WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer – Resources
Infrastructure, Regeneration & Economic Development Committee:
4 February 2026
_________________________________________________________________
Subject: Infrastructure, Regeneration & Economic Development Capital
Budgetary Control Report 2025/26 31 October (Period 7)
1. Purpose
1.1 This report provides an update on the capital financial performance to    
31 October 2025 of those services under the auspices of the Infrastructure,
Regeneration & Economic Development Committee (IRED).
2. Recommendations
2.1 Committee is asked to:
i) Note the current position of the 2025/26 IRED capital budget.
ii) Note the revised completion dates in respect of 1 project detailed in
appendix 2 reported to Council on 17 December 2025.
iii) Note the reprofiling of 3 projects in appendix 3 reported to Council on
17 December 2025.
iv) Note additional capital budget of £0.500m for food waste vehicles
reported to Council on 17 December 2025. See paragraph 4.4 for
further details.
v) Grant delegated authority to the Chief Officer Regulatory &
Regeneration, in consultation with the Procurement Manager, to award
procurement and contract awards for projects relating to the Local
Economic Development Plan to develop Mitchell Way and Main Street
in Alexandria.
vi) Grant delegated authority to Chief Officer Roads & Neighbourhood, in
consultation with the Procurement Manager, to award any procurement
and contract awards for projects related to the vehicle replacement
programme.
3. Background
3.1 On 5 March 2025 the Council approved the updated General Services Capital
Plan for 2025/26 to 2034/35. The three years from 2025/26 to 2027/28 were
approved in detail with the remaining years being indicative. The budget
agreed under the auspice of IRED Committee was £56.791m for 2025/26 and
£209.142m for the project life budget.
4. Main Issues
ITEM 10

Page 2

4.1 Exhibit 1 sets out the revised capital budget at period 5 as reported to Council
on 29 October 2025 and Committee 12 November 2025.
Exhibit 1: Revised Capital Budget as at 31 August 2025.
2025/26
(£m)
Project Life
(£m)
Capital Budget Agreed 5 March 2025 56.791 209.142
Updates reported to Committee on 13 August and
12 November plus adjustments for year-end
carried forward balances
3.063 8.502
Reprofiling reported to Committee on 13 August
and 19 November (7.346) 0
Revised Capital Budget as at Period 5 52.508 217.644
4.2 Progress against the 2025/26 capital plan is detailed in:
Appendix 1 – Project Life Summary by Chief Officer
Appendix 2 – Off Track Projects
Appendix 3 – Changes to Capital Plan for Noting
Appendix 4 – All Approved Projects
4.3 The overall programme summary report at Appendix 1 shows that planned
expenditure against the budget is currently on track.
4.4 Appendix 2 highlights 1 project currently showing as off-track, which is due to
a revised completion date.
 Project RN23 (Creation of 3 all new weather pitches at Argyll Park, Lachie
Stewart Memorial Park and Mountblow playing fields), is off track due to a
delay in planning and Argyll and Mountblow now expect to go to tender early
2026. 
4.5 Appendix 3 highlights 3 projects where the project expenditure requires to be
reprofiled but there is no need for approval of additional budget.
4.6 Decisions taken on 17 December 2025 at Council on the Financial Update
(savings taken) and the Review of West Dunbartonshire Council’s Capital
Programme will be applied to the P10 Capital BCR due to the timing
differences of the reports.
4.7 Exhibit 2 sets out the revised IRED capital budget at period 7 factoring in the
decisions taken by Council on 17 December 2025.
Exhibit 2: Revised Capital Budget
2025/26
(£m)
Project Life
(£m)

Page 3

Capital Budget as at 31 August 2025 52.508 217.644
Approved Capital Bid – RN36 Food Waste
Vehicles (Para 4.9)
0 0.500
Additional Funding – RN 6 Place Based
Investment Programme (Para 4.8)
0.369 0.369
Proposed revised Capital Budget as at Period 7 52.877 218.513
Reprofiling over project life (Appendix 3) (1.682) 0
Revised Capital Budget as at Period 7 approved
at Council 17 December.
51.195 218.513
4.8 Appendix 4 shows all projects with approved in year and project life budgets
as well anticipated expenditure. It highlights that the 2025/26 budget is
£51.195m. Spend as at period 7 is £13.512m (26.39%) of the current forecast
spend of £51.195m.
4.9 Other minor changes to the capital plan included in the summarised plan in
appendix 4 are:
 Additional funding from Scottish Government for Place Based Investment
Programme (RR 06) of £0.369m
4.10 Members are asked to note a capital budget of £0.500m to Roads and
Neighbourhood for Food Waste Vehicles which was approved at Council on
17 December 2025.
This bid has been reviewed by the Strategic Asset Management Group who
recommend that £0.500m is added to the Capital plan to procure 4 food waste
vehicles to allow food waste to be recycled separately from garden waste. An
element of this cost will be funded through the Extended Producer
Responsibility funding.
This project has been included in Appendix 4 (RN 36)
4.11 This report also asks the Committee to approve any procurement and contract
award of projects under the Regeneration/Local Economic Development
Project to deliver aspects of Alexandria Town Centre budget in relation to
Mitchell Way and Main Street in Alexandria to be made by the Chief Officer
Regulatory and Regeneration, in consultation with the Procurement Manager
provided the contract costs remain within the approved budget, and the
tenders adhere to standard procurement parameters.
4.12 The Fleet Service have undertaken a prioritisation exercise to determine the
corporate fleet requirements to be delivered through the vehicle replacement
programme. To facilitate the purchase of the vehicles approval is sought to
undertake the procurement and contract award of the Vehicle Replacement
Programme 2026/27 by the Chief Officer – Roads and Neighbourhood in
consultation with the Procurement Service and to appoint the contractor of the
returned tender if the contract cost being within the approved budget and the
tender being in line with normal tender parameters.

Page 4

5. Option Appraisal
5.1 No option appraisal was required for this report.
6. People Implications
6.1 There are no people implications.
7. Financial and Procurement Implications
7.1 The report notes the projected in-year financial position for capital budgets.
8. Risk Analysis
8.1 The main risks are as follows:
(a) The reported variances should be viewed in the knowledge that there are
a number of variable factors which could arise between now and 31
March which could affect the year end results for capital budgets.
(b) As a consequence of current market conditions, inflation is at an all-time
high and interest rates continue to be volatile. To forecast for the full year
costs budget assumptions have been required. These assumptions
continue to change regularly and therefore it is likely the projected year
end budgetary position will change from that reported.
9. Equalities Impact Assessment (EIA)
9.1 No equalities impact assessment was required in relation to this report.
10. Environmental Sustainability
10.1 No assessment of environmental sustainability was required in relation to this
report.
11. Consultation
11.1 All services involved in delivering the capital budgets have been consulted in
the compilation of this report.
12. Strategic Assessment
12.1 Proper budgetary control and sound financial practice are cornerstones
of good governance and support Council and officers to pursue the
strategic priorities of the Council’s current Strategic Plan. This report
forms part of the financial governance of the Council.
______________
Laurence Slavin
Chief Officer – Resources

Page 5

Date: 8 January 2026
Person to Contact:
Jackie Nicol-Thomson
Council Offices, Church Street, Dumbarton
E-mail: jackie.nicolthomson@west-dunbarton.gov.uk
Appendices:
Appendix 1 - Project Life Summary
Appendix 2 - Off Track Projects
Appendix 3 - Changes to Capital Plan and Implications
Appendix 4 - All Projects Approved
Background Papers: 
General Services Capital Plan Update - Council 5 March 2025
Wards Affected          
All Wards