Item 13 - Appendix 1

West Dunbartonshire Council · 20 May 2026
Back to Infrastructure, Regeneration & Economic Development Committee — 20 May 2026 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Official#
Summary at Period 10
Project Life
Budget
Project Life
Forecast
Spend
Project Life
Variance On Track Off Track
£'000 £'000 £'000
Resources 36,055             36,055            0 6                                     2
Regulatory and Regeneration 57,125             57,125            0 6                                     2
Roads and Neighbourhoods 149,455           149,455          0 31                                   2
Total 242,635           242,635          0 43 6
ITEM 13 - APPENDIX 1