Changes to Capital Plan and Implications at P5 Appendix 3
Regulatory and Regeneration
Project - RR5 Initial End Date 
Revised End
Date Reprofiling Current Year  2026/27  2027/28  2028/29  2029/30  2030/31  2031/32  2032/33  2033/34  Total Capital Plan
£'000 £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000
Regeneration Fund 31/03/2028 31/03/2029 2,000 1,824 0 0 0 0 0 0                      3,824
Regeneration Fund Revised (200) 200 1,074 1,670 880 0 0 0 0 0                      3,824
Explanation
Project - RR7  Initial End Date 
Revised End
Date Reprofiling Current Year  2026/27  2027/28  2028/29  2029/30  2030/31  2031/32  2032/33  2033/34  Total Capital Plan
£'000 £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000
Level Up Funding 31/12/2026 31/12/2027 7,076                 3,173           0 0 0 0 0 0 0                    10,249
Level Up Funding Revised 900 6,176 4,073 0 0 0 0 0 0 0                    10,249
Explanation
Dumbarton Artizan element of project is taking longer to deliver than first anticipated, due to additional pre-commencement activities including site investigations which took longer than expected.
Roads and Neighbourhood
Project - RN16 Initial End Date 
Revised End
Date Reprofiling Current Year  2026/27  2027/28  2028/29  2029/30  2030/31  2031/32  2032/33  2033/34  Total Capital Plan
£'000 £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000
Allotment Development 31/12/2026 31/03/2027 180                    0 0 0 0 0 0 0 0                         180
Allotment Development Revised 58 123 58 0 0 0 0 0 0 0                         180
Explanation
Delay in tender process due to Council service restructure and allocating new resource
Project - RN17 Initial End Date 
Revised End
Date Reprofiling Current Year  2026/27  2027/28  2028/29  2029/30  2030/31  2031/32  2032/33  2033/34  Total Capital Plan
£'000 £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000
Waste Transfer Station 31/03/2026 31/03/2029 1,821                 0 0 0 0 0 0 0 0                      1,821
Waste Transfer Station Revised 1,821 0 0 0 1,821 0 0 0 0 0                      1,821
Explanation
Project - RN18 Initial End Date 
Revised End
Date Reprofiling Current Year  2026/27  2027/28  2028/29  2029/30  2030/31  2031/32  2032/33  2033/34  Total Capital Plan
£'000 £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000
Play Area Upgrade Programme 31/03/2030 31/03/2030 613                    100 100 100 100 100 100 100 100                      1,413
Play Area Upgrade Programme Revised 237 376 337 100 100 100 100 100 100 100                      1,413
Explanation
Delay in tender process due to Council service restructure and allocating new resource
Project - RN23 Initial End Date 
Revised End
Date Reprofiling Current Year  2026/27  2027/28  2028/29  2029/30  2030/31  2031/32  2032/33  2033/34  Total Capital Plan
£'000 £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000
Creation of 3 new all weather pitches at Argyll Park, Posties Park and Mountblow playing
fields. 31/03/2026 31/03/2027 2,203                 0 0 0 0 0 0 0 0                      2,203
Creation of 3 new all weather pitches at Argyll Park, Posties Park and Mountblow
playing fields Revised 1,422 782 1,422 0 0 0 0 0 0 0                      2,203
Explanation
Delay in tender process due to Council service restructure and allocating new resource.  Posties Park now not expected to progress as anticipated.  Balance of budget to be rephased to 26/27, pending appropriate site being identified.
There is a requirement to accelerate £0.200m to 2025/26 for upfront spend requirements for Scottish Marine Technology Park (SMTP) project, including consultancy fees.  Final budget spend now anticipated to be spent by end of 2028/29, with Waterfront Walkway progress being dependent on external
factors.
The outline design has been completed and the construction cost is significantly higher than the available budget. In addition following the implementation of the Net Zero Cooperation Agreement the Council now has resilience and this will be monitored and reported to Council to consider whether the project is
still required.