Changes to Capital Plan and Implications at P7
RESOURCES
Project - RES 13
Current Year
2024/25  2025/26  2026/27  2027/28 
Future
Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000
Depot Rationalisation 500                3,000           4,351             -           -           7,851            
Depot Rationalisation - Revised 1,500             2,000           4,351             -           -           7,851            
Explanation
REGULATORY & REGENERATION
Project - RR 3
Current Year
2024/25  2025/26  2026/27  2027/28 
Future
Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000
Installation of Solar PV at Clydebank Leisure Centre 57                  -               -                 -           -           57                 
Installation of Solar PV at Clydebank Leisure Centre Revised -                 57                -                 -           -           57                 
Explanation
Due to staff vacancies within the team, the project will not progress during this financial year.
Project - RR 5
Current Year
2024/25  2025/26  2026/27  2027/28 
Future
Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000
Meadow Centre/Vale Swimming Pool - Air Handling Unit Upgrade 226                -               -                 -           -           226               
Meadow Centre/Vale Swimming Pool - Air Handling Unit Upgrade -
Revised -                 226              -                 -           -           226               
Explanation
Due to staff vacancies within the team, the project will not progress during this financial year.
Acceleration of £1m budget required from 25/26 into 24/25 for additional costs incurred as a result of depot rationalisation at Overburn Avenue and Bridge
Street efficiency savings.
ITEM 15 -
APPENDIX 3

Page 2

Changes to Capital Plan and Implications at P7 Appendix 3
Project - RR 6
Current Year
2024/25  2025/26  2026/27  2027/28 
Future
Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000
Regeneration/Local Economic Development 1,100             1,907           1,855             560          2,500       7,922            
Regeneration/Local Economic Development - Revised 375                2,232           2,055             760          2,500       7,922            
Explanation
Project development taking longer than anticipated.  Project delayed due to external factors.
Project - RR 8
Current Year
2024/25  2025/26  2026/27  2027/28 
Future
Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000
Place Based Investment Programme                310 -               -                 -           -           310               
Place Based Investment Programme - Revised 3                    307              -                 -           -           310               
Explanation
Project - RR 9
Current Year
2024/25  2025/26  2026/27  2027/28 
Future
Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000
Clydebank Can 717                -               -                 -           -           717               
Clydebank Can Revised -                 717              -                 -           -           717               
Explanation
Project is supported by the Clydebank Town Board and its delivery and future maintenance is linked to 3 Year Investment Plan as agreed by the Board and
Long Term Plan for Town funding timescales.
Project is supported by the Clydebank Town Board and its delivery and future maintenance is linked to 3 Year Investment Plan as agreed by the Board and
Long Term Plan for Town funding timescales.

Page 3

Changes to Capital Plan and Implications at P7 Appendix 3
Project - RR 10
Current Year
2024/25  2025/26  2026/27  2027/28 
Future
Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000
LUF 11,959           2,588           -                 -           -           14,547          
LUF-Revised 9,133             5,414           -                 -           -           14,547          
Explanation
Project - RR11
Current Year
2024/25  2025/26  2026/27  2027/28 
Future
Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000
Levelling Up Capacity                161 -               -                 -           -           161               
Levelling Up Capacity Revised -                               161 -                 -           -           161               
Explanation
ROADS & NEIGHBOURHOOD
Project - RN 2
Current Year
2024/25  2025/26  2026/27  2027/28 
Future
Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000
Flood Risk Management 500                500              200                200          915          2,315            
Flood Risk Management - Revised 400                500              200                200          915          2,215            
Explanation
Limited actions are required under the current management plan.
Project development process and procurement process have taken a considerable amount of time. The construction programme received from the preferred
bidder indicates the completion date as end of October 2025.
The budget is to support development of Levelling Up projects. It has been reprofiled to align with the revised LUF timescales.

Page 4

Changes to Capital Plan and Implications at P7 Appendix 3
Project - RN 4
Current Year
2024/25  2025/26  2026/27  2027/28 
Future
Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000
Flood Prevention 339                -               -                 -           -           339               
Flood Prevention - Revised 289                -               -                 -           -           289               
Explanation
Original estimates for surface water management plans were lower than expected, there was also limited uptake on property level protection.
Project - RN 28
Current Year
2024/25  2025/26  2026/27  2027/28 
Future
Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000
Balloch Mountain Bike Track 600                -               -                 -           -           600               
Balloch Mountain Bike Track - Revised 100                350              -                 -           -           450               
Explanation
Project scope has been reduced which has in turn reduced match funding element.
Project - RN 32
Current Year
2024/25  2025/26  2026/27  2027/28 
Future
Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000
Cycling, Walking, Safer Routes Tier 1 (Active Travel) 389                -               -                 -           -           389               
Cycling, Walking and Safer Routes Tier 1 (Active Travel) 641                -               -                 -           -           641               
Explanation
Additional funding from Scottish Government.

Page 5

Changes to Capital Plan and Implications at P7 Appendix 3
Project - RN 34
Current Year
2024/25  2025/26  2026/27  2027/28 
Future
Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000
Strathclyde Partnership for Transport - Bus, cycling and walking
infrastructure improvements & Park and Rides -                 -               -                 -           -           -                
Strathclyde Partnership for Transport - Bus, cycling and walking
infrastructure improvements & Park and Rides - Revised 310                -               -                 -           -           310.0            
Explanation
Additional Scottish Government funding.
OVERALL REPROFILING TOTAL 4,418