Document Pack (Bookmarked) - IRED Committee 04 02 26

West Dunbartonshire Council · 4 February 2026
Back to Infrastructure, Regeneration & Economic Development Committee — 4 February 2026 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Agenda 
Infrastructure, Regeneration and
Economic Development Committee 
Date:  Wednesday, 4 February 2026
___________________________________________________________________ 
Time:  10:00 
___________________________________________________________________ 
Format:  Hybrid meeting
___________________________________________________________________ 
Contact:    Nicola Moorcroft, Committee Officer
nicola.moorcroft@west-dunbarton.gov.uk  
committee.admin@west-dunbarton.gov.uk 
Dear Member 
Please attend a meeting of the Infrastructure, Regeneration and Economic
Development Committee as detailed above. 
Members will have the option to attend the meeting remotely, or in person, at the Civic
Space, 16 Church Street, Dumbarton G82 1QL.
The business is shown on the attached agenda. 
Yours faithfully 
PETER HESSETT 
Chief Executive 
Page 1

Page 2

Distribution:- 
Councillor David McBride (Chair)
Councillor Kevin Crawford
Councillor Michelle McGinty
Councillor Lawrence O’Neill (Vice Chair)
Councillor Lauren Oxley
Councillor Chris Pollock
Councillor Martin Rooney
Councillor William Rooney
Councillor Gordon Scanlan
Councillor Hazel Sorrell
Councillor Clare Steel
Councillor Sophie Traynor 
All other Councillors for information 
Chief Executive
Chief Officer – Regulatory and Regeneration
Chief Officer – Roads and Neighbourhood
Chief Officer – Resources 
Date of Issue: 22 January 2026 
Audio Streaming 
Audio recordings of the meeting (including the attendance or contribution of any party
participating or making a contribution) will be published on the Council’s website and the
Council’s host’s webcast/audio stream platform. 
You should be aware that the Council is a Data Controller under the General Data
Protection Regulation.  Data collected during this audio stream will be retained in
accordance with the Council’s Privacy Notice* and Retention Schedules including, but not
limited to, for the purpose of keeping historical records and making those records available
via the Council’s internet site. 
*http://www.west-dunbarton.gov.uk/privacy/privacy-notice/ 
Page 2

Page 3

INFRASTRUCTURE, REGENERATION AND ECONOMIC
DEVELOPMENT COMMITTEE 
WEDNESDAY, 4 FEBRUARY 2026
AGENDA 
1 STATEMENT BY CHAIR – AUDIO STREAMING 
The Chair will be heard in connection with the above. 
2 APOLOGIES 
3 DECLARATIONS OF INTEREST 
Members are invited to declare if they have an interest in any of the items of
business on this agenda and the reasons for such declarations. 
4 RECORDING OF VOTES 
The Committee is asked to agree that all votes taken during the meeting be done by
roll call vote to ensure an accurate record. 
5 OPEN FORUM               
The Committee is asked to note that no open forum questions have been
submitted by members of the public. 
6 MINUTES OF PREVIOUS MEETINGS      5 - 9 
Submit for approval, as a correct record, the Minutes of the Meeting of the
Infrastructure, Regeneration and Economic Development Committee held on 12
November 2025. 
7 UPDATE ON ACTIVITY BY CLYDEBANK PROPERTY 
COMPANY LTD. 
11 - 14      
Submit report by the Chief Officer – Resources providing an update on the financial
position of Clydebank Property Company following completion of the audit of the
2024/25 accounts. 
Page 3

Page 4

8 PRIDE IN PLACE IMPACT FUND ALLOCATION     15 - 42       
Submit report by the Chief Officer – Regulatory and Regeneration seeking approval
for allocation of funding from Pride in Place Impact Fund. 
9 INFRASTRUCTURE, REGENERATION AND ECONOMIC    43 -  58               
DEVELOPMENT REVENUE MONITORING REPORT 2025/256 
TO PERIOD 7 (31 OCTOBER 2025)  
Submit report by the Chief Officer – Resources providing an update on the revenue
financial performanceto 31 October 2025 of those services under the auspices of the
Infrastructure, Regeneration and Economic Development Committee. 
10  INFRASTRUCTURE, REGENERATION AND ECONOMIC               59 - 67       
DEVELOPMENT CAPITAL MONITORING REPORT 2025/26
TO PERIOD 7 (31 OCTOBER 2025)   
Submit report by the Chief Officer – Resources providing an update on the capital
financial performance to 31 October 2025 of those services under the auspices of
the Infrastructure, Regeneration and Economic Development Committee. 
Page 4

Page 5

INFRASTRUCTURE, REGENERATION AND ECONOMIC DEVELOPMENT
COMMITTEE 
At a Hybrid Meeting of the Infrastructure, Regeneration and Economic Development
Committee held in the Civic Space, 16 Church Street, Dumbarton on Wednesday, 12
November 2025 at 10.00 a.m. 
Present: Councillors Kevin Crawford, David McBride, Michelle McGinty,
Lawrence O’Neill, Lauren Oxley, Chris Pollock, Martin Rooney,
William Rooney, Gordon Scanlan, Hazel Sorrell, Clare Steel and
Sophie Traynor. 
Attending: Gail Macfarlane, Chief Officer - Roads and Neighbourhood;
Laurence Slavin, Chief Officer - Resources; Alan Douglas, Chief
Officer - Regulatory and Regeneration; Michelle Lynn, Asset
Manager; Ian Bain, Greenspace Manager; Stephen Brooks
Working 4U and Fleet Manager; Christopher Anderson, Principal
Solicitor and Section Head; and Nicola Moorcroft and Scott
Kelly, Committee Officers. 
Councillor David McBride in the Chair 
STATEMENT BY CHAIR – AUDIO STREAMING 
Councillor McBride, Chair, advised that the meeting was being audio streamed and
broadcast live to the internet and would be available for playback. 
DECLARATIONS OF INTEREST 
It was noted that there were no declarations of interest in any of the items of
business on the agenda. 
RECORDING OF VOTES 
The Committee agreed that all votes taken during the meeting be carried out by roll
call vote to ensure an accurate record. 
OPEN FORUM 
The Committee noted that no open forum questions had been submitted by
members of the public. 
ITEM 6
Page 5

Page 6

MINUTES OF PREVIOUS MEETINGS 
The Minutes of Meetings of the Infrastructure, Regeneration and Economic
Development Committee held on 13 August 2025 were submitted and approved as
correct records. 
REGULATION AND REGENERATION DELIVERY PLAN 25/26 – ECONOMIC
DEVELOPMENT - MID-YEAR PROGRESS 
A report was submitted by the Chief Officer - Regulatory and Regeneration
setting out the mid-year progress of the 2025/26 Plan in relation to Economic
Development. 
After discussion and having heard the Chief Officer - Regulatory and Regeneration in
further explanation and in answer to Members’ questions, the Committee agreed to
note the progress achieved at mid-year. 
ROADS AND NEIGHBOURHOOD DELIVERY PLAN 25/26 MID-YEAR ROGRESS 
A report was submitted by the Chief Officer - Roads and Neighbourhood setting out
the midyear progress of the Roads and Neighbourhood Delivery Plan 2025/26. 
After discussion and having heard the Chief Officer - Roads and Neighbourhood in
further explanation and in answer to Members’ questions, the Committee agreed to
note the progress achieved at mid-year. 
RESOURCES DELIVERY PLAN 2025/26 – ASSET MANAGEMENT MID-YEAR
PROGRESS  
A report was submitted by the Chief Officer - Resources setting out the mid-year
progress of the 2025/26 Plan in relation to Asset Management. 
After discussion and having heard the Chief Officer - Resources and the Asset
Manager in further explanation and in answer to Members’ questions, the Committee
agreed to note the progress achieved at mid-year. 
LOCAL CHILD POVERTY ACTION REPORT 
A report was submitted by the Chief Officer - Roads and Neighbourhood providing
an update on the Local Child Poverty Action Report 2024 - 25. 
After discussion and having heard the Working 4U and Fleet Manager in further
explanation and in answer to Members’ questions, the Committee agreed:- 
(1) to note and support the actions set within the child poverty report; and 
Page 6

Page 7

(2) to note partners were asked to commit support, and representation where
appropriate to the Family Prosperity Network and its aims. 
VISITOR LEVY 
A report was submitted by the Chief Officer - Regulation and Regeneration regarding
the above. 
After discussion and having heard the Chief Officer - Regulatory and Regeneration in
further explanation and in answer to Members’ questions, Councillor David McBride
seconded by Councillor Lawrence O’Neill, moved that the Committee: 
(1) note the outcomes of the stage 1 and stage 2 consultations relating to a visitor
levy scheme for West Dunbartonshire; 
(2) agree to implement the final West Dunbartonshire visitor levy scheme, as set
out in Appendix 1 of the report; 
(3)  agree to establish the West Dunbartonshire Visitor Levy Forum and to begin
the process to identify a Chair for the forum, with the appointment subject to
the approval of the Council; 
(4) agree to meet the additional set-up, tourism strategy and staff costs through
the implementation period and offset these costs against future revenues
raised through a visitor levy scheme; and 
(5 ) agree that this scheme may be amended from time to time by the Chief
Officer – Regulatory and Regeneration in consultation with the Chief
Executive and Chief Officer: Resources where it is deemed necessary to
comply with any change in legislation, binding guidance or other provision of
law and otherwise may be amended by Committee. 
As an amendment, Councillor Gordon Scanlan, seconded by Councillor Chris
Pollock, moved that: 
Elected members did not receive oversight of this item until over a week after
the initial papers were published and finally received the detail late on
Thursday afternoon giving us just 3 working days to properly address and
scrutinise both the public survey results and proposals. 
This is not adequate for making a decision on a matter of this magnitude and
this item should be continued to a future meeting. 
On a roll call vote being taken, 5 Members voted for the amendment namely Councillors
Crawford, Pollock, Oxley, Scanlan and Traynor and 7 Members voted for the motion
namely, Councillors McBride, McGinty, O’Neill, Martin Rooney, William Rooney and
Sorrell. The motion was, accordingly, carried. 
Page 7

Page 8

WASTE STRATEGY UPDATE 
A report was submitted by the Chief Officer - Roads and Neighbourhood updating on
progress against the key actions identified in the Waste Strategy Action Plan, which
provides an overarching route map to achieve our regulatory and legislative targets. 
After discussion and having heard the Chief Officer - Roads and Neighbourhood in
further explanation and in answer to Members’ questions, the Committee noted the
content of the report. 
INFRASTRUCTURE, REGENERATION AND ECONOMIC DEVELOPMENT
REVENUE BUDGETARY CONTROL REPORT 2025/26 TO PERIOD 5 (30
AUGUST 2025) 
A report was submitted by the Chief Officer - Resources providing an update on the
revenue financial performance to Period 5 (30 August 2025) of those services under
the auspices of the Infrastructure, Regeneration and Economic Development
Committee (IRED). 
After discussion, the Committee agreed:- 
(1) to note a projected adverse variance against a budget of £0.745m (4.34% of
total budget); and 
(2) to note the current projected use of earmarked reserves of £0.504m. 
INFRASTRUCTURE, REGENERATION AND ECONOMIC DEVELOPMENT
CAPITAL BUDGETARY CONTROL REPORT 2025/26 TO PERIOD 5 (30 AUGUST
2025) 
A report was submitted by the Chief Officer - Resources providing an update on the
capital financial performance to Period 5 (30 August 2025) of those services under
the auspices of the Infrastructure, Regeneration and Economic Development
Committee (IRED). 
After discussion and having heard the Chief Officer - Resources and the Chief
Officer - Roads and Neighbourhood in further explanation, and in answer to
Members’ questions, the Committee agreed:- 
(1) to note the current position of the 2025/26 IRED capital budget; 
(2) to note the revised completion dates in respect of 5 projects detailed in
appendix 2 of the report, reported to Council on 29 October 2025; 
(3) to approve the reprofiling of 6 projects in appendix 3 reported to Council on 29
October 2025; 
Page 8

Page 9

(4)  to note additional capital budget of £1.316m for plant and machinery reported
to Council on 29 October 2025, paragraph 4.9 of the report for further details; 
(5)  to note additional capital budget of £0.352m for vehicle replace programme
reported Council on 29 October 2025, paragraph 4.10 for further details; and 
(6) to grant delegated authority to Chief Officer - Roads and Neighbourhood and
Transport, in consultation with the Procurement Manager, to award contracts
in relation to procurement of waste collection vehicles. 
The meeting closed at 11.52 a.m.
Page 9

Page 10

Page 10

Page 11

WEST DUNBARTONSHIRE COUNCIL
Report by Chief Officer: Resources
Infrastructure Regeneration and Economic Development Committee:
4 February 2023
___________________________________________________________________
Subject: Update on activity by Clydebank Property Company Limited
1. Purpose
1.1 The purpose of this report is to update the Committee on the financial position
of Clydebank Property Company following completion of the audit of the
2024/25 accounts.  
2. Recommendations
2.1 It is recommended the Committee notes:
(i) Clydebank Property Company returned a 2024/25 net loss of £0.060m
(ii) as at 31 March 2025, Clydebank Property Company has total reserves
of £2.883m of which £2.464m are non-distributable and £0.419m are
distributable. 
3. Background
3.1 In 2014 Clydebank Rebuilt closed its operation. As part of this closure West
Dunbartonshire Council agreed to purchase its assets to allow those assets to
continue to serve the business needs of the Clydebank Community.   Details
can be found in the background paper to the IRED Committee on 17
September 2014.
3.2 Updates on the progress of activity of Clydebank Property Company  have
been provided to the IRED Committee since November 2017. 
4. Main Issues
4.1 A report was submitted to the IRED Committee on 27 September 2022 to note
the activity on both property and Titan Crane.
4.2 The tender process for repainting the Crane concluded on 25 September
2024, with two submissions received at £1.129 million and £7.364 million
respectively. Following a review of these costs, Clydebank Property Company
determined that full repainting works will remain on hold at this time. Instead,
the focus will be on undertaking essential maintenance and repairs to the 
ITEM 7
Page 11

Page 12

structure, while ensuring that the navigational lighting continues to operate
effectively.
4.3 Clydebank Property Company continues to actively explore potential funding
streams to support the future refurbishment and reopening of the Crane.
4.4 Occupancy levels across Clydebank Property Company’s commercial and
industrial portfolio remain strong, with the majority of units fully let. This
performance is particularly positive given the wider national trend of declining
occupancy rates in similar sectors. The sustained demand for space within
Clydebank reflects the area’s resilience and attractiveness for businesses,
supported by ongoing regeneration efforts and strategic location advantages.
High occupancy continues to contribute to stable rental income and underpins
confidence in the local economy.
5. People Implications
5.1 There are no people implications arising from this report.
6. Financial and Procurement Implications
6.1      Following the year end, the distributable reserves as detailed below:
Profit/(Loss) Reserves Dividend paid post year end
2023/24 (£0.20m) £0.544m £0.050m
2024/25 (£0.06m) £0.419m £0.050m
6.2 The year end financial position of a loss in year of £0.06m noted in 6.1 is after
taxation and an upwards revaluation to investment properties of £0.020m. 
The taxation charge of £0.033m includes Corporation Tax of £0.007m and a
re-measurement of Deferred Tax for changes in tax rates of £0.026m.
The Deferred Tax is an estimate of the amount of tax payable in respect of the
taxable profit for future reporting periods if the assets were sold. The Deferred
Tax is held as a liability in the accounts and is not actually paid until the
property is sold in a future accounting period.
In 2024/25 the rate of Corporation tax assumed remains at 25%.
FY 2024/2025
£m
Loss on ordinary activities (0.047)
Profit on revaluation of investment properties 0.020
Net Trading Profit (0.027)
Net tax position (0.033)
Net (loss) for the year (0.060)
Page 12

Page 13

6.3 The primary reasons for the in year loss of £0.060m are set out in the table
below.
6.4 Following the year end, the Company now holds £2.464m of non distributable
reserves and £0.419m of distributable reserves as detailed in the table below:
Non Distributable
Reserve
(£m)
Distributable
Reserve
(£m)
Total
Reserves 
(£m)
At 1 April 2024 2.449 0.544 2.993
Dividend paid 0 (0.050) (0.050)
Remaining reserves 2.449 0.494 2.943
(Deficit)/Surplus for
2024/25 0.020 (0.047) (0.027)
Adjustment for taxes (0.005) (0.028) (0.033)
At 31 March 2025 2.464 0.419 2.883
The £2.464m of non-distributable reserves are due to changes to valuations
of investment properties and are consequently not cash based.
6.5 The expectation is that the organisation will generate a surplus which should
generate a dividend to the Council.  The Council's budget assumed a dividend
would be received from Clydebank Property Company each year from
2016/17 onwards (future projections assume £0.050m per annum). The
company has continued to trade with increased levels of operational estate
being let and following the approval of the audited accounts the Board has
agreed to provide the Council with a dividend of £0.050m.
6.6 The Council acquired Clydebank Property Company for £273,000 as an
investment, which was substantially lower than the maximum sum approved
by Council of £800,000.  Since its acquisition CPC has absorbed new costs
charged from the Council associated with the running of its assets. This has
inevitably reduced the surplus position of CPC, however the services would
have been required to have been funded from elsewhere if not provided by
the Council.
6.7 There are no procurement issues associated with this report.
7. Risk Analysis
7.1 The ownership of Clydebank Property Company  is a low-level risk to the
Council. The purchase price was minimal, given the assets owned by
Impact £m
Running costs and impairment of Titan Crane (0.234)
Gain on disposal of John Knox Street plot 0.187
Revaluation of Investment Properties 0.020
Deferred tax charge (0.033)
(0.060)
Page 13

Page 14

Clydebank Property Company . The ongoing position is likely to remain
favourable with likely dividends being provided to the Council.
7.2 The main risk to Clydebank Property Company  and therefore the value of the
Council’s ownership lies in the Titan Crane and the potential for significant
costs should any major structural repairs, etc. be required. Clydebank
Property Company  attempts to mitigate against this risk by maintaining the
crane and undertaking appropriate inspections on a regular basis.
8. Equalities Impact Assessment (EIA)
8.1 No significant issues were identified in relation to equality impact screening
previously carried out.
9. Strategic Environmental Assessment
9.1 A Strategic Environmental Assessment is not required 
10. Consultation
10.1 Consultation was undertaken with officers within Regulatory & Regeneration,
Resources, and Citizen, Culture & Facilities.
11. Strategic Assessment
11.1 The company will continue to significantly contribute to improving economic
growth and employability; and improving local housing and environmentally
sustainable infrastructure.
Laurence Slavin
Chief Officer: Resources
Date: 5 January 2026
Person to Contact: Michelle Lynn, Asset Manager
Email: michelle.lynn@west-dunbarton.gov.uk
Appendices: None
Background Papers: Clydebank Rebuilt – Conclusion to the Purchase of
Clydebank Property Company – Infrastructure,
Regeneration and Economic Development Committee –
17 September 2014
Wards Affected: Ward 6
Page 14

Page 15

WEST DUNBARTONSHIRE COUNCIL
Report by Chief Officer (Regulatory & Regeneration)
Infrastructure, Regeneration & Economic Development Committee
4 February 2026
Subject: Pride in Place Impact Fund allocation
1 Purpose
1.1 This report seeks Members’ approval for allocation of funding from Pride in
Place Impact Fund.
2 Recommendations
2.1 It is recommended that Committee:
I. Notes that the Council has been allocated £1.5M of Pride in Place Impact
Fund in 2025/26 and 2026/27
II. Approves the allocation of £0.240M to Holm Park improvement,
Clydebank
III. Approves the allocation of £0.060M to Western Titans BMX Club track
improvements, Clydebank
IV. Approves the allocation of £0.600M to create new destination playparks in
Alexandria (Christie Park) and Dumbarton (Dumbarton Common)
V. Approves the allocation of £0.600M to community grants for capital
projects which meets the aim and objectives of the fund.
VI. Authorises the commencement of procurement processes relating to the
projects as appropriate and the subsequent award of contracts by the
Chief Officer: Regulatory and Regeneration. and:
VII. Agrees that in the event of any project not appearing to be deliverable
within the required timescale or requirements of the funding conditions
then the Chief Officer: Regulatory and Regeneration may substitute an
alternative project following consultation with the Convenor of IRED
Committee.
3 Background
3.1 In September 2025 the UK Government announced Pride in Place Impact
Fund, which is part of the wider long-term Pride in Place funding
programme. The Council has been allocated £1.5M of capital funding over
Financial Years 2025/26 & 2026/27. The Pride in Place Programme is a
ITEM 8
Page 15

Page 16

continuation of the Neighbourhood Plan under which up to £20m has been
awarded to Clydebank.
The Pride in Place Impact Fund has 3 objectives:
a. Community spaces: creating, extending, improving or refurbishing
existing community facilities and enabling community organisations to
take control or ownership of underused but valued local assets.
b. Public spaces: enhancing the physical environment in public spaces.
c. High street and town centre revitalisation: making these areas more
attractive and welcoming places where people congregate and which
encourage economic activity.
3.2 Pride in Place Impact Fund is a two-year non-competitive Programme.
2025/26 allocation has already been received, and 2026/27 allocation is
expected in Spring 2026.
All funding has to be spent or at least legally committed by the end of March
2027. The first report to the UK Government which will outline the funding
allocation and delivery timescales is due on 16 February 2026.
3.3 The Council which will act as he accountable body for the funding should work
in collaboration with Member of Parliament (MP) and other stakeholders to
identify the interventions that will deliver the needs of the local residents and
will deliver most benefits to the local area.
4 Main Issues
4.1 In considering the allocation of the funding, officers reviewed feedback from
the recent community consultations, particularly in terms of their local need
and ambitions, and consulted with the MP for West Dunbartonshire Douglas
McAlister. The proposed project options were also assessed against the
criteria and objectives of the Pride in Place Impact Fund to ensure
compliance.
4.2 The proposed funding allocation is outlined below.
£240k - Holm Park improvements, Clydebank
£60k - Western Titans BMX Club track improvements, Clydebank
£300k  - Destination Playpark in Christie Park, Alexandria
£300k  - Destination Playpark on the Common, Dumbarton
£600k  - Community grants, Council-wide
Page 16

Page 17

4.3 Holm Park is an important community asset which is under lease from and
owned by West Dunbartonshire and is managed by Holm Park Facilities. It is
a home football ground used by both Clydebank Football Club (the Club) and
Yoker Athletic. Community engagement undertaken in Autumn 2025 for the
Pride in Place Programme in Clydebank mentions the importance of
Clydebank FC in boosting community pride and bringing all ages of the town
together.
Clydebank Football Club are currently a leader of the Scottish Lowland
Football League. If they finish in 1st place they will be promoted to the Scottish
Professional Football League (SPFL) for 2026/27 season. A requirement of
entry is for the Club's facilities to have a Scottish Football Association (SFA)
bronze licence. This bronze licence must be confirmed by March 2026, or
alternatively convincing evidence must be provided to the SPFL that the
licence status will be achieved and in place by the start of the new season in
August 2026. The Club has funding in place for construction of a new
spectator stand. The Pride in Place Impact Fund grant funding of £0.240M will
enable the club to upgrade the pitch and floodlighting and install a stand-alone
referee facility. All these measures are required to achieve the SFA Bronze
licence and will benefit the wider community and other users of the facility.
4.4      Western Titans BMX Club is a small volunteer-run BMX club based in
Clydebank. They host a number of racing events every year and have
nationally ranked riders amongst their members, 6 of whom have qualified to
compete in the World Championships in Brisbane in 2026.
The race track which is open all year round, 24/7, allows children from the
local community and further afield to visit the track, stay exercised, and be
diverted from negative influences such as youth disorder and anti social
behaviour. Due to continuous use the track has deteriorated and could face
closure in the near future, unless the necessary upgrades can be undertaken.
A grant of up to £0.060M will enable the club to upgrade the track.
4.5 New destination playparks in Alexandria and Dumbarton will create a modern,
attractive and bespoke play area for the local families as well as a potential to
draw visitors from further afield. The playparks will cater for both younger and
older children and include provision for children with additional needs.
Long terms strategy will include improvements to pedestrian links between the
playparks and the town centres of Dumbarton and Alexandria. This has the
potential to encourage additional visits to the town centre, contribute to
increased overall footfall and dwell time and support town centre regeneration.
4.6 Community Grants will be awarded through a competitive process to local
groups and organisations, with the aim of supporting delivery of capital
Page 17

Page 18

projects which meet aims and objectives of the Pride in Place Impact Fund. It
is envisaged that the grants would be advertised in March 2026, with the
applications deadline in late April 2026. All applications will be assessed
against the funding criteria, with deliverability within the funding timescales
being the lead criteria to ensure use of funds are maximised.
The Regeneration and Communities Teams have recent experience of
running a community grants scheme along similar lines with the former Place
Based Investment Fund grants.
4.7 The Regeneration team will monitor the progress of the projects to ensure that
all funding is legally committed by the end of March 2027. If there is a
significant risk that some funding is not legally committed by the deadline, it
will be re-allocated to other quick-win projects. The decision on which
alternative projects to fund will be delegated the Chief Officer Regulatory &
Regeneration following consultation with the Convenor of IRED.   A report will
then follow to a future meeting of the IRED Committee for information.
6 People Implications
6.1 Existing staff within Greenspace team will deliver the Playpark projects.
Existing staff within Regeneration and Communities will develop and
implement the Community Grants, and support will be required at key stages
from other Services, including Procurement, Legal and Finance.
Holm Park improvements and Titan’s track improvements will be delivered by
the grantees, with reports submitted to the Council at key stages to ensure
compliance.
7 Financial & Procurement Implications
7.1 Pride in Place Impact Fund is new capital funding available to West
Dunbartonshire Council.  The Council is responsible for ensuring expenditure
is spent in accordance with all applicable legal requirements. Where the
funding is distributed as grants, the Council should ensure that procurements
achieve value for money.
8 Risk Analysis
8.1 All projects are subject to a range of risks that may impact on them being
delivered on time and on budget. In addition there is a higher risk of non-
compliance for externally led projects. For Council led projects risk will be
mitigated by availability of a suitable level of resource to progress the projects.
For externally led projects, risk will be mitigated by ensuring that any grantees
Page 18

Page 19

have suitable experience and resources to deliver the projects, through Grant
conditions dictating stringent drawdown criteria and through monitoring the
development and delivery of each project to ensure compliance with the
funding terms and conditions.
8.2 Where it appears likely that any project may not be able to deliver the
outcomes in line with timing, funding or grant conditions, the Chief Officer
Regulatory and Regeneration may, after consultation with the Convenor of
IRED, substitute the project for another which is likely to be able to comply.
9 Equalities Impact Assessment
9.1 Screening and impact assessments will be carried out on specific projects as
they are further developed.
10   Environmental Sustainability
10.1    Environmental sustainability will be considered when developing individual
projects to reflect the aims of the Council’s Climate Change Strategy.
11  Consultation
11.1 Proposed allocations of funding respond directly to feedback from recent
community consultations, and address local needs and ambitions.
11.2  Legal and Finance Officers have been consulted on the contents of this report.
12 Strategic Assessment
12.1 The Council has agreed its four main strategic priorities for 2022 –
2027. The allocation of the PP Impact Funding is consistent with the
following priorities:
 Our Communities: Resilient and Thriving
 Our Economy: Strong and Flourishing
Alan Douglas
Chief Officer: Regulatory and Regeneration
Date: 12th January 2026
Page 19

Page 20

Person to Contact: Alan Douglas
Alan.Douglas@west-dunbarton.gov.uk
Appendix: 1 - Pride in Place EIA - Holm Park improvements grant
2 - Pride in Place EIA - Western Titans BMX 
improvements grant
3 - Pride in Place EIA - Destination Playparks in Christie
Park, Alexandria & Dumbarton Common, Dumbarton
4 - Pride in Place EIA - Community Grants 
Fund
Background Papers: None
Wards Affected: All
Page 20

Page 21

ITEM 8 - APPENDIX 1
Page 21

Page 22

Page 22

Page 23

Page 23

Page 24

Page 24

Page 25

Page 25

Page 26

ITEM 8 - APPENDIX 2
Page 26

Page 27

Page 27

Page 28

Page 28

Page 29

Page 29

Page 30

Page 30

Page 31

ITEM 8 - APPENDIX 3
Page 31

Page 32

Page 32

Page 33

Page 33

Page 34

Page 34

Page 35

Page 35

Page 36

ITEM 8 - APPENDIX 4
Page 36

Page 37

Page 37

Page 38

Page 38

Page 39

Page 39

Page 40

Page 40

Page 41

Page 41

Page 42

Page 42

Page 43

WEST DUNBARTONSHIRE COUNCIL
Report by Chief Officer - Resources
Infrastructure, Regeneration & Economic Development Committee:
4 February 2026
___________________________________________________________________
Subject: Infrastructure, Regeneration & Economic Development Revenue
Budgetary Control Report 2025/26 to Period 7 (31 October 2025)
1. Purpose
1.1 This report provides an update on the revenue financial performance to 31
October 2025 of those services under the auspices of the Infrastructure,
Regeneration & Economic Development Committee (IRED).
2. Recommendations
2.1 Members are asked to:
 note a projected adverse variance against budget of £0.416m (2.41%
of total budget).
 note the current projected use of earmarked reserves of £0.504m.
3. Background
Revenue
3.1 At the meeting of West Dunbartonshire Council on 5 March 2025, Members
agreed the revenue estimates for 2025/26. A total net budget of £17.042m
was approved for IRED services. Since then, budget changes to the value of
£0.201m have occurred as detailed in the table below:
Description £m
Budget Agreed March 2025 17.042
Changes reported at period 5 0.115
Additional EPR allowance 0.186
Movement of School Crossing Patrollers to CCCF (0.099)
Other Minor Changes (0.001)
Revised Budget 17.243
4. Main Issues
Revenue Budget
4.1 The summary report at Appendix 1 identifies a projected adverse variance
(overspend) of £0.416m (2.41% of total budget). Detailed service reports are
attached at Appendix 2.
ITEM 9
Page 43

Page 44

4.2 Of the 13 services monitored 7 are showing either a favourable or nil variance,
with 6 services showing an adverse variance. Comments are shown in
Appendix 3 when there are projected net annual variances greater than
£0.050m and where the net variance is below £0.050m but there are offsetting
variances of over £0.050m within the service while the table below shows the
main reasons for the movement in the outturn from period 5.
£m £m
Variance at Period 5 0.745
Movement in Service Variance
Roads, Neighbourhood and Transport
Roads
 Reduction in employees costs due to
vacancies
 Increase in payments to contracts for works
undertaken on roads
Crematorium
 Reduction in income anticipated due to level
of cremations being undertaken.
Grounds Maintenance and Street Cleaning
 Reduction in employees costs due to
vacancies
 Additional water rates
Waste Services
 Reduction in costs relating to waste collection
(0.181)
0.045
0.037
(0.226)
0.028
(0.046)
Regulatory and Regeneration
Environmental Health
 Reduction in employees costs due to
vacancies
Legal Services/Trading Standards
 Reduction in employees costs due to
vacancies
(0.028)
(0.023)
Resources
Asset Management
 Reduction in level of rental income anticipated
0.050
Other small variances across the Services 0.015
Total Movement in Service Delivery variance   (0.329)
General Fund variance at Period 7 0.416
4.3 Services are anticipating the use of £0.504m (Period 5: £0.504m) of
earmarked reserves. Information on the earmarked reserve spend is shown in
Appendix 4.
Page 44

Page 45

4.4 A list of agreed efficiencies and management adjustments totalling £3.011m is
shown within Appendix 5. Current indications show that £2.633m is on target
to be achieved.  However, Appendix 6 also shows that it is anticipated that
£0.m will not be achieved and will be funded by the smoothing fund
5. People Implications
5.1 There are no people implications.
6. Financial Implications
6.1 Other than the financial position noted above, there are no financial
implications of the budgetary control report. Officers are currently reviewing
budgets and projections with a view to improving the position by financial year
end and progress will be highlighted in future reports to committee.
7. Risk Analysis
7.1 The present variances should be viewed in the knowledge that there are a
number of variable factors which could arise between now and 31 March and
which could affect the year end results.
8. Equalities Impact Assessment (EIA)
8.1 The report is for noting and therefore no Equalities Impact Assessment was
completed for this report.
9 Consultation
9.1 The views of both Finance and Legal services have been requested on this
report and both have advised there are neither any issues nor concerns with
the proposal. As the report is for noting no further consultation is envisaged.
10. Strategic Assessment
10.1 Proper budgetary control and sound financial practice are cornerstones of
good governance and support Council and officers to pursue the five strategic
priorities of the Council’s Strategic Plan. This report forms part of the financial
governance of the Council. This report is for noting and, therefore, does not
directly affect any of the strategic priorities.
Laurence Slavin
Chief Officer – Resources 
Date:   8 January 2026
Page 45

Page 46

Person to Contact: Jackie Thomson - Business Unit Finance Partner, 16
Church Street, Dumbarton, G81 1QL.
e-mail jackie.nicolthomson@west-dunbarton.gov.uk
Appendices: Appendix 1 - Summary Budgetary Position (Revenue)
Appendix 2 - Detailed Budgetary Position (Revenue)
Appendix 3 - Variance Analysis (Revenue)
Appendix 4 - Earmarked Balances
Appendix 5 - Efficiencies & Management Adjustments
Background Papers: None
Wards Affected: All
Page 46

Page 47

WEST DUNBARTONSHIRE COUNCIL
REVENUE BUDGETARY CONTROL 2025/26
IRED SUMMARY
MONTH END DATE 31 October 2025
Total Budget
2025/26
Spend to
Date 2025/26
Forecast
Spend
2025/26
Net Variance
attributable to
earmarked
reserves spend
Underlying
Variance
excluding
earmarked
reserves spend
Annual
RAG
Status
£000 £000 £000 £000 % £000 £000
(55) 0 (55) 0 0% 0 0 
(99) (29) (0) 99 -100% 0 99 
2,397 2,148 2,507 110 5% 150 (40) 
299 25 349 50 17% 0 50 
(245) (314) (196) 49 -20% 0 49 
(1,057) (309) (893) 165 -16% 0 165 
10,023 3,615 10,148 124 1% 0 124 
(2,029) 4,093 (1,524) 506 -25% 228 278 
1,204 1,011 1,115 (89) -7% 0 (89) 
0 419 0 0 0% 0 0 
2,039 1,532 1,945 (94) -5% 110 (204) 
0 579 0 0 0% 0 0 
4,767 3,670 4,766 (1) 0% 16 (17) 
17,243 16,440 18,163 920 5.33% 504 416 
Transport, Fleet & Maintenance Services
Service / Subjective Summary Annual Variance 2025/26
Corporate Asset Maintenance
Roads Services
Outdoor Services
Burial Grounds
Crematorium
Waste Services
Corporate Assets
Economic Development
Ground Maintenance & Street Cleaning
Total Net Expenditure
Depots
Working 4 U
Shared Prosperity Fund
ITEM 9 - APPENDIX 1  
Page 47

Page 48

WEST DUNBARTONSHIRE COUNCIL
REVENUE BUDGETARY CONTROL 2025/26
IRED COMMITTEE DETAIL
PERIOD END DATE 31 October 2025
7
Actual
Outturn
2024/25
Total
Budget
2025/26
Spend to
Date
2025/26
Forecast
Spend
2025/26
Net Variance
attributable to
earmarked
reserves spend
Underlying Variance
excluding earmarked
reserves spend
RAG
Status
£000 £000 £000 £000 £000 % £000 £000
18,087 Employee 22,455 11,707 21,963 (492) -2% 0 (492) 
5,028 Property 4,587 2,482 4,740 152 3% 0 152 
5,494 Transport and Plant 4,095 2,394 4,683 588 14% 0 588 
13,313 Supplies, Services and Admin 12,201 5,579 12,389 187 2% 16 171 
9,503 Payments to Other Bodies 4,317 1,716 4,464 148 3% 110 38 
1,670 Other 114 94 141 27 24% 0 27 
53,094 Gross Expenditure 47,770 23,972 48,379 609 1% 126 483 
(33,977) Income (30,527) (7,531) (30,216) 310 1% 378 (68) 
19,117 Net Expenditure 17,243 16,440 18,163 920 5% 504 416 
£000 £000 £000 £000 £000 % £000 £000
1,735 Employee 1,970 1,149 1,970 0 0% 0 0 
26 Property 18 15 26 8 44% 0 8 
127 Transport and Plant 131 71 121 (10) -8% 0 (10) 
1,873 Supplies, Services and Admin 1,088 995 1,256 168 15% 0 168 
0 Payments to Other Bodies 0 0 0 0 0% 0 0 
113 Other 114 67 114 0 0% 0 0 
3,874 Gross Expenditure 3,321 2,297 3,487 166 5% 0 166 
(3,885) Income (3,376) (2,297) (3,542) (166) -5% 0 0 
(11) Net Expenditure (55) 0 (55) 0 0% 0 166 
£000 £000 £000 £000 £000 % £000 £000
2,024 Employee 2,163 1,203 2,273 111 5% 0 111 
108 Property 118 5 120 2 1% 0 2 
1,688 Transport and Plant 1,665 1,101 1,907 243 15% 0 243 
821 Supplies, Services and Admin 579 285 585 6 1% 0 6 
1 Payments to Other Bodies 0 0 0 0 0% 0 0 
0 Other 0 0 0 0 0% 0 0 
4,642 Gross Expenditure 4,524 2,594 4,885 361 8% 0 361 
(4,578) Income (4,624) (2,623) (4,885) (262) -6% 0 (262) 
64 Net Expenditure (99) (29) (0) 99 -100% 0 99 
£000 £000 £000 £000 £000 % £000 £000
2,946 Employee 2,854 1,293 2,543 (310) -11% 0 (310) 
254 Property 261 139 267 6 2% 0 6 
890 Transport and Plant 384 290 663 279 73% 0 279 
3,104 Supplies, Services and Admin 2,730 1,080 2,715 (15) -1% 0 (15) 
893 Payments to Other Bodies 317 5 318 1 0% 0 1 
0 Other 0 0 0 0 0% 0 0 
8,088 Gross Expenditure 6,545 2,807 6,505 (40) -1% 0 (40) 
(4,194) Income (4,149) (658) (3,999) 150 4% 150 0 
3,894 Net Expenditure 2,397 2,148 2,507 110 5% 150 (40) 
Service Summary Annual Variance
2025/26
All Services
Corporate Asset Maintenance
Transport, Fleet & Maintenance Services
Roads Services
ITEM 9 - APPENDIX 2
Page 48

Page 49

WEST DUNBARTONSHIRE COUNCIL APPENDIX 2
REVENUE BUDGETARY CONTROL 2025/26
IRED COMMITTEE DETAIL
PERIOD END DATE 31 October 2025
7
Actual
Outturn
2024/25
Total
Budget
2025/26
Spend to
Date
2025/26
Forecast
Spend
2025/26
Net Variance
attributable to
earmarked
reserves spend
Underlying Variance
excluding earmarked
reserves spend
RAG
Status Service Summary Annual Variance
2025/26
£000 £000 £000 £000 £000 % £000 £000
74 Employee 67 38 69 2 3% 0 2 
179 Property 156 26 186 30 19% 0 30 
0 Transport and Plant 0 0 0 0 0% 0 0 
144 Supplies, Services and Admin 116 8 124 7 6% 0 7 
17 Payments to Other Bodies 37 (0) 18 (19) -51% 0 (19) 
0 Other 0 0 0 0 0% 0 0 
414 Gross Expenditure 377 71 397 20 5% 0 20 
(117) Income (78) (47) (48) 30 39% 0 30 
298 Net Expenditure 299 25 349 50 17% 0 50 
£000 £000 £000 £000 £000 % £000 £000
0 Employee 0 0 0 0 0% 0 0 
29 Property 27 16 27 0 0% 0 0 
0 Transport and Plant 0 0 0 0 0% 0 0 
0 Supplies, Services and Admin 0 0 0 0 0% 0 0 
442 Payments to Other Bodies 486 0 486 0 0% 0 0 
0 Other 0 0 0 0 0% 0 0 
471 Gross Expenditure 513 16 513 0 0% 0 0 
(689) Income (758) (330) (709) 49 6% 0 49 
(218) Net Expenditure (245) (314) (196) 49 -20% 0 49 
£000 £000 £000 £000 £000 % £000 £000
215 Employee 194 124 207 13 7% 0 13 
265 Property 304 171 301 (2) -1% 0 (2) 
0 Transport and Plant 0 0 0 0 0% 0 0 
21 Supplies, Services and Admin 18 8 23 5 26% 0 5 
6 Payments to Other Bodies 33 8 10 (23) -70% 0 (23) 
0 Other 0 0 0 0 0% 0 0 
507 Gross Expenditure 549 311 542 (7) -1% 0 (8) 
(1,460) Income (1,606) (619) (1,434) 172 11% 0 172 
(952) Net Expenditure (1,057) (309) (893) 165 -16% 0 164 
£000 £000 £000 £000 £000 % £000 £000
3,583 Employee 3,648 2,030 3,764 116 3% 0 116 
200 Property 182 34 203 21 12% 0 21 
1,504 Transport and Plant 1,294 664 1,360 66 5% 0 66 
6,503 Supplies, Services and Admin 6,775 2,653 6,795 21 0% 0 21 
27 Payments to Other Bodies 22 28 28 6 28% 0 6 
0 Other 0 0 0 0 0% 0 0 
11,817 Gross Expenditure 11,920 5,410 12,151 231 2% 0 231 
(1,362) Income (1,897) (1,796) (2,003) (106) -6% 0 (106) 
10,455 Net Expenditure 10,023 3,615 10,148 124 1% 0 124 
Outdoor Services
Crematorium
Burial Grounds
Waste Services
Page 49

Page 50

WEST DUNBARTONSHIRE COUNCIL APPENDIX 2
REVENUE BUDGETARY CONTROL 2025/26
IRED COMMITTEE DETAIL
PERIOD END DATE 31 October 2025
7
Actual
Outturn
2024/25
Total
Budget
2025/26
Spend to
Date
2025/26
Forecast
Spend
2025/26
Net Variance
attributable to
earmarked
reserves spend
Underlying Variance
excluding earmarked
reserves spend
RAG
Status Service Summary Annual Variance
2025/26
£000 £000 £000 £000 £000 % £000 £000
864 Employee 1,377 665 1,274 (103) -7% 0 (103) 
2,401 Property 2,345 1,559 2,383 38 2% 0 38 
4 Transport and Plant 12 4 12 0 0% 0 0 
(19) Supplies, Services and Admin 27 54 23 (4) -16% 0 (4) 
65 Payments to Other Bodies 60 52 136 76 128% 0 76 
0 Other 0 0 0 0 0% 0 0 
3,315 Gross Expenditure 3,821 2,334 3,828 7 0% 0 7 
(5,065) Income (5,850) 1,759 (5,352) 498 9% 228 270 
(1,750) Net Expenditure (2,029) 4,093 (1,524) 506 -25% 228 278 
£000 £000 £000 £000 £000 % £000 £000
620 Employee 1,114 547 991 (123) -11% 0 (123) 
489 Property 41 16 41 0 1% 0 0 
2 Transport and Plant 5 1 7 1 22% 0 1 
13 Supplies, Services and Admin 112 20 112 0 0% 0 0 
618 Payments to Other Bodies 550 456 550 0 0% 0 0 
0 Other 0 0% 0 0 
1,743 Gross Expenditure 1,823 1,040 1,702 (121) -7% 0 (121) 
(976) Income (619) (29) (587) 32 5% 0 32 
767 Net Expenditure 1,204 1,011 1,115 (89) -7% 0 (89) 
£000 £000 £000 £000 £000 % £000 £000
0 Employee 0 0 0 0 0% 0 0 
657 Property 759 419 765 6 1% 0 6 
0 Transport and Plant 0 0 0 0 0% 0 0 
(1) Supplies, Services and Admin 15 0 15 0 0% 0 0 
0 Payments to Other Bodies 0 0 0 0 0% 0 0 
0 Other 0 0 0 0 0% 0 0 
656 Gross Expenditure 774 419 780 6 1% 0 6 
(656) Income (774) 0 (780) (6) -1% 0 0 
(0) Net Expenditure 419 0 0 0% 0 6 
0
£000 £000 £000 £000 £000 % £000 £000
2,422 Employee 2,829 1,362 2,639 (190) -7% 0 (190) 
Property 0 0 0 0 0% 0 0 
11 Transport and Plant 20 4 19 (1) -6% 0 (1) 
50 Supplies, Services and Admin 46 8 43 (3) -6% 0 (3) 
1,766 Payments to Other Bodies 1,732 888 1,839 107 6% 110 (3) 
178 Other 0 27 27 27 0% 0 27 
4,427 Gross Expenditure 4,627 2,289 4,567 (60) -1% 110 (170) 
(2,428) Income (2,588) (757) (2,622) (34) -1% 0 (34) 
1,999 Net Expenditure 2,039 1,532 1,945 (94) -5% 110 (204) 
£000 £000 £000 £000 £000 % £000 £000
634 Employee 616 326 616 0 0% 0 0 
Property 0 0 0 0 0% 0 0 
2 Transport and Plant 0 1 0 0 0% 0 0 
26 Supplies, Services and Admin 0 1 0 0 0% 0 0 
2,149 Payments to Other Bodies 1,079 261 1,079 0 0% 0 0 
0 Other 0 0 0 0 0% 0 0 
2,811 Gross Expenditure 1,695 589 1,695 0 0% 0 0 
(2,811) Income (1,695) (10) (1,695) 0 0% 0 0 
(0) Net Expenditure 0 579 0 0 0% 0 0 
Economic Development
Depots
Corporate Assets
Working 4 U
Shared Prosperity Fund
Page 50

Page 51

WEST DUNBARTONSHIRE COUNCIL APPENDIX 2
REVENUE BUDGETARY CONTROL 2025/26
IRED COMMITTEE DETAIL
PERIOD END DATE 31 October 2025
7
Actual
Outturn
2024/25
Total
Budget
2025/26
Spend to
Date
2025/26
Forecast
Spend
2025/26
Net Variance
attributable to
earmarked
reserves spend
Underlying Variance
excluding earmarked
reserves spend
RAG
Status Service Summary Annual Variance
2025/26
£000 £000 £000 £000 £000 %
6,003 Employee 5,624 2,970 5,614 (9) 0% 0 (9) 
419 Property 377 82 421 43 11% 0 43 
957 Transport and Plant 584 258 594 10 2% 0 10 
852 Supplies, Services and Admin 695 467 698 2 0% 16 (14) 
19 Payments to Other Bodies 0 19 0 0 0% 0 0 
718 Other 0 0 0 0 0% 0 0 
8,968 Gross Expenditure 7,281 3,796 7,327 46 1% 16 30 
(10,997) Income (2,513) (126) (2,560) (47) -2% 0 (47) 
(2,029) Net Expenditure 4,767 3,670 4,766 (1) 0% 16 (17) 
Ground Maintenance & Street Cleaning
Page 51

Page 52

WEST DUNBARTONSHIRE COUNCIL
REVENUE BUDGETARY CONTROL 2025/26
ANALYSIS FOR VARIANCES OVER £50,000
PERIOD END DATE
Variance Analysis
Total Budget Projected
Spend Use of EMR RAG Status
£000 £000 £000 £000 %
Transport, Fleet & Maintenance
Services (99) (0) 0 99 -100% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Crematorium (1,057) (893) 0 165 0% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Variance after the use
of EMR
Budget Details
31 October 2025
Overspend anticipated.
This service provides crematorium services within the Council area
Income from cremations is anticipated to be £165k less than budgeted mainly due to a
new crematorium recently opened in East Dunbartonshire. This budget is uncontrollable
and may change throughout the year.
The Service will continue to monitor and review costs and reduce overspends as
Transport services across WDC.
Transport Services is operated on behalf of services across the Council. An under
recovery on income is anticipated as while the service fully allocates all costs out to
appropriate services there is currently a mis-alignment between the expenditure and
income budgets. A cost pressure was agreed at Council 17 December to rectify this from
2026/27 budget.
None available as cannot recharge out more than the service costs to run.
Under recovery of income anticipated.
ITEM 9 - APPENDIX 3
Page 52

Page 53

WEST DUNBARTONSHIRE COUNCIL APPENDIX 3
REVENUE BUDGETARY CONTROL 2025/26
ANALYSIS FOR VARIANCES OVER £50,000
PERIOD END DATE
Budget Details
31 October 2025
Waste Services 10,023 10,148 0 124 0% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Corporate Assets (2,029) (1,524) 228 278 -14% 
Service Description This service provides asset and estate management
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Economic Development 1,204 1,115 (89) (89) -7% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Adverse variance due to asset rationalisation, with property disposals that were previous
rental income generating capital receipts that contribute to the wider budget position.    A
review of rental income has taken place and a cost pressure has been added to 2026/27
budget.
An ongoing cost pressure of £50k has been introduced for future years due to higher
property valuation costs. Employee turnover savings are mitigating the £50k rise in
Property costs linked to last year’s increases.
The Service will continue to monitor and review costs and reduce overspends as
appropriate.
Overspend anticipated.
Overspend anticipated.
Underspend is anticipated.
The favourable variance is mainly attributable to employee costs anticipating an
underspend of £123k. This is due to superannuation costs being lower than budgeted
and current staff vacancies. The current underspend in employee costs will be partially
off-set by the reduction in recharge income of £32k.The remaining £2k is due to small
vacancies in the service.
The Service will continue to monitor and review costs.
This service relates to Economic Development within West Dunbartonshire
Waste Collection and Refuse disposal services
The Service will continue to monitor and review costs and reduce overspends as
appropriate.
Employee costs are anticipated to overspend by £116k mainly due to turnover not being
met. Supplies and Services are anticipated to overspend by £21k due to higher levels of
tonnage than anticipated and levels of inflation. Transport costs are expected to
overspend by £66k principally due to internal recharges of £28k which are required to
ensure the Service can fully operate and £30k for repairs and maintenance of vehicles
due to the age of the vehicles and fuel costs of £8k. Waste removal Income is expected
to under-recover by £30k due to a reduction in the level of waste collection to external
customers. This shortfall is off-set by additional income from internal recharges and
general sales of £136k, resulting in an overall anticipated additional income of £106k.The
remaining £26k variance is due to small variances throughout the service.
Page 53

Page 54

WEST DUNBARTONSHIRE COUNCIL APPENDIX 3
REVENUE BUDGETARY CONTROL 2025/26
ANALYSIS FOR VARIANCES OVER £50,000
PERIOD END DATE
Budget Details
31 October 2025
Working 4 U 2,039 1,945 (94) (204) -5% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Provision of Working 4U Service.
The underspend is mainly due to staffing. Savings on staffing were allocated over a two
year period (2025/26 and 2026/27). However, additional external funding from UK Shared
Prosperity Fund (UKSPF) has been received which requires additional staffing.
Therefore, staffing from posts which were taken as savings for next year have been
moved to.UKSPF this year thereby allowing additional savings to be achieved in year
one.
None Required
Favourable variance anticipated.
Page 54

Page 55

WEST DUNBARTONSHIRE COUNCIL
MONITORING OF EARMARKED BALANCES 2025/26 BY CHIEF OFFICER
DEPARTMENT  Amount b/fwd
into 25/26 from
24/25 
25/26
Transfers
in/(Out)  
25/26 Estimate  25/26        
Spend to Date 
25/26 Probable
Outturn 
25/26 to be
released 
To be carried
forward into
26/27 
Description 
£  £  £  £  £  £  £
13 Modern Apprentice 23/24 underspend 177,494             177,494                 -                     -                     177,494             The Balance will be used as part of the four year modern apprenticeship programme to cover payment across financial years.   The funding
will be fully utilised in year five of the programme.           
ROADS & NEIGHBOURHOOD
ITEM 9 - APPENDIX 4
Page 55

Page 56

WEST DUNBARTONSHIRE COUNCIL APPENDIX 4
MONITORING OF EARMARKED BALANCES 2025/26 BY CHIEF OFFICER
DEPARTMENT  Amount b/fwd
into 25/26 from
24/25 
25/26
Transfers
in/(Out)  
25/26 Estimate  25/26        
Spend to Date 
25/26 Probable
Outturn 
25/26 to be
released 
To be carried
forward into
26/27 
Description 
£  £  £  £  £  £  £
16 Set up a an energy Household Energy Support Fund using
£250,000
15,990               15,990                   12,000               12,000               3,990                  Fund set up to support residents who require crisis support to ensure their properties remain heated.
19 Cost of Living 3: Additional Support for Apprenticeships. £50,000
per year for 4 years.
150,000             150,000                 50,000               50,000               100,000              The Apprenticeship Investment Programme being part of a broader programme which is over a four year period. Payments can cover more
than one financial year and therefore the reserves ensures continuity of the programme.
21 Cost of Living 6: Transitional Funding Support to Y-Sort-It over 4
years. £39,000 per year
78,000               78,000                   39,000               39,000               39,000                Transitional funding support for Y-Sort It over a four year period to give them time to secure external funding.
23 Provide £ 64,000 for family fund day events in 2023/24 and the
following three years (approx 32 events at £2,000 per event)
32,000               32,000                   16,000               16,000               16,000                Provision of Family fun days within West Dunbartonshire Council over a four year period This is year three of the four years and therefore
£16k will be carried forward inot 2026/27 to be used.
25 £12k over 3years to Renton Community Food Hub from April 2024
to March 2028 (formerly Tontine Food Parcels)
9,000                 9,000                      3,000                 3,000                 6,000                  Subsidy provided to food banks over a three year period to asist with the provision of food parcels.
26 £12k over 3 years to Lomond Food Pantry from April 2024 to
March 2028
9,000                 9,000                      3,000                 3,000                 6,000                  Subsidy provided to food banks over a three year period to asist with the provision of food parcels.
27 £12k over 3 years to Time for Tully from April 2024 to March 2028 9,000                 9,000                      3,000                 3,000                 6,000                  Subsidy provided to food banks over a three year period to asist with the provision of food parcels.
TOTAL USE OF SERVICE RESERVES              480,484                         -                     480,484               126,000               126,000                         -                 354,484
29 Smoothing Fund - Corproate Assets -                     -                     228,000                 -                     228,000             -                     -                     This is part of the overall council smoothing fund and is being used to cover savings options not being fully achieved in 2025/26 for
caretakers restructrure (RES008) and office rationalisation (SDP05)
30 Smoothing Fund - Roads -                     -                     150,000                 -                     150,000             -                     -                     This is part of the overall council smoothing fund and is being used to cover savings options not being fully achieved in 2025/26 for parking
enforecment (RN05)
TOTAL USE OF STRATEGIC RESERVES                        -                           -                     378,000                         -                 378,000                         -   -                     
TOTAL USE OF EARMARKED RESERVES               480,484                         -                     858,484               126,000               504,000                         -                 354,484
STRATEGIC RESERVES
COST OF LIVING
Page 56

Page 57

WEST DUNBARTONSHIRE COUNCIL
MONITORING OF EFFICIENCIES AND MANAGEMENT ADJUSTMENTS 2025/26
Efficiency Detail Ref Chief Officer
Budgeted
Amount      
£000 
Projection of
Total Saved      
£000 
Projection of
Total Not Saved       
£000 Comment
Parking Enforcement RN05 G Macfarlane 325 175 150
The implementation of DPE commenced a soft roll out in
October with tickets being issued from November.There
will be a part year income and therefore the use of the
smoothing fund is required for the period of the year
before DPE is in place.
Office/ Depot Rationalisation SDP05 L Slavin 380 176 204
Relates to two properties (Kilbowie Road and Elm road
where tenants have yet to be identified.   24/25 shortfall to
be funded from the smoothing fund.  A review has been
undertaken and a cost pressure has been added to the
budget for 2026/27.
Electric Vehicle Charging RN13 G Macfarlane 11                      11                      -                        complete
School crossing patrollers - adhere to best practice RN01 G Macfarlane 25                      25                      -                        complete
Introduce £60 Garden Waste Charge RN02 G Macfarlane 180                   180                    -                        complete
Amend roads service activities to support education to statutory level RN04 G Macfarlane 37                      37                      -                        complete
Reduce the Consultancy Services/Capital Investment Team by 25% RN18 G Macfarlane 15                      15                      -                        complete
Reduce the roads operations service from 29 FTE to 26 FTE which will reduce
resilience in the team RN21 G Macfarlane 60                      60                      -                        complete
Reduce maintenance costs through replacing 6 under utilised grass pitches with
3 new 4G pitches
RN22(24-
25 option) G Macfarlane 50                      50                      -                       
Not complete, planning approval process underway and if
approved will issue  tender. 
Structural Patching RN23 G Macfarlane 50                      50                      -                        Complete
Review compliance with Strategic Opening Model to identify areas where teams
or posts can be merged CCF26 G Macfarlane 50                      50                      -                        Not currently progressed, reviewing options for delivery.
Review Allotment charges RN03 G Macfarlane 5                        5                         -                        Complete, charges updated April 25
Special Uplift Charge RN26 G Macfarlane 22                      22                      -                        Complete, charges updated April 25
Stopping Saturday burials RN01 G Macfarlane 10                      10                      -                        Complete
Capitalise Play Park Fitter RN07 G Macfarlane 40                      40                      -                        Complete
Further replacement of hire vehicles RN09 G Macfarlane 171                   171                    -                       
Vehicles have been procured and are expected to arrive late
Summer
Reduce Working4U service by 50% HE02 G Macfarlane 206                   206                    -                        complete
School Crossing Patrollers -Retain 17 Crossing Patrollers RN17 G Macfarlane 23                      23                      -                        Underway, 2 locations still to be resolved
Review or remove provision of footway gritting - Cease Footway Gritting RN18 G Macfarlane 68                      68                      -                        complete
Close or reduce Dalmuir golf course - Close completely RN20 G Macfarlane 184                   184                    -                        Completed
Cease the Care of Gardens scheme RN21 G Macfarlane 143                   143                    -                        Complete
Review levels of street cleaning - Reduce by 2 staff
RN22
(2025-26
option) G Macfarlane 26                      26                      -                        Complete
Review of park maintenance RN24 G Macfarlane 60                      60                      -                        Complete
2023/24 Efficiencies not achieved
2025/26 Efficiencies and Management Adjustments
Page 57
ITEM 9 - APPENDIX 5

Page 58

WEST DUNBARTONSHIRE COUNCIL APPENDIX 5
MONITORING OF EFFICIENCIES AND MANAGEMENT ADJUSTMENTS 2025/26
Efficiency Detail Ref Chief Officer
Budgeted
Amount      
£000 
Projection of
Total Saved      
£000 
Projection of
Total Not Saved       
£000 Comment
Remove open space maintenance on non council land RN28 G Macfarlane 20                      20                      -                        Complete
Review Event Support by Grounds Service RN29 G Macfarlane 15                      15                      -                        Complete. Costs will be recharged to event organisers
Road Network & Capital Management Reduction RN30 G Macfarlane 50                      50                      -                       
Part complete, 0.6FTE reduction with further employee
reduction being assessed
Review Winter Plan RN31 G Macfarlane 55                      55                      -                        Complete, Plan approved.
Reduce Grass Cutting RN35 G Macfarlane 150                   150                    -                        Complete
Review Footway Gritting Operational Method RN14 G Macfarlane 60                      60                      -                        Complete
Historical Lease Review RES13 L Slavin 44                      44                      -                        Saving anticipated to be achieved
Remove one Council officer RES09 L Slavin 8                        8                         -                        Saving anticipated to be achieved
Reduce number of caretakers RES08 L Slavin 24                      -                     24                          Saving cannot be realised due to full salary recharge.
Income Generation through Commercialisation RES09 L Slavin 15                      15                      -                        Saving anticipated to be achieved
Further asset rationalisation SDP04 L Slavin 99                      99                      -                        Saving anticipated to be achieved
External Consultancy Income SDP09 L Slavin 25                      25                      -                        Saving anticipated to be achieved
Review of charges for use of offices by external parties RES09 L Slavin 7                        7                         -                        Saving anticipated to be achieved
Historical lease review RES13 L Slavin 15                      15                      -                        Saving anticipated to be achieved
Reduce size of Building Services RES15 L Slavin 228                   228                    -                        Saving anticipated to be achieved
Review Asset Management team RES19 L Slavin 55                      55                      -                        Saving anticipated to be achieved
TOTAL AGREED SAVINGS OPTIONS & MANAGEMENT ADJUSTMENTS 3,011                2,633                 378                      
Page 58

Page 59

WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer – Resources
Infrastructure, Regeneration & Economic Development Committee:
4 February 2026
_________________________________________________________________
Subject: Infrastructure, Regeneration & Economic Development Capital
Budgetary Control Report 2025/26 31 October (Period 7)
1. Purpose
1.1 This report provides an update on the capital financial performance to    
31 October 2025 of those services under the auspices of the Infrastructure,
Regeneration & Economic Development Committee (IRED).
2. Recommendations
2.1 Committee is asked to:
i) Note the current position of the 2025/26 IRED capital budget.
ii) Note the revised completion dates in respect of 1 project detailed in
appendix 2 reported to Council on 17 December 2025.
iii) Note the reprofiling of 3 projects in appendix 3 reported to Council on
17 December 2025.
iv) Note additional capital budget of £0.500m for food waste vehicles
reported to Council on 17 December 2025. See paragraph 4.4 for
further details.
v) Grant delegated authority to the Chief Officer Regulatory &
Regeneration, in consultation with the Procurement Manager, to award
procurement and contract awards for projects relating to the Local
Economic Development Plan to develop Mitchell Way and Main Street
in Alexandria.
vi) Grant delegated authority to Chief Officer Roads & Neighbourhood, in
consultation with the Procurement Manager, to award any procurement
and contract awards for projects related to the vehicle replacement
programme.
3. Background
3.1 On 5 March 2025 the Council approved the updated General Services Capital
Plan for 2025/26 to 2034/35. The three years from 2025/26 to 2027/28 were
approved in detail with the remaining years being indicative. The budget
agreed under the auspice of IRED Committee was £56.791m for 2025/26 and
£209.142m for the project life budget.
4. Main Issues
ITEM 10
Page 59

Page 60

4.1 Exhibit 1 sets out the revised capital budget at period 5 as reported to Council
on 29 October 2025 and Committee 12 November 2025.
Exhibit 1: Revised Capital Budget as at 31 August 2025.
2025/26
(£m)
Project Life
(£m)
Capital Budget Agreed 5 March 2025 56.791 209.142
Updates reported to Committee on 13 August and
12 November plus adjustments for year-end
carried forward balances
3.063 8.502
Reprofiling reported to Committee on 13 August
and 19 November (7.346) 0
Revised Capital Budget as at Period 5 52.508 217.644
4.2 Progress against the 2025/26 capital plan is detailed in:
Appendix 1 – Project Life Summary by Chief Officer
Appendix 2 – Off Track Projects
Appendix 3 – Changes to Capital Plan for Noting
Appendix 4 – All Approved Projects
4.3 The overall programme summary report at Appendix 1 shows that planned
expenditure against the budget is currently on track.
4.4 Appendix 2 highlights 1 project currently showing as off-track, which is due to
a revised completion date.
 Project RN23 (Creation of 3 all new weather pitches at Argyll Park, Lachie
Stewart Memorial Park and Mountblow playing fields), is off track due to a
delay in planning and Argyll and Mountblow now expect to go to tender early
2026. 
4.5 Appendix 3 highlights 3 projects where the project expenditure requires to be
reprofiled but there is no need for approval of additional budget.
4.6 Decisions taken on 17 December 2025 at Council on the Financial Update
(savings taken) and the Review of West Dunbartonshire Council’s Capital
Programme will be applied to the P10 Capital BCR due to the timing
differences of the reports.
4.7 Exhibit 2 sets out the revised IRED capital budget at period 7 factoring in the
decisions taken by Council on 17 December 2025.
Exhibit 2: Revised Capital Budget
2025/26
(£m)
Project Life
(£m)
Page 60

Page 61

Capital Budget as at 31 August 2025 52.508 217.644
Approved Capital Bid – RN36 Food Waste
Vehicles (Para 4.9)
0 0.500
Additional Funding – RN 6 Place Based
Investment Programme (Para 4.8)
0.369 0.369
Proposed revised Capital Budget as at Period 7 52.877 218.513
Reprofiling over project life (Appendix 3) (1.682) 0
Revised Capital Budget as at Period 7 approved
at Council 17 December.
51.195 218.513
4.8 Appendix 4 shows all projects with approved in year and project life budgets
as well anticipated expenditure. It highlights that the 2025/26 budget is
£51.195m. Spend as at period 7 is £13.512m (26.39%) of the current forecast
spend of £51.195m.
4.9 Other minor changes to the capital plan included in the summarised plan in
appendix 4 are:
 Additional funding from Scottish Government for Place Based Investment
Programme (RR 06) of £0.369m
4.10 Members are asked to note a capital budget of £0.500m to Roads and
Neighbourhood for Food Waste Vehicles which was approved at Council on
17 December 2025.
This bid has been reviewed by the Strategic Asset Management Group who
recommend that £0.500m is added to the Capital plan to procure 4 food waste
vehicles to allow food waste to be recycled separately from garden waste. An
element of this cost will be funded through the Extended Producer
Responsibility funding.
This project has been included in Appendix 4 (RN 36)
4.11 This report also asks the Committee to approve any procurement and contract
award of projects under the Regeneration/Local Economic Development
Project to deliver aspects of Alexandria Town Centre budget in relation to
Mitchell Way and Main Street in Alexandria to be made by the Chief Officer
Regulatory and Regeneration, in consultation with the Procurement Manager
provided the contract costs remain within the approved budget, and the
tenders adhere to standard procurement parameters.
4.12 The Fleet Service have undertaken a prioritisation exercise to determine the
corporate fleet requirements to be delivered through the vehicle replacement
programme. To facilitate the purchase of the vehicles approval is sought to
undertake the procurement and contract award of the Vehicle Replacement
Programme 2026/27 by the Chief Officer – Roads and Neighbourhood in
consultation with the Procurement Service and to appoint the contractor of the
returned tender if the contract cost being within the approved budget and the
tender being in line with normal tender parameters.
Page 61

Page 62

5. Option Appraisal
5.1 No option appraisal was required for this report.
6. People Implications
6.1 There are no people implications.
7. Financial and Procurement Implications
7.1 The report notes the projected in-year financial position for capital budgets.
8. Risk Analysis
8.1 The main risks are as follows:
(a) The reported variances should be viewed in the knowledge that there are
a number of variable factors which could arise between now and 31
March which could affect the year end results for capital budgets.
(b) As a consequence of current market conditions, inflation is at an all-time
high and interest rates continue to be volatile. To forecast for the full year
costs budget assumptions have been required. These assumptions
continue to change regularly and therefore it is likely the projected year
end budgetary position will change from that reported.
9. Equalities Impact Assessment (EIA)
9.1 No equalities impact assessment was required in relation to this report.
10. Environmental Sustainability
10.1 No assessment of environmental sustainability was required in relation to this
report.
11. Consultation
11.1 All services involved in delivering the capital budgets have been consulted in
the compilation of this report.
12. Strategic Assessment
12.1 Proper budgetary control and sound financial practice are cornerstones
of good governance and support Council and officers to pursue the
strategic priorities of the Council’s current Strategic Plan. This report
forms part of the financial governance of the Council.
______________
Laurence Slavin
Chief Officer – Resources
Page 62

Page 63

Date: 8 January 2026
Person to Contact:
Jackie Nicol-Thomson
Council Offices, Church Street, Dumbarton
E-mail: jackie.nicolthomson@west-dunbarton.gov.uk
Appendices:
Appendix 1 - Project Life Summary
Appendix 2 - Off Track Projects
Appendix 3 - Changes to Capital Plan and Implications
Appendix 4 - All Projects Approved
Background Papers: 
General Services Capital Plan Update - Council 5 March 2025
Wards Affected          
All Wards
Page 63

Page 64

Summary at Period 7
Project Life
Budget
Project Life
Forecast
Spend
Project Life
Variance On Track/Complete Off Track
£'000 £'000 £'000
Resources 36,055             36,055            0 8                                     0
Regulatory and Regeneration 57,327             57,327            0 11                                   0
Roads and Neighbourhoods 125,131           125,131          0 35                                   1
Total 218,514           218,514          0 54 1                  
ITEM 10 - APPENDIX 1
Page 64

Page 65

Projects that are Off Track at Period 7
Service Project
Approved Project Life
Cost
Revised Project
Life Cost
Project Life
Variance
Initial Completion
Date
Revised
Completion Date
£'000 £'000 £'000
Roads and Neighbourhood RN23 - Creation of 3 new all weather pitches at Argyll Park, Lachie Stewart
Memorial Park and Mountblow playing fields                                  2,203                      2,203                  -   31/03/2026 31/03/2027
Project Name: Project - RN23 - Creation of 3 new all weather pitches at Argyll Park, Lachie
Stewart Memorial Park and Mountblow playing fields
Project Manager: Michelle Lynn
Initial Completion End Date: 31/03/2026 Revised End Date: 31/03/2027
How was this project initially funded: Please Detail any additional funding:
Prudential Borrowing n/a
Why is the project classified as off track and what has caused the issues identified?
What action will be taken to rectify the position?
New Completion Date: 31/03/2027 Prudential Borrowing
What are the implications on the actions proposed?
Revenue Implications:-
Virement Implications:- n/a
Argyll and Mountblow have experienced a delay in planning and now expected to go to tender early 2026.  It is anticpated half the works will be complete by end of 2025/26 with remaining budget required to be
rephased to 2026/27 for project completion.
Source of Funding:
n/a
ITEM 10 - APPENDIX 2
Page 65

Page 66

Changes to Capital Plan and Implications at P7
Project - RR4 Initial End Date  Revised End Date Reprofiling Current Year  2026/27  2027/28  2028/29  2029/30  2030/31  2031/32  2032/33  2033/34  Total Capital Plan
£'000 £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000
Regeneration/Local Economic Development Recurring budget Recurring budget 758 2,840 1,300 830 500 500 500 500 500                      8,228
Regeneration/Local Economic Development Revised 320 438 3,160 1,300 830 500 500 500 500 500                      8,228
Explanation
Project - RR7 Initial End Date  Revised End Date Reprofiling Current Year  2026/27  2027/28  2028/29  2029/30  2030/31  2031/32  2032/33  2033/34  Total Capital Plan
£'000 £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000
Levelling Up 31/12/2026 31/12/2027 6,176 4,073 0 0 0 0 0 0 0                    10,249
Levelling Up - Revised 681 5,495 4,754 0 0 0 0 0 0 0                    10,249
Explanation
Project - RN23 Initial End Date  Revised End Date Reprofiling Current Year  2026/27  2027/28  2028/29  2029/30  2030/31  2031/32  2032/33  2033/34  Total Capital Plan
£'000 £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000 
Creation of 3 new all weather pitches at Argyll Park, Lachie Stewart Memorial Park and
Mountblow playing fields 31/12/2026 31/12/2027                    781            1,423                    -                    -                    -                   -                   -                    -                    -                         2,203 
Creation of 3 new all weather pitches at Argyll Park, Lachie Stewart Memorial Park, and
Mountblow playing fields Revised 681                    100            2,103                    -                    -                    -                   -                   -                    -                    -                         2,203
Explanation
Project development on multiple projects, including Alexandria masterplan projects are slower than anticipated due to resourcing issues, resulting in some spend delay.  Budget rephased to align with revised anticipated progression.
Project delivery  taking longer than expected, delays to site start and programme extension  are related to planning requirements.
Argyll and Mountblow have experienced a delay in planning and now expected to go to tender early 2026.  It is anticpated half the works will be complete by end of 2025/26 with remaining budget required to be rephased to 2026/27 for project completion.
ITEM 10 - APPENDIX 3
Page 66

Page 67

All Projects Approved at P7
Service Project Completion Date Revised End Date
Project Life
Budget
Spend to
31/03/2025
Spend Projected
in Current Year Projected
Future Spend
Total Projected Spend Project Variance Approved Budget
2025/26 Actual to date 2025/26 Projected Spend In Year Variance
£000 £'000  £'000  £'000  £'000 £'000 £'000 £'000 £'000
RES 6 Strathleven Place (formerly part of Glencairn House project) 31 March 2026 31 March 2026 1,590 0 1,590 0 1,590 0 1,590 0 1,590 0
RES 7 New Sports Changing Facility Dumbarton West (Old OLSP site)  31 March 2026 31 March 2026 349 9 340 0 349 0 340 0 340 0
RES 8 Building Upgrades and H&S - lifecycle & reactive building upgrades 31 March 2026 31 March 2026 24,704 0 2,536 22,168 24,704 0 2,536 285 2,536 0
RES 10 Depot Rationalisation 31 March 2027 31 March 2027 8,500 2,335 1,779 4,386 8,500 0 1,779 79 1,779 0
RES 12 Community Sports Facility at Millburn 31 March 2028 31 March 2028 500 0 20 480 500 0 20 16 20 0
RES 13 Holm Park Community Football Academy Accesibility Project 31 March 2026 31 March 2026 75 0 75 0 75 0 75 0 75 0
RES 14 4G Football pitch at Faifley Knowles 31 March 2026 31 March 2026 150 0 0 150 150 0 0 0 0 0
RES 15 Design, Creation, Installation of Digital Content for Glencairn House 31 March 2026 31 March 2026 187 0 187 0 187 0 187 0 187 0
Total Resources 36,055 2,344 6,527 27,184 36,055 0 6,527 379 6,527 0
RR 2 Installation of Solar PV at Clydebank Leisure Centre 31 March 2026 31 March 2027 61 4 0 57 61 0 0 0 0 0
RR 3
Leisure Energy projects - air handling units, upgrade lighting, circulating pumps, and
draught proofing 31 March 2026 31 March 2027 290 64 0 226 290 0 0 0 0 0
RR 4 Regeneration/Local Economic Development 31 March 2026 31 March 2026 8,228 0 438 7,790 8,228 0 758 118 438 (320)
RR 5 Regeneration Fund 31 March 2028 31 March 2029 10,931 7,107 200 3,624 10,931 0 200 0 200 0
RR 6 Place Based Investment 31 March 2026 31 March 2026 2,175 1,401 775 0 2,175 0 775 0 775 0
RR 7 Level Up Funding 31 March 2026 31 December 2027 22,100 11,851 5,495 4,754 22,100 0 6,176 2,581 5,495 (681)
RR 8 Level Up Capacity Funding 31 March 2026 31 March 2026 320 160 160 0 320 0 160 0 160 0
RR 9 District Heating Network Expansion 31 March 2028 31 March 2028 11,104 259 201 10,644 11,104 0 201 12 201 0
RR10 Clyde Mission Catalyst Fund 31 March 2026 31 March 2027 2,000 673 625 702 2,000 0 625 375 625 0
RR11 Securing sites to make safe 31 March 2026 31 March 2026 66 35 30 0 66 0 30 0 30 0
RR12 Hybrid Meetings Equipment 31 March 2026 31 March 2026 53 0 53 0 53 0 53 0 53 0
Total Regulatory and Regeneration 57,327 21,553 7,977 27,797 57,327 0 8,978 3,087 7,977 (1,001)
RN 1 Infrastructure - Roads 31 March 2026 31 March 2026 23,010 0 2,658 20,352 23,010 0 2,658 616 2,658 0
RN 2 Flood Risk Management 31 March 2026 31 March 2026 2,180 0 685 1,495 2,180 0 685 24 685 0
RN 3 Street lighting and associated electrical infrastructure 31 March 2026 31 March 2026 900 0 100 800 900 0 100 0 100 0
RN 4 Flood Prevention 31 March 2026 31 March 2026 450 257 193 0 450 0 193 45 193 0
RN 5 Vehicle Replacement 31 March 2026 31 March 2026 13,217 0 4,975 8,242 13,217 0 4,975 1,107 4,975 0
RN 6 Auld Street Clydebank - Bond 31 March 2026 31 March 2026 256 214 42 0 256 0 42 0 42 0
RN 7 Clydebank Charrette, A814 31 March 2026 31 March 2026 4,303 4,251 52 0 4,303 0 52 (0) 52 0
RN 8 Roads Plant 31 March 2026 31 March 2026 79 79 0 0 79 0 0 0 0 0
RN 9 A813 Road Improvement Phase 1 31 March 2026 31 March 2026 1,700 1,379 322 0 1,700 0 322 8 322 0
RN 10 Traffic Signal Updates 31 March 2026 31 March 2026 300 286 14 0 300 0 14 0 14 0
RN 11 Gruggies Burn Flood Prevention 31 March 2028 31 March 2028 15,028 987 882 13,160 15,028 0 882 95 882 0
RN 12 River Leven Flood Prevention Scheme 31 March 2026 31 March 2026 801 181 620 0 801 0 620 0 620 0
RN 13 Public non-adopted paths and roads 31 March 2026 31 March 2026 2,341 0 541 1,800 2,341 0 541 31 541 0
RN 14 Cemetery Extension, North Dalnotter 31 March 2026 31 March 2026 264 14 250 0 264 0 250 0 250 0
RN 15 Vale of Leven Cemetery 31 March 2025 31 March 2025 925 912 13 0 925 0 13 13 13 0
RN 16 Allotment Development 31 March 2026 31 March 2027 492 312 122 58 492 0 122 23 122 0
RN 17 Waste Transfer Station 31 March 2026 31 March 2029 1,980 159 0 1,821 1,980 0 0 0 0 (0)
RN 18 Play Area Upgrade Programme 31 March 2030 31 March 2030 2,007 594 376 1,037 2,007 0 376 185 376 0
RN 19 East End Park Resurfacing 31 March 2026 31 March 2026 385 183 202 0 385 0 202 23 202 0
RN 20 Balloch Mountain Bike Track 31 March 2026 31 March 2026 450 7 443 0 450 0 443 4 443 0
RN 21 Pappert 2G Pitch 31 March 2026 31 March 2026 251 8 242 0 251 0 242 120 242 0
RN 22 Kilmaronock Cemetery Extension 31 March 2026 31 March 2026 50 45 5 0 50 0 5 0 5 0
RN 23
Creation of 3 new all weather pitches at Argyll Park, Lachie Stewart Memorial Park and
Mountblow playing fields 31 March 2026 31 March 2027 2,250 47 100 2,103 2,250 0 781 0 100 (681)
RN 24 Exxon City Deal 31 March 2028 31 March 2028 46,942 11,370 20,585 14,988 46,942 0 20,585 7,602 20,585 0
RN 25 Active Travel 31 March 2028 31 March 2028 942 0 942 0 942 0 942 46 942 0
RN 26
Strathclyde Partnership for Transport - Bus, cycling and walking infrastructure
improvements & Park and Rides 31 March 2028 31 March 2028 278 0 278 0 278 0 278 0 278 0
RN27 Transport Scotland 24-25 Implementation 20MPH Speed Limits 31 March 2028 31 March 2028 458 0 458 0 458 0 458 13 458 0
RN 28 Review of schools speed Limits 31 March 2028 31 March 2028 75 0 75 0 75 0 75 0 75 0
RN 29 Roads Lining and Signing 31 March 2027 31 March 2027 150 0 150 0 150 0 150 0 150 0
RN 30 Plant and Machinery Replacement 31 March 2026 31 March 2026 1,316 0 516 800 1,316 0 516 78 516 0
RN 31 Bus Infrastructure Fund 31 March 2026 31 March 2026 50 0 50 0 50 0 50 0 50 0
RN 32 People and Places - Transport Scotland 31 March 2026 31 March 2026 35 0 35 0 35 0 35 0 35 0
RN 33 Shared Prosperity Funding - Open Places 31 March 2026 31 March 2026 396 0 396 0 396 0 396 0 396 0
RN 34 Nature Restoration Fund 31 March 2026 31 March 2026 185 0 185 0 185 0 185 14 185 0
RN 35 Road Safety Improvement Fund 31 March 2026 31 March 2026 185 0 185 0 185 0 185 0 185 0
RN 36 Food Waste Vehicles 31 March 2027 31 March 2027 500 0 0 500 500 0 0 0 0 0
Total Roads and Neighbourhood 125,131 21,285 36,691 67,155 125,131 0 37,372 10,047 36,691 (681)
Overall Total 218,513 45,182 51,195 122,137 218,513 0 52,877 13,512 51,195 (1,682)
Full Project Life In Year
ITEM 10 - APPENDIX 4
Page 67