Appendix 1: Regulatory & Regeneration Delivery Plan 2024/25 – Economic Development Year-end Progress
1. Our Environment
Our resources are used in an environmentally sustainable way
2023/24 2024/25
Performance Indicator Value Status Value Target Short
Trend
Long
Trend Note Owner
Tonnage of carbon dioxide
emissions from Council operations
and assets
19,342
Work to confirm the 2023/24 value is
on-going, delayed due to vacancies
and resourcing challenges. Data for
2024/25 will be available in
November when all utilities bills and
waste figures are validated in
advance of preparing our annual
mandatory climate change report for
submission to Scottish Government.
Elaine
Troup
Action Status Progress Due Date Note Owner
Co-ordinate, monitor and report
the progress of the Council’s
Climate Change Action Plan for
2024/25
31-Mar-
2025
Completed as planned. The Climate Change Action Plan
has been completed for 2024/25 and new actions
developed for the 2025/26 Plan.
Elaine
Troup
Develop a Local Heat and
Energy Efficiency Strategy and
Delivery Plan
31-Mar-
2025
Completed as planned. Public consultation on the draft
strategy closed in June 2024 and the strategy, with
outline delivery plan, was published at the end of
September 2024. Work is ongoing to develop a detailed
delivery plan, with publication due mid-2025.
Elaine
Troup
ITEM 8 - APPENDIX 1

Page 2

Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Inability to
reduce carbon
footprint in line
with targets
The risk that the Council will be
unable to achieve net zero
emissions by 2045, both in relation
to mitigating carbon emissions and
adapting to the impacts of climate
change. Net zero refers to
achieving an overall balance
between emissions produced and
emissions taken out of the
atmosphere. This target has been
developed in a way that mirrors the
emission reduction trajectory set
by the Scottish Government in light
of the Climate Emergency.
08-Apr-
2025
The risk of not delivering carbon
emissions targets remains
moderate. Progress is being
made through the delivery of the
Climate Change Action Plan;
however, pace of delivery has
been, and will continue to be,
impeded due to lack of internal
resource and additional funding
to deliver. This risk will be
reviewed again once the Scottish
Government publishes the
revised net-zero targets.
Elaine
Troup
Our neighbourhoods are sustainable and attractive
Action Status Progress Due Date Note Owner
Promote the next phase of
Queens Quay Housing
31-Mar-
2025
Completed as planned. The Council continues to meet
the owner and agent to progress opportunities for future
housing development at Queens Quay. Under the terms
of the Joint Venture agreement, the owner and agent of
Queens Quay are responsible for the commercial
discussions on future housing development. The
challenges faced at the site have also been raised with
senior officials at the Scottish Government. 
Elaine
Troup

Page 3

2. Our Economy
Our area has the infrastructure for sustainable and inclusive growth where businesses can flourish
2023/24 2024/25
Performance Indicator Value Status Value Target Short
Trend
Long
Trend Note Owner
Number of businesses given
advice and assistance to start up
through Business Gateway
200 190 180
190 clients were assisted to start-
up a new business, exceeding the
target of 180 set for the year.
Gillian
Scholes
Number of business gateway start-
ups per 10,000 population 22.54 21.41 19.78
There were 21.41 business
gateway start-ups per 10,000
population, exceeding the target of
19.78 set for the year.
Gillian
Scholes
Proportion of properties receiving
superfast broadband 99.3% 99%
2024/25 data for this LGBF
indicator will be available in
December 2025 following
publication by the Improvement
Service. Based on the most recent
LGBF comparative data for the
previous year (2023/24),
performance at 99.3% was better
than the Scottish average of
95.9% with a ranking of 1st of 32
local authorities, consistent with
the previous year. 
Gillian
Scholes

Page 4

Action Status Progress Due Date Note Owner
Implement, monitor and report
the progress of the Economic
Development Strategy
31-Mar-
2025
Completed as planned. The Economic Development
Strategy annual update was reported to Infrastructure,
Regeneration & Economic Development Committee in
November 2024. This Strategy covers the period
2022/27 and will continue in the coming year. 
Elaine
Troup
Deliver key regeneration sites
across West Dunbartonshire
31-Mar-
2025
Completed as planned. Work has progressed on the key
regeneration sites across the Council area that include
the three town centres, and the strategic sites of Queens
Quay, Exxon and the Carless site. Milestones relating to
the Scottish Marine Technology Park, Exxon
Infrastructure Project and our three town centres have
been successfully completed. This is a multi-year action
that will continue into 2025/26.
Elaine
Troup
Explore commercial
opportunities in our town
centres and wider regeneration
sites
31-Mar-
2025
Completed as planned. The Planning Permission in
Principle application for the Artizan redevelopment
masterplan in Dumbarton was submitted to the Council
in July 2024. This very complex application has taken
significant time to process and will be considered by the
Council later in 2025. The Long-Term Plan and the
accompanying 3 Year Investment Plan for Clydebank
were submitted to UK Government in October 2024.
Following the general election in 2024, the programme
has been reformed and renamed Plan for
Neighbourhoods. A Regeneration Plan (which will
replace the Long-term Plan and the Investment Plan) is
due to be submitted to the UK Government in
Spring/Summer 2025.
Magda
Swider

Page 5

Action Status Progress Due Date Note Owner
Develop and implement
business support interventions
through the UK Shared
Prosperity Fund
31-Mar-
2025
Completed as planned. UK Shared Prosperity Fund
interventions have been developed and widely promoted
through the Council website, social media, partner
organisations and directly to eligible businesses. The
Business Support team are continuing to promote the
grant support and appraise applications.
Gillian
Scholes
Support town centre
revitalisation
31-Mar-
2025
Overdue. We have made good progress with the
development of projects in Dumbarton and Alexandria,
including obtaining planning permission and appointing a
contractor for the Artizan redevelopment (Phase 1) and
appointing a design team for Mitchell Way project.
However, the Alexander Street project took longer than
anticipated due to prolonged consultations with
stakeholders. The tender process has been delayed, and
it is now expected that the contractor will be appointed in
summer 2025.
Magda
Swider
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Failure to
deliver Queens
Quay
Masterplan
Following completion of Council
investment there is a risk the
housing plot sales do not
materialise in the next 3-7 years,
with implications for the return
on investment and the business
case for the District Heating
Network.
14-Mar-
2025
Risk remains unchanged. Focus
continues on landowner agreeing
a housing proposal with a
potential developer. Delivery
embedded into workstreams to
promote development at site.
Michael
Mulgrew;
Elaine
Troup

Page 6

Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Inability to meet
demands of
Council to
progress
regeneration
projects within
desired
timescales
The number and complexity of
regeneration projects is putting
considerable strain on the
resources available which can
be exacerbated by delays out
with the control of the service
and when pinch points on
different projects occur at
roughly the same time.
14-Mar-
2025
Risk remains unchanged.
Individual projects continue to
progress, reducing the likelihood
of undesirable outcomes.
Embedded into workstreams to
ensure sufficient resource to
support delivery of projects within
required timescales.
Michael
McDougall;
Michael
Mulgrew;
Elaine
Troup
Action Status
Overdue
Completed
PI Status
Target met or exceeded
Risk Status
Warning
OK
Long Term Trends
Declining
Short Term Trends
Declining