Page 1

Agenda 
Infrastructure, Regeneration and
Economic Development Committee 
Date:  Wednesday, 20 May 2026
___________________________________________________________________ 
Time:  10:00 
___________________________________________________________________ 
Format:  Hybrid meeting
___________________________________________________________________ 
Contact:    Nicola Moorcroft, Committee Officer
nicola.moorcroft@west-dunbarton.gov.uk  
committee.admin@west-dunbarton.gov.uk 
Dear Member 
Please attend a meeting of the Infrastructure, Regeneration and Economic
Development Committee as detailed above. 
Members will have the option to attend the meeting remotely, or in person, at the Civic
Space, 16 Church Street, Dumbarton G82 1QL. 
The business is shown on the attached agenda. 
Yours faithfully 
PETER HESSETT 
Chief Executive 
Page 1

Page 2

Distribution:- 
Councillor David McBride (Chair)
Councillor Kevin Crawford
Councillor Michelle McGinty
Councillor John Millar
Councillor Lawrence O’Neill (Vice Chair)
Councillor Lauren Oxley
Councillor Chris Pollock
Councillor Martin Rooney
Councillor William Rooney
Councillor Gordon Scanlan
Councillor Hazel Sorrell
Councillor Sophie Traynor 
All other Councillors for information 
Chief Executive
Chief Officer – Regulatory and Regeneration
Chief Officer – Roads and Neighbourhood
Chief Officer – Resources 
Date of Issue: 7 May 2026 
Audio Streaming 
Audio recordings of the meeting (including the attendance or contribution of any party
participating or making a contribution) will be published on the Council’s website and the
Council’s host’s webcast/audio stream platform. 
You should be aware that the Council is a Data Controller under the General Data
Protection Regulation.  Data collected during this audio stream will be retained in
accordance with the Council’s Privacy Notice* and Retention Schedules including, but not
limited to, for the purpose of keeping historical records and making those records available
via the Council’s internet site. 
*http://www.west-dunbarton.gov.uk/privacy/privacy-notice/ 
Page 2

Page 3

INFRASTRUCTURE, REGENERATION AND ECONOMIC
DEVELOPMENT COMMITTEE 
WEDNESDAY, 20 MAY 2026
AGENDA 
1 STATEMENT BY CHAIR – AUDIO STREAMING 
The Chair will be heard in connection with the above. 
2 APOLOGIES 
3 DECLARATIONS OF INTEREST 
Members are invited to declare if they have an interest in any of the items of
business on this agenda and the reasons for such declarations. 
4 RECORDING OF VOTES 
The Committee is asked to agree that all votes taken during the meeting be done by
roll call vote to ensure an accurate record. 
5 OPEN FORUM               
The Committee is asked to note that no open forum questions have been
submitted by members of the public. 
6 MINUTES OF PREVIOUS MEETING      5 - 8 
Submit for approval, as a correct record, the Minutes of the Meeting of the
Infrastructure, Regeneration and Economic Development Committee held on 4
February 2026. 
7 ROADS AND NEIGHBOURHOOD 25/26 DELIVERY PLAN 
YEAR-END REPORT AND ROADS AND NEIGHBOURHOOD
26/27 DELIVERY PLAN 
9 - 54 
Submit report by the Chief Officer – Roads and Neighbourhood setting out the year-
end progress of the 2025/26 Delivery Plan and presenting the new Delivery Plan for
2026/27. 
Page 3

Page 4

8 REGULATORY AND REGENERATION DELIVERY PLAN  
2025/26 - ECONOMIC DEVELOPMENT YEAR-END 
PROGRESS AND REGULATORY AND REGENERATION 
DELIVERY PLAN 2026/27 - ECONOMIC DEVELOPMENT
55 - 84
Submit report by the Chief Officer – Regulation and Regeneration setting out the
year-end progress of the 2025/26 Delivery Plan and presenting the new Delivery
Plan for 2026/27 in relation to Economic Development. 
9 RESOURCES DELIVERY PLAN 2025/26 YEAR-END  
PROGRESS (ASSET MANAGEMENT) AND RESOURCES
DELIVERY PLAN 2026/27 (ASSET MANAGEMENT) 
85 - 103
Submit report by the Chief Officer – Resources setting out the year-end progress of
the 2025/26 Delivery Plan and presenting the new Delivery Plan for 2026/27 in
relation to Asset Management. 
10  TRAFFIC REGULATION ORDER REVIEW PANEL   105 - 121
Submit report by the Chief Officer – Roads and Neighbourhood seeking approval for
the detailed process for the review and approval of new Traffic Regulation Orders. 
11 REVIEW OF 20MPH STREET TRO OBJECTIONS    123 - 146
Submit report by the Chief Officer – Roads and Neighbourhood seeking approval to
proceed with Traffic Regulation Orders to support reduction of speed limits on the
road’s detailed within the Appendix 1 of the report. 
12 INFRASTRUCTURE, REGENERATION AND ECONOMIC     147 - 160                 
DEVELOPMENT REVENUE MONITORING REPORT 2025/256 
TO PERIOD 10 (31 JANUARY 2026)  
Submit report by the Chief Officer – Resources providing an update on the revenue
financial performanceto 31 January 2026 of those services under the auspices of the
Infrastructure, Regeneration and Economic Development Committee. 
13  INFRASTRUCTURE, REGENERATION AND ECONOMIC               161 - 173       
DEVELOPMENT CAPITAL MONITORING REPORT 2025/26
TO PERIOD 10 (31 JANUARY 2026)   
Submit report by the Chief Officer – Resources providing an update on the capital
financial performance to 31 January 2026 of those services under the auspices of
the Infrastructure, Regeneration and Economic Development Committee. 
Page 4

Page 5

INFRASTRUCTURE, REGENERATION AND ECONOMIC DEVELOPMENT
COMMITTEE 
At a Hybrid Meeting of the Infrastructure, Regeneration and Economic Development
Committee held in the Civic Space, 16 Church Street, Dumbarton on Wednesday,
4 February 2026 at 10.00 a.m. 
Present: Councillors David McBride, Kevin Crawford, Michelle McGinty.
Lawrence O’Neill, Chris Pollock, Martin Rooney, William
Rooney, Hazel Sorrell, Clare Steel and Sophie Traynor. 
Attending: Gail Macfarlane, Chief Officer – Roads and Neighbourhood;
Laurence Slavin, Chief Officer – Resources; Michelle Lynn,
Asset Manager; Christopher Anderson, Section Head and
Principal Solicitor; and Nicola Moorcroft and Scott Kelly,
Committee Officers. 
Apologies: Apologies for absence were intimated on behalf of Councillors
Lauren Oxley and Gordon Scanlan.
.
Councillor David McBride in the Chair 
STATEMENT BY CHAIR – AUDIO STREAMING 
Councillor McBride, Chair, advised that the meeting was being audio streamed and
broadcast live to the internet and would be available for playback. 
DECLARATIONS OF INTEREST 
Councillor Lawrence O’Neill declared an interest in the item ‘Pride in Place Impact
Fund Allocation’, being Chair to the Board of a funding recipient, and indicated that
he would leave the meeting during consideration of this item. 
RECORDING OF VOTES 
The Committee agreed that all votes taken during the meeting be carried out by roll
call vote to ensure an accurate record. 
ITEM 6
Page 5

Page 6

OPEN FORUM 
The Committee noted that no open forum questions had been submitted by
members of the public. 
MINUTES OF PREVIOUS MEETING 
The Minutes of Meeting of the Infrastructure, Regeneration and Economic
Development Committee held on 12 November 2025 were submitted and approved
as a correct record. 
UPDATE ON ACTIVITY BY CLYDEBANK PROPERTY COMPANY LTD 
A report was submitted by the Chief Officer – Resources providing an update on the
financial position of Clydebank Property Company following completion of the audit
of the 2024/25 accounts. 
After discussion and having heard the Chief Officer – Resources and the Asset
Manager in further explanation and in answer to Members’ questions, the Committee
agreed:- 
(1) to note that the Clydebank Property Company returned a 2024/25 net loss of
£0.060m; and 
(2) to note that as at 31 March 2025, Clydebank Property Company had total
reserves of £2.883m of which £2.464m were non-distributable and £0.419m
were distributable. 
Having previously declared an interest in the following item, Councillor O’Neill left the
meeting at this point. 
PRIDE IN PLACE IMPACT FUND ALLOCATION 
A report was submitted by the Chief Officer – Regulatory and Regeneration seeking
approval for allocation of funding from the Pride in Place Impact Fund. 
After discussion and having heard the Chief Officer – Roads and Neighbourhood in
further explanation and in answer to Members’ questions, Councillor McBride,
seconded by Councillor Sorrell, moved that the Committee:- 
(1) notes that the Council has been allocated £1.5M of Pride in Place Impact
Fund in 2025/26 and 2026/27; 
(2) approves the allocation of £0.240M to Holm Park improvement, Clydebank; 
(3) approves the allocation of £0.060M to Western Titans BMX Club track
improvements, Clydebank;
Page 6

Page 7

(4) approves the allocation of £0.600M to create new destination playparks in
Alexandria (Christie Park) and Dumbarton (Dumbarton Common); 
(5) approves the allocation of £0.600M to community grants for capital projects
which meet the aims and objectives of the fund; 
(6) authorises the commencement of procurement processes relating to the
projects as appropriate and the subsequent award of contracts by the Chief
Officer – Regulatory and Regeneration; and 
(7) agrees that in the event of any project not appearing to be deliverable within
the required timescale or requirements of the funding conditions then the
Chief Officer – Regulatory and Regeneration may substitute an alternative
project following consultation with the Convenor of IRED Committee. 
As an amendment, Councillor Pollock, seconded by Councillor Traynor, moved:- 
That the Committee agrees to the recommendations as set out in the report
with the following amendment to recommendation (7):- 
That in the event of any project not appearing to be deliverable within the
desired timescales or requirements of the funding conditions, then the
Chief Officer – Regulatory and Regeneration brings the matter back for
consideration to a future IRED Committee or hold a Special IRED
Committee meeting to determine how the funding should be allocated. 
On a roll call vote being taken, 3 Members voted for the amendment namely Councillors
Crawford, Pollock, and Traynor and 6 Members voted for the motion namely, Councillors
McBride, McGinty, Martin Rooney, William Rooney, Steel and Sorrell. The motion was
accordingly declared carried. 
Note: Councillor O’Neill rejoined the meeting at this point. 
INFRASTRUCTURE, REGENERATION AND ECONOMIC DEVELOPMENT
REVENUE MONITORING REPORT 2025/256 TO PERIOD 7 (31 OCTOBER 2025) 
A report was submitted by the Chief Officer – Resources providing an update on the
revenue financial performance to 31 October 2025 of those services under the
auspices of the Infrastructure, Regeneration and Economic Development
Committee. 
After discussion and having heard the Chief Officer – Resources and the Chief
Officer – Roads and Neighbourhood in further explanation and in answer to
Members’ questions, the Committee agreed:- 
(1) to note a projected adverse variance against budget of £0.416m (2.41% of
total budget); and 
(2) to note the current projected use of earmarked reserves of £0.504m.
Page 7

Page 8

INFRASTRUCTURE, REGENERATION AND ECONOMIC DEVELOPMENT
CAPITAL MONITORING REPORT 2025/26 TO PERIOD 7 (31 OCTOBER 2025) 
A report was submitted by the Chief Officer – Resources providing an update on the
capital financial performance to 31 October 2025 of those services under the
auspices of the Infrastructure, Regeneration and Economic Development
Committee. 
After discussion and having heard the Chief Officer – Roads and Neighbourhood and
the Asset Manager in further explanation and in answer to Members’ questions, the
Committee agreed:- 
(1) to note the current position of the 2025/26 IRED capital budget; 
(2) to note the revised completion dates in respect of one project detailed in
Appendix 2 to the report, reported to Council on 17 December 2025; 
(3) to note the reprofiling of three projects in Appendix 3 to the report, reported to
Council on 17 December 2025; 
(4) to note additional capital budget of £0.500m for food waste vehicles reported
to Council on 17 December 2025, as detailed in paragraph 4.4 of the report; 
(5) to grant delegated authority to the Chief Officer – Regulatory and
Regeneration, in consultation with the Procurement Manager, to award
procurement and contract awards for projects relating to the Local Economic
Development Plan to develop Mitchell Way and Main Street in Alexandria;
and 
(6) to grant delegated authority to Chief Officer – Roads and Neighbourhood, in
consultation with the Procurement Manager, to award any procurement and
contract awards for projects related to the vehicle replacement programme. 
Note: Councillor Steel left the meeting during consideration of this item. 
The meeting closed at 10.48 a.m. 
Page 8

Page 9

WEST DUNBARTONSHIRE COUNCIL 
Report by Chief Officer – Roads and Neighbourhood 
Infrastructure, Regeneration and Economic Development Committee 
on 20 May 2026 
Subject: Roads and Neighbourhood Delivery Plan 2025/26 - Year-end
Progress & Roads and Neighbourhood Delivery Plan 2026/27 
1 Purpose 
1.1 This report sets out the year-end progress of the 2025/26 Delivery Plan and
presents the new Delivery Plan for 2026/27. 
2 Recommendations 
2.1 It is recommended that Committee notes the progress achieved at year-end
and the new Plan for 2026/27. 
3 Background 
3.1 In line with the Strategic Planning & Performance Framework, each Chief
Officer develops an annual Delivery Plan which sets out actions to help deliver
the Strategic Plan and address the performance challenges and service
priorities identified in the planning process. The Plan also provides an
overview of services and resources, including employees and budgets, sets
out the performance indicators (PIs) for monitoring progress and considers the
relevant risks. 
4 Main Issues 
2025/26 Year-end Progress 
4.1 The 2025/26 Delivery Plan was presented to Infrastructure, Regeneration and
Economic Development Committee on 21 May 2024 and mid-year progress
reported on 12 November 2025. 
4.2 Full details of year-end progress are set out in Appendix 1. 
ITEM 7
Page 9

Page 10

4.3 The progress of the Plan’s 34 actions is summarised below: 
Progress No. (%) 
Completed 30 (88%) 
Overdue 4 (12%) 
4.4 Overdue actions relate to the following and will be carried forward and
progressed / completed in 2026/27: 
• Progress plan to increase the number of 4G pitches – 50% complete. 
• Develop a new local bio diversity action plan – 75% complete. 
• Provide recommendations to Council based on draft Surface Water
Management Plans – 87% complete.
• Work force planning; Develop and implement wellbeing, employee
engagement quality and learning and development plans to enable
capabilities, improve resilience and promotion of a diverse workforce –
83% complete 
4.5 Year-end data is available for 22 of the Plan’s 24 PIs. The performance of
those PIs is summarised below: 
Performance Against Target No. (%) 
Target met or exceeded 15 (68%) 
Target significantly missed 3 (14%) 
Target marginally missed 4 (18%)
Performance Over Time No. (%) 
Improved over short term (or maintained high
level of performance)
4 (18%) 
Improved over longer term (or maintained high
level of performance)
6 (27%) 
4.6 Where target was significantly missed, this relates to the following PIs: 
• % Residents satisfied with the waste service overall; 51% against a
target of 70%. 
• % Residents satisfied with roads maintenance; 20% against a target of
40%.
• % residents satisfied with the street cleaning service; 46% against a
target of 60%.
4.7 The full set of PIs will be reported through the Council’s annual performance
reporting process once all data becomes available. 
Page 10

Page 11

2026/27 Delivery Plan 
4.8 The 2026/27 Delivery Plan is set out at Appendix 2. 
4.9 Key priorities include: 
• Progress phased delivery of public and fleet electric charging points. 
• Progress preparatory work for Gruggies Burn Flood Management,
progress flood management improvement plans and provide
recommendations on draft Surface Water Management Plans.
• Progress strategy to implement 20 miles speed limit in residential areas
• Progress the delivery of the Exxon City Deal Project
• Progress ash die back action plan and finalise a new local biodiversity
action plan
• Progress plan to increase the number of 4G pitches and complete the
upgrade of 4 existing play parks and deliver two new destination parks.
• Revise service provision of litter collection and street cleaning of trunk
road
• Revise service provision of Crematorium
• Within Working4U, ensure compliance with External Funding
requirements and continue partnership working.
• Develop a new employability partnership investment plan and explore
the potential for securing training and opportunities in the green energy
sector
• Compile and publish the local child poverty actions and manage and
deliver the Community Learning Development partnership and plan.
• Reduce Working4U team and realign the service.
• Develop Strategy for transition to electric fleet and introduce operational
management of the corporate fleet. 
4.10 Implementation of the Plan will be monitored by the management team with
mid-year and year-end progress reported to Infrastructure, Regeneration and
Economic Development Committee around November 2025 and May 2026
respectively. 
5 People Implications 
5.1 There are no direct people implications arising from this report. 
Page 11

Page 12

6 Financial & Procurement Implications 
6.1  There are no direct financial or procurement implications arising from this
report. 
7 Risk Analysis 
7.1 Failure to deliver on the actions assigned to Roads and Neighbourhood may
have a direct impact on the delivery of the Council’s Strategic Plan. It is
essential that remedial action is taken to ensure strategic delivery plans
achieve the commitments detailed. 
8 Equalities Impact Assessment 
8.1 Screening and impact assessments will be carried out on specific activities as
required. 
9 Consultation 
9.1  The delivery plans were developed through consultation with officers from the
strategic service areas. 
10 Strategic Assessment 
10.1  The delivery plans set out actions to support the successful delivery of the
strategic priorities and objectives of the Council. 
Chief Officer: Gail Macfarlane
Service Area:  Roads and Neighbourhood
Date:   6 May 2026
_____________________________________________________________ 
Person to Contact:  Karen Connelly    
Performance & Strategy Business Partner    
karen.Connelly@west-dunbarton.gov.uk 
Appendices:  Appendix 1: Roads and Neighbourhood Delivery Plan
2025/26 - Year-end Progress 
Appendix 2: Roads and Neighbourhood Delivery Plan
2026/27 
Page 12

Page 13

Background Papers: Roads and Neighbourhood Delivery Plan 2025/26 -
Infrastructure Regeneration and Economic Development
Committee, 21 May 2025 
Roads and Neighbourhood Delivery Plan 2025/26 Mid-
year Progress - Infrastructure Regeneration and
Economic Development, 12 November 2025 
Strategic Planning & Performance Framework 2022/27   
Wards Affected: All
Page 13

Page 14

Appendix 1 - R&N Delivery Plan Year-end Progress 25/26 
1. Our communities 
Objective 1. Our neighbourhoods are safe, resilient and inclusive 
Performance Indicator
2024/25 2025/26
Owner
Value Status Value Target Short Trend Long Trend Note
Percentage of non serious road related defects
repaired within 7 working days of being reported 93.3%  86.5% 85%   Target achieved. Liam Greene
Percentage of routine road related defects repaired
within 28 working days of being reported 80.97%  86.3% 85%  
Target achieved. Over 4%
improvement on previous year with
upward trend.
Liam Greene
Percentage of emergency road related defects
repaired within 4 hours of being reported 99.08%  98.25% 95%   Continue to exceed target. Liam Greene
Percentage of all traffic light repairs completed
within 48 hours 98%  98% 98%   Target met. Liam Greene
Percentage of all street light repairs completed
within 7 days 97.7%  95% 95%   Target met. Liam Greene 
Action Status Progress Due Date Note Owner
Progress the development of pavement parking
enforcement strategy for consideration by
relevant Committee  
31-Mar-2026
Action complete. Officers to monitor pavement
parking violations identified by Parking enforcement
Officers to review resource requirements to support
future Council wide enforcement and policy
recommendations. 
Liam Greene                           
ITEM 7 - APPENDIX 1
Page 14

Page 15

Action Status Progress Due Date Note Owner
Progress plan to introduce Parking Enforcement   31-Mar-2026
Action complete. All consolidation orders are
promoted to introduce parking enforcement. Issuing
of Penalty Charge Notice (PCN) for parking
violations commenced in November 2025.  
Liam Greene
Implement revised service provision for school
crossing patrollers   31-Mar-2026 Action complete. Crossing patroller locations
reduced and limited to priority locations. Liam Greene
Implement 20 miles speed limit at Balloch
Campus and Dalreoch Primary School   31-Mar-2026 Action complete. Lining and signing works
completed. Liam Greene
Prepare strategy to implement 20 miles speed
limit in residential areas   31-Mar-2026 Action complete. Traffic order promoted with phase
1 to go live in May 2026. Liam Greene 
Objective 2. Our residents health and wellbeing remains a priority 
Action Status Progress Due Date Note Owner
Complete construction of 4 new MUGA's and
delivery of 2025/26 playpark improvement
programme  
31-Mar-2026
Action complete. We have completed 4 new Multi
Use Games Areas (MUGA) at Bonhill, Goldenhill
Park, Milton Park and Breval Crescent. In addition,
five further play areas were delivered and located at
Dennistoun Forge, Lusset Park, Braes Avenue,
Dalmuir Park and Balloch Country Park.
Ian Bain
Progress plan to increase the number of 4G
pitches   31-Mar-2026
Action will be carried forward to 2026 due to
delaying receiving planning permission. Work will
commence on Argyle Park in May with Mount Blow
estimated to be delivered October 2026. 
Ian Bain 
2. Our Environment 
Page 15

Page 16

Objective 4. Our local environment is protected, enhanced and valued 
Performance Indicator
2024/25 2025/26
Owner
Value Status Value Target Short Trend Long Trend Note
Tonnage of biodegradable municipal waste
landfilled 8,001  4,533.17 13,300  
Target exceeded with Significant
improvement over the year. All
general waste is now sent to an
energy-from-waste processing
facility, with only residual waste
going to landfill. Target will be
reviewed for 2026/27.
Ian Bain
% Residents satisfied with the Waste service
overall 60%  51% 70%  
Performance significantly missed
target and trending down. Of the 300
responses to this question,
comments include; people very
unhappy or disagree with the
introduction of the charge for brown
bin / garden waste collections and
changes to bin collection frequency. 
Satisfaction data is now sourced from
the Council’s Citizens’ Panel. This
change has resulted in a smaller
respondent base, meaning that
variations in satisfaction levels are
more pronounced. As a result,
findings should be viewed as
indicative rather than fully
representative.  
Ian Bain
Percentage of missed bins collected within 3
working days of being reported 96%  92% 95%  
Target marginally missed. Due to
significant service change in the early
stages there were a higher number of
missed bins and extended
recollection times
Ian Bain
% of total household waste that is recycled 54.5%   60%   Year end data will be available mid
May Ian Bain
% residents satisfied with the street cleaning
service 62%  46% 60%  
Performance significantly missed
target and continuing a downward
trend. Of the 290 responses to this
Ian Bain
Page 16

Page 17

4
Performance Indicator
2024/25 2025/26
Owner
Value Status Value Target Short Trend Long Trend Note
question, comments include; lack of
cleaning of streets, not seeing street
cleaners, waste left when bins are
collected, too much dog dirt, lack of
litter bins and overfull litter bins. 
Satisfaction data is now sourced from
the Council’s Citizens’ Panel. This
change has resulted in a smaller
respondent base, meaning that
variations in satisfaction levels are
more pronounced. As a result,
findings should be viewed as
indicative rather than fully
representative.  
% Residents satisfied with Parks & open spaces 72%  68% 75%  
Performance narrowly missed target
and down by 4% from previous year.
Of the 268 responses to this
question, Comments include
dissatisfaction with the lack of grass
cutting and reduced flower planting
and high levels of dog fouling. There
were positive comments on
Levengrove park and the
improvement in grass cutting. 
Satisfaction data is now sourced from
the Council’s Citizens’ Panel. This
change has resulted in a smaller
respondent base, meaning that
variations in satisfaction levels are
more pronounced. As a result,
findings should be viewed as
indicative rather than fully
representative.  
Ian Bain 
Action Status Progress Due Date Note Owner
Explore funding opportunities for delivery of
Dumbarton Common allotments   31-Mar-2026
Action complete. Final allotment site at Dumbarton
Common will be complete early in May. This will
provide 50 individual allotments together with a
community growing site. 
Ian Bain
Page 17

Page 18

Action Status Progress Due Date Note Owner
Develop a new local biodiversity action plan   31-Mar-2026
Action carried over to 26/27 due to delay in Scottish
Government publishing the national plan and
guidance. Draft plan nearing completion and
expected to be presented to September IRED
Committee.  
Ian Bain
Develop ash die back action plan – next phase   31-Mar-2026
Action complete. The action plan is in place,
including dealing with high-risk trees that are
categorised as requiring immediate action. We will
continue to progress this and deal with low and
medium risk trees.  
Ian Bain 
Objective 5. Our resources are used in an environmentally sustainable way 
Action Status Progress Due Date Note Owner
Continue to refine the strategy for transition to
an electric fleet   31-Mar-2026
Action progressing. We have established a service
plan that identifies our priorities as
.      Enhance fleet efficiency: 
.      Promote sustainability: 
.      Increase operational transparency:
.      Improve fleet safety and compliance: 
Within this context we will promote sustainability by
developing a vehicle replacement programme that
tracks Government targets for the transition of the
fleet to electric vehicles. We are exploring ways, in
tandem, to establish and effective charging
infrastructure. We have set clear targets for both
elements to ensure we meet the policy
requirements.
Stephen Brooks
Progress phased delivery of public and fleet
electric charging points – next phase   31-Mar-2026
Action complete, next phase will progress next year.
High level locations for spread of public chargers
developed with City Region. All site details provided
to consultants. Glasgow City Council as project lead
will issue tender with proposed implementation date
of 2026.   
Liam Greene
Implement the Prioritisation of collection of
recycling project.   31-Mar-2026 Action complete. Implementation resulted in some
early challenges with service delivery the service in Ian Bain
Page 18

Page 19

Action Status Progress Due Date Note Owner
the main is now business as usual. Early indications
show that tonnages of recycling waste have
increased. this was the main aim of the introduction
of the new collection schedule 
Objective 6. Our neighbourhoods are sustainable and attractive 
Performance Indicator
2024/25 2025/26
Owner
Value Status Value Target Short Trend Long Trend Note
% of Class A roads that should be considered for
maintenance treatment 19.2%  21.8% 24%   Target met. Liam Greene
% of Class B roads that should be considered for
maintenance treatment 19.9%   24.5%   Data will be available mid-May Liam Greene
% of Class C roads that should be considered for
maintenance treatment 23.3%  27.3% 30%   Target met. Liam Greene
Percentage of unclassified roads that should be
considered for maintenance treatment 30.2%  31.2% 37%   Target met. Liam Greene
% Residents satisfied with roads maintenance 24%  20% 40%  
Performance significantly missed
target and down by 4% from
previous year. Of the 295 responses
to this question, Comments include
concern at the number and size of
potholes, poor general maintenance
of roads and concern shown over lack
of white lines in a number of
locations.
Satisfaction data is now sourced from
the Council’s Citizens’ Panel. This
change has resulted in a smaller
respondent base, meaning that
variations in satisfaction levels are
more pronounced. As a result,
findings should be viewed as
indicative rather than fully
representative. 
Liam Greene
Page 19

Page 20

Performance Indicator
2024/25 2025/26
Owner
Value Status Value Target Short Trend Long Trend Note
The service continue to show
satisfactory results in the operational
performance measures, including
response to reported repairs. We also
continue to investment in the road
network in line with the Roads Asset
Management Plan. 
Action Status Progress Due Date Note Owner
Implement Greenspace Service Redesign   31-Mar-2026
Action complete. Staffing restructure complete
across greenspace service, service reviewed and
changes to ground maintenance programme agreed
Ian Bain
Review and Implement Changes to Grounds
Maintenance Programme   31-Mar-2026
Action complete. Service reviewed and changes to
ground maintenance programme agreed and in
progress.
Ian Bain
Award contract for Gruggies Burn Flood
Management design   31-Mar-2026
Action complete. Contract awarded to Balfour Beatie
for construction phase which will begin Autumn
2026.
Liam Greene
Provide recommendations to Council based on
draft Surface Water Management Plans   31-Mar-2026
Action carried forward to 2026, delays in completion
due to additional consultations required with
Network Rail and Scottish Water. Report to be
issued to IRED committee in 2026.
Liam Greene
Progress Flood Management Improvement
plans for Dumbarton and Vale of Leven   31-Mar-2026 Action complete. Final surface water actions will be
submitted to Council for consideration. Liam Greene
Develop new Roads and Transport Winter Plan
for consideration at May Committee   31-Mar-2026
Action complete. Road and Transport winter plan
was presented to Committee in May. Plan is in
progress.
Liam Greene 
Page 20

Page 21

Risk Description Current
Assessment Target Assessment Date Reviewed Note Owner
Impact of major adverse
weather incidents on
services
A significant period of adverse weather
may result on failure to deliver key
operational functions of R&N services  
09-Apr-2026
The Business Continuity Plan would
come into effect in the event of a
major adverse weather incident. 
No change to risk matrix        
Ian Bain
Failure to maintain road
network during adverse
weather
A significant period of adverse weather
may result in failure to deliver key
operational functions of R&T services
and other Council services. 
09-Apr-2026
Winter training programme is in place,
and business continuity plan is in
place. 
No change to Risk Matrix
Liam Greene
Failure to manage and
maintain the road network
effectively
Failure to manage and maintain the road
network effectively will have an adverse
impact on user safety, traffic movement,
air quality, economic growth and reduce
access to facilities and amenities. The
Council’s reputation as a place to live
and work with access to employment,
education, leisure and health
opportunities would be adversely
affected. 
07-Apr-2026
Significant investment in resurfacing
works.  Service continues to respond
to reported defects across the
network. Number of internal controls
and monitoring in place. Whilst Street
lighting columns are inspected there
are significant number that are over
their expected life span. 
Likely hood reassessed to unlikely
taking account of investment plan,
roads maintenance plans and
monitoring results. 
Matrix change, from 3X2 to 3X1 
Liam Greene
Challenges in delivering
effective services in
relation to Roads &
Neighbourhoods
The risk that the Council’s fails to deliver
on the three service areas within Roads
& Neighbourhood: Roads &
Transportation, Waste & Greenspace and
Fleet & Working 4 You. These areas
provide services across a range of areas
including managing and maintaining
roads, footpaths and associated
infrastructure, managing flood risk,
winter gritting, grounds maintenance,
street cleaning, burial and cremation,
outdoor facilities, waste and recycling,
vehicle fleet management and providing  
09-Apr-2026
Monitoring and action plans in place to
manage risk. 
No change to Risk Matrix 
Gail Macfarlane
Page 21

Page 22

Risk Description Current
Assessment Target Assessment Date Reviewed Note Owner
working 4 you services such as
employability, child poverty plan, access
to benefits etc. Failing to ensure these
services are not fully fit for purpose
could result in adverse consequences in
relation to delivering efficient and
effective services. 
3. Our Economy 
Objective 7. Our area has the infrastructure for sustainable and inclusive growth where businesses can flourish 
Action Status Progress Due Date Note Owner
Support the progress of Exxon City Deal Project
– construction phase (next phase)   31-Mar-2026
Action complete. Works began on site began in
February, and all works progressing as per
programme.
Liam Greene 
Objective 8. Our residents are supported to access employment and training opportunities 
Performance Indicator
2024/25 2025/26
Owner
Value Status Value Target Short
Trend Long Trend Note
Number of local people entering education or
training 1,175  1089 750  
The annual target was exceeded,
with support delivered through a
wide range of accredited and
Stephen Brooks
Page 22

Page 23

Performance Indicator
2024/25 2025/26
Owner
Value Status Value Target Short
Trend Long Trend Note
community-based learning, targeted
employability programmes, and
apprenticeship opportunities. UKSPF
and No One Left Behind funding
focused on removing barriers and
improving long-term employability
for priority groups across West
Dunbartonshire.
Number of local people gaining an accredited
qualification 996  829 450  
Performance exceeded targets, with
Working4U delivering a broad range
of qualifications and awards, from
Modern and Foundation
Apprenticeships to community-based
and accredited courses, all focused
on improving employability and
removing barriers.
Stephen Brooks
Number of local people entering employment
through Working 4U Adult Employability 537  459 400  
Performance exceeded target. During
2025/26, W4U employability teams
focused on supporting economically
inactive and vulnerable people,
helping 459 individuals into
employment—exceeding the target of
400. Support included 1-to-1 key
worker assistance, training, barrier
removal, and job-matching through
internal provision and commissioned
NOLB and UKSP funding
Stephen Brooks
Value (£) of debt managed £1,441,721  £1,348,076 £1,520,000  
Performance marginally missed
target. Figures show that from 1st
April 2025 to 31st March 2026, 131
unique residents have been
supported to manage £1,348,076 of
debt.
There have been lower recorded debt
levels than might otherwise be
expected
Stephen Brooks 
Page 23

Page 24

Action Status Progress Due Date Note Owner
Manage, deliver and monitor the Community
Learning and Development (CLD) partnership
and associated plan.  
31-Mar-2026
Action complete. Strategic Partnership Group
continues to meet and submitted CLD Key
performance indicators nationally to CLD Managers
Scotland for West Dunbartonshire for 24/25. 
Figures for 25/26 will be collated and submitted
around Dec 2026.
Stephen Brooks
We will ensure we are compliant with funding
requirements including the need to work in
partnership and commission specialist services.  
31-Mar-2026
Action complete. As all commissioned services reach
the end of their service delivery their final position
with regards to achievement of key performance
indicators is being compiled and reported to external
funders and the Strategic Employability Group.
Stephen Brooks 
Objective 9. Our partnerships will support economic development to deliver increased prosperity for our area 
Performance Indicator
2024/25 2025/26
Owner
Value Status Value Target Short
Trend
Long
Trend Note
Number of local people receiving support through
Working 4U 7,490  6,885 4,510  
Target exceeded. In response to
increased levels of need linked to the
cost-of-living crisis and
unemployment, alongside service
reviews and the addition of specialist
provision funded through No One Left
Behind and UK Shared Prosperity
Fund resources, this target was
significantly exceeded The service
supported a total of 6,885 people
through Work, Learn and Money
support.
Stephen Brooks
Number of people receiving support through
Working 4U with more than one barrier to
employment (aggregate)
1,507  1,198 854  
Target exceeded. The Adult Learning
team and the Employability teams
target services to those individuals
with barriers to
employment.  Barriers include, lack
of qualifications, low skills, disability
or a health condition, care
Stephen Brooks
Page 24

Page 25

Performance Indicator
2024/25 2025/26
Owner
Value Status Value Target Short
Trend
Long
Trend Note
experienced, carer, justice impacted,
lived experience of substance misuse,
long term unemployed, mental health
issues among others.
Total Value (£) of Income Generated £9,218,527  £9,337,471 £6,000,000  
Target exceeded. Working4U Money
supporting residents to increase
income by £9.34m through benefit,
grant and debt management support.
Despite reduced resources, the
service now focuses on providing
advice, signposting and case
monitoring to maximise reach and
ensure outcomes are secured.
Stephen Brooks
Percentage of local people supported - with
increased or sustained income through reduced
debt liability/debt management
83.1%  81.1% 85%  
Performance marginally missed
target. With the help of Working4U,
284 local residents were supported
with debt advice/issues.  148 of
these were assisted to manage £1.3
million worth of debt.  81.1%
proceeded with their agreed debt
strategy options, with the remaining
18.9% being undecided at this time.
Progression to debt strategy options
can be limited by financial instability,
fear of consequences, emotional
barriers, eligibility restrictions, and
practical engagement challenges. In
many cases, clients require additional
time, reassurance, or stabilisation
support before proceeding.
Stephen Brooks 
Action Status Progress Due Date Note Owner
Develop a new employability partnership action
plan   31-Mar-2026
Action complete. Commissioning for 26-27 has been
agreed by the Strategic Employability Group based
on data in West Dunbartonshire and the priority
groups identified through No One Left Behind
Funding and Local Growth Funding.
Stephen Brooks
Page 25

Page 26

Action Status Progress Due Date Note Owner
Explore the potential for securing training and
opportunities in the carbon/green energy
sectors  
31-Mar-2026
Action complete. The Strategic Employability Group
have analysed data within West Dunbartonshire to
inform commissioning priorities for 26-27.  A focus
on green jobs remains a key policy area for No One
Left Behind funding.
Stephen Brooks
Compile and publish the local child poverty
report to demonstrate our actions to address
poverty and disadvantage  
31-Mar-2026 Action complete. The annual child poverty plan is
published.  Stephen Brooks 
Risk Description Current
Assessment Target Assessment Date Reviewed Note Owner
Failure to respond to child
poverty legislation will have
a significant impact on the
Council’s reputation, more
importantly an opportunity
to raise issues and respond
more effectively to child
poverty issues will be lost
The Local Child Poverty Plan sets out
what we will do to respond to child
poverty, failure to respond will have a
significant impact on the Council’s
reputation, more importantly an
opportunity to raise issues and respond
more effectively to child poverty issues
will be lost  
08-Apr-2026
The Family Prosperity Network develop
the local child poverty report and will
undertake a self-evaluation to assess
the effectiveness of our approach. The
self-evaluation will inform future
developments. The Child Poverty Plan
has been published and is available
online. No change to Risk matrix.
Stephen Brooks
The cost of living crisis will
lead to a substantial
demand for access to
welfare/debt support
services.
We will monitor the changing levels of
demand and target our resources to
individuals and areas that are most in
need. We will seek to work with partners
to ensure we receive appropriate
referrals who can benefit from our
support.   
08-Apr-2026
Welfare rights team have improved the
triage system for referrals being
received from residents with most
contacts being made within 4 working
days of referrals being received.  No
change to risk matrix.
Stephen Brooks 
4. Our Council 
Objective 10. Our workforce is resilient and skilled where digital technology supports service delivery for our residents 
Page 26

Page 27

Action Status Progress Due Date Note Owner
Develop and implement wellbeing, employee
engagement, equality and learning and
development plans to enable capabilities,
improve resilience and promotion of a diverse
workforce  
31-Mar-2026
Action progressing. Roads Structure Review
undertaken, identifying single point dependencies,
Grounds and Waste Review commenced. Working
4UWe have continued to promote of roles with a
gender bias across all genders. This includes
sessions within schools to attract or encourage
school students to have a broader understanding of
the opportunities available to them. Grounds and
Waste services will promote use of trickle with front
line staff at the next “toolbox talks”. There is a
significant amount of work to get front line staff to
use personal devise, this activity will carry over into
2026/27. 
Develop and implement employee life cycle
plans in line with the People First Strategy to
attract and retain the workforce.  
31-Mar-2026
Action complete. Fit for future actions progressed
including training for mechanics and new ilearn
developed within Fleet Services to promote
development opportunities. Cross service
consideration being given to hard to recruit roles. 
Implement service review process including
role design, use of new technology and new
ways of working to add resilience, address
gaps, and establish opportunities for
efficiencies  
31-Mar-2026
Action complete. Cross service review undertaken to
review service capacity and resources. Roads and
Transport service review complete and complies
with Standard Operating Model (SOM). 
Develop and implement learning and
development opportunities to improve
capabilities and resilience within the workforce.  
31-Mar-2026
Action complete. Drivers have been put through
large Goods Vehicle (LGV) training and medium
sized goods (C1+E) trailer training. This will provide
resilience. Mechanics trained in maintenance of
Electric Vehicles. Also continue to monitor
development of technology to stay up to date 
Objective 11. Our Council is adaptable and focused on delivering best value for our residents 
Action Status Progress Due Date Note Owner
Support the project board and monitor progress
of the Net Zero Cooperation Agreement with
Glasgow City Council  
31-Mar-2026
Action complete. Project board established with
alternate chairing between Glasgow and WDC.
Workstreams established and meetings underway to
Gail Macfarlane
Page 27

Page 28

Action Status Progress Due Date Note Owner
develop actions. This will now progress as Business
as Usual.
Progress and manage service level agreements
for Fleet management.   31-Mar-2026
Action complete. We have established a set of
tailored service agreements with all services that
operate fleet vehicles. These agreements clearly
define roles and responsibilities and are supported
by key performance metrics. The metrics will
strengthen the information available to inform
future fleet requirements and associated costs. We
are reviewing and finalising these agreements
through regular meetings with key staff from each
service area. Overall, the agreements aim to
improve fleet efficiency, support sustainability,
enhance operational transparency, and strengthen
fleet safety and compliance.
Stephen Brooks
Prepare plans to close Dalmuir Golf Course   31-Mar-2026
Action complete. The golf course in no longer in
Council ownership. The members have taken over
the course by way of asset transfer. 
Ian Bain
Road Construction Consent Charging review
and team reduction   31-Mar-2026
Action complete. Team changes made. Appropriate
council services advised of charging for Roads
Construction Consent Charging (RCCC) in line with
external charging regime. 
Liam Greene
W4U Team Reduction and Service Realignment   31-Mar-2026
Action complete. We have established a set of
dashboard indicators that take into account the
resources available for delivery. These provide data
for performance management and help us identify
areas of increasing demand.
Stephen Brooks 
Risk Description Current
Assessment Target Assessment Date Reviewed Note Owner
Challenge to delivery of
burial and cremation
services
A number of factors may impact on
ability to deliver these services.  For
example a pandemic would create
significant immediate demand on
services. 
09-Apr-2026
We have completed extensions to
Dumbarton and North Dalnottar
cemeteries and Vale Of Leven
Cemetery. This will mitigate the impact
of any challenges to the burial and
cremation services. 
No change to risk matrix.
Ian Bain
Page 28

Page 29

Risk Description Current
Assessment Target Assessment Date Reviewed Note Owner
Inability to deliver priority
services as a result of fuel
shortages
A fuel shortage would significantly
impacting on our ability to provide
priority service across West
Dunbartonshire. 
09-Apr-2026
Council participates in the Scottish
Government Liquid Fuels Framework
and contributes to the work of the
Scottish Government Fuel Resilience
Group. The fuel situation is being
monitored closely at this time due to
the conflict in Iran. 
No change to risk matrix.
Gail Macfarlane 
Action Status 
Overdue 
Not on track 
In Progress and on track 
Completed 
PI Status 
Target significantly missed 
Target narrowly missed 
Target met or exceeded 
Long Term Trends 
Improving 
No change 
Getting worse 
Short Term Trends 
Improving 
No change 
Getting worse 
Page 29

Page 30

2026/27
ROADS &
NEIGHBOURHOOD 
ITEM 7 - APPENDIX 2
Page 30

Page 31

Contents
1. Introduction .................................................................................................................................................................................................... 3
2. Performance Review ...................................................................................................................................................................................... 3
3. Strategic Assessment .................................................................................................................................................................................... 7
4. Resources .................................................................................................................................................................................................... 15
Appendix 1: Action Plan .......................................................................................................................................................................................... 17 
Page 31

Page 32

1. Introduction 
Roads & Neighbourhood comprises a wide range of services covering Roads and Transportation and Environment and Neighbourhood,
including Greenspace and Waste Management, Working 4U and Fleet Management.
It is one of seven strategic areas responsible for delivering the Council’s Strategic Plan. Key actions to help achieve this are set out in this
Delivery Plan, together with actions to address any performance issues and service priorities identified in the planning process. 
The progress of this Plan will be monitored and managed by the management team and reported to Infrastructure, Regeneration and Economic
Development Committee twice yearly, at mid-year and year-end. 
2. Performance Review 
The Roads & Neighbourhood management team completed a detailed review of 2025/26 performance, focusing on the following: 
 2025/26 Delivery Plan year end progress;
 Local Government Benchmarking Framework (LGBF) comparative data;
 Association for Public Service Excellence (APSE) comparative data;
 Citizens’ Panel feedback;
 Complaints; and
 Continuous Improvement 
This review highlighted our key achievements in 2025/26 as well as the challenges to be addressed in 2026/27. These are summarised below. 
Key Achievements in 2025/26 
Listed below are some of the major achievements. All services achieved many other key outcomes for the Council and its residents throughout
the year which are not recorded here but are as important. 
Strategic Team 
 The collaborative approach between West Dunbartonshire Council and the wider City Region to increase resilience, share best practice and
identify opportunities in the delivery of Electric Vehicle Strategy and Waste management is now embedded. 
 The Net Zero Cooperation Agreement with Glasgow City Council continues to deliver financial savings, shared learning and reduction of
duplication and also identifies further opportunities for joint working.
Page 32

Page 33

Greenspace & Waste Management
 As a result of introducing a prioritised recycling waste project, significant improvements have been made, waste sent to landfill has reduced
substantially—from 8,001 tonnes per year to 4,533 tonnes. The new collection regime is a significant change for residents and the
introduction was supported with a communications strategy providing information on recycling.
 Developed a major extension to North Dalnottar Cemetery that will secure a long-term sustainable burial site for local residents.
 Provided training and employment opportunities for 10 modern apprentices and engaged with over 300 volunteers to carry out environmental
improvement work.
 Secured external funding from Scottish Government and Nature Scotland to recruit a conservation volunteer trainer. This has allowed us to
increase the number of volunteers working within West Dunbartonshire.   
Roads & Transport
 Progressed speed reduction measures to improve road safety by securing external funding to implement mandatory 20mph speed limits in
residential streets with the first 5 areas scheduled for going live in May 2026. 
 Continued to lead on the delivery of the project transforming the former Exxon site into a key strategic development site. Completed key
project milestone with construction of the western under-bridge at A82/A814 Glasgow Road junction through partnership with Network Rail.
Primary works were completed in advance to allow for the excavation and installation of new under-bridge below the main train lines over the
Christmas Period 2025.
 Successfully applied for transfer of parking enforcement powers to West Dunbartonshire Council and completed the necessary back-office
management and road marking upgrades to begin enforcement. Supported colleagues in Housing Operations to develop new service
structure to create parking enforcement team with 4 full-time equivalent parking enforcement officers now carrying out regular patrols within
our town centres and key strategic enforcement areas.
 Worked with delivery partners to complete Gruggies Burn Detailed design and successfully completed contract negotiations to have
construction contract in place with Balfour Beatty by the 31st March 2026 Scottish Government deadline. Funding has now been secured to
deliver the £48m flood alleviation project over the next 4 years. 
Working4U & Fleet Management
 Achieved national recognition and received an Adult Learning Award in Wellbeing.  
 Extended support to particularly vulnerable groups through the Family Poverty Network and strengthened governance arrangements. The
Family Poverty Network successfully secured Fairer Futures Partnership funding to support families affected by involvement in the justice
Page 33

Page 34

system, alongside Child Poverty Accelerator funding to provide targeted support for families with children and young people with
Additional Support Needs. Supporting two full‑time equivalent staff, to deliver focused, preventative interventions.
 Funding has been secured to deliver maritime engineering focused interventions, aligned with Glasgow City Region Skills Investment
Scottish Government funding for 2025–2027. Supports 0.5 full-time equivalent staff and the commissioning of a local training provider to
deliver targeted skills provision.
 Successfully completed Her Majesty’s Inspectorate of Education Progress Visit for Community Learning and Development.
 Awarded South of Scotland Regional Lead for Macmillan welfare rights services, moving from annual to a three-year funding cycle. 
 Reduced vehicle hire costs in consultation with services by 35%.
 Developed a procurement strategy to establish the basis for the transition from internal combustion engines to electric powered vehicles. 
(13.1 % of fleet hybrid or EV).
 All mechanics completed Institute of the Motor Industry 3 & 4 level Electric Vehicle certification. This was successfully funded by
Working4U's No One Left Behind commissioned provision. 
Key Challenges from 2025/26 
Along with the achievements noted above, there were significant challenges in 2025/26. 
Cross Service 
 Resilience / Capacity Challenges. The ongoing rationalisation of resources and development of service efficiencies and savings has
resulted in many service changes. There are a range of challenges linked to a continuing and increased reduction to front line services, both
employee reductions and service delivery rationalisation. This has resulted in a number of initiatives taking longer than anticipated, increased
demand on staff, reduction in service satisfaction levels and increased complaints. This will require strict prioritisation going forward and
delivering services in a different way including service delivery redesign where required.   
 Demographic of Workforce. R&N has an aging demographic within the workforce and this is also the case nationally. We will continue to
carry out workforce analysis to identify skills gaps to provide upskilling appropriate training and succession planning to allow the Council to
plan for the future.
 Staff. The national skills shortage of qualified and experienced officers in Roads and Neighbourhood Services resulting in reduced staff
complements across services and increased demands on existing staff. Due to high demand outstripping the labour supply, labour rates
continue to increase together with challenges recruiting and retaining skilled staff. Annual external funding results in staff being recruited into
fixed term contracts for the financial year with a key drawback being that it creates job insecurity and makes retaining skilled staff more
Page 34

Page 35

challenging. This means that we will have to optimise staff retention and improve recruitment practices to ensure job roles are in line with
demand.  
 Climate Change. Due to more adverse weather condition and extreme weather events due to climate change Roads and Neighbourhood
require to make changes to operational ongoing service delivery and response to events. In particular flood risk management plans. 
Greenspace & Waste Management 
 Development of the revised ground management model to respond to reduction in budget and capacity reflecting the resources available.
This will potentially impact on the perception of service delivery and resident satisfaction.  
 Due to suppliers leaving the market we expect there will be challenges in getting suppliers / contracts in place for waste treatment options for
organic food/garden waste. This is likely to lead to increased costs. 
Roads & Transport
 Flood risk management including prioritisation and progress of initiatives continues to be a challenge. Scottish Government Cycle 2 funding
for major flood alleviation projects has been paused indefinitely and whilst we await confirmation about any future funding it is expected that
due to the rising construction costs for flood alleviation projects there will be more of a focus on flood resilience rather than alleviation. 
 Pavement parking strategy and implementation is dependent on the capacity of parking enforcement officers and identifying funding and
resources. Any large-scale enforcement would require additional enforcement resources to manage.
 Construction and material costs continue to rise, and with reductions in capital budgets the volume of carriageway and footway resurfacing
works that can be completed each year is continuously reduced. The Council has aged Street Lighting assets with 60% of existing columns
beyond their 25-year life expectancy. Limited Capital budgets mean that the service is unable to address such issues in a large, targeted
replacement programme with only severe or dangerous assets being able to be prioritised. 
Working4U & Fleet Management 
Working4U 
 Rising living costs and the growing challenges faced by people experiencing disadvantage are driving a continual increase in demand for
support. As more individuals seek welfare and benefits advice, community-based learning opportunities, and employability assistance,
services are coming under significant pressure.
 Macmillan are moving to a Regional Lead model for the delivery of Welfare Rights services to people affected by cancer from June 2026.  As
Regional Lead there is funding for project management however overall, there is a reduction in available funds for the subsequent 3 years of
the programme which will impact partners.
Page 35

Page 36

 UK Shared Prosperity funding ceased at the end of March 2026 with new funding through the Local Growth Fund for 2026-29 having a focus
on capital investment and a subsequent reduction in revenue funding affecting employability and learning delivery within Working 4U.  UK
Shared Prosperity funding supported 12 full-time equivalent posts and commissioned employability interventions from local private and third
sector organisations.  Local authorities as part of the Glasgow City Region will work across the region to design and deliver services,
potentially reducing local flexibility to meet needs within West Dunbartonshire. No One Left behind and Local Growth Fund have a focus on
employment as opposed to UK Shared Prosperity funding focus on wellbeing/anti-poverty approach. 
 Pride in Place funding through UK Government has been allocated to Clydebank with some focus on learning and employability support – the
strategic plan has been agreed with UK Government and implementation will commence from 2026. At this point the delivery of the
interventions for employability and skills development are not known.
 Scottish Government funding for both Modern and Foundation Apprenticeship programmes will transfer from Skills Development Scotland to
the Scottish Funding Council in line with the Tertiary Education and Training Bill.  Discussions are ongoing focussed on potential impacts to
local contracts for delivery.
 From April 2026, Council Apprenticeship Investment funding (£1.0m over a four‑year period) will cease. This will result in a reduction in the
number of apprentices employed by both the Council and local businesses, with a likely adverse impact on participation and attainment rates.
Reduced funding increases contract risk, making it harder to retain staff and maintain partner confidence 
Fleet Management
 The financial constraints faced by the Council and subsequent challenge in maintaining a 7 and 10 year vehicle replacement programme and
transition to electric fleet may result in increased reliance on hire vehicles. Services face significant challenges and transformation resulting in
difficulty in establishing comprehensive information about current use and future service fleet requirements. This presents challenges around
fleet planning, management and meeting service requirements.
 Transition to electric fleet and associated charging infrastructure implementation is constrained within current property/accommodation.
Progress will be dependent on the development of the plans for maintenance and fleet depot.  
 Ongoing challenges remain due to cross-service dependencies and reliance on other teams to apply required frameworks and guidance.
 Ongoing budget reduction requirements and resulting staffing changes are diminishing organisational expertise, awareness, and
understanding of responsibilities around data capture and process input, increasing the risk of compliance issues.
 Ongoing challenges due to the high specifications and costs to upgrade garage infrastructure to maintain electric vehicles. 
3. Strategic Assessment  
The Roads & Neighbourhood management team completed a strategic assessment to determine the major influences on service delivery and
priorities in 2026/27 and identified a range of key factors recognised as significant. These are summarised below.
Page 36

Page 37

Financial Challenges 
The entire public sector is continuing to face significant financial challenges due to a range of factors including inflationary cost increases, pay
awards not being fully funded by the Scottish Government and insufficient overall funding to support the delivery of front line and back-office
services. The Council is currently faced with an estimated cumulative funding gap in 2027/28 of £10.905m rising to £44.028m by 2030/31. We
will continue to monitor the overall financial position of the Council and updates on estimated future budget gaps will be reported to Elected
Members throughout 2026/27. 
These challenges require further action to balance our budget and protect services for residents. Within Roads and Neighbourhood, this means
that available funding will be reduced over time and we will need to reconfigure how we work, what we do, where we work, and potentially
reduce the number of people employed. In this context, we will aim to continue to provide a sustainable, quality service to internal clients, and
external clients and the public. 
Budget Sensitivity Analysis 
In reviewing the service budget projections, consideration has been given to sensitivity of these budgets, in particular for higher risk/ higher value
budgets which may have a significant impact on budgetary control and future budget projections. The analysis has considered sensitivity around
demand, costs and charges, and income levels. 
In Roads and Neighbourhood, budgets which have been identified as being more susceptible to fluctuations include; R&N income budgets given
the uncertainties surrounding demand and the costs relating to Waste Services can be susceptible to fluctuation depending on tonnage being
disposed of. 
Roads & Neighbourhood Action Plan 
Greenspace & Waste Management 
Ash Die Back
Ash dieback is a serious disease of ash trees caused by a fungus. The disease causes leaf loss and crown dieback in affected trees and can
lead to the death of the tree. Of the 10 million ash trees in Scotland 90% may die due to this disease. Infected trees need to be identified and
removed to prevent or minimise the spread of the disease. We carried out a full audit of affected trees, and an action plan was developed
Page 37

Page 38

identifying the extent of the issue and the associated cost pressures. In 2025/26 we progressed the Ash Die back action plan, including dealing
with trees that are categorised as requiring immediate action and high risk. In 2026/27 we will implement phase two of the removal plan 
Bio Diversity Strategy
The new Scottish Biodiversity Strategy is being developed with the aim of halting biodiversity decline by 2030 and having nature restoration
underway by 2045. Giving full consideration to the strategy the Service will develop a new local Biodiversity Action Plan identifying local actions
that will contribute to the overall aims of the national strategy. The final Scottish Government delivery plan was not published until December
2024, which was later than expected. In 2025/26, following consideration of the national strategy, we progressed the development of a local
Biodiversity Action Plan. In 2026/27 the Plan will be presented to Committee.   
Play Parks and Recreation Facilities 
We have developed plans and upgraded 8 play parks throughout West Dunbartonshire, investing £465K to improve accessibility and inclusivity.
We have completed 4 new Multi Use Games Areas (MUGA) at Bonhill, Goldenhill Park, Milton Park and Brevel Crescent to provide additional
sports facilities for young people throughout West Dunbartonshire. In addition, five further play areas were delivered in 2025/26 and located at
Dennystoun Forge, Lusset Park, Braes Avenue, Dalmuir Park and Balloch Country Park. In 26/27 we will complete the upgrade of 4 existing play
parks located at; Linnvale, Onslow Rd Clydebank, Ross Head Alexandria and Dalmonach Bonhill. 
Increase Number of 4G Pitches
The savings options agreed to delivery 2024/25 budget have resulted in changes to sports pitches. The Grounds Service maintain grass pitches
utilised for sports activities throughout West Dunbartonshire. This original proposal was to build 3 new 4G pitches to replace six underutilised
grass pitches located in Alexandria, Dumbarton and Clydebank.  In 2024/25 we undertook the design and preparation of tender documents to
deliver the 4G pitches. In 2025/26 we progressed the procurement of Argyle Park with plans submitted to Planning for Mount Blow site. There
was no suitable site located in Dumbarton therefore the Service will now deliver 2 4G pitches. Work will commence on Argyle Park in May with
Mount Blow estimated to be delivered October 2026. Due to delays in gaining planning permission the construction of these 2 pitches will be
carried forward into 2026/27.   
Destination Playparks – Pride in Place
The Council has secured £600,000 of funding through the Pride in Place programme to support the development of two new destination
playparks. The funding allocation is evenly split, with £300,000 earmarked for Dumbarton Common and £300,000 for Christie Park.
These projects are intended to deliver large-scale, high-quality destination playparks, designed to serve not only local communities but also
attract families from across the wider area. Destination playparks typically offer a broader range of inclusive, modern play equipment, improved
landscaping, accessibility features, and supporting infrastructure, helping to encourage longer visits and increased use of surrounding green
spaces. The projects are currently at the early stages of development.
Page 38

Page 39

Street Sweeping and Litter Collection of Trunk Road
The savings options agreed to deliver the 2026/27 budget have resulted in a service adjustment. The Greenspace Team undertake street
cleaning and litter collection of the A82 trunk road which is owned and maintained by Transport Scotland. The current cost to undertake is
£150,000 per annum. While there is a statutory obligation to undertake these activities, there is no set level of maintenance required. In 2026/27
we will make a saving by reducing the frequency of litter collection and street cleaning of the trunk road. 
Reduce apprenticeships 
The savings options agreed to deliver the 2026/27 budget have resulted in a reduction in apprentices in Roads and Greenspace service. The
Council’s Roads and Greenspace teams currently offer 11 apprenticeships across both services, with 1 in Roads and the remainder in
Greenspace.  These posts have been typically difficult to fill, with 5 currently vacant. Under this option, these 5 apprenticeships would be
deleted, removing the Roads apprentice opportunity, and bringing Greenspace opportunities to 6. No apprentices in post will be impacted and as
deleted posts are currently vacant there will be no service reduction. In 2026/27 we will reduce the number of apprentice posts. 
Crematorium Weekend Operations 
The savings options agreed to deliver the 2026/27 budget have resulted in a change to the service at the crematorium. Cremations have been
offered Monday to Friday and on a Saturday morning. In addition, the Book of Remembrance has been open for viewing seven days per week,
including three hours on a Saturday and five hours on a Sunday. In 2024 and 2025, there were adequate available weekday slots to
accommodate cremations held on a Saturday. Cremations and viewings of the Book of Remembrance will now be offered Monday to Friday
only, with the crematorium closed to the public at weekends. Overtime would still be utilised to cover essential activities including crematorium
cooldown after cremations taking place later in the day. In 2026/27 we will adjust the service provision of the Crematorium. 
Roads & Transport 
Electric Charging Points 
This continues to be a priority initiative with a collaborative approach to the phased delivery of public and fleet charging infrastructure in
partnership with the City Region. We have finalised with City Region the strategy to engage with external suppliers to support and increase our
Electric Vehicle Charging Point infrastructure for both on and off-street parking. This was presented to Elected Members for consideration; it
includes the Implementation Strategy and Expansion Plan and detail of the proposed procurement model to implement a phased delivery of
public and fleet charging infrastructure. In 2025/26 we worked with City region and the appointed consultant to prepare the tender to bring in an
external company to supply and maintain the ECP’s. High level locations for spread of public chargers developed with City Region. All site
details provided to consultants with tender issued. In 2026/27, this will be progressed with Glasgow City Region acting as project lead, including
issuing the tender, with implementation proposed from 2026. Fleet charging points will be developed in conjunction with Depot Project 
Page 39

Page 40

Gruggies Burn  
The service has completed the detailed design with a contract in place to construct the new flood alleviation scheme. Total construction costs
are £48m with 80% secured funding from Scottish Government completed by 31st March 2026 deadline. In 2026/27 we will progress the
preparatory work with on site works expected in Autumn 2026. 
Surface Water Management Plan (SWMP)
The Clyde and Loch Lomond Flood Risk Management Plan highlights action which need to be undertaken by local Councils to address flooding
in the area. These actions are split into 6 year cycles to make outcomes easier to achieve and spread costs. Following the improvement study
for Dumbarton and Vale of Leven to modal the surface water, pluvial and sewer flooding to ensure suggested actions identified in the SWMP for
Dumbarton and the Vale were appropriate and provide high level estimates and designs for the implementation of any actions. This has
highlighted what actions can be undertaken in the area to address flooding and support the development of the SWMP for Clydebank. Feasibility
and cost benefit analysis for flood management improvement study for Dumbarton and Vale of Leven has been undertaken. In 2025/26
additional work will progress in Dumbarton and Vale of Leven. The recommendations in the draft SWMP have been given consideration with
high level plans developed and assessment of options complete. There have been delays in completion due to additional consultations required
with Network Rail and Scottish Water. This action will carry forward to 2026/27, and we will present a report and recommendations to IRED
committee in 2026.   
Implement 20 Miles Speed Limit 
The Council is committed to improving road safety in and around residential areas. In 2025/26 the service developed a wider 20mph policy for
residential streets for West Dunbartonshire for consideration and approval. New traffic regulation orders have been promoted and road markings
upgraded to support implementation in initial phase areas. Service will work to secure additional funding for 2026/27 to expand on current 20mph
streets. In 2026/27 we will progress the implementation of the agreed three year strategy. 
Exxon – City Deal Project
The Glasgow City region deal is an agreement between the UK Government, the Scottish Government and eight Local Authorities across
Glasgow and the Clyde Valley to invest in communities across Scotland. A major industrial and commercial development at the former
ExxonMobil terminal in Bowling West Dunbartonshire is underway with detailed planning approval received in January 2024. In 2026/27 we will
continue to progress with the construction phase of the Exxon Project in line with the current programme. A specific Exxon Project Board meets
to discuss this project providing governance and monitoring. 
Page 40

Page 41

Working 4U and Fleet Management
Working 4U
Local Growth Fund
The Local Growth Fund officially launched in January 2026 with several critical components still being finalised. Further details on delivery,
including specific investment themes and intervention frameworks, are expected to be published later in Q1 2026/27. Local Growth Fund
allocations have now been determined at a Regional Economic Partnership / City Region level, rather than individual Local Authority level with a
focus on capital investment and a decreased amount allocated to revenue funding with significant implications for Working 4U activity and
delivery for internal teams and commissioned services.
No One Left Behind, Child Poverty and Specialist Employment Support has been secured from Scottish Government with support focused on
target groups which include families at risk of child poverty, people with disabilities and long‑term health conditions, ethnic minority communities,
those who are economically inactive, and vulnerable young people. In 2026/27, we will ensure full compliance with funding requirements by
working in partnership, commissioning specialist services, reviewing and further developing access to welfare rights and debt management
support, and continuing to provide employability services.
Local Employability Developments / Fair work 
The No One Left Behind Strategic Plan for 2024-2027 focuses on improving employability services in Scotland, aiming to support individuals
facing barriers to employment through tailored and integrated approaches. West Dunbartonshire Council acts as lead partner to manage the
funds and work with private and third-sector service providers to identify local needs and make informed decisions about how best to support
employability. 
The Strategic Employability Group is a partnership to ensure that we co-ordinate employability service provision in an effective way. The Local
Growth Funding available for use to support employability and learning is still to be agreed with the Glasgow City Region and UK Government. In
2026/27 the Strategic Employability Group will collaboratively create a new Annual Investment Plan to identify priorities and co-ordinate the use
of resources to achieve the outcomes expected by No One Left Behind and Local Growth funds.
Employment: Green jobs 
We will work closely with employers to identify in‑demand skills and qualifications. Through our Employer Support offer, and by using our
Employer Recruitment Incentive where appropriate, we will also help employers advance their carbon‑reduction goals. We will map relevant
courses and apprenticeship pathways and, where needed, commission specialist training providers to deliver the required skills training. This
approach will help jobseekers gain industry‑standard qualifications and improve their employability and career progression within the expanding
carbon and green energy sectors. 
Page 41

Page 42

Supporting Vulnerable People
People are considered vulnerable when they are unable to maintain the standard of living that most others take for granted. Addressing
vulnerability requires more than focusing on specific groups; it demands an understanding of the everyday circumstances, life transitions, and
barriers that families and individuals face. To date, we have established a local employability partnership to ensure that we coordinate
employability service provision in an effective way. In addition to No One Left Behind, Parental Employability Support and Modern
Apprenticeship programme funds we will also manage the delivery of UK Local Growth fund priorities. We will integrate strategic management of
the funds into the Strategic Employability Group approach to maximise the benefits for West Dunbartonshire residents
The Family Prosperity Network works collaboratively to address the drivers of poverty and compiles and publishes the local child poverty report
to demonstrate our actions to address poverty and disadvantage.  
The Community Learning and Development Strategic partnership manages, delivers and monitors the three-year CLD plan and continues to
provide access to community-based learning opportunities. 
Working4U Team Reduction and Service Realignment
The savings options agreed to deliver the 2026/27 budget have resulted in a reduction in the Working 4U Service. The Working 4U Service will
progress a review of the service to reduce the number of employees funded by the Council. Grant conditions stipulate the need for: strategic and
operational delivery plans; partnership management and working with the third sector through the provision of grants and contracts. This
includes the development of assurance/risk management frameworks; service quality assurance; and extensive progress and finance monitoring
and reporting (grant lifecycle management). Without council funded posts to deliver these elements the external funds may be at risk. Reduction
in the Council funded workforce will impact services and activities delivered directly by Working 4U and commissioned partners to support
residents. In 2026/27 we will reduce the Service by 6 full-time equivalent council funded posts. 
Fleet Management 
Transition to Electric Fleet
The service is developing a transition to electric fleet strategy in response to the National agenda for decarbonising transport. We require to
increase the percentage of either hybrid or EV vehicles year on year until the final date for decarbonisation in 2035, failure to meet this deadline
will result in fines. The strategy will set out a programme of implementation of fleet procurement and disposal, charging infrastructure and
consider financial implications for each future financial year. In 2025/26 we increased the percentage of hybrid and EV vehicles to 13.1% a move
from 4.5% and set up a fleet Board.  The strategy has now been refined. In 2026/27 we will work with services to embed the strategy. 
Operational Management of Fleet 
To further enhance the operational management of Fleet to deliver efficiencies and cost-effective solutions over 2025/26 we will develop
customised service agreements with departments using fleet vehicles. This will provide them with the information they require to make effective
Page 42

Page 43

decisions about their service fleet needs. This will also incorporate practical support and identification of potential effective/efficient alternatives
for their fleet to ensure they have the right size of fleet for their service. This action will progress further in 2026/27 
Purchase of Vehicles to Replace Hire Cars 
The savings options agreed to deliver the 2026/27 budget include a reduction in ongoing costs of the use of hire vehicles The Council has for the
past five years hired a number of vehicles for use in the delivery of essential work in Roads, Grounds and other service throughout the council.
We plan to reduce the Council outgoings by purchasing the required vehicles, bringing the annual cost for the vehicles down. In 2026/27 we will
progress the purchase of vehicles to replace the hire fleet. 
Action Plan 
The challenges identified in Section 2 and the key factors identified in Section 3 have informed Roads & Neighbourhood priorities for 2026/27.
Appendix 1 sets out the action plan to address them. It also includes: 
 performance indicators and targets that will enable progress to be monitored and reported to stakeholders.
 strategic workforce actions 
 strategic and/or service risks 
In relation to the latter, strategic risks represent the potential for the Council to take advantage of opportunities or fail to meet stated strategic
objectives and those that require strategic leadership; while service risks relate to service delivery and represent the potential for impact on
individual services, or the experience of those who work within the services, i.e. employees, partners, contractors and volunteers or service
users and clients in receipt of the services provided. In identifying the relevant risks for 2026/27 and actions to mitigate them, the aim is to
improve or maintain the current position (i.e. the current risk score) set out in the appendix.
Continuous Improvement 
Continuous improvement is central to all that we do. The actions set out in this section as well as those at an operational level not included in
this Delivery Plan, demonstrate our commitment to continuous improvement and take account of the wider Best Value focus on vision and
leadership; governance and accountability; effective use of resources; partnerships and collaborative working; working with communities;
sustainability; and fairness and equality. 
Page 43

Page 44

4. Resources 
Finance 
Roads & Neighbourhood has a net revenue budget of £19.660m and a capital budget of £25.557m in 2026/27. A breakdown by service area is
set out below. We will make the best use of the resources available to deliver on key priority areas and secure external/match funding where this
is possible. 
Service Area
Gross
Expenditure
2026/27 (£m)
Gross Income
2026/27 (£m)
Net
Expenditure
2026/27
(£m)
Capital Budget
2026/27 (£m)
Transport, Fleet & Maintenance Services 5.013 -5.013 0.00 1.440
Roads Services 6.792 -4.083 2.709 20.323
Outdoor Services 0.290 -0.020 0.270 0.000
Burial Grounds 0.622 -0.796 -0.174 0.000
Crematorium 0.568 -1.525 -0.957 2.573
Waste Services 12.948 -1.889 11.059 0.500
Depots 0.562 -0.562 0.000 0.325
Ground Maintenance & Street Cleaning Trading A/c 7.194 -2.147 5.047 0.000
UK Shared Prosperity Fund (UKSPF) 1.045 -1.045 0.000 0.396
Working4U 4.294 -2.588 1.706 0.000
Total 39.328 -19.668 19.660 25.557 
Employees 
Employee Numbers 
The headcount and full time equivalent staff in each service area (as of 31st March 2026) are as follows:
Page 44

Page 45

Absence in 2025/26 
The quarterly absence statistics for Roads & Neighbourhood are shown below together with the Council average for the same periods for
comparison. The figures have been lower than the Council average in 2025/26: 
Absence in 2025/26 Quarter 1 Quarter 2 Quarter 3 Quarter 4 Annual FTE days lost
per FTE employee
Roads & Neighbourhood  4.76% 5.14% 5% 5.59% 12.06
COUNCIL WIDE TOTAL 6.17% 5.39% 7.2% 7.65% 14.38
Service Area Headcount FTE
Waste  92 89.4
Greenspace 139 129.7
Roads & Transportation  42 41.5
Working4U & Fleet (new for 2025) 131 123.5
TOTAL 405 385.1
Page 45

Page 46

Appendix 1: Action Plan 
1. Our communities 
Objective 1. Our neighbourhoods are safe, resilient and inclusive
Performance Indicator Target 26-27 Owner
Percentage of emergency road related defects repaired within 4 hours of being reported 95% Liam Greene
Percentage of non-serious road related defects repaired within 7 working days of being reported 85% Liam Greene
Percentage of routine road related defects repaired within 28 working days of being reported 85% Liam Greene
RL2: Percentage of all traffic light repairs completed within 48 hours 98% Liam Greene
RL3: Percentage of all street light repairs completed within 7 days 95% Liam Greene 
Action Due Date Owner
Progress strategy to implement 20 miles speed limit in residential areas 31-Mar-2027 Liam Greene 
Objective 2. Our resident’s health and wellbeing remains a priority
Page 46

Page 47

Action Due Date Owner
Complete the upgrade of 4 existing play parks  31-Mar-2027 Ian Bain
Progress plan to increase the number of 4G pitches - Argyle Park and Mount Blow.   31-Mar-2027 Ian Bain
Progress plan to develop two new destination play parks 31-Mar-2027 Ian Bain 
2. Our Environment 
Objective 4. Our local environment is protected, enhanced and valued 
Performance Indicator Target 26-27 Owner
Percentage of missed bins collected within 3 working days of being reported 95% Ian Bain
Percentage of total household waste that is recycled 60% Ian Bain
Tonnage of biodegradable municipal waste landfilled 6000 Ian Bain 
Action Due Date Owner
New Bio Diversity Action Plan will be presented to Committee 31-Mar-2027 Ian Bain
Remove trees affected by Ash Die Back- phase two of plan     31-Mar-2027 Ian Bain 
Page 47

Page 48

Objective 5. Our resources are used in an environmentally sustainable way 
Action Due Date Owner
Progress phased delivery of public electric charging points  31-Mar-2027 Liam Greene
Work with Depot Project to prepare the plan for expansion of fleet Charging points 31-Mar-2027 Stephen Brooks
Embed the Strategy for Transition to Electric Fleet. 31-Mar-2027 Stephen Brooks 
Objective 6. Our neighbourhoods are sustainable and attractive 
Performance Indicator Target 26-27 Owner
Percentage of Class A roads that should be considered for maintenance treatment  24% Liam Greene
Percentage of Class B roads that should be considered for maintenance treatment  24.5% Liam Greene
Percentage of Class C roads that should be considered for maintenance treatment  30% Liam Greene
Percentage of unclassified roads that should be considered for maintenance treatment 37% Liam Greene 
Page 48

Page 49

Action Due Date Owner
Progress preparatory work for Gruggies Burn Flood Management with contractor 31-Mar-2027 Liam Greene
We will make a recommendation on SWMP following approval we will progress next steps 31-Mar-2027 Liam Greene
Revise service provision of litter collection and street cleaning of trunk road. 31-Mar-2027 Ian Bain 
Risk Description Current
Assessment
Target
Assessment Owner
Impact of major adverse
weather incidents on
services
A significant period of adverse weather may result on
failure to deliver key operational functions of R&N
services 
Ian Bain
Failure to maintain road
network during adverse
weather
A significant period of adverse weather may result in
failure to deliver key operational functions of R&T
services 
Liam Greene
Failure to manage and
maintain the road
network effectively
Failure to manage and maintain the road network
effectively will have an adverse impact on user safety,
traffic movement, air quality, economic growth and
reduce access to facilities and amenities. The Council’s
reputation as a place to live and work with access to
employment, education, leisure and health opportunities
would be adversely affected. 
Liam Greene
Page 49

Page 50

Risk Description Current
Assessment
Target
Assessment Owner
Challenges in delivering
effective services in
relation to Roads &
Neighbourhoods
The risk that the Council fails to deliver on the three
services within Roads & Neighbourhood: Roads &
Transportation, Fleet & Waste and Greenspace. These
areas provide services across a range of areas including
managing and maintain roads, footpaths and associated
infrastructure, managing flood risk, grounds
maintenance, street cleaning, burial and cremation,
outdoor facilities, waste and recycling and vehicle fleet
management. Failing to ensure these services are not
fully fit for purpose could result in adverse consequences
in relation to delivering efficient and effective services.    
Gail Macfarlane 
3. Our Economy 
Objective 7. Our area has the infrastructure for sustainable and inclusive growth where businesses can flourish 
Objective 8. We will support our residents to access employment and training opportunities 
Action Due Date Owner
Support the progress of Exxon City Deal Project – (next phase) 31-Mar-2027 Liam Greene
Page 50

Page 51

Performance Indicator Target 26-27 Owner
Value (£) of debt managed £1,350,000 Stephen Brooks
Number of local people entering employment through Working 4U 300 Stephen Brooks
Number of local people entering education or training 750 Stephen Brooks
Number of local people gaining a full qualification 500 Stephen Brooks 
Action Due Date Owner
Manage, deliver and monitor the Community Learning and Development (CLD) partnership and associated
plan.
31-Mar-2027 Stephen Brooks
We will meet all funding requirements by working in partnership, commissioning specialist services 31-Mar-2027 Stephen Brooks 
Objective 9. We will work with partners to support economic development to deliver increased prosperity for our area 
Performance Indicator Target 26-27 Owner
Total Value (£) of Income Generated £6,000,000 Stephen Brooks
Number of local people receiving support through Working 4U 4,500 Stephen Brooks 
Action Due Date Owner
Develop a new employability partnership action plan 31-Mar-2027 Stephen Brooks
Explore the potential for securing training and opportunities in the carbon/green energy sectors 31-Mar-2027 Stephen Brooks
Page 51

Page 52

Action Due Date Owner
Compile and publish the local child poverty report to demonstrate our actions to address poverty and
disadvantage
31-Mar-2027 Stephen Brooks 
Risk Description Current
Assessment
Target
Assessment Owner
Failure to respond to
child poverty
legislation 
Failure to respond to child poverty legislation will have a
significant impact on the Council’s reputation, more importantly
an opportunity to raise issues and respond more effectively to
child poverty issues will be lost  
Stephen Brooks
The cost-of-living crisis
will lead to a
substantial demand for
access to welfare/debt
support services.
We will monitor the changing levels of demand and target our
resources to individuals and areas that are most in need. We
will seek to work with partners to ensure we receive appropriate
referrals who can benefit from our support.    
Stephen Brooks 
Objective 4. Our Council 
Objective 10. Our workforce is resilient and skilled where digital technology supports service delivery for our residents 
Page 52

Page 53

Action Due Date Owner
Workforce Planning: Develop and implement wellbeing, employee engagement, equality and learning and
development plans to enable capabilities, improve resilience and promotion of a diverse workforce
31-Mar-2027 All Managers
Workforce Planning: Develop and implement employee life cycle plans in line with the People First Strategy
to attract and retain the workforce.
31-Mar-2027 All Managers
Workforce Planning: Implement service review process including role design, use of new technology and new
ways of working to add resilience, address gaps, and establish opportunities for efficiencies
31-Mar-2027 All Managers
Workforce Planning: Develop and implement learning and development opportunities to improve capabilities
and resilience within the workforce.
31-Mar-2027 All Managers 
Objective 11. Our Council is adaptable and focused on delivering best value for our residents 
Action Due Date Owner
Reduce Apprentices within Roads and Greenspace Service 31-Mar-2027 Ian Bain
Revise service provision of Crematorium 31-Mar-2027 Ian Bain
Progress W4U Team Reduction and Service Realignment 31-Mar-2027 Stephen Brooks
Progress and Manage Service Level Agreements for Fleet Management.   31-Mar-2027 Stephen Brooks
Progress Purchase of Required Vehicles to replace agreed Hire Vehicles 31-Mar-2027 Stephen Brooks 
Page 53

Page 54

Risk Description Current
Assessment
Target
Assessment Owner
Challenge to delivery of
burial and cremation
services
A number of factors may impact on ability to deliver
these services. For example, a pandemic would
create significant immediate demand on services. 
Ian Bain
Inability to deliver priority
services as a result of
fuel shortages
A fuel shortage would significantly impacting on our
ability to provide priority service across West
Dunbartonshire. 
Gail Macfarlane 
Page 54

Page 55

Official
WEST DUNBARTONSHIRE COUNCIL 
Report by Chief Officer - Regulatory & Regeneration 
Committee: Infrastructure, Regeneration & Economic Development
Committee 20 May 2026 
Subject: Regulatory & Regeneration Delivery Plan 2025/26 - Economic
Development Year-end Progress & 
Regulatory & Regeneration Delivery Plan 2026/27 - Economic
Development 
1 Purpose 
1.1 This report sets out the year-end progress of the 2025/26 Delivery Plan and
presents the new 2026/27 Delivery Plan, both in relation to Economic
Development. 
2 Recommendations 
2.1 It is recommended that Committee notes the progress achieved at year-end
and the new Delivery Plan for 2026/27. 
3 Background 
3.1 In line with the Strategic Planning & Performance Framework, each Chief
Officer develops an annual Delivery Plan which sets out actions to help deliver
the Strategic Plan and address the performance challenges and service
priorities identified in the planning process. The Plan also provides an
overview of services and resources, including employees and budgets, sets
out the performance indicators (PIs) for monitoring progress and considers the
relevant risks. 
4 Main Issues 
2025/26 Year-end Progress 
4.1 The 2025/26 Delivery Plan was presented to Infrastructure, Regeneration &
Economic Development Committee on 21 May 2025 and mid-year progress
reported on 12 November 2025. 
4.2 Full details of year-end progress are set out in Appendix 1. 
4.3 The progress of the Delivery Plan’s ten Economic Development actions is
summarised below: 
Progress No. (%) 
Completed 8 (80%) 
Overdue 2 (20%)
ITEM 8
Page 55

Page 56

Official
4.4 Overdue actions relate to the following and will be carried forward and
completed in 2026/27:
• Develop the Local Heat and Energy Efficiency Strategy Delivery Plan -
50% complete
• Explore commercial opportunities in our town centres and wider
regeneration sites - 75% complete 
4.5 Year-end data is available for one of the Plan’s four Economic Development
PIs and this exceeded target: Number of businesses given advice and
assistance to start up through Business Gateway. 
4.6 The full set of PIs will be reported through the Council’s annual performance
reporting process once all data becomes available. 
2026/27 Delivery Plan 
4.7 The 2026/27 Delivery Plan is set out at Appendix 2. 
4.8 Key priorities include:
• delivering sustainable, quality services within the context of significant
financial challenges
• delivering key regeneration sites across West Dunbartonshire
• promoting the next phase of Queens Quay Housing
• exploring commercial opportunities in our town centres and wider
regeneration sites 
• supporting town centre revitalisation
• finalising the Visitor Levy Scheme
• developing a new Economic Development Strategy
• developing a Climate Change Strategy and action plan
• completing the Local Heat and Energy Efficiency Delivery Plan
• reviewing the Scheme for Establishment of Community Councils
• developing Community Planning
• contributing to the Community Learning and Development Plan 
4.9 Implementation of the Plan will be monitored by the management team with
mid-year and year-end progress reported to Corporate Services Committee
and Infrastructure, Regeneration and Economic Development Committee
(economic development elements only) around November 2026 and May
2027 respectively. 
5 People Implications 
5.1 There are no direct people implications arising from this report. 
6 Financial & Procurement Implications 
6.1  There are no direct financial or procurement implications arising from this
report. 
Page 56

Page 57

Official
7 Risk Analysis 
7.1 Failure to deliver on the actions assigned to Economic Development may
have a direct impact on the delivery of the Council’s Strategic Plan. It is
essential that remedial action is taken to ensure strategic delivery plans
achieve the commitments detailed. 
8 Equalities Impact Assessment 
8.1 Screening and impact assessments will be carried out on specific activities as
required. 
9 Consultation 
9.1  The delivery plans were developed through consultation with officers from the
strategic service areas. 
10 Strategic Assessment 
10.1  The delivery plans set out actions to support the successful delivery of the
strategic priorities and objectives of the Council. 
Chief Officer: Alan Douglas
Service Area:  Regulatory & Regeneration
Date:   23 April 2026
_____________________________________________________________ 
Person to Contact:  Lynn Henderson    
lynn.henderson@west-dunbarton.gov.uk 
Appendices:  Appendix 1: Regulatory & Regeneration Delivery Plan
2025/26 - Economic Development Year-end Progress 
Appendix 2: Regulatory & Regeneration Delivery Plan
2026/27 - Economic Development 
Background Papers: Regulatory & Regeneration Delivery Plan 2025/26 -
Economic Development,  
Infrastructure, Regeneration & Economic Development
Committee, 21 May 2025 
Regulatory & Regeneration Delivery Plan 2025/26 -
Economic Development Mid-year Progress,
Infrastructure, Regeneration & Economic Development
Committee, 12 November 2025 
Strategic Planning & Performance Framework 2022/27 
Wards Affected: All
Page 57

Page 58

Official
Appendix 1: Regulatory & Regeneration Delivery Plan 2025/26 – Economic Development Year-end Progress 
Our Environment 
Our resources are used in an environmentally sustainable way 
Performance Indicator
2024/25 2025/26 Owner
Value Status Value Target Short
Trend
Long
Trend Note 
Tonnage of carbon dioxide
emissions from Council
operations and assets
18,235   18,188  
2025/26 data is available in November when all
utilities bills and waste figures are validated in
advance of preparing our annual mandatory
climate change report for submission to the
Scottish Government in November 2026. 
2024/25 data, reported in November 2025,
shows significant progress. The value of 18,235
tonnes represents 33.8% reduction on the
previous year, 44.7% reduction on the 2012/13
baseline and 5.7% ahead of projected target.
These are positive steps. However, the main
reduction is from the Council's scope 3 waste
emissions, which is a result of shifting a
significant amount of waste from landfill to
incineration through the Net Zero Cooperation
Agreement with Glasgow City Council. Both
scope 1 and 2 emissions increased slightly for
2024/25 period. To reach a 61% reduction by
2030/31 we need to reduce a further 16.3% in
just over five years and investment in required to
reduce gas, electricity and diesel consumption. 
Amanda
Kean
ITEM 8 - APPENDIX 1
Page 58

Page 59

Official
Action Status Progress Due Date Note Owner
Co-ordinate, monitor and report
the progress of the Council’s
Climate Change Action Plan for
2025/26  
31-Mar-
2026
Completed as planned. The Climate Change Action
Group meets regularly to progress and monitor this work
stream. To encourage wider engagement, service
specific meetings have been arranged and are now
underway.
Amanda
Kean
Develop the Local Heat and
Energy Efficiency Strategy
Delivery Plan  
31-Mar-
2026
Overdue. Recruitment for the Local Heat and Energy
Efficiency post has taken longer than anticipated. Due to
other commitments, there is not the capacity within the
climate team to finalise the Local Heat and Energy
Efficiency Delivery Plan. Once the post is filled, the
Delivery Plan will be finalised. This action will be carried
forward in 2026/27 and completed.
Amanda
Kean 
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Inability to
reduce carbon
footprint in line
with targets
The risk that the Council will be
unable to achieve net zero
emissions by 2045, both in
relation to mitigating carbon
emissions and adapting to the
impacts of climate change. Net
zero refers to achieving an
overall balance between
emissions produced and
emissions taken out of the
atmosphere. This target has
been developed in a way that
mirrors the emission reduction
trajectory set by the Scottish  
01-Apr-
2026
The risk assessment remains
unchanged from mid-year. 
The Council's most recent
emissions, reported in November
2025 for 2024/25, showed
significant progress. (Details are
set out under the PI ‘Tonnage of
carbon dioxide emissions from
Council operations and assets’
above.) 
The long-term Climate Change
Coordinator vacancy has been
Alan
Douglas;
Amanda
Kean; Gail
Macfarlane
Page 59

Page 60

Official
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Government in light of the
Climate Emergency. 
filled internally; this currently
leaves another vacancy within the
energy team that will be filled as
soon as possible. Participation
from service areas has increased
at Climate Change Action Plan
meetings and emission
reductions actions and projects
are forthcoming. The Council also
has the opportunity to utilise
ClimateView and track trajectory
to Net Zero, allowing actions and
projects to be prioritised and a
more collective, strategic
approach to be implemented. 
The Strategic Risk will be
reviewed at the next Climate
Change Action Plan meeting for
relevance and an amended risk /
set of risks will be reported to
future meetings. 
Page 60

Page 61

Official
Our neighbourhoods are sustainable and attractive 
Action Status Progress Due Date Note Owner
Promote the next phases of
Queens Quay Housing  
31-Mar-
2026
Completed as planned. Officers continue to progress this
site and support delivery. A planning application for
residential development on part of the site has been
submitted and further residential applications are
expected Q2 2026/2027.
Michael
Mulgrew;
Magda
Swider 
Our Economy 
Our area has the infrastructure for sustainable and inclusive growth where businesses can flourish 
Performance Indicator
2024/25 2025/26
Owner Value Status Value Target Short
Trend
Long
Trend Note
Number of businesses given
advice and assistance to
start up through Business
Gateway
190  188 180  
Target exceeded. During 2025/26, 188
businesses were provided with advice to
start-up through Business Gateway,
exceeding the target of 180.
Gillian
Scholes
Number of business
gateway start-ups per
10,000 population
21.32   19.78  
2025/26 data for this Local Government
Benchmarking Framework (LGBF) indicator
will be available at a later date following
publication by the Improvement Service. 
Based on the LGBF comparative data for the
previous year (2024/25) published by the
Improvement Service in February 2026,
performance was better than the Scottish
average of 12.3, and better than the family
Gillian
Scholes
Page 61

Page 62

Official
Performance Indicator
2024/25 2025/26
Owner Value Status Value Target Short
Trend
Long
Trend Note
group average of 12.2, with a ranking of 2 of
32 local authorities, down 1 place from the
previous year.
Proportion of properties
receiving superfast
broadband
99.8%   99%  
2025/26 data for this LGBF indicator will be
available at a later date following publication
by the Improvement Service. 
Based on the LGBF comparative data for the
previous year (2024/25) published by the
Improvement Service in February 2026,
performance was better than the Scottish
average of 97.1%, and better than the family
group average of 99.1%, with a ranking of 1
of 32 local authorities, consistent with the
previous year.
Gillian
Scholes 
Action Status Progress Due Date Note Owner
Deliver key regeneration sites
across West Dunbartonshire  
31-Mar-
2026
Completed as planned. 
• Work to support the regeneration of the Exxon and
Scottish Marine Technology Park (SMTP) is progressing
well. SMTP was approved as an Investment Zone project
in November 2025 and Malin Group are currently
preparing an Outline Business Case. Investment Zone
funding will contribute £20m towards development of the
SMTP over the next 10 years. 
• An application for Regeneration Capital Grant funding
progressed to Stage 2 and results are expected in
Spring. 
Magda
Swider
Page 62

Page 63

Official
Action Status Progress Due Date Note Owner
• Construction works on the Exxon site are progressing
well, with a significant milestone achieved in January
2026 when the western underbridge was completed by
Network Rail. Work is also underway on marketing the
Exxon site and further updates will be provided to the
project board.
Explore commercial
opportunities in our town
centres and wider regeneration
sites  
31-Mar-
2026
Progress has been achieved in a number of areas over
the year including discussions with prospective
developers with regards to the Queens Quay
development and appointment of consultants to develop
a Tourism Strategy for the West Dunbartonshire. 
However, one milestone relating to the Council's
consideration of the Planning Permission in Principle
(PPIP) application for the Masterplan Dumbarton Artizan
redevelopment has been delayed due to prolonged
engagement with the Scottish Environmental Protection
Agency (SEPA) which is a statutory consultee. SEPA
objected to the application on the grounds that it does
not comply with Policy 22 of the National Planning
Framework 4 and provided comments on our Flood Risk
Assessment. The Flood Risk Assessment was
subsequently amended to address their feedback and
re-submitted to Planning and we are currently awaiting
SEPA’s response. SEPA’s objection will not be lifted,
however, once their response is received, the PPIP will
be considered by the Council. It is expected to be Spring
or early Summer 2026. 
Magda
Swider
Page 63

Page 64

Official
Action Status Progress Due Date Note Owner
Deliver business support
interventions through the UK
Shared Prosperity Fund
2025/26  
31-Mar-
2026
Completed as planned. Business grants available
through the UK Shared Prosperity Fund have been
promoted through social media, council website and
directly to eligible businesses. The UK Government has
extended the deadline for grant spend until the end of
September 2026. We will continue to appraise and
process applications to maximise funding through this
period.
Gillian
Scholes
Support town centre
revitalisation  
31-Mar-
2026
Completed as planned. In Alexandria, we have been
working with the Business Improvement District to
develop designs for Mitchell Way/main Street
improvements. We have also appointed a contractor for
the Alexander Street improvements, another of the
Alexandria Masterplan projects. In Clydebank, a big
milestone was achieved when the Pride in Place Plan
was submitted to the UK Government. Once approved it
will unlock up to £20m funding over the next 10 years. In
Dumbarton, delivery of the UK Government funded
regeneration works in the town centre is progressing
well, with Phase 1 of Artizan redevelopment now on site. 
Magda
Swider 
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Failure to
deliver Queens
Quay
Masterplan
Following completion of Council
investment there is a risk the
housing plot sales do not
materialise in the next 3-7
years, with implications for the
return on investment and the  
11-Mar-
2026
Risk remains unchanged.
Delivery of site remains
embedded in service
workstreams.
Michael
Mulgrew;
Magda
Swider
Page 64

Page 65

Official
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
business case for the District
Heating Network. 
Inability to meet
demands of
Council to
progress
regeneration
projects within
desired
timescales
The number and complexity of
regeneration projects is putting
considerable strain on the
resources available which can
be exacerbated by delays out
with the control of the service
and when pinch points on
different projects occur at
roughly the same time. 
11-Mar-
2026
Risk remains unchanged.
Individual projects continue to
progress and are regularly
reviewed, reducing the likelihood
of undesirable outcomes.
Embedded in workstreams to
ensure sufficient resource to
support delivery of projects within
required timescales.
Michael
Mulgrew;
Magda
Swider 
Our Council 
Our residents are engaged and empowered 
Action Status Progress Due Date Note Owner
Continue the development of
Community Planning  
31-Mar-
2026
Completed as planned. The development of Community
Planning has progressed well during 2025/26. A review
of Delivery Improvement Groups was completed and a
recommendations paper was submitted to the
Management Board in November setting out
recommendations on partnership reporting. A pilot in
Alexandria looking at access to services was established
and the initial engagement stage was completed in
2025/26. Next steps will be identified, and this work will
continue in 2026/27.
Colin Smith
Page 65

Page 66

Official
Action Status Progress Due Date Note Owner
Continue to contribute to the
Community Learning and
Development Plan 2024/27  
31-Mar-
2026
Completed as planned. The Communities Team
continues to deliver community development support to
groups across West Dunbartonshire to maximise their
impact. This can be through support to secure external
funding, promotion or by developing skills and improving
governance arrangements. The team is represented on
the Community Development Alliance and plays a key
role in supporting communities through the development
of Locality Plans. Of particular note, we supported the
completion of two community-led Local Place Plans in
Old Kilpatrick and Central Alexandria, both of which have
been approved and adopted at Planning Committee.
Colin Smith
Conclude the Cash First Project
including evaluation  
31-Mar-
2026
Completed as planned. The Cash First Project is a
Scottish Government initiative to end the need for food
banks in Scotland through providing funds or vouchers to
people in financial crisis. Delivered jointly by the
Communities Team and Working 4U, it has been very
successful, with the available funding reaching those
most in need through a network of trusted partner
referrals. The Communities Team has developed and
carried out the evaluation engagement to support the
Cash-First programme. This will be submitted to the
Scottish Government as the end of the project draws to a
successful close.
Colin Smith 
Page 66

Page 67

Official
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Engaging
positively with
Residents,
Communities &
Partnerships
The risk that the Council fails to
adequately engage, establish
and maintain positive
relationships with local residents
and communities in addition to
partnership bodies.   
11-Mar-
2026
A partnership approach to
Community engagement is being
undertaken led by the Community
Planning Partnership and
associated partnerships -
Community Learning and
Development and Community
Development Alliance in
particular. The Communities
Team and other partners deliver
community development work
which seeks to raise awareness
of community planning and
Community Empowerment in
communities. Locality plans,
community-led place planning
and work to support the
Clydebank Neighbourhood
Board’s community engagement
means this risk is unchanged.
Colin Smith 
Page 67

Page 68

Official
Action Status 
Overdue 
Completed 
PI Status 
Target met or exceeded 
Risk Status 
Warning 
OK 
Long Term Trends 
Getting worse 
Short Term Trends 
Getting worse 
Page 68

Page 69

Official
Appendix 2: Regulatory & Regeneration Delivery Plan 2026/27 - Economic Development 
1. Introduction 
Regulatory & Regeneration comprises a wide range of services covering legal, trading standards, licensing, records management,
planning, building standards, environmental health, democratic and registration services, economic development, community
planning and procurement. It is one of seven strategic areas responsible for delivering the Council’s Strategic Plan. Key actions to
help achieve that are set out in this Delivery Plan, together with actions to address any performance issues and service priorities
identified in the planning process. 
The progress of this Plan will be monitored and managed by the management team and reported to Corporate Services Committee
and Infrastructure, Regeneration & Economic Development Committee (economic development elements only) twice yearly, at mid-
year and year-end. 
2. Performance Review 
The management team completed a detailed review of 2025/26 performance, focusing on the following:
 2025/26 Delivery Plan year-end progress;
 Local Government Benchmarking Framework comparative performance;
 Citizens’ Panel feedback; and
 Complaints. 
This review highlighted our key achievements and challenges in 2025/26. These are summarised below. 
Key Achievements in 2025/26 
Economic Development and Regeneration
 Completed formal visitor levy consultation and obtained Council approval to implement a 5% visitor levy from 1 July 2027.
 With support from the Council, the Malin Group and Strathclyde University succeeded in securing £20m funding for the Scottish
Marine Technology Park from the City Region’s Advanced Manufacturing and Precision Engineering Investment Zone. 
ITEM 8 - APPENDIX 2
Page 69

Page 70

Official
 Contributed to numerous strands of the UK Shared Prosperity Fund delivery, including providing support to 190 new business
start-ups and delivering a range of business growth interventions and successfully delivering a series of community soup events
to increase local democracy. 
 Started construction works on site for Phase 1 of the UK Government funded redevelopment of the Artizan shopping centre in
Dumbarton.
 Supported the Clydebank Neighbourhood Board in developing a Regeneration Plan (including a 4-year Investment Plan) which
outlines the main priorities for Clydebank to be delivered over the next 10 years with (up to) £20m of Pride in Place funding.
 Worked with Alexandria BID and wider Alexandria community to develop proposals for the Main Street improvements,
progressing delivery of projects originating from the Alexandria Masterplan. 
 Worked with the Loch Lomond and Trossachs National Park to develop Balloch Pierhead Action Plan. 
 Submitted 5 applications to the Scottish Government's Regeneration Capital Grant Fund with the application for Scottish Marine
Technology Park progressing to Stage 2.
 Reported significant progress in reducing carbon emissions from Council operations and assets based on the latest 2024/25
figure of 18,235 tonnes. This represents a 33.8% reduction on the previous year, a 44.7% reduction on 2012/13 baseline and
5.7% ahead of projected target.
 Delivered 5 Community Soup Events in Old Kilpatrick, Dalmuir and Dumbarton, with two additional themed Soups working with
West Dunbartonshire secondary schools and groups engaged in biodiversity activities. Some were organised by the
Communities Team with community input while others were led by communities with support from the Team. Over £6,000 in
small grants were awarded to local community groups supporting community activity.
 Delivered 250 appointments and co-ordinated 670.30 hours of volunteer activity (2025 calendar year) through the Community
Transport’s Health Appointments Transport Service. £30,000 in Strathclyde Partnership for Transport funding was brought into
West Dunbartonshire.
 Supported Old Kilpatrick Community Council and Alexandria Community Council to complete Local Place Plans for their areas,
which have subsequently been adopted at the Council’s Planning Committee. 
Page 70

Page 71

Official
Key Challenges in 2025/26 
Economic Development and Regeneration
 Delivering private sector homes at Queens Quay continued to be a challenge in 2025/26 but we meet with our commercial
partner regularly and there were some positive discussions with potential developers.
 Businesses continued to face many economic challenges in 2025/26, including energy costs and employee recruitment and
retention. The on-going advice available through Business Gateway will continue to help them to recover and grow in the year
ahead.
 Significant proposed reductions in the UK Shared Prosperity Fund revenue budget for 2026/27 is likely to have an impact on the
grant funding available to support local businesses with growth projects and job creation.
 Securing external funding to progress regeneration of our strategic sites and town centre assets is challenging. Regeneration
team continue to explore funding streams and provide support to private owners to help them progress their projects.
 Significant proportion of privately owned buildings in our town centres which suffer from lack of maintenance and investment
continues to be a challenge which hinders town centre revitalisation.
 Uncertainty regarding the regeneration funding in the Scottish Government’s budget and longer-term spending plans.
 Lack of funding to secure adequate long-term management and maintenance programme for new and existing regeneration
projects, and public areas in general.
 Resourcing the operation and further development of the District Heating Centre remains very challenging due to inability to
attract a lead officer within the Climate Change team.
 Despite carbon emissions for 2024/25 showing a significant reduction, it will be challenging to achieve future targets as outlined
in our Climate Change Strategy. Emissions were reduced in 2024/25 due to new waste arrangements with Glasgow City
Council while emissions from some other sources increased. To ensure Net Zero targets are met by 2045, consideration should
be given to additional resources to ensure continued progress.
 The Climate Change Team had vacancies throughout the year which impacted on the completion of some tasks, particularly the
Local Heat and Energy Efficiency Delivery Plan.
 The cost-of-living crisis and the increase in various renewable energy technologies within the Council’s new supply housing
have seen a significant uplift in the number of residents requiring Energy Efficiency support. This has proved challenging to
facilitate within our existing resources.  
Page 71

Page 72

Official
3. Strategic Assessment 
The Regulatory & Regeneration management team completed a detailed strategic assessment to determine the major influences
on service delivery and priorities in 2026/27 and beyond. This covered a review of local and national political priorities, new
legislation and technology, Council policies, and our continued recovery from the pandemic, cost of living crisis and the financial
challenges facing the Council. The key issues are outlined below. 
Key Factors 
Financial Challenges 
The entire public sector is continuing to face significant financial challenges due to a range of factors including inflationary cost
increases, pay awards not being fully funded by the Scottish Government and insufficient overall funding to support the delivery of
front line and back-office services. The Council is currently faced with an estimated cumulative funding gap in 2027/28 of £10.905m
rising to £44.028m by 2030/31. We will continue to monitor the overall financial position of the Council and updates on estimated
future budget gaps will be reported to Elected Members throughout 2026/27. 
These challenges require further action to balance our budget and protect services for residents. Within Regulatory &
Regeneration, this means that available funding will be reduced over time and we will need to reconfigure how we work, what we
do, where we work, and potentially reduce the number of people employed. In this context, we will aim to continue to provide a
sustainable, quality service to internal clients and the public. 
Budget Sensitivity Analysis 
In reviewing the service budget projections, consideration has been given to the sensitivity of these budgets, in particular for higher
risk/ higher value budgets which may have a significant impact on budgetary control and future budget projections. The analysis
has considered sensitivity around demand, costs and charges, and income levels. 
In Regulatory & Regeneration there were no budgets identified as being more susceptible to fluctuations. However, on a more
Council-wide basis, the Council’s cost of borrowing is susceptible to fluctuations in the bank interest rate due to the level of the
Council’s short-term borrowing.
Page 72

Page 73

Official
Key Strategic Regeneration Sites 
Delivery of a number of key regeneration projects, which span multiple years, will continue to be progressed in 2026/27. The main
focus will be the Bowling Strategic Opportunity on the former Exxon site and the Scottish Marine Technology Park on the former
Carless oil terminal site, led by the Malin group. 
For the Exxon site, the focus will be on delivering the infrastructure and developing the marketing strategy to realise the economic
benefits of the site. Funding opportunities to deliver the proposed Dunglass Castle Community Parkland will also be explored. For
the Carless site, the Council will continue to support the Malin group in the delivery of the first phase of the proposed Scottish
Marine Technology Park. 
Actions: Deliver key strategic regeneration sites across West Dunbartonshire 
Queens Quay 
Infrastructure works for this 80-acre residential waterfront development were completed in 2020/21. In the year ahead, the focus on
securing housing developments across the site in partnership with site owner Clydeside Regeneration Ltd. will continue. This is a
challenge, particularly in relation to flatted private homes which the market is finding commercially challenging. Discussions will
continue with a range of public and private sector parties. Missives are being concluded for one site with a further site expected in
quarter 1 2026/27. 
Action: Promote the next phases of Queens Quay Housing 
Key Commercial Opportunities 
Identifying commercial opportunities in conjunction with the private sector will continue to be a priority in 2026/27. Discussions with
developers who may wish to enter a partnership with the Council to achieve joint benefits from a commercial, housing and low
carbon perspective will be progressed. The Regeneration Capital Fund of £12.40m has been allocated across a number of projects.
The Fund’s key operating principles and allocations to specific projects agreed by Committee will be progressed. Opportunities
include: 
Page 73

Page 74

Official
 Exxon: As infrastructure works progress, the Council will consider how to promote and deliver the best uses for the site and,
working with the City Region and Scottish Enterprise, will encourage developer interest in the site to meet the growth targets set
out in the City Deal business case. 
 NHS Golden Jubilee: We will seek to deliver the extension of the District Heating network to the hospital and explore
opportunities presented by the expansion of the hospital for development and regeneration of Queen Quay and Clydebank,
generally.
 Scottish Marine Technology Park: We will continue to work with the Malin Group in their ambition to deliver the Scottish Marine
Technology Park at the former Carless site near Old Kilpatrick and assist them in attracting business and funding to the site. A
joint project board continues to provide support and direction as the Malin Group progress the development through the
planning and infrastructure implementation stages.
 Clydebank: We will support the Neighbourhood Board in undertaking a feasibility study to explore redevelopment and
investment opportunities for the southern part of the shopping centre,
 Artizan: We will explore opportunities and undertake a feasibility study to explore investment opportunities in future phases of
the Artizan redevelopment. 
Action: Explore commercial opportunities in our town centres and wider regeneration sites 
Visitor Levy Scheme 
West Dunbartonshire Council approved the decision to introduce a 5% visitor levy scheme at Council committee in November
2025. The start date for the levy will be 1 July 2027. The income raised must be used to develop, support, and sustain facilities and
services which are 
substantially used by visitors and is estimated to be approximately £1.7 million per annum. 
Action: Finalise the Visitor Levy Scheme for introduction in July 2027 
Page 74

Page 75

Official
Economic Development Strategy 2027-2032 
A new Economic Development Strategy will be developed which will provide an updated economic vision and strategic priorities for
West Dunbartonshire for a five-year period from 2027 to 2032. This new strategy will build on the foundations established in the
previous 2022-2027 Economic Development Strategy. 
Action: Develop a new Economic Development Strategy 2027- 2032 
Town Centre Revitalisation 
Assisting town centres to adjust to the current shopping trends and embrace new challenges will be our focus in 2026/27, with
support for high street businesses a key priority. We will continue to develop projects to make our town centres attractive places
and take advantage of the external funding, including the UK Government’s funding streams and Place-Based Investment
Programme funds provided by the Scottish Government. We will also work with and support community groups or businesses
which plan to invest in and establish themselves in our town centres, and whose plans align with our town centre regeneration
agenda. 
 Clydebank has been awarded £20 million funding from the UK Government as part of the Pride in Place Programme (former
Plan for 
Neighbourhood). This funding will support delivery of the projects which reflect the priorities of the local community. Many
projects align with the Clydebank Development Framework which provides a vision for how the town will be transformed, from
reducing retail dominance to a vibrant mixed use and inhabited town centre that meets the needs of the whole community. A
Clydebank Neighbourhood Board (former Town Board), chaired by Liz Connolly, oversees the Fund and the Pride in Place Plan
which has been submitted to the UK Government for review. The first tranche of capital funding is expected in April 2026.
Meanwhile, capacity funding has already been awarded to support engagement and initial project development costs. 
 In Dumbarton, the focus for the next year will be on completing the Levelling Up Fund programme of works, including the
refurbishment and reuse of Glencairn House as a library and museum, and the revitalisation of the Artizan Centre. We are also
exploring other ways to improve the High Street over the coming years and will continue supporting Planning with the Heritage
and Place Programme application which could fund works to some of the most prominent town centre historic properties. Over
the next year we expect to be working with the landowner Turnberry Homes in preparations for delivery of the waterfront
Page 75

Page 76

Official
pathway on their land, planned to start in 2027.We will also continue working in partnership with Historic Environment Scotland
and the Maritime Museum to make Dumbarton town centre and waterfront a more attractive place for visitors. 
 In Alexandria, the next phase of the 2021 Masterplan will be delivered, with an emphasis on Alexander Street improvements
which align with Green Heritage Corridors and Cycling and Walking Network masterplan priority projects. We will also continue
to work with Alexandria BID and the local community to develop detailed designs for Mitchell Way and Main Street
improvements, with works expected to start on site in early 2027. 
Action: Support town centre revitalisation 
Climate Change Strategy 2026-2031 and Action Plan 2026/27 
The Council has a Climate Change Strategy for 2021 to 2026 which was developed in response to the climate emergency and to
provide a route map towards meeting Scotland’s national net zero carbon target by 2045. A revised Strategy will be developed in
the year ahead, building on the accomplishments and progress set out in the current strategy and reinforcing the ambition to deliver
a just transition to net zero emissions. It will focus on reducing the Council’s carbon emissions and adapting to the impacts of
climate change over a five-year period from 2026 to 2031. An annual action plan will be developed to support delivery, with actions
devolved to relevant service areas to take forward. Progress against the 2026/27 action plan will be monitored and reported to
senior management and Council on a regular basis. 
Action: Develop the Climate Change Strategy 2026-2031 and associated Action Plan for 2026/27 
Local Heat and Energy Efficiency Delivery Plan 
The Local Heat and Energy Efficiency Strategy 2024-2029 sets out the long-term plan for heat decarbonisation and improved
energy efficiency of buildings throughout the Council area. It sets out the changes to each sector of buildings stock that are needed,
identifying strategic heat decarbonisation zones and prioritising delivery areas. Development of the existing Queens Quay District
Heat Network will continue and other opportunities for area-based heat decarbonisation and energy efficiency will be progressed. A
Delivery Plan will be completed in 2026/27 to support the implementation of the Strategy. 
Action: Complete the Local Heat and Energy Efficiency Delivery Plan for implementation 
Page 76

Page 77

Official
Scheme for the Establishment of Community Councils in West Dunbartonshire 
The Scheme for the establishment of Community Councils in West Dunbartonshire requires to be reviewed in 2026 (every four
years). The review will comprise a three-stage consultation process commencing with a review of the existing community council
boundaries in February 2026 and ending with a revised scheme in October 2026. The review will be led by the Manager of
Democratic and Registration Services and supported by the Communities Team who will assist with the consultation process and
engage with all community councils and the Community Council Forum. 
Action: Review the Scheme for Establishment of Community Councils 
Community Planning West Dunbartonshire 
The Community Empowerment (Scotland) Act 2015 sets out clear requirements for public bodies in promoting a greater level of
local decision-making and empowerment of citizens. Empowered communities can deliver a range of benefits that include improved
physical and mental health, increased confidence and social networks, reduced sense of isolation and can reduce demand on
public sector resources. 
Our approach to community empowerment focuses on Community Planning and the development of locality plans, specific projects
that promote local participation and empowerment and regular engagement with local people, particularly in our most
disadvantaged communities. Progress will be monitored by Community Planning West Dunbartonshire and reported through the
Empowered Delivery Improvement Group. 
Action: Continue the development of Community Planning 
Community Learning and Development 
The Community Learning and Development (Scotland) Regulations 2013 place a statutory requirement on local authorities to
publish a plan every three years. The plan should outline how the Council will co-ordinate and secure ‘adequate and efficient’
Community Learning and Development provision with other sector partners. We continue to deliver against our current Community
Learning & Development Plan 2024/27 to provide community-based learning opportunities throughout West Dunbartonshire. 
Page 77

Page 78

Official
For 2026/27, we will contribute to the delivery of the Community Learning and Development Plan through community planning and
community development work and further development of and participation in the Empowered Delivery Improvement Group
/Community Development Alliance. 
Action: Contribute to the Community Learning and Development Plan 2024-2027 
Continuous Improvement 
Continuous improvement is central to all that we do. The actions set out in this section, as well as those at an operational level not
included in this Delivery Plan, demonstrate our commitment to continuous improvement and take account of the wider Best Value
focus on vision and leadership; governance and accountability; effective use of resources; partnerships and collaborative working;
working with communities; sustainability; and fairness and equality. 
Action Plan 
The challenges identified in Section 2 and the key factors identified in Section 3 have informed Regulatory & Regeneration priorities
for 2026/27. Appendix 1 sets out the action plan to address them. It also includes:
 performance indicators that will enable progress to be monitored and reported to stakeholders;
 strategic workforce actions to address workforce issues identified in the planning process; and
 strategic and/or service risks. 
In relation to the latter, strategic risks represent the potential for the Council to take advantage of opportunities or fail to meet stated
strategic objectives and that require strategic leadership. Service risks relate to service delivery and represent the potential for
impact on individual services, or the experience of those who work within the services, i.e. employees, partners, contractors and
volunteers, or service users and clients in receipt of the services provided. In identifying the relevant risks for 2026/27 and actions
to mitigate them, we aim to improve or maintain the current position (i.e. the current risk score) set out in the appendix.
Page 78

Page 79

Official
4. Resources 
Finance 
Regulatory & Regeneration has a net revenue budget of £5.829m and a capital budget of £11.471m in 2026/27. A breakdown by
service area is set out below. We will make the best use of the resources available to deliver on key priority areas and secure
external/match funding where this is possible.      
Service Area Gross Expenditure
2026/27 (£m)
Gross Income
2026/27 (£m)
Net Expenditure
2026/27 (£m)
Capital Budget
2026/27 (£m) (Figures subject to ongoing
verification)
Democratic & Registration 1.832 0.115 1.717 0.000
Environmental Health 1.056 0.374 0.682 0.000
Licensing 0.272 0.465 -0.193 0.000
Legal Services & Trading Standards 1.016 0.088 0.928 0.000
Procurement 0.789 0.080 0.709 0.000
Building & Planning 1.461 0.743 0.718 0.000
Economic Development 1.887 0.619 1.268 11.471
Total 8.313 2.484 5.829 11.471
Page 79

Page 80

Official
Employees 
Employee Numbers
The headcount and full time equivalent (FTE) staff in each service area (as of 31st March 2026) are as follows: 
Absence 
The 2025/26 quarterly absence figures for Regulatory & Regeneration are shown below together with the Council average for the
same periods for comparison. Absence was lower than the Council average throughout 2025/26: 
Absence in 2025/26 Quarter 1 Quarter 2 Quarter 3 Quarter 4 Annual FTE* days lost
per FTE employee
Regulatory & Regeneration 3.08% 2.94% 1.71% 2.2% 6.35
Council Wide Total 6.17% 5.39% 7.2% 7.65% 14.38  
Regulatory and Regeneration Headcount FTE
Democratic and Registration Services 28 19.8
Economic Development 19 17.8
Legal Services 21 19.3
Planning, Building Standards and Environmental Health 35 33.6
Regulatory Management 2 2
Procurement 11 10.8
TOTAL 116 103.3
Page 80

Page 81

Official
Appendix 1: Action Plan 
Please Note: PI targets for 2026/27 are indicative until 2025/26 year-end values are available. 
1. Our communities 
Our residents are supported to increase life and learning skills 
Action Due Date Owner
Continue to contribute to the Community Learning and Development Plan 2024-2027 31-Mar-2027 Colin Smith 
2. Our Environment 
Our resources are used in an environmentally sustainable way
Performance Indicator 2026/27 Owner Target
Tonnage of carbon dioxide emissions from Council operations and assets 17,035 Amanda Kean 
Action Due Date Owner
Develop the Climate Change Strategy 2026-2031 and associated Action Plan for 2026/27 31-Mar-2027 Amanda Kean
Complete the Local Heat and Energy Efficiency Delivery Plan for implementation 31-Mar-2027 Amanda Kean 
Page 81

Page 82

Official
Risk Description Current
Assessment
Target
Assessment Owner
Inability to reduce
carbon footprint in line
with targets
The risk that the Council will be unable to achieve net
zero emissions by 2045, both in relation to mitigating
carbon emissions and adapting to the impacts of climate
change. Net zero refers to achieving an overall balance
between emissions produced and emissions taken out of
the atmosphere. This target has been developed in a
way that mirrors the emission reduction trajectory set by
the Scottish Government in light of the Climate
Emergency. 
Alan Douglas;
Amanda Kean;
Gail
Macfarlane 
Our neighbourhoods are sustainable and attractive 
Action Due Date Owner
Finalise the Visitor Levy Scheme for introduction in July 2027 31-Mar-2027 Gillian Scholes 
3. Our Economy 
Our area has the infrastructure for sustainable and inclusive growth where businesses can flourish 
Performance Indicator 2026/27 Owner Target
Number of businesses given advice and assistance to start up through Business Gateway 180 Gillian Scholes
Number of business gateway start-ups per 10,000 population 19.78 Gillian Scholes
Proportion of properties receiving superfast broadband 99% Gillian Scholes 
Page 82

Page 83

Official
Action Due Date Owner
Deliver key strategic regeneration sites across West Dunbartonshire 31-Mar-2027 Magda Swider
Promote the next phases of Queens Quay Housing 31-Mar-2027
Michael
Mulgrew;
Magda Swider
Explore commercial opportunities in our town centres and wider regeneration sites 31-Mar-2027 Magda Swider
Support town centre revitalisation 31-Mar-2027 Magda Swider
Develop a new Economic Development Strategy 2027-2032 31-Mar-2027 Gillian Scholes 
Risk Description Current
Assessment
Target
Assessment Owner
Failure to deliver
Queens Quay
Masterplan
Following completion of Council investment there is a
risk the housing plot sales do not materialise in the next
3-7 years, with implications for the return on investment
and the business case for the District Heating Network.   
Michael
Mulgrew;
Magda Swider
Inability to meet
demands of Council to
progress regeneration
projects within desired
timescales
The number and complexity of regeneration projects is
putting considerable strain on the resources available
which can be exacerbated by delays out with the control
of the service and when pinch points on different
projects occur at roughly the same time.   
Manager of
Legal and
Democratic
Services;
Michael
Mulgrew;
Magda Swider 
Page 83

Page 84

Official
4. Our Council 
Our residents are engaged and empowered 
Action Due Date Owner
Continue the development of Community Planning 31-Mar-2027 Colin Smith
Review the Scheme for Establishment of Community Councils 31-Mar-2027
Colin Smith;
Manager of Legal
and Democratic
Services 
Risk Description Current
Assessment
Target
Assessment Owner
Engaging positively
with Residents,
Communities &
Partnerships
The risk that the Council fails to adequately engage,
establish and maintain positive relationships with local
residents and communities in addition to partnership
bodies.   
Colin Smith 
Page 84

Page 85

Official
WEST DUNBARTONSHIRE COUNCIL 
Report by Chief Officer - Resources 
Committee: Infrastructure, Regeneration and Economic Development
Committee 20 May 2026 
Subject: Resources Delivery Plan 2025/26 - Asset Management Year-end
Progress &
Resources Delivery Plan 2026/27 - Asset Management 
1 Purpose 
1.1 This report sets out the year-end progress of the 2025/26 Delivery Plan and
presents the new Delivery Plan for 2026/27, both in relation to Asset
Management. 
2 Recommendations 
2.1 It is recommended that Committee notes the progress achieved at year-end
and the new Plan for 2026/27. 
3 Background 
3.1 In line with the Strategic Planning & Performance Framework, each Chief
Officer develops an annual Delivery Plan which sets out actions to help deliver
the Strategic Plan and address the performance challenges and service
priorities identified in the planning process. The Plan also provides an
overview of services and resources, including employees and budgets, sets
out the performance indicators (PIs) for monitoring progress and considers the
relevant risks. 
4 Main Issues 
2025/26 Year-end Progress 
4.1 The 2025/26 Delivery Plan was presented to Infrastructure, Regeneration and
Economic Development Committee on 21 May 2025 and mid-year progress
reported on 12 November 2025. 
4.2 Full details of year-end progress are set out in Appendix 1. 
4.3 The progress of the Delivery Plan’s seven Asset Management actions is
summarised below: 
Progress No. (%) 
Completed 7 (100%) 
ITEM 9
Page 85

Page 86

Official
4.4 Year-end data is available for all five of the Delivery Plan’s Asset
Management PIs. The performance of those PIs is summarised below: 
Performance Against Target No. (%) 
Target met or exceeded 5 of 5 (100%)
Performance Over Time
(As one of the five PIs is new for 2025/26, this section relates to
four PIs)
No. (%) 
Improved over short term (or maintained a high
level of performance)
3 of 4 (75%) 
Improved over longer term (or maintained a high
level of performance)
3 of 4 (75%) 
2026/27 Delivery Plan 
4.5 An extract from the 2026/27 Delivery Plan is set out at Appendix 2. This
outlines Asset Management’s achievements and challenges over the past
year, as well as the priorities for the year ahead. These include:
• progressing the disposal of key strategic sites
• maximising rental income from the Council’s non-operational property
portfolio
• reviewing non-domestic rates of the Council’s operational property
portfolio
• completing the Artizan redevelopment
• completing the Faifley Community Campus development
• progressing the buildings upgrades programme
• progressing the depot refurbishment programme
• supporting Council services to deliver the asset related savings agreed by
Council 
4.6 Implementation of the Delivery Plan will be monitored by the management
team with mid-year and year-end progress reported to Infrastructure,
Regeneration and Economic Development Committee around November
2026 and May 2027 respectively. 
5 People Implications 
5.1 There are no direct people implications arising from this report. 
6 Financial & Procurement Implications 
6.1  There are no direct financial or procurement implications arising from this
report. 
7 Risk Analysis 
7.1 Failure to deliver on the actions assigned to Asset Management may have a
direct impact on the delivery of the Council’s Strategic Plan. It is essential that 
Page 86

Page 87

Official
remedial action is taken to ensure strategic delivery plans achieve the
commitments detailed. 
8 Equalities Impact Assessment 
8.1  Screening and impact assessments will be carried out on specific activities as
required. 
9 Consultation 
9.1  The delivery plans were developed through consultation with officers from the
strategic service areas. 
10 Strategic Assessment 
10.1  The delivery plans set out actions to support the successful delivery of the
strategic priorities and objectives of the Council. 
Chief Officer: Laurence Slavin
Service Area:  Resources
Date:   20 April 2026
_____________________________________________________________ 
Person to Contact:  Lynn Henderson    
lynn.henderson@west-dunbarton.gov.uk 
Appendices:  Appendix 1: Resources Delivery Plan 2025/26 - Asset
Management Year-end Progress  
Appendix 2: Resources Delivery Plan 2026/27 - Asset
Management 
Background Papers: Resources Delivery Plan 2025/26 - Asset Management,
Infrastructure, Regeneration and Economic Development
Committee, 21 May 2025 
Resources Delivery Plan 2025/26 - Asset Management
Mid-Year Progress, Infrastructure, Regeneration and
Economic Development Committee, 12 November 2025 
Strategic Planning & Performance Framework 2022/27 
Wards Affected: All 
Page 87

Page 88

Official
Appendix 1: Resources Delivery Plan 2025/26 – Asset Management Year end Progress 
Our Communities 
Our residents are supported to increase life and learning skills 
Action Status Progress Due Date Note Owner
Complete the redevelopment of
Glencairn House   31-Mar-2026
Completed as planned. The redevelopment of Glencairn
House, a heritage-led regeneration initiative to transform a
historically significant building in Dumbarton town centre
into a vibrant cultural and community hub, was completed
and handed over to the responsible service area for final
preparations before it opens to the public later this year.
Michelle
Lynn
Progress the Faifley Community
Campus development   31-Mar-2026
Completed as planned. This £34.5 million investment
creates a modern, sustainable, purpose-built campus that
brings together education, community, and leisure
facilities under one roof. It provides state-of-the-art
classrooms, flexible learning spaces, and enhanced digital
infrastructure to support improved educational outcomes.
Phase 2 works relating to the demolition of the old school
buildings, the construction of outdoor sports facilities, and
external landscaping, are due to be completed in 2026.
Michelle
Lynn 
ITEM 9 - APPENDIX 1
Page 88

Page 89

Official 
Our Environment 
Our neighbourhoods are sustainable and attractive 
Performance Indicator
2024/25 2025/26
Owner Value Status Value Target Short
Trend
Long
Trend Note
Percentage of Consultancy
Services project
deliverables for General
Services projects delivered
as planned
New for
2025/26  100% 80% N/A N/A Target exceeded. Michelle
Lynn 
Action Status Progress Due Date Note Owner
Progress the building upgrades
programme   31-Mar-2026
Completed as planned. All works were completed on
schedule and within budget. They included improvements
across a range of assets, from education and community
facilities to operational depots, embedding sustainability
principles such as energy-efficient systems, low-carbon
materials, and improved accessibility. 
Our strong performance is further demonstrated through
the latest Local Government Benchmarking Framework
data for 2024/25, where West Dunbartonshire exceeded
both the Scottish and family group averages for suitability
and condition of operational buildings. We achieved a
national ranking of 6th for suitability and 13th for condition
out of 32 councils, reflecting the positive impact of
sustained investment and effective asset management.
Michelle
Lynn       
Page 89

Page 90

Official 
Our Council 
Our Council is adaptable and focused on delivering best value for our residents 
Performance Indicator
2024/25 2025/26
Owner Value Status Value Target Short
Trend
Long
Trend Note
Percentage of council
buildings in which all public
areas are suitable for and
accessible to disabled
people
97%  97% 97%  
Target met with performance
consistently high over both the
short and long term.
Michelle
Lynn
Percentage of capital
receipts achieved as
forecast
100%  90% 90%   Target achieved in 2025/26 as per
programme.
Michelle
Lynn
Proportion of operational
buildings that are suitable
for their current use
95%  95% 93%  
Target exceeded. Based on the
LGBF comparative data for
2024/25 published by the
Improvement Service in February
2026, performance was better
than the Scottish average of
85.7% and better than the family
group average of 86.1%, with a
ranking of 6 of 32 local authorities,
up 4 places from the previous
year.
Michelle
Lynn
Proportion of internal floor
area of operational buildings
in satisfactory condition
93%  93% 91%  
Target exceeded. Based on the
LGBF comparative data for
2024/25 published by the
Improvement Service in February
Michelle
Lynn
Page 90

Page 91

Official
Performance Indicator
2024/25 2025/26
Owner Value Status Value Target Short
Trend
Long
Trend Note
2026, performance was better
than the Scottish average of
91.0%, and better than the family
group average of 90.1%, with a
ranking of 13 of 32 local
authorities, consistent with the
previous year. 
Action Status Progress Due Date Note Owner
Progress the disposal of key
strategic sites   31-Mar-2026
Completed as planned. We implemented the Council’s
Disposal Strategy, ensuring surplus and underutilised
assets were identified, marketed, and sold in line with
strategic objectives, delivering the agreed capital receipts.
Michelle
Lynn
Progress the depot
refurbishment programme   31-Mar-2026
Completed as planned. The successful refurbishment of
Council depots ensures these operational hubs remain fit
for purpose and compliant with health, safety, and
environmental standards and that they embed
sustainability principles to reduce environmental impact
and support the Council’s net-zero targets, including
energy efficient systems, improved insulation, and low-
carbon materials.
Michelle
Lynn
Develop and implement plans
and support services to achieve
the asset related savings
agreed by Council  
31-Mar-2026
Completed as planned. We consulted with services to
support them to achieve the asset related savings due in
2025/26.
Michelle
Lynn 
Page 91

Page 92

Official
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Maintaining
Council Assets
that are fit for
purpose
The risk that the Council's
assets and facilities are not fully
fit for purpose with consequent
adverse impact on our ability to
deliver efficient and effective
services. Assets included in this
assessment are the Council’s
property portfolio.  
01-Apr-
2026
The risk score remains low due to
the ongoing programme of capital
works. The Property Action Plan
2023-28, approved at
Infrastructure, Regeneration and
Economic Development
Committee in February 2023, will
monitor all requirements to
maintain the risk score.
Michelle
Lynn 
Our residents are engaged and empowered 
Action Status Progress Due Date Note Owner
Engage with relevant
community groups over the
potential to lease Dalmuir Golf
Course  
31-Mar-2026 Completed as planned. Lease transaction to the existing
users was completed 1 July 2025.
Michelle
Lynn 
Action Status 
Completed 
PI Status 
Target met or exceeded 
Risk Status 
OK 
Long Term Trends 
Improving 
No change 
Getting worse 
Short Term Trends 
No change 
Getting worse 
Page 92

Page 93

Official
Appendix 2: Resources Delivery Plan 2026/27 - Asset Management 
1. Introduction 
Resources comprises Finance, Business Support, Internal Audit & Fraud and Asset Management. It provides accountancy, treasury
management, business support, internal audit and fraud and asset management services to the Council and external clients including the West
Dunbartonshire Leisure Trust, the Valuation Joint Board, Clydebank Property Company, charities and trusts, and West Dunbartonshire Energy
Ltd. Company. In addition, it provides direct services to residents of West Dunbartonshire. 
It is one of seven strategic areas responsible for delivering the Council’s Strategic Plan. Key actions to help achieve that are set out in this
Delivery Plan, together with actions to address any performance issues and service priorities identified in the planning process. Progress will be
monitored and managed by the management team and reported to Corporate Services Committee and Infrastructure, Regeneration & Economic
Development Committee (asset management elements only) twice yearly, at mid-year and year-end. 
2. Performance Review 
The Resources management team completed a detailed review of 2025/26 performance, focusing on: 
 2025/26 Delivery Plan year-end progress
 Local Government Benchmarking Framework (LGBF) comparative performance
 Citizens’ Panel feedback
 Complaints. 
This review highlighted our key achievements and challenges in 2025/26. These are summarised below. 
Key Achievements in 2025/26 
Asset Management 
 Progressed the delivery of the Glencairn House project which is an ambitious heritage-led regeneration initiative to transform a historically
significant building into a vibrant cultural and community hub, preserving its architectural character while introducing modern facilities.
ITEM 9 - APPENDIX 2
Page 93

Page 94

Official
 Delivered the Faifley Campus project which is a £34.5million investment to create a modern, purpose-built campus that brings together
education, community, and leisure facilities under one roof and provides state-of-the-art classrooms, flexible learning spaces, and enhanced
digital infrastructure to support improved educational outcomes.
 Played a pivotal role in advancing the development phase of the Exxon City Deal Project, a major regeneration initiative designed to unlock
economic growth and improve connectivity across West Dunbartonshire. This phase focused on complex preparatory work, including
extensive stakeholder engagement with landowners, statutory bodies, and community representatives to ensure alignment with planning and
infrastructure requirements.
 Played a critical role in the successful refurbishment of Council depots and the school estate, ensuring these operational hubs remain fit for
purpose and compliant with health, safety, and environmental standards and embed sustainability principles, incorporating energy efficient
systems, improved insulation, and low-carbon materials to reduce environmental impact and support the Council’s net-zero targets.
 Completed the Posties Park project which was a flagship development to transform Posties Park into a state-of-the-art sports hub, delivering
on the Council’s commitment to high-quality facilities that promote community engagement, health, and leisure. Originally moved to Asset
Management in January 2025, the project overcame earlier delays and was successfully managed to ensure steady progress and adherence
to the revised schedule. By completing and renaming the development as Lachie Stewart Memorial Park in October 2025, the Council has
delivered a sustainable, inclusive facility that enhances local wellbeing and supports active lifestyles. 
Key Challenges in 2025/26 
Asset Management 
 Staff turnover, coupled with the time required to recruit, and train employees, continued to present significant challenges and is expected to
remain a pressure point into 2026/27. Retaining skilled staff and accelerating onboarding processes will be critical to maintaining service
continuity and delivering planned projects.
 The national skills shortage of qualified and experienced officers in Asset Management has led to a reduced workforce and increased
demands on existing teams. This has required the introduction of alternative service delivery models, including greater use of external
consultants and shared service arrangements, which will need careful management to ensure quality and cost control.
 Increasing supply chain issues driven by rising energy, transport, and raw material costs, continue to impact the availability of labour and
materials and ultimately project costs and delays.  
Page 94

Page 95

Official
3. Strategic Assessment 
The Resources management team completed a strategic assessment to determine the major influences on service delivery and priorities in
2026/27. The key factors are summarised below. 
Key Factors 
Financial Challenges 
The entire public sector is continuing to face significant financial challenges due to a range of factors including inflationary cost increases, pay
awards not being fully funded by the Scottish Government and insufficient overall funding to support the delivery of front line and back-office
services. The Council is currently faced with an estimated cumulative funding gap in 2027/28 of £10.905m rising to £44.028m by 2030/31. We
will continue to monitor the overall financial position of the Council and updates on estimated future budget gaps will be reported to Elected
Members throughout 2026/27. 
These challenges require further action to balance our budget and protect services for residents. Within Resources, this means available funding
will be reduced over time and we will need to reconfigure how we work, what we do, where we work, and potentially reduce the number of
people employed. In this context, we will aim to continue to provide a sustainable, quality service to internal and external clients and the public. 
Budget Sensitivity Analysis 
In reviewing the service budget projections, consideration has been given to the sensitivity of these budgets, in particular for higher risk/ higher
value budgets which may have a significant impact on budgetary control and future budget projections. The analysis has considered sensitivity
around demand, costs and charges, and income levels. 
Within Resources, budgets which have been identified as being more susceptible to fluctuations include:
 Building materials which are subject to global supply chain pressures and price volatility.
 Labour costs which are impacted by national skills shortages and recruitment challenges
 Transport fuel costs which are influenced by energy markets trends and inflation
 Capital plan delivery which is exposed to delays and cost escalation due to procurement and contractor availability 
Page 95

Page 96

Official
From an Asset Management perspective, additional sensitivity arises from:
 Property maintenance and lifecycle costs, which can increase significantly due to inflation in construction and compliance requirements.
 Land acquisition and disposal values, which fluctuate with market conditions and economic uncertainty.
 Sustainability and compliance investments, where costs for energy efficient upgrades and carbon reduction measures may rise due to
regulatory changes and technology pricing. 
On a more Council-wide basis, the Council’s cost of borrowing is susceptible to fluctuations in the bank interest rate due to the level of the
Council’s short to medium term borrowing. 
Income from Capital Receipts 
Continuing to secure income for the Council is a key priority and the Corporate Asset Management Framework supports this through the delivery
of capital receipts from the disposal of key strategic sites. The Framework will highlight non-performing property assets, inform the process for
considering future disposals, and generate additional income through the disposal of redundant assets. In 2026/27, we will monitor progress
against the Framework and the disposal of key strategic sites and provide an annual update on progress. We are in the process of phasing out
the reliance placed on capital receipts as part of the annual budget setting process. 
Income from Non-Operational Portfolio 
In addition to generating capital receipts through disposals, the Council’s non-operational property portfolio continues to provide an important
source of recurring income. Asset Management actively manages these assets (such as leased commercial properties, industrial units, and land
holdings) to maximise rental income and ensure strong occupancy levels. This involves regular lease reviews, rent negotiations, and proactive
marketing of vacant units, alongside maintaining compliance with statutory obligations and delivering value for money. By optimising the
performance of the non-operational portfolio, the Council secures a sustainable revenue stream that supports service delivery and reduces
reliance on one-off capital receipts. Looking ahead to 2026/27, Asset Management will continue to monitor market conditions, explore
opportunities for portfolio rationalisation, and identify potential for income growth through strategic investment and improved asset utilisation. 
Review of Non-Domestic Rates of Operational Portfolio 
Asset Management has continued to review and monitor Non-Domestic Rates (NDR) liabilities across the Council’s operational property portfolio
to ensure accuracy and value for money. This work involves validating rateable values, challenging discrepancies, and identifying opportunities
for reliefs or exemptions where applicable. The review process also supports budget forecasting and financial planning, as NDR represents a
Page 96

Page 97

Official
significant cost for operational assets such as schools, offices, and depots. By maintaining up-to-date property data and engaging with the
Assessor’s Office, Asset Management ensures compliance while actively seeking to minimise unnecessary expenditure. Looking ahead, the
team will continue to explore efficiency measures, including rationalisation of underutilised space and leveraging changes in property use to
reduce rate liabilities, contributing to the Council’s wider financial sustainability objectives. 
Artizan Redevelopment 
The Levelling Up Fund is a UK government initiative for regenerating town centres and high streets, upgrading local transport, and investing in
cultural and heritage assets. Following a successful bid to the Fund, work is underway to progress the redevelopment of Artizan in Dumbarton
town centre. Planning permission has been approved and a contractor appointed. In 2026/27, we will complete the redevelopment in line with
the agreed plan and report progress to the Levelling Up Project Board. 
Faifley Community Campus Development 
In September 2023, the Council approved plans to create a new education and community campus on the site of the current St Joseph’s Primary
School. This significant capital investment project brings together a range of education and community facilities within the Faifley Schools
Community Campus. Following planning approval and the start of construction in February 2024, Phase1 was completed in 2025/26. This has
delivered modern, purpose-built school buildings for St Joseph’s and Edinbarnet Primary Schools, integrated early learning and childcare
facilities, and shared community spaces designed to support local engagement and wellbeing. The campus includes state-of-the-art classrooms,
digital learning infrastructure, sports facilities, and landscaped outdoor areas, all built to high sustainability standards with energy-efficient
systems and low-carbon materials. Governance and oversight have continued through the dedicated Learning Estate Project Board, with regular
updates provided to the Education Committee and Council via budgetary reports. The completion of Phase 1 represents a major milestone in
creating a vibrant, inclusive hub for education and community life in Faifley. Work is now progressing on the second and final phase of the
project, due for completion in 2026/27. This will focus on demolishing the old buildings and creating new car parking and external landscaped
spaces, including an all-weather sports pitch and multi-use games area. 
Building Upgrades 
The 2026/27 programme for delivering corporate asset building upgrades will focus on renovation, remodelling, and refreshing key corporate
buildings in line with the objectives of the Corporate Asset Management Plan. This includes improving building functionality, compliance with
statutory standards, and enhancing energy efficiency to support the Council’s net-zero ambitions. Works will target priority assets identified
through condition surveys and lifecycle assessments, ensuring investment is directed where it delivers the greatest operational and financial
Page 97

Page 98

Official
benefit. Upgrades will incorporate modernised office layouts to support hybrid working, improved accessibility, and sustainability measures such
as LED lighting, insulation improvements, and low-carbon heating systems. In 2026/27, we will progress the building upgrades programme in
accordance with the agreed plan and timeframe, while maintaining robust governance, cost control, and stakeholder engagement to minimise
disruption and deliver long-term value. 
Depot Refurbishment 
The Council’s depot estate has been identified as no longer fit for purpose, impacting operational efficiency and compliance. Following a
comprehensive review and feasibility assessment, it was agreed that refurbishment of the existing estate offered the most cost-effective solution
compared to a full new-build programme. In 2026/27, the Depots Project Board will continue to lead the delivery of the refurbishment
programme, building on the progress achieved in 2025/26. This phase will focus on modernising facilities to meet health and safety standards,
improving welfare areas for staff, upgrading fleet maintenance workshops, and incorporating sustainability measures such as energy-efficient
lighting, improved insulation, and low-carbon heating systems. The programme will also address site security, digital connectivity, and layout
optimisation to support operational needs and future service delivery models. Robust governance and stakeholder engagement will remain
central to ensure works are delivered on time, within budget, and with minimal disruption to frontline services. 
Asset Related Council Savings 
In line with the Council’s agreed savings options for 2026/27, a number of initiatives involve changes to the Council’s asset base that will require
dedicated support from the Asset Management team. These initiatives include rationalisation of underutilised properties, space optimisation
within corporate buildings, and potential disposal or repurposing of non-essential assets to reduce operating costs and generate income.
Throughout the year, Asset Management will work in close partnership with relevant services to develop detailed implementation plans, ensuring
that changes are delivered in a way that supports service continuity and compliance with statutory obligations. The team will also provide
technical advice, property data analysis, and project management expertise to enable informed decision-making and timely delivery of agreed
savings. By embedding sustainability and efficiency principles into these initiatives, Asset Management will help the Council achieve its financial
targets while maintaining a fit-for-purpose estate that supports operational needs. 
Continuous Improvement 
Continuous improvement is central to all that we do. The actions set out in this section, as well as those at an operational level not included in
this Delivery Plan, demonstrate our commitment to continuous improvement and take account of the wider Best Value focus on vision and
Page 98

Page 99

Official
leadership; governance and accountability; effective use of resources; partnerships and collaborative working; working with communities;
sustainability; and fairness and equality. 
Action Plan 
The challenges identified in Section 2 and the key factors identified in Section 3 have informed Resources priorities for 2026/27. Appendix 1 sets
out the action plan to address them. It also includes: 
 performance indicators and targets that will enable progress to be monitored and reported to stakeholders
 strategic workforce actions to address workforce issues identified in the planning process
 strategic and/or service risks. 
In relation to the latter, strategic risks represent the potential for the Council to take advantage of opportunities or fail to meet stated strategic
objectives and those that require strategic leadership. Service risks relate to service delivery and represent the potential for impact on individual
services, or the experience of those who work within the services, i.e. employees, partners, contractors and volunteers, or service users and
clients in receipt of the services provided. In identifying the relevant risks for 2026/27 and actions to mitigate them, the aim is to improve or
maintain the current position (i.e. the current risk score) set out in the appendix.  
Page 99

Page 100

Official
4. Resources 
Finance 
Resources has a net revenue budget of £6.209m and a capital budget of £13.049m in 2026/27. A breakdown by service area is set out below.
We will make the best use of the resources available to deliver on key priority areas and secure external/match funding where this is possible. 
Service Area Gross Expenditure
2026/27 (£m)
Gross Income
2026/27(£m)
Net Expenditure
2026/27 (£m)
Capital Budget
2026/27(£m) (Figures subject to ongoing verification)
Audit 0.387 0.057 0.330 0.000
Finance 1.862 0.135 1.727 0.554
Rent Rebates & Allowances 32.426 30.225 2.201 0.000
Revenue & Benefits 3.159 0.443 2.716 0.000
Finance Service Centre 0.545 0.069 0.476 0.000
Cost of Collection of Rates 0.091 0.120 -0.029 0.000
Cost of Collection of Council Tax 0.074 1.162 -1.088 0.000
Office Accommodation 1.538 0.396 1.142 0.000
Central Repairs & Maintenance 1.453 0.000 1.453 0.000
Corporate Asset Maintenance 2.729 2.729 0.000 12.495
Corporate Assets 2.712 5.431 -2.719 0.000
Total 46.976 40.767 6.209 13.049 
Page 100

Page 101

Official
Employees 
Employee Numbers 
The headcount and full-time equivalent staff in each service area (as of 31 March 2026) are as follows: 
*Figures do not reflect matrix management arrangements and resources shared with other services. 
Absence 
The 2025/26 quarterly absence figures for Resources are shown below, together with the Council average for the same periods for comparison.
The figures for Resources were lower than the Council average throughout 2025/26. 
2025/26 Absence  Quarter 1 Quarter 2 Quarter 3 Quarter 4 Annual FTE days lost
per FTE employee
Resources 4.45% 4.25% 5.68% 3.33% 11.38
Council Wide Total 6.17% 5.39% 7.2% 7.65% 14.38 
Service Area Headcount FTE
Audit & Fraud 4 3.1
Finance 35 31.6
Asset Management* 20 19.2
Business Support 75 67.5
Total 134 121.4
Page 101

Page 102

Official
5. Action Plan 
1. Our Communities 
Our residents are supported to increase life and learning skills 
Action Due Date Owner
Complete the Faifley Community Campus 31-Mar-2027 Michelle Lynn 
2. Our Environment 
Our neighbourhoods are sustainable and attractive 
Action Due Date Owner
Progress the building upgrades programme 31-Mar-2027 Michelle Lynn 
3. Our Economy 
Our area has the infrastructure for sustainable and inclusive growth where businesses can flourish 
Action Due Date Owner
Complete the Artizan redevelopment 31-Mar-2027 Michelle Lynn 
4. Our Council 
Our Council is adaptable and focused on delivering best value for our residents 
Page 102

Page 103

Official
Performance Indicator 2026/27 Owner Target
Percentage of council buildings in which all public areas are suitable for and accessible to disabled people 97% Michelle Lynn
Percentage of capital receipts achieved as forecast 90% Michelle Lynn
Percentage of income from non-operational portfolio achieved as forecast 85% Michelle Lynn
Proportion of operational buildings that are suitable for their current use 93% Michelle Lynn
Proportion of internal floor area of operational buildings in satisfactory condition 91% Michelle Lynn 
Action Due Date Owner
Progress the disposal of key strategic sites 31-Mar-2027 Michelle Lynn
Maximise income from non-operational portfolio 31-Mar-2027 Michelle Lynn
Review non-domestic rates of operational portfolio 31-Mar-2027 Michelle Lynn
Progress the depot refurbishment programme 31-Mar-2027 Michelle Lynn
Develop and implement plans and support services to achieve the asset related savings agreed by Council 31-Mar-2027 Michelle Lynn 
Risk Description Current
Assessment
Target
Assessment Owner
Maintaining Council
Assets that are fit for
purpose
The risk that the Council's assets and facilities are not fully fit
for purpose with consequent adverse impact on our ability to
deliver efficient and effective services. Assets included in this
assessment are the Council’s property portfolio.  
Michelle Lynn   
Page 103

Page 104

Page 104

Page 105

Unmarked
WEST DUNBARTONSHIRE COUNCIL 
Report by Chief Officer Roads and Neighbourhood 
Infrastructure, Regeneration and Economic Development 
on 20 May 2026 
Subject: Traffic Order Review Panel 
1. Purpose 
1.1 To agree the detailed process for the review and approval of new traffic
regulation orders. 
2. Recommendations 
2.1 It is recommended that the Committee: 
a) Note the contents of this report; 
b) Approve the noted procedures; and
c) Delegate to the Chief Officer the implementation of the Orders in
accordance with the associated statutory procedures where no
objections are received. 
3. Background 
3.1 Under the Road Traffic Act 1984, local authorities are the traffic authorities
for non-trunk roads and have the power to make various traffic regulation
orders, including alterations to speed limits and new parking restrictions
orders on their network. ‘The Local Authorities’ Traffic Orders (Procedure)
(Scotland) Regulations 1999’ sets out the statutory requirements for
promotion, consultation and confirmation of new traffic orders. 
3.2 As part of that process ‘The Traffic Orders (Procedure), Regulation 4 requires
that the appropriate statutory consultation is undertaken with any
organisations or persons likely to be affected by any provision of a proposed
order including key stakeholders such as Emergency services, local transport
partners (SPT), Elected Members and all local Community Councils.     
3.3 Where possible key stakeholders are notified by email of any proposed
orders with a Public Notice also published in the Clydebank Post newspaper
to advise the wider local community. 
3.4 These Notices publicises the consultation and advises where a copy of the
draft Order, including a plan showing the extent of the roads affected and a
Statement of Reason for making the Order, can be viewed and where any
representations or objections to the proposals should be sent. Details of the
proposals are also published on the Council’s various social media platforms.
ITEM 10
Page 105

Page 106

Unmarked
3.5 Should any proposed Order be subject to an objection, the Roads and
Transportation team will first engage with the objector and to try and resolve
their concerns. Where appropriate the order may be amended by the Service
to resolve the issue causing the objection. 
3.6 Where representations or objections cannot be resolved or removed by the
objector the ‘Procedure’ requires that the authority consider all objections
made to try and resolve the issue or amend the proposal. 
3.7 The Traffic Order (Procedure) Regulation 12 requires the authority to
consider any objections that are duly made and not withdrawn, but it does not
require those objection to be referred to Scottish Ministers as a matter of
course, and allows for these objections to be considered at a local level
before deciding whether to proceed with the Order. 
4. Main Issues 
4.1 The Council has recently implemented Parking Enforcement within West
Dunbartonshire and officers are regularly patrolling our town centres and key
enforcement areas to manage existing parking restrictions. 
4.2 The Roads and Transportation team have also been working to introduce
mandatory 20mph speed limits around our schools and residential streets
with a 20mph Strategy being agreed by the IRED committee on 21st May
2025. 
4.3 In previous years the service has introduced only limited new permanent
traffic regulation orders, with parking concerns generally referred to Police
Scotland or managed through informal means. 
4.4 The continuing development of these two initiatives will require the Roads
and Transportation service to introduce a number of new traffic regulation
orders to support their implementation. As it is anticipated that any new
orders, particularly any new parking restrictions, will receive objections from
local residents and businesses, an appropriate method of managing these
objections is required.   
4.5 Escalating these objections to the Scottish Ministers for review would result in
prolonged timescales for any implementation of new orders and officers have
consulted with our colleagues in Legal as well as various other local
authorities on their consideration and approval process to identify a more
appropriate way to manage these at a local level. 
4.6 Through these discussions it has been identified that all other local
authorities will present details of any new orders and maintained objections
to the appropriate Committee for review and decision. 
4.7 It is proposed that the IRED Committee undertake the role of the Traffic
Order Review Panel for West Dunbartonshire Council and any proposed new
Orders which receive objections presented to the Committee for their
consideration. 
Page 106

Page 107

Unmarked
4.8 In line with requirements of the Local Authorities Traffic Order (Procedures)
1999 officers will provide reports detailing the Schedule of Orders, the
Statement of Reason for the orders as well as details of the objections
received and officer recommendations for consideration. 
4.9 Where any new Traffic Orders are promoted and no objections are received,
these will be delegated to the Chief Officer for Roads and Neighbourhood for
implementation in accordance with the associated statutory procedures. 
4.10 There are some instances where new orders must be escalated to the
Secretary of Sate for final decision. These include: - 
 Orders which impact the trunk road network
 Stopping Up orders 
5.  People Implications 
5.1  There are no people implications for this proposal. 
6. Financial and Procurement Implications 
6.1  There are no financial or procurement implications associated with this
proposal. 
7. Risk Analysis 
7.1  All traffic orders to support this strategy will be promoted via permanent
orders and whilst it is anticipated the introduction of this strategy will be
generally well received amongst residents there is the potential for isolated
objections for some locations which may impact the delivery times and
proposed budget.   
8. Equalities Impact Assessment (EIA) 
8.1  This proposal will help the socio-economically disadvantaged as there are
more likely to be the victims of road traffic accidents. Improves the health and
well-being of our residents by providing safer roads to encourage walking
and cycling. Equality impact assessments were completed for both the
introduction of parking enforcement and the 20mph Street Strategy. 
9. Consultation 
9.1 Consultations will be undertaken through the statutory traffic regulation order
consultation process. 
Page 107

Page 108

Unmarked
10. Strategic Assessment 
10.1 The review sets out actions to support the successful delivery of the strategic  
priorities and objectives of the Council, in particular: 
 Our Neighbourhoods are sustainable and attractive. 
Chief Officer  Gail Macfarlane
Service Area Roads and Neighbourhood
Date:  30 April 2026 
Person to Contact: Liam Greene, 
Roads and Transport Manager, 
Liam.greene@west-dunbarton.gov.uk 
Appendix  1 - 20mph Strategy EIA
2 - Parking Enforcement  
EIA 
Wards Affected: All wards 
Page 108

Page 109

Assessment No 1274 Owner liam.greene                            
Resource Transformation Service Education, Learning &
Attainment
FirstName Surname Job Title
Head Officer Liam Greene Roads and Transportation
Manager
Members Gail MacFarlane - Chief Officer Roads and Neighbourhood
Raymond Walsh - Roads Network Coordinator
(Please note: the word 'policy' is used as shorthand for strategy policy
function or financial decision)
Policy Title Implementation of 20mph Street Strategy
The aim, objective, purpose and intended out come of policy
Implement 20mph limit strategy across the whole of West Dunbartonshire
Service/Partners/Stakeholders/service users involved in the development
and/or implementation of policy.
Scottish Government
Elected Members
Transport Scotland
Does the proposals involve the procurement of any goods or services? No
If yes please confirm that you have contacted our procurement services to
discuss your requirements.
No
SCREENING
You must indicate if there is any relevance to the four areas
Duty to eliminate discrimination (E), advance equal opportunities (A) or
foster good relations (F)
Yes
Relevance to Human Rights (HR) Yes
Relevance to Health Impacts (H) Yes
Relevance to Social Economic Impacts (SE) Yes
Who will be affected by this policy?
All local residents and traffic that use the local road network
Who will be/has been involved in the consultation process?
Discussions with Scottish Government and Transport Scotland
ITEM 10 - APPENDIX 1
Page 109

Page 110

Please outline any particular need/barriers which equality groups may have in relation to
this policy list evidence you are using to support this and whether there is any negative
impact on particular groups.
Specific group to
consider
Needs Evidence Impact
Age                           The Equality Act 2010
requires local authorities
(amongst others) to provide
equality of opportunity
between
people who share a
protected characteristic and
those who do not. Of
particular relevance to
20mph limits
are children, older persons,
those with disabilities, and
women, who are more likely
to be dependent on
walking rather than car use,
or seen as more vulnerable
road users.
Children are more likley to be
seriously injured/killed in a
collision. This risk is
significantly reduced when
speeds are reduced to 20mph
or below
A 20mph limit will
provide a
safer environment for
children
Surveys have shown
that children are more
likely to cycle/walk
locally more
after the introduction of
20mph limits
benefits of 20mph limits
to be focused around
safety,
including safer
environments , safer
crossing facilities for
pedestrians (particularly
for older
people and those with
disabilities)
Page 110

Page 111

Disability                    The Equality Act 2010
requires local authorities
(amongst others) to provide
equality of opportunity
between
people who share a
protected characteristic and
those who do not. Of
particular relevance to
20mph limits
are children, older persons,
those with disabilities, and
women, who are more likely
to be dependent on
walking rather than car use,
or seen as more vulnerable
road users.
Implementing 20mph limits
prevents road injury and
disability. It helps the less able
to get about. 20mph limits
increase accessibility and
opportunities for the most
vulnerable and leads to fairer,
healthier more social lives.
Equality and inclusivity
improves, raising quality for
everyone including carers and
those with dependent family
Benefits of 20mph limits
to be focused around
safety,
including safer
environments , safer
crossing facilities for
pedestrians (particularly
for older
people and those with
disabilities)
Slower speeds improve
access, especially for
those with restricted
mobility, vision, hearing
or mental health.  The
ability to get around
safely and affordably
increases opportunities
for work and friendship. 
With low accessibility,
people can become
lonely.  Social isolation
has been linked to poor
mental and physical
health and mortality. 
Residents of heavy
traffic areas know fewer
neighbours than in light
traffic streets. With few,
slow car movements
people enjoy the street
scene. They chat. It is
quieter and not so
dangerous or polluted. 
Inclusivity and social
cohesion increase when
traffic slows down.
Gender Reassign              
Marriage & Civil
Partnership 
Pregnancy &
Maternity        
Important to check how this
Protected characteristic is
affected and how it
crosscuts
In effect will cross cut with sex In terms of impacts
these will likely be
similar on those for
women under 'sex'
Race                          We need to assess potential
differential impacts,
including how these interact
with economic and social
factors
Most BME groups have less
access to cars than most white
ethnic groups
Positive
Religion and Belief          
Sex                           We need to assess potential
differential impacts,
including how these interact
with economic and social
factors
Women have less access to
cars than men. Women are the
majority of care givers, for
example of children, relatives
and friends. They are more
likely to be using pushing
chairs for example.
Positive especially for
women
Sexual Orientation 
Page 111

Page 112

Human Rights                  Human Rights
Act/European Convention
on Human Rights
(ECHR)Article 8
UNCRC especially in terms
of the
'Protection' and the 'best
interests' of children
20mph limits will deliver
changes in traffic speed and
casualty rates, influence travel
behaviour,
Surveys have shown that
children are more likely to
cycle/walk locally more
after the introduction of 20mph
limits
benefits of 20mph limits to be
focused around safety,
including safer environments
around schools, safer crossing
facilities for pedestrians
(particularly for older
people and those with
disabilities)
20mph schemes have the
potential to deliver a wide
range of benefits, and in the
longer term, health,
environmental and
Positive both in terms of
the ECHR and UNCRC
Page 112

Page 113

Health                      Under the Health and Social
Care Act 2012, local
authorities have public
health responsibilities; of
relevance to 20mph limits
given the strong links
between road safety and
public health.
20mph limits will deliver
changes in traffic speed and
casualty rates, influence travel
behaviour,
and lead to associated
environmental, health,
community and economic
benefits
The World Health Organisation
(WHO, 2017) recommends
20mph limits as best practice
in residential
areas, and states that ‘a safe
speed on roads with possible
conflicts between cars and
pedestrians,
cyclists or other vulnerable
road users is 30kmh/20mph
20 mph limits cut the number
and severity of road fatalities
and injuries.  Some collisions
are avoided or impact speed is
less, reducing the harm done
by a crash.
Surveys have shown
that people are more
likely to cycle/walk
locally more
after the introduction of
20mph limits
benefits of 20mph limits
to be focused around
safety,
including safer
environments around
schools, safer crossing
facilities for pedestrians
(particularly for older
people and those with
disabilities)
20mph schemes have
the potential to deliver a
wide range of benefits,
and in the
longer term, health,
environmental and
community benefits
could be greater than
the more obvious road
safety benefits
Existing research
suggests that 20mph
limits (signed only) have
the potential to improve
health and wellbeing
and reduce pressure on
the NHS, as a result of
an overall increase in
use of active travel
modes, and
an overall reduction in
injuries from vehicle
collisions as a result of a
reduction in speed
Health promoting
activities like walking,
cycling and being
outdoors are
encouraged as speeds
reduce. This builds a
positive spiral of
increased activity
bringing reduced illness
from diseases
associated with obesity,
heart disease and
stress.  Health
inequalities in life
expectancy are reduced
by 20 mph limits  as
poorer people
(especially boys) are
more often road victims.
Page 113

Page 114

Social & Economic
Impact     
Safer and more attractive
local environments were
expected to encourage
more social interaction
Scottish Consumer Duty:
We have screened for
relevance to the Duty and
concluded that there
nothing that might be
relevant that it is not already
addressed in this impact
assessment.
The majority of people agree
that the 20mph speed limit is
beneficial for residents.
However, child safety still
appears to be a concern
This proposal will help
the socio-economically
disadvantaged as there
are   more likely to be
the victims of road traffic
accidents. Benefits of
20mph limits to be
focused around safety,
including safer
environments around
schools, safer crossing
facilities for pedestrians
(particularly for older
people and those with
disabilities)
Creates and
environment where
streets feel safer and is
a more desirable place
to live
Cross Cutting          Important to consider cross
cutting effects
Evidence shows benefits for
various groups
Available evidence have
shown that implementation of
20 mph limits has minimal
effect on journey
Crossing cutting positive
benefits
Page 114

Page 115

Actions
Page 115

Page 116

Policy has a negative impact on an equality group,but is still to be implemented, please
provide justification for this.
Positive impact - Opportunities to improve local environment and road safety
Will the impact of the policy be monitored and reported on an ongoing bases?
Accident and crash data can be monitored and reported on
Q7 What is you recommendation for this policy?
Intoduce
Please provide a meaningful summary of how you have reached the recommendation
EIA 1274: The implementation of 20mph limits has some potential positive impacts for children
and young people, disabled people and women, and those ethnic groups who have less access to
cars, especially. 20 mph may also support health and well being by encouraging more active
travel and improving road safety and reducing casualty rates.
Page 116

Page 117

Assessment No 480 Owner GMacfarlane2
Resource Regeneration, Environment and
Growth
Service Environment and
Neighbourhood
FirstName Surname Job Title
Head Officer Gail Macfarlane Chief Officer - Roads &
Neighbourhood
Members Roads Service
(Please note: the word 'policy' is used as shorthand for strategy policy
function or financial decision)
Policy Title EIA 480 Savings Option Introduction of Decriminalised Parking/Pavement Parking
The aim, objective, purpose and intended out come of policy
Introduction of decriminalised parking enforcement fully or limited to pavement parking
enforcement
Service/Partners/Stakeholders/service users involved in the development
and/or implementation of policy.
Roads Service
Police Scotland
Transport Scotland
Does the proposals involve the procurement of any goods or services? Yes
If yes please confirm that you have contacted our procurement services to
discuss your requirements.
Yes
SCREENING
You must indicate if there is any relevance to the four areas
Duty to eliminate discrimination (E), advance equal opportunities (A) or
foster good relations (F)
No
Relevance to Human Rights (HR) No
Relevance to Health Impacts (H) No
Relevance to Social Economic Impacts (SE) Yes
Who will be affected by this policy?
All road users, pedestrians, cyclists and vehicles
Who will be/has been involved in the consultation process?
Statutory Consultees
Transport Scotland
ITEM 10 - APPENDIX 2
Page 117

Page 118

Please outline any particular need/barriers which equality groups may have in relation to
this policy list evidence you are using to support this and whether there is any negative
impact on particular groups.
Specific group to
consider
Needs Evidence Impact
Age Enforcement of parking
restrictions improves road
safety for all users and
those that are older or
younger can be more
vulnerable
Inconsiderate parking can
cause access and visibility
issues that can impact on road
safety that can increase for
those younger and older
members of the community
Positive
Cumulative and
intersectional
impacts
Disability Members of the community
that are disabled require
safe access to footways and
parking
Misuse of disabled parking
spaces, inconsiderate
pavement parking and parking
at bus boarders etc can make
access more difficult for
disabled people
Positive
Social & Economic
Impact
Access to town centre
amenities and facilities
improved by enforcement of
time restrictions and
improving turnover
.Good parking management
recognised as a method to
support town centres and
access to amenities
Positive
Sex
Gender Reassign
Health Those walking or cycling
are adversely affected by
inconsiderate parking
Walking and cycling and
access to public transport
supported by enforcement of
no parking restrictions to
improve road safety
Positive
Human Rights
Marriage & Civil
Partnership
Pregnancy &
Maternity
Inconsiderate parking can
cause difficulty for those
that are pregnant or with
young families
Potentially members of the
community more likely to have
prams or pushchairs and
require footway access
Positive
Race
Page 118

Page 119

Religion and Belief
Sexual Orientation
Page 119

Page 120

Actions
Page 120

Page 121

Policy has a negative impact on an equality group,but is still to be implemented, please
provide justification for this.
Will the impact of the policy be monitored and reported on an ongoing bases?
Yes
Q7 What is you recommendation for this policy?
Intoduce
Please provide a meaningful summary of how you have reached the recommendation
The introduction of decriminalised parking and/or pavement parking enforcement will support
access to town centres and other amenities but also improve road safety for all users.  This will
allow the council to reduce inconsiderate parking such as in bus stops, in the proximity of schools
or in disabled parking bays.
In relation to pavement parking enforcement this will reduce vehicles that park with 2 wheels on
pavements making safe movement of pedestrians difficult and obstructing wheelchairs and use of
prams/pushchairs.
Page 121

Page 122

Page 122

Page 123

Unmarked
WEST DUNBARTONSHIRE COUNCIL 
Report by Chief Officer Roads and Neighbourhood 
Infrastructure, Regeneration and Economic Development 
on 20 May 2026 
Subject: Review of 20mph Street TRO Objections 
1. Purpose 
1.1 To seek approval to proceed with Traffic Regulation Orders to support
reduction of speed limits on the road’s details in Appendix 1. 
2. Recommendations 
2.1 It is recommended that the Committee: 
a) Notes the contents of this report; 
b) Approves the making and confirmation of the enclosed Traffic
Regulation Orders; and
c) Delegate to the Chief Officer the implementation of the Orders in
accordance with the associated statutory procedures. 
3. Background 
3.1 The Council 20mph Strategy was presented and approved by the Committee
on 21 May 2025. This strategy introduced mandatory 20mph speed limits on
residential streets within the authority. 
3.2 As part of the development of the Strategy 26 individual 20mph zones were
created across the authority based on priority and physical boundaries such
as major roads, railways, natural barriers, and changes in area character. 
3.3 Scottish Government funding was received in August 2025 to support the roll
out of mandatory 20mph limits across the country as part of their national
commitment to extend 20mph speed limits to appropriate roads in built-up
areas by the end of 2025 to improve road safety and to help encourage
alternative modes of travel. 
3.4 In line with the funding provided, the Roads and Transportation Team
promoted new traffic regulation orders for the first 7 zones and undertook the
upgrade of road markings within these areas. The service also carried out
pre-implementation speed surveys on 10% of the streets included and
purchased the associated signage. 
ITEM 11
Page 123

Page 124

Unmarked
3.5 A statutory consultation on the proposed reduction to the speed limit was
carried out between 21st November 2025 and 22nd December 2025 in
compliance with regulations. Key stakeholders were contacted directly via
email and a Public Notice placed in the Clydebank Post and through the
Councils social media platforms. Details of the Orders are provided in
Appendix 1 and the Statement of Reasons provided in Appendix 2. 
3.6 This process provided details of the proposed new Orders, a Statement of
Reason, and details where any objections or representations should be sent. 
4. Main Issues 
4.1 In November 2025, we formally consulted Police Scotland’s Traffic
Management team to request their view on the Council’s pending rollout of
the 20mph speed limit Order.  In December 2025, Police Scotland
acknowledged our proposal, and a meeting took place regarding signage
which they were happy with our approach however no formal response was
provided by Police Scotland. 
4.2 The approach by Police Scotland is that enforcement measures are only
carried out where speed limits being exceeded are observed, with additional
patrols carried out where there is a perceived increased or known risk.
However, the use of signs to restrict and lower speed limits has been found
to be effective, with behavioural shifts evidenced in Edinburgh despite no
additional patrols or traffic calming measures. 
4.3 During the statutory consultation period, 20 representations were received of
which 3 confirmed support for the proposals, 2 were objections against the
proposals and 15 did not confirm either way 
4.4 In accordance with the ‘Local Authorities’ Traffic Orders (Procedure)
(Scotland) Regulations 1999, where objections to a proposed Traffic
Regulation Order are duly made and not withdrawn, the local authority is
required to consider those objections before deciding whether to make the
Order 
4.5 Objector 1 - stated that the reduction of the speed limit on Round Riding
Road was unnecessary, as they did not consider it to be a residential street.
The objector also expressed concern that the introduction of 20 mph limits
had not been made clear in elected members’ election manifestos and
objected in principle to the wider introduction of 20 mph speed limits 
4.6 Officers advised that Round Riding Road is an unclassified residential road
with residential frontage and direct vehicular access along its length. The
road also functions as an access route serving a further seven residential
streets, a care home, and a primary school. On this basis, the road meets the
criteria for inclusion within a residential 20 mph speed limit. 
Page 124

Page 125

Unmarked
4.7 Officers further clarified that the introduction of 20 mph limits forms part of
national Scottish Government policy and guidance, which recommends lower
speed limits on residential streets to improve road safety, rather than being
linked to individual election manifestos. 
4.8 Objector 2 - considers the proposed 20 mph speed limit to be unnecessary
and impractical for the area. They believe it will increase journey times,
cause congestion, and negatively impact residents’ daily routines. The
objector states that the existing 30 mph limit is appropriate given the width,
condition and visibility of the roads, low pedestrian activity, and an apparent
long-term absence of collision history. They also raised concerns that
modern vehicle safety systems reduce the need for lower speed limits and
argue that enforcement of a 20-mph limit would be disproportionate. The
objector suggests that parking issues associated with school activity are the
primary traffic problem in the area and should be addressed instead of
introducing a lower speed limit. 
4.9 Officers advised that evidence from other 20 mph schemes indicates only a
minimal impact on journey times, typically around a 3% increase impact on
journey time. It was noted that 20 mph limits are intended for residential
streets, which typically form the start or end of journeys, while strategic
routes remain subject to higher speed limits. Experience elsewhere suggests
that congestion does not materially increase and that lower, more consistent
speeds can improve traffic flow and reduce harsh braking and acceleration. 
4.10 Officers acknowledged the historically low collision record in the area but
highlighted that national and local policy prioritises preventative road safety
measures. While modern vehicle safety features are beneficial, reduced
vehicle speeds remain critical in lowering collision severity and improving
reaction times, particularly for pedestrians and cyclists. 
4.11 Although the roads are described as wide and well maintained, they serve
residential areas where pedestrians and school-related activity occur. The
proposals are consistent with national guidance recommending 20 mph limits
on residential streets. Issues relating to inconsiderate parking are being
addressed separately through enforcement and do not remove the wider
safety benefits of lower speeds. Clear signage and communications will
accompany the scheme to minimise driver confusion. The proposed 20 mph
limit forms part of a national initiative supported by the Scottish Government
to improve road safety and encourage active travel. 
4.12 After responses were provided by officers both objectors were given the
opportunity to reconsider their position. Objector 1 confirmed they did not
wish to remove their objection, and no response was received from Objector
2.   
Page 125

Page 126

Unmarked
4.13 Several representations were received in support of the proposed 20 mph
speed limits. Supporters cited frequent speeding on residential streets,
concerns for pedestrian and child safety particularly on routes used by school
pupils, and potential benefits in reducing traffic noise. Support was also
expressed for the principle of lower speed limits being accompanied by
effective monitoring and enforcement to ensure compliance and maximise
safety benefits. 
4.14 The Scottish Government’s Road Safety Framework to 2030 sets out the five
pillars of a ‘safe system’ approach to road safety. These are Safe Road Use;
Safe Vehicles; Safe Speeds; Safe Roads and Roadsides; and Post-Crash
Response. Improvement in all of these pillars is required to achieve the
Scottish Government’s vision. Introducing 20mph speed limits will make an
important contribution to achieving a ‘safe system’ and supplement rather
than replace other efforts. 
4.15 There is strong evidence that safety concerns discourage greater uptake of
cycling. Research funded by Transport Scotland in 2023 identified poor
perceptions of safety as one of the key deterrents to cycling. Unlike some of
the other issues identified, such as weather and practicality, safety can be
directly influenced by local and national government. 
4.16 No significant adverse changes to vehicle journey times are anticipated. The
proposed Order focuses on residential streets typically used for a short
distance at the start or end of a journey. Main roads will retain their speed
limits, and hence journey times on the vast majority of a typical journey’s
length would be unaffected 
5.  People Implications 
5.1  There are no people implications associated with these proposals. 
6. Financial and Procurement Implications 
6.1  All materials and large-scale works have been completed with only limited
cost associated with the erection of signage to support the new speed limits.
The majority of these signs will be erected on existing infrastructure. 
6.2  No funding confirmation for 26/27 has been provided by Scottish Government
for future package roll out. 
6.3 Failure to proceed may result in request from Scottish Government to pay
back funding received. 
Page 126

Page 127

Unmarked
7. Risk Analysis 
7.1  Potential risk of requiring to pay back Scottish Government funding received
for the implementation of 20mph limits should the decision be taken not to
proceed.   
8. Equalities Impact Assessment (EIA) 
8.1  This proposal will help the socio-economically disadvantaged as there are
more likely to be the victims of road traffic accidents. Improves the health and
well-being of our residents by providing safer roads to encourage walking
and cycling. An EIA was completed the 20mph Street Strategy. 
9. Consultation 
9.1 As a Scottish Government initiative consultation with appropriate key
stakeholders has been undertaken on a national level. Local consultations
have been completed through the statutory process. 
10. Strategic Assessment 
10.1 The review sets out actions to support the successful delivery of the strategic  
priorities and objectives of the Council, in particular: 
 Our Neighbourhoods are sustainable and attractive. 
Chief Officer  Gail Macfarlane
Service Area Roads and Neighbourhood
Date:  30 April 2026 
Person to Contact: Liam Greene, 
Roads and Transport Manager, 
Liam.greene@west-dunbarton.gov.uk 
Appendix  1 - Traffic Regulation Orders 
2 - Statement of Reasons 
Wards Affected: All wards 
Page 127

Page 128

Official
APPENDIX 1
PROPOSED ORDERS
THE WEST DUNBARTONSHIRE COUNCIL
WEST DUNBARTONSHIRE COUNCIL (ALEXANDRIA NORTH) (20MPH SPEED LIMIT) ORDER
202[] 
West Dunbartonshire Council in exercise of the powers conferred on them by Section 84(1)(a) of the 
Road Traffic Regulation Act 1984 (which Act of 1984 is herein referred to as “the said Act”) and all
other powers enabling them in that behalf and after consultation with the Chief Constable in
accordance with Part 111 of Schedule 9 to the Act hereby make the following Order: - 
1. This Order may be cited as West Dunbartonshire Council (Alexandria North) (20mph Speed
Limit) Order 202[] and shall come into operation on the [DATE].
2. The Interpretation Act 1978 shall apply for the interpretation of this Order as it applies for the
interpretation of an Act of Parliament.
3. No person shall drive a motor vehicle on any lengths of roads specified in the Schedule to this
Order at a speed exceeding 20 miles per hour.
4. The Order will apply only when such a restriction is identified as applying to that road by
means of the display of appropriate traffic signs as prescribed by the Traffic Signs
Regulations and General Directions 2016.
5. This Order shall have effect subject to the following variations of existing orders: 
The provisions of any existing orders whether made or having effect as if made under the
Road Traffic Regulation Act 1984, as amended, or under any other enactment are hereby
varied to the extent that the provisions are inconsistent with this Order. 
SIGNED at WEST DUNBARTONSHIRE on the X day of X TWO THOUSAND AND TWENTY FIVE. 
Chief Officer
Roads and Neighbourhood Services
Council Offices
Church Street
Dumbarton G82 1QL 
ITEM 11 - APPENDIX 1
Page 128

Page 129

Official
SCHEDULE 
The effect of the Order is as follows: 
No person shall drive or cause or permit any vehicle to be driven at a speed in excess of 20mph on
the lengths of road in West Dunbartonshire specified in the table below:
SCHEDULE
Name Extents 
Argyll Street For its entire length
Baird Crescent For its entire length
Bannachra Crescent For its entire length
Broomley Crescent For its entire length
Burn Street For its entire length
Cameron Drive For its entire length
Campbell Crescent For its entire length
Craig Avenue For its entire length
Cullen Street For its entire length
Engels Street For its entire length
Gaitskell Avenue For its entire length
Hardie Street For its entire length
Kirkpatrick Crescent For its entire length
Lansbury Street For its entire length
Lomond Crescent For its entire length
Lomond Drive For its entire length
Lomond Road For its entire length
Luss Road For its entire length
McColl Avenue For its entire length
McColl Place For its entire length
McCulloch Lane For its entire length
Muir Crescent For its entire length
Muir Street For its entire length
Russell Drive For its entire length
Swanson Road For its entire length
Taylor Street For its entire length
Tullichewan Crescent For its entire length
Tullichewan Drive For its entire length
Woodbank Court For its entire length
Woodbank Gardens For its entire length
Woodlands Court For its entire length 
Page 129

Page 130

Official 
THE WEST DUNBARTONSHIRE COUNCIL
WEST DUNBARTONSHIRE COUNCIL (BELLSMYRE & SURROUNDING AREA) (20MPH SPEED
LIMIT) ORDER 202[] 
West Dunbartonshire Council in exercise of the powers conferred on them by Section 84(1)(a) of the 
Road Traffic Regulation Act 1984 (which Act of 1984 is herein referred to as “the said Act”) and all
other powers enabling them in that behalf and after consultation with the Chief Constable in
accordance with Part 111 of Schedule 9 to the Act hereby make the following Order: - 
1. This Order may be cited as West Dunbartonshire Council (Bellsmyre & Surrounding Area)
(20mph Speed Limit) Order 20[] and shall come into operation on the [DATE].
2. The Interpretation Act 1978 shall apply for the interpretation of this Order as it applies for the
interpretation of an Act of Parliament.
3. No person shall drive a motor vehicle on any lengths of roads specified in the Schedule to this
Order at a speed exceeding 20 miles per hour.
4. The Order will apply only when such a restriction is identified as applying to that road by
means of the display of appropriate traffic signs as prescribed by the Traffic Signs
Regulations and General Directions 2016.
5. This Order shall have effect subject to the following variations of existing orders: 
The provisions of any existing orders whether made or having effect as if made under the
Road Traffic Regulation Act 1984, as amended, or under any other enactment are hereby
varied to the extent that the provisions are inconsistent with this Order. 
SIGNED at WEST DUNBARTONSHIRE on the X day of X TWO THOUSAND AND TWENTY FIVE. 
Chief Officer
Roads and Neighbourhood Services
Council Offices
Church Street
Dumbarton G82 1QL  
Page 130

Page 131

Official
SCHEDULE 
The effect of the Order is as follows: 
No person shall drive or cause or permit any vehicle to be driven at a speed in excess of 20mph on
the lengths of road in West Dunbartonshire specified in the table below:
SCHEDULE
Name Extents 
Aitkenbar Circle For its entire length
Aitkenbar Drive For its entire length
Allan Crescent For its entire length
Argyll Avenue For its entire length
Argyll Place For its entire length
Auchenreoch Avenue For its entire length
Barnhill Road For its entire length
Barwood Hill For its entire length
Bellsmyre Avenue For its entire length
Brackenhurst Street For its entire length
Braeside Drive For its entire length
Broomhill Drive For its entire length
Brown Avenue For its entire length
Campbell Avenue For its entire length
Campbell Drive For its entire length
Campbell Terrace For its entire length
Carman View For its entire length
Crosslet Avenue For its entire length
Fraser Avenue For its entire length
Garshake Avenue For its entire length
Garshake Road For its entire length
Garshake Terrace For its entire length
Garshake Row For its entire length
Garshake Wynd For its entire length
Glebe Park For its entire length
Glenpath For its entire length
Glenside Road For its entire length
Hillfoot Avenue For its entire length
Howatshaws Road For its entire length
Hunters Avenue For its entire length
Langlands Terrace For its entire length
Loaninghead Drive For its entire length
Lomond Drive For its entire length
Lomondgate Drive For its entire length
Long Crags View For its entire length
Macphie Road For its entire length
Mansewood Drive For its entire length
Maryland Road For its entire length
McGregor Drive For its entire length
McLeod Road For its entire length
Merkins Avenue For its entire length
Muir Road For its entire length
Murray Place For its entire length
Murroch Avenue For its entire length
Penniecroft Avenue For its entire length
Pinewood Court For its entire length
St Andrews Brae For its entire length
St Andrews Crescent For its entire length
Page 131

Page 132

Official
Stirling Road From its extended kerbline with A82 (Barloan
Toll Roundabout)
in a general north-westerly direction for a
distance of 815 Metres or Thereby.
Stoneyflatt Avenue For its entire length
Stoneyflatt Court For its entire length
Stoneyflatt Gardens For its entire length
Stoneyflatt Road For its entire length
Strowans Well Road For its entire length
Stuart Road For its entire length
Sutherland Drive For its entire length
Valeview Terrace For its entire length
Whiteford Avenue For its entire length
Whiteford Crescent For its entire length
Whiteford Gardens For its entire length
Whiteford Place For its entire length 
Page 132

Page 133

Official
THE WEST DUNBARTONSHIRE COUNCIL
WEST DUNBARTONSHIRE COUNCIL (BONHILL & HALDANE) (20MPH SPEED LIMIT)
ORDER 202[] 
West Dunbartonshire Council in exercise of the powers conferred on them by Section 84(1)(a) of the
Road Traffic Regulation Act 1984 (which Act of 1984 is herein referred to as “the said Act”) and all
other powers enabling them in that behalf and after consultation with the Chief Constable in
accordance with Part 111 of Schedule 9 to the Act hereby make the following Order: - 
1. This Order may be cited as West Dunbartonshire Council (Bonhill & Haldane) (20mph Speed
Limit) Order 202[] and shall come into operation on the [DATE].
2. The Interpretation Act 1978 shall apply for the interpretation of this Order as it applies for the
interpretation of an Act of Parliament.
3. No person shall drive a motor vehicle on any lengths of roads specified in the Schedule to this
Order at a speed exceeding 20 miles per hour.
4. The Order will apply only when such a restriction is identified as applying to that road by
means of the display of appropriate traffic signs as prescribed by the Traffic Signs
Regulations and General Directions 2016.
5. This Order shall have effect subject to the following variations of existing orders: 
The provisions of any existing orders whether made or having effect as if made under the Road Traffic
Regulation Act 1984, as amended, or under any other enactment are hereby varied to the extent that
the provisions are inconsistent with this Order. 
SIGNED at WEST DUNBARTONSHIRE on the X day of X TWO THOUSAND AND TWENTY FIVE. 
Chief Officer
Roads and Neighbourhood Services
Council Offices
Church Street
Dumbarton G82 1QL 
Page 133

Page 134

Official
SCHEDULE 
The effect of the Order is as follows:
No person shall drive or cause or permit any vehicle to be driven at a speed in excess of 20mph on
the lengths of road in West Dunbartonshire specified in the table below:
SCHEDULE
Name Extents 
Auchincarroch Road For its entire length
Barton Avenue For its entire length
Brooke Avenue For its entire length
Brown Street For its entire length
Buchanan Avenue For its entire length
Buchanan Court For its entire length
Burn Street Lane For its entire length
Burn Street For its entire length
Cables Drive For its entire length
Carmona Drive For its entire length
Cook Road For its entire length
Craiglynn Gardens For its entire length
Dalmonach Road For its entire length
Davidson Road For its entire length
Dumbain Crescent For its entire length
Dumbain Road For its entire length
Elmbank Drive For its entire length
First Avenue For its entire length
Glen Avenue For its entire length
Golfhill Drive For its entire length
Haldane Terrace For its entire length
Hall Street For its entire length
Hillbank Street For its entire length
Levenbank Terrace For its entire length
Lindsay Quadrant For its entire length
Page 134

Page 135

Official
Manse Drive For its entire length
Martin Avenue For its entire length
McFarlane Road For its entire length
McGregor Avenue For its entire length
McInnes Street For its entire length
McKinlay Avenue For its entire length
Miller Road For its entire length
Napierston Road For its entire length
Northfield Drive For its entire length
Northfield Road For its entire length
Oakburn Gardens For its entire length
Oakburn Walk For its entire length
Oakfield Drive For its entire length
Peters Avenue For its entire length
Roy Young Avenue For its entire length
Sandbank Crescent For its entire length
Second Avenue For its entire length
Shandon Brae For its entire length
Shandon Crescent For its entire length
Shearer Quadrant For its entire length
Simpson Quadrant For its entire length
Steadings Drive For its entire length
Steele Crescent For its entire length
Steele Walk For its entire length
Talbot Road For its entire length
Third Avenue For its entire length
Union Street For its entire length
Union Street Lane For its entire length
Woodburn Avenue For its entire length
Woodside Crescent For its entire length 
Page 135

Page 136

Official 
Page 136

Page 137

Official 
THE WEST DUNBARTONSHIRE COUNCIL
WEST DUNBARTONSHIRE COUNCIL (BOWLING & OLD KILPATRICK) (20MPH SPEED LIMIT)
ORDER 202[] 
West Dunbartonshire Council in exercise of the powers conferred on them by Section 84(1)(a) of the 
Road Traffic Regulation Act 1984 (which Act of 1984 is herein referred to as “the said Act”) and all
other powers enabling them in that behalf and after consultation with the Chief Constable in
accordance with Part 111 of Schedule 9 to the Act hereby make the following Order: - 
1. This Order may be cited as West Dunbartonshire Council (Bowling & Old Kilpatrick) (20mph
Speed Limit) Order 202[] and shall come into operation on the [DATE].
2. The Interpretation Act 1978 shall apply for the interpretation of this Order as it applies for the
interpretation of an Act of Parliament.
3. No person shall drive a motor vehicle on any lengths of roads specified in the Schedule to this
Order at a speed exceeding 20 miles per hour.
4. The Order will apply only when such a restriction is identified as applying to that road by
means of the display of appropriate traffic signs as prescribed by the Traffic Signs
Regulations and General Directions 2016.
5. This Order shall have effect subject to the following variations of existing orders: 
The provisions of any existing orders whether made or having effect as if made under the
Road Traffic Regulation Act 1984, as amended, or under any other enactment are hereby
varied to the extent that the provisions are inconsistent with this Order. 
SIGNED at WEST DUNBARTONSHIRE on the X day of X TWO THOUSAND AND TWENTY FIVE. 
Chief Officer
Roads and Neighbourhood Services
Council Offices
Church Street
Dumbarton G82 1QL 
Page 137

Page 138

Official
SCHEDULE 
The effect of the Order is as follows: 
No person shall drive or cause or permit any vehicle to be driven at a speed in excess of 20mph on
the lengths of road in West Dunbartonshire specified in the table below:
SCHEDULE
Name Extents 
Ashtree Court For its entire length
Church Place For its entire length
Clyde View Court For its entire length
Erskine View For its entire length
Gavinburn Gardens For its entire length
Gavinburn Place For its entire length
Gavinburn Street For its entire length
Kirk Cescent For its entire length
Kirkton For its entire length
Lusset Road For its entire length
Manse Road For its entire length
Mansefield Crescent For its entire length
Mount Pleasant Drive For its entire length
Portpatrick Road For its entire length
Roman Crescent For its entire length
Scott Avenue For its entire length
Thistle Neuk For its entire length 
Page 138

Page 139

Official
THE WEST DUNBARTONSHIRE COUNCIL
WEST DUNBARTONSHIRE COUNCIL (LINNVALE) (20MPH SPEED LIMIT) ORDER 202[] 
West Dunbartonshire Council in exercise of the powers conferred on them by Section 84(1)(a) of the 
Road Traffic Regulation Act 1984 (which Act of 1984 is herein referred to as “the said Act”) and all
other powers enabling them in that behalf and after consultation with the Chief Constable in
accordance with Part 111 of Schedule 9 to the Act hereby make the following Order: - 
1. This Order may be cited as West Dunbartonshire Council (Linnvale) (20mph Speed Limit)
Order 202[] and shall come into operation on the [DATE].
2. The Interpretation Act 1978 shall apply for the interpretation of this Order as it applies for the
interpretation of an Act of Parliament.
3. No person shall drive a motor vehicle on any lengths of roads specified in the Schedule to this
Order at a speed exceeding 20 miles per hour.
4. The Order will apply only when such a restriction is identified as applying to that road by
means of the display of appropriate traffic signs as prescribed by the Traffic Signs
Regulations and General Directions 2016.
5. This Order shall have effect subject to the following variations of existing orders: 
The provisions of any existing orders whether made or having effect as if made under the
Road Traffic Regulation Act 1984, as amended, or under any other enactment are hereby
varied to the extent that the provisions are inconsistent with this Order. 
SIGNED at WEST DUNBARTONSHIRE on the X day of X TWO THOUSAND AND TWENTY FIVE. 
Chief Officer
Roads and Neighbourhood Services
Council Offices
Church Street
Dumbarton G82 1QL 
Page 139

Page 140

Official
SCHEDULE 
The effect of the Order is as follows: 
No person shall drive or cause or permit any vehicle to be driven at a speed in excess of 20mph on
the lengths of road in West Dunbartonshire specified in the table below:
SCHEDULE
Name Extents 
Attlee Avenue For its entire length
Bevin Avenue For its entire length
Cripps Avenue For its entire length
Dalton Avenue For its entire length
Greenwood Quadrant For its entire length
Jowitt Avenue For its entire length
Kirkwood Avenue For its entire length
Livingstone Street For its entire length
McNeil Avenue For its entire length
Morrison Quadrant For its entire length
Shinwell Avenue For its entire length
Silkin Avenue For its entire length
Strauss Avenue For its entire length
Westwood Quadrant For its entire length 
Page 140

Page 141

Official
THE WEST DUNBARTONSHIRE COUNCIL
WEST DUNBARTONSHIRE COUNCIL (MILTON) (20MPH SPEED LIMIT) ORDER 202[] 
West Dunbartonshire Council in exercise of the powers conferred on them by Section 84(1)(a) of the 
Road Traffic Regulation Act 1984 (which Act of 1984 is herein referred to as “the said Act”) and all
other powers enabling them in that behalf and after consultation with the Chief Constable in
accordance with Part 111 of Schedule 9 to the Act hereby make the following Order: - 
1. This Order may be cited as West Dunbartonshire Council (Milton) (20mph Speed Limit) Order
202[] and shall come into operation on the [DATE].
2. The Interpretation Act 1978 shall apply for the interpretation of this Order as it applies for the
interpretation of an Act of Parliament.
3. No person shall drive a motor vehicle on any lengths of roads specified in the Schedule to this
Order at a speed exceeding 20 miles per hour.
4. The Order will apply only when such a restriction is identified as applying to that road by
means of the display of appropriate traffic signs as prescribed by the Traffic Signs
Regulations and General Directions 2016.
5. This Order shall have effect subject to the following variations of existing orders: 
The provisions of any existing orders whether made or having effect as if made under the
Road Traffic Regulation Act 1984, as amended, or under any other enactment are hereby
varied to the extent that the provisions are inconsistent with this Order. 
SIGNED at WEST DUNBARTONSHIRE on the X day of X TWO THOUSAND AND TWENTY FIVE. 
Chief Officer
Roads and Neighbourhood Services
Council Offices
Church Street
Dumbarton G82 1QL 
Page 141

Page 142

Official
SCHEDULE 
The effect of the Order is as follows: 
No person shall drive or cause or permit any vehicle to be driven at a speed in excess of 20mph on
the lengths of road in West Dunbartonshire specified in the table below: 
SCHEDULE
Name Extents 
Colquhoun Road For its entire length
Crannog Road For its entire length
Hillview For its entire length
Lennox Road For its entire length
Milton Brae From a point 25 metres or thereby north of its
western extended kerb line with (A82)
Dumbarton Rd in a northern direction, for a
distance of 380 metres or thereby.
Milton Court For its entire length
Whyte Corner For its entire length 
Page 142

Page 143

Official
THE WEST DUNBARTONSHIRE COUNCIL
WEST DUNBARTONSHIRE COUNCIL (SILVERTON) (20MPH SPEED LIMIT) ORDER 202[] 
West Dunbartonshire Council in exercise of the powers conferred on them by Section 84(1)(a) of the 
Road Traffic Regulation Act 1984 (which Act of 1984 is herein referred to as “the said Act”) and all
other powers enabling them in that behalf and after consultation with the Chief Constable in
accordance with Part 111 of Schedule 9 to the Act hereby make the following Order: - 
1. This Order may be cited as West Dunbartonshire Council (Silverton) (20mph Speed Limit)
Order 202[] and shall come into operation on the [DATE].
2. The Interpretation Act 1978 shall apply for the interpretation of this Order as it applies for the
interpretation of an Act of Parliament.
3. No person shall drive a motor vehicle on any lengths of roads specified in the Schedule to this
Order at a speed exceeding 20 miles per hour.
4. The Order will apply only when such a restriction is identified as applying to that road by
means of the display of appropriate traffic signs as prescribed by the Traffic Signs
Regulations and General Directions 2016.
5. This Order shall have effect subject to the following variations of existing orders: 
The provisions of any existing orders whether made or having effect as if made under the
Road Traffic Regulation Act 1984, as amended, or under any other enactment are hereby
varied to the extent that the provisions are inconsistent with this Order. 
SIGNED at WEST DUNBARTONSHIRE on the X day of X TWO THOUSAND AND TWENTY FIVE. 
Chief Officer
Roads and Neighbourhood Services
Council Offices
Church Street
Dumbarton G82 1QL 
Page 143

Page 144

Official
SCHEDULE 
The effect of the Order is as follows: 
No person shall drive or cause or permit any vehicle to be driven at a speed in excess of 20mph on
the lengths of road in West Dunbartonshire specified in the table below:
SCHEDULE
Name Extents 
Alclutha Avenue For its entire length
Alexander Street For its entire length
Barloan Crescent For its entire length
Boghead Avenue For its entire length
Boghead Road For its entire length
Broomfauld Gardens For its entire length
Colquhoun Street For its entire length
Crosslet Place For its entire length
Crosslet Road For its entire length
Douglas Road For its entire length
Doveholm Avenue For its entire length
Dumbuck Road For its entire length
Dumbuie Avenue For its entire length
Dunbrittion Road For its entire length
Gibson Avenue For its entire length
Gibson Street For its entire length
Greenhead Avenue For its entire length
Hartfield Court For its entire length
Kilpatrick View For its entire length
Latta Street For its entire length
Lennox Road For its entire length
Millburn Crescent For its entire length
Millburn Road For its entire length
Miller Court For its entire length
Miller Street For its entire length
Netherbog Avenue For its entire length
Netherbog Road For its entire length
Overtoun Avenue For its entire length
Overwood Drive For its entire length
Overwood Grove For its entire length
Park Avenue For its entire length
Park Street For its entire length
Round Riding Road For its entire length
Silverton Avenue For its entire length
Smollett Road For its entire length
Strowan’s Road For its entire length
White Avenue For its entire length
Willox Park For its entire length 
Page 144

Page 145

Official 
Page 145

Page 146

Official 
APPENDIX 2
STATEMENT OF REASONS
THE WEST DUNBARTONSHIRE COUNCIL
ROAD TRAFFIC REGULATION ACT 1984 
It is considered necessary to make the above-named Order to -
• Reduce vehicle speeds and enhance road safety for all users within West
Dunbartonshire, particularly pedestrians and cyclists
• Support active travel
• Reduce the severity and likelihood of collisions
The proposed speed limit aligns with Scottish Government’s National 20mph Strategy. 
ITEM 11 - APPENDIX 2
Page 146

Page 147

WEST DUNBARTONSHIRE COUNCIL 
Report by Chief Officer - Resources 
Infrastructure, Regeneration & Economic Development Committee: 
22 May 2026
___________________________________________________________________ 
Subject:  Infrastructure, Regeneration & Economic Development Revenue
Budgetary Control Report 2025/26 to Period 10 (31 January 2026) 
1. Purpose 
1.1 This report provides an update on the revenue financial performance to 31
January 2026 of those services under the auspices of the Infrastructure,
Regeneration & Economic Development Committee (IRED). 
2.  Recommendations 
2.1 Members are asked to: 
• note a projected adverse variance against budget of £0.478m (2.77%
of total budget).
• note the current projected use of earmarked reserves of £0.504m. 
3. Background 
Revenue 
3.1 The revised 2025/26 revenue budget presented to Committee in January was
£17.243m. Since then, changes worth £0.001m have been agreed to the
budget which revises the 2025/26 budget as follows: 
£m
Budget as at Period 7 17.243
Minor Change  0.001
Revised Budget 17.244 
4. Main Issues 
Revenue Budget
4.1 The summary report at Appendix 1 identifies a projected adverse variance
(overspend) of £0.478m (2.77% of total budget). Detailed service reports are
attached at Appendix 2. 
4.2 Of the 13 services monitored 7 are showing either a favourable or nil variance,
with 6 showing an adverse variance. Comments are provided in Appendix 3
when projected net annual variances exceed £0.050m or where the net
variance is below £0.050m but there are offsetting variances of over £0.050m. 
ITEM 12
Page 147

Page 148

The table below shows the main reasons for the movement in the outturn
since period 7. 
£m £m
Variance at Period 7  0.416
Movement in Service Variance  
Roads, Neighbourhood and Transport  
Roads
• Increase in contract payments for roadworks 
Crematorium
• Reduction in anticipated cremation income 
Burial Grounds
• Additional burial income
Grounds Maintenance
• Reduction in employee costs due to vacancies
• Additional water rates payments
• Additional equipment required to undertaken
required services
Outdoor Services
• Credits received for electricity bills
Waste Services
• Reduction in waste collection costs 
0.068 
0.024 
(0.045) 
(0.207)
0.028 
0.060 
(0.072) 
(0.042) 
Resources  
Asset Management
• Costs relating Storm Eowyn  0.262 
Other small variances across the Services (0.014) 
Total Movement in Service Delivery variance     0.062
General Fund variance at Period 7      0.478 
4.3 Services are anticipating the use of £0.504m (Period 7: £0.504m) of
earmarked reserves. Information on the earmarked reserve spend is shown in
Appendix 4.  
4.4 A list of agreed efficiencies and management adjustments totalling £3.011m is
shown within Appendix 5. Current indications show that £2.633m is on target
to be achieved.  However, Appendix 6 also shows that it is anticipated that
£0.378m will not be achieved and will be funded by the smoothing fund. 
5. People Implications 
5.1 There are no people implications. 
6. Financial Implications 
Page 148

Page 149

6.1 Other than the financial position noted above, there are no financial
implications of the budgetary control report. Officers are currently reviewing
budgets and projections with a view to improving the position by financial year
end and progress will be highlighted in future reports to committee. 
7. Risk Analysis 
7.1 The present variances should be viewed in the knowledge that there are a
number of variable factors which could arise between now and 31 March and
which could affect the year end results. 
8. Equalities Impact Assessment (EIA) 
8.1 The report is for noting and therefore no Equalities Impact Assessment was
completed for this report. 
9 Consultation 
9.1 The views of both Finance and Legal services have been requested on this
report and both have advised there are neither any issues nor concerns with
the proposal. As the report is for noting no further consultation is envisaged. 
10. Strategic Assessment 
10.1 Proper budgetary control and sound financial practice are cornerstones of
good governance and support Council and officers to pursue the five strategic
priorities of the Council’s Strategic Plan. This report forms part of the financial
governance of the Council. This report is for noting and, therefore, does not
directly affect any of the strategic priorities. 
Laurence Slavin
Chief Officer – Resources  
Date:  16 April 2026 
Person to Contact:  Jackie Thomson - Business Unit Finance Partner, 16 Church
Street, Dumbarton, G81 1QL.
e-mail jackie.nicolthomson@west-dunbarton.gov.uk   
Appendices:  Appendix 1 - Summary Budgetary Position (Revenue)                                
Appendix 2 - Detailed Budgetary Position Revenue)                                
Appendix 3 - Variance Analysis (Revenue)                                
Appendix 4 - Earmarked Balances
Appendix 5 - Efficiencies & Management Adjustments           
Background Papers:  None 
Page 149

Page 150

Wards Affected:  All 
Page 150

Page 151

WEST DUNBARTONSHIRE COUNCIL
REVENUE BUDGETARY CONTROL 2025/26
IRED SUMMARY
MONTH END DATE 31 January 2026
Total Budget
2025/26
Spend to
Date 2025/26
Forecast
Spend
2025/26
Annual
RAG
Status
Net Variance
attributable to
earmarked
reserves spend
Underlying
Variance
excluding
earmarked
reserves spend
£000 £000 £000 £000 % £000 £000
(55) 145 (55) 0 0%  0 0
(99) (177) 0 99 -100%  0 99
2,397 3,396 2,575 178 7%  150 28
300 133 278 (22) -7%  0 (22)
(245) (536) (241) 4 -2%  0 4
(1,072) (566) (884) 189 -18%  0 189
10,074 7,622 10,157 82 1%  0 82
(2,029) 4,145 (1,303) 727 -36%  228 499
1,204 1,301 1,123 (81) -7%  0 (81)
0 518 0 0 0%  0 0
2,039 2,227 1,959 (80) -4%  110 (190)
0 790 0 0 0%  0 0
4,731 5,423 4,617 (114) -2%  16 (130)
17,244 24,421 18,226 982 5.70%  504 478
Working 4 U
Shared Prosperity Fund
Roads Services
Outdoor Services
Burial Grounds
Crematorium
Waste Services
Corporate Assets
Economic Development
Ground Maintenance & Street Cleaning
Total Net Expenditure
Depots
Transport, Fleet & Maintenance Services
Service / Subjective Summary Annual Variance 2025/26
Corporate Asset Maintenance
ITEM 12 - APPENDIX 1
Page 151

Page 152

WEST DUNBARTONSHIRE COUNCIL
REVENUE BUDGETARY CONTROL 2025/26
IRED COMMITTEE DETAIL
PERIOD END DATE 31 January 2026
10
Actual
Outturn
2024/25
Total
Budget
2025/26
Spend to
Date 2025/26
Forecast
Spend
2025/26
Use of
Earmarked
Reserves
Variance after the
use of Earmarked
Reserves
Annual
RAG
Status
£000 £000 £000 £000 £000 % £000 £000
18,087 Employee 22,511 17,712 21,374 (1,138) -5% 0 (1,138) 
5,028 Property 4,587 3,337 4,743 156 3% 0 156 
5,494 Transport and Plant 4,095 3,613 4,919 825 20% 0 825 
13,313 Supplies, Services and Admin 12,421 9,666 12,557 136 1% 16 120 
9,503 Payments to Other Bodies 4,279 2,367 4,689 410 10% 110 300 
1,670 Other 114 122 141 27 24% 0 27 
53,094 Gross Expenditure 48,008 36,817 48,424 416 1% 126 290 
(33,977) Income (30,764) (12,396) (30,197) 566 2% 378 188 
19,117 Net Expenditure 17,244 24,421 18,226 982 6% 504 478 
£000 £000 £000 £000 £000 % £000 £000
1,735 Employee 1,970 1,370 1,645 (325) -16% 0 (325) 
26 Property 18 24 29 11 61% 0 11 
127 Transport and Plant 131 113 135 4 3% 0 4 
1,873 Supplies, Services and Admin 1,308 1,095 1,176 (132) -10% 0 (132) 
0 Payments to Other Bodies 0 0 0 0 0% 0 0 
113 Other 114 95 114 0 0% 0 0 
3,874 Gross Expenditure 3,541 2,697 3,099 (442) -12% 0 (442) 
(3,885) Income (3,596) (2,552) (3,154) 442 12% 0 442 
(11) Net Expenditure (55) 145 (55) 0 0% 0 0 
£000 £000 £000 £000 £000 % £000 £000
2,024 Employee 2,163 1,905 2,306 144 7% 0 144 
108 Property 118 5 119 1 1% 0 1 
1,688 Transport and Plant 1,665 1,651 2,149 484 29% 0 484 
821 Supplies, Services and Admin 579 521 608 29 5% 0 29 
1 Payments to Other Bodies 0 0 0 (0) -2% 0 (0) 
0 Other 0 0 0 0 0% 0 0 
4,642 Gross Expenditure 4,524 4,082 5,182 658 15% 0 658 
(4,578) Income (4,624) (4,259) (5,182) (559) -12% 0 (559) 
64 Net Expenditure (99) (177) 0 99 -100% 0 99 
£000 £000 £000 £000 £000 % £000 £000
2,946 Employee 2,854 2,006 2,480 (373) -13% 0 (373) 
254 Property 261 182 281 20 8% 0 20 
890 Transport and Plant 384 421 703 319 83% 0 319 
3,104 Supplies, Services and Admin 2,730 1,935 2,965 235 9% 0 235 
893 Payments to Other Bodies 317 7 317 0 0% 0 0 
0 Other 0 0 0 0 0% 0 0 
8,088 Gross Expenditure 6,545 4,552 6,746 201 3% 0 201 
(4,194) Income (4,149) (1,156) (4,171) (23) -1% 150                 (173) 
3,894 Net Expenditure 2,397 3,396 2,575 178 7% 150 28 
Roads Services
Service Summary Annual Variance
2025/26
All Services
Corporate Asset Maintenance
Transport, Fleet & Maintenance Services
ITEM 12 - APPENDIX 2
Page 152

Page 153

WEST DUNBARTONSHIRE COUNCIL
REVENUE BUDGETARY CONTROL 2025/26
IRED COMMITTEE DETAIL
PERIOD END DATE 31 January 2026
10
Actual
Outturn
2024/25
Total
Budget
2025/26
Spend to
Date 2025/26
Forecast
Spend
2025/26
Use of
Earmarked
Reserves
Variance after the
use of Earmarked
Reserves
Annual
RAG
Status
Service Summary Annual Variance
2025/26
£000 £000 £000 £000 £000 % £000 £000
74 Employee 67 48 58 (9) -13% 0 (9) 
179 Property 156 52 107 (49) -31% 0 (49) 
0 Transport and Plant 0 0 0 0 0% 0 0 
144 Supplies, Services and Admin 117 81 161 43 37% 0 43 
17 Payments to Other Bodies 37 (0) 18 (19) -51% 0 (19) 
0 Other 0 0 0 0 0% 0 0 
414 Gross Expenditure 378 180 345 (33) -9% 0 (33) 
(117) Income (78) (47) (66) 12 15% 0 12 
298 Net Expenditure 300 133 278 (22) -7% 0 (22) 
£000 £000 £000 £000 £000 % £000 £000
0 Employee 0 0 0 0 0% 0 0 
29 Property 27 20 26 (1) -3% 0 (1) 
0 Transport and Plant 0 0 0 0 0% 0 0 
0 Supplies, Services and Admin 0 0 0 0 0% 0 0 
442 Payments to Other Bodies 486 0 486 0 0% 0 0 
0 Other 0 0 0 0 0% 0 0 
471 Gross Expenditure 513 20 512 (1) 0% 0 (1) 
(689) Income (758) (556) (753) 5 1% 0 5 
(218) Net Expenditure (245) (536) (241) 4 -2% 0 4 
£000 £000 £000 £000 £000 % £000 £000
215 Employee 194 186 222 29 15% 0 29 
265 Property 304 217 262 (41) -14% 0 (41) 
0 Transport and Plant 0 0 0 0 0% 0 0 
21 Supplies, Services and Admin 18 21 25 7 39% 0 7 
6 Payments to Other Bodies 18 18 18 0 0% 0 0 
0 Other 0 0 0 0 0% 0 0 
507 Gross Expenditure 534 442 528 (6) -1% 0 (6) 
(1,460) Income (1,606) (1,009) (1,412) 194 12% 0 194 
(952) Net Expenditure (1,072) (566) (884) 189 -18% 0 189 
£000 £000 £000 £000 £000 % £000 £000 
3,583 Employee 3,685 3,220 3,828 144 4% 0 144 
200 Property 182 55 207 25 14% 0 25 
1,504 Transport and Plant 1,294 1,033 1,337 43 3% 0 43 
6,503 Supplies, Services and Admin 6,775 5,222 6,710 (64) -1% 0 (64) 
27 Payments to Other Bodies 37 28 43 6 17% 0 6 
0 Other 0 0 0 0 0% 0 0 
11,817 Gross Expenditure 11,972 9,558 12,125 154 1% 0 154 
(1,362) Income (1,897) (1,936) (1,969) (71) -4% 0 (71) 
10,455 Net Expenditure 10,074 7,622 10,157 82 1% 0 82 
Burial Grounds
Waste Services
Outdoor Services
Crematorium
Page 153

Page 154

WEST DUNBARTONSHIRE COUNCIL
REVENUE BUDGETARY CONTROL 2025/26
IRED COMMITTEE DETAIL
PERIOD END DATE 31 January 2026
10
Actual
Outturn
2024/25
Total
Budget
2025/26
Spend to
Date 2025/26
Forecast
Spend
2025/26
Use of
Earmarked
Reserves
Variance after the
use of Earmarked
Reserves
Annual
RAG
Status
Service Summary Annual Variance
2025/26
£000 £000 £000 £000 £000 % £000 £000
864 Employee 1,377 1,005 1,226 (151) -11% 0 (151) 
2,401 Property 2,345 2,140 2,635 290 12% 0 290 
4 Transport and Plant 12 6 12 0 0% 0 0 
(19) Supplies, Services and Admin 27 121 (23) (50) -184% 0 (50) 
65 Payments to Other Bodies 60 52 136 76 128% 0 76 
0 Other 0 0 0 0 0% 0 0 
3,315 Gross Expenditure 3,821 3,324 3,987 166 4% 0 166 
(5,065) Income (5,850) 821 (5,289) 561 10% 228                 333 
(1,750) Net Expenditure (2,029) 4,145 (1,303) 727 -36% 228 499 
£000 £000 £000 £000 £000 % £000 £000
620 Employee 1,114 832 986 (128) -11% 0 (128) 
489 Property 41 29 29 (12) -30% 0 (12) 
2 Transport and Plant 5 2 3 (3) -47% 0 (3) 
13 Supplies, Services and Admin 112 43 127 15 13% 0 15 
618 Payments to Other Bodies 550 494 562 11 2% 0 11 
0 Other 0 0 0 0 0% 0 0 
1,743 Gross Expenditure 1,823 1,399 1,706 (117) -6% 0 (117) 
(976) Income (619) (99) (583) 36 6% 0 36 
767 Net Expenditure 1,204 1,301 1,123 (81) -7% 0 (81) 
£000 £000 £000 £000 £000 % £000 £000
0 Employee 0 0 0 0 0% 0 0 
657 Property 759 517 647 (112) -15% 0 (112) 
0 Transport and Plant 0 0 0 0 0% 0 0 
(1) Supplies, Services and Admin 15 1 3 (12) -78% 0 (12) 
0 Payments to Other Bodies 0 0 0 0 0% 0 0 
0 Other 0 0 0 0 0% 0 0 
656 Gross Expenditure 774 518 651 (123) -16% 0 (123) 
(656) Income (774) 0 (651) 123 16% 0 123 
(0) Net Expenditure 0 518 0 0 0% 0 0 
£000 £000 £000 £000 £000 % £000 £000
2,422 Employee 2,885 2,162 2,624 (261) -9% 0 (261) 
Property 0 0 0 0 0% 0 0 
11 Transport and Plant 20 7 14 (5) -27% 0 (5) 
50 Supplies, Services and Admin 45 17 49 5 11% 0 5 
1,766 Payments to Other Bodies 1,695 1,429 2,011 316 19% 110                 206 
178 Other 0 27 27 27 0% 0 27 
4,427 Gross Expenditure 4,644 3,642 4,726 82 2% 110 (28) 
(2,428) Income (2,605) (1,415) (2,767) (162) -6% 0 (162) 
1,999 Net Expenditure 2,039 2,227 1,959 (80) -4% 110 (190) 
£000 £000 £000 £000 £000 % £000 £000
634 Employee 616 482 616 0 0% 0 0 
Property 0 0 0 0 0% 0 0 
2 Transport and Plant 0 2 0 0 0% 0 0 
26 Supplies, Services and Admin 0 1 0 0 0% 0 0 
2,149 Payments to Other Bodies 1,079 320 1,079 0 0% 0 0 
0 Other 0 0 0% 0 0 
2,811 Gross Expenditure 1,695 805 1,695 0 0% 0 0 
(2,811) Income (1,695) (15) (1,695) 0 0% 0 0 
(0) Net Expenditure 0 790 0 0 0% 0 0 
Economic Development
Depots
Corporate Assets
Working 4 U
Shared Prosperity Fund
Page 154

Page 155

WEST DUNBARTONSHIRE COUNCIL
REVENUE BUDGETARY CONTROL 2025/26
IRED COMMITTEE DETAIL
PERIOD END DATE 31 January 2026
10
Actual
Outturn
2024/25
Total
Budget
2025/26
Spend to
Date 2025/26
Forecast
Spend
2025/26
Use of
Earmarked
Reserves
Variance after the
use of Earmarked
Reserves
Annual
RAG
Status
Service Summary Annual Variance
2025/26
£000 £000 £000 £000 £000 % £000 £000
6,003 Employee 5,588 4,496 5,381 (207) -4% 0 (207) 
419 Property 377 96 401 23 6% 0 23 
957 Transport and Plant 584 378 565 (18) -3% 0 (18) 
852 Supplies, Services and Admin 695 608 755 60 9% 16                   44 
19 Payments to Other Bodies 0 19 19 19 0% 0 19 
718 Other 0 0 0 0 0% 0 0 
8,968 Gross Expenditure 7,244 5,598 7,121 (123) -2% 16 (139) 
(10,997) Income (2,513) (175) (2,504) 9 0% 0 9 
(2,029) Net Expenditure 4,731 5,423 4,617 (114) -2% 16 (130) 
Ground Maintenance & Street Cleaning
Page 155

Page 156

WEST DUNBARTONSHIRE COUNCIL
REVENUE BUDGETARY CONTROL 2025/26
ANALYSIS FOR VARIANCES OVER £50,000
PERIOD END DATE
Variance Analysis
Total Budget Projected
Spend Use of EMR RAG Status
£000 £000 £000 £000 %
Transport, Fleet & Maintenance Services (99) 0 0 99 -100%
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Roads Services 2,397 2,575 178 7% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Crematorium (1,072) (884) 0 189 0% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Waste Services 10,074 10,157 0 82 0% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Variance after the use of
EMR
Budget Details
Overspend anticipated.
This service provides crematorium services within the Council area
Employee costs are overspending (£29k) due to non achievement of turnover savings. Property
costs are showing a favourable variance (£41k) due to utility costs being lowered than
anticipated and income from cremations is anticipated to be £194k less than budgeted mainly
due to a new crematorium recently opened in East Dunbartonshire. This budget is
uncontrollable and may change throughout the year. The remainder of the variance (£7k) is due
to small variances within the service.
The Service will continue to monitor and review costs and reduce overspends as appropriate.
31 January 2026
Employee costs are underspending by anticipated to underspend by £373k due to current levels
of vacancies. Transport and plant are anticipating overspending of £319k due to the current
vehicles on hire to ensure that planned works are undertaken and supplies and services are
projecting an overspend of £235k mainly due to materials required to undertake planned works
Transport services across WDC.
Transport Services is operated on behalf of services across the Council. An under recovery on
income is anticipated as while the service fully allocates all costs out to appropriate services
there is currently a mis-alignment between the expenditure and income budgets. A cost
pressure was agreed at Council 17 December to rectify this from 2026/27 budget.
None available as cannot recharge out more than the service costs to run.
Under recovery of income anticipated.
Waste Collection and Refuse disposal services
The Service will continue to monitor and review costs and reduce overspends as appropriate.
Employee costs are anticipated to overspend by £144k mainly due to turnover not being met.
Property Costs are overspending by £25K due to an increase in Pest Control visits required at
Recycling Centres and an increase in Electricity costs due to Compactors at Recycling Centres.
Transport Costs are currently overspending by £43K due to repairs and maintenance required
on vehicles.The overspends are partially offset by an underspend in Supplies of £64k mainly
due to anticipated reduction in the costs for tonnage in relation to waste collection and £71K
additional Income manly due to Brown Bin Waste Permits. The remaining £5k variance is due to
small variances throughout the service.
This service relates to Roads operations, design, structures, street lighting, road safety and
school crossing patrols
The Service will continue to monitor and review costs and reduce overspends as appropriate.
Overspend anticipated.
Overspend anticipated.
ITEM 12 - APPENDIX 3
Page 156

Page 157

WEST DUNBARTONSHIRE COUNCIL APPENDIX 3
REVENUE BUDGETARY CONTROL 2025/26
ANALYSIS FOR VARIANCES OVER £50,000
PERIOD END DATE
Budget Details
31 January 2026
Corporate Assets (2,029) (1,303) 228 499 -25% 
Service Description This service provides asset and estate management
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Economic Development 1,204 1,123 0 (81) -7% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Working 4 U 2,039 1,959 (196) (276) -10% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Ground Maintenance & Street Cleaning 4,731               4,617               0 (114) -2%
Service Description Provision of grounds maintenance and street cleaning services
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome An underspend is anticipated at the year end.
Employee costs are underspending by £207k mainly due to current levels of vacancies. Property
costs are expected to overspend of £23k driven mainly by higher than anticipated water rates. 
Transport costs are anticipating to underspend overall due to lower costs for Hiring of Vehicles
(£51k) and lower fuel costs (£55k), These underspends are partially offset by a projected
overspend of £64k in Fleet Maintenance and £25k in leasing charges. Supplies and services are
expected to overspend by £60k, mainly due to payments being made for tools and equipment,.
The remaining variance of £27k is due to small overspends in various areas.
The Service will continue to monitor and review costs and reduce overspends as appropriate.
£250k adverse variance due to asset rationalisation, with property disposals that were previously
rental‑income‑generating now contributing capital receipts to the wider budget position.
The variance also now reflects £262k of Storm Eowyn damage, which cannot be absorbed
within the remaining repairs and maintenance budget due to the scale of the works.
An ongoing cost pressure of £50k has been introduced for future years due to higher property
valuation costs. Employee turnover savings are mitigating the rise in Property costs linked to last
year’s increases.
The Service will continue to monitor and review costs and reduce overspends as appropriate.
Overspend anticipated.
Underspend is anticipated.
The favourable variance is mainly attributable to employee costs anticipating an underspend of
(£128k). This is due to superannuation costs being lower than budgeted and current staff
vacancies. This is partially off-set by a reduction in income( £36k).The remaining (£11k) is due
to small variances in the service.
The Service will continue to monitor and review costs.
This service relates to Economic Development within West Dunbartonshire
Provision of Working 4U Service.
The underspend  is mainly due to employee costs as a result of achieving savings within the
current financial year and in year vacancies. The service received additional in year funding
which offsets employee costs
None Required
Favourable variance anticipated.
Page 157

Page 158

WEST DUNBARTONSHIRE COUNCIL
MONITORING OF EARMARKED BALANCES 2025/26 BY CHIEF OFFICER
DEPARTMENT  Amount b/fwd
into 25/26 from
24/25 
25/26
Transfers
in/(Out)  
25/26 Estimate  25/26        
Spend to Date 
25/26 Probable
Outturn 
25/26 to be
released 
To be carried
forward into
26/27 
Description 
£  £  £  £  £  £  £
13 Modern Apprentice 23/24 underspend 177,494             177,494                 -                     -                     177,494             The Balance will be used as part of the four year modern apprenticeship programme to cover payment across financial years.   The funding
will be fully utilised in year five of the programme.           
16 Set up a an energy Household Energy Support Fund using
£250,000
15,990               15,990                   12,000               12,000               3,990                  Fund set up to support residents who require crisis support to ensure their properties remain heated.
19 Cost of Living 3: Additional Support for Apprenticeships. £50,000
per year for 4 years.
150,000             150,000                 50,000               50,000               100,000              The Apprenticeship Investment Programme being part of a broader programme which is over a four year period. Payments can cover more
than one financial year and therefore the reserves ensures continuity of the programme.
21 Cost of Living 6: Transitional Funding Support to Y-Sort-It over 4
years. £39,000 per year
78,000               78,000                   39,000               39,000               39,000                Transitional funding support for Y-Sort It over a four year period to give them time to secure external funding.
23 Provide £ 64,000 for family fund day events in 2023/24 and the
following three years (approx 32 events at £2,000 per event)
32,000               32,000                   16,000               16,000               16,000                Provision of Family fun days within West Dunbartonshire Council over a four year period This is year three of the four years and therefore
£16k will be carried forward inot 2026/27 to be used.
25 £12k over 3years to Renton Community Food Hub from April 2024
to March 2028 (formerly Tontine Food Parcels)
9,000                 9,000                      3,000                 3,000                 6,000                  Subsidy provided to food banks over a three year period to asist with the provision of food parcels.
26 £12k over 3 years to Lomond Food Pantry from April 2024 to
March 2028
9,000                 9,000                      3,000                 3,000                 6,000                  Subsidy provided to food banks over a three year period to asist with the provision of food parcels.
27 £12k over 3 years to Time for Tully from April 2024 to March 2028 9,000                 9,000                      3,000                 3,000                 6,000                  Subsidy provided to food banks over a three year period to asist with the provision of food parcels.
TOTAL USE OF SERVICE RESERVES              480,484                         -                     480,484               126,000               126,000                         -                 354,484
29 Smoothing Fund - Corproate Assets -                     -                     228,000                 -                     228,000             -                     -                     This is part of the overall council smoothing fund and is being used to cover savings options not being fully achieved in 2025/26 for
caretakers restructrure (RES008) and office rationalisation (SDP05)
30 Smoothing Fund - Roads -                     -                     150,000                 -                     150,000             -                     -                     This is part of the overall council smoothing fund and is being used to cover savings options not being fully achieved in 2025/26 for parking
enforecment (RN05)
TOTAL USE OF STRATEGIC RESERVES                        -                           -                     378,000                         -                 378,000                         -   -                     
TOTAL USE OF EARMARKED RESERVES               480,484                         -                     858,484               126,000               504,000                         -                 354,484
STRATEGIC RESERVES
COST OF LIVING
ROADS & NEIGHBOURHOOD
ITEM 12 - APPENDIX 4
Page 158

Page 159

WEST DUNBARTONSHIRE COUNCIL
MONITORING OF EFFICIENCIES AND MANAGEMENT ADJUSTMENTS 2025/26
Efficiency Detail Ref Chief Officer
Budgeted
Amount      
£000 
Projection of
Total Saved      
£000 
Projection of
Total Not Saved       
£000 Comment
Parking Enforcement RN05 G Macfarlane 325 175 150
The implementation of DPE commenced a soft roll out in
October with tickets being issued from November.There
will be a part year income and therefore the use of the
smoothing fund is required for the period of the year
before DPE is in place.
Office/ Depot Rationalisation SDP05 L Slavin 380 176 204
Relates to two properties (Kilbowie Road and Elm road
where tenants have yet to be identified.   24/25 shortfall to
be funded from the smoothing fund.  A review has been
undertaken and a cost pressure has been added to the
budget for 2026/27.
Electric Vehicle Charging RN13 G Macfarlane 11                      11                      -                        complete
School crossing patrollers - adhere to best practice RN01 G Macfarlane 25                      25                      -                        complete
Introduce £60 Garden Waste Charge RN02 G Macfarlane 180                   180                    -                        complete
Amend roads service activities to support education to statutory level RN04 G Macfarlane 37                      37                      -                        complete
Reduce the Consultancy Services/Capital Investment Team by 25% RN18 G Macfarlane 15                      15                      -                        complete
Reduce the roads operations service from 29 FTE to 26 FTE which will reduce
resilience in the team RN21 G Macfarlane 60                      60                      -                        complete
Reduce maintenance costs through replacing 6 under utilised grass pitches with
3 new 4G pitches
RN22(24-
25 option) G Macfarlane 50                      50                      -                       
Not complete, planning approval process underway and if
approved will issue  tender. 
Structural Patching RN23 G Macfarlane 50                      50                      -                        Complete
Review compliance with Strategic Opening Model to identify areas where teams
or posts can be merged CCF26 G Macfarlane 50                      50                      -                        Not currently progressed, reviewing options for delivery.
Review Allotment charges RN03 G Macfarlane 5                        5                         -                        Complete, charges updated April 25
Special Uplift Charge RN26 G Macfarlane 22                      22                      -                        Complete, charges updated April 25
Stopping Saturday burials RN01 G Macfarlane 10                      10                      -                        Complete
Capitalise Play Park Fitter RN07 G Macfarlane 40                      40                      -                        Complete
Further replacement of hire vehicles RN09 G Macfarlane 171                   171                    -                       
Vehicles have been procured and are expected to arrive late
Summer
Reduce Working4U service by 50% HE02 G Macfarlane 206                   206                    -                        complete
School Crossing Patrollers -Retain 17 Crossing Patrollers RN17 G Macfarlane 23                      23                      -                        Underway, 2 locations still to be resolved
Review or remove provision of footway gritting - Cease Footway Gritting RN18 G Macfarlane 68                      68                      -                        complete
Close or reduce Dalmuir golf course - Close completely RN20 G Macfarlane 184                   184                    -                        Completed
Cease the Care of Gardens scheme RN21 G Macfarlane 143                   143                    -                        Complete
Review levels of street cleaning - Reduce by 2 staff
RN22
(2025-26
option) G Macfarlane 26                      26                      -                        Complete
Review of park maintenance RN24 G Macfarlane 60                      60                      -                        Complete
2023/24 Efficiencies not achieved
2025/26 Efficiencies and Management Adjustments
ITEM 12 - APPENDIX 5
Page 159

Page 160

WEST DUNBARTONSHIRE COUNCIL APPENDIX 5
MONITORING OF EFFICIENCIES AND MANAGEMENT ADJUSTMENTS 2025/26
Efficiency Detail Ref Chief Officer
Budgeted
Amount      
£000 
Projection of
Total Saved      
£000 
Projection of
Total Not Saved       
£000 Comment
Remove open space maintenance on non council land RN28 G Macfarlane 20                      20                      -                        Complete
Review Event Support by Grounds Service RN29 G Macfarlane 15                      15                      -                        Complete. Costs will be recharged to event organisers
Road Network & Capital Management Reduction RN30 G Macfarlane 50                      50                      -                       
Part complete, 0.6FTE reduction with further employee
reduction being assessed
Review Winter Plan RN31 G Macfarlane 55                      55                      -                        Complete, Plan approved.
Reduce Grass Cutting RN35 G Macfarlane 150                   150                    -                        Complete
Review Footway Gritting Operational Method RN14 G Macfarlane 60                      60                      -                        Complete
Historical Lease Review RES13 L Slavin 44                      44                      -                        Saving anticipated to be achieved
Remove one Council officer RES09 L Slavin 8                        8                         -                        Saving anticipated to be achieved
Reduce number of caretakers RES08 L Slavin 24                      -                     24                          Saving cannot be realised due to full salary recharge.
Income Generation through Commercialisation RES09 L Slavin 15                      15                      -                        Saving anticipated to be achieved
Further asset rationalisation SDP04 L Slavin 99                      99                      -                        Saving anticipated to be achieved
External Consultancy Income SDP09 L Slavin 25                      25                      -                        Saving anticipated to be achieved
Review of charges for use of offices by external parties RES09 L Slavin 7                        7                         -                        Saving anticipated to be achieved
Historical lease review RES13 L Slavin 15                      15                      -                        Saving anticipated to be achieved
Reduce size of Building Services RES15 L Slavin 228                   228                    -                        Saving anticipated to be achieved
Review Asset Management team RES19 L Slavin 55                      55                      -                        Saving anticipated to be achieved
TOTAL AGREED SAVINGS OPTIONS & MANAGEMENT ADJUSTMENTS 3,011                2,633                 378                      
Page 160

Page 161

WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer – Resources
Infrastructure, Regeneration & Economic Development Committee: 
20 May 2026
_________________________________________________________________ 
Subject: Infrastructure, Regeneration & Economic Development Capital
Budgetary Control Report 2025/26 31 January (Period 10) 
1. Purpose
1.1 This report provides an update on the capital financial performance to     
31 January 2026 of those services under the auspices of the Infrastructure,
Regeneration & Economic Development Committee (IRED). 
2. Recommendations
2.1 Committee is asked to: 
i) Note the current position of the 2025/26 IRED capital budget. 
ii) Note the revised completion dates in respect of 6 projects detailed in
appendix 2 reported to Council on 25 March 2026. 
iii) Note the reprofiling of 12 projects in appendix 3 reported to Council on
25 March 2026. 
3. Background 
3.1 On 5 March 2025 the Council approved the updated General Services Capital
Plan for 2025/26 to 2034/35. The three years from 2025/26 to 2027/28 were
approved in detail with the remaining years being indicative. The budget
agreed under the auspice of IRED Committee was £56.791m for 2025/26 and
£209.142m for the project life budget. 
4. Main Issues 
4.1 Exhibit 1 sets out the revised capital budget at period 7 as reported to Council
on 17 December 2025 and Committee 4 February 2026. 
Exhibit 1: Revised Capital Budget as at 30 October 2025. 
2025/26
(£m)
Project Life
(£m)
Capital Budget Agreed 5 March 2025 56.791 209.142
Updates reported to Committee on 13 August, 12
November and 4 February plus adjustments for
year-end carried forward balances 
3.432 9.371
Reprofiling reported to Committee on 13 August,
19 November and 4 February. (9.028) 0
Revised Capital Budget as at Period 7 51.195 218.513  
ITEM 13
Page 161

Page 162

4.2 Progress against the 2025/26 capital plan is detailed in: 
Appendix 1 – Project Life Summary by Chief Officer 
Appendix 2 – Off Track Projects 
Appendix 3 – Changes to Capital Plan for Noting 
Appendix 4 – All Approved Projects 
4.3 The overall programme summary report at Appendix 1 shows that planned
expenditure against the budget is currently on track. 
4.4 Appendix 2 highlights 6 projects currently showing as off-track, which is due to
revised completion dates. 
• Project RES 6 (Strathleven Place) is off track as it is dependent on the
completion of a linked project that has not yet reached its required
milestones. 
• Project RES 7 (New Sports Changing Facility Dumbarton West) is off
track due to dependency on the adjacent housing development which
has not progressed in line with the original programme. 
• Project RR 6 (Place Based Investment Programme) is off track due to a
project development and tendering taking longer than anticipated 
• Project RR8 (Levelling Up Capacity Funding) is off track as the delivery
of the LUF programme is taking longer than originally anticipated. 
• Project RN 20 (Balloch Mountain Bike Track) is off track due to
identifying a suitable site to satisfy planning and ecological concerns. 
• Project RN 33 (Shared Prosperity Funding – Open Places) is off track
as the contract award has been extended to September 2026. 
4.5  Appendix 3 highlights 12 projects where the project expenditure requires to be
reprofiled but there is no need for approval of additional budget. 
4.6 Exhibit 2 sets out the revised IRED capital budget at period 10 factoring in the
decisions taken by Council on 17 December 2025. 
Exhibit 2: Revised Capital Budget 
2025/26
(£m)
Project Life
(£m)
Capital Budget as at 30 October 2025 51.195 218.513
New Funding – RR 13 Pride in Place Impact
Fund (Para 4.9)
0.750 1.500
Approved Gruggies Burn Flood Alleviation
Scheme
(Para 4.10)
0 29.672
Approved review of capital programme (para
4.11)
(0.926) (5.331)
Page 162

Page 163

Project life removed (para 4.12)  (0.980)
Projects completed as at 31 January 2026 (para
4.13)
(0.097) (1.192)
Approved political savings with capital
implications 
0.453
Budget Agreed as at 4 March 2026 50.922 242.635
Reprofiling over project life (Appendix 3) (6.756) 0
Revised Capital Budget as at Period
10approved at Council25 March.
44.166 242.635 
4.8 Appendix 4 shows all projects with approved in year and project life budgets
as well anticipated expenditure. It highlights that the 2025/26 budget is
£50.922m. Spend as at period 10 is £21.370m (48.38%) of the current
forecast spend of £44.166m. 
4.9  Other minor changes to the capital plan included in the summarised plan in
appendix 4 are: 
• New funding from Scottish Government for Pride in Place Impact Fund (RR
13) of £0.750m in 2025/26 with a further £0.750m in 2026/27. 
4.10 Following the Gruggies Burn Flood Alleviation Scheme paper approved at
council on 17 December 2025 an additional £29.672m has been added to the
capital plan in RN 11. 
4.11 Following the Review of West Dunbartonshire Councils Capital Programme
paper approved at council on 17 December 2025 with one amendment per
the motion, the below changes have been applied to the capital plan: 
• Projects removed (total £2.139m):
o Installation of Solar PV at Clydebank Leisure Centre (RR 2) - £0.057m
o Leisure Energy Projects (RR 3) - £0.226m 
o Waste Transfer Station (RN 17) - £1.821m 
o Kilmaronock Cemetery Extension (RN 22) - £0.005m
o Securing Sites to make safe (RR 11) - £0.030m 
• Projects where budgets have been reduced (total £1.511m): 
o A813 Road Improvement Phase 1 (RN 9) - £0.121m 
o River Leven Flood Prevention Scheme (RN 12) - £0.420m 
o East End Park Resurfacing (RN 19) - £0.171m 
o Creation of 3 all new weather pitches (RN 23) - £0.799 
• Projects with reduced recurring budget allocation (total £1.681m) 
o Regeneration/Local Economic Development (RR 4) - £1.233m 
o Public non-adopted paths and roads (RN 13) - £0.448m 
4.12 Following the above adjustments, historic project life budgets for projects
completed and removed have been applied which reduces project life by
£0.980m
Page 163

Page 164

4.13 Additionally the below projects have been completed at 31 January 2026: 
o Vale of Leven Cemetery (RN 15) 
o East End Park Resurfacing (RN 19) 
4.13 As agreed in the Finance Update paper taken to council on 17 December
2025 3 Political savings options were approved by members which had capital
implications. These have been added to the capital plan in 2026/27. 
o CCTV Upgrade at Depots (RN 37) - £0.050m 
o Gully Motor Purchase (RN 38) - £0.275m 
o Purchase of 3 mini buses (added to RN 5 Vehicle Replacement) -
£0.128m 
5. Option Appraisal
5.1 No option appraisal was required for this report. 
6. People Implications
6.1 There are no people implications. 
7. Financial and Procurement Implications
7.1 The report notes the projected in-year financial position for capital budgets. 
8. Risk Analysis
8.1 The main risks are as follows: 
(a) The reported variances should be viewed in the knowledge that there
are a number of variable factors which could arise between now and 31
March which could affect the year end results for capital budgets. 
(b) As a consequence of current market conditions, inflation is at an all-time
high and interest rates continue to be volatile. To forecast for the full
year costs budget assumptions have been required. These assumptions
continue to change regularly and therefore it is likely the projected year
end budgetary position will change from that reported. 
9. Equalities Impact Assessment (EIA) 
9.1 No equalities impact assessment was required in relation to this report. 
10. Environmental Sustainability 
10.1 No assessment of environmental sustainability was required in relation to this
report. 
11. Consultation 
11.1 All services involved in delivering the capital budgets have been consulted in
the compilation of this report. 
Page 164

Page 165

12. Strategic Assessment 
12.1 Proper budgetary control and sound financial practice are cornerstones
of good governance and support Council and officers to pursue the
strategic priorities of the Council’s current Strategic Plan. This report
forms part of the financial governance of the Council. 
______________
Laurence Slavin
Chief Officer – Resources
Date: 16 April 2026 
Person to Contact: Jackie Nicol-Thomson
Council Offices, Church Street, Dumbarton  
E-mail: jackie.nicolthomson@west-dunbarton.gov.uk 
Appendices: Appendix 1 - Project Life Summary 
Appendix 2 - Off Track Projects
Appendix 3 - Changes to Capital Plan and Implications
Appendix 4 - All Projects Approved 
Background Papers:  General Services Capital Plan Update - Council 5 March        
2025 
Wards Affected       All Wards 
Page 165

Page 166

Official#
Summary at Period 10
Project Life
Budget
Project Life
Forecast
Spend
Project Life
Variance On Track Off Track
£'000 £'000 £'000
Resources 36,055             36,055            0 6                                     2
Regulatory and Regeneration 57,125             57,125            0 6                                     2
Roads and Neighbourhoods 149,455           149,455          0 31                                   2
Total 242,635           242,635          0 43 6
ITEM 13 - APPENDIX 1
Page 166

Page 167

Official#
Projects that are Off Track at Period 10
Service Project
Approved Project Life
Cost
Revised Project
Life Cost
Project Life
Variance
Initial Completion
Date
Revised
Completion Date
£'000 £'000 £'000
Resources RES 6 - Strathleven Place (formerly part of Glencairn House project)                                  1,590                      1,590                  -   31/03/2026 31/03/2027
Resources RES 7 - New Sports Changing Facility Dumbarton West (Old OLSP site)                                       349                         349                  -   31/03/2026 31/03/2027
Regulatory and Regeneration RR 6 - Place Based Investment Programme                                     775                         775                  -   31/03/2026 31/03/2027
Regulatory and Regeneration RR 8 - Levelling Up Capacity Funding 160                                                             160                  -   31/03/2026 31/03/2027
Roads and Neighbourhood RN 20 - Balloch Mountain Bike Track                                     443                         443                  -   31/03/2026 31/03/2027
Roads and Neighbourhood RN 33 - Shared Prosperity Funding - Open Places                                     396                         396                  -   31/03/2026 31/08/2026
Project Name: Project - RES 6 - Strathleven Place (formerly part of Glencairn House
project)
Project Manager: Michelle Lynn
Initial Completion End Date: 31/03/2026 Revised End Date: 31/03/2027
How was this project initially funded: Please Detail any additional funding:
Prudential Borrowing n/a
Why is the project classified as off track and what has caused the issues identified?
What action will be taken to rectify the position?
New Completion Date: 31/03/2027 Prudential Borrowing
What are the implications on the actions proposed?
Revenue Implications:-
Virement Implications:- n/a
Project Name: Project - RES 7 - New Sports Changing Facility Dumbarton West (Old OLSP
site) 
Project Manager: Michelle Lynn
Initial Completion End Date: 31/03/2026 Revised End Date: 31/03/2027
How was this project initially funded: Please Detail any additional funding:
Prudential Borrowing n/a
Why is the project classified as off track and what has caused the issues identified?
What action will be taken to rectify the position?
New Completion Date: 31/03/2027 Prudential Borrowing
What are the implications on the actions proposed?
Revenue Implications:-
Virement Implications:- n/a
n/a
Progress on this project has been delayed as it is dependent on the completion of a linked project that has not yet reached its required milestones. Key elements of the planned works cannot proceed until the preceding
project is finalised, resulting in unavoidable slippage to the project’s delivery timeline.  To ensure accurate financial planning and alignment with the revised programme, it is proposed that the associated budget be
reprofiled into the next financial year. This reprofiling will allow expenditure to be matched to the updated schedule and will support efficient delivery once the prerequisite project is completed.
Source of Funding:
n/a
Delivery of the sports changing facility has been delayed due to dependency on the adjacent housing development, which has not progressed in line with the original programme. The sequencing of works requires the
housing development to reach specific construction stages before site access, utilities connections, and shared infrastructure can be finalised for the changing facility.  As these prerequisite elements remain
incomplete, the project cannot move into its planned construction phase. This has resulted in unavoidable slippage, and expenditure originally profiled for the current financial year will not be incurred as expected.  It is
therefore proposed that the budget for the sports changing facility be reprofiled into the next financial year to reflect the revised delivery timeline. This approach maintains alignment between project milestones and
financial planning, ensuring that funding remains in place once the adjacent development has advanced sufficiently to allow works to proceed.  Officers will continue to monitor progress on the housing development
closely and will update the programme for the changing facility as soon as conditions permit.
Source of Funding:
ITEM 13 - APPENDIX 2
Page 167

Page 168

Official#
Project Name: Project - RR 6 - Place Based Investment Programme Project Manager: Magda Swider
Initial Completion End Date: 31/03/2026 Revised End Date: 31/03/2027
How was this project initially funded: Please Detail any additional funding:
External grant funding from UK Government n/a
Why is the project classified as off track and what has caused the issues identified?
What action will be taken to rectify the position?
New Completion Date: 31/03/2027 Scottish Government funding
What are the implications on the actions proposed?
Revenue Implications:-
Virement Implications:- n/a
Project Name: Project - RR 8 - Levelling Up Capacity Funding Project Manager: Magda Swider
Initial Completion End Date: 31/03/2026 Revised End Date: 31/03/2027
How was this project initially funded: Please Detail any additional funding:
External grant funding from UK Government n/a
Why is the project classified as off track and what has caused the issues identified?
What action will be taken to rectify the position?
New Completion Date: 31/03/2027 Scottish Government funding
What are the implications on the actions proposed?
Revenue Implications:-
Virement Implications:- n/a
Project Name: Project - RN 20 - Balloch Mountain Bike Track Project Manager: Ian Bain
Initial Completion End Date: 31/03/2026 Revised End Date: 31/03/2027
How was this project initially funded: Please Detail any additional funding:
External match funding from Sportscotland n/a
Why is the project classified as off track and what has caused the issues identified?
What action will be taken to rectify the position? n/a
New Completion Date: 31/03/2027 Sportscotland
What are the implications on the actions proposed?
Revenue Implications:-
Virement Implications:- n/a
Project development and tendering taking longer than anticipated.
Source of Funding:
n/a
Delivery of the LUF programme is taking longer than originally anticipated. This funding will be used towards the end o fthe LUF programme, or if any funding gap is identiified earlier.
Source of Funding:
n/a
Difficulty identifying a suitable site that satisfied planning and ecological concerns has delayed project progress.  Suitable site located and project to progress in 26/27.
Source of Funding:
n/a
Page 168

Page 169

Official#
Project Name: Project - RN 33 - Shared Prosperity Funding - Open Places Project Manager: Ian Bain
Initial Completion End Date: 31/03/2026 Revised End Date: 31/08/2026
How was this project initially funded: Please Detail any additional funding:
UK Shared Prosperity Capital Funding n/a
Why is the project classified as off track and what has caused the issues identified?
What action will be taken to rectify the position? n/a
New Completion Date: 31/08/2026 UK Shared Prosperity Capital Funding
What are the implications on the actions proposed?
Revenue Implications:-
Virement Implications:- n/a
n/a
The Contract award extended to September 2026. Two projects planned, Westbridge End Project to upgarde community space including playpark with procurement contract awarded and work expected to start before
end of March.  Second project involves development of Allotment Site at Overburn Avenue for which work has gone out to tender amd awaiting bids.
Source of Funding:
Page 169

Page 170

Official#
Changes to Capital Plan and Implications at P10
Project - RES 6 Initial End Date  Revised End Date Reprofiling Current Year  2026/27  2027/28  2028/29  2029/30  2030/31  2031/32  2032/33  2033/34  Total Capital Plan
£'000 £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000
Strathleven Place (formerly part of Glencairn House project) 1,590 0 0 0 0 0 0 0 0                      1,590
Strathleven Place (formerly part of Glencairn House project) Revised 31/03/2026 31/03/2027 1,590 0 1,590 0 0 0 0 0 0 0                      1,590
Explanation
Project - RES 7 Initial End Date  Revised End Date Reprofiling Current Year  2026/27  2027/28  2028/29  2029/30  2030/31  2031/32  2032/33  2033/34  Total Capital Plan
£'000 £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000
New Sports Changing Facility Dumbarton West (Old OLSP site)  340 0 0 0 0 0 0 0 0                         340
New Sports Changing Facility Dumbarton West (Old OLSP site)   Revised 31/03/2026 31/03/2027 340 0 340                         340
Explanation
Project - RES 10 Initial End Date  Revised End Date Reprofiling Current Year  2026/27  2027/28  2028/29  2029/30  2030/31  2031/32  2032/33  2033/34  Total Capital Plan
£'000 £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000
Depot Rationalisation 31/03/2027 31/03/2027 1,779 4,386 0 0 0 0 0 0 0                      6,165
Depot Rationalisation  Revised 1,279 500 5,665 0 0 0 0 0 0 0                      6,165
Explanation
Progress on this project has been delayed as it is dependent on the completion of a linked project that has not yet reached its required milestones. Key elements of the planned works cannot proceed until the preceding project is finalised, resulting in unavoidable slippage to the project’s delivery timeline.  To ensure
accurate financial planning and alignment with the revised programme, it is proposed that the associated budget be reprofiled into the next financial year. This reprofiling will allow expenditure to be matched to the updated schedule and will support efficient delivery once the prerequisite project is completed.
Delivery of the sports changing facility has been delayed due to dependency on the adjacent housing development, which has not progressed in line with the original programme. The sequencing of works requires the housing development to reach specific construction stages before site access, utilities connections,
and shared infrastructure can be finalised for the changing facility.  As these prerequisite elements remain incomplete, the project cannot move into its planned construction phase. This has resulted in unavoidable slippage, and expenditure originally profiled for the current financial year will not be incurred as expected. 
It is therefore proposed that the budget for the sports changing facility be reprofiled into the next financial year to reflect the revised delivery timeline. This approach maintains alignment between project milestones and financial planning, ensuring that funding remains in place once the adjacent development has
advanced sufficiently to allow works to proceed.  Officers will continue to monitor progress on the housing development closely and will update the programme for the changing facility as soon as conditions permit.
There has been a delay in progressing the Depot Rationalisation Project Board activities, resulting in revised timescales for key project milestones.
ITEM 13 - APPENDIX 3
Page 170

Page 171

Official#
Project - RR 5 Initial End Date  Revised End Date Reprofiling Current Year  2026/27  2027/28  2028/29  2029/30  2030/31  2031/32  2032/33  2033/34  Total Capital Plan
£'000 £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000
Regeneration Fund 31/03/2029 31/03/2029 200 1,074 1,670 880                      3,824
Regeneration Fund Revised 150 50 1,074 1,820 880 0 0 0 0 0                      3,824
Explanation
Project - RR 6 Initial End Date  Revised End Date Reprofiling Current Year  2026/27  2027/28  2028/29  2029/30  2030/31  2031/32  2032/33  2033/34  Total Capital Plan
£'000 £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000
Place Based Investment 31/03/2026 31/03/2027 775 0 0 0                         775
Place Based Investment Revised 625 150 625 0 0 0 0 0 0 0                         775
Explanation
Project - RR 7 Initial End Date  Revised End Date Reprofiling Current Year  2026/27  2027/28  2028/29  2029/30  2030/31  2031/32  2032/33  2033/34  Total Capital Plan
£'000 £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000
Levelling Up Fund 31/03/2026 31/03/2027 5,495 4,754 0 0                    10,249
Levelling Up Fund Revised 1,116 4,379 5,870 0 0 0 0 0 0 0                    10,249
Explanation
Project - RR 8 Initial End Date  Revised End Date Reprofiling Current Year  2026/27  2027/28  2028/29  2029/30  2030/31  2031/32  2032/33  2033/34  Total Capital Plan
£'000 £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000
Levelling Up Capacity Funding 160 0 0 0 0 0 0 0 0                         160
Levelling Up Capacity Funding Revised 160 0 160 0 0 0 0 0 0 0                         160
Explanation
Project - RR 13 Initial End Date  Revised End Date Reprofiling Current Year  2026/27  2027/28  2028/29  2029/30  2030/31  2031/32  2032/33  2033/34  Total Capital Plan
£'000 £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000
Pride in Place Impact Fund 750 750 0 0 0 0 0 0 0                      1,500
Pride in Place Impact Fund Revised 750 0 1,500 0 0 0 0 0 0 0                      1,500
Explanation
Project - RN 5 Initial End Date  Revised End Date Reprofiling Current Year  2026/27  2027/28  2028/29  2029/30  2030/31  2031/32  2032/33  2033/34  Total Capital Plan
£'000 £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000
Vehicle Replacement 31/03/2026 31/03/2026 4,975 1,168 1,040 1,027 1,027 1,027 1,027 1,027 1,027                    13,345
Vehicle Replacement Revised -128 5,103 1,040 1,040 1,027 1,027 1,027 1,027 1,027 1,027                    13,345
Explanation
Project - RN 20 Initial End Date  Revised End Date Reprofiling Current Year  2026/27  2027/28  2028/29  2029/30  2030/31  2031/32  2032/33  2033/34  Total Capital Plan
£'000 £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000
Balloch Mountain Bike Track 31/03/2026 31/03/2027 443 0 0 0 0 0 0 0 0                         443
Balloch Mountain Bike Track Revised 428 15 428 0 0 0 0 0 0 0                         443
Explanation
Reprofiling relates to grant to an external partner taking longer than anticipated.
Project development and tendering taking longer than anticipated.
Project spend in Q3 and Q4 has been lower than originally anticipated due a delay in commencement of the landscaping works on site.
Delivery of the LUF programme is taking longer than originally anticipated. This funding will be used towards the end of the LUF programme, or if any funding gap is identiified earlier.
This is new external funding from UK Government, IRED Committee approval for spend/allocation expected to be obtained in February 2026, with projects developed and delivered in 26/27.
£128k budget was approved at December 2025 Council for the purchase of 3 mini-buses with the budget added to 26/27.  The buses will however be purchased before 31st March 2026, therefore budget required to be accelerared from 26/27 to fund purchase.
Difficulty identifying a suitable site that satisfied planning and ecological concerns has delayed project progress.  Suitable site located and project to progress in 26/27.
Page 171

Page 172

Official#
Project - RN 23 Initial End Date  Revised End Date Reprofiling Current Year  2026/27  2027/28  2028/29  2029/30  2030/31  2031/32  2032/33  2033/34  Total Capital Plan
£'000 £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000 
Creation of 3 new all weather pitches at Argyll Park, Lachie Stewart Memorial Park and
Mountblow playing fields 31/03/2027 31/03/2027 100 1,304 0 0 0 0 0 0 0                      1,404
Creation of 3 new all weather pitches at Argyll Park, Lachie Stewart Memorial Park and
Mountblow playing fields Revised 50 50 1,354 0 0 0 0 0 0 0                      1,404
Explanation
Project - RN 33 Initial End Date  Revised End Date Reprofiling Current Year  2026/27  2027/28  2028/29  2029/30  2030/31  2031/32  2032/33  2033/34  Total Capital Plan
£'000 £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000
Shared Prosperity Funding - Open Places 31/03/2026 30/09/2026 395 0 0 0 0 0 0 0 0                         395
Shared Prosperity Funding - Open Places Revised 395 0 395 0 0 0 0 0 0 0                         395
Explanation
Contract award extended to September 2026.  Two projects planned, Westbridge End Project to upgarde community space including playpark with procurement contract awarded and work expected to start before end of March.  Second project involves development of Allotment Site at Overburn Avenue for which work
has gone out to tender amd awaiting bids.
Tender has been issued for Argyll Park but not yet for Mountblow with discussions ongoing.  It was previously anticipated that £50k would be spent on each of the two remaining sites at Argyll Park and Mountblow in 25/26, however with the dealy in tender issue for Mountblow, it is now expected only £50k will be spent
on Argyll Park with £50k required to be rephased to 26/27 for project progression.
Page 172

Page 173

Official#
All Projects Approved at P10
Service Project Completion Date Revised End Date
Project Life
Budget
Spend to
31/03/2025
Spend Projected
in Current Year Projected
Future Spend
Total Projected Spend Project Variance Approved Budget
2025/26 Actual to date 2025/26 Projected Spend In Year Variance
£000 £'000  £'000  £'000  £'000 £'000 £'000 £'000 £'000
RES 6 Strathleven Place (formerly part of Glencairn House project) 31 March 2026 31 March 2027 1,590 0 0 1,590 1,590 0 1,590 0 0 (1,590)
RES 7 New Sports Changing Facility Dumbarton West (Old OLSP site)  31 March 2026 31 March 2027 349 9 0 340 349 0 340 0 0 (340)
RES 8 Building Upgrades and H&S - lifecycle & reactive building upgrades 31 March 2026 31 March 2026 24,704 0 2,536 22,168 24,704 0 2,536 1,569 2,536 0
RES 10 Depot Rationalisation 31 March 2027 31 March 2027 8,500 2,335 500 5,665 8,500 0 1,779 191 500 (1,279)
RES 12 Community Sports Facility at Millburn 31 March 2028 31 March 2028 500 0 20 480 500 0 20 16 20 0
RES 13 Holm Park Community Football Academy Accesibility Project 31 March 2026 31 March 2026 75 0 75 0 75 0 75 56 75 0
RES 14 4G Football pitch at Faifley Knowles 31 March 2026 31 March 2026 150 0 0 150 150 0 0 0 0 0
RES 15 Design, Creation, Installation of Digital Content for Glencairn House 31 March 2026 31 March 2026 187 0 187 0 187 0 187 0 187 0
Total Resources 36,055 2,344 3,318 30,393 36,055 0 6,528 1,831 3,318 (3,209)
RR 4 Regeneration/Local Economic Development 31 March 2026 31 March 2026 6,995 0 258 6,737 6,995 0 258 164 258 0
RR 5 Regeneration Fund 31 March 2028 31 March 2029 10,931 7,107 50 3,774 10,931 0 200 0 50 (150)
RR 6 Place Based Investment 31 March 2026 31 March 2026 2,175 1,401 150 625 2,175 0 775 0 150 (625)
RR 7 Level Up Funding 31 March 2026 31 December 2027 22,100 11,851 4,379 5,870 22,100 0 5,495 3,385 4,379 (1,116)
RR 8 Level Up Capacity Funding 31 March 2026 31 March 2027 320 160 0 160 320 0 160 0 0 (160)
RR 9 District Heating Network Expansion 31 March 2028 31 March 2028 11,104 259 201 10,644 11,104 0 201 (30) 201 0
RR 10 Clyde Mission Catalyst Fund 31 March 2026 31 March 2027 2,000 673 625 702 2,000 0 625 378 625 0
RR 13 Pride in Place Impact Fund 31 March 2026 31 March 2027 1,500 0 0 1,500 1,500 0 750 0 0 (750)
Total Regulatory and Regeneration 57,125 21,450 5,663 30,012 57,125 0 8,464 3,896 5,663 (2,801)
RN 1 Infrastructure - Roads 31 March 2026 31 March 2026 23,010 0 2,658 20,352 23,010 0 2,658 653 2,658 0
RN 2 Flood Risk Management 31 March 2026 31 March 2026 2,180 0 685 1,495 2,180 0 685 33 685 0
RN 3 Street lighting and associated electrical infrastructure 31 March 2026 31 March 2026 900 0 100 800 900 0 100 0 100 0
RN 4 Flood Prevention 31 March 2026 31 March 2026 450 257 193 0 450 0 193 48 193 0
RN 5 Vehicle Replacement 31 March 2026 31 March 2026 13,345 0 5,103 8,242 13,345 0 4,975 1,824 5,103 128
RN 6 Auld Street Clydebank - Bond 31 March 2026 31 March 2026 256 214 42 0 256 0 42 0 42 0
RN 7 Clydebank Charrette, A814 31 March 2026 31 March 2026 4,303 4,251 52 0 4,303 0 52 52 52 0
RN 9 A813 Road Improvement Phase 1 31 March 2026 31 March 2026 1,579 1,379 201 0 1,579 0 201 8 201 0
RN 10 Traffic Signal Updates 31 March 2026 31 March 2026 300 286 14 0 300 0 14 0 14 0
RN 11 Gruggies Burn Flood Prevention 31 March 2028 31 March 2028 44,700 987 882 42,832 44,700 0 882 256 882 0
RN 12 River Leven Flood Prevention Scheme 31 March 2026 31 March 2026 381 181 200 0 381 0 200 0 200 0
RN 13 Public non-adopted paths and roads 31 March 2026 31 March 2026 1,893 0 541 1,352 1,893 0 541 49 541 0
RN 14 Cemetery Extension, North Dalnotter 31 March 2026 31 March 2026 264 14 250 0 264 0 250 25 250 0
RN 16 Allotment Development 31 March 2026 31 March 2027 492 312 122 58 492 0 122 23 122 0
RN 18 Play Area Upgrade Programme 31 March 2030 31 March 2030 1,413 0 376 1,037 1,413 0 376 241 376 0
RN 20 Balloch Mountain Bike Track 31 March 2026 31 March 2027 450 7 15 428 450 0 443 4 15 (428)
RN 21 Pappert 2G Pitch 31 March 2026 31 March 2026 251 8 242 0 251 0 242 123 242 0
RN 23
Creation of 3 new all weather pitches at Argyll Park, Lachie Stewart Memorial Park and
Mountblow playing fields 31 March 2026 31 March 2027 1,450 47 50 1,354 1,450 0 100 0 50 (50)
RN 24 Exxon City Deal 31 March 2028 31 March 2028 46,942 11,370 20,585 14,988 46,942 0 20,585 12,080 20,585 0
RN 25 Active Travel 31 March 2028 31 March 2028 942 0 942 0 942 0 942 46 942 0
RN 26
Strathclyde Partnership for Transport - Bus, cycling and walking infrastructure
improvements & Park and Rides 31 March 2028 31 March 2028 278 0 278 0 278 0 278 8 278 0
RN 27 Transport Scotland 24-25 Implementation 20MPH Speed Limits 31 March 2028 31 March 2028 458 0 458 0 458 0 458 44 458 0
RN 28 Review of schools speed Limits 31 March 2028 31 March 2028 75 0 75 0 75 0 75 0 75 0
RN 29 Roads Lining and Signing 31 March 2027 31 March 2027 150 0 150 0 150 0 150 32 150 0
RN 30 Plant and Machinery Replacement 31 March 2026 31 March 2026 1,316 0 516 800 1,316 0 516 78 516 0
RN 31 Bus Infrastructure Fund 31 March 2026 31 March 2026 50 0 50 0 50 0 50 0 50 0
RN 32 People and Places - Transport Scotland 31 March 2026 31 March 2026 35 0 35 0 35 0 35 0 35 0
RN 33 Shared Prosperity Funding - Open Places 31 March 2026 31 August 2026 396 0 0 396 396 0 396 0 0 (396)
RN 34 Nature Restoration Fund 31 March 2026 31 March 2026 185 0 185 0 185 0 185 14 185 0
RN 35 Road Safety Improvement Fund 31 March 2026 31 March 2026 185 0 185 0 185 0 185 0 185 0
RN 36 Food Waste Vehicles 31 March 2027 31 March 2027 500 0 0 500 500 0 0 0 0 0
RN 37 CCTV Upgrade at Depots 31 March 2027 31 March 2027 50 0 0 50 50 0 0 0 0 0
RN 38 Gully Motor Purchase 31 March 2027 31 March 2027 275 0 0 275 275 0 0 0 0 0
Total Roads and Neighbourhood 149,455 19,312 35,185 94,958 149,455 0 35,931 15,642 35,185 (746)
Overall Total 242,635 43,106 44,166 155,363 242,635 0 50,922 21,370 44,166 (6,756)
Full Project Life In Year