WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer – Resources
Infrastructure, Regeneration & Economic Development Committee:
12 November 2025
_________________________________________________________________
Subject: Infrastructure, Regeneration & Economic Development Capital
Budgetary Control Report 2025/26 31 August (Period 5).
1. Purpose
1.1 This report provides an update on the capital financial performance to    
31 August 2025 of those services under the auspices of the Infrastructure,
Regeneration & Economic Development Committee (IRED).
2. Recommendations
2.1 Committee is asked to:
i) Note the current position of the 2025/26 IRED capital budget.
ii) Note the revised completion dates in respect of 5 projects detailed in
appendix 2 reported to Council on 29 October 2025.
iii) Approve the reprofiling of 6 projects in appendix 3 reported to Council
on 29 October 2025.
iv) Note additional capital budget of £1.316m for plant and machinery
reported to Council on 29 October 2025. See 4.9 for further details.
v) Note additional capital budget of £0.352m for vehicle replace
programme reported Council on 29 October 2025. See 4.10 for further
details.
vi) Grant delegated authority to Chief Officer for Roads, Neighbourhood
and Transport, in consultation with the Procurement Manager, to award
contracts in relation to procurement of waste collection vehicles.
3. Background
3.1 On 5 March 2025 the Council approved the updated General Services Capital
Plan for 2025/26 to 2034/35. The three years from 2025/26 to 2027/28 were
approved in detail with the remaining years being indicative. The budget
agreed under the auspice of IRED Committee was £56.791m for 2025/26 and
£209.142m for the project life budget.
ITEM 14

Page 2

4. Main Issues
4.1 Exhibit 1 sets out the revised capital budget at period 3 as reported to Council
on 27 August 2025.
Exhibit 1: Revised Capital Budget as at 30 June 2025.
2025/26
(£m)
Project Life
(£m)
Capital Budget Agreed 5 March 2025 56.791 209.142
Updates reported to Council on 27 August plus
adjustments for year-end carried forward
balances
0.341 0.971
Reprofiling reported to Council on 27 August
(3.109) 4.009
Revised Capital Budget as at Period 3 54.023 214.122
4.2 Progress against the 2025/26 capital plan is detailed in:
Appendix 1 – Project Life Summary by Chief Officer
Appendix 2 – Off Track Projects
Appendix 3 – Changes to Capital Plan for Noting
Appendix 4 – All Approved Projects
4.3 The overall programme summary report at Appendix 1 shows that planned
expenditure against the budget is currently on track.
4.4 Appendix 2 highlights 5 projects currently showing as off-track, all of which are
due to revised completion dates.
 Project RR 5 (Regeneration Fund) is off track due to the Waterfront
Walkway progress being dependent on external factors, with an
anticipated completion date of 31 March 2029.
 Project RR 7 (Level Up Funding) is off track due to the project delivery
taking longer than initially expected. Resulting in an updated
completion date of 31 December 2027.
 Project RN 16 (Allotment Development) is off track due to a delay in the
tender process as a result of a service restructure and allocation of new
resources. The project completion date has been extended to 31 March
2027.
 Project RN 17 (Waste Transfer Station) has currently been paused as
the construction cost is significantly higher than the available budget. In
addition, following the implementation of the Net Zero Cooperation
Agreement the Council now has resilience and this will be monitored
and reported to Council to consider whether the project is still required.
The completion date for the project has therefore been extended to 31
March 2029 while this monitoring and discussions are taking place.

Page 3

 Project RN 23 (Creation of 3 new all weather pitches at Argyll Park,
Posties Park and Mountblow playing fields) is off track due to a delay in
the tender process because of Council service restructure and the
allocation of new resources. Posties Park (to be renamed to
commemorate Lachie Stewart) is now not expected to progress as
anticipated, the balance of the budget is being rephased to 2026/27
pending an appropriate site being identified.
4.5 Appendix 3 highlights 6 projects where the project expenditure requires to be
reprofiled but there is no need for approval of additional budget.
4.6 Exhibit 2 sets out the revised capital budget at period 5 assuming approval by
Council on 29 October 2025 of all recommendations contained within this
report.
Exhibit 2: Revised Capital Budget
2025/26
(£m)
Project Life
(£m)
Capital Budget as at 30 June 2025 54.023 214.122
New Funding – RES 15 Design, Creation,
Installation of Digital Content for Glencairn House
(Para 4.8)
0.187 0.187
New Funding – RN 31 Bus Infrastructure Fund
(Para 4.8)
0.050 0.050
New Funding – RN 32 People and Places –
Transport Scotland (Para 4.8)
0.035 0.035
New Funding – RN 34 Nature Restoration Fund
(Para 4.8)
0.185 0.185
New Funding – RN 35 Road Safety Improvement
Fund (Para 4.8)
0.185 0.185
Additional Funding – RN 25 Active Travel (Para
4.8)
0.306 0.306
Additional Funding – RN 27 Implementation
20mph Speed Limits (Para 4.8)
0.458 0.458
Added RN 33 Shared Prosperity Funding – Open
Places (Para 4.8)
0.396 0.396
Approved RN 30 Capital Bid – Plant and
Machinery Replacement (Para 4.9)
0.515 1.315
Approved Capital Bid – Vehicle Replacement
Strategy (Para 4.10) (added to RN 5)
0.352 0.352
Added RR 12 Hybrid Meetings Equipment (Para
4.8)
0.053 0.053
Proposed revised Capital Budget as at Period
5
56.745 217.644
Reprofiling over project life (Appendix 3) (4.237) 0
Proposed revised Capital Budget as at Period
5 subject to Council Approval
52.268 217.644

Page 4

4.7 Appendix 4 shows all projects with approved in year and project life budgets
as well anticipated expenditure. It highlights that the 2025/26 budget is
£56.745m. Spend as at period 5 is £7.951m (15.14%) of the current forecast
spend of £52.508m
4.8 Other minor changes to the capital plan included in the summarised plan in
appendix 4 are:
 New funding has been received from Scottish Government of £0.050m for
Bus Infrastructure Fund (RN 31) to support improvements to bus
infrastructure and accessibility.
 New funding has been received from Transport Scotland of £0.035m for
People and Place Local Authority Direct Award (RN 32) for active and
sustainable travel behaviour change programme.
 New funding has been received from Scottish Government of £0.185m for
Nature Restoration Fund (RN 34) to support approaches to restoring
biodiversity.
 New funding has been received from Transport Scotland of £0.185m for
Road Safety Improvement Fund (RN 35).
 Additional funding from Scottish Government for Active Travel (RN 25) of
£0.306m to support and promote active travel within the authority and to
improve active travel links.
 Additional funding from Transport Scotland for Implementation of 20mph
Speed Limits (RN 27) of £0.458m.
 Shared Prosperity Funding (RN 33) of £0.396m for open places such as
West Bridgend Community Space and Allotments.
 Addition of Hybrid Meetings Equipment (RR 12) approved at Council on
the 27 August 2025 of £0.053m to replace conference units and
microphones to allow hybrid meetings to continue with improved sound
quality
 New funding from Strathleven Foundation for Inspiring Change for the
Design, Creation, Installation, and ongoing Management of Digital Content
for Glencairn House (RES 15) of £0.187m.
4.9 Members are asked to note a capital budget of £1.316m for the plant and
machinery replacement program.
This bid has been reviewed by the Strategic Asset Management Group who
recommend that £1.316m is added to the Capital plan to allow the Roads and
Neighbourhood team to replace plant and machinery which is no longer fit for
purpose.

Page 5

This project has been included in appendix 4 (RN 30).
4.10 Members are asked to note a capital budget of £0.352m for the vehicle
replacement strategy.
This bid has been reviewed by the Strategic Asset Management Group who
recommend that £0.352m is added to the Capital plan to allow the Roads and
Neighbourhood team to replace vehicles which are no longer fit for purpose.
This project has been included in appendix 4 (included within RN 5).
4.11 The Council’s Standing Orders have been changed to have contract
authorisation submitted to service committees and delegated authority sought
to appoint the contractor of the returned tender if the contract cost is within the
approved budget and the tender is in line with normal tender parameters.
4.12 The Council is required to procure waste vehicles for the collection of food
waste. This will allow the recycling of food waste separately from garden
waste. The budget will, in part, be met from revenue income received for
Extended Producer Responsibility. The remaining required budget will be
subject to a capital bid through the normal procedures or from existing
revenue budgets.
5. Option Appraisal
5.1 No option appraisal was required for this report.
6. People Implications
6.1 There are no people implications.
7. Financial and Procurement Implications
7.1 The report notes the projected in-year financial position for capital budgets.
8. Risk Analysis
8.1 The main risks are as follows:
(a) The reported variances should be viewed in the knowledge that there are
a number of variable factors which could arise between now and 31
March which could affect the year end results for capital budgets.
(b) As a consequence of current market conditions, inflation is at an all-time
high and interest rates continue to be volatile. To forecast for the full year
costs budget assumptions have been required. These assumptions
continue to change regularly and therefore it is likely the projected year
end budgetary position will change from that reported.
9. Equalities Impact Assessment (EIA)
9.1 No equalities impact assessment was required in relation to this report.
10. Environmental Sustainability

Page 6

10.1 No assessment of environmental sustainability was required in relation to this
report.
11. Consultation
11.1 All services involved in delivering the capital budgets have been consulted in
the compilation of this report.
12. Strategic Assessment
12.1 Proper budgetary control and sound financial practice are cornerstones
of good governance and support Council and officers to pursue the
strategic priorities of the Council’s current Strategic Plan. This report
forms part of the financial governance of the Council.
______________
Laurence Slavin
Chief Officer – Resources
Date: 30 October 2025
Person to Contact:
Jackie Nicol-Thomson
Council Offices, Church Street, Dumbarton
E-mail: jackie.nicolthomson@west-dunbarton.gov.uk
Appendices:
Appendix 1 - Project Life Summary
Appendix 2 - Off Track Projects
Appendix 3 - Changes to Capital Plan and Implications
Appendix 4 - All Projects Approved
Background Papers: 
General Services Capital Plan Update - Council 5 March 2025
Wards Affected          
All Wards