Projects that are Off Track at Period 5 Appendix 2
Service Project
Approved Project Life
Cost
Revised Project
Life Cost
Project Life
Variance
Initial
Completion Date
Revised
Completion
Date
£'000 £'000 £'000
Regulatory and Regeneration RR5 - Regeneration Fund                                    3,824 3,824                 -   31/03/2028 31/03/2029
Regulatory and Regeneration RR7 - Level Up Funding                                 10,249 10,249                 -   31/12/2026 31/12/2027
Roads and Neighbourhood RN16 - Allotment Development                                      180                          180                  -   31/12/2026 31/03/2027
Roads and Neighbourhood RN17 - Waste Transfer Station                                   1,821                       1,821                  -   31/03/2026 31/03/2029
Roads and Neighbourhood
RN23 - Creation of 3 new all weather pitches at Argyll Park, Posties Park and
Mountblow playing fields                                   2,203                       2,203                  -   31/03/2026 31/03/2027
Project Name: Project - RR5 Regeneration Fund Project Manager: Elaine Troup
Initial Completion End Date: 31/03/2028 Revised End Date: 31/03/2029
How was this project initially funded: Please Detail any additional funding:
Prudential Borrowing n/a
Why is the project classified as off track and what has caused the issues identified?
What action will be taken to rectify the position? n/a
New Completion Date: 31/03/2029 Prudential Borrowing
What are the implications on the actions proposed?
Revenue Implications:-
Virement Implications:- n/a
Project Name: Project - RR7 Level Up Funding Project Manager: Elaine Troup
Initial Completion End Date: 31/12/2026 Revised End Date: 31/12/2027
How was this project initially funded: Please Detail any additional funding:
Level Up Government Grant n/a
Why is the project classified as off track and what has caused the issues identified?
What action will be taken to rectify the position? n/a
New Completion Date: 31/12/2027 Level Up Government Grant
What are the implications on the actions proposed?
Revenue Implications:-
Virement Implications:- n/a
Final budget spend now anticipated to be spent by end of 2028/29, with Waterfront Walkway progress being dependent on external factors.
Source of Funding:
n/a
Dumbarton Artizan element of project is taking longer to deliver than first anticipated, due to additional pre-commencement activities including site investigations which took longer than expected.
Source of Funding:
n/a
ITEM 14 - APPENDIX 2

Page 2

Project Name: Project - RN16 Allotment Development Project Manager: Ian Bain
Initial Completion End Date: 31/12/2026 Revised End Date: 31/03/2027
How was this project initially funded: Please Detail any additional funding:
Prudential Borrowing n/a
Why is the project classified as off track and what has caused the issues identified?
What action will be taken to rectify the position? n/a
New Completion Date: 31/03/2027 Prudential Borrowing
What are the implications on the actions proposed?
Revenue Implications:-
Virement Implications:- n/a
Project Name: Project - RN 17 Waste Transfer Station Project Manager: Gail Macfarlane
Initial Completion End Date: 31/03/2026 Revised End Date: 31/03/2029
How was this project initially funded: Please Detail any additional funding:
Prudential Borrowing n/a
Why is the project classified as off track and what has caused the issues identified?
What action will be taken to rectify the position? n/a
New Completion Date: 31/03/2029 Prudential Borrowing
What are the implications on the actions proposed?
Revenue Implications:-
Virement Implications:- n/a
Project Name: Project - RN 23 Creation of 3 new all weather pitches at Argyll Park, Posties
Park and Mountblow playing fields
Project Manager:
Ian Bain
Initial Completion End Date: 31/03/2026 Revised End Date: 31/03/2027
How was this project initially funded: Please Detail any additional funding:
Prudential Borrowing n/a
Why is the project classified as off track and what has caused the issues identified?
What action will be taken to rectify the position? Search underway for new suitable site
New Completion Date: 31/03/2027 Prudential Borrowing
What are the implications on the actions proposed?
Revenue Implications:-
Virement Implications:- n/a
Delay in tender process due to Council service restructure and allocating new resource.  Posties Park now not expected to progress as anticipated.  Balance of budget to be rephased to 26/27, pending appropriate
site being identified.
Source of Funding:
n/a
The project was paused while external funding was explored. This is now in place and therefiore the project can now proceed.
Source of Funding:
n/a
The outline design has been completed and the construction cost is significantly higher than the available budget. In addition following the implementation of the Net Zero Cooperation Agreement the Council now has
resilience and this will be monitored and reported to Council to consider whether the project is still required.
Source of Funding:
n/a