WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer – Resources
Infrastructure, Regeneration & Economic Development Committee: 
13 August 2025
_________________________________________________________________ 
Subject: Infrastructure, Regeneration & Economic Development Capital
Budgetary Control Report 2025/26 30 June (Period 3). 
1. Purpose
1.1 This report provides an update on the capital financial performance to     
30 June 2025 of those services under the auspices of the Infrastructure,
Regeneration & Economic Development Committee (IRED). 
2. Recommendations
2.1 Committee is asked to: 
i) Note the current position of the 2025/26 IRED capital budget. 
ii)  Note the additional capital budget of £0.013m in respect of Vale of
Leven Cemetery which is subject to formal approval at Council on 27
August 2025, detailed in appendix 2. 
iii) Note the revised completion dates in respect of 4 projects detailed in
appendix 2 to be formally approved at Council on 27 August 2025. 
iv) Approve the reprofiling of 7 projects in appendix 3 to be formally
approved at Council on 27 August 2025 
v) Grant delegated authority to Chief Officer Roads & Neighbourhood, in
consultation with the Procurement Manager, to award any procurement
and contract awards for projects related to Roads – Infrastructure
recurring budget using appropriate procurement routes. 
vi) Grant delegated authority to Chief Officer Roads & Neighbourhood, in
consultation with the Procurement Manager, to award any procurement
and contract awards for projects related to Strathclyde Partnership for
Transport provided the contract costs remain within the approved
budget of £0.278m as set out in Appendix 4. 
3. Background
3.1 On 5 March 2025 the Council approved the updated General Services Capital
Plan for 2025/26 to 2034/35. The three years from 2025/26 to 2027/28 were
approved in detail with the remaining years being indicative. The budget
agreed under the auspice of IRED Committee was £56.791m for 2025/26 and
£209.142m for the project life budget. 
4. Main Issues
ITEM 9

Page 2

4.1 Exhibit 1 sets out the revised capital budget at period 3 subject to Council
approving the changes noted in this report when it meets on 27 August 2025. 
Exhibit 1: Revised Capital Budget as at 30 June 2025. 
2025/26
(£m)
Project Life
(£m)
Capital Budget Agreed 5 March 2025 56.791 209.142
Additional budget for Capital agreed at Council 6
March 2024 (Para 4.7)
0.095 0.575
Additional budget for Capital agreed at Council 5
March 2025 (Para 4.7) 0 0.150
Additional budget for Hot Box Vehicles per
Management Adjustment RN09 agreed at Council
18 December 2024 (Para 4.7) 0.800 0.800
Revised Capital Budget as at Period 3 57.686 210.667
Reprofiling from 2024/25 4.009 4.009
Reprofiling over project life (Appendix 3) (7.118) 0
Approved Capital Bid – Roads Lining and Signing
(Para 4.8) 0.150 0.150
Funding to be returned for Regeneration Capital
Grant Funding for Clydebank Activity Centre
(Para 4.9) (0.717) (0.717)
Additional spend Vale of Leven Cemetery (Para
4.3) 0.013 0.013
Revised Capital Budget as at Period 3 subject
to Council approval 54.023 214.122  
4.2 Progress against the 2025/26 capital plan is detailed in: 
Appendix 1 – Project Life Summary by Chief Officer 
Appendix 2 – Off Track Projects 
Appendix 3 – Changes to Capital Plan for Noting 
Appendix 4 – All Approved Projects 
4.3 The overall programme summary report at Appendix 1 shows that planned
expenditure against the budget is currently off track by £0.013m for the
Vale of Leven Cemetery. The additional spend was as a result of more
imported soil being required than was originally anticipated at design
stage. 
4.4 Appendix 2 highlights that: 
• Project RN16 (Vale of Leven Cemetery) is off track due to an
overspend of £0.013m as reported above (Para 4.3). 
• Project RR 2 (Installation of Solar PV at Clydebank Leisure Centre) is
off track due to planning permission and building control requirements.
This means that the project end date has been extended by 1 year to
31 March 2027.

Page 3

• Project RR 3 (Leisure Energy projects – air handling units, upgrade
lighting, circulating pumps and draught proofing) is off track due to a
revised completion date as the cost submitted through the single tender
framework was double the budget allocated. This means there is
insufficient budget to deliver the project, the council is not being asked
to approve further capital allocation at the current time as officers will
first explore alternative delivery approaches to achieve the intended
outcomes within existing resource. The completion date for the project
has been extended to 31 March 2027 while this is ongoing. 
• Project RR 7 (Levelling Up Fund) is off track due to the project delivery
taking longer than initially expected. Resulting in an updated
completion date of 31 December 2026. 
• Project RR 10 (Clyde Mission Catalyst Fund) is off track due to project
development taking longer than expected as timescales of the external
partner are outwith our control. The project completion date has been
extended by a year to the 31 March 2027. 
4.5  Appendix 3 highlights 7 projects where the project expenditure requires to be
reprofiled but there is no need for approval of additional budget. 
4.6 Appendix 4 shows all projects with approved in year and project life budgets
as well anticipated expenditure. It highlights that the 2025/26 budget is
£54.010m. Spend as at period 3 is £4.508m (8.34%) of the current forecast
spend of £54.023m 
4.7  Other changes to the capital plan included in the summarised plan in
appendix 4 are: 
• The Community Sports Facility at Millburn (RES 12) of £0.500m and Holm
Park Community Football Academy Accessibility Project (RES 13) of
£0.075m have been added onto the Capital Plan. These items were
previously omitted from the capital plan as they had been managed
through operational arrangements but were approved by Council on the 6th
of March 2024. They are now expected to incur expenditure during the
2025/26 financial year and have therefore been incorporated into the
capital plan. 
• It was agreed at the council meeting on the 5th of March 2025 that the cost
of living capital fund would contribute £0.150m towards a new football pitch
at Faifley Knowes (RES 14). 
• The purchase of hot box vehicles in line with the Management Adjustment
RN09 taken at Council on the 18th of December 2024 (included in RN 5).
At the time of approval cost was unknown, this has now been confirmed at
£0.800m and can be added to the capital plan. 
4.8  Members are asked to note an additional capital budget of £0.150m to fund
the signage and road markings to support our decriminalised parking
enforcement, this is subject to formal approval at Council on 27 August 2025

Page 4

This bid has been reviewed by the Strategic Asset Management Group who
recommend that £0.150m is added to the Capital plan to allow the Roads and
Neighborhoods team to implement the decriminalised parking enforcement. 
This project has been included in appendix 4 (RN 30). 
4.9 Scottish Government has requested that the grant funding for Clydebank
Activity Centre be returned due to the original community groups withdrawing
their interest because of external funding issues. Regeneration approached
Scottish Government with a proposal for a different local group and a
departure from the original proposal but this was unsuccessful. 
The £0.717m removed from the capital plan at the moment is the unspent
budget for this project with £0.040m already outlaid. We are awaiting
confirmation from Scottish Government on whether professional fees and
other outlays commissioned are required to be returned.   
Shown on appendix 4 under RR 10. 
4.10  This report also asks the Committee to approve any procurement and contract
award of projects under the Roads - Infrastructure recurring budget within
Roads to be made by the Chief Officer Roads & Neighbourhood, in
consultation with the Procurement Manager provided the contract costs
remain within the approved budget and the tenders adhere to standard
procurement parameters. This is required due to the time constraints required
to deliver spend in each financial year. There is a risk should this not be
approved that projects will not be able to be carried out in the financial year
which will impact on the delivery of the service. 
4.11  This report also asks the Committee to approve any procurement and contract
award of projects under the Strathclyde Partnership for Transport budget
within Roads to be made by the Chief Officer Roads & Neighbourhood, in
consultation with the Procurement Manager provided the contract costs
remain within the approved budget of £0.278m set out in Appendix 4 and the
tenders adhere to standard procurement parameters. This is required due to
the time constraints required to deliver spend in the financial year. There is a
risk should this not be approved that the project will not be able to be carried
out in the financial year. 
5. Option Appraisal
5.1 No option appraisal was required for this report. 
6. People Implications
6.1 There are no people implications. 
7. Financial and Procurement Implications
7.1 The report notes the projected in-year financial position for capital budgets. 
8. Risk Analysis

Page 5

8.1 The main risks are as follows: 
(a) The reported variances should be viewed in the knowledge that there
are a number of variable factors which could arise between now and 31
March which could affect the year end results for capital budgets. 
(b) As a consequence of current market conditions, inflation is at an all-time
high and interest rates continue to be volatile. To forecast for the full
year costs budget assumptions have been required. These assumptions
continue to change regularly and therefore it is likely the projected year
end budgetary position will change from that reported. 
9. Equalities Impact Assessment (EIA)
9.1 No equalities impact assessment was required in relation to this report. 
10. Environmental Sustainability
10.1 No assessment of environmental sustainability was required in relation to this
report. 
11. Consultation
11.1 All services involved in delivering the capital budgets have been consulted in
the compilation of this report. 
12. Strategic Assessment
12.1 Proper budgetary control and sound financial practice are cornerstones
of good governance and support Council and officers to pursue the
strategic priorities of the Council’s current Strategic Plan. This report
forms part of the financial governance of the Council. 
______________
Laurence Slavin
Chief Officer – Resources
Date: 15 July 2025 
Person to Contact: 
Lynsey Dickson
Council Offices, Church Street, Dumbarton
E-mail: lynsey.dickson@west-dunbarton.gov.uk 
Appendices: 
Appendix 1 - Project Life Summary 
Appendix 2 - Off Track Projects
Appendix 3 -  Changes to Capital Plan and Implications
Appendix 4 -  All Projects Approved 
Background Papers:  
General Services Capital Plan Update - Council 5 March 2025

Page 6

Wards Affected           
All Wards