Item 9 - Appendix 1

West Dunbartonshire Council · 13 August 2025
Back to Infrastructure, Regeneration & Economic Development Committee — 13 August 2025 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Summary at Period 3
Project Life
Budget
Project Life
Forecast
Spend
Project Life
Variance On Track/Complete Off Track
£'000 £'000 £'000
Resources 35,868             35,868            -                7                                0
Regulatory and Regeneration 56,905             56,905            -                6                                4
Roads and Neighbourhoods 121,336           121,348          13                 29                              1
Total 214,109           214,121          13 42 5
ITEM 9 - APPENDIX 1