Appendix 1 - R&N Delivery Plan 24/25 Year-end Progress 
1. Our communities 
Objective 1. Our neighbourhoods are safe, resilient and inclusive 
Performance Indicator
2023/24 2024/25
Owner
Value Status Value Target Short Trend Long Trend Note
Percentage of non serious road related defects
repaired within 7 working days of being reported 91.4%  93.3% 85%   Target exceeded. Improvement
from previous year. Liam Greene
Percentage of routine road related defects repaired
within 28 working days of being reported 69.25%   85%   Data not available until mid May
due to response times. Liam Greene
Percentage of emergency road related defects
repaired within 4 hours of being reported 96.9%  99.08% 95%   Target exceeded. Improvement
from previous year. Liam Greene
RL2: Percentage of all traffic light repairs
completed within 48 hours 100%  98% 98%   Target met.  Liam Greene
RL3: Percentage of all street light repairs
completed within 7 days 98%  97.7% 95%   Target exceeded Liam Greene 
ITEM 7b - APPENDIX 1

Page 2

Code Action Status Progress Due Date Note Owner
R&N/24-
25/R&T/02
Pavement parking, develop and implement
the enforcement strategy in line with
Scottish guidance next phase  
31-Mar-2025
Action overdue. This will be progressed
following the implementation of parking
enforcement. This action will carry over to
2025/26
Liam Greene
R&N/24-
25/R&T/03
Progress a plan to introduce Parking
Enforcement   31-Mar-2025
Action completed as planned. Service
continues to work towards introduction and
currently on programme for 2025
implementation. Communication strategy
being developed which will include elected
member briefing. Application to transfer
powers submitted and approved. Enforcement
will commence in 2025/26. 
Liam Greene 
Objective 2. Our resident’s health and wellbeing remains a priority 
Action Status Progress Due Date Note Owner
Upgrade 8 play parks and construct 4 new
MUGA's   31-Mar-2025
Action overdue. There are two playparks
outstanding and will be completed by end of June
2025, these are, Pappert and Ross Head. Delayed
due to the contractor’s capacity to complete the
works. This action will carry over to 2025/26.
Ian Bain
Prepare a plan to increase the number of 4G
pitches   31-Mar-2025
Action overdue. Plan has been prepared. The issue
of tender documents has been paused as there have
been a number of formal objections at planning
stage. Awaiting planning decision scheduled for May
2025. Action will carry over to 2025/26.
Ian Bain 
Objective 3. Our residents are supported to increase life and learning skills

Page 3

Action Status Progress Due Date Note Owner
Progress Faifley Campus in line with agreed
programme   31-Mar-2025
Action completed as planned. A review of the
programme and budget was carried out. Phase 1 of
the programme is on time and within revised
budget. Due to internal reorganisation the project
transferred to the Asset Team
Michelle Lynn 
2. Our Environment 
Objective 4. Our local environment is protected, enhanced and valued 
Performance Indicator
2023/24 2024/25
Owner
Value Status Value Target Short Trend Long Trend Note
Tonnage of biodegradable municipal waste
landfilled 16,432  540 13,300  
Target exceeded with significant
improvement which is a result of
the actions that have been
completed. Our overall waste sent
to landfill has reduced by more than
15,800 tonnes per year. 
Ian Bain 
% Residents satisfied with the Waste service
overall 82%  60% 82%  
Target significantly missed. Recent
changes across the service,
particularly the introduction of a
charge for garden waste (brown
bin) collection due to budget
reductions have impacted on the
satisfaction.
Ian Bain
Percentage of missed bins collected within 3
working days of being reported 97%  95% 95%  
Target met. The introduction of the
new online chat bot to report
missed bins has improved the
process for both citizens and the
Waste team.
Ian Bain

Page 4

Performance Indicator
2023/24 2024/25
Owner
Value Status Value Target Short Trend Long Trend Note
Percentage of offensive graffiti removed within 24
hours of being reported 100%  100% 100%   Target met. Ian Bain
Percentage of non offensive graffiti removed within
5 working days of being reported 100%  100% 100%   Target met. Ian Bain
% of total household waste that is recycled 35.1%  54.5% 60%  
Target marginally missed. However,
we have made significant
improvement over the year because
of the actions that have been
completed resulting in our overall
total of waste that is categorized as
being recycled has increased by
almost 20%. In comparison,
benchmarking from LGBF figures,
last updated in 2023/24, shows this
performance is above the national
average of 43.5% and compared to
other local authorities. 
Ian Bain
% residents satisfied with the street cleaning
service 73%  64% 73%  
Target marginally missed with a
continued downward trend. Recent
changes across the service due to
budget reductions have impacted
on the satisfaction levels.
Ian Bain
% Residents satisfied with Parks & open spaces 77%  72% 85%  
Target significantly missed and is
continuing a downward trend. The
continued progress of a number of
initiatives which are underway and
recently completed including
improving play parks may increase
satisfaction.
Ian Bain
Percentage of abandoned vehicles that require to
be removed by the council that are removed within
14 days
100%  100% 100%   Target met. Ian Bain

Page 5

Action Status Progress Due Date Note Owner
Finalise the delivery of two new allotment sites   31-Mar-2025
Action completed. The Overburn, Dumbarton
Common allotment site project will not progress to
construction stage until funding has been identified
and agreement made on options for delivery. 
Ian Bain
Develop a new local bio diversity action plan   31-Mar-2025
Action overdue. The overall delivery date of the
Local Biodiversity Action Plan is now anticipated for
December 2025. The final Scottish Government
delivery plan was only published in December 2024,
much later than originally anticipated. This action
will carry over to 2025/26.
Ian Bain
Develop Ash die back action plan   31-Mar-2025
Action completed as planned. The audit of trees
within the Council boundary which may be affected
by the Ash Die-back disease is complete and the
action plan has been developed and will be
progressed. Operational process agreed to deal with
cases that are identified on a risk based approach
Ian Bain 
Objective 5. Our resources are used in an environmentally sustainable way 
Action Status Progress Due Date Note Owner
Develop Strategy for transition to electric fleet   31-Mar-2025
Action completed as planned. In addition to the
development of our approach to EV transition we
have established a collaborative approach that aims
to reinforce the programme to transition to ultra-low
and zero emission fleet including upskilling of
workforce. There are a number of actions identified
through consultation and agreement which we will
continue to progress. These include, vehicle
replacement, procurement opportunities, training
and upskilling, develop depot provision for safe
areas for repair and storage of electric vehicles and
establishing policies and incentives to encourage the
appropriate employee behaviour. 
Stephen Brooks

Page 6

Action Status Progress Due Date Note Owner
Develop detailed design and costings for the
resource recycling and reuse centre (RRRC)   31-Mar-2025
Action complete. Design and costs are complete, we
will not move to construction phase at this time as
this will give time for the Co-operation agreement to
show required resilience. This was agreed at March
Council. 
Ian Bain
Progress development of a best value proposal
for the management of biodegradable municipal
waste  
31-Mar-2025
Action completed as planned. Cooperation
agreement with Glasgow City Council has been
finalised. Operational processes to move all waste
processing to incineration implemented.
Ian Bain
Develop the procurement model for the phased
delivery of public and fleet charging
infrastructure including consideration of the
Implementation Strategy and Expansion Plan.  
31-Mar-2025
Action completed as planned. Service continues to
work with Glasgow City Region. Consultant now
appointed to prepare tender to move to
procurement and to bring in an external company to
supply and maintain network of charging
infrastructure
Liam Greene 
Objective 6. Our neighbourhoods are sustainable and attractive 
Performance Indicator
2023/24 2024/25
Owner
Value Status Value Target Short Trend Long Trend Note
% of Special Needs Adaptation projects completed
by consultancy services from receipt of referral to
carrying out survey, design and submission of
building warrant within 60 day target for type 3
projects
93%   70%   Data not available until late May Gail McFarlane
% Consultancy Services project deliverables for
Housing and General Services projects that were
delivered to programme
83%   80%   Data not available until late May  Gail McFarlane
% of Class A roads that should be considered for
maintenance treatment 19.2%  19.2% 24%   Target met. Liam Greene
% of Class B roads that should be considered for
maintenance treatment 19.9%  19.9% 24.5%   Target met. Liam Greene
% of Class C roads that should be considered for
maintenance treatment 23.3%  23.3% 30%   Target met. Liam Greene

Page 7

Performance Indicator
2023/24 2024/25
Owner
Value Status Value Target Short Trend Long Trend Note
Percentage of unclassified roads that should be
considered for maintenance treatment 30.2%  30.2% 37%   Target met. Liam Greene
% Residents satisfied with roads maintenance 22%  24% 40%  
Target significantly missed with a
marginal improvement from
previous year. Although the Roads
satisfaction is at a low level
benchmarking from LGBF figures,
last updated in 2023/24,
highlighted West Dunbartonshire
Council as the 6th highest investor
in their roads assets per kilometre
compared to other local authorities.
Investment in the roads
maintenance programme continues
Liam Greene 
Action Status Progress Due Date Note Owner
Review any representations received following
the notification of the scheme and finalise
detailed design for the construction of the
Gruggies Burn Flood Management  
31-Mar-2025
Action completed as planned. Outline design
complete, community engagement undertaken and
outputs taken into consideration with modification
made to address valid concerns. Detailed design in
progress. 
Liam Greene
Undertake flood management Improvement
Study for Dumbarton and Vale   31-Mar-2025
Action Overdue. Feasibility works underway of
proposed actions from Surface Water Management
Plan (SWMP). Development options being prepared.
Additional assessments and data are now required
and will be reviewed by the service to identified
potential interventions. This action will carry over to
2025/26. 
Liam Greene
Consider the initiatives recommended within
the draft surface water management plans and
present to Council for consideration and budget
allocation  
31-Mar-2025
Action delayed. Proposed options have been
reviewed for the Clydebank area with those
warranting further investigation. Cost Benefit
Analysis being prepared. This action will carry over
to 2025/26.  
Liam Greene
Progress plan to change the method used for
road defect repairs   31-Mar-2025
Action complete. Structural Patching programme
implemented and will be delivered over 4 phases
across the year.
Liam Greene

Page 8

Action Status Progress Due Date Note Owner
Prepare a plan to uncover issues relating to
roads satisfaction levels   31-Mar-2025
Action completed as planned. Citizen satisfaction
survey undertaken. Responses reviewed to identify
areas of improvement. 
Liam Greene 
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Impact of major adverse
weather incidents on
services
A significant period of adverse weather
may result on failure to deliver key
operational functions of R&N services  
31-Mar-2025
The Business Continuity Plan would
come into effect in the event of a
major adverse weather incident. 
No change to risk matrix
Ian Bain
Failure to maintain road
network during adverse
weather
A significant period of adverse weather
may result in failure to deliver key
operational functions of R&T services
and other Council services. 
31-Mar-2025
Winter training programme is in place,
and business continuity plan is in
place. 
No change to Risk Matrix
Liam Greene
Failure to manage and
maintain the road network
effectively
Failure to manage and maintain the road
network effectively will have an adverse
impact on user safety, traffic movement,
air quality, economic growth and reduce
access to facilities and amenities. The
Council’s reputation as a place to live
and work with access to employment,
education, leisure and health
opportunities would be adversely
affected. 
31-Mar-2025
Significant investment in resurfacing
works.  Service continues to respond
to reported defects across the
network. 
No change to Risk Matrix.
Liam Greene
Challenges in delivering
effective services in
relation to Roads &
Neighbourhoods
The risk that the Council’s fails to deliver
on the three service areas within Roads
& Neighbourhood: Roads &
Transportation, Waste & Greenspace and
Fleet. These areas provide services
across a range of areas including
managing and maintaining roads,
footpaths and associated infrastructure,
managing flood risk, winter gritting, 
31-Mar-2025
Service continues to provide full
service, monitoring in place to ensure
any adverse issues are highlighted and
appropriate actions taken. 
No change to Risk Matrix. 
Gail Macfarlane

Page 9

Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
grounds maintenance, street cleaning,
burial and cremation, outdoor facilities,
waste and recycling, vehicle fleet
management. Failing to ensure these
services are not fully fit for purpose
could result in adverse consequences in
relation to delivering efficient and
effective services. 
3. Our Economy 
Objective 7. Our area has the infrastructure for sustainable and inclusive growth where businesses can flourish 
Action Status Progress Due Date Note Owner
Progress demolition of Artizan Centre within
agreed timeframes – next phase   31-Mar-2025 Action completed planned. Demolition complete.
Regeneration of the site will now progress  Gail Macfarlane
Support the progress of Exxon City Deal Project   31-Mar-2025
Action completed as planned. The project will now
move to construction phase in 2025/26.  Liam Greene   
4. Our Council

Page 10

Objective 10. Our workforce is resilient and skilled where digital technology supports service delivery for our residents 
Action Status Progress Due Date Note Owner
Develop and implement wellbeing, employee
engagement, equality and learning and
development plans to enable capabilities,
improve resilience and promotion of a diverse
workforce  
31-Mar-2025
Action overdue. We have reviewed succession
planning requirements across services, completed
analysis of workforce profiles. Developed training
plans where required and will undertake further
work in the coming year including consideration of
the succession planning requirements. 
All Managers
Develop and implement employee life cycle
plans in line with the People First Strategy to
attract and retain the workforce.  
31-Mar-2025
Action completed as planned. We have reviewed and
adjusted role requirements where necessary.
Reviewed turnover and reasons for exit to identify
areas of improvement. Role profiles for hard to fill
posts have been reviewed and improvements have
been made to attract staff. This work will continue in
the coming year.  
All Managers
Implement service review process including
role design, use of new technology and new
ways of working to add resilience, address
gaps, and establish opportunities for
efficiencies  
31-Mar-2025
Action completed as planned. We have undertaken a
review of critical roles to ensure resilience.
Concluded an analysis of overtime and use of casual
workers, there is limited use of casual workers
across the service.  Overtime remains an area of
consideration in line with the service needs.  Further
work continues to understand if re-modelling the
workforce can be achieved and this will be done in
2025/26.
All Managers
Develop and implement learning and
development opportunities to improve
capabilities and resilience within the workforce.  
31-Mar-2025
Action completed as planned. We continue to
explore opportunities for shared learning with
Glasgow city Council under the Net Zero
Cooperation Agreement. Targeted training and
upskilling have been identified and delivered as
required across the service areas. 
All Managers 
Objective 11. Our Council is adaptable and focused on delivering best value for our residents

Page 11

Performance Indicator
2023/24 2024/25
Owner
Value Status Value Target Short Trend Long Trend Note
% of capital projects supported by capital
investment team, delivered within agreed plan 83%  81% 80%   Data not available until late May Patricia Rowley 
Action Status Progress Due Date Note Owner
Implement Consultancy Services/ Capital
Investment team restructure   31-Mar-2025 Action completed as planned. Restructure complete
saving target achieved. Gail Macfarlane
Reduce fleet hire costs   31-Mar-2025
Action completed as planned. Working closely with
the service areas considerable progress has been
made in reducing reliance and associated costs. 
Where purchase is not the most economically
effective approach due to seasonal requirements
and where services have changing needs, whilst the
costs are met by the services areas and they
authorise the hire, we have introduced a process to
apply an alternative where this is available. We will
continue to develop and operational framework to
manage fleet across the Council.  
Stephen Brooks
Work jointly in partnership with Glasgow City
Council and the wider City Region to progress
collaborative working opportunities  (including
Net Zero)  
31-Mar-2025
Action completed as planned. Priority locations
provided to the City Region and identified for
phased implementation with the successful private
partner. 
Gail Macfarlane
Complete phase 3 of the Fit for Service review
of waste services, implementing the
prioritisation collection of recycling  
31-Mar-2025
Action completed as planned. The planning and
preparation are complete. Project implementation is
estimated to be summer 2025.
Ian Bain
Progress new charging structure for garden
waste and commercial waste   31-Mar-2025
Action completed successfully with a significant 
number of permits purchased, supporting additional
income.
Ian Bain
Implement revised service provision for school
crossing patrols   31-Mar-2025
Action complete. Service provision reviewed
changes implemented including reduction in
resources and changes to service provision.  
Liam Greene

Page 12

Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Challenge to delivery of
burial and cremation
services
A number of factors may impact on
ability to deliver these services.  For
example a pandemic would create
significant immediate demand on
services. 
31-Mar-2025
We have completed extensions to
Dumbarton and North Dalnottar
cemeteries and Vale Of Leven
Cemetery. This will mitigate the impact
of any challenges to the burial and
cremation services. 
No change to risk matrix.
Ian Bain
Inability to deliver priority
services as a result of fuel
shortages
A fuel shortage would significantly
impacting on our ability to provide
priority service across West
Dunbartonshire. 
31-Mar-2025
Council participates in the Scottish
Government Liquid Fuels Framework
and contributes to the work of the
Scottish Government Fuel Resilience
Group. There are no issues with fuel at
this time. 
No change to risk matrix.
Gail Macfarlane   
Action Status 
Overdue 
Not on track 
In Progress and on track 
Completed 
PI Status 
Target significantly missed 
Target narrowly missed 
Target met or exceeded 
Long Term Trends 
Improving 
No change 
Declining 
Short Term Trends 
Improving 
No change 
Declining

Page 13

Risk Status 
Alert 
Warning 
OK