WEST DUNBARTONSHIRE COUNCIL
Report by Chief Officer - Resources
Committee: Infrastructure, Regeneration and Economic Development
Committee 21 May 2025
Subject:Resources Delivery Plan 2024/25 - Asset Management Year-end
Progress &
Resources Delivery Plan 2025/26 - Asset Management
1 Purpose
1.1 This report sets out the year-end progress of the 2024/25 Delivery Plan and
presents the new 2025/26 Delivery Plan, both in relation to Asset
Management.
2 Recommendations
2.1 It is recommended that Committee notes the progress achieved at year-end
and the new Delivery Plan for 2025/26.
3 Background
3.1 In line with the Strategic Planning & Performance Framework, each Chief
Officer develops an annual Delivery Plan which sets out actions to help deliver
the Strategic Plan and address the performance challenges and service
priorities identified in the planning process. The Plan also provides an
overview of services and resources, including employees and budgets, sets
out the performance indicators (PIs) for monitoring progress and considers the
relevant risks.
3.2 In the last few months of 2024/25, several services and teams across the
Council were realigned to other Chief Officer areas. For consistency and
transparency, the year-end progress reports reflect the content of the 2024/25
delivery plans reported to the relevant committees at the beginning of that
year, with none of the organisational changes that took place in-year included.
Those changes are, however, reflected in the new delivery plans for 2025/26.
4 Main Issues
2024/25 Year-end Progress
4.1 The 2024/25 Delivery Plan was presented to Infrastructure, Regeneration and
Economic Development Committee on 22 May 2024 and mid-year progress
reported on 6 November 2024.
4.2 Full details of year-end progress are set out in Appendix 1.
ITEM 9

Page 2

4.3 The progress of the Delivery Plan’s five Asset Management actions is
summarised below:
Progress No. (%)
Completed 5 (100%)
4.4 Year-end data is available for all four of the Delivery Plan’s Asset
Management PIs. The performance of those PIs is summarised below:
Performance Against Target No. (%)
Target met or exceeded 4 (100%)
Performance Over Time No. (%)
Improved over short term (or maintained a high
level of performance)
4 (100%)
Improved over longer term (or maintained a high
level of performance)
4 (100%)
2025/26 Delivery Plan
4.5 An extract from the 2025/26 Delivery Plan is set out at Appendix 2. This
outlines Asset Management’s achievements and challenges over the past
year, as well as the priorities for the year ahead. These include:
 progressing the disposal of key strategic sites
 completing the redevelopment of Glencairn House
 progressing the Faifley Community Campus development
 progressing the buildings upgrades programme
 progressing the depot refurbishment programme
 supporting Council services to deliver the asset related savings agreed by
Council
 engaging with relevant community groups over the potential to lease
Dalmuir Golf Course
4.6 Implementation of the Delivery Plan will be monitored by the management
team with mid-year and year-end progress reported to Infrastructure,
Regeneration and Economic Development Committee around November
2025 and May 2026 respectively.
5 People Implications
5.1 There are no direct people implications arising from this report.
6 Financial & Procurement Implications
6.1 There are no direct financial or procurement implications arising from this
report.

Page 3

7 Risk Analysis
7.1 Failure to deliver on the actions assigned to Asset Management may have a
direct impact on the delivery of the Council’s Strategic Plan. It is essential that
remedial action is taken to ensure strategic delivery plans achieve the
commitments detailed.
8 Equalities Impact Assessment
8.1 Screening and impact assessments will be carried out on specific activities as
required.
9 Consultation
9.1 The delivery plans were developed through consultation with officers from the
strategic service areas.
10 Strategic Assessment
10.1 The delivery plans set out actions to support the successful delivery of the
strategic priorities and objectives of the Council.
Chief Officer: Laurence Slavin
Service Area: Resources
Date: 30 April 2025
_____________________________________________________________
Person to Contact: Lynn Henderson
lynn.henderson@west-dunbarton.gov.uk
Appendices: Appendix 1: Resources Delivery Plan 2024/25 - Asset
Management Year-end Progress
Appendix 2: Resources Delivery Plan 2025/26 - Asset
Management
Background Papers: Resources Delivery Plan 2024/25 - Asset Management,
Infrastructure, Regeneration and Economic Development
Committee, 22 May 2024
Resources Delivery Plan 2024/25 - Asset Management
Mid-year Progress, Infrastructure, Regeneration and
Economic Development Committee, 6 November 2024
Strategic Planning & Performance Framework 2022/27
Wards Affected: All