0 0% 
1 Payments to Other Bodies 0 (0) 0 0 0% 
0 Other 0 0 0 0 0% 
4,243 Gross Expenditure 4,475 508 4,588 113 3% 
(4,626) Income (5,067) (657) (5,081) (14) 0% 
(383) Net Expenditure (592) (149) (493) 99 -17% 
£000 £000 £000 £000 £000 %
1,092 Employee 833 232 833 0 0% 
0 Property 0 0 0 0 0% 
6 Transport and Plant 7 1 7 0 0% 
4 Supplies, Services and Admin 5 1 5 0 0% 
45 Payments to Other Bodies 0 0 0 0 0% 
0 Other 0 0 0 0 0% 
1,147 Gross Expenditure 845 234 845 0 0% 
(528) Income (235) 0 (235) 0 0% 
619 Net Expenditure 610 234 610 0 0% 
£000 £000 £000 £000 £000 %
2,707 Employee 2,794 609 2,860 65 2% 
226 Property 216 8 235 19 9% 
697 Transport and Plant 552 122 556 4 1% 
2,423 Supplies, Services and Admin 2,113 106 2,136 23 1% 
817 Payments to Other Bodies 836 0 836 0 0% 
0 Other 0 0 0 0 0% 
6,871 Gross Expenditure 6,513 846 6,623 111 2% 
(4,212) Income (3,580) (4) (3,610) (30) -1% 
2,658 Net Expenditure 2,933 842 3,013 80 3% 
Service Summary Annual Variance
2022/23
All Services
Corporate Asset Maintenance
Transport, Fleet & Maintenance Services
Consultancy Services
Roads Services
Page 80

Page 29

WEST DUNBARTONSHIRE COUNCIL APPENDIX 2
REVENUE BUDGETARY CONTROL 2022/23
IRED COMMITTEE DETAIL
PERIOD END DATE 30 June 2022
PERIOD 3
Actual
Outturn
2021/22
Total
Budget
2022/23
Spend to
Date 2022/23
Forecast
Spend
2022/23
RAG
Status Service Summary Annual Variance
2022/23
£000 £000 £000 £000 £000 %
0 Employee 0 0 0 0 0% 
0 Property 0 0 0 0 0% 
0 Transport and Plant 0 0 0 0 0% 
0 Supplies, Services and Admin 0 0 0 0 0% 
7,360 Payments to Other Bodies 7,503 1,876 7,503 0 0% 
0 Other 0 0 0 0 0% 
7,360 Gross Expenditure 7,503 1,876 7,503 0 0% 
0 Income 0 0 0 0 0% 
7,360 Net Expenditure 7,503 1,876 7,503 0 0% 
£000 £000 £000 £000 £000 %
61 Employee 111 14 58 (53) -48% 
84 Property 85 13 109 24 28% 
0 Transport and Plant 0 0 0 0 0% 
113 Supplies, Services and Admin 117 3 117 0 0% 
62 Payments to Other Bodies 45 12 55 10 22% 
0 Other 0 0 0 0 0% 
320 Gross Expenditure 358 41 339 (19) -5% 
(144) Income (171) (51) (171) 0 0% 
176 Net Expenditure 187 (10) 168 (19) -10% 
£000 £000 £000 £000 £000 %
0 Employee 0 0 0 0 0% 
21 Property 23 1 24 1 4% 
0 Transport and Plant 0 0 0 0 0% 
0 Supplies, Services and Admin 0 0 0 0 0% 
425 Payments to Other Bodies 442 0 442 0 0% 
0 Other 0 0 0 0 0% 
447 Gross Expenditure 465 1 466 1 0% 
(666) Income (658) (114) (696) (38) -6% 
(220) Net Expenditure (193) (113) (230) (37) 19% 
£000 £000 £000 £000 £000 %
199 Employee 191 49 194 3 2% 
161 Property 166 16 180 14 8% 
0 Transport and Plant 0 0 0 0 0% 
18 Supplies, Services and Admin 18 3 19 0 2% 
37 Payments to Other Bodies 33 6 31 (3) -8% 
0 Other 0 0 0 0 0% 
415 Gross Expenditure 409 75 424 15 4% 
(1,364) Income (1,440) (229) (1,415) 25 2% 
(949) Net Expenditure (1,031) (154) (991) 40 -4% 
£000 £000 £000 £000 £000 %
3,034 Employee 2,850 742 3,026 176 6% 
175 Property 146 (8) 155 8 6% 
1,066 Transport and Plant 1,037 187 991 (47) -4% 
5,275 Supplies, Services and Admin 5,149 1,006 5,227 78 2% 
2 Payments to Other Bodies 22 0 22 0 0% 
0 Other 0 0 0 0 0% 
9,551 Gross Expenditure 9,205 1,926 9,420 216 2% 
(1,118) Income (1,227) (63) (1,222) 5 0% 
8,434 Net Expenditure 7,978 1,862 8,199 221 3% 
Grounds Maintenance & Street Cleaning Client
Outdoor Services
Crematorium
Burial Grounds
Waste Services
Page 81

Page 30

WEST DUNBARTONSHIRE COUNCIL APPENDIX 2
REVENUE BUDGETARY CONTROL 2022/23
IRED COMMITTEE DETAIL
PERIOD END DATE 30 June 2022
PERIOD 3
Actual
Outturn
2021/22
Total
Budget
2022/23
Spend to
Date 2022/23
Forecast
Spend
2022/23
RAG
Status Service Summary Annual Variance
2022/23
£000 £000 £000 £000 £000 %
1,138 Employee 1,405 273 1,406 1 0% 
1,794 Property 1,767 237 1,769 2 0% 
3 Transport and Plant 8 1 8 0 0% 
74 Supplies, Services and Admin (39) 3 (39) (0) 0% 
47 Payments to Other Bodies 43 8 42 (1) -2% 
0 Other 0 0 0 0 0% 
3,056 Gross Expenditure 3,185 522 3,186 2 0% 
(2,968) Income (5,500) (720) (5,500) (0) 0% 
88 Net Expenditure (2,315) (198) (2,313) 2 0% 
£000 £000 £000 £000 £000 %
620 Employee 989 234 976 (13) -1% 
489 Property 22 7 23 1 4% 
2 Transport and Plant 4 0 1 (3) -78% 
13 Supplies, Services and Admin 16 2 13 (3) -20% 
618 Payments to Other Bodies 444 194 426 (18) -4% 
0 Other 0 0 0 0 0% 
1,743 Gross Expenditure 1,477 437 1,439 (38) -3% 
(976) Income (1,231) 0 (1,231) 0 0% 
767 Net Expenditure 246 437 208 (38) -15% 
£000 £000 £000 £000 £000 %
0 Employee 0 0 0 0 0% 
485 Property 504 63 510 7 1% 
0 Transport and Plant 0 0 0 0 0% 
16 Supplies, Services and Admin 15 (2) 15 0 0% 
0 Payments to Other Bodies 0 0 0 0 0% 
0 Other 0 0 0 0 0% 
501 Gross Expenditure 519 61 525 7 1% 
(501) Income (519) 0 (525) (7) -1% 
0 Net Expenditure 0 61 0 0 0% 
£000 £000 £000 £000 £000 %
5,696 Employee 6,425 1,416 6,425 0 0% 
334 Property 332 21 347 16 5% 
796 Transport and Plant 827 121 888 61 7% 
869 Supplies, Services and Admin 712 129 713 1 0% 
0 Payments to Other Bodies 0 0 0 0 0% 
390 Other 557 0 557 0 0% 
8,085 Gross Expenditure 8,852 1,687 8,929 78 1% 
(11,393) Income (11,091) (25) (11,091) 0 0% 
(3,308) Net Expenditure (2,239) 1,662 (2,162) 78 -3% 
Economic Development
Depots
Ground Maintenance & Street Cleaning Trading A/c
Corporate Assets /Capital Investment Programme
Page 82

Page 31

WEST DUNBARTONSHIRE COUNCIL APPENDIX 3
REVENUE BUDGETARY CONTROL 2022/23
ANALYSIS FOR VARIANCES OVER £50,000
PERIOD END DATE
Total Budget Forecast
Spend RAG Status
£000 £000 £000 %
Corporate Asset Maintenance (266) (206) 60 -23% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Transport, Fleet & Maintenance
Services (592) (493) 99 -17% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
30 June 2022
Budget Details
Variance Analysis
Variance
This service manages and undertakes repairs and maintenance to public
buildings
Lower than budgeted income due to a reduced programme of CAMS work
delviered by subcontractor partners
None - although service will endeavour to reduce the adverse variance
where possible
Surplus to be less than target
Surplus slightly less than target
Transport services across WDC
There is a favourable variance (£39k) against employee costs due to a
number of vacancies. However this is more than offset by higher fuel costs
(£150k), which will follow through to higher recharges to services.
The level of internal recharges is under review
Page 83

Page 32

WEST DUNBARTONSHIRE COUNCIL APPENDIX 3
REVENUE BUDGETARY CONTROL 2022/23
ANALYSIS FOR VARIANCES OVER £50,000
PERIOD END DATE
Total Budget Forecast
Spend RAG Status
£000 £000 £000 %
30 June 2022
Budget Details
Variance Analysis
Variance
Roads Services 2,933 3,013 80 3% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Outdoor Services 187 168 (19) -10% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
An adverse variance is anticipated
This service relates to Roads operations, design, structures, street lighting,
road safety and school crossing patrols
Employee costs are adverse (£65k) because overtime is projected to be in
excess of budget although this is partly offset by additional grant income
(£30k). Electricity (£19k) and street lighting (£22k) costs have increased
during the year to a level not anticipated when the budget was set.
management will continue to monitor all budget heads with a view to
minimising the overspend
This service covers the outdoor sporting facilities provided by WDC and
public conveniences
Employee costs are favourable (£53k) because of a number of vacancies.
This favourable variance has offset the adverse variance against
electricity/gas (£24k).
none necessary
small favourable variance
Page 84

Page 33

WEST DUNBARTONSHIRE COUNCIL APPENDIX 3
REVENUE BUDGETARY CONTROL 2022/23
ANALYSIS FOR VARIANCES OVER £50,000
PERIOD END DATE
Total Budget Forecast
Spend RAG Status
£000 £000 £000 %
30 June 2022
Budget Details
Variance Analysis
Variance
Ground Maintenance & Street Cleaning
Trading A/c (2,239) (2,162) 78 -3% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Burial Grounds (193) (230) (37) 19% 
Service Description This service provides burial services within the Council area
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Crematorium (1,031) (991) 40 -4% 
Service Description This service provides crematorium services within the Council area
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Waste Services 7,978 8,199 221 3% 
Service Description Waste Collection and Refuse disposal services
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Trading operation providing grounds maintenance and street cleaning
services
Property costs are adverse due to electricity costs. Fuel (£41k) and tyre
(£20k) costs have increased to a level not anticipated when the budget was
set.
None possible at this time
A small adverse variance is anticipated
Overspend anticipated
Gas costs are higher than budgeted (£15k) while income is projected to be
less than budgeted , particularly from plaques/books of remembrance etc
(£25k)
management will continue to monitor all budget heads with a view to
minimising the overspend
none possible at present
Employee costs are higher (£176k) as projected savings from waste route
optimisation ,which depend on operating from a single depot, are not yet
achievable . Expenditure on bin replacements is higher (£71k) than
anticipated when the budget was set. These have been partly offset by
reduced vehicle hires (£45k).
None necessary
A favourable variance is anticipated
Income from internments/lairs is projected to exceed budget.
small overspend
Page 85

Page 34

WEST DUNBARTONSHIRE COUNCIL APPENDIX 3
REVENUE BUDGETARY CONTROL 2022/23
ANALYSIS FOR VARIANCES OVER £50,000
PERIOD END DATE
Total Budget Forecast
Spend RAG Status
£000 £000 £000 %
30 June 2022
Budget Details
Variance Analysis
Variance
Corporate Assets /Capital Investment
Programme (2,315) (2,313) 2 0% 
Service Description This service provides asset and estate management
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Overall Corporate Assets/ Capital Investment Programme has a small
adverse variance of £3k. However, there are favourable and adverse
variances which offset each other. The main ones being: There has been
an over recovery of income of £35k due to good estates management and
maximising income.    
There is also a favourable variance on employee costs of £70k due to
current vacancies.    
However, there is an adverse variance because, Aon/BAM PPP issued an
Insurance Cost Sharing Report in December 2020, with a cost share of
£117k to the Authority. In May 2021 they issued a statement that there was
an error in the report and the sum should have read a cost share of £18k
and not £117k. All information was passed to WDC’s insurance broker for
review who have recently confirmed there is no grounds to challenge the
revised figure. This results in and adverse variance of £104k within supplies
and services.
Income and expenditure will continue to be monitored throughout the year.
A small overspend is anticipated
Page 86

Page 35

WEST DUNBARTONSHIRE COUNCIL APPENDIX 4
GENERAL SERVICES CAPITAL PROGRAMME
OVERALL PROGRAMME SUMMARY
MONTH END DATE
PERIOD
Spend to
Date
Spend to
Date
£000 £000
Red
16 20% 6,066 12% 16 20% 525 64%
Amber
0 0% 0 0% 0 0% 0 0%
Green
65 80% 45,860 88% 65 80% 291 36%
81 100% 51,926 100% 81 100% 816 100%
Budget Spend to
Date
Forecast
Spend
Forecast
Variance Budget Spend to
Date
Forecast
Spend
Forecast
Variance Slippage Over/
(Under)
£000 £000 £000 £000 £000 £000 £000 £000 £000 £000
PL CY
33,016 6,066 32,842 (175) 14,898 525 4,682 (10,215) (9,471) (744) -1% -69%
0 0 0 0 0 0 0 0 0 0 #DIV/0! #DIV/0!
146,682 45,860 144,895 (1,788) 32,622 291 30,787 (1,836) (693) (1,144) -1% -6%
179,698 51,926 177,736 (1,962) 47,520 816 35,469 (12,052) (10,164) (1,888)
30 June 2022
03 January 1900
Project Status Analysis
Project Life Status Analysis Current Year Project Status Analysis
Number of
Projects at
RAG Status
% Projects at
RAG Status
% Project
Spend at
RAG Status
Number of
Projects at
RAG Status
% Projects at
RAG Status
Red
% Project
Spend at
RAG Status
Red
Projects are forecast to be overspent and/or experience material delay to completion
Amber
Projects are either at risk of being overspent and/or delay in completion (although this is unquantifiable at
present) or the project has any issues that require to be reported at this time
Green
Projects are on target both in relation to overall budget and the forecast stages in the project life cycle and
no issues are anticipated at this time
TOTAL EXPENDITURE
Project Life Financials Current Year Financials
Projects are on target both in relation to overall budget and the forecast stages in the project life cycle and
no issues are anticipated at this time
TOTAL EXPENDITURE
Projects are forecast to be overspent and/or significant delay to completion
Amber
Projects are either at risk of being overspent and/or delay in completion (although this is unquantifiable at
present) or the project has any issues that require to be reported at this time
Green
Page 87

Page 36

WEST DUNBARTONSHIRE COUNCIL APPENDIX 5
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT RED ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
Project Life Financials 61 3 5% 61 (0) 0%
Current Year Financials 55 0 0% 58 3 5%
Project Description
Project Manager Steven Milne/ John McKenna
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-23 31-Mar-23
Project Life Financials 342 237 69% 347 5 1%
Current Year Financials 110 0 0% 16 (94) -85%
Project Description
Project Manager Steven Milne/ John McKenna
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-24 31-Mar-24
Project Life Financials 80 19 24% 80 0 0%
Current Year Financials 61 1 1% 30 (31) -51%
Project Description
Project Manager Steven Milne/ John McKenna
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-24 31-Mar-24
30 June 2022
Budget Details
Project Life Financials
Spend to Date Variance
Installation of Solar PV at Clydebank Leisure Centre
Installation of Solar PV at Clydebank Leisure Centre.
Planned End Date Forecast End Date
Replace obsolete boilers (plant greater than 30 years old).
Replace obsolete boilers (plant greater than 30 years old).
Main Issues / Reason for Variance
Technical scope currently being compiled and will be passed to procurement in July for tender issue. Anticipate works to start October
2022.
Mitigating Action
Opportunities to mitigate are limited at this stage. 
Anticipated Outcome
Complete in 2022/23.
Anticipated Outcome
Retention for St Mary's Primary School and design fees this year. Insufficient budget available to carry out Hub works.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Await chimney inspection report and appointment of consultant for HUB CEC. Due to complications in installing heat pump anticipate
only design fees spend this year and release of the retention for works at St Marys Primary School, Alexandria.
Mitigating Action
None available at this time.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Further orders have been raised and await invoices. Total expenditure this financial year estimated to be £0.030m with the rest of the
funding to be carried forward into next financial year.
Mitigating Action
None available at this time
Energy Projects quick wins
Spend to Save projects.
Anticipated Outcome
Anticipate some spend this year and the remainder to be rephased into 2023/24.
Page 88

Page 37

WEST DUNBARTONSHIRE COUNCIL APPENDIX 5
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT RED ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2022
Budget Details
Project Life Financials
Spend to Date Variance
Installation of Solar PV at Clydebank Leisure Centre
Project Life Financials 344 86 25% 344 0 0%
Current Year Financials 258 0 0% 80 (178) -69%
Project Description
Project Manager Steven Milne/ John McKenna
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-24 31-Mar-24
Project Life Financials 160 0 0% 160 0 0%
Current Year Financials 152 0 0% 50 (102) -67%
Project Description
Project Manager Steven Milne/ John McKenna
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-24 31-Mar-24
Zero Carbon Fund
Zero Carbon Fund.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Works initiated to install a heat pump to complement HUB CEC boiler. Liasing with BAM FM and Asset Management to decide which
site to install solar PV following successful installation at St Peters. Works will cross into next financial year.
Upgrade obsolete heating controls (BEMS) across Council estate
Upgrade obsolete heating controls (BEMS) across Council estate.
Planned End Date Forecast End Date
Mitigating Action
None available at this time
Anticipated Outcome
Project delivered within budget.
Main Issues / Reason for Variance
Tender documentation currently being prepared. Work scheduled between October 2022 and March 2023 but suspect it will carry
forward into the new financial year due to necessary disruption to heating in the buildings.
Mitigating Action
None available at this time.
Anticipated Outcome
Delivery of project within budget.
Page 89

Page 38

WEST DUNBARTONSHIRE COUNCIL APPENDIX 5
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT RED ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2022
Budget Details
Project Life Financials
Spend to Date Variance
Installation of Solar PV at Clydebank Leisure Centre
Project Life Financials 750 0 0% 0 (750) -100%
Current Year Financials 750 0 0% 0 (750) -100%
Project Description
Project Manager Gillian McNamara/ Michael McGuinness
Chief Officer Peter Hessett
Project Lifecycle 31-Dec-22 30-Jun-23
Project Life Financials 22,100 1,806 8% 22,100 (0) 0%
Current Year Financials 7,465 38 1% 2,851 (4,614) -62%
Project Description
Project Manager Gillian McNamara/ Michael McGuinness
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-23 31-Mar-23
Main Issues / Reason for Variance
Due to factors outwith the Council's control, progress couldn’t be made on a timeline that would be acceptable to funders and as a
result Scottish Government will withdraw the grant offer. Therefore the project cannot be progresses at this time.
Mitigating Action
None available at this time.
Anticipated Outcome
Repurposing and restoration of B listed former St Andrew's church in Alexandria for community arts uses.
Viresco Studios and Arts Centre
Viresco Studios and Arts Centre in Alexandria, aimed to encourage wider participation in the arts,
creative enterprises and cultural activity in West Dunbartonshire.
Planned End Date Forecast End Date
LUF
Year one LUF spend includes acquisition cost of Artizan Centre, and design development for
Glencairn House and Connecting Dumbarton
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Connecting Dumbarton and Glencairn House are progressing per the agreed programme. A future programme for the Artizan Centre
based on the Redevelopment Options consultancy will be reported to IRED, after which proposed in year spend may be adjusted.
Costs will continue to be monitored by the LUF Project Board. Costs are being reported as per the first Programme Management
Update (Nov 2021) and may not represent the current projections.
Mitigating Action
None available at this time.
Anticipated Outcome
Redevelopment of the Dumbarton Town Centre
Page 90

Page 39

WEST DUNBARTONSHIRE COUNCIL APPENDIX 5
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT RED ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2022
Budget Details
Project Life Financials
Spend to Date Variance
Installation of Solar PV at Clydebank Leisure Centre
Project Life Financials 382 388 102% 388 6 2%
Current Year Financials 0 6 0% 6 6 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-21 31-Mar-21
Project Life Financials 400 44 11% 400 0 0%
Current Year Financials 357 0 0% 100 (257) -72%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Oct-23 31-Oct-23
Main Issues / Reason for Variance
Project completed over budget due to ground conditions on site.  Final costs now charged.
Mitigating Action
None available at this time.
Anticipated Outcome
New sports changing facility completed.
New Sports Changing Facility at Duntocher
New Sports Changing Facility at Duntocher
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Two sites are being developed at Dillichip Loan Bonhill and Overburn Dumbarton. These sites will provide eighty traditional allotment
plots together with community food growing facilities. It is anticipated that project works will commence in February 2023 with a
completion date of October 2023.
Mitigating Action
None available at this time.
Allotment Development
To develop an allotment site.
Anticipated Outcome
Two new allotment sites with 80 plots and community growing space.
Page 91

Page 40

WEST DUNBARTONSHIRE COUNCIL APPENDIX 5
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT RED ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2022
Budget Details
Project Life Financials
Spend to Date Variance
Installation of Solar PV at Clydebank Leisure Centre
Project Life Financials 2,646 2,847 108% 3,210 565 21%
Current Year Financials 844 480 57% 741 (103) -12%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-22 31-Mar-23
Project Life Financials 817 263 32% 817 (0) 0%
Current Year Financials 553 0 0% 150 (403) -73%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-22 30-Sep-22
Posties Park Sports Hub - New sports hub to include Gym & running track
Creation of a sports hub at Posties/Marinecraft to include a new changing pavilion/Gym, new all-
weather 6 lane running track, conversion of blaze sports pitch to grass, new fencing, upgrade of
existing floodlights and additional car parking.  This combines the budget approved by the Council
in February 2015 for Community Sports Facilities at Posties Park, draw down of budget from the
generic sports facilities budget line. No match funding from Sport Scotland was received.
Planned End Date Forecast End Date
Vale of Leven Cemetery Extension
Extension of existing cemetery in Vale of Leven.
Main Issues / Reason for Variance
Project start was delayed due to planning issues and COVID-19 restrictions. Work commenced January 2021 with a proposed
completion date of March 2022 which has been extended to October 2022 due to design changes required by Planning. There is still a
significant amount of work to be undertaken to complete the project and the cost of this work has been affected by Brexit and supply
chain issues. A forecast is uncertain at this time pending discussions and negotiations with the contractor.
Mitigating Action
None required at this time.
Anticipated Outcome
New all weather running track and gymnasium.
Anticipated Outcome
Extension to existing cemetery providing a sustainable burial environment.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Project is now being developed for tendering, with project commencing February 2023 and completion expected by 31 October 2023. 
It is anticipated that £0.150m will be spent this financial year mainly on consultant costs and enabling works.
Mitigating Action
None available at this time.
Page 92

Page 41

WEST DUNBARTONSHIRE COUNCIL APPENDIX 5
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT RED ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2022
Budget Details
Project Life Financials
Spend to Date Variance
Installation of Solar PV at Clydebank Leisure Centre
Project Life Financials 217 3 1% 217 0 0%
Current Year Financials 214 0 0% 0 (214) -100%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
Project Life Financials 400 358 90% 400 0 0%
Current Year Financials 42 0 0% 0 (42) -100%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
Project Life Financials 500 11 2% 500 0 0%
Current Year Financials 220 0 0% 0 (220) -100%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
Bus Rapid Deployment Fund
Funding has been awarded from Sustrans to assist with social distancing measures required as a
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Officers working with external partners to identify projects to support funding. Investigation on going however unlikely works will be able
to progress this financial year.
Mitigating Action
None available at this time.
Anticipated Outcome
To improve journey times and reliability of bus services.
Mitigating Action
None available at this time.
Anticipated Outcome
To complete remaining civil works required.
Auld Street Clydebank - Bond
Completion of roadworks associated with Auld Street housing development. Creation of a footpath
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Road construction works completed in previous years. Remaining funds are insufficient to complete footpath construction. Works on
hold until such time as additional funds can be secured.
Main Issues / Reason for Variance
Awaiting Scottish Government recommendations.
Mitigating Action
None available at this time.
Anticipated Outcome
Project to be delivered within budget.
Mandatory 20mph Residential communities
Mandatory 20mph Residential communities.
Planned End Date Forecast End Date
Page 93

Page 42

WEST DUNBARTONSHIRE COUNCIL APPENDIX 5
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT RED ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2022
Budget Details
Project Life Financials
Spend to Date Variance
Installation of Solar PV at Clydebank Leisure Centre
Project Life Financials 1,000 0 0% 1,000 0 0%
Current Year Financials 1,000 0 0% 0 (1,000) -100%
Project Description
Project Manager Kenny Lang
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
Project Life Financials 2,817 0 0% 2,817 0 0%
Current Year Financials 2,817 0 0% 600 (2,217) -79%
Project Description
Project Manager Kenny Lang
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
Vehicle Replacement Strategy
Replacement of refuse collection vehicles.
Main Issues / Reason for Variance
Vehicles are being ordered for delivery in this financial year but larger vehicles will be delayed into financial year 2023/2024.
Mitigating Action
None Required.
Anticipated Outcome
Replacement of fleet within budget.
Anticipated Outcome
Replacement of refuse collection vehicles.
Vehicle Replacement
Replacement of vehicles which have reached end of programmed lifespan (7 year heavy vehicles,
10 year light vehicles).
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Larger vehicles will be delayed due to supply chain issues. Delivery timescales anticipated at 18 months.
Mitigating Action
None available.
Page 94

Page 43

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
1
Project Life Financials 83 0 0% 83 0 0%
Current Year Financials 83 0 0% 83 0 0%
Project Description
Project Manager Steven Milne/ John McKenna
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-23 31-Mar-23
2
Project Life Financials 20 13 66% 20 0 0%
Current Year Financials 7 0 0% 7 0 0%
Project Description
Project Manager Steven Milne/ John McKenna
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-23 31-Mar-23
3
Project Life Financials 290 63 22% 290 0 0%
Current Year Financials 216 0 0% 216 0 0%
Project Description
Project Manager Steven Milne/ John McKenna
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-23 31-Mar-23
30 June 2022
Budget Details
Project Life Financials
Spend to Date Variance
Mitigating Action
None available at this time.
Anticipated Outcome
Physical works being carried out by 31/3/23.
Replace existing main hall Air Handling unit at Clydebank Town Hall
Replace existing main hall Air Handling unit at Clydebank Town Hall.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Works are integrated with the new Baths refurbishment. Await design proposals from Vital for approval. Works to be complete by 31 March 2023
to compliment the district heating installation.
Leisure Energy projects - air handling units, upgrade lighting, circulating pumps, and draught proofing
Measures to be installed at both Meadow Centre & Vale of Leven Swimming Pool; new pool hall Air
Handling Units, upgrade lighting, circulating pumps Vale of Leven Swimming Pool, internal and external
lighting and draught proofing.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Works to be passed to Consultancy Services and meeting to be arranged.
Main Issues / Reason for Variance
Further works ordered. Expect full spend by 31 March 2023.
Mitigating Action
None required.
Anticipated Outcome
Delivery of project with full budget spend.
Replace failed heating controls/valves & recommission
Replace failed heating controls/valves & recommission.
Planned End Date Actual End Date
Mitigating Action
All works to be complete in one tender package.
Anticipated Outcome
All works to be completed next financial year 2023/24.
Page 95

Page 44

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2022
Budget Details
Project Life Financials
Spend to Date Variance
4
Project Life Financials 85 55 64% 85 (0) 0%
Current Year Financials 30 0 0% 27 (3) -10%
Project Description
Project Manager Steven Milne/ John McKenna
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-23 31-Mar-23
5
Project Life Financials 16 14 85% 16 0 0%
Current Year Financials 2 0 0% 2 (0) 0%
Project Description
Project Manager Steven Milne/ John McKenna
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-23 31-Mar-23
6
Project Life Financials 50 0 0% 50 0 0%
Current Year Financials 50 0 0% 50 0 0%
Project Description
Project Manager Steven Milne/ John McKenna
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-23 31-Mar-23
Automatic Meter Readers - Water
Automatic Meter Readers.
Planned End Date Forecast End Date
Water Meter Downsize
Water Meter Downsize.
Main Issues / Reason for Variance
Water meter works to be carried out in the last quarter of the year. Previous works with electricity meter supplier did not meet expectations. Await
resolutions before issuing further orders.
Mitigating Action
None required.
Anticipated Outcome
All works to be completed 2022/23.
Anticipated Outcome
Delivery of project within budget.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Project integrated with Water AMR project. All works to be carried out in the last quarter of the year. Expect full spend.
Mitigating Action
None required
Mitigating Action
None available at this time.
Anticipated Outcome
Works complete 2022/23
Lighting upgrades to LED in schools and Corporate buildings
Upgrade lighting in schools and corporate buildings.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Initial building surveys being carried out with layout of existing lighting. Expect full spend depending on access restrictions and availability of DLO
to carry out the work.
Page 96

Page 45

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2022
Budget Details
Project Life Financials
Spend to Date Variance
7
Project Life Financials 2,188 58 3% 1,651 (538) -25%
Current Year Financials 1,651 58 4% 1,450 (201) -12%
Project Description
Project Manager Gillian McNamara/ Michael McGuinness
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-23 31-Mar-24
8
Project Life Financials 9,782 4,928 50% 9,797 15 0%
Current Year Financials 2,223 30 1% 2,075 (148) -7%
Project Description
Project Manager Gillian McNamara/ Michael McGuinness
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-24 31-Mar-24
9
Project Life Financials 1,166 1,023 88% 1,166 0 0%
Current Year Financials 143 0 0% 143 0 0%
Project Description
Project Manager Gillian McNamara/ Michael McGuinness
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-23 31-Mar-23
Planned End Date Forecast End Date
Main Issues / Reason for Variance
LED budget is invested across our town centres and strategic sites and is used to develop and implement projects as well as providing match
funding to lever in external funding. During 2022/2023 the key projects to be developed and delivered include a contribution towards Smollett
Fountain public realm, enabling works at Mitchell Way subject to the timescale of the developer, development costs associated with Dumbarton
Waterfront, the Arc of Attraction Strategy and in Clydebank implementation of the Development Framework and delivery of the Activities Centre.
Many regeneration projects are subject to factors outwith Council control and close monitoring of the programming is required. A contingency is
included for increasing costs and new funding opportunities.
Mitigating Action
None available at this time.
Regeneration/Local Economic Development
Budget to facilitate the delivery of Regeneration throughout West Dunbartonshire, aligned to the Economic
Strategy. External funding will be sought to maximise opportunities for redevelopment of these sites.
Town Centre Fund
Scottish Government funding to help improve local town centres.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
The remaining Town Centre Fund will be spent on the Smollett Fountain public realm works which will be completed by the end of the financial
year.
Main Issues / Reason for Variance
The remaining Regeneration Fund projects are Dumbarton Waterfront Path; the contribution towards the costs of Glencairn House; Connecting
Dumbarton; and the Scottish Marine Technology Park at the former Carless site. As Levelling Up Fund is programmed to be spent before
Regeneration Fund for Glencairn House and Connecting Dumbarton, it is not anticipated that any Regeneration Fund will be spent on these
projects during this financial year and will be carried forward. Spend against The £2.0m Clyde Mission funding for SMTP will continue during the
financial year 2022/2023 before an agreement is reached on the £2.0m of Regeneration Fund investment. Dumbarton Waterfront Path will be
developed according to landowner timescales, and only some spend is anticipated this year.
Mitigating Action
Programme management approach to delivery.
Anticipated Outcome
Progress towards delivery of planned projects from Economic Development Strategy and Charrette Action Plans albeit later than originally
anticipated.
Anticipated Outcome
Improved town centres and strategic sites across West Dunbartonshire.
Regeneration Fund
Funding to implement major regeneration projects linked to community charrettes. 
Planned End Date Forecast End Date
Mitigating Action
None available at this time.
Anticipated Outcome
Regenerated Town Centres.
Page 97

Page 46

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2022
Budget Details
Project Life Financials
Spend to Date Variance
10
Project Life Financials 1,456 139 10% 1,456 0 0%
Current Year Financials 1,317 0 0% 1,112 (205) -16%
Project Description
Project Manager Gillian McNamara/ Michael McGuinness
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-23 31-Mar-23
11
Project Life Financials 747 0 0% 747 0 0%
Current Year Financials 747 0 0% 747 0 0%
Project Description
Project Manager Gillian McNamara/ Michael McGuinness
Chief Officer Peter Hessett
Project Lifecycle 31-Dec-22 30-Jun-23
12
Project Life Financials 125 56 45% 125 0 0%
Current Year Financials 69 0 0% 69 0 0%
Project Description
Project Manager Gillian McNamara/ Michael McGuinness
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-23 30-Jun-23
Anticipated Outcome
Place-based improvements that advance Scottish Government's priorities of 20 min neighbourhoods and carbon zero.
Clydebank Can On The Canal
New activities centre in Clydebank Town Centre.
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
The budget includes a £0.641m contribution to Titan Boulevard at Queens Quay and £0.441m towards implementation of Alexandria Masterplan
projects.
Mitigating Action
Programme involves  expenditure over a number of projects led by different services. Regular reporting between services will help early
identification of risk.
Place Based Investment Programme
Scottish Government Funding to establish a Place-Based Investment Programme to ensure that all place
based investments are shaped by the needs and aspirations of local communities.
Mitigating Action
None available at this time.
Anticipated Outcome
Successful LUF applications that meet UK Government's over-riding objective of Levelling Up and transformational regeneration.
Levelling up
Successful LUF applications that meet UK Government's over-riding objective of Levelling Up and
transformational regeneration.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
This capacity funding was awarded by UK Government to assist with development of LUF bids. WDC has been awarded a grant from LUF
Round 1 and the capacity funding will be used in part to produce Artizan Centre redevelopment options. The balance will be used for
Roads/Transportation to develop a major transportation bid for LUF2.
Main Issues / Reason for Variance
Kier is appointed to design and deliver the Activities Centre at Clydebank Town Centre. Design of the project is underway and a commencement
date for construction is to be confirmed however this will be later than anticipated due to some administrative delays.
Mitigating Action
None available at this time.
Anticipated Outcome
New community-run activities centre in Clydebank Town Centre.
Page 98

Page 47

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2022
Budget Details
Project Life Financials
Spend to Date Variance
13
Project Life Financials 21,578 21,628 100% 21,748 170 1%
Current Year Financials 120 0 0% 120 0 0%
Project Description
Project Manager Patricia Rowley/ Craig Jardine
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-23 31-Mar-23
14
Project Life Financials 11,100 0 0% 11,100 0 0%
Current Year Financials 3,600 0 0% 3,600 0 0%
Project Description
Project Manager Patricia Rowley/ Craig Jardine
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-24 31-Mar-24
15
Project Life Financials 34,050 2,726 8% 34,049 (1) 0%
Current Year Financials 986 46 5% 986 (0) 0%
Project Description
Project Manager Patricia Rowley/ Craig Jardine
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-27 31-Mar-27
Main Issues / Reason for Variance
Consultancy costs financed by income received
Mitigating Action
None required
Anticipated Outcome
Consultancy costs for District Heating
District Heating
Consultancy Costs for District Heating
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Regular updates are provided at every Council meeting and monthly Project Board meetings and to City Deal.  The main issues contained within
the new Council's approved Outline Business Case are still valid, which include Exxon's remediation strategy, land transfer arrangements and
issues relating to adjoining owners.  WDC Consultants are monitoring the remediation process to ensure compliance with specification, also
Esso are independently monitoring the remediation works.  Final Business Case submission is November 2022. Through the Scape framework
we are working closely with Balfour Beatty to achieve a formal pre construction agreement to allow the detailed design works to commence and
the full construction programme to be developed. Agreements in principle are progressing with third party land owners.
Mitigating Action
None required.
Mitigating Action
None available at this time.
Anticipated Outcome
Project will be delivered on budget.
Exxon City Deal
As part of the City Deal project the WDC Exxon site at Bowling regeneration with alternative A82 route
included.
District Heating Network Expansion
District Heating Network Expansion.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Network expansion to GJNH (Golden Jubilee National Hospital) will commence pending approval to proceed by the GJNH Board. 
Anticipated Outcome
Delivery of the project on time and within the increased budget.
Page 99

Page 48

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2022
Budget Details
Project Life Financials
Spend to Date Variance
16
Project Life Financials 8,535 124 1% 8,535 (0) 0%
Current Year Financials 1,715 5 0% 1,715 0 0%
Project Description
Project Manager Sharon Jump/ Craig Jardine
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-25 31-Mar-25
17
Project Life Financials 1,912 124 7% 1,912 0 0%
Current Year Financials 1,912 124 7% 1,912 (0) 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-23 31-Mar-23
18
Project Life Financials 350 9 3% 350 0 0%
Current Year Financials 0 0 0% 0 0 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-24 31-Mar-24
Depot Rationalisation
Depot Rationalisation.
Main Issues / Reason for Variance
Works progressing.
Mitigating Action
None available at this time.
Anticipated Outcome
Full budget spend anticipated and request for FY22/23 acceleration of budget received.
Anticipated Outcome
Project business case will be brought back to project board and Council.
Building Upgrades and H&S - lifecycle & reactive building upgrades
Lifecycle and reactive building upgrades.
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Design Team have been appointed to develop feasibility options for the DRP Project, currently in stage 1 of this phase reviewing service
requirements.  The conclusion of the feasibility report will provide input for the options appraisal exercise.  The intention would be to bring a
business case to the IRED Committee in November 2022.
Mitigating Action
None available at this time.
Mitigating Action
None available at this time.
Anticipated Outcome
To deliver new sports changing facility.
New Sports Changing Facility Dumbarton West (Old OLSP site) 
New Sports Changing Facility Dumbarton West (Old OLSP site) 
Planned End Date Forecast End Date
Main Issues / Reason for Variance
The budget for this project has been rephased to FY 2023/2024.
Page 100

Page 49

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2022
Budget Details
Project Life Financials
Spend to Date Variance
19
Project Life Financials 150 16 11% 150 0 0%
Current Year Financials 134 0 0% 134 (0) 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-21 31-Mar-23
20
Project Life Financials 750 664 89% 750 0 0%
Current Year Financials 86 0 0% 86 (0) 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-22 31-Mar-23
21
Project Life Financials 2,375 87 4% 2,375 (0) 0%
Current Year Financials 1,090 3 0% 1,090 (0) 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-22 31-Mar-24
Holm Park & Yoker Athletic FC
Develop a new 3G pitch to act as a home venue for Clydebank FC with extensive community access.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Project now complete awaiting invoices.
Main Issues / Reason for Variance
Project had been delayed due to a number of COVID-19 related issues and utilities issues.  Unit is now in production but delay to site due to the
utility disconnection and demolition works. 
Mitigating Action
None available at this time.
Anticipated Outcome
To deliver new sports changing facility.
New Sports Changing Facility at Lusset Glen in Old Kilpatrick
New Sports Changing Facility at Lusset Glen in Old Kilpatrick
Planned End Date Forecast End Date
Anticipated Outcome
New build community facility.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Planning Permission received and currently working on internal room layouts to confirm overall budget required to complete project.  Previous
delays, include application for planning permission which Officers elongated due to requirement to go to design panel, and delays in additional
information being able to be provided to Planning due to site visits not being able to be carried out because of COVID-19 restrictions.  Currently
room layouts are being discussed with the group, this will then allow a review of costs to minimise the additional budget required to complete the
Mitigating Action
None available at this time.
Mitigating Action
None available at this time.
Anticipated Outcome
Project delivered on budget.
New Westbridgend Community Centre
New Westbridgend Community Centre
Page 101

Page 50

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2022
Budget Details
Project Life Financials
Spend to Date Variance
22
Project Life Financials 150 0 0% 150 0 0%
Current Year Financials 150 0 0% 150 0 0%
Project Description
Project Manager Michelle Lynn
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-25 31-Mar-25
23
Project Life Financials 78 0 0% 78 0 0%
Current Year Financials 78 0 0% 78 0 0%
Project Description
Project Manager Martin Feeney
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-22 31-Mar-23
24
Project Life Financials 45 0 0% 45 0 0%
Current Year Financials 45 0 0% 45 0 0%
Project Description
Project Manager Martin Feeney
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-22 31-Mar-23
Changing Places Toilet Provision
Changing places toilet provision in four public buildings - Balloch bus stance toilets, Concord Community
Centre, Dalmuir Community Centre and Clydebank East Community Centre.
Planned End Date Forecast End Date
Mitigating Action
None available at this time.
Anticipated Outcome
Project delivered within budget.
Elevated Platforms (Building Services)
Elevated Platforms (Building Services).
Purchase of 3 Welfare Units
At Council meeting on 30th August 2017 it was agreed to purchase 3 Welfare Units as a spend-to-save
proposal.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Welfare Units will be purchased by the end of the financial year.
Main Issues / Reason for Variance
Plans have been prepared and projects will be progressed by the end of the financial year.
Mitigating Action
None available at this time.
Anticipated Outcome
Project delivered within budget.
Anticipated Outcome
Project delivered within budget.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
It is anticipated that spend will be achieved by the end of the financial year 2022/2023.
Mitigating Action
None available at this time.
Page 102

Page 51

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2022
Budget Details
Project Life Financials
Spend to Date Variance
25
Project Life Financials 405 2 0% 405 0 0%
Current Year Financials 405 2 0% 405 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
26
Project Life Financials 472 406 86% 472 0 0%
Current Year Financials 66 0 0% 66 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
27
Project Life Financials 1,726 1,718 100% 1,726 0 0%
Current Year Financials 13 5 38% 13 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
Main Issues / Reason for Variance
Projects are currently being developed to deliver better access in our parks, cemeteries and open spaces. Full budget spend anticipated in
2022/23.
Mitigating Action
None required at this time.
Anticipated Outcome
Better access with parks, cemeteries and open spaces.
Public non-adopted paths and roads
Upgrades to drainage and lighting to enhance the lifespan of paths and roads within  facilities in public
parks, cemeteries and civic spaces.
Planned End Date Forecast End Date
Anticipated Outcome
Budget to be vired to Posties Park Project.
Environmental Improvement Fund
This fund has been created to deliver environmental improvement projects for communities throughout West
Dunbartonshire.
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
This fund has now closed. Funding to be vired to Posties Park project.
Mitigating Action
None required
Community Sports Fund
Match funding of up to 75% for local sports clubs to develop business cases to improve facilities.
Main Issues / Reason for Variance
Remaining budget rephased from 2021/22 to progress with tree planting in 2022/23 in line with the Councils Climate Change and Biodiversity
action plans.  Full budget spend anticipated.
Mitigating Action
None required at this time.
Anticipated Outcome
Improvements to the environment of West Dunbartonshire.
Page 103

Page 52

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2022
Budget Details
Project Life Financials
Spend to Date Variance
28
Project Life Financials 50 37 73% 50 (0) 0%
Current Year Financials 13 0 0% 13 (0) 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
29
Project Life Financials 220 214 97% 220 0 0%
Current Year Financials 7 0 0% 7 (0) 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 03-Apr-21 31-Mar-22
30
Project Life Financials 200 0 0% 200 0 0%
Current Year Financials 30 0 0% 30 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
31
Project Life Financials 581 59 10% 581 (0) 0%
Current Year Financials 122 0 0% 122 (0) 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-22 31-Mar-22
Mitigating Action
None required at this time.
Anticipated Outcome
Sustainable burial environment for local residents.
Kilmaronock Cemetery Extension
Extension of existing cemetery at Kilmaronock. 
Planned End Date Forecast End Date
Main Issues / Reason for Variance
This budget will be used to develop an area of the existing Cemetery for additional burials.  Project scope has now been developed and will be
tendered under the minor civils framework.  Budget spend anticipated in 2022/23.
Main Issues / Reason for Variance
Project works complete.  Retentions to be paid in 2022/23.
Mitigating Action
None required at this time.
Anticipated Outcome
New all weather tennis courts.
Sports Facilities Upgrades - Argyll Park - Construction of 3 All Weather Tennis Courts
Project is part of wider investment in sporting facilities and is dependent on match funding from Sports
Scotland. Agreement in principle to wider WDC strategic priorities.
Planned End Date Actual End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Consultant and design team fees for resurfacing of 3G pitch at East End Park.
Mitigating Action
None required.
East End Park Resurfacing
Resurfacing of 3G pitch at East End Park.
Main Issues / Reason for Variance
Development of play areas to improve accessibility and inclusiveness of play areas throughout West Dunbartonshire.
Mitigating Action
None required at this time.
Anticipated Outcome
Renewal of play parks
Anticipated Outcome
Resurfacing of 3G pitch at East End Park.
Play Parks Grant Funding
Renew and replace play park equipment
Planned End Date Forecast End Date
Page 104

Page 53

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2022
Budget Details
Project Life Financials
Spend to Date Variance
32
Project Life Financials 210 0 0% 210 0 0%
Current Year Financials 10 0 0% 10 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 30-Nov-23 30-Nov-23
33
Project Life Financials 25 0 0% 25 0 0%
Current Year Financials 25 0 0% 25 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
34
Project Life Financials 102 0 0% 102 0 0%
Current Year Financials 102 0 0% 102 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
Balloch Mountain Bike Track
Develop a mountain bike skills trail at Balloch Castle Country Park.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Design fees to develop Mountain bike skills trail in Balloch country park. Project to commence April 2023 and works to be complete by November
2023.
Anticipated Outcome
Large bins provided for high traffic areas
Knowes Nature Reserve
Nature resource for Faifley Community
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Supply and install extra large litter bins as a pilot project within hotspot problem areas. Project is due to commence August 2022 and completion
is anticipated by March 2023.
Mitigating Action
None required at this time.
Mitigating Action
None required at this time.
Anticipated Outcome
Mountain bike track
Large bins for high traffic areas (pilot)
Supply and install extra large litter bins as a pilot project within hotspot problem areas.
Main Issues / Reason for Variance
Funding received from Nature Restoration Fund to build nature resource for Faifley community. Project due to commence 1st April 2022 and
completion anticipated by November 2022.
Mitigating Action
None required at this time.
Anticipated Outcome
Nature resource for Faifley Community
Page 105

Page 54

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2022
Budget Details
Project Life Financials
Spend to Date Variance
35
Project Life Financials 740 350 47% 350 (390) -53%
Current Year Financials 390 0 0% 0 (390) -100%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Jul-22 31-Jul-22
36
Project Life Financials 683 0 0% 566 (117) -17%
Current Year Financials 683 0 0% 566 (117) -17%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
37
Project Life Financials 203 0 0% 107 (96) -47%
Current Year Financials 107 0 0% 107 (0) 0%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
Mitigating Action
None required at this time.
Anticipated Outcome
To provide people of West Dunbartonshire additional space to help adhere to social distancing guidelines.
Spaces for People
Funding has been awarded from Sustrans to assist with social distancing measures required as a result of
the COVID-19 pandemic.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
The programme is now complete and there will be no further expenditure.
Main Issues / Reason for Variance
To develop projects including Balloch Park Phase 2, and other projects principally around National Cycle Network 7 and further pedestrian
dropped kerbs
Mitigating Action
None required at this time.
Anticipated Outcome
To improve connectivity and enhanced Cycling routes within West Dunbartonshire.
Cycling, Walking and Safer Streets
Introduction of enhanced walking routes and traffic calming schemes to introduce safer streets within West
Dunbartonshire.
Planned End Date Forecast End Date
Mitigating Action
None required at this time.
Anticipated Outcome
To improve Footways in West Dunbartonshire.
Footways/Cycle Path Upgrades
Renewal and/or enhancement of failed footpaths/cycle paths through West Dunbartonshire.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Projects and locations still to be decided.
Page 106

Page 55

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2022
Budget Details
Project Life Financials
Spend to Date Variance
38
Project Life Financials 200 0 0% 5 (195) -97%
Current Year Financials 5 0 0% 5 0 0%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
39
Project Life Financials 60 55 91% 60 0 0%
Current Year Financials 5 0 0% 5 0 0%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
40
Project Life Financials 314 215 68% 314 (0) 0%
Current Year Financials 100 0 0% 100 (0) 0%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Budget to be used for retention payment from last years surfacing of Dumbarton East footways.
Mitigating Action
None required at this time.
Additional Pavement Improvements
Extra funding to accelerate pavement maintenance and improvements across West Dunbartonshire.
Turnberry Homes - traffic calming/ management at Turnberry housing development off Castle Road
Funding has been received from Turnberry Homes and will be used to introduce traffic calming and traffic
management measures to mitigate the impact of additional traffic accessing the housing development off
Castle Road, Dumbarton.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Consultation completed 2021/2022 and speed humps will be installed prior to 31 March 2023.
Anticipated Outcome
To improve Footways in West Dunbartonshire.
Anticipated Outcome
To provide Electric Vehicle Charging points within West Dunbartonshire.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Charging points to be installed at Moss O' Balloch park by the end of this financial year.
Mitigating Action
None required at this time.
Mitigating Action
None required at this time.
Anticipated Outcome
Traffic calming to be installed in Dumbarton East.
Electrical Charging Points - Rapid Charge
Funding has been awarded from Transport Scotland for the Installation of electrical charging points
Page 107

Page 56

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2022
Budget Details
Project Life Financials
Spend to Date Variance
41
Project Life Financials 1,257 0 0% 1,257 0 0%
Current Year Financials 1,257 0 0% 1,257 0 0%
Project Description
Project Manager Raymond Walsh/ Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
42
Project Life Financials 500 0 0% 500 0 0%
Current Year Financials 500 0 0% 500 0 0%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
43
Project Life Financials 149 0 0% 149 0 0%
Current Year Financials 149 0 0% 149 0 0%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
Flood Risk Management
Enhancement of drainage infrastructure to ensure compliance with Flood Risk Management Act 2009.
Planned End Date Forecast End Date
Mitigating Action
None required at this time.
Anticipated Outcome
Projects should be complete within budget.
Infrastructure - Flooding
Essential renewal of failed drainage assets to minimise flood risk within West Dunbartonshire.
Flood Prevention
Various flood prevention projects.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Plans are under consideration by officers.
Main Issues / Reason for Variance
A detailed design for Gruggies Burn will be undertaken by the end of the financial year.
Mitigating Action
None required at this time.
Anticipated Outcome
Project should be complete within budget.
Anticipated Outcome
Intention is to complete works within budget.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Small value projects to tackle flooding events in various areas
Mitigating Action
None required at this time.
Page 108

Page 57

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2022
Budget Details
Project Life Financials
Spend to Date Variance
44
Project Life Financials 800 181 23% 800 0 0%
Current Year Financials 620 0 0% 620 0 0%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
45
Project Life Financials 1,627 5 0% 1,075 (552) -34%
Current Year Financials 1,627 5 0% 1,075 (552) -34%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
46
Project Life Financials 3,444 7 0% 3,444 0 0%
Current Year Financials 3,444 7 0% 3,444 (0) 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
Main Issues / Reason for Variance
Awaiting outcome of Scottish Government & SEPA deliberations, however officers are hopeful full budget spend can be incurred by the end of
the financial year.
Mitigating Action
None required at this time.
Anticipated Outcome
Project should be completed within budget.
River Leven Flood Prevention Scheme
River Leven Flood Prevention Scheme.
Planned End Date Forecast End Date
Mitigating Action
None required at this time.
Anticipated Outcome
Improve accessibility to Public Transport and improve journey time reliability.
Strathclyde Partnership for Transport - Bus, cycling and walking infrastructure improvements & Park and Rides
Strathclyde Partnership for Transport - Bus, cycling and walking infrastructure improvements.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Work will be undertaken during this financial year for A8014 Kilbowie Rd, A814 Congestion Measures, Balloch Station Park & Ride and Bus
Infrastructure Improvements. All of these projects will be undertaken by Roads Services.
Main Issues / Reason for Variance
Roads Operations are progressing an extensive surfacing program and have a number of schemes to be completed by the end of the financial
year.
Mitigating Action
None required at this time.
Anticipated Outcome
Intention is to complete various surfacing works by the end of March 2023.
Infrastructure - Roads
Infrastructure - Roads.
Planned End Date Forecast End Date
Page 109

Page 58

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2022
Budget Details
Project Life Financials
Spend to Date Variance
47
Project Life Financials 12 0 0% 12 0 0%
Current Year Financials 12 0 0% 12 (0) 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
48
Project Life Financials 97 35 36% 97 (0) 0%
Current Year Financials 55 0 0% 55 (0) 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
49
Project Life Financials 15,053 421 3% 15,053 (0) 0%
Current Year Financials 1,524 0 0% 1,524 0 0%
Project Description
Project Manager Sharron Worthington
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
Street lighting and associated electrical infrastructure
WDC is responsible for the maintenance of 18,000 street lighting columns and associated illuminated signs
and bollards.  This budget is required for this infrastructure.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Budget will be used for any service work carried out by Scottish Power before or after column replacement works.
Anticipated Outcome
Intention is to complete works within budget.
Gruggies Burn Flood Prevention
Commission of Gruggies Flood Prevention Scheme.
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
This budget will be utilised for depot rationalisation works during the financial year.
Mitigating Action
None available at this time.
Mitigating Action
None available at this time.
Anticipated Outcome
Intention is to complete works within budget.
Depot Improvement Works
Improvement of WDC Roads Depot.
Main Issues / Reason for Variance
Budget to be used for a detailed design for Gruggies Burn.
Mitigating Action
None available at this time.
Anticipated Outcome
Project should be completed within budget.
Page 110

Page 59

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2022
Budget Details
Project Life Financials
Spend to Date Variance
50
Project Life Financials 2,325 1,007 43% 2,325 0 0%
Current Year Financials 693 0 0% 693 (0) 0%
Project Description
Project Manager Sharron Worthington
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-26 31-Mar-26
51
Project Life Financials 2,325 0 0% 2,325 0 0%
Current Year Financials 0 0 0% 0 0 0%
Project Description
Project Manager Sharron Worthington
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-26 31-Mar-26
52
Project Life Financials 4,300 3,802 88% 4,300 (0) 0%
Current Year Financials 498 0 0% 498 (0) 0%
Project Description
Project Manager Sharron Worthington
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-22 31-Mar-22
Mitigating Action
None required at this time.
Anticipated Outcome
To provide an improved A813.
A813 Road Improvement Phase 2
A813 Road Improvement Phase 2.
A813 Road Improvement Phase 1
A813 Road Improvement Phase 1.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Plans have been developed for carriageway widening and footway and cycleway construction between Strathleven and Lions Gate.  There are
ongoing discussions with Aggreko and other land owners in regards to access and land acquisition with construction commencing during
2022/2023.
Main Issues / Reason for Variance
Works substantially complete. Additional works as a compensation event due to start on Wallace street in July 2022.
Mitigating Action
None required at this time.
Anticipated Outcome
Project should be completed within budget enhancing the A814 through Clydebank.
Anticipated Outcome
To provide an improved A813.
Clydebank Charrette, A814
Clydebank Charrette, A814
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
These works are not due to commence until Phase 1 has been completed.
Mitigating Action
None required at this time.
Page 111

Page 60

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2022
Budget Details
Project Life Financials
Spend to Date Variance
53
Project Life Financials 3,930 3,846 98% 3,846 (84) -2%
Current Year Financials 84 0 0% 0 (84) -100%
Project Description
Project Manager Cameron Muir
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-22 31-May-21
54
Project Life Financials 1,039 650 63% 1,039 (0) 0%
Current Year Financials 117 6 5% 117 (0) 0%
Project Description
Project Manager Cameron Muir
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
55
Project Life Financials 80 0 0% 80 0 0%
Current Year Financials 40 0 0% 40 0 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Works to Renton footbridge are now complete and work will commence on the other bridges.
Mitigating Action
None available at this time.
Mitigating Action
None required.
Anticipated Outcome
To provide an improved Lomond Bridge.
Protective overcoating to 4 over bridges River Leven
To overcoat 4 bridges over River Leven.
A811 Lomond Bridge
Upgrade of Lomond Bridge.
Planned End Date Actual End Date
Main Issues / Reason for Variance
Works to Lomond Bridge were completed May 2021. No further costs expected.
Main Issues / Reason for Variance
New Plant to be purchased
Mitigating Action
None required.
Anticipated Outcome
To purchase equipment.
Anticipated Outcome
To upgrade bridges within West Dunbartonshire.
Roads Plant
Purchase of Roads plant and equipment.
Planned End Date Forecast End Date
Page 112

Page 61

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2022
Budget Details
Project Life Financials
Spend to Date Variance
56
Project Life Financials 350 0 0% 350 0 0%
Current Year Financials 350 0 0% 350 0 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
57
Project Life Financials 300 0 0% 300 0 0%
Current Year Financials 300 0 0% 300 0 0%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
58
Project Life Financials 1,000 0 0% 1,000 0 0%
Current Year Financials 1,000 0 0% 1,000 0 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
Footway Resurfacing (RAMP)
Footway resurfacing
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Projects and locations to be decided.
Anticipated Outcome
To upgrade traffic signals.
Roads improvements
Various road improvement projects
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Projects and locations to be decided.
Mitigating Action
None required.
Mitigating Action
None required.
Anticipated Outcome
Resurface footways.
Traffic Signal Upgrades
Upgrade Traffic Signals
Main Issues / Reason for Variance
Projects and locations to be decided.
Mitigating Action
None required.
Anticipated Outcome
Improvements to roads
Page 113

Page 62

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2022
Budget Details
Project Life Financials
Spend to Date Variance
59
Project Life Financials 100 0 0% 100 0 0%
Current Year Financials 100 0 0% 100 0 0%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
60
Project Life Financials 1,000 0 0% 1,000 0 0%
Current Year Financials 1,000 0 0% 1,000 0 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
61
Project Life Financials 30 0 0% 30 0 0%
Current Year Financials 30 0 0% 30 0 0%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
62
Project Life Financials 400 0 0% 400 0 0%
Current Year Financials 400 0 0% 400 0 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-22 31-Mar-23
Mitigating Action
None required.
Anticipated Outcome
Renewal of street signage.
Pavement improvements
Various pavement improvement projects.
Street sign renewal
Renewal of street signs
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Projects and locations to be decided.
Main Issues / Reason for Variance
Expenditure on water safety equipment will be made as required throughout the year.
Mitigating Action
None required
Anticipated Outcome
Water safety equipment as required.
Anticipated Outcome
Improvement to pavements.
Water Safety
To develop Water Safety Policy & enhance water safety equipment in WDC
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Projects and locations to be decided.
Mitigating Action
None required.
Main Issues / Reason for Variance
Delivery expected by September 2022 and full budget spend expected before the end of the financial year.
Mitigating Action
None available at this time.
Anticipated Outcome
Project delivered within  budget.
Purchase of gritters
Purchase of gritters.
Planned End Date Forecast End Date
Page 114

Page 63

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2022
Budget Details
Project Life Financials
Spend to Date Variance
63
Project Life Financials 1,980 0 0% 1,980 0 0%
Current Year Financials 180 0 0% 45 (135) -75%
Project Description
Project Manager Kenny Lang
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
64
Project Life Financials 160 0 0% 160 0 0%
Current Year Financials 80 0 0% 80 0 0%
Project Description
Project Manager Kenny Lang
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
65
Project Life Financials 1,150 1,124 98% 1,150 (0) 0%
Current Year Financials 26 0 0% 26 0 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-22 30-Apr-22
Waste Transfer Station
The design, development and construction of a recycling and bulk waste transfer facility that will ensure all
recycling material can be sorted and disposed off appropriately to ensure compliance with landfill ban in
2025.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Consultant project nearing completion and spend will be made thereafter.
Anticipated Outcome
Project delivered within  budget.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Compactors have now been delivered.
Mitigating Action
None Required.
Mitigating Action
None Required.
Anticipated Outcome
Project delivered within budget.
Replacement of compactors at Dalmoak civic amenity site
The purchase of 2 compactors for the Council civic amenity site at Dalmoak.
Mitigating Action
None required.
Anticipated Outcome
To create new community facilities with additional space for early years provisions.
Dalmonach CE Centre
To create new community facilities with additional space for early years provisions.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Project complete and final account to be agreed.
Page 115