WEST DUNBARTONSHIRE COUNCIL
Report by Chief Officer Roads and Neighbourhood
Infrastructure, Regeneration and Economic Development
5 February 2025
Subject: Roads Asset Management Plan 2025-30
1. Purpose
1.1 West Dunbartonshire Council as the “Roads Authority” has a responsibility
to ensure that assets are managed in a strategic manner so that they
enhance and improve service delivery, that the asset base is aligned to
the organisation’s corporate goals and objectives and that they are
managed in an active, effective and efficient manner.
1.2 The Roads Service have updated their Roads Asset Management Plan to
reflect the current level of investment and the impacts those investments
will have on the overall asset condition.
2. Recommendations
2.1 It is recommended that the Committee:
a) Notes the contents of this report; and
b) Approves the adoption of the Roads Asset Management Plan for
2025-30
3. Background
3.1 West Dunbartonshire Council’s Strategic Plan identifies the aims and
objectives for the Council. The Roads Asset Management Plan (RAMP)
directly links to the outcomes of the Council’s Strategic Plan 2022-27.
3.2 The targets and strategies within the RAMP are used to develop annual
works programmes, based on the roads budget allocation, that support
the outcomes highlighted within the Strategic Plan
3.3 The Roads Asset Management Plan (RAMP) sets out plans for all the
Roads assets for the period 2025 to 2030 to align with the Councils Capital
and Revenue investment programme. 
ITEM 8

Page 2

3.4 The purpose of the RAMP is to formalise the strategies for investment in
roads assets, define service standards and devise an organised plan  
which accounts for the roads assets and money spent on them facilitating
efficient and effective investment.
3.5 The Roads assets consist of the following:
Carriageways 389.4km
Footways, footpaths and cycleways 717.3km
Structures 118
Street Lighting 16452
Traffic Management systems 110
Street Furniture 25000 (Approximately)
Table 1 – Roads Assets
3.6 This plan is based upon currently available inventory data for Road assets,
i.e. carriageway, footway, structures, street lighting, traffic signals and
street furniture.  For some minor Road assets inventory data is not
currently held, however an attempt has been made to incorporate these
assets within this plan using local estimates and sample surveys.
4. Main Issues
4.1 The current satisfaction level with our customers in relation to our road
condition is at an all-time low with our current satisfaction rating sitting at
22%.
4.2 Whilst the satisfaction survey shows a low percentage satisfaction rate
for the road condition, in reviewing our Road Condition Index (RCI)
scores against those available for all other 32 local authorities our ratings
are quite high with West Dunbartonshire placing 5th for overall RCI
scores.
A breakdown of our score against national position is provided below:
Road Classification RCI Score National Rating
A Class 19.2 5th
B Class 19.9 6th
C Class 23.3 2nd
Unclassified 30.2 7th
Overall Network 27.9 7th
4.3 The Roads and Transportation team has been working with our
Performance team to undertake additional investigations into the reason
behind this.
4.4 Full details of the results are included within the Plan however our
customers main concerns would appear to surround the overall condition
of our roads and footways, and the volume of potholes recorded.

Page 3

4.5 The current budget pressures are impacting on the service the council
can deliver and it is therefore important that the service adopts an
approach which makes best use of the funding available and addresses
the concerns of our customers as much as possible.
4.6 In the longer term the roads asset management plan will allow West
Dunbartonshire Council to minimise whole life costs and maximise value
for money which is essential given current funding available. It will allow
the effect of these budgets to be quantified in terms of deterioration of
the asset or reduction in service levels and help identify where spend will
maximise value for money, whilst considering the risks and benefits.
4.7 Developed lifecycle plans for the roads infrastructure has identified that;
 27% of our carriageways are in need of repair
 18% of our footways are in need of repair
 30% of our street lighting apparatus is in need of replacement
4.8 In addition to the above deterioration value, through the SCOTS Roads
Asset Management Group, various asset condition and cost projection
tools have been developed. These tools allow us to predict the effect the
current level of investment will have on the asset over the coming years.
5. People Implications
5.1  There are no people implications associated with this proposal.
6. Financial and Procurement Implications
6.1 The existing plan has been developed in line with current Capital and
Revenue funding levels.
6.2 Any future alterations to these levels may require the figures and
assessments within the RAMP to be revised.
7. Risk Analysis
7.1 There is a risk that with any reduction in investment and subsequent increase
defects that the council may also see an increase in liability claims as a result
of damage to vehicles/persons.
7.2 A lack in consistent and robust planning in respect of asset management
could result in the Council being ill prepared to meet future demands in
maintaining its assets These plans mitigate this risk by developing actions
that will address potential risks.

Page 4

7.3 The aim of the Asset Management Strategies and their associated plans is to
ensure that these matters are appropriately prioritised from a corporate
perspective and the financial consequences in revenue and capital
investments terms can be properly assessed
8. Equalities Impact Assessment (EIA)
8.1 There will be likely positive impacts for some protected groups especially women
and disabled people and younger and older people. Human Rights and health and
social/economic areas may also benefit.
9. Consultation
9.1 Consultations were undertaken with customers through the corporate
performance assessment process and incorporated into the plan.
10. Strategic Assessment
10.1 The asset infrastructure discussed in this report is fundamental in promoting
social and economic regeneration within West Dunbartonshire. The
introduction of the asset management plan will assist in the efficient
management and maintenance of the assets and associated infrastructure.
Best value will be achieved through making the most efficient use of available
funding and a best practice approach to management and maintenance of the
assets are all promoted through the introduction of the asset management
plans.
Chief Officer Gail Macfarlane
Service Area Roads and Neighbourhood
Date: 22 January 2025
Person to Contact: Liam Greene,
Roads and Transport Manager,
Liam.greene@west-dunbarton.gov.uk
Appendix Roads Asset Management Plan
Wards Affected: All wards