Appendix 1: Regulatory & Regeneration Delivery Plan 2025/26 – Economic Development Year-end Progress 
Our Environment 
Our resources are used in an environmentally sustainable way 
Performance Indicator
2024/25 2025/26 Owner
Value Status Value Target Short
Trend
Long
Trend Note 
Tonnage of carbon dioxide
emissions from Council
operations and assets
18,235   18,188  
2025/26 data is available in November when all
utilities bills and waste figures are validated in
advance of preparing our annual mandatory
climate change report for submission to the
Scottish Government in November 2026. 
2024/25 data, reported in November 2025,
shows significant progress. The value of 18,235
tonnes represents 33.8% reduction on the
previous year, 44.7% reduction on the 2012/13
baseline and 5.7% ahead of projected target.
These are positive steps. However, the main
reduction is from the Council's scope 3 waste
emissions, which is a result of shifting a
significant amount of waste from landfill to
incineration through the Net Zero Cooperation
Agreement with Glasgow City Council. Both
scope 1 and 2 emissions increased slightly for
2024/25 period. To reach a 61% reduction by
2030/31 we need to reduce a further 16.3% in
just over five years and investment in required to
reduce gas, electricity and diesel consumption. 
Amanda
Kean
ITEM 8 - APPENDIX 1

Page 2

Official
Action Status Progress Due Date Note Owner
Co-ordinate, monitor and report
the progress of the Council’s
Climate Change Action Plan for
2025/26  
31-Mar-
2026
Completed as planned. The Climate Change Action
Group meets regularly to progress and monitor this work
stream. To encourage wider engagement, service
specific meetings have been arranged and are now
underway.
Amanda
Kean
Develop the Local Heat and
Energy Efficiency Strategy
Delivery Plan  
31-Mar-
2026
Overdue. Recruitment for the Local Heat and Energy
Efficiency post has taken longer than anticipated. Due to
other commitments, there is not the capacity within the
climate team to finalise the Local Heat and Energy
Efficiency Delivery Plan. Once the post is filled, the
Delivery Plan will be finalised. This action will be carried
forward in 2026/27 and completed.
Amanda
Kean 
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Inability to
reduce carbon
footprint in line
with targets
The risk that the Council will be
unable to achieve net zero
emissions by 2045, both in
relation to mitigating carbon
emissions and adapting to the
impacts of climate change. Net
zero refers to achieving an
overall balance between
emissions produced and
emissions taken out of the
atmosphere. This target has
been developed in a way that
mirrors the emission reduction
trajectory set by the Scottish  
01-Apr-
2026
The risk assessment remains
unchanged from mid-year. 
The Council's most recent
emissions, reported in November
2025 for 2024/25, showed
significant progress. (Details are
set out under the PI ‘Tonnage of
carbon dioxide emissions from
Council operations and assets’
above.) 
The long-term Climate Change
Coordinator vacancy has been
Alan
Douglas;
Amanda
Kean; Gail
Macfarlane

Page 3

Official
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Government in light of the
Climate Emergency. 
filled internally; this currently
leaves another vacancy within the
energy team that will be filled as
soon as possible. Participation
from service areas has increased
at Climate Change Action Plan
meetings and emission
reductions actions and projects
are forthcoming. The Council also
has the opportunity to utilise
ClimateView and track trajectory
to Net Zero, allowing actions and
projects to be prioritised and a
more collective, strategic
approach to be implemented. 
The Strategic Risk will be
reviewed at the next Climate
Change Action Plan meeting for
relevance and an amended risk /
set of risks will be reported to
future meetings.

Page 4

Official
Our neighbourhoods are sustainable and attractive 
Action Status Progress Due Date Note Owner
Promote the next phases of
Queens Quay Housing  
31-Mar-
2026
Completed as planned. Officers continue to progress this
site and support delivery. A planning application for
residential development on part of the site has been
submitted and further residential applications are
expected Q2 2026/2027.
Michael
Mulgrew;
Magda
Swider 
Our Economy 
Our area has the infrastructure for sustainable and inclusive growth where businesses can flourish 
Performance Indicator
2024/25 2025/26
Owner Value Status Value Target Short
Trend
Long
Trend Note
Number of businesses given
advice and assistance to
start up through Business
Gateway
190  188 180  
Target exceeded. During 2025/26, 188
businesses were provided with advice to
start-up through Business Gateway,
exceeding the target of 180.
Gillian
Scholes
Number of business
gateway start-ups per
10,000 population
21.32   19.78  
2025/26 data for this Local Government
Benchmarking Framework (LGBF) indicator
will be available at a later date following
publication by the Improvement Service. 
Based on the LGBF comparative data for the
previous year (2024/25) published by the
Improvement Service in February 2026,
performance was better than the Scottish
average of 12.3, and better than the family
Gillian
Scholes

Page 5

Official
Performance Indicator
2024/25 2025/26
Owner Value Status Value Target Short
Trend
Long
Trend Note
group average of 12.2, with a ranking of 2 of
32 local authorities, down 1 place from the
previous year.
Proportion of properties
receiving superfast
broadband
99.8%   99%  
2025/26 data for this LGBF indicator will be
available at a later date following publication
by the Improvement Service. 
Based on the LGBF comparative data for the
previous year (2024/25) published by the
Improvement Service in February 2026,
performance was better than the Scottish
average of 97.1%, and better than the family
group average of 99.1%, with a ranking of 1
of 32 local authorities, consistent with the
previous year.
Gillian
Scholes 
Action Status Progress Due Date Note Owner
Deliver key regeneration sites
across West Dunbartonshire  
31-Mar-
2026
Completed as planned. 
• Work to support the regeneration of the Exxon and
Scottish Marine Technology Park (SMTP) is progressing
well. SMTP was approved as an Investment Zone project
in November 2025 and Malin Group are currently
preparing an Outline Business Case. Investment Zone
funding will contribute £20m towards development of the
SMTP over the next 10 years. 
• An application for Regeneration Capital Grant funding
progressed to Stage 2 and results are expected in
Spring. 
Magda
Swider

Page 6

Official
Action Status Progress Due Date Note Owner
• Construction works on the Exxon site are progressing
well, with a significant milestone achieved in January
2026 when the western underbridge was completed by
Network Rail. Work is also underway on marketing the
Exxon site and further updates will be provided to the
project board.
Explore commercial
opportunities in our town
centres and wider regeneration
sites  
31-Mar-
2026
Progress has been achieved in a number of areas over
the year including discussions with prospective
developers with regards to the Queens Quay
development and appointment of consultants to develop
a Tourism Strategy for the West Dunbartonshire. 
However, one milestone relating to the Council's
consideration of the Planning Permission in Principle
(PPIP) application for the Masterplan Dumbarton Artizan
redevelopment has been delayed due to prolonged
engagement with the Scottish Environmental Protection
Agency (SEPA) which is a statutory consultee. SEPA
objected to the application on the grounds that it does
not comply with Policy 22 of the National Planning
Framework 4 and provided comments on our Flood Risk
Assessment. The Flood Risk Assessment was
subsequently amended to address their feedback and
re-submitted to Planning and we are currently awaiting
SEPA’s response. SEPA’s objection will not be lifted,
however, once their response is received, the PPIP will
be considered by the Council. It is expected to be Spring
or early Summer 2026. 
Magda
Swider

Page 7

Official
Action Status Progress Due Date Note Owner
Deliver business support
interventions through the UK
Shared Prosperity Fund
2025/26  
31-Mar-
2026
Completed as planned. Business grants available
through the UK Shared Prosperity Fund have been
promoted through social media, council website and
directly to eligible businesses. The UK Government has
extended the deadline for grant spend until the end of
September 2026. We will continue to appraise and
process applications to maximise funding through this
period.
Gillian
Scholes
Support town centre
revitalisation  
31-Mar-
2026
Completed as planned. In Alexandria, we have been
working with the Business Improvement District to
develop designs for Mitchell Way/main Street
improvements. We have also appointed a contractor for
the Alexander Street improvements, another of the
Alexandria Masterplan projects. In Clydebank, a big
milestone was achieved when the Pride in Place Plan
was submitted to the UK Government. Once approved it
will unlock up to £20m funding over the next 10 years. In
Dumbarton, delivery of the UK Government funded
regeneration works in the town centre is progressing
well, with Phase 1 of Artizan redevelopment now on site. 
Magda
Swider 
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Failure to
deliver Queens
Quay
Masterplan
Following completion of Council
investment there is a risk the
housing plot sales do not
materialise in the next 3-7
years, with implications for the
return on investment and the  
11-Mar-
2026
Risk remains unchanged.
Delivery of site remains
embedded in service
workstreams.
Michael
Mulgrew;
Magda
Swider

Page 8

Official
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
business case for the District
Heating Network. 
Inability to meet
demands of
Council to
progress
regeneration
projects within
desired
timescales
The number and complexity of
regeneration projects is putting
considerable strain on the
resources available which can
be exacerbated by delays out
with the control of the service
and when pinch points on
different projects occur at
roughly the same time. 
11-Mar-
2026
Risk remains unchanged.
Individual projects continue to
progress and are regularly
reviewed, reducing the likelihood
of undesirable outcomes.
Embedded in workstreams to
ensure sufficient resource to
support delivery of projects within
required timescales.
Michael
Mulgrew;
Magda
Swider 
Our Council 
Our residents are engaged and empowered 
Action Status Progress Due Date Note Owner
Continue the development of
Community Planning  
31-Mar-
2026
Completed as planned. The development of Community
Planning has progressed well during 2025/26. A review
of Delivery Improvement Groups was completed and a
recommendations paper was submitted to the
Management Board in November setting out
recommendations on partnership reporting. A pilot in
Alexandria looking at access to services was established
and the initial engagement stage was completed in
2025/26. Next steps will be identified, and this work will
continue in 2026/27.
Colin Smith

Page 9

Official
Action Status Progress Due Date Note Owner
Continue to contribute to the
Community Learning and
Development Plan 2024/27  
31-Mar-
2026
Completed as planned. The Communities Team
continues to deliver community development support to
groups across West Dunbartonshire to maximise their
impact. This can be through support to secure external
funding, promotion or by developing skills and improving
governance arrangements. The team is represented on
the Community Development Alliance and plays a key
role in supporting communities through the development
of Locality Plans. Of particular note, we supported the
completion of two community-led Local Place Plans in
Old Kilpatrick and Central Alexandria, both of which have
been approved and adopted at Planning Committee.
Colin Smith
Conclude the Cash First Project
including evaluation  
31-Mar-
2026
Completed as planned. The Cash First Project is a
Scottish Government initiative to end the need for food
banks in Scotland through providing funds or vouchers to
people in financial crisis. Delivered jointly by the
Communities Team and Working 4U, it has been very
successful, with the available funding reaching those
most in need through a network of trusted partner
referrals. The Communities Team has developed and
carried out the evaluation engagement to support the
Cash-First programme. This will be submitted to the
Scottish Government as the end of the project draws to a
successful close.
Colin Smith

Page 10

Official
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Engaging
positively with
Residents,
Communities &
Partnerships
The risk that the Council fails to
adequately engage, establish
and maintain positive
relationships with local residents
and communities in addition to
partnership bodies.   
11-Mar-
2026
A partnership approach to
Community engagement is being
undertaken led by the Community
Planning Partnership and
associated partnerships -
Community Learning and
Development and Community
Development Alliance in
particular. The Communities
Team and other partners deliver
community development work
which seeks to raise awareness
of community planning and
Community Empowerment in
communities. Locality plans,
community-led place planning
and work to support the
Clydebank Neighbourhood
Board’s community engagement
means this risk is unchanged.
Colin Smith

Page 11

Official
Action Status 
Overdue 
Completed 
PI Status 
Target met or exceeded 
Risk Status 
Warning 
OK 
Long Term Trends 
Getting worse 
Short Term Trends 
Getting worse