WEST DUNBARTONSHIRE COUNCIL 
Report by Chief Officer – Roads and Neighbourhood 
Infrastructure, Regeneration and Economic Development Committee 
on 20 May 2026 
Subject: Roads and Neighbourhood Delivery Plan 2025/26 - Year-end
Progress & Roads and Neighbourhood Delivery Plan 2026/27 
1 Purpose 
1.1 This report sets out the year-end progress of the 2025/26 Delivery Plan and
presents the new Delivery Plan for 2026/27. 
2 Recommendations 
2.1 It is recommended that Committee notes the progress achieved at year-end
and the new Plan for 2026/27. 
3 Background 
3.1 In line with the Strategic Planning & Performance Framework, each Chief
Officer develops an annual Delivery Plan which sets out actions to help deliver
the Strategic Plan and address the performance challenges and service
priorities identified in the planning process. The Plan also provides an
overview of services and resources, including employees and budgets, sets
out the performance indicators (PIs) for monitoring progress and considers the
relevant risks. 
4 Main Issues 
2025/26 Year-end Progress 
4.1 The 2025/26 Delivery Plan was presented to Infrastructure, Regeneration and
Economic Development Committee on 21 May 2024 and mid-year progress
reported on 12 November 2025. 
4.2 Full details of year-end progress are set out in Appendix 1. 
ITEM 7

Page 2

4.3 The progress of the Plan’s 34 actions is summarised below: 
Progress No. (%) 
Completed 30 (88%) 
Overdue 4 (12%) 
4.4 Overdue actions relate to the following and will be carried forward and
progressed / completed in 2026/27: 
• Progress plan to increase the number of 4G pitches – 50% complete. 
• Develop a new local bio diversity action plan – 75% complete. 
• Provide recommendations to Council based on draft Surface Water
Management Plans – 87% complete.
• Work force planning; Develop and implement wellbeing, employee
engagement quality and learning and development plans to enable
capabilities, improve resilience and promotion of a diverse workforce –
83% complete 
4.5 Year-end data is available for 22 of the Plan’s 24 PIs. The performance of
those PIs is summarised below: 
Performance Against Target No. (%) 
Target met or exceeded 15 (68%) 
Target significantly missed 3 (14%) 
Target marginally missed 4 (18%)
Performance Over Time No. (%) 
Improved over short term (or maintained high
level of performance)
4 (18%) 
Improved over longer term (or maintained high
level of performance)
6 (27%) 
4.6 Where target was significantly missed, this relates to the following PIs: 
• % Residents satisfied with the waste service overall; 51% against a
target of 70%. 
• % Residents satisfied with roads maintenance; 20% against a target of
40%.
• % residents satisfied with the street cleaning service; 46% against a
target of 60%.
4.7 The full set of PIs will be reported through the Council’s annual performance
reporting process once all data becomes available.

Page 3

2026/27 Delivery Plan 
4.8 The 2026/27 Delivery Plan is set out at Appendix 2. 
4.9 Key priorities include: 
• Progress phased delivery of public and fleet electric charging points. 
• Progress preparatory work for Gruggies Burn Flood Management,
progress flood management improvement plans and provide
recommendations on draft Surface Water Management Plans.
• Progress strategy to implement 20 miles speed limit in residential areas
• Progress the delivery of the Exxon City Deal Project
• Progress ash die back action plan and finalise a new local biodiversity
action plan
• Progress plan to increase the number of 4G pitches and complete the
upgrade of 4 existing play parks and deliver two new destination parks.
• Revise service provision of litter collection and street cleaning of trunk
road
• Revise service provision of Crematorium
• Within Working4U, ensure compliance with External Funding
requirements and continue partnership working.
• Develop a new employability partnership investment plan and explore
the potential for securing training and opportunities in the green energy
sector
• Compile and publish the local child poverty actions and manage and
deliver the Community Learning Development partnership and plan.
• Reduce Working4U team and realign the service.
• Develop Strategy for transition to electric fleet and introduce operational
management of the corporate fleet. 
4.10 Implementation of the Plan will be monitored by the management team with
mid-year and year-end progress reported to Infrastructure, Regeneration and
Economic Development Committee around November 2025 and May 2026
respectively. 
5 People Implications 
5.1 There are no direct people implications arising from this report.

Page 4

6 Financial & Procurement Implications 
6.1  There are no direct financial or procurement implications arising from this
report. 
7 Risk Analysis 
7.1 Failure to deliver on the actions assigned to Roads and Neighbourhood may
have a direct impact on the delivery of the Council’s Strategic Plan. It is
essential that remedial action is taken to ensure strategic delivery plans
achieve the commitments detailed. 
8 Equalities Impact Assessment 
8.1 Screening and impact assessments will be carried out on specific activities as
required. 
9 Consultation 
9.1  The delivery plans were developed through consultation with officers from the
strategic service areas. 
10 Strategic Assessment 
10.1  The delivery plans set out actions to support the successful delivery of the
strategic priorities and objectives of the Council. 
Chief Officer: Gail Macfarlane
Service Area:  Roads and Neighbourhood
Date:   6 May 2026
_____________________________________________________________ 
Person to Contact:  Karen Connelly    
Performance & Strategy Business Partner    
karen.Connelly@west-dunbarton.gov.uk 
Appendices:  Appendix 1: Roads and Neighbourhood Delivery Plan
2025/26 - Year-end Progress 
Appendix 2: Roads and Neighbourhood Delivery Plan
2026/27

Page 5

Background Papers: Roads and Neighbourhood Delivery Plan 2025/26 -
Infrastructure Regeneration and Economic Development
Committee, 21 May 2025 
Roads and Neighbourhood Delivery Plan 2025/26 Mid-
year Progress - Infrastructure Regeneration and
Economic Development, 12 November 2025 
Strategic Planning & Performance Framework 2022/27   
Wards Affected: All