WEST DUNBARTONSHIRE COUNCIL
Report by Chief Officer - Resources
Infrastructure, Regeneration & Economic Development Committee:
12 November 2025
___________________________________________________________________
Subject: Infrastructure, Regeneration & Economic Development Revenue
Budgetary Control Report 2025/26 to Period 5 (30 August 2025)
1. Purpose
1.1 This report provides an update on the revenue financial performance to 30
August 2025 of those services under the auspices of the Infrastructure,
Regeneration & Economic Development Committee (IRED).
2. Recommendations
2.1 Members are asked to:
 note a projected adverse variance against budget of £0.745m (4.34%
of total budget).
 note the current projected use of earmarked reserves of £0.504m.
3. Background
Revenue
3.1 At the meeting of West Dunbartonshire Council on 5 March 2025, Members
agreed the revenue estimates for 2025/26. A total net budget of £17.042m
was approved for IRED services. Since then, budget changes to the value of
£0.115m have occurred as detailed in the table below:
Description £m
Budget Agreed March 2025 17.042
Additional budget for pay award 0.147
Movement of budget between Economic Development and
Regulatory to right size employee budgets (0.032)
Revised Budget 17.157
4. Main Issues
Revenue Budget
4.1 The summary report at Appendix 1 identifies a projected adverse variance
(overspend) of £0.745m (4.34% of total budget). Detailed service reports are
attached at Appendix 2. 
ITEM 13

Page 2

4.2 Of the 13 services monitored 5 are showing either a favourable or nil variance,
with 8 services showing an adverse variance. Comments are shown in
Appendix 3 when there are projected net annual variances greater than
£0.050m and where the net variance is below £0.050m but there are offsetting
variances of over £0.050m within the service while the table below shows the
main reasons for the movement in the outturn from period 3.
 
 
£m £m
Net Underlying Adverse Variance at Period 3 0.987
Movement in Service
Variances
Explanation
RNT
Roads Use of the smoothing fund for delayed saving
option
(0.150)
Working for You Employee costs lower due to savings option
being implemented earlier than anticipated
(0.236)
Ground Maintenance &
Street Cleaning
Increased expenditure due to re-introduction of
grass cutting
0.240
Grounds Maintenance
& Street Cleaning
Reduction in employees costs due to vacancies (0.051)
Waste Increase in costs relating to tonnage 0.067
Corporate Functions
Corporate Assets Reduction in employees costs due to vacancies (0.061)
Other small variances across the Services (0.051)
Total Movement (0.242)
Net Underlying Adverse Variance at Period 5 0.745
4.3 Services are anticipating the use of £0.504m (Period 3: £0.030m) of
earmarked reserves. Information on the earmarked reserve spend is shown in
Appendix 4.
4.4 Appendix 5 to the report summarises the current position against the saving
options agreed by council as part of setting the 2025/26 budget.
5. People Implications
5.1 There are no people implications.
6. Financial Implications
6.1 Other than the financial position noted above, there are no financial
implications of the budgetary control report. Officers are currently reviewing
budgets and projections with a view to improving the position by financial year
end and progress will be highlighted in future reports to committee.

Page 3

7. Risk Analysis
7.1 The present variances should be viewed in the knowledge that there are a
number of variable factors which could arise between now and 31 March and
which could affect the year end results.
8. Equalities Impact Assessment (EIA)
8.1 The report is for noting and therefore no Equalities Impact Assessment was
completed for this report.
9 Consultation
9.1 The views of both Finance and Legal services have been requested on this
report and both have advised there are neither any issues nor concerns with
the proposal. As the report is for noting no further consultation is envisaged.
10. Strategic Assessment
10.1 Proper budgetary control and sound financial practice are cornerstones of
good governance and support Council and officers to pursue the five strategic
priorities of the Council’s Strategic Plan. This report forms part of the financial
governance of the Council. This report is for noting and, therefore, does not
directly affect any of the strategic priorities.
Laurence Slavin
Chief Officer – Resources 
Date:   9 October 2025
Person to Contact: Jackie Thomson - Business Unit Finance Partner, 16
Church Street, Dumbarton, G81 1QL.
e-mail jackie.nicolthomson@west-dunbarton.gov.uk
Appendices: Appendix 1 - Summary Budgetary Position (Revenue)
Appendix 2 - Detailed Budgetary Position (Revenue)
Appendix 3 - Variance Analysis (Revenue)
Appendix 4 - Earmarked Balances
Appendix 5 - Efficiencies & Management Adjustments
Background Papers: None