WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer – Resources
Infrastructure, Regeneration & Economic Development Committee:
6 February 2025
_________________________________________________________________
Subject: Infrastructure, Regeneration & Economic Development Capital
Budgetary Control Report 2024/25 31 October 2024 (Period 7).
1. Purpose
1.1 This report provides an update on the capital financial performance to    
31 October 2024 of those services under the auspices of the Infrastructure,
Regeneration & Economic Development Committee (IRED).
2. Recommendations
2.1 Committee is asked to:
i) Note the current position of the 2024/25 IRED capital budget.
ii) Note the revised completion dates detailed in appendix 3 agreed at
Council on 18 December 2024.
iii) Note the additional capital budget of £0.133m in respect of Posties
Park agreed at Council on 18 December 2024.
iv) Note an in-year variance of (£4.284m) mainly due to reprofiling
(£4.418m).
3. Background
3.1 On 6 March 2024 the Council approved the updated General Services Capital
Plan for 2024/2025 to 2032/33. The three years from 2024/25 to 2026/27 were
approved in detail with the remaining years being indicative. The budget
agreed under the auspice of IRED Committee was £51.612m for 2024/25 and
£215.153m for the project life budget.
4. Main Issues
Exhibit 1 sets out the revised capital budget at period 5 as reported to
Committee 6 November 2024.
ITEM 15

Page 2

Exhibit 1: Revised Capital Budget as at 30 October 2024
2024/25 Project
Life
£m £m
Capital Budget Agreed 6 March 2024 51.612 215.153
Updates Reported to Committee 14 August and 6
November 0.930 4.276
Reprofiling Reported to Committee 14 August
(13.311
)
Revised Capital Budget at Period 5 39.231 219.429
Reprofiling Reported at Period 5 (1.05)
Additional Budget Approved for Posties Park at
period 5 0.231 0.231
New Approved Budget as at Period 5 38.412 219.66
Changes Between Period 5 and Period 7
Removal of Nature Restoration (0.034) (0.600)
New SPT Funding 0.310
Revised Budget as at Period 5 38.688 219.06
4.1 Progress against the 2024/25 capital plan is detailed in:
Appendix 1 – Project Life Summary by Chief Officer
Appendix 2 – Off Track Projects
Appendix 3 – Changes to Capital Plan for Noting
Appendix 4 – All Approved Projects
4.2 The overall programme summary report at Appendix 1 shows that planned
expenditure is lower than the budget agreed by £0.166m mainly due to
three projects not utilising their full budget. These are:
 RN2 Flood Risk Management – limited actions are required under the
current management plan.
 RN4 Flood Prevention – original estimates for surface water
management plans were lower than expected, there was also limited
uptake on property level protection.
 RN28 Balloch Mountain Bike Track – project scope has been reduced
which has in turn reduced match funding element.
4.3 Appendix 2 highlights two projects currently showing as off track. One project
(RN17 Posties Park) requires additional budget and (RN28 Balloch Mountain
Bike Track) is off track due to revised completion dates.
 RR17 Posties Park – additional budget of £0.133 required for utility
costs incurred as part of capital build project (approved by Council on
18 December 2024).
 RN28 Balloch Mountain Bike Track – completion date amended due to
revised project scope.

Page 3

4.4 Appendix 3 highlights eleven projects where the project expenditure requires
to be reprofiled but there is no need for approval of additional budget.  It also
highlights two projects already existing in the capital programme where
additional funding has been made available from Scottish Government.
 RN32 – Cycling, Walking, Safer Route Tier 1 (Active Travel) –
additional Scottish Government funding of £0.252m.
 RN34 – Strathclyde Partnership for Transport Bus, Cycling and
Walking Infrastructure Improvements & Park & Rides – additional
Scottish Government funding of £0.310m.
4.5 Appendix 4 shows all projects with approved in year and project life budgets
as well as anticipated expenditure. It highlights that the 2024/25 budget is
£38.687m with current forecast spend of £34.403m, a surplus variance of
£4.284m mainly due to reprofiling (£4.418m) and additional budget of
£0.133m. The spend as at period 7 is £11.769m (34.21%) of the current
forecast spend of £34.403m.
4.6 Exhibit 2 sets out the revised IRED capital budget at period 7 following
approval by Council on 18 December 2024.
Exhibit 2: Revised Capital Budget £m £m
Revised Capital Budget at 30 October 2024 38.688 219.06
Reprofiling of Budgets as reported at Appendix 3
(4.680
) 0.000
Reduction of Budgets as reported at Appendix 3
(0.300
) (0.300)
New Funding as reported at Appendix 3 0.562 0.562
Added RN17 additional funding Posties Park 0.133 0.133
Proposed Revised Capital Budget Period 7 34.403 219.455
5. Option Appraisal
5.1 No option appraisal was required for this report.
6. People Implications
6.1 There are no people implications.
7. Financial and Procurement Implications
7.1 The report notes the projected in-year financial position for capital budgets.
8. Risk Analysis
8.1 The main risks are as follows:
(a) The reported variances should be viewed in the knowledge that there are
a number of variable factors which could arise between now and 31
March which could affect the year end results for capital budgets.

Page 4

(b) As a consequence of current market conditions, inflation is at an all-time
high and interest rates continue to be volatile. To forecast for the full year
costs budget assumptions have been required. These assumptions
continue to change regularly and therefore it is likely the projected year
end budgetary position will change from that reported.
9. Equalities Impact Assessment (EIA)
9.1 No equalities impact assessment was required in relation to this report.
10. Environmental Sustainability
10.1 No assessment of environmental sustainability was required in relation to this
report.
11. Consultation
11.1 All services involved in delivering the capital budgets have been consulted in
the compilation of this report.
12. Strategic Assessment
12.1 Proper budgetary control and sound financial practice are cornerstones
of good governance and support Council and officers to pursue the
strategic priorities of the Council’s current Strategic Plan. This report
forms part of the financial governance of the Council.
______________
Laurence Slavin
Chief Officer – Resources
Date: 21 January 2025
Person to Contact: Jackie Thomson
Council Offices, Church Street, Dumbarton
E-mail: jackie.nicolthomson@west-dunbarton.gov.uk
Appendices: Appendix 1 - Project Life Summary
Appendix 2- Off Track Projects
Appendix 3 - Reprofiling and Acceleration of Projects
Appendix 4 - Details of all Projects.
Background Papers:  General Services Capital Plan Update - Council 6 March     
2024.
Capital Monitoring Report – Council 6 November 2024.
Wards Affected           All Wards