Democracy Spraffa

Item 13 - Appendix 2

West Dunbartonshire Council · 6 November 2024
Back to Infrastructure, Regeneration & Economic Development Committee — 6 November 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

MAKING
PLACESBETTER
Prepared for the Clydebank Town Board
Clydebank LTP:
Three Year
Investment Plan
August 2024
2
ITEM 13 - APPENDIX 2

Page 2

3Introduction2
About This Document
This Three Year Investment Plan is the second
element of the Clydebank Long Term Plan and has
been developed from its first, the Ten Year Vision for
the town. It identifies how the Town Board intend to
utilise the first three years of available programme
funding, underpinned by evidence of consultation
with the local community and stakeholders.
It illustrates the specific interventions selected by the
Town Board, supported by West Dunbartonshire
Council that are being taken forward, which of the
three investment headings they fall under, their ‘on’
or ‘off’ menu status and, where applicable, the
powers as per the policy toolkit that the town will
seek to use to deliver and/or supplement this activity.
The proposals have been developed to an RIBA
Stage 1 level and are supported with preliminary high
level cost, programme, risk and delivery
considerations.
Three Year Investment Plan

Page 3

clydebank
long term
plan
54
contents
Client
Clydebank Town Board
Project Team
West Dunbartonshire Council
Turner & Townsend
Threesixty Architecture
Sweco
Introduction                 03
Intervention 1
Intervention 2a
Intervention 2b
Intervention 3
Intervention 4
Long Term Plan for Towns
The Town Board
Community Engagement 
Development of the Long List
The Long List
Selection of Three Year
Investment Plan Interventions 
context
06
08
10
12
24
26
34
36
38
48
58
68
78
chosen
interventions
The Town Board, in conjunction with the
local community, have prepared a Long-
Term Plan (ten year vision for the town)
to guide the funding spend and this three
Year Investment Plan.
This document illustrates the priority
interventions to be delivered during 2024-
2027 and contribute towards realising the
longer-term vision.
ContentsThree Year Investment Plan

Page 4

context
7ContextThree Year Investment Plan6

Page 5

9Context8
Scope
The Government have set out two key
requirements upon which their funding
is dependent, namely:
A 10 Year Long-Term Plan  
comprising:
High level Vision Statement
-
Strategic case for change: evidence/
data/stories (definition of boundary /
focus area)
-
Outcomes / objectives and alignment
with community
-
Proposals / interventions across the 3
investment themes
-
Evidence of community and
stakeholder representation
engagement & ongoing mechanism
-
Delivery Milestones (phasing) over
10 years & use of powers across 3
investment themes
A 3 Year Investment Plan
describing:
Interventions and powers employed
over the 3 years for each investment
theme
-
Commentary on whether
interventions ‘on or off menu’ the
latter requiring outline business
case, insight from local stakeholders
and agreement of local authority
underwriting/support.
Long Term Plan for Towns
Clydebank has been chosen as one
of seven towns in Scotland to receive
funding as part of this programme.
Each town is expected to do the
following:
Develop a Long-Term Plan to invest in
and regenerate their town, based on
the priorities of local people, and put
to local people for consultation.
-
Receive £20 million in endowment-
style funding and support over ten
years to support the Town Plan, to be
spent on issues that matter to local
people, including regenerating high
streets and securing public safety.
This plan will be put to local people.
-
Establish a Town Board to bring
together community leaders,
employers, local authorities, and the
local MP to oversee and deliver the
Long-Term Plan.
-
Use a toolkit of powers, from tackling
anti-social behaviour to auctioning
empty high street shops, reforming
licensing rules on shops and
restaurants and supporting more
housing in town centres.
Established Priorities
Flexibility has been provided to make
a range of improvements under three
broad investment themes, and are
open to being driven by the needs
and wishes of local communities.
These themes are:
The UK Government have identified 55 towns to
benefit from from the Levelling Up Programme via the
Long-Term Plans, to drive ambitious proposals to
regenerate local towns across the UK over the next
decade.
1.     High Streets, Heritage and     
Regeneration
2.  Transport and Connectivity
3.  Safety and Security
OUR LONG-TERM PLAN FOR TOWNS 
OCTOBER 2023 
In accordance with the requirements
within the scoping document we
will ensure that the Urban Capacity
Study will be capable of being
read as both a stand-alone report
and offer analysis and evidence to
influence and shape the Long Term
Plan.
Clydebank Long Term Plan: Defined Area Boundary
Three Year Investment Plan

Page 6

The UK Government published
guidance in December 2023
outlining the requirement for each
of the towns identified to benefit
from the £20 million investment to
establish a ‘Town Board’ to draw
up and drive ambitious proposals
to regenerate their town over the 10
year period.
The guidance stipulated both the
responsibilities of the Town Board and 
who its members should be drawn
from within the community. It stated:
‘While the local authority remains the
accountable body for funding and
executing plans, Town Boards are
responsible for developing the Long-
Term Plan, working closely with local
people.
The independent chair of Long-
Term Plan for Town Boards should
be invited by the local authority,
considering who is best placed to
convene partners and is a respected
figure in the community with an
obvious passion for the place. The
local MP should be engaged as part
of the process.
Town Boards must be chaired by
a local community leader or local
businessperson. The chair should
act as a champion for the town and
provide leadership for the Town
Board, ensuring it is community-led
and embedded within the local area.
They can be anyone who holds a
prominent role such as:
• a local charitable organisation
• a philanthropist
• the head of a Further Education
College
• a director for the NHS Board or
Trust
• a director of a football club
Elected representatives, such as MPs,
MSPs, MSs or local councillors, must
not chair the Town Board.’
Ensuring the Town Board is a
community-led institution
Town Boards should be community-
led institutions that build civic capacity
in the town, with the local authority,
or an alternative organisation such
as a community group, providing a
secretariat function. The local authority
will act as the accountable funding
body.
We encourage local authorities to
help empower the Town Board in
realising this role and driving forward
a community-led vision for change.
This may include providing advice
and support on legal duties like
impact assessments, to help leaders
with non-public sector backgrounds
navigate those requirements they may
be less familiar with.
The Town Board and the local
authority should also consider existing
community organisations that might
want to undertake work on behalf of
the Town Board. Capacity funding
could be used support this, or the
recruitment by a third-party of an
individual to lead the development of
the Long-Term Plan full-time.
Local Trust research shows that
employing a single member of full-time
staff from the community helps to
build local capacity and resilience.
If support is required to identify
suitable community organisations,
local authorities should speak to their
respective area team leads in the
first instance. Area teams will provide
ongoing support for the duration of
the programme, including helping
local authorities and Town Boards to
access the support they need, and
acting as a focal point between them
and central government, including the
Towns Unit and the High Streets and
Towns Taskforce.’
1110
The Town Board
West College Scotland   Liz Connolly, Principal, Chair of Clydebank Town Fund Board
WDC (Elected Members)   Lawrence O’Neill
Clare Steel
Dunbartonshire Chamber of Commerce Mary Ann Smith, President
Police Scotland    Kirsten McLatchie, Area Commander
Golden Jubilee National Hospital  Sandie Scott, Director of Strategic Communications and      
Stakeholder Relations
Clyde Shopping Centre   Andrew Forrester, Centre Manager
Clydebank Co-Operative   Fiona McInnes, Chief Executive
Clydebank Housing Association  Lynette Lees, Chief Executive,    
John Mooney, Board Member
Community Representative  June Todd
Member of Parliament    Douglas McAllister MP
Member of Scottish Parliament  Marie McNair MSP
Youth Representative    Calum (Supported by Lucy McGovern (Development Officer)
West Dunbartonshire CVS  Selina Ross, Chief Officer
West Dunbartonshire Council (Officers) Peter Hessett, Chief Executive,    
Alan Douglas, Chief Officer Regulatory & Regulation,    
Gail Macfarlane, Chief Officer Roads & Neighbourhood,    
Laurence Slavin, Chief Officer, Resources
Clydebank Town Board Members                            UK Government Guidance
At a meeting of West
Dunbartonshire Council’s
Infrastructure, Regeneration and
Economic Development committee
in February 2024, approval was
given for Liz Connolly, Principal
of West College Scotland to be
appointed as Chairperson of the
Clydebank Town Board.
The Board, in accordance with
the guidance is made up of a
combination of local businesses and
groups, essential service providers,
politicians and local elected members,
council officers and members of the
community.
Liz Connolly, Principal, Chair of Clydebank
Town Fund Board
Clydebank Town Board
It is a privilege to be chosen to lead this
important steering group to ensure that
Clydebank prospers through this investment. I
look forward to working with the members of
the Board and others to drive projects forward
for the benefit of the whole community.
- Liz Connolly, Principal, Chair of
Clydebank Town Fund Board
Three Year Investment Plan Context

Page 7

Key to the success of the Long
Term Plan for Clydebank will be
meaningful engagement with the
local community that will influence
the positive transformation of
Clydebank in the coming years.
The local community have been
asked to take part in a number of
engagement events and charrettes
in the last few years and the opinions
collected informed the 2021 Vision
and Developmet Framework which
this Long Term Plan takes as its
starting point.
Beyond these events, the community
have again been asked by the Town
Board, as part of the creation of this
Long Term Plan to give their thoughts
and opinions on Clydebank, this time
tailored to the three key investment
headings.
This was undertaken in two ways,
firstly, a questionnaire was sent out to
a number of community groups and
secondly, a public event was held in
the Clyde Shopping Centre over two
days in July.
A summary of the responses received
from all events thus far, that have
informed this Long Term Plan are
outlined on the next pages.
12
Community Engagement
Three Year Investment Plan 13Context
West Dunbartonshire Council,
supported by the Scottish
Government as part of the
Scottish Government’s Charrette
Mainstreaming Programme,
sponsored a locally driven town
centre design Charrette, an intensive
consultation that engages local people
in the design of their community in
early 2015.
Conclusions
In response to the issues and
observations emerging from the Brief
and discussions in the Charrette a
series of overarching transformational
themes for inclusion in the Vision for
Clydebank Town Centre 2025, were
presented, including:
Enrich the town centre
Capitalise on its loyal local customer
base
Refresh Clydebank Regional
Shopping Centre and Cinema
Maximise existing strong transport
links
Improve open space, walking and
cycling connections
Develop Queens Quay to complement
the Town Centre
Focus on health well-being, social
justice and community safety
Clydebank as a vibrant social
destination
Support new employment
opportunities
Clydebank Can was a series of
placemaking workshops held
between March and May of
2018, supported by the Scottish
Government’s Making Places
programme and was an opportunity
for the local community to collaborate
with WDC and Scottish Canals and
their design team, to undertake
additional design and implementation
work on the projects and actions from
the Charrette.
Conclusions
Clydebank Placemaking Principles
forming overall strategy for the town
centre:
An active canal - add to the activity
on the banks, the towpath and on the
water.
Make more of what exists in the town
centre – re-use empty buildings and
spaces.
Work to change the vehicle/pedestrian
balance – create more space for
people.
Diversify the town centre – incorporate
more than just retail.
Encourage Jobs, employment and
training.
Biodiversity - help the areas that
already have good biodiversity to
flourish and introduce more.
Placemaking - create spaces and
routes that promote local peoples’
happiness, health and enjoyment of
the town centre.
Town centre living – housing in the
town centre that has a good mix of
types and tenures
Maximise Inclusion.
Clydebank Town
Centre Design Charette
Clydebank Can

Page 8

14 Three Year Investment Plan 15Context
Families with Young Children
• Local activities for children
of varying ages within close
proximity, walkable
• Community hub to meet like-
minded people and support for
young families
• Good schools
• Green space  / Central outdoor
play space with play equipment
• Public toilets/accessible facilities
• Colour coded routes through
town for different levels of ability 
• Program of family events
• Nurseries
Teenagers
• Activities - Bowling, sport and
leisure facilities, evening venues
(for under 18s)
• Places to meet and gather
informally
• Water activities on the canal
• Independent restaurants and
kiosks with outdoor seating
• Retail variety; local, artisan
• Extended nighttime activity
• Super-fast Wi-Fi - digital town
Young Adults (18-25)
• Bars, restaurants, night time
economy. Music venues 
• Affordable housing
• Good transport links and
updating the station
• Variety in job opportunities
• Connections to the college
• Walkable activities / destinations
• Add street food / food hall
Adults (26-60)
• Safety in the town centre. Need
passive surveillance  
• Work hub area
• Program of cultural events
• Industry & workshops
Seniors (60+)
• Senior clubs to socialise
• Accessibility
• Market or foodhall with smaller
food retailers
• Bowling green/allotments in town
• Rest points; shelter, seating,
refreshments
As part of the work undertaken
to develop the Vision and
Development Framework, a
stakeholder event was held on the
19th August 2021
The stakeholder event was attended
by a wide cross section of those
with an interest in the town, including
secondary school pupils from St.
Peter the Apostle High School,
members of community groups,
representatives of the business
community, private developers and
West College Scotland, the further
education establishment with an
extensive campus at Queen’s Quay.
It was explained that the event had
been set up to help shape the brief
for a visioning project for  Clydebank
town centre and to understand where
the key stakeholders can contribute to
the process.
The purpose of the afternoon was
not to educate but to gather the ideas
of those in attendance. It was hoped
that everyone in attendance would
approach the series of workshops
with the best interests of Clydebank
at heart and that they would become
ambassadors for the visioning project
within their respective organisations
and communities.
The invaluable and extensive
consultation previously undertaken
(Design Charette and Clydebank Can)
was acknowledged and attendants
who had been involved in this
process were asked to continue their
enthusiasm for this new exercise.
Four workshops were run over the
course of the afternoon with the
following titles;
Workshop 1
SWOT Analysis
(Strengths, Weaknesses,
Opportunities, Threats)
Workshop 2
What is Clydebank’s Future Story?
Workshop 3
What do I Need from my Town
Centre? & What would make me live in
the Town Centre area?
For this workshop, attendees were
asked to consider these questions
from the standpoint of 5 key
demographic groups:
Families with young children
Teenagers (13-17)
Young Adults (18-25)
Adults (26-60)
Seniors (60+)
to obtain responses from specific
perspectives.
Workshop 4
How can my Organisation Invest More
in Clydebank Town Centre and why
Should we?
This exercise looked to create three
groups, each focussed on a particular
interest; Education, Commercial and
Residential, with community-based
attendees then distributed amongst
them.
The outcomes of the workshop
sessions were summarised and
published in a report document that in
turn informed the development of the
detailed project brief for the visioning
study.
Strengths
• The people of Clydebank’s
motivation
• Active communities keen to
engage
• The canal and river
• Transport links
• The lived experience of recent
history of the town
• Heritage
• Town reinventing itself and looking
towards the water
• Free Parking
Weaknesses
• Lack of activities / facilities for
young people
• Lack of connectivity/walk-ability/
visibility
• Lack of ‘dwell’ points and shelter
• Competing with out of town retail
• Lack of attractors
• Lack of a clear purpose
• Too focused on Queens Quay
• Lack of heart to town centre
• Inward facing shopping centre
closes at 5.30pm
• Lack of green space
• Shortage of spaces to hang out
informally for free
• Lack of activation around Three
Queens Square
Opportunities
• People want to live in the area
• Proximity to rest of Scotland
(Kilpatrick hills and beyond)
• The Canal
• Clydebank as green sustainable
town
• Lose parking, gain green space
• Open space and vacant sites
• Offer an authentic town centre,
unlike Braehead etc.
• Cultural opportunities (west of
Scotland’s cultural centre)
• Digital connectivity and skills
• Renfrew bridge
• Open up shopping centre to
canal for bars & restaurants
• More housing / more people
Threats
• Renfrew bridge
• Traffic (Kilbowie Road & bridge)
• Lack of funding
• Queens Quay successful but
disconnected from town
• Policy limitations on pubs in areas
of centre
• Town centre closes when
shopping centre closes
Clydebank Town Centre Vision
& Development Framework
Workshop 1 Outcomes: 
SWOT Analysis (Strengths, Weaknesses,Opportunities, Threats)
Workshop 3 Outcomes:   
What do I need from my Town Centre?
What would make me live in Clydebank town centre?

Page 9

16 Three Year Investment Plan 17Context
High Street
• Create a recognisable town
centre, not just a decent shopping
centre
• A greater focus on corner/
speciality shops rather than the
‘vanilla’ high street offerings in
place within the current Clyde
Centre
• There will probably be a drift
of people to Braehead when
the bridge is completed, so the
offering in Clydebank will have to
be diverse and appealing if trade
is to be maintained
• Canal is significant factor in ‘high
street’ – this needs to be better
utilised.
• Current store locations /
entrances don’t reflect the
opportunities to maximise the
canal as an extension of the high
street
• Dog litter bins on all main streets
• Seating for older people/disabled
Better, more accessible meeting
spaces
• Better, more accessible use of
existing, available community
buildings for community activity. 
• Developing any new community
spaces should be on the basis
that they can support diverse
activities
• Disabled access and needs must
be taken more seriously
• Local parks need more attention
and equipment. Valuable to
support the wellbeing outdoors
brings, but must be kept open
• Ensure basic rights for children to
have safe free areas for play
• Destinations and activities which
allow families to socialise together
free or at low cost
• Resources to help to keep local
community centres open
• Exercise equipment in playparks/
parks
• Extend a Waterfront walkway
to the Hospital / Beardmore...
Bistros, cafes, a Saturday market.
Heritage and Culture
• New sustainable projects are
needed to exploit the areas’
heritage and culture to attract
people to the area, including local
people
• Projects to get more local
people involved in arts & culture,
need to think about how these
can be better used to support
employability and provide
employment opportunities
• The canal is a large part of
Clydebank’s heritage however the
lack of maintenance/innovation in
its use is off-putting.
• Improved walking routes, linking in
local walking groups and history
society to ensure a sustainable
collaborative approach
• Three Queens Square is vastly
under-used. This civic community
asset has huge potential yet is
used only a handful of times per
year
• There is a lack of evidence of
Clydebank’s importance in the
Industrial heritage of Scotland. A
world-class museum evidencing
John Brown’s Shipyard and the
Singer Sewing Machine Factory
would be highly desirable: also a
living memorial to the Clydebank
Blitz. The Kelpies have brought an
estimated 80 million to their local
area in the last 10 years. If done
correctly, a purpose-built heritage
centre/theatre could do the same
here. Work with the Shipyard
Trust to deliver?
A questionnaire based around the
three key investment themes was
developed and issued by CVS to 37
registered groups with a potential
membership reach of around 9000
people within the Clydebank area.
Returns were received from 19
groups and the findings collated and
published in July 2024.
A summary of the key responses is
shown on the next pages under each
theme.
Clydebank Town Board
Consultation Questionnaire
Responses:
High Streets, Heritage and Regeneration

Page 10

18 Three Year Investment Plan 19Context
Road/Pavement Routes
• Potholes and broken pavements
damage cars and people
• We’d like to see paths and cycle
paths especially along the canal
area
• Pedestrians hardly able to get
halfway across the road before
the lights change especially on
Kilbowie Road
• Immediate issue with the pending
relocation of the Carers Centre.
• More improvements to roads
& pavements especially for the
disabled as not enough lowered
curbs & not enough disabled
parking
• Shared space model in
Dumbarton Road is not working
as expected. A number of
near misses, car-car and car-
pedestrian. Also turning space for
buses onto Kilbowie Road is now
problematic
• Better street-lighting needed. LED
lighting is very poor especially in
winter
• The bus lane on Kilbowie Road
between Hardgate and the Fire
station isn’t working. It is creating
way more congestion than it is
solving.
• Many utility providers have dug up
pavements leaving them uneven
which may lead to walkers being
injured. The Council should
ensure that the contractors leave
the pavements in an acceptable
condition.
• Need to cut green areas more
often cut down over hanging
trees.
Infrastructure
• Better broadband -  fibre
broadband is not widely available
• Better lighting, better outdoor
seating, better interactivity
• Lightning along the canal
pathways
• Improve the environment
by cleaning up the Canal /
overgrown grass / trees.
• Upgrade / provide public toilets
• The improvement to canal path
at Centre 81 was great - more
activities and connections to
improve the usage, safety and
active travel activities
Public Transport
• New and extended bus routes
needed – and running into the
evening
• Bus / Train interchange needs
to be fulfilled.  Visually impaired /
disabled persons have difficulty
because of the number of bus
shelters
• Lack of bus route to / lack of
parking at the health centre is a
significant issue
Community Policing – as deterrent
and engagement tool
• Greater police presence on the
ground to deter gathering in
groups
• Anti-Social behaviour is increasing
including gang challenges
• Feeling of being unsafe in
certain key areas e.g. underpass
between Shopping Centre and
Business Park and areas of
Canalside, especially after 5pm
• Do not use policing tactics
that target the young and
poor, alienating them from the
policing community – increase
engagement to reduce past
perceptions
• Policing of increasingly visible
e-bike/drug dealing issues.
• Does CCTV actually deter crime
– people and communities deter
crime
• Better policing needed to ensure
outdoor meeting spaces are safe
and available for all sections of the
community
Community Engagement /
Participation
• Increased and more diverse
range of community opportunities
for children and young people –
revitalising community facilities
• General lack of dedicated places
for young people. Commonly
used spaces are badly lit and
not well policed, raising issues of
safety
• Increased focus on disabled
access
• More regular outdoor activities
and greater focus on maximising
outdoor spaces and opportunities
for wellbeing
• Support for neighbourhood-
based initiatives such as gala
days/events
• Make more use of the Riverside,
in innovative way, not for
additional housing
• Investment in community facilities
should not be limited to larger
organisations but should focus
on neighbourhood services,
increasing local buy-in and
feelings of ownership
Amenities
• Better repairs for potholes on key
roads - temporary repairs are a
false economy and cause issues
for disabled people and carers
• Traffic crossing timings do not
reflect the actual time required for
pedestrians to cross – causing
anxiety in older residents and
potentially restricting engagement
• Improving street lightning and
extending this to cover areas such
as cycle paths and canals would
ensure these areas can be used
all year round.
• Need for more lowered kerbs
where disabled or elderly people
live
Responses:
Transport and Connectivity
Responses:
Safety and Security

Page 11

20 Three Year Investment Plan 21Context
Public engagement events were
held on the 25th and 26th July
in the Clyde Shopping Centre
to showcase the project and
ascertain the opinions of the local
community.
Over the two days there were 111
attendees to the event. The display
boards remained on display in the
Shopping Centre and were also
hosted online. A deadline of 9th
August was set for responses. In total
308 responses were received.
A detailed report can be found
in the appendices section of this
document, however a summary of
the key responses received can be
summarised as follows:
Public Engagement Events:
Clyde Shopping Centre
Public Engagement:
Feedback Summary
Don’t Know
Yes
No
Are you aware of or have you
participated in any of the previous
consultations in Clydebank?
Have you heard of the Long Term Plan
before today?
Don’t Know
Yes
No
Part 1: About the Long Term Plan
Part 2: Prioritising Projects
Theme 1 -
High Streets, Heritage and Regeneration
Respondents were given the
opportunity to highlight specific
activities and suggest additional
ideas that can be looked at in the
first three years of the fund. Below
is the thematic analysis of the
respondents’ suggestions.
The most recurrent theme was
activities and amenities for families
and young people - especially
teenagers - to attract people to
Clydebank, enhance health and
wellbeing and to divert the youth
from anti-social behaviour. There was
an emphasis that these should be
affordable.
The other suggestions were:
Maintenance and cleanliness of the
whole area
-
The creation of a multi-group centre
-
Amenities and activities for all ages
including families and young people
that are affordable
-
Parks and green areas
-
Better use of the river and canal for
activities
-
Regeneration of the Clydebank
Shopping Centre
-
Improved Night economy

Page 12

22
The combined feedback based
on responses from both the
questionnaire and the public
engagement events has produced
lists of desired projects /
interventions from the community.
They are presented here under
their relevant investment theme
heading.
There has been a consistency of
responses across all community
engagement undertaken, including
the earlier events that influenced the
recent Clydebank Town Centre Vision
and Development Framework.
Focusing on the town centre was a
strong message received through the
engagement process, as people felt it
was where the funding could have the
biggest long term impact and would
be the most visible.
The vast majority of the interventions
suggested by the public are included
within the long list but two currently
are not, as they do not have a physical
building / landscape component,
namely:
• Better broadband and digital
access
• Increased hot-spot policing
23
High Streets, Heritage
and Regeneration
Transport and
Connectivity
Safety and Security
Context
In order of Preference:
1.   New Parks / Green Spaces
2.   Better Use of Community
Spaces
3.   Funding for Sports
Facilities and Bringing
People Together
4.   Funding for Volunteering
and Social Action Projects
5.   Improving the Shopping
Area
In order of Preference:
1.   Better Maintenance of
Roads / Pavements
2.   Upgrade or Create New
Footpaths / Cycle paths
3.   Better Connectivity of Train
/ Bus Travel Options
4.   Better Broadband & Digital
Access
5.   New Greenspace at the
Canal
In order of Preference:
1.   Diversionary Activities for
Young People
2.   Increased Hot-spot
Policing
3.   Better Streetlighting
4.   Ensure Daytime & Evening
Activity
5.   Activate the Canalside for
All
Long Term Plan Community Engagement:
Summary of Findings
Three Year Investment Plan
The respondents were given the
opportunity to highlight specific
activities and suggest additional ideas
that can be looked at in the first three
years of the fund. Below is the analysis
of the respondents’ comments and
suggestions.
The comments and suggestions
received were:
Diversionary activity for young people:
engage youth and prevent antisocial
behaviour.
-
More facilities and opportunities in
Clydebank: music venues, an arcade
centre which stays open till at least
10pm
-
Regular outdoor events to build
positive police-youth relationships
-
Create graffiti walls around Clydebank
-
Improve street lighting around new
housing and canal paths to boost
safety and encourage use
-
Improve the Railway viaduct
-
Town-wide safety measures by
implementing CCTV, improved lighting
-
Increase police presence and
community care to tackle anti-social
behaviour and drug dealing including
more social workers
-
Engagement with young people and
educate the youth on hate crimes
against disabled people
-
Enhance security to deter group
gatherings and ASB
-
Increase town centre living
The respondents were given the
opportunity to highlight specific
activities and suggest additional
ideas that can be looked at in the
first three years of the fund. Below
is the analysis of the respondents’
comments and suggestions.
The comments and suggestions
received were:
Develop walking routes with history
markers, sustainable lighting, central
clock, and canal integration
-
Create better connections to enhance
green link movement and overall town
walkability.
-
Develop and extend bus routes,
including a dedicated route to the
health centre, Queens Quay and
Golden Jubilee for better accessibility.
-
Address the need for a bus station,
improve local main routes, and
enhance bus stops
-
Repair potholes and broken
pavements
-
Create a scheme for green bicycles
and scooters for short term hire.
-
Enhance connectivity with the south
side of the city, specifically Renfrew &
Braehead.
-
Introduce bus boats going along
Clyde both to Greenock and to
Glasgow.
-
Better broadband connection,
introduce fibre broadband.
Theme 2 -
Transport and Connectivity
Theme 3 -
Safety and Security

Page 13

The long list of potential
interventions outlined in the
following pages was developed
using both the recently completed
Clydebank Town Centre Vision
and Development Framework and
the responses to the Community
Engagement
In accordance with the UK
Government guidance, each
intervention was judged as to its status
as either ‘on menu’ or ‘off menu’.
The pre-determined list of ‘on menu’
interventions from the guidance for
each of the three investement themes
is shown below.
All potential interventions were
determined to be ‘on menu’ and, in
accordance with the guidance, where
it spaned more than one theme, it was
wholly allocated to the theme that it
best meets.
Transport and Connectivity
Pre-determined ‘On Menu’ Interventions
2524
High Streets, Heritage and Regeneration
Pre-determined ‘On Menu’ Interventions
H1: Funding for place-based
regeneration and town centre and high
street improvements.
H2: Funding for new or improvements
to existing, community and
neighbourhood infrastructure projects
and assets including those that
increase communities’ resilience to
natural hazards, such as flooding, and
support for decarbonisation of
facilities, energy efficiency audits, and
installation of energy efficiency and
renewable measures in community
buildings.
H3: Creation of, and improvement
to, local green spaces, community
gardens, watercourses and
embankments.
H4: Enhanced support for arts,
cultural, heritage and creative activities,
projects and facilities and historic
institutions that make up the local
cultural heritage offer.
H5: Support for local arts, cultural,
heritage and creative activities.
H6: Funding for the development and
promotion of wider campaigns which
encourage people to visit and explore
the local area.
H7: Funding for impactful volunteering
and social action projects.
H8: Funding for local sports facilities,
tournaments, teams and leagues.
H9: Investment in capacity building,
resilience (which could include climate
change resilience) and infrastructure
support for local civil society and
community groups.
H10: Investment and support for digital
infrastructure for local community
facilities.
H11: Investment in open markets and
improvements to town centre retail
and service sector infrastructure,
with wraparound support for small
businesses.
H12: Funding for the development and
promotion (both trade and consumer)
of the visitor economy, such as local
attractions, trails, tours and tourism
products more generally.
H13: Grants to help places bid for and
host international business events and
conferences that support wider local
growth sectors.
T1: Support for active travel
enhancements in the local area.
T2: Funding for bus infrastructure and
connections to speed up journeys.
T3: England and Scotland Only:
Additional revenue funding added
to the Bus Service Improvement
Programme Plus (BSIP+) funding
model from June 2024.
T4: Funding for new, or improvements
to road networks to improve access
within and to the town.
T5: Funding to improve rail connectivity
and access.
T6: Reducing vehicle emissions.
T7: Investment and support for digital
infrastructure for local community
facilities.
Safety and Security
Pre-determined ‘On Menu’ Interventions
S1: Design and management of the
built and landscaped environment to
‘design out crime’.
S2: Engage with Police Force and
together consider interventions to
focus on visible crime prevention in
defined areas places.
S3: Measures to prevent anti-
social behaviour, crime and reduce
reoffending.
S4: Measures to reduce repeat
burglary.
Three Year Investment Plan Context
Development of the ‘Long List’

Page 14

2726
Description ‘Menu’ Compliance Visibility / Impact
1
2
3
4
Delivery
Considerations
Projected High Level
Cost (where possible to
determine)
The potential interventions below were
organised, as requested by the Town
Board in terms of ease of deliverability
based on a number of considerations:
• Potential programme to delivery
• Projected cost
• Land / asset ownership
Introduce a series of
‘meanwhile’ uses to vacant /
underlet buildings and spaces
throughout the town centre
H1: Funding for place-based
regeneration and town centre and
high street improvements.
H5: Support for local arts, cultural,
heritage and creative activities.
H7: Funding for impactful volunteering
and social action projects.
Instant positive transformation
of both vacant buildings / retail
units and gap sites or underused
external spaces, increasing
activity and vibrancy throughout
the town centre.
Opportunity for localised short
term improvements
Potential Programme:
3 - 12 months
Potential to host events, revenue
funding would be required
£100K - £500K
(dependent on scale / type of intervention(s)
proposed)
Improvements and activation
to Three Queens Square
H1: Funding for place-based
regeneration and town centre and
high street improvements.
H12: Funding for the development and
promotion of the visitor economy, such
as local attractions, trails, tours and
tourism products more generally.
Transforms existing inactive,
underused area into a leisure
(hospitality) focused active
community space.
Potential to introduce greenery,
better seating, childrens play or
temporary pavilion
Potential Programme:
52 - 76 weeks
Potential to host events, revenue
funding would be required
£0.5 million
(dependent on scale / type of intervention
proposed)
Transform the existing railway
viaducts with lighting and
public art and develop a
lighting / public art strategy
for town centre and key
connecting routes
S1: Design and management of the
built and landscaped environment to
‘design out crime’.
S3: Measures to prevent anti-
social behaviour, crime and reduce
reoffending.
More attractive, colourful and
vibrant urban realm that feels
safer for those passing through.
Potential Programme:
9 - 12 months
£0.6 million
Introduce a new Canalside
Activity Centre
H1: Funding for place-based
regeneration and town centre and
high street improvements.
H7: Funding for impactful volunteering
and social action projects.
H8: Funding for local sports facilities,
tournaments, teams and leagues.
Brings new activity and life to
the canal, reinvigorating Three
Queens Square in the process.
(Current published location does
not reflect published town centre
framework and may frustrate
future development)
New-build option already has
funding, potential programme:
12 months
Alternative location in repurposed
unit within Clyde Shopping
Centre adjacent to Canal
Potential Programme:
48 weeks
£1.3 million (majority secured from RCFG,
revenue funding required)
£0.5 million
‘Long List’ of Potential Interventions
Three Year Investment Plan Context
T&T High Level Cost
£1,824,273
Increase to scope & to include additional
area and improvements to existing surfaces
T&T High Level Cost
£756,300
Increase to scope & to include external works

Page 15

2928 Three Year Investment Plan Context
5
6
7
8
Description ‘Menu’ Compliance Visibility / Impact
Delivery
Considerations
Projected High Level
Cost (where possible to
determine)
Develop a new all ages
greenspace at the heart of the
town centre
H3: Creation of, and improvement
to, local green spaces, community
gardens, watercourses and
embankments.
Brings much needed multi-use
greenspace to the heart of the
town centre for the benefit of
the local population and visitors.
Positively transformational and
provides greater resilience
in terms of surface water
attenuation etc.
Proposed greenspace at
Playdrome site will be in private
ownership. Potential to improve
existing green ‘pockets’ on
canalside instead
Potential Programme:
42 -62 weeks
£0.5 - £0.75 million
(no location identified, dependent on extent of
intervention)
Undertake public realm
improvements within town
centre
T1: Support for active travel
enhancements in the local area.
T6: Reducing vehicle emissions.
Transforms the urban streets
and spaces throughout the town
centre, increasing accessibility
and promoting more walking /
wheeled journeys.
Potential Programme:
9 - 18 months
£0.5 - £2 million
(dependent on scale / type of intervention
proposed)
Strengthen connectivity and
accessibility to and from
town centre for surrounding
communities, Queens Quay
and the Golden Jubilee
Hospital
T1: Support for active travel
enhancements in the local area.
T6: Reducing vehicle emissions.
Visible improvements to routes
with the introduction of new
surface finishes, seating,
wayfinding / information signage
and lighting. Fewer journeys
being made by car, decreasing
road congestion and improving
air quality.
Potential Programme:
38 weeks
£0.5 - £2 million
(dependent on scale / type of intervention
proposed)
Develop of a series of new
walking / cycling trails
(Heritage / Active / Dog
Walking / Safe Walking etc.)
H12: Funding for the development
and promotion (both trade and
consumer) of the visitor economy,
such as local attractions, trails, tours
and tourism products more generally.
Visible improvements to a
number of routes with the
introduction of new surface
finishes, seating, wayfinding /
information signage and lighting.
Potential Programme:
40 weeks
£0.3 - £2 million
(dependent on extent and number of routes /
trails proposed)
T&T High Level Cost
£993,600
(Based on provision of three new trails)
T&T High Level Cost
£1,238,000
(Queens Quay, GJH & 5 Neighbourhood
routes)
T&T High Level Cost
£1.23 - 2.34 million
(Based on ‘small’ and ‘large’ options)

Page 16

3130
9
10
11
12
Description ‘Menu’ Compliance Visibility / Impact
Delivery
Considerations
Projected High Level
Cost (where possible to
determine)
Make Improvements to public
transport provision
T1: Support for active travel
enhancements in the local area.
T2: Funding for bus infrastructure and
connections to speed up journeys.
T5: Funding to improve rail
connectivity and access.
Enhanced environment around
train station and bus stance
areas. Fewer journeys being
made by car, decreasing road
congestion and improving air
quality.
Transport Interchange proposals
may take 3+ years to deliver
Opportunity for localised short
term improvements
Potential Programme:
9 - 18 Months
£6 million +
£0.5 - £1.5 million
(dependent on scale / type of intervention
proposed)
Work with West College
Scotland to bring elements
of their public facing services
(hair and beauty / catering
etc. to the town centre
H11: Investment in open markets and
improvements to town centre retail
and service sector infrastructure,
with wraparound support for small
businesses.
Could restore activity to existing
underused / vacant street level
spaces within the town centre
combined wth an increase in
footfall.
Potential Programme:
6 - 9 Months
£100K - £250K
(dependent on scale / type of intervention
proposed)
Improve accessibility by
providing new public welfare
facilities including a changing
places toilet, improved seating
and sheltered areas within the
town centre
H1: Funding for place-based
regeneration and town centre and
high street improvements.
Improves accessibility,
welcoming all members of the
community to enjoy their town
centre, regardless of age or
ability. Creates a more attractive
urban realm and encourages
greater dwell time within the
town centre.
Could be located within existing
vacant unit or as part of new
canalside activity centre or
market hall community building
(should these be taken forward)
Potential Programme:
12 -18 Months
£0.75 - £1 million
(If stand alone new build element)
Encourage new workplace
(flexible co-work / maker
spaces) at the heart of the
town centre
H5: Support for local arts, cultural,
heritage and creative activities.
H11: Investment in open markets and
improvements to town centre retail
and service sector infrastructure,
with wraparound support for small
businesses.
Increases activity, footfall and
employment opportunities at the
heart of the town centre
Potential use for vacant retail units
or former council ‘one stop shop’
on Sylvania Way or within upper
levels of Co-operative building
Potential Programme:
6 Months
£TBC
Three Year Investment Plan Context

Page 17

3332
13
14
15
16
Description ‘Menu’ Compliance Visibility / Impact
Delivery
Considerations
Projected High Level
Cost (where possible to
determine)
Create new serviced
development platforms with
associated streetscape and
public realm, to facilitate the
Introduction of new mixed-use
residential blocks south of the
canal at the heart of the town
centre
H1: Funding for place-based
regeneration and town centre and
high street improvements.
Positively transforms key town
centre routes, introducing scale,
enclosure, active street facing
uses and passive surveillance
Requires purchase of southern
end of shopping centre (Current
lease lengths TBC)
Potential Programme:
36 - 48 Months
£5 million (includes allowance of £2 million for
purchase of asset)
Introduce a new town square
/ events space adjacent to
Co-operative building on
Sylvania Way
H1: Funding for place-based
regeneration and town centre and
high street improvements.
H5: Support for local arts, cultural,
heritage and creative activities.
Positively transforms town centre
through the introduction of an
active space of civic quality
at a key location, visible upon
approach from distance and
upon arrival by bus or train.
Creates a visible heart to the
town and community.
Requires as a minimum purchase
of part of southern end of
shopping centre (Current lease
lengths TBC)
Potential Programme:
24 Months
Potential to host events, revenue
funding would be required
£4 million (includes allowance of £1 million
for purchase of relevant section of asset)
Develop a new market hall /
community building at heart
of the town centre framing
proposed town square
H5: Support for local arts, cultural,
heritage and creative activities.
H11: Investment in open markets and
improvements to town centre retail
and service sector infrastructure,
with wraparound support for small
businesses.
Highly visible new element at
the heart of the town centre with
active frontages energising the
adjacent square and streets in
stark contrast with existing inward
looking shoping ‘parade’ that
currently occupies the site.
Contingent on progressing with
new town square works to create
cleared site
Potential Programme:
18 Months
£2 million
Introduce more diverse uses
to Co-operative Building
and other heritage assets to
safeguard their future
H1: Funding for place-based
regeneration and town centre and
high street improvements.
H4: Enhanced support for arts,
cultural, heritage and creative activities,
projects and facilities and historic
institutions that make up the local
Improves the building fabric
and provides greater footfall
around and within a key heritage
asset of the town centre. More
visible impact from street level
intervention.
Would require agreement with
owners / operators of building(s)
Potential Programme:
9 - 12 Months
£0.5 - £1 million
(dependent on extent of intervention)
Three Year Investment Plan Context

Page 18

3534 Three Year Investment Plan Context
Selection of Three Year
Investment Plan Priorities
Long List Project 5:
Develop of a series of new walking and cycling trails
(Heritage / Active / Dog Walking / Safe Walking etc.) which
could link with existing squares and spaces within the town.
A combination of Long List Projects 2 and 4:
Introduce a series of Improvements and activation to
Three Queens Square; and Introduction of new Canalside
Activity Centre.
1. 2.
Long List Project 8:
Develop new all ages greenspace at the heart of the town
centre.
Long List Project 7:
Strengthen connectivity and accessibility to and from town
centre for surrounding communities, Queens Quay and
the Golden Jubilee Hospital. This would include exploring
better public transport provision with SPT so links with
project 12.
3. 4.
HIGH ST R EETS, H
E
R
ITAGE & REGENERATIO
N
TRANSPOR
T
&
CONNECTIVITY
HIGH ST R EETS, H
E
R
ITAGE & REGENERATIO
N
HIGH ST R EETS, H
E
R
ITAGE & REGENERATIO
N
Chosen Interventions
The Long List of potential
interventions outlined on pages
26-33 was presented to the Town
Board at their meeting on 2nd
August 2024.
Following the meeting, it was
reorganised in terms of ease
of deliverability and issued for
consideration.
Board members were requested
to respond with their comments
and to select their top four potential
interventions. These were then
compiled into a preference chart
based on their collective popularity.
The Chair of the Town Board then
met with representatives of West
Dunbartonshire Council and the
final list of chosen interventions was
decided upon and issued to the
design team.
The next chapter of this report
illustrates the RIBA Stage 1 initial
design concepts for each of the
shortlisted interventions.
Moving Forward
As stated, the next chapter illustrates
an RIBA Stage 1 response from
the design team that has developed
a detailed brief and initial concept
design proposals, together with a
high level view of costs, preliminary
programme and associated project
risks.
Beyond this work, it is recommended
that the Town Board select the
detailed intervention(s) they wish to
take forward first and appoint a design
team to assist them in developing
designs through the necessary RIBA
Stages, that would involve:
• Design development
• Obtaining all necessary statutory
consents,
• Providing regular updates and
checks on costs,
• Preparation of production
information
• Tendering the works
• Working with a Contractor to
deliver on site.
Requirement for Revenue Funding
In order to maximise the opportunities
that the selected interventions will
bring to Clydebank and to ensure
their ongoing positive impact for the
community, there may require to be an
allowance for revenue funding for the
following purposes:
• Event organisation and
management
• Ongoing maintenance costs for
capital projects

Page 19

37Report TitleClydebank Long Term Plan36
chosen
interventions
3736 Chosen InterventionsThree Year Investment Plan

Page 20

3938 Three Year Investment Plan Chosen Interventions
Priority Intervention 1: Town
Centre Walking and Cycling Trails
Harbour Promenade, Oslo
Only a few years ago to be able to walk along the
Oslo harbour for almost 10 kilometres, with no
interruptions was unimaginable.
The route reconnects old and new parts of the city
with a variety of experiences, big and small, to be
enjoyed along the way.
Orange towers show the way
Information markers with a shipping container
aesthetic are set up at regular intervals along the
whole promenade, to make sure you find your way.
These are decorated with art and house boards with
information on nearby attractions and the historic
significance of the area.
Other interventions such as coffee kiosks and bench
seating creating pause points are also branded to
provide a consistent language to aid navigation along
the length of the route.
Clydebank town centre is currently
dominated by seas of surface
car parking with limited legible
pedestrian connectivity.
Creating a safer and more attactive
walking and cycling environment for all
within the town centre will ensure that
Clydebank evolves into a welcoming
and sustainable town, ready to
meet the challenges of the climate
emergency.
Three new trails are proposed, that
will appeal to a wide cross section of
the local community and, in the case
of the Heritage Trail, encourage an
increase in visitor numbers. Those
proposed are as follows:
1.  Clydebank Heritage Trail
2.  Active 2.5Km Trail
3.  Safe Walking / Dog walking Trail
The creation of a series of new walking
/ cycling routes and trails will not only
meet the ambition stated above but
willl also celebrate the town’s unique
history and heritage buildings, take
advantage of its key civic spaces
(Three Queens Square / Solidarity
Plaza / International Asbestos
Memorial), provide opportunities for
the community to ‘get active’ and
allow those with limited mobility a safe
defined route that links the key facilities
of the town centre together with many
pause points along the way.
All proposed trails take advantage of
existing streets and paths and do not
require the creation of extensive areas
of new hard surface finishes. There
may however be requirements for
localised strategic improvements to
surfaces to widen areas etc. to ensure
safe use by wheelchair users, cyclists
and prams. Identifying the extent of
these works is beyond the scope
of this study but will be determined
as part of the next stages of design
development.
Compliance with UK Government
Guidance
The creation of a series of new town
centre trails is ‘on menu’, as outlined
by criteria H12:
‘Funding for the development
and promotion (both trade and
consumer) of the visitor economy,
such as local attractions, trails,
tours and tourism products more
generally.’
Identifying Markers
The new routes are identified by
a series of physical interventions
within the existing urban realm. At
each heritage trail point of interest
an interpretation totem will provide
mapping and the history of the
location.
On all routes, at changes in direction
or at key points a combination of
new colour coded paving, directional
signage and a bench / planter would
clearly identify the trails. Precedent
examples of each component are
shown on the adjacent page.
Precedent Imagery
HIGH ST R EETS, HERITAGE & REGENERATIO
N
Community Feedback:
‘Activate the Canalside
for All ’
Community Feedback:
‘Upgrade or Create New
Footpaths / Cycle paths’

Page 21

1.   Clydebank Heritage Trail
The suggested heritage trail begins
and ends with the Co-operative
building, a key building of note at
the heart of the town centre.
The route continues to incorporate
Solidarity Plaza and the Town Hall
/ Library Complex on Dumbarton
Road before venturing down through
Queens Quay to experience the grade
‘A’ listed Titan Crane.
It then travels, via the International
Asbestos Memorial north through the
redeveloped Playdrome site to the
Forth and Clyde Canal before returning
via Sylvania Way to its starting point.
This route passes through all
key elements of the town centre,
encouraging increased footfall
for shops, cafes and businesses,
hopefully leading to longer dwell times.
x     Denotes building / point of interest
A new interpretation signage totem
to be introduced at each location
o     Denotes location for wayfinding
point. A 2m x 2m bonded resin
pavement insert, directional totem
and coordinated bench / planter at
each location (may be shared with
other routes where possible)
Proposed Route
4140 Three Year Investment Plan Chosen Interventions

Page 22

2.    Active Running / Cycling     
‘The Tower Route’
4342 Three Year Investment Plan
This circular route can be embarked
upon at any point and is 2.5 Km in
length to allow it to be used either
once or in a series of multiples to
travel the popular distances of 5
and 10 Km. 
It has has been conceived to minimise
interaction with vehicular transport
wherever possible whilst using the
distinctive ‘towers’ of the town centre
as markers and a connecting narrative.
It connects both the existing Leisure
Centre, West College Scotland, the
free bike hire facilities at Queen’s Quay
and the proposed Canalside Activity
Centre, the latter perhaps being the
ideal start / end point for cycling on the
route.
x     Denotes building / point of interest
o     Denotes location for wayfinding
point. A 2m x 2m bonded resin
pavement insert, directional totem
and coordinated bench / planter at
Chosen Interventions
Proposed Route

Page 23

3.    Safe Walking / Dog Walking Route
4544 Three Year Investment Plan
This route has been conceived to
provide a safe walking route that
takes in the key elements of the
town centre, from the shopping
and cafes to the canalside and new
grenspace.
A compact looping route, it runs along
predominantly pedestrianised streets
and pathways, provides shelter within
Sylvania Way and the opportunity to
diverge off into the Clyde Shopping
Centre and Retail Park, Three Queens
Square and to take advantage of
public transport options on Chalmers
Street for those wishing to venture
further afield.
It is also suitable as a dog walking
route and passes through a number of
proposed greenspaces, one of which
could incorporate an enclosed area
to allow dogs to run free under their
owners supervision.
It passes the majority of shops and
cafes in the heart of the town centre.
If these businesses were pet friendly
it would maximise their opportunity to
take advantage of the recent increase
in dog ownership.
o     Denotes location for wayfinding
point. A 2m x 2m bonded resin
pavement insert, directional totem
and coordinated bench / planter
at each location (may be shared
with other routes where possible)
Chosen Interventions
GG Three Queens
Square Sketch
Proposed Route

Page 24

4746 Three Year Investment Plan Chosen Interventions
High Level Cost Estimate
Client Confidential#
Clydebank LTP Options - Sketch 103 - Town Centre Trails
Item Unit Qty Total
Historic / Heritage totems at points of
interest, illuminated
Nr 10 £75,000
Wayfinding locations - 2x2m paving
intervention with coloured bonded
gravel / resin
m2 80 £28,000
Wayfinding locations - totem style
signpost
Nr 20 £30,000
Wayfinding locations - Bench / planter Nr 20 £60,000
Downtakings / repairs / making good Item 1 £400,000
£593,000
Add
Prelims @ 17.5% £103,775
Contingency @ 15% £104,516
Sub-total £801,291
Design fees @ 20% £160,258
Inflation to assumed project midpoint of 3Q 2025 £32,051
Total £993,600
Basis of High Level Costs
1. Costs are high level estimates based on limited information currently available.
2. Threesixty Architecture sketch drawing reference 24013-SK-103 Town Centre Trails.
3. Discussion on scope with Threesixty Architecture.
4. It is assumed the works at the various locations can be carried out in a single continuous phase.
5. It is assumed that power would be readily available at each location.
6. Assume no issues in relation to ownership / wayleaves etc.
7. Inflation is based on high level programme indicated by TTPM.
Exclusions From High Level Costs
1. General drainage or street lighting works.
2. Any work in connection with utility services or diversion of same.
3. Any work not stated or implied on drawings.
4. VAT on works or fees.
Preliminary Programme, Risk
and Approval Considerations
Risk
1.   Power supplies not easily accessible for illuminated
totems throughout trails and that extensive diversions/
new supplies are required.
2.   Interventions in remote locations could be subject
to vandalism and plastered with stickers, etc. if
not designed robustly with security and ongoing
maintenance in mind.
3.   Proposed interventions may not be located within an
area of local authority ownership and either need to be
changed, or permission sought to install.
4.   Conflict / injury from overlapping of walking, wheeled
and running routes.
5.   Extent of existing repairs to make surfaces consistently
safe and viable is underestimated.
Mitigation
Utilities surveys of intervention locations to be undertaken at
earliest opportunity and proposals amended accordingly to
minimise cost / requirement for diversions.
Ensure robust design of any elements to minimise damage
from vandalism, ensure allowance for ongoing maintenance
and develop detailed design in collaboration with planned
CCTV roll-out. The combined stategies of the Vision will
lead to more activity and passive surveillance.
Identify ownerships as a priority moving forward and adjust
locations / begin dialogue with owners where necessary.
Delineation where practical and signage reinforcing
pedestrian priority.
Enhanced allowance for making good surfaces and
detailed survey in subsequent stages of design and
scoping.
The programme above demonstrates that the three trails described in this report could be
developed from this initial concept and delivered in a 40 week period (subject to extent of
making good established in detail design stages).
Lifecycle costs for ongoing maintenance of totems in particular to be established in following
development stages and added to budget.
This is based on the following key stages:
Approval / Utility   Required (Yes / No)
Planning   N
Warrant   Y
RCC   N
Utility Diversion / Supply  Y (Power for signage)
Landlord Approval   N
Other Approvals   N
© Turner & Townsend Project Management. All rights reserved 21/08/2024. This document is expressly provided to and solely for the use of West Dumbartonshire Council and must not be quoted from, referred to,
used by or distributed to any other party without the prior consent of Turner & Townsend Project Management who accept no liability of whatsoever nature for any use by any other party.
Clydebank 3 year plan options
Programme
Notes:
Gantt Chart Ref: C:\Users\youngdav1\OneDrive - Turner & Townsend Group Limited\Desktop\Clydebank LTP\3 Year plan options\Programmes\Clydebank 3 year plan options.pp
Border Ref: C:\Users\youngdav1\OneDrive - Turner & Townsend Group Limited\Desktop\1. T&T MASTER Landscape.B
Programme No:01                             
Revision:   on date: 
Origin Date: 21/08/2024  page 1 of 1
Turner & Townsend Project Management
Clydebank 3 year plan options 
Programme
Originator: David Young
Checked by: David Crombie
Approved by:           
Clydebank 3 year plan options
making the difference  1
Line Name Duration Start Finish
2024 2025
September October November December January February March April May June July August September October NovemberA Dec
2 9 16 23 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
3 year plan options
Town centre trails
Assemble design team
Design period inc
surveys
Client approval
Utility diversions inc
procurement and works
Procurement
Construction inc
mobilisation
Completion
Three Queens Square
Assemble design team
Design period inc
surveys
Client approval
Planning
Landlord approval
Scottish Water approval
for new drainage
Procurement inc
containers
Construction inc
mobilisation
Completion
Canalside Activity
Centre
Assemble design team
Design period inc
surveys
Client approval
Planning
Building Warrant
Landlord approval/ AfL
Scottish Canals approval
Procurement
Construction inc
mobilisation and lift
procurement
Completion
Greenspace Option 1
Assemble design team
Design period inc
surveys
Client approval
Utility diversions inc
procurement and works
Planning
Procurement
Construction inc
mobilisation and lift
procurement
Completion
Greenspace Option 2
Assemble design team
Design period inc
surveys
Client approval
Utility diversions inc
procurement and works
Planning
Building Warrant for
skatepark and MUGA
Landlord approval for
car park alterations (not
inc land sale)
RCC for car park
alterations/ stopping up
Scottish Water approval
for new drainage
Procurement
Construction inc MUGA
and skatepark
procurement
Completion
Connecting
Communities - Queens
Quay, Golden Jubilee
and Wider Communities
Assemble design team
Design period inc
surveys
Client approval
Roads authority
approval for road
painting
Procurement
Construction
Completion
Meanwhile space - Basic
works
Assemble design team
Design period inc
surveys
Client approval
Planning/ advertisement
consent
Landlord approval/ AfL
Procurement
Construction
Completion
Meanwhile space -
Intensite strategy
Assemble design team
Design period inc
surveys
Client approval
Planning/ advertisement
consent
Building Warrant
Landlord approval/ AfL
Procurement
Construction
Completion
62w
40w
2w
6w
2w
20w
4w
12w
52w
2w
12w
2w
12w
8w
8w
20w
16w
48w
2w
12w
2w
12w
12w
8w
12w
12w
20w
42w
2w
8w
2w
20w
12w
16w
12w
62w
2w
16w
2w
20w
12w
12w
8w
12w
8w
16w
24w
38w
2w
10w
2w
8w
12w
12w
24w
2w
4w
2w
12w
8w
6w
6w
42w
2w
10w
2w
12w
12w
8w
12w
16w
02/09/2024
02/09/2024
02/09/2024
16/09/2024
28/10/2024
28/10/2024
11/11/2024
31/03/2025
27/06/2025
02/09/2024
02/09/2024
16/09/2024
09/12/2024
06/01/2025
06/01/2025
09/12/2024
06/01/2025
30/05/2025
22/09/2025
02/09/2024
02/09/2024
16/09/2024
09/12/2024
09/12/2024
09/12/2024
06/01/2025
09/12/2024
06/01/2025
31/03/2025
22/08/2025
02/09/2024
02/09/2024
16/09/2024
11/11/2024
11/11/2024
11/11/2024
25/11/2024
14/04/2025
11/07/2025
02/09/2024
02/09/2024
16/09/2024
20/01/2025
20/01/2025
20/01/2025
20/01/2025
03/02/2025
20/01/2025
20/01/2025
03/02/2025
13/06/2025
01/12/2025
02/09/2024
02/09/2024
16/09/2024
25/11/2024
25/11/2024
09/12/2024
17/03/2025
13/06/2025
02/09/2024
02/09/2024
16/09/2024
14/10/2024
14/10/2024
28/10/2024
28/10/2024
20/01/2025
03/03/2025
02/09/2024
02/09/2024
16/09/2024
25/11/2024
25/11/2024
25/11/2024
09/12/2024
09/12/2024
17/03/2025
11/07/2025
01/12/2025
27/06/2025
13/09/2024
25/10/2024
08/11/2024
28/03/2025
06/12/2024
26/06/2025
27/06/2025
22/09/2025
13/09/2024
06/12/2024
20/12/2024
28/03/2025
28/02/2025
14/02/2025
29/05/2025
19/09/2025
22/09/2025
22/08/2025
13/09/2024
06/12/2024
20/12/2024
14/03/2025
14/03/2025
28/02/2025
14/03/2025
28/03/2025
21/08/2025
22/08/2025
11/07/2025
13/09/2024
08/11/2024
22/11/2024
11/04/2025
14/02/2025
28/03/2025
10/07/2025
11/07/2025
01/12/2025
13/09/2024
17/01/2025
31/01/2025
12/06/2025
11/04/2025
11/04/2025
28/03/2025
11/04/2025
14/03/2025
29/05/2025
28/11/2025
01/12/2025
13/06/2025
13/09/2024
22/11/2024
06/12/2024
31/01/2025
14/03/2025
12/06/2025
13/06/2025
03/03/2025
13/09/2024
11/10/2024
25/10/2024
17/01/2025
20/12/2024
06/12/2024
28/02/2025
03/03/2025
11/07/2025
13/09/2024
22/11/2024
06/12/2024
28/02/2025
28/02/2025
14/02/2025
14/03/2025
10/07/2025
11/07/2025
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
Milestone Appearances
Start Milestone
© Turner & Townsend Project Management. All rights reserved 21/08/2024. This document is expressly provided to and solely for the use of West Dumbartonshire Council and must not be quoted from, referred to,
used by or distributed to any other party without the prior consent of Turner & Townsend Project Management who accept no liability of whatsoever nature for any use by any other party.
Clydebank 3 year plan options
Programme
Notes:
Gantt Chart Ref: C:\Users\youngdav1\OneDrive - Turner & Townsend Group Limited\Desktop\Clydebank LTP\3 Year plan options\Programmes\Clydebank 3 year plan options.pp
Border Ref: C:\Users\youngdav1\OneDrive - Turner & Townsend Group Limited\Desktop\1. T&T MASTER Landscape.B
Programme No:01                             
Revision:   on date: 
Origin Date: 21/08/2024  page 1 of 1
Turner & Townsend Project Management
Clydebank 3 year plan options 
Programme
Originator: David Young
Checked by: David Crombie
Approved by:           
Clydebank 3 year plan options
making the difference  1
Line Name Duration Start Finish
2024 2025
September October November December January February March April May June July August September October NovemberA Dec
2 9 16 23 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
3 year plan options
Town centre trails
Assemble design team
Design period inc
surveys
Client approval
Utility diversions inc
procurement and works
Procurement
Construction inc
mobilisation
Completion
Three Queens Square
Assemble design team
Design period inc
surveys
Client approval
Planning
Landlord approval
Scottish Water approval
for new drainage
Procurement inc
containers
Construction inc
mobilisation
Completion
Canalside Activity
Centre
Assemble design team
Design period inc
surveys
Client approval
Planning
Building Warrant
Landlord approval/ AfL
Scottish Canals approval
Procurement
Construction inc
mobilisation and lift
procurement
Completion
Greenspace Option 1
Assemble design team
Design period inc
surveys
Client approval
Utility diversions inc
procurement and works
Planning
Procurement
Construction inc
mobilisation and lift
procurement
Completion
Greenspace Option 2
Assemble design team
Design period inc
surveys
Client approval
Utility diversions inc
procurement and works
Planning
Building Warrant for
skatepark and MUGA
Landlord approval for
car park alterations (not
inc land sale)
RCC for car park
alterations/ stopping up
Scottish Water approval
for new drainage
Procurement
Construction inc MUGA
and skatepark
procurement
Completion
Connecting
Communities - Queens
Quay, Golden Jubilee
and Wider Communities
Assemble design team
Design period inc
surveys
Client approval
Roads authority
approval for road
painting
Procurement
Construction
Completion
Meanwhile space - Basic
works
Assemble design team
Design period inc
surveys
Client approval
Planning/ advertisement
consent
Landlord approval/ AfL
Procurement
Construction
Completion
Meanwhile space -
Intensite strategy
Assemble design team
Design period inc
surveys
Client approval
Planning/ advertisement
consent
Building Warrant
Landlord approval/ AfL
Procurement
Construction
Completion
62w
40w
2w
6w
2w
20w
4w
12w
52w
2w
12w
2w
12w
8w
8w
20w
16w
48w
2w
12w
2w
12w
12w
8w
12w
12w
20w
42w
2w
8w
2w
20w
12w
16w
12w
62w
2w
16w
2w
20w
12w
12w
8w
12w
8w
16w
24w
38w
2w
10w
2w
8w
12w
12w
24w
2w
4w
2w
12w
8w
6w
6w
42w
2w
10w
2w
12w
12w
8w
12w
16w
02/09/2024
02/09/2024
02/09/2024
16/09/2024
28/10/2024
28/10/2024
11/11/2024
31/03/2025
27/06/2025
02/09/2024
02/09/2024
16/09/2024
09/12/2024
06/01/2025
06/01/2025
09/12/2024
06/01/2025
30/05/2025
22/09/2025
02/09/2024
02/09/2024
16/09/2024
09/12/2024
09/12/2024
09/12/2024
06/01/2025
09/12/2024
06/01/2025
31/03/2025
22/08/2025
02/09/2024
02/09/2024
16/09/2024
11/11/2024
11/11/2024
11/11/2024
25/11/2024
14/04/2025
11/07/2025
02/09/2024
02/09/2024
16/09/2024
20/01/2025
20/01/2025
20/01/2025
20/01/2025
03/02/2025
20/01/2025
20/01/2025
03/02/2025
13/06/2025
01/12/2025
02/09/2024
02/09/2024
16/09/2024
25/11/2024
25/11/2024
09/12/2024
17/03/2025
13/06/2025
02/09/2024
02/09/2024
16/09/2024
14/10/2024
14/10/2024
28/10/2024
28/10/2024
20/01/2025
03/03/2025
02/09/2024
02/09/2024
16/09/2024
25/11/2024
25/11/2024
25/11/2024
09/12/2024
09/12/2024
17/03/2025
11/07/2025
01/12/2025
27/06/2025
13/09/2024
25/10/2024
08/11/2024
28/03/2025
06/12/2024
26/06/2025
27/06/2025
22/09/2025
13/09/2024
06/12/2024
20/12/2024
28/03/2025
28/02/2025
14/02/2025
29/05/2025
19/09/2025
22/09/2025
22/08/2025
13/09/2024
06/12/2024
20/12/2024
14/03/2025
14/03/2025
28/02/2025
14/03/2025
28/03/2025
21/08/2025
22/08/2025
11/07/2025
13/09/2024
08/11/2024
22/11/2024
11/04/2025
14/02/2025
28/03/2025
10/07/2025
11/07/2025
01/12/2025
13/09/2024
17/01/2025
31/01/2025
12/06/2025
11/04/2025
11/04/2025
28/03/2025
11/04/2025
14/03/2025
29/05/2025
28/11/2025
01/12/2025
13/06/2025
13/09/2024
22/11/2024
06/12/2024
31/01/2025
14/03/2025
12/06/2025
13/06/2025
03/03/2025
13/09/2024
11/10/2024
25/10/2024
17/01/2025
20/12/2024
06/12/2024
28/02/2025
03/03/2025
11/07/2025
13/09/2024
22/11/2024
06/12/2024
28/02/2025
28/02/2025
14/02/2025
14/03/2025
10/07/2025
11/07/2025
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
Milestone Appearances
Start Milestone
Expected Outcomes
and Benefits
Encourages active travel – Health and Well Being
Greater physical and emotional connection to town
centre and heritage – Shared Identity and Pride
Encourages Visitors and footfall strengthens
economic activity – Welcoming and Economic Resilience
Potential Risks
Approval / Utility Considerations
Assemble Design Team:     2 weeks
Design Development (incl. surveys):   6 weeks
Utilities Diversions (4 week Procurement
period runs concurrently):     20 weeks
Construction (incl. mobilisation period)   12 weeks
Client Confidential#
Clydebank LTP Options - Sketch 103 - Town Centre Trails
Item Unit Qty Total
Historic / Heritage totems at points of
interest, illuminated
Nr 10 £75,000
Wayfinding locations - 2x2m paving
intervention with coloured bonded
gravel / resin
m2 80 £28,000
Wayfinding locations - totem style
signpost
Nr 20 £30,000
Wayfinding locations - Bench / planter Nr 20 £60,000
Downtakings / repairs / making good Item 1 £30,000
£223,000
Add
Prelims @ 17.5% £39,025
Contingency @ 15% £39,304
Sub-total £301,329
Design fees @ 20% £60,266
Inflation to assumed project midpoint of 3Q 2025 £12,005
Total £373,600
Basis of High Level Costs
1. Costs are high level estimates based on limited information currently available.
2. Threesixty Architecture sketch drawing reference 24013-SK-103 Town Centre Trails.
3. Discussion on scope with Threesixty Architecture.
4. It is assumed the works at the various locations can be carried out in a single continuous phase.
5. It is assumed that power would be readily available at each location.
6. Assume no issues in relation to ownership / wayleaves etc.
7. Inflation is based on high level programme indicated by TTPM.
Exclusions From High Level Costs
1. General drainage or street lighting works.
2. Any work in connection with utility services or diversion of same.
3. Any work not stated or implied on drawings.
4. VAT on works or fees.
Client Confidential#
Clydebank LTP Options - Sketch 103 - Town Centre Trails
Item Unit Qty Total
Historic / Heritage totems at points of
interest, illuminated
Nr 10 £75,000
Wayfinding locations - 2x2m paving
intervention with coloured bonded
gravel / resin
m2 80 £28,000
Wayfinding locations - totem style
signpost
Nr 20 £30,000
Wayfinding locations - Bench / planter Nr 20 £60,000
Downtakings / repairs / making good Item 1 £30,000
£223,000
Add
Prelims @ 17.5% £39,025
Contingency @ 15% £39,304
Sub-total £301,329
Design fees @ 20% £60,266
Inflation to assumed project midpoint of 3Q 2025 £12,005
Total £373,600
Basis of High Level Costs
1. Costs are high level estimates based on limited information currently available.
2. Threesixty Architecture sketch drawing reference 24013-SK-103 Town Centre Trails.
3. Discussion on scope with Threesixty Architecture.
4. It is assumed the works at the various locations can be carried out in a single continuous phase.
5. It is assumed that power would be readily available at each location.
6. Assume no issues in relation to ownership / wayleaves etc.
7. Inflation is based on high level programme indicated by TTPM.
Exclusions From High Level Costs
1. General drainage or street lighting works.
2. Any work in connection with utility services or diversion of same.
3. Any work not stated or implied on drawings.
4. VAT on works or fees.

Page 25

A number of interventions are
proposed to breathe life back in to
Three Queens Square and attract
more people to the heart of the town
centre. The adjacent precedent
imagery shows the potential look and
feel of a number of these and their
combined effect is illustrated on pages
50-51. The interventions consist of the
following:
New mural to wall of existing centre to
southern edge of square
-
New shopfront glazing to existing units
that face onto square
-
Removal of glazed screens between
Sylvania Way ‘mall’ and the Square
and the replacement of existing paving
within newly exposed northern area of
Sylvania way ‘mall’
-
New fixed seating around the
Bandstand to facilitate performances
-
Pop-up services bollards to provide
power for markets and events
-
Urban Activity Park with designated
small children’s play, sports area and
dog exercise zone (option 2 only) 
surrounded by new paths, benches
and lighting
-
Significant allowance to be made for
reinforcing hard landscaping of 3QS
to accomodate flexible use by heavier
vehicles.
4948 Three Year Investment Plan Chosen Interventions
Priority Intervention 2a:
Improving Three Queens Square
The location of Three Queens
Square onto the Forth and
Clyde Canal would, in other
circumstances warrant a vibrant
town centre location.
However, and notwithstanding it’s
recent refurbishment in high quality
materials – it lacks activity and ‘civic-
ness’ for the following reasons:
Lack of enclosure due to a reduced
scale of built form
-
Lack of ‘overlooking’ and the passive
surveillance of a safe environment
-
Inactive facades to most of the
southern part of the Square
-
Dead façade to the Shopping
Centre on the north side creating an
unwelcoming environment
-
Lack of curated activity around the
refurbished bandstand
Lack of curated activity along the
Canal
Compliance with UK Government
Guidance
The creation of a series of new town
centre trails is ‘on menu’, as outlined
by criteria H1:
‘Funding for place-based
regeneration and town centre and
high street improvements.’
and H12:
‘Funding for the development and
promotion of the visitor economy,
such as local attractions, trails,
tours and tourism products more
generally.’
HIGH ST R EETS, HERITAGE & REGENERATIO
N
Precedent Imagery
Proposals
Community Feedback:
‘Activate the Canalside
for All’
Community Feedback:
‘Better Use of
Community Spaces’
Community Feedback:
‘Funding for Sports
Facilities and Bringing
People Together’

Page 26

5150 Three Year Investment Plan Chosen Interventions
Three Queens Square Transformed
(Option 1: Incorporation of Canalside Activity Centre)
Smaller Urban Activity Park with
designated small children’s play
surrounded by new paths, benches and
lighting.
Existing glazed screens
to Sylvania Way mall
removed to provide
access to square
New shopfronts to
commercial units onto
square
Pop-up power bollards
added to square to
facilitate markets and
events
New fixed seating
surrounding
Bandstand and
platform
New large format mural
to enliven existing blank
facade (note: design
shown here is indicative
only)
Potential for
temporary food
trucks to inhabit the
space
Proposed Activity Centre
building on south bank of
canal

Page 27

5352 Three Year Investment Plan Chosen Interventions
Preliminary Programme, Risk & Approval Considerations
Approval / Utility Considerations
Approval / Utility   Required (Yes / No)
Planning   Y
Warrant   Y
RCC   Y (Public Realm)
Utility Diversion / Supply  N (Assume existing 
mall services can be   
used)
Landlord Approval   Y (Mall facade     
alterations)
Other Approvals   Scottish Water for new 
drainage?
Client Confidential#
Clydebank LTP Options - Sketch 101 - Three Queens Square Improvement - Option 2
Item Unit Qty Total
Existing glazed screen to be removed and
structure retained, assumed 4.5m high
m2 153 £22,950
Allow for making good Item 1 £10,000
Allowance for reinforcement of existing
hard landscaping to Three Queens Square
for heavy vehicle usage
Item 1 £500,000
New external paving / surfacing to zone of
Sylvania Way revealed when mall screens
are removed
m2 350 £157,500
Enlargement of existing openings to
market hall
Item 1 £40,000
New Decorative Wall Mural m2 240 £36,000
Formation of small children's play area
(70% of overall area)
m2 187 £32,708
Perimeter fencing to small children's play
area
m 43 £3,240
Gates to small children's play area Nr 2 £2,500
Allowance for play equipment Item 1 £15,000
General downtakings / making good Item 1 £40,000
Allowance for drainage / street lighting
modifications
Item 1 £50,000
£909,898
Add
Prelims @ 17.5% £159,232
Contingency @ 15% £160,369
£1,229,499
Design fees @ 20% £245,900
Inflation to assumed project midpoint of 3Q 2025 £49,201
Total £1,524,600
Basis of High Level Costs
1. Costs are high level estimates based on limited information currently available.
2. Threesixty Architecture sketch drawing reference 24013-SK-101 Three Queens    
Square Improvement and emails dated 20/09/24 & 08/10/2024.
3. Discussion on reduction in scope with Threesixty Architecture in line with the addition of the    
activity centre.
4. It is assumed the works can be carried out in a single continuous phase.
5. It is assumed for the 'Box Park' services can be connected to the existing market hall development.
5. It is assumed the 'Box Park' facility is 2-storey with ground level F+B terrace.
6. Small children's play area - assumed new surfacing to 70% area and budget for play equipment.
7. Inflation is based on high level programme indicated by TTPM.
Exclusions From High Level Costs
1. Any work in connection with utility services or diversion of same.
2. Any work not stated or implied on drawings.
3. VAT on works or fees.
© Turner & Townsend Project Management. All rights reserved 21/08/2024. This document is expressly provided to and solely for the use of West Dumbartonshire Council and must not be quoted from, referred to,
used by or distributed to any other party without the prior consent of Turner & Townsend Project Management who accept no liability of whatsoever nature for any use by any other party.
Clydebank 3 year plan options
Programme
Notes:
Gantt Chart Ref: C:\Users\youngdav1\OneDrive - Turner & Townsend Group Limited\Desktop\Clydebank LTP\3 Year plan options\Programmes\Clydebank 3 year plan options.pp
Border Ref: C:\Users\youngdav1\OneDrive - Turner & Townsend Group Limited\Desktop\1. T&T MASTER Landscape.B
Programme No:01                             
Revision:   on date: 
Origin Date: 21/08/2024  page 1 of 1
Turner & Townsend Project Management
Clydebank 3 year plan options 
Programme
Originator: David Young
Checked by: David Crombie
Approved by:           
Clydebank 3 year plan options
making the difference  1
Line Name Duration Start Finish
2024 2025
September October November December January February March April May June July August September October NovemberA Dec
2 9 16 23 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
3 year plan options
Town centre trails
Assemble design team
Design period inc
surveys
Client approval
Utility diversions inc
procurement and works
Procurement
Construction inc
mobilisation
Completion
Three Queens Square
Assemble design team
Design period inc
surveys
Client approval
Planning
Landlord approval
Scottish Water approval
for new drainage
Procurement inc
containers
Construction inc
mobilisation
Completion
Canalside Activity
Centre
Assemble design team
Design period inc
surveys
Client approval
Planning
Building Warrant
Landlord approval/ AfL
Scottish Canals approval
Procurement
Construction inc
mobilisation and lift
procurement
Completion
Greenspace Option 1
Assemble design team
Design period inc
surveys
Client approval
Utility diversions inc
procurement and works
Planning
Procurement
Construction inc
mobilisation and lift
procurement
Completion
Greenspace Option 2
Assemble design team
Design period inc
surveys
Client approval
Utility diversions inc
procurement and works
Planning
Building Warrant for
skatepark and MUGA
Landlord approval for
car park alterations (not
inc land sale)
RCC for car park
alterations/ stopping up
Scottish Water approval
for new drainage
Procurement
Construction inc MUGA
and skatepark
procurement
Completion
Connecting
Communities - Queens
Quay, Golden Jubilee
and Wider Communities
Assemble design team
Design period inc
surveys
Client approval
Roads authority
approval for road
painting
Procurement
Construction
Completion
Meanwhile space - Basic
works
Assemble design team
Design period inc
surveys
Client approval
Planning/ advertisement
consent
Landlord approval/ AfL
Procurement
Construction
Completion
Meanwhile space -
Intensite strategy
Assemble design team
Design period inc
surveys
Client approval
Planning/ advertisement
consent
Building Warrant
Landlord approval/ AfL
Procurement
Construction
Completion
62w
40w
2w
6w
2w
20w
4w
12w
52w
2w
12w
2w
12w
8w
8w
20w
16w
48w
2w
12w
2w
12w
12w
8w
12w
12w
20w
42w
2w
8w
2w
20w
12w
16w
12w
62w
2w
16w
2w
20w
12w
12w
8w
12w
8w
16w
24w
38w
2w
10w
2w
8w
12w
12w
24w
2w
4w
2w
12w
8w
6w
6w
42w
2w
10w
2w
12w
12w
8w
12w
16w
02/09/2024
02/09/2024
02/09/2024
16/09/2024
28/10/2024
28/10/2024
11/11/2024
31/03/2025
27/06/2025
02/09/2024
02/09/2024
16/09/2024
09/12/2024
06/01/2025
06/01/2025
09/12/2024
06/01/2025
30/05/2025
22/09/2025
02/09/2024
02/09/2024
16/09/2024
09/12/2024
09/12/2024
09/12/2024
06/01/2025
09/12/2024
06/01/2025
31/03/2025
22/08/2025
02/09/2024
02/09/2024
16/09/2024
11/11/2024
11/11/2024
11/11/2024
25/11/2024
14/04/2025
11/07/2025
02/09/2024
02/09/2024
16/09/2024
20/01/2025
20/01/2025
20/01/2025
20/01/2025
03/02/2025
20/01/2025
20/01/2025
03/02/2025
13/06/2025
01/12/2025
02/09/2024
02/09/2024
16/09/2024
25/11/2024
25/11/2024
09/12/2024
17/03/2025
13/06/2025
02/09/2024
02/09/2024
16/09/2024
14/10/2024
14/10/2024
28/10/2024
28/10/2024
20/01/2025
03/03/2025
02/09/2024
02/09/2024
16/09/2024
25/11/2024
25/11/2024
25/11/2024
09/12/2024
09/12/2024
17/03/2025
11/07/2025
01/12/2025
27/06/2025
13/09/2024
25/10/2024
08/11/2024
28/03/2025
06/12/2024
26/06/2025
27/06/2025
22/09/2025
13/09/2024
06/12/2024
20/12/2024
28/03/2025
28/02/2025
14/02/2025
29/05/2025
19/09/2025
22/09/2025
22/08/2025
13/09/2024
06/12/2024
20/12/2024
14/03/2025
14/03/2025
28/02/2025
14/03/2025
28/03/2025
21/08/2025
22/08/2025
11/07/2025
13/09/2024
08/11/2024
22/11/2024
11/04/2025
14/02/2025
28/03/2025
10/07/2025
11/07/2025
01/12/2025
13/09/2024
17/01/2025
31/01/2025
12/06/2025
11/04/2025
11/04/2025
28/03/2025
11/04/2025
14/03/2025
29/05/2025
28/11/2025
01/12/2025
13/06/2025
13/09/2024
22/11/2024
06/12/2024
31/01/2025
14/03/2025
12/06/2025
13/06/2025
03/03/2025
13/09/2024
11/10/2024
25/10/2024
17/01/2025
20/12/2024
06/12/2024
28/02/2025
03/03/2025
11/07/2025
13/09/2024
22/11/2024
06/12/2024
28/02/2025
28/02/2025
14/02/2025
14/03/2025
10/07/2025
11/07/2025
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
Milestone Appearances
Start Milestone
© Turner & Townsend Project Management. All rights reserved 21/08/2024. This document is expressly provided to and solely for the use of West Dumbartonshire Council and must not be quoted from, referred to,
used by or distributed to any other party without the prior consent of Turner & Townsend Project Management who accept no liability of whatsoever nature for any use by any other party.
Clydebank 3 year plan options
Programme
Notes:
Gantt Chart Ref: C:\Users\youngdav1\OneDrive - Turner & Townsend Group Limited\Desktop\Clydebank LTP\3 Year plan options\Programmes\Clydebank 3 year plan options.pp
Border Ref: C:\Users\youngdav1\OneDrive - Turner & Townsend Group Limited\Desktop\1. T&T MASTER Landscape.B
Programme No:01                             
Revision:   on date: 
Origin Date: 21/08/2024  page 1 of 1
Turner & Townsend Project Management
Clydebank 3 year plan options 
Programme
Originator: David Young
Checked by: David Crombie
Approved by:           
Clydebank 3 year plan options
making the difference  1
Line Name Duration Start Finish
2024 2025
September October November December January February March April May June July August September October NovemberA Dec
2 9 16 23 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
3 year plan options
Town centre trails
Assemble design team
Design period inc
surveys
Client approval
Utility diversions inc
procurement and works
Procurement
Construction inc
mobilisation
Completion
Three Queens Square
Assemble design team
Design period inc
surveys
Client approval
Planning
Landlord approval
Scottish Water approval
for new drainage
Procurement inc
containers
Construction inc
mobilisation
Completion
Canalside Activity
Centre
Assemble design team
Design period inc
surveys
Client approval
Planning
Building Warrant
Landlord approval/ AfL
Scottish Canals approval
Procurement
Construction inc
mobilisation and lift
procurement
Completion
Greenspace Option 1
Assemble design team
Design period inc
surveys
Client approval
Utility diversions inc
procurement and works
Planning
Procurement
Construction inc
mobilisation and lift
procurement
Completion
Greenspace Option 2
Assemble design team
Design period inc
surveys
Client approval
Utility diversions inc
procurement and works
Planning
Building Warrant for
skatepark and MUGA
Landlord approval for
car park alterations (not
inc land sale)
RCC for car park
alterations/ stopping up
Scottish Water approval
for new drainage
Procurement
Construction inc MUGA
and skatepark
procurement
Completion
Connecting
Communities - Queens
Quay, Golden Jubilee
and Wider Communities
Assemble design team
Design period inc
surveys
Client approval
Roads authority
approval for road
painting
Procurement
Construction
Completion
Meanwhile space - Basic
works
Assemble design team
Design period inc
surveys
Client approval
Planning/ advertisement
consent
Landlord approval/ AfL
Procurement
Construction
Completion
Meanwhile space -
Intensite strategy
Assemble design team
Design period inc
surveys
Client approval
Planning/ advertisement
consent
Building Warrant
Landlord approval/ AfL
Procurement
Construction
Completion
62w
40w
2w
6w
2w
20w
4w
12w
52w
2w
12w
2w
12w
8w
8w
20w
16w
48w
2w
12w
2w
12w
12w
8w
12w
12w
20w
42w
2w
8w
2w
20w
12w
16w
12w
62w
2w
16w
2w
20w
12w
12w
8w
12w
8w
16w
24w
38w
2w
10w
2w
8w
12w
12w
24w
2w
4w
2w
12w
8w
6w
6w
42w
2w
10w
2w
12w
12w
8w
12w
16w
02/09/2024
02/09/2024
02/09/2024
16/09/2024
28/10/2024
28/10/2024
11/11/2024
31/03/2025
27/06/2025
02/09/2024
02/09/2024
16/09/2024
09/12/2024
06/01/2025
06/01/2025
09/12/2024
06/01/2025
30/05/2025
22/09/2025
02/09/2024
02/09/2024
16/09/2024
09/12/2024
09/12/2024
09/12/2024
06/01/2025
09/12/2024
06/01/2025
31/03/2025
22/08/2025
02/09/2024
02/09/2024
16/09/2024
11/11/2024
11/11/2024
11/11/2024
25/11/2024
14/04/2025
11/07/2025
02/09/2024
02/09/2024
16/09/2024
20/01/2025
20/01/2025
20/01/2025
20/01/2025
03/02/2025
20/01/2025
20/01/2025
03/02/2025
13/06/2025
01/12/2025
02/09/2024
02/09/2024
16/09/2024
25/11/2024
25/11/2024
09/12/2024
17/03/2025
13/06/2025
02/09/2024
02/09/2024
16/09/2024
14/10/2024
14/10/2024
28/10/2024
28/10/2024
20/01/2025
03/03/2025
02/09/2024
02/09/2024
16/09/2024
25/11/2024
25/11/2024
25/11/2024
09/12/2024
09/12/2024
17/03/2025
11/07/2025
01/12/2025
27/06/2025
13/09/2024
25/10/2024
08/11/2024
28/03/2025
06/12/2024
26/06/2025
27/06/2025
22/09/2025
13/09/2024
06/12/2024
20/12/2024
28/03/2025
28/02/2025
14/02/2025
29/05/2025
19/09/2025
22/09/2025
22/08/2025
13/09/2024
06/12/2024
20/12/2024
14/03/2025
14/03/2025
28/02/2025
14/03/2025
28/03/2025
21/08/2025
22/08/2025
11/07/2025
13/09/2024
08/11/2024
22/11/2024
11/04/2025
14/02/2025
28/03/2025
10/07/2025
11/07/2025
01/12/2025
13/09/2024
17/01/2025
31/01/2025
12/06/2025
11/04/2025
11/04/2025
28/03/2025
11/04/2025
14/03/2025
29/05/2025
28/11/2025
01/12/2025
13/06/2025
13/09/2024
22/11/2024
06/12/2024
31/01/2025
14/03/2025
12/06/2025
13/06/2025
03/03/2025
13/09/2024
11/10/2024
25/10/2024
17/01/2025
20/12/2024
06/12/2024
28/02/2025
03/03/2025
11/07/2025
13/09/2024
22/11/2024
06/12/2024
28/02/2025
28/02/2025
14/02/2025
14/03/2025
10/07/2025
11/07/2025
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
Milestone Appearances
Start Milestone
The costs and programme would
require adjustment if ‘stand alone’
activity centre option progressed.
Revenue funding for ongoing
maintenance and a recurring events
programme to be established in
subsequent development stages.
The programme on page 52
demonstrates that the improvements
to Three Queens Square described in
this report could be developed from
this initial concept and delivered in a
52 - 76 week period.
This is based on the following key stages:
Assemble Design Team:     2 weeks
Design Development (incl. surveys):   12 weeks
Planning, Scottish Water Approval,
Landlord Approval, Procurement (mainly concurrent)  22 weeks
Construction (incl. mobilisation period)   16 - 40 weeks  
(dependent on reinforcement works to 3QS surface)
Client Confidential#
Clydebank LTP Options - Sketch 101 - Three Queens Square Improvement
Item Unit Qty Total
Existing glazed screen to be removed and
structure retained, assumed 4.5m high
m2 153 £22,950
Allow for making good Item 1 £10,000
Allowance for reinforcement of existing
hard landscaping to Three Queens Square
for heavy vehicle usage
Item 1 £500,000
New external paving / surfacing to zone of
Sylvania Way revealed when mall screens
are removed
m2 350 £157,500
Enlargement of existing openings to
market hall
Item 1 £40,000
New Decorative Wall Mural m2 240 £36,000
Formation of small children's play area
(70% of overall area)
m2 623 £109,025
Perimeter fencing to small children's play
area
m 144 £10,800
Gates to small children's play area Nr 2 £2,500
Allowance for play equipment Item 1 £50,000
General downtakings / making good Item 1 £100,000
Allowance for drainage / street lighting
modifications
Item 1 £50,000
£1,088,775
Add
Prelims @ 17.5% £190,536
Contingency @ 15% £191,897
£1,471,207
Design fees @ 20% £294,241
Inflation to assumed project midpoint of 3Q 2025 £58,824
Total £1,824,273
Basis of High Level Costs
1. Costs are high level estimates based on limited information currently available.
2. Threesixty Architecture sketch drawing reference 24013-SK-101 Three Queens    
Square Improvement and email dated 20/09/24.
3. Discussion on scope with Threesixty Architecture.
4. It is assumed the works can be carried out in a single continuous phase.
5. It is assumed for the 'Box Park' services can be connected to the existing market hall development.
5. It is assumed the 'Box Park' facility is 2-storey with ground level F+B terrace.
6. Small children's play area - assumed new surfacing to 70% area and budget for play equipment.
7. Inflation is based on high level programme indicated by TTPM.
Exclusions From High Level Costs
1. Any work in connection with utility services or diversion of same.
2. Any work not stated or implied on drawings.
3. VAT on works or fees.
Client Confidential#
Clydebank LTP Options - Sketch 101 - Three Queens Square Improvement
Item Unit Qty Total
Existing glazed screen to be removed and
structure retained, assumed 4.5m high
m2 153 £22,950
Allow for making good Item 1 £10,000
Enlargement of existing openings to market
hall
Item 1 £40,000
Create new shipping container based retail
/ food 'Box Park' facility over 2 floors
m2 318 £556,500
Formation of F+B terrace (ground level) m2 173 £43,250
Formation of occasional seating zone m2 422 £105,500
Allow perimeter fencing to 'Box Park' /
occasional seating zone
m 113 £8,475
Gates to both entries to service zone Nr 2 £3,500
Formation of small children's play area
(70% of overall area)
m2 623 £109,025
Perimeter fencing to small children's play
area
m 144 £10,800
Gates to small children's play area Nr 2 £2,500
Allowance for play equipment Item 1 £50,000
General downtakings / making good Item 1 £100,000
Allowance for drainage / street lighting
modifications
Item 1 £50,000
£1,112,500
Add
Prelims @ 17.5% £194,688
Contingency @ 15% £196,078
£1,503,266
Design fees @ 20% £300,653
Inflation to assumed project midpoint of 3Q 2025 £60,082
Total £1,864,000
Basis of High Level Costs
1. Costs are high level estimates based on limited information currently available.
2. Threesixty Architecture sketch drawing reference 24013-SK-101 Three Queens    
Square Improvement.
3. Discussion on scope with Threesixty Architecture.
4. It is assumed the works can be carried out in a single continuous phase.
5. It is assumed for the 'Box Park' services can be connected to the existing market hall development.
5. It is assumed the 'Box Park' facility is 2-storey with ground level F+B terrace.
6. Small children's play area - assumed new surfacing to 70% area and budget for play equipment.
7. Inflation is based on high level programme indicated by TTPM.
Exclusions From High Level Costs
1. Any work in connection with utility services or diversion of same.
2. Any work not stated or implied on drawings.
3. VAT on works or fees.
Overlapping uses with multi-generational appeal –
Inclusion
Greater community pride in town centre, greater feeling
of safety and right to inhabit
Expected Outcomes
and Benefits
High Level Cost Estimate (option 1)
Risk
1.   Protracted negotiations or failure to reach agreement     
with landlord for alterations to existing mall façade.
2.    New surface water drainage required for playpark may
result in need to seek Scottish Water approval and      
carry out diversion works.
3.    CCTV and lighting may need augmented to contribute to
safe usage of 3QS.
Mitigation
Engage with landlord at earliest opportunity and highlight
benefits of better access to transformed square.
Undertake utilities survey of location and begin preliminary
dialogue with Scottish water at earliest opportunity.
In later design stages, co-ordinate with Police and WDC on
planned CCTV roll-out and existing lighting and maintence,
identify any shortfall, establish responsibility and adjust
capital and revenue budget accordingly.
Potential Risks

Page 28

5554 Three Year Investment Plan Chosen Interventions
Three Queens Square Transformed
(Option 2)
New Urban Activity Park with
designated small children’s play, sports
area and dog exercise zone  surrounded
by new paths, benches and lighting.
Existing glazed screens
to Sylvania Way mall
removed to provide
access to square
New shopfronts to
commercial units onto
square
Pop-up power bollards
added to square to
facilitate markets and
events
New fixed seating
surrounding
Bandstand and
platform
New large format mural
to enliven existing blank
facade (note: design
shown here is indicative
only)
Potential for
temporary food
trucks to inhabit the
space

Page 29

High Level Cost Estimate (option 2)
5756 Three Year Investment Plan Chosen Interventions
Preliminary Programme, Risk & Approval Considerations
Approval / Utility Considerations
Approval / Utility   Required (Yes / No)
Planning   Y
Warrant   Y
RCC   Y (Public Realm)
Utility Diversion / Supply  N (Assume existing 
mall services can be   
used)
Landlord Approval   Y (Mall facade     
alterations)
Other Approvals   Scottish Water for new 
drainage?
Client Confidential#
Clydebank LTP Options - Sketch 101 - Three Queens Square Improvement
Item Unit Qty Total
Existing glazed screen to be removed and
structure retained, assumed 4.5m high
m2 153 £22,950
Allow for making good Item 1 £10,000
Allowance for reinforcement of existing
hard landscaping to Three Queens Square
for heavy vehicle usage
Item 1 £500,000
New external paving / surfacing to zone of
Sylvania Way revealed when mall screens
are removed
m2 350 £157,500
Enlargement of existing openings to
market hall
Item 1 £40,000
New Decorative Wall Mural m2 240 £36,000
Formation of small children's play area
(70% of overall area)
m2 623 £109,025
Perimeter fencing to small children's play
area
m 144 £10,800
Gates to small children's play area Nr 2 £2,500
Allowance for play equipment Item 1 £50,000
General downtakings / making good Item 1 £100,000
Allowance for drainage / street lighting
modifications
Item 1 £50,000
£1,088,775
Add
Prelims @ 17.5% £190,536
Contingency @ 15% £191,897
£1,471,207
Design fees @ 20% £294,241
Inflation to assumed project midpoint of 3Q 2025 £58,824
Total £1,824,273
Basis of High Level Costs
1. Costs are high level estimates based on limited information currently available.
2. Threesixty Architecture sketch drawing reference 24013-SK-101 Three Queens    
Square Improvement and email dated 20/09/24.
3. Discussion on scope with Threesixty Architecture.
4. It is assumed the works can be carried out in a single continuous phase.
5. It is assumed for the 'Box Park' services can be connected to the existing market hall development.
5. It is assumed the 'Box Park' facility is 2-storey with ground level F+B terrace.
6. Small children's play area - assumed new surfacing to 70% area and budget for play equipment.
7. Inflation is based on high level programme indicated by TTPM.
Exclusions From High Level Costs
1. Any work in connection with utility services or diversion of same.
2. Any work not stated or implied on drawings.
3. VAT on works or fees.
© Turner & Townsend Project Management. All rights reserved 21/08/2024. This document is expressly provided to and solely for the use of West Dumbartonshire Council and must not be quoted from, referred to,
used by or distributed to any other party without the prior consent of Turner & Townsend Project Management who accept no liability of whatsoever nature for any use by any other party.
Clydebank 3 year plan options
Programme
Notes:
Gantt Chart Ref: C:\Users\youngdav1\OneDrive - Turner & Townsend Group Limited\Desktop\Clydebank LTP\3 Year plan options\Programmes\Clydebank 3 year plan options.pp
Border Ref: C:\Users\youngdav1\OneDrive - Turner & Townsend Group Limited\Desktop\1. T&T MASTER Landscape.B
Programme No:01                             
Revision:   on date: 
Origin Date: 21/08/2024  page 1 of 1
Turner & Townsend Project Management
Clydebank 3 year plan options 
Programme
Originator: David Young
Checked by: David Crombie
Approved by:           
Clydebank 3 year plan options
making the difference  1
Line Name Duration Start Finish
2024 2025
September October November December January February March April May June July August September October NovemberA Dec
2 9 16 23 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
3 year plan options
Town centre trails
Assemble design team
Design period inc
surveys
Client approval
Utility diversions inc
procurement and works
Procurement
Construction inc
mobilisation
Completion
Three Queens Square
Assemble design team
Design period inc
surveys
Client approval
Planning
Landlord approval
Scottish Water approval
for new drainage
Procurement inc
containers
Construction inc
mobilisation
Completion
Canalside Activity
Centre
Assemble design team
Design period inc
surveys
Client approval
Planning
Building Warrant
Landlord approval/ AfL
Scottish Canals approval
Procurement
Construction inc
mobilisation and lift
procurement
Completion
Greenspace Option 1
Assemble design team
Design period inc
surveys
Client approval
Utility diversions inc
procurement and works
Planning
Procurement
Construction inc
mobilisation and lift
procurement
Completion
Greenspace Option 2
Assemble design team
Design period inc
surveys
Client approval
Utility diversions inc
procurement and works
Planning
Building Warrant for
skatepark and MUGA
Landlord approval for
car park alterations (not
inc land sale)
RCC for car park
alterations/ stopping up
Scottish Water approval
for new drainage
Procurement
Construction inc MUGA
and skatepark
procurement
Completion
Connecting
Communities - Queens
Quay, Golden Jubilee
and Wider Communities
Assemble design team
Design period inc
surveys
Client approval
Roads authority
approval for road
painting
Procurement
Construction
Completion
Meanwhile space - Basic
works
Assemble design team
Design period inc
surveys
Client approval
Planning/ advertisement
consent
Landlord approval/ AfL
Procurement
Construction
Completion
Meanwhile space -
Intensite strategy
Assemble design team
Design period inc
surveys
Client approval
Planning/ advertisement
consent
Building Warrant
Landlord approval/ AfL
Procurement
Construction
Completion
62w
40w
2w
6w
2w
20w
4w
12w
52w
2w
12w
2w
12w
8w
8w
20w
16w
48w
2w
12w
2w
12w
12w
8w
12w
12w
20w
42w
2w
8w
2w
20w
12w
16w
12w
62w
2w
16w
2w
20w
12w
12w
8w
12w
8w
16w
24w
38w
2w
10w
2w
8w
12w
12w
24w
2w
4w
2w
12w
8w
6w
6w
42w
2w
10w
2w
12w
12w
8w
12w
16w
02/09/2024
02/09/2024
02/09/2024
16/09/2024
28/10/2024
28/10/2024
11/11/2024
31/03/2025
27/06/2025
02/09/2024
02/09/2024
16/09/2024
09/12/2024
06/01/2025
06/01/2025
09/12/2024
06/01/2025
30/05/2025
22/09/2025
02/09/2024
02/09/2024
16/09/2024
09/12/2024
09/12/2024
09/12/2024
06/01/2025
09/12/2024
06/01/2025
31/03/2025
22/08/2025
02/09/2024
02/09/2024
16/09/2024
11/11/2024
11/11/2024
11/11/2024
25/11/2024
14/04/2025
11/07/2025
02/09/2024
02/09/2024
16/09/2024
20/01/2025
20/01/2025
20/01/2025
20/01/2025
03/02/2025
20/01/2025
20/01/2025
03/02/2025
13/06/2025
01/12/2025
02/09/2024
02/09/2024
16/09/2024
25/11/2024
25/11/2024
09/12/2024
17/03/2025
13/06/2025
02/09/2024
02/09/2024
16/09/2024
14/10/2024
14/10/2024
28/10/2024
28/10/2024
20/01/2025
03/03/2025
02/09/2024
02/09/2024
16/09/2024
25/11/2024
25/11/2024
25/11/2024
09/12/2024
09/12/2024
17/03/2025
11/07/2025
01/12/2025
27/06/2025
13/09/2024
25/10/2024
08/11/2024
28/03/2025
06/12/2024
26/06/2025
27/06/2025
22/09/2025
13/09/2024
06/12/2024
20/12/2024
28/03/2025
28/02/2025
14/02/2025
29/05/2025
19/09/2025
22/09/2025
22/08/2025
13/09/2024
06/12/2024
20/12/2024
14/03/2025
14/03/2025
28/02/2025
14/03/2025
28/03/2025
21/08/2025
22/08/2025
11/07/2025
13/09/2024
08/11/2024
22/11/2024
11/04/2025
14/02/2025
28/03/2025
10/07/2025
11/07/2025
01/12/2025
13/09/2024
17/01/2025
31/01/2025
12/06/2025
11/04/2025
11/04/2025
28/03/2025
11/04/2025
14/03/2025
29/05/2025
28/11/2025
01/12/2025
13/06/2025
13/09/2024
22/11/2024
06/12/2024
31/01/2025
14/03/2025
12/06/2025
13/06/2025
03/03/2025
13/09/2024
11/10/2024
25/10/2024
17/01/2025
20/12/2024
06/12/2024
28/02/2025
03/03/2025
11/07/2025
13/09/2024
22/11/2024
06/12/2024
28/02/2025
28/02/2025
14/02/2025
14/03/2025
10/07/2025
11/07/2025
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
Milestone Appearances
Start Milestone
© Turner & Townsend Project Management. All rights reserved 21/08/2024. This document is expressly provided to and solely for the use of West Dumbartonshire Council and must not be quoted from, referred to,
used by or distributed to any other party without the prior consent of Turner & Townsend Project Management who accept no liability of whatsoever nature for any use by any other party.
Clydebank 3 year plan options
Programme
Notes:
Gantt Chart Ref: C:\Users\youngdav1\OneDrive - Turner & Townsend Group Limited\Desktop\Clydebank LTP\3 Year plan options\Programmes\Clydebank 3 year plan options.pp
Border Ref: C:\Users\youngdav1\OneDrive - Turner & Townsend Group Limited\Desktop\1. T&T MASTER Landscape.B
Programme No:01                             
Revision:   on date: 
Origin Date: 21/08/2024  page 1 of 1
Turner & Townsend Project Management
Clydebank 3 year plan options 
Programme
Originator: David Young
Checked by: David Crombie
Approved by:           
Clydebank 3 year plan options
making the difference  1
Line Name Duration Start Finish
2024 2025
September October November December January February March April May June July August September October NovemberA Dec
2 9 16 23 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
3 year plan options
Town centre trails
Assemble design team
Design period inc
surveys
Client approval
Utility diversions inc
procurement and works
Procurement
Construction inc
mobilisation
Completion
Three Queens Square
Assemble design team
Design period inc
surveys
Client approval
Planning
Landlord approval
Scottish Water approval
for new drainage
Procurement inc
containers
Construction inc
mobilisation
Completion
Canalside Activity
Centre
Assemble design team
Design period inc
surveys
Client approval
Planning
Building Warrant
Landlord approval/ AfL
Scottish Canals approval
Procurement
Construction inc
mobilisation and lift
procurement
Completion
Greenspace Option 1
Assemble design team
Design period inc
surveys
Client approval
Utility diversions inc
procurement and works
Planning
Procurement
Construction inc
mobilisation and lift
procurement
Completion
Greenspace Option 2
Assemble design team
Design period inc
surveys
Client approval
Utility diversions inc
procurement and works
Planning
Building Warrant for
skatepark and MUGA
Landlord approval for
car park alterations (not
inc land sale)
RCC for car park
alterations/ stopping up
Scottish Water approval
for new drainage
Procurement
Construction inc MUGA
and skatepark
procurement
Completion
Connecting
Communities - Queens
Quay, Golden Jubilee
and Wider Communities
Assemble design team
Design period inc
surveys
Client approval
Roads authority
approval for road
painting
Procurement
Construction
Completion
Meanwhile space - Basic
works
Assemble design team
Design period inc
surveys
Client approval
Planning/ advertisement
consent
Landlord approval/ AfL
Procurement
Construction
Completion
Meanwhile space -
Intensite strategy
Assemble design team
Design period inc
surveys
Client approval
Planning/ advertisement
consent
Building Warrant
Landlord approval/ AfL
Procurement
Construction
Completion
62w
40w
2w
6w
2w
20w
4w
12w
52w
2w
12w
2w
12w
8w
8w
20w
16w
48w
2w
12w
2w
12w
12w
8w
12w
12w
20w
42w
2w
8w
2w
20w
12w
16w
12w
62w
2w
16w
2w
20w
12w
12w
8w
12w
8w
16w
24w
38w
2w
10w
2w
8w
12w
12w
24w
2w
4w
2w
12w
8w
6w
6w
42w
2w
10w
2w
12w
12w
8w
12w
16w
02/09/2024
02/09/2024
02/09/2024
16/09/2024
28/10/2024
28/10/2024
11/11/2024
31/03/2025
27/06/2025
02/09/2024
02/09/2024
16/09/2024
09/12/2024
06/01/2025
06/01/2025
09/12/2024
06/01/2025
30/05/2025
22/09/2025
02/09/2024
02/09/2024
16/09/2024
09/12/2024
09/12/2024
09/12/2024
06/01/2025
09/12/2024
06/01/2025
31/03/2025
22/08/2025
02/09/2024
02/09/2024
16/09/2024
11/11/2024
11/11/2024
11/11/2024
25/11/2024
14/04/2025
11/07/2025
02/09/2024
02/09/2024
16/09/2024
20/01/2025
20/01/2025
20/01/2025
20/01/2025
03/02/2025
20/01/2025
20/01/2025
03/02/2025
13/06/2025
01/12/2025
02/09/2024
02/09/2024
16/09/2024
25/11/2024
25/11/2024
09/12/2024
17/03/2025
13/06/2025
02/09/2024
02/09/2024
16/09/2024
14/10/2024
14/10/2024
28/10/2024
28/10/2024
20/01/2025
03/03/2025
02/09/2024
02/09/2024
16/09/2024
25/11/2024
25/11/2024
25/11/2024
09/12/2024
09/12/2024
17/03/2025
11/07/2025
01/12/2025
27/06/2025
13/09/2024
25/10/2024
08/11/2024
28/03/2025
06/12/2024
26/06/2025
27/06/2025
22/09/2025
13/09/2024
06/12/2024
20/12/2024
28/03/2025
28/02/2025
14/02/2025
29/05/2025
19/09/2025
22/09/2025
22/08/2025
13/09/2024
06/12/2024
20/12/2024
14/03/2025
14/03/2025
28/02/2025
14/03/2025
28/03/2025
21/08/2025
22/08/2025
11/07/2025
13/09/2024
08/11/2024
22/11/2024
11/04/2025
14/02/2025
28/03/2025
10/07/2025
11/07/2025
01/12/2025
13/09/2024
17/01/2025
31/01/2025
12/06/2025
11/04/2025
11/04/2025
28/03/2025
11/04/2025
14/03/2025
29/05/2025
28/11/2025
01/12/2025
13/06/2025
13/09/2024
22/11/2024
06/12/2024
31/01/2025
14/03/2025
12/06/2025
13/06/2025
03/03/2025
13/09/2024
11/10/2024
25/10/2024
17/01/2025
20/12/2024
06/12/2024
28/02/2025
03/03/2025
11/07/2025
13/09/2024
22/11/2024
06/12/2024
28/02/2025
28/02/2025
14/02/2025
14/03/2025
10/07/2025
11/07/2025
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
Milestone Appearances
Start Milestone
The costs and programme would
require adjustment if ‘stand alone’
activity centre option progressed.
Revenue funding for ongoing
maintenance and a recurring events
programme to be established in
subsequent development stages.
The programme on page 56
demonstrates that the improvements
to Three Queens Square described in
this report could be developed from
this initial concept and delivered in a
52 - 76 week period.
This is based on the following key stages:
Assemble Design Team:     2 weeks
Design Development (incl. surveys):   12 weeks
Planning, Scottish Water Approval,
Landlord Approval, Procurement (mainly concurrent)  22 weeks
Construction (incl. mobilisation period)   16 - 40 weeks  
(dependent on reinforcement works to 3QS surface)
Client Confidential#
Clydebank LTP Options - Sketch 101 - Three Queens Square Improvement
Item Unit Qty Total
Existing glazed screen to be removed and
structure retained, assumed 4.5m high
m2 153 £22,950
Allow for making good Item 1 £10,000
Allowance for reinforcement of existing
hard landscaping to Three Queens Square
for heavy vehicle usage
Item 1 £500,000
New external paving / surfacing to zone of
Sylvania Way revealed when mall screens
are removed
m2 350 £157,500
Enlargement of existing openings to
market hall
Item 1 £40,000
New Decorative Wall Mural m2 240 £36,000
Formation of small children's play area
(70% of overall area)
m2 623 £109,025
Perimeter fencing to small children's play
area
m 144 £10,800
Gates to small children's play area Nr 2 £2,500
Allowance for play equipment Item 1 £50,000
General downtakings / making good Item 1 £100,000
Allowance for drainage / street lighting
modifications
Item 1 £50,000
£1,088,775
Add
Prelims @ 17.5% £190,536
Contingency @ 15% £191,897
£1,471,207
Design fees @ 20% £294,241
Inflation to assumed project midpoint of 3Q 2025 £58,824
Total £1,824,273
Basis of High Level Costs
1. Costs are high level estimates based on limited information currently available.
2. Threesixty Architecture sketch drawing reference 24013-SK-101 Three Queens    
Square Improvement and email dated 20/09/24.
3. Discussion on scope with Threesixty Architecture.
4. It is assumed the works can be carried out in a single continuous phase.
5. It is assumed for the 'Box Park' services can be connected to the existing market hall development.
5. It is assumed the 'Box Park' facility is 2-storey with ground level F+B terrace.
6. Small children's play area - assumed new surfacing to 70% area and budget for play equipment.
7. Inflation is based on high level programme indicated by TTPM.
Exclusions From High Level Costs
1. Any work in connection with utility services or diversion of same.
2. Any work not stated or implied on drawings.
3. VAT on works or fees.
Client Confidential#
Clydebank LTP Options - Sketch 101 - Three Queens Square Improvement
Item Unit Qty Total
Existing glazed screen to be removed and
structure retained, assumed 4.5m high
m2 153 £22,950
Allow for making good Item 1 £10,000
Enlargement of existing openings to market
hall
Item 1 £40,000
Create new shipping container based retail
/ food 'Box Park' facility over 2 floors
m2 318 £556,500
Formation of F+B terrace (ground level) m2 173 £43,250
Formation of occasional seating zone m2 422 £105,500
Allow perimeter fencing to 'Box Park' /
occasional seating zone
m 113 £8,475
Gates to both entries to service zone Nr 2 £3,500
Formation of small children's play area
(70% of overall area)
m2 623 £109,025
Perimeter fencing to small children's play
area
m 144 £10,800
Gates to small children's play area Nr 2 £2,500
Allowance for play equipment Item 1 £50,000
General downtakings / making good Item 1 £100,000
Allowance for drainage / street lighting
modifications
Item 1 £50,000
£1,112,500
Add
Prelims @ 17.5% £194,688
Contingency @ 15% £196,078
£1,503,266
Design fees @ 20% £300,653
Inflation to assumed project midpoint of 3Q 2025 £60,082
Total £1,864,000
Basis of High Level Costs
1. Costs are high level estimates based on limited information currently available.
2. Threesixty Architecture sketch drawing reference 24013-SK-101 Three Queens    
Square Improvement.
3. Discussion on scope with Threesixty Architecture.
4. It is assumed the works can be carried out in a single continuous phase.
5. It is assumed for the 'Box Park' services can be connected to the existing market hall development.
5. It is assumed the 'Box Park' facility is 2-storey with ground level F+B terrace.
6. Small children's play area - assumed new surfacing to 70% area and budget for play equipment.
7. Inflation is based on high level programme indicated by TTPM.
Exclusions From High Level Costs
1. Any work in connection with utility services or diversion of same.
2. Any work not stated or implied on drawings.
3. VAT on works or fees.
Overlapping uses with multi-generational appeal –
Inclusion
Greater community pride in town centre, greater feeling
of safety and right to inhabit
Expected Outcomes
and Benefits
Risk
1.   Protracted negotiations or failure to reach agreement     
with landlord for alterations to existing mall façade.
2.    New surface water drainage required for playpark may
result in need to seek Scottish Water approval and      
carry out diversion works.
3.    CCTV and lighting may need augmented to contribute to
safe usage of 3QS.
Mitigation
Engage with landlord at earliest opportunity and highlight
benefits of better access to transformed square.
Undertake utilities survey of location and begin preliminary
dialogue with Scottish water at earliest opportunity.
In later design stages, co-ordinate with Police and WDC on
planned CCTV roll-out and existing lighting and maintence,
identify any shortfall, establish responsibility and adjust
capital and revenue budget accordingly.
Potential Risks

Page 30

5958 Three Year Investment Plan Chosen Interventions
Priority Intervention 2b:
Canalside Activity Centre
HIGH ST R EETS, HERITAGE & REGENERATIO
N
A new Canalside Activity
Centre was proposed by West
Dunbartonshire Council and £1.3
million funding was secured mainly
from the Scottish Government’s
Regeneration Capital Grant Fund.
This is envisaged as a new build
pavilion on the southern bank of
the Canal, adjacent to Sylvania
way (illustrated as option 1 in this
document).
The Long Term plan also explores
an alternative option (option 2), a
commensurate facility in a repurposed
prominent vacant retail unit that faces
directly onto the canal within the Clyde
Shopping Centre.
Compliance with UK Government
Guidance
The creation of a series of new
canalside activity centre is ‘on menu’,
as outlined by criteria H1:
‘Funding for place-based
regeneration and town centre and
high street improvements.’
H7:
‘Funding for impactful volunteering
and social action projects.’
and H8:
‘Funding for local sports facilities,
tournaments, teams and leagues.’
Community Feedback:
‘Activate the Canalside
for All’
Community Feedback:
‘Diversionary Activities
for Young People’
Community Feedback:
‘Funding for Sports
Facilities and Bringing
People Together’

Page 31

6160 Three Year Investment Plan Chosen Interventions
The layout (shown below) has been
developed to support a wide range
of activities.
A bike workshop stands alone as a
single element to the east of the site
addressing both Queen Square and
the canal and will provide bicycle
repairs and workshops for youth and
community groups and local cyclists.
The community space sited within
the main linear form will be used by
community and youth groups for
a whole manner of recreation and
educational activities including Yoga
classes and Cooking classes.
The centre also incorporates a
covered exterior space allowing
activities to be conducted undercover
outdoors.
The activity centre has previously
been allocated Scottish Government
funding towards the capital cost.
Revenue funding for operational costs
will require to be established in next
stages and allowed for.
Impact on Urban Activity Park
proposals
The sketch above shows the
proposed stand alone activity centre
building in its wider context and
its impact on the proposed Urban
Activity Park, reducing this to two
small ‘islands’ to the left of the building
(refer to pages 48-51 for more details).
Drawings & Images of proposed
Activity Centre (JM Architects)
Proposed Activity Centre
building on south bank of
canal
Reduced area of
external childrens play
alongside new activity
centre
Option 1:
A New Stand-Alone Activity Centre

Page 32

High Level Cost Estimate (option 1)
Risk
1.   Tenant / Operator vacates the premises leaving WDC
liable for ongoing maintenance / security costs and
requirement to find alternative operator or use.
2.    New activity centre is unsustainable due to difficulties     
in generating sufficient ongoing revenue.
3.   Potential overlap / displacement of activities from other
local facilities e.g. Clydebank Housing Associations’
Centre 81 in the Whitecrook area.
Mitigation
Manage risk of vacancy / surrender through leasing
arrangement with tenants to mitigate liabilities. Consider
opportunities for future reduction of space / subdivision to
ensure flexibility.
Allow for element of revenue funding and develop a detailed
business case involving all potential stakeholder groups.
In subsequent stages, progress programme of uses /
activities in collaboration with existing providers outside the
town centre to identify complementary uses and uses that
reinforce wider activity by being visible in and accessible
from the heart of the town centre.
6362 Three Year Investment Plan Chosen Interventions
Preliminary Programme, Risk
and Approval Considerations
Potential Risks
Approval / Utility   Required (Yes / No)
Planning   Granted
Warrant   Y
RCC   N
Utility Diversion / Supply  N
Landlord Approval   N
The stand alone Canalside Activity
Centre described in this report could
be developed from its current status
of having achieved planning consent
and delivered in a 36 week period.
This is based on the following key
stages:
Design Development beyond Planning:   9 weeks
Construction (incl. mobilisation period)   27 weeks
Promotes Activity – Health and Well Being
Increased activity / vibrancy in heart of town – Greater
Safety
Diversionary and positive activity for young people in
particular
Expected Outcomes
and Benefits
Approval / Utility Considerations
The Cost Plan below and programme
information has been provided by
West Dunbartonshire Council.
The design of the building has
been developed by another design
team on behalf of WDC and the
programme information on the next
page demonstrates the time required
to progress the delivery of the centre
from its current position of having
achieved Detailed Planning Consent.

Page 33

6564 Three Year Investment Plan Chosen Interventions
Potential New Canalside Activity Centre,
Unit 1, Clyde Shopping Centre
New windows to
upper floor community
meeting / activity
rooms
New Roller
Shutter Opening
for equipment
access
New signage
to facade
New entrance
doors adjacent to
retained shopfront
New timber
decked area and
seating platforms
New decorative
paint finish to
facade
Option 2:
Activity Centre in a repurposed retail unit
This alternative option locates
the new activity centre within
a prominent unit of the Clyde
Shopping Centre that, at the time
of writing, lies vacant.
The proposals create a series of
flexible spaces for the community with
direct access from the canalside via a
new public entrance. The inclusion of
new toilet facilities, a new kitchen and
passenger lift serving the first floor will
make the centre fully accessible.
The adjacent visual demonstrates
a number of the key moves that
will transform the vacant unit into a
vibrant community hub, including the
introduction of windows to the upper
floor and the potential for a large scale
decorative mural / graphic to the
facade facing the canal.
A new decked area complete with
seating and steps leading down to the
canal are also proposed to make the
most of this canalside location.
The benefit of this location is the
increased size provides the ability
to introduce more flexible spaces
for community groups to use and to
expand the ‘active’ offer to include
watersports in the future. It could
also be where the potential MUGA
and Skate Park included in the
larger option for the new adjacent
greenspace could be managed from.
Proposed activities include guided
bike rides & skills training, bike repair/
maintenance training and bike hire,
mainly targeted at the local young
people and families who may lack
opportunities to try and participate in
outdoor sports.
It will also work with the local schools
and other community groups, such
as Community Links Scotland, who
are keen to use the new facility to host
a number of their classes and clubs,
a drop in energy advice clinic and to
host both exhibitions and community
consultation events.
The repurposing of a vacant retail
space is in lock-step with current
Scottish Government Policy,
particularly NPF4, which places a
greater emphasis on the reuse of
brownfield, vacant and derelict land
and empty buildings. It states:
‘Proposals for the reuse of existing
buildings, including listed buildings
and other historic assets, will be
supported - taking into account their
suitability for conversion to other uses.’
Unit 1, Clyde Shopping Centre with a
prominent canalside setting

Page 34

Risk
1.   Agreement for lease cannot be agreed or results in
protracted negotiations in regards to plans to redevelop
unit. Rent and service charge costs prove prohibitive.
2.   External space results in the need to engage with
and seek approval from Scottish Canals to develop,
potentially limiting future expansion of activities.
3.    New activity centre is unsustainable due to difficulties     
in generating sufficient ongoing revenue.
4.   Complications with building warrant due to upper floor
fire strategy/ escape strategy.
5.   Potential overlap / displacement of activities from other
local facilities e.g. Clydebank Housing Associations’
Centre 81 in the Whitecrook area.
Mitigation
Begin negotiations with landlord at earliest opportunity to
demonstrate positive footfall benefits for remainder of their
asset that the Activity Centre would bring. Seek standard
landlord’s contribution to fit-out / rent free period to reduce
rental burden.
Initiate discussions with Scottish Canals at earliest
opportunity and demonstrate positive benefits of proposals
for the town and the canalside.
Allow for element of revenue funding and develop a detailed
business case involving all potential stakeholder groups.
Design team to develop proposals in compliance with
current regulations or highlight where ‘views’ or a fire
engineering solution may be required.
In subsequent stages, progress programme of uses /
activities in collaboration with existing providers outside the
town centre to identify complementary uses and uses that
reinforce wider activity by being visible in and accessible
from the heart of the town centre.
6766 Three Year Investment Plan Chosen Interventions
Preliminary Programme, Risk
and Approval Considerations
Potential Risks
Approval / Utility   Required (Yes / No)
Planning   Y
Warrant   Y
RCC   N
Utility Diversion / Supply  N
Landlord Approval   Y (Unit Lease)
Other Approvals   Scottish Canals for 
external decking
Client Confidential#
Clydebank LTP Options - Sketch 102 - Canalside Activity Centre
Item Unit Qty Total
Allowance for general downtakings /
site preparation
Item 1 £20,000
New external door, quayside elevation Nr 1 £2,500
New roller shutter, quayside elevation Nr 1 £2,000
New windows generally Nr 4 £15,000
Minor modifications to existing stair Item 1 £2,000
New lift between ground and upper floor Nr 1 £70,000
Basic fit-out of activity centre and
upper floor space
m2 421 £294,700
New room divider, 9500mm long Nr 1 £20,000
Deck area extended from footpath m2 126 £25,200
£451,400
Add
Prelims @ 17.5% £78,995
Contingency @ 15% £79,559
£609,954
Design fees @ 20% £121,991
Inflation to assumed project midpoint of 3Q 2025 £24,355
Total £756,300
Basis of High Level Costs
1. Costs are high level estimates based on limited information currently available.
2. Threesixty Architecture sketch drawing reference 24013-SK-102 Canalside Activity Centre
3. Discussion on scope with Threesixty Architecture.
4. It is assumed the works can be carried out in a single continuous phase.
5. It is assumed the existing building shell is capable of refurbishment without significant    
structural changes.
6. Inflation is based on high level programme indicated by TTPM.
Exclusions From High Level Costs
1. External drainage, external works / external services.
2. Any work in connection with utility services or diversion of same.
3. Any work not stated or implied on drawings.
4. VAT on works or fees.
© Turner & Townsend Project Management. All rights reserved 21/08/2024. This document is expressly provided to and solely for the use of West Dumbartonshire Council and must not be quoted from, referred to,
used by or distributed to any other party without the prior consent of Turner & Townsend Project Management who accept no liability of whatsoever nature for any use by any other party.
Clydebank 3 year plan options
Programme
Notes:
Gantt Chart Ref: C:\Users\youngdav1\OneDrive - Turner & Townsend Group Limited\Desktop\Clydebank LTP\3 Year plan options\Programmes\Clydebank 3 year plan options.pp
Border Ref: C:\Users\youngdav1\OneDrive - Turner & Townsend Group Limited\Desktop\1. T&T MASTER Landscape.B
Programme No:01                             
Revision:   on date: 
Origin Date: 21/08/2024  page 1 of 1
Turner & Townsend Project Management
Clydebank 3 year plan options 
Programme
Originator: David Young
Checked by: David Crombie
Approved by:           
Clydebank 3 year plan options
making the difference  1
Line Name Duration Start Finish
2024 2025
September October November December January February March April May June July August September October NovemberA Dec
2 9 16 23 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
3 year plan options
Town centre trails
Assemble design team
Design period inc
surveys
Client approval
Utility diversions inc
procurement and works
Procurement
Construction inc
mobilisation
Completion
Three Queens Square
Assemble design team
Design period inc
surveys
Client approval
Planning
Landlord approval
Scottish Water approval
for new drainage
Procurement inc
containers
Construction inc
mobilisation
Completion
Canalside Activity
Centre
Assemble design team
Design period inc
surveys
Client approval
Planning
Building Warrant
Landlord approval/ AfL
Scottish Canals approval
Procurement
Construction inc
mobilisation and lift
procurement
Completion
Greenspace Option 1
Assemble design team
Design period inc
surveys
Client approval
Utility diversions inc
procurement and works
Planning
Procurement
Construction inc
mobilisation and lift
procurement
Completion
Greenspace Option 2
Assemble design team
Design period inc
surveys
Client approval
Utility diversions inc
procurement and works
Planning
Building Warrant for
skatepark and MUGA
Landlord approval for
car park alterations (not
inc land sale)
RCC for car park
alterations/ stopping up
Scottish Water approval
for new drainage
Procurement
Construction inc MUGA
and skatepark
procurement
Completion
Connecting
Communities - Queens
Quay, Golden Jubilee
and Wider Communities
Assemble design team
Design period inc
surveys
Client approval
Roads authority
approval for road
painting
Procurement
Construction
Completion
Meanwhile space - Basic
works
Assemble design team
Design period inc
surveys
Client approval
Planning/ advertisement
consent
Landlord approval/ AfL
Procurement
Construction
Completion
Meanwhile space -
Intensite strategy
Assemble design team
Design period inc
surveys
Client approval
Planning/ advertisement
consent
Building Warrant
Landlord approval/ AfL
Procurement
Construction
Completion
62w
40w
2w
6w
2w
20w
4w
12w
52w
2w
12w
2w
12w
8w
8w
20w
16w
48w
2w
12w
2w
12w
12w
8w
12w
12w
20w
42w
2w
8w
2w
20w
12w
16w
12w
62w
2w
16w
2w
20w
12w
12w
8w
12w
8w
16w
24w
38w
2w
10w
2w
8w
12w
12w
24w
2w
4w
2w
12w
8w
6w
6w
42w
2w
10w
2w
12w
12w
8w
12w
16w
02/09/2024
02/09/2024
02/09/2024
16/09/2024
28/10/2024
28/10/2024
11/11/2024
31/03/2025
27/06/2025
02/09/2024
02/09/2024
16/09/2024
09/12/2024
06/01/2025
06/01/2025
09/12/2024
06/01/2025
30/05/2025
22/09/2025
02/09/2024
02/09/2024
16/09/2024
09/12/2024
09/12/2024
09/12/2024
06/01/2025
09/12/2024
06/01/2025
31/03/2025
22/08/2025
02/09/2024
02/09/2024
16/09/2024
11/11/2024
11/11/2024
11/11/2024
25/11/2024
14/04/2025
11/07/2025
02/09/2024
02/09/2024
16/09/2024
20/01/2025
20/01/2025
20/01/2025
20/01/2025
03/02/2025
20/01/2025
20/01/2025
03/02/2025
13/06/2025
01/12/2025
02/09/2024
02/09/2024
16/09/2024
25/11/2024
25/11/2024
09/12/2024
17/03/2025
13/06/2025
02/09/2024
02/09/2024
16/09/2024
14/10/2024
14/10/2024
28/10/2024
28/10/2024
20/01/2025
03/03/2025
02/09/2024
02/09/2024
16/09/2024
25/11/2024
25/11/2024
25/11/2024
09/12/2024
09/12/2024
17/03/2025
11/07/2025
01/12/2025
27/06/2025
13/09/2024
25/10/2024
08/11/2024
28/03/2025
06/12/2024
26/06/2025
27/06/2025
22/09/2025
13/09/2024
06/12/2024
20/12/2024
28/03/2025
28/02/2025
14/02/2025
29/05/2025
19/09/2025
22/09/2025
22/08/2025
13/09/2024
06/12/2024
20/12/2024
14/03/2025
14/03/2025
28/02/2025
14/03/2025
28/03/2025
21/08/2025
22/08/2025
11/07/2025
13/09/2024
08/11/2024
22/11/2024
11/04/2025
14/02/2025
28/03/2025
10/07/2025
11/07/2025
01/12/2025
13/09/2024
17/01/2025
31/01/2025
12/06/2025
11/04/2025
11/04/2025
28/03/2025
11/04/2025
14/03/2025
29/05/2025
28/11/2025
01/12/2025
13/06/2025
13/09/2024
22/11/2024
06/12/2024
31/01/2025
14/03/2025
12/06/2025
13/06/2025
03/03/2025
13/09/2024
11/10/2024
25/10/2024
17/01/2025
20/12/2024
06/12/2024
28/02/2025
03/03/2025
11/07/2025
13/09/2024
22/11/2024
06/12/2024
28/02/2025
28/02/2025
14/02/2025
14/03/2025
10/07/2025
11/07/2025
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
Milestone Appearances
Start Milestone
© Turner & Townsend Project Management. All rights reserved 21/08/2024. This document is expressly provided to and solely for the use of West Dumbartonshire Council and must not be quoted from, referred to,
used by or distributed to any other party without the prior consent of Turner & Townsend Project Management who accept no liability of whatsoever nature for any use by any other party.
Clydebank 3 year plan options
Programme
Notes:
Gantt Chart Ref: C:\Users\youngdav1\OneDrive - Turner & Townsend Group Limited\Desktop\Clydebank LTP\3 Year plan options\Programmes\Clydebank 3 year plan options.pp
Border Ref: C:\Users\youngdav1\OneDrive - Turner & Townsend Group Limited\Desktop\1. T&T MASTER Landscape.B
Programme No:01                             
Revision:   on date: 
Origin Date: 21/08/2024  page 1 of 1
Turner & Townsend Project Management
Clydebank 3 year plan options 
Programme
Originator: David Young
Checked by: David Crombie
Approved by:           
Clydebank 3 year plan options
making the difference  1
Line Name Duration Start Finish
2024 2025
September October November December January February March April May June July August September October NovemberA Dec
2 9 16 23 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
3 year plan options
Town centre trails
Assemble design team
Design period inc
surveys
Client approval
Utility diversions inc
procurement and works
Procurement
Construction inc
mobilisation
Completion
Three Queens Square
Assemble design team
Design period inc
surveys
Client approval
Planning
Landlord approval
Scottish Water approval
for new drainage
Procurement inc
containers
Construction inc
mobilisation
Completion
Canalside Activity
Centre
Assemble design team
Design period inc
surveys
Client approval
Planning
Building Warrant
Landlord approval/ AfL
Scottish Canals approval
Procurement
Construction inc
mobilisation and lift
procurement
Completion
Greenspace Option 1
Assemble design team
Design period inc
surveys
Client approval
Utility diversions inc
procurement and works
Planning
Procurement
Construction inc
mobilisation and lift
procurement
Completion
Greenspace Option 2
Assemble design team
Design period inc
surveys
Client approval
Utility diversions inc
procurement and works
Planning
Building Warrant for
skatepark and MUGA
Landlord approval for
car park alterations (not
inc land sale)
RCC for car park
alterations/ stopping up
Scottish Water approval
for new drainage
Procurement
Construction inc MUGA
and skatepark
procurement
Completion
Connecting
Communities - Queens
Quay, Golden Jubilee
and Wider Communities
Assemble design team
Design period inc
surveys
Client approval
Roads authority
approval for road
painting
Procurement
Construction
Completion
Meanwhile space - Basic
works
Assemble design team
Design period inc
surveys
Client approval
Planning/ advertisement
consent
Landlord approval/ AfL
Procurement
Construction
Completion
Meanwhile space -
Intensite strategy
Assemble design team
Design period inc
surveys
Client approval
Planning/ advertisement
consent
Building Warrant
Landlord approval/ AfL
Procurement
Construction
Completion
62w
40w
2w
6w
2w
20w
4w
12w
52w
2w
12w
2w
12w
8w
8w
20w
16w
48w
2w
12w
2w
12w
12w
8w
12w
12w
20w
42w
2w
8w
2w
20w
12w
16w
12w
62w
2w
16w
2w
20w
12w
12w
8w
12w
8w
16w
24w
38w
2w
10w
2w
8w
12w
12w
24w
2w
4w
2w
12w
8w
6w
6w
42w
2w
10w
2w
12w
12w
8w
12w
16w
02/09/2024
02/09/2024
02/09/2024
16/09/2024
28/10/2024
28/10/2024
11/11/2024
31/03/2025
27/06/2025
02/09/2024
02/09/2024
16/09/2024
09/12/2024
06/01/2025
06/01/2025
09/12/2024
06/01/2025
30/05/2025
22/09/2025
02/09/2024
02/09/2024
16/09/2024
09/12/2024
09/12/2024
09/12/2024
06/01/2025
09/12/2024
06/01/2025
31/03/2025
22/08/2025
02/09/2024
02/09/2024
16/09/2024
11/11/2024
11/11/2024
11/11/2024
25/11/2024
14/04/2025
11/07/2025
02/09/2024
02/09/2024
16/09/2024
20/01/2025
20/01/2025
20/01/2025
20/01/2025
03/02/2025
20/01/2025
20/01/2025
03/02/2025
13/06/2025
01/12/2025
02/09/2024
02/09/2024
16/09/2024
25/11/2024
25/11/2024
09/12/2024
17/03/2025
13/06/2025
02/09/2024
02/09/2024
16/09/2024
14/10/2024
14/10/2024
28/10/2024
28/10/2024
20/01/2025
03/03/2025
02/09/2024
02/09/2024
16/09/2024
25/11/2024
25/11/2024
25/11/2024
09/12/2024
09/12/2024
17/03/2025
11/07/2025
01/12/2025
27/06/2025
13/09/2024
25/10/2024
08/11/2024
28/03/2025
06/12/2024
26/06/2025
27/06/2025
22/09/2025
13/09/2024
06/12/2024
20/12/2024
28/03/2025
28/02/2025
14/02/2025
29/05/2025
19/09/2025
22/09/2025
22/08/2025
13/09/2024
06/12/2024
20/12/2024
14/03/2025
14/03/2025
28/02/2025
14/03/2025
28/03/2025
21/08/2025
22/08/2025
11/07/2025
13/09/2024
08/11/2024
22/11/2024
11/04/2025
14/02/2025
28/03/2025
10/07/2025
11/07/2025
01/12/2025
13/09/2024
17/01/2025
31/01/2025
12/06/2025
11/04/2025
11/04/2025
28/03/2025
11/04/2025
14/03/2025
29/05/2025
28/11/2025
01/12/2025
13/06/2025
13/09/2024
22/11/2024
06/12/2024
31/01/2025
14/03/2025
12/06/2025
13/06/2025
03/03/2025
13/09/2024
11/10/2024
25/10/2024
17/01/2025
20/12/2024
06/12/2024
28/02/2025
03/03/2025
11/07/2025
13/09/2024
22/11/2024
06/12/2024
28/02/2025
28/02/2025
14/02/2025
14/03/2025
10/07/2025
11/07/2025
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
Milestone Appearances
Start Milestone
The programme on page 66
demonstrates that the Canalside
Activity Centre described in this report
could be developed from this initial
concept and delivered in a 48 week
period.
This is based on the following key
stages:
Assemble Design Team:     2 weeks
Design Development (incl. surveys):   12 weeks
Planning, Scottish Water Approval,
Landlord Approval, Procurement (mainly concurrent)  14 weeks
Construction (incl. mobilisation period)   20 weeks
Client Confidential#
Clydebank LTP Options - Sketch 102 - Canalside Activity Centre
Item Unit Qty Total
Allowance for general downtakings /
site preparation
Item 1 £20,000
New external door, quayside elevation Nr 1 £2,500
New roller shutter, quayside elevation Nr 1 £2,000
New windows generally Nr 4 £15,000
Minor modifications to existing stair Item 1 £2,000
New lift between ground and upper floor Nr 1 £70,000
Basic fit-out of activity centre and
upper floor space
m2 421 £294,700
New room divider, 9500mm long Nr 1 £20,000
Deck area extended from footpath m2 126 £25,200
£451,400
Add
Prelims @ 17.5% £78,995
Contingency @ 15% £79,559
£609,954
Design fees @ 20% £121,991
Inflation to assumed project midpoint of 3Q 2025 £24,355
Total £756,300
Basis of High Level Costs
1. Costs are high level estimates based on limited information currently available.
2. Threesixty Architecture sketch drawing reference 24013-SK-102 Canalside Activity Centre
3. Discussion on scope with Threesixty Architecture.
4. It is assumed the works can be carried out in a single continuous phase.
5. It is assumed the existing building shell is capable of refurbishment without significant    
structural changes.
6. Inflation is based on high level programme indicated by TTPM.
Exclusions From High Level Costs
1. External drainage, external works / external services.
2. Any work in connection with utility services or diversion of same.
3. Any work not stated or implied on drawings.
4. VAT on works or fees.
Client Confidential#
Clydebank LTP Options - Sketch 102 - Canalside Activity Centre
Item Unit Qty Total
Allowance for general downtakings /
site preparation
Item 1 £20,000
New external door, quayside elevation Nr 1 £2,500
New roller shutter, quayside elevation Nr 1 £2,000
New windows generally Nr 4 £15,000
Minor modifications to existing stair Item 1 £2,000
New lift between ground and upper floor Nr 1 £70,000
Basic fit-out of activity centre and
upper floor space
m2 421 £294,700
New room divider, 9500mm long Nr 1 £20,000
Deck area extended from footpath m2 126 £25,200
£451,400
Add
Prelims @ 17.5% £78,995
Contingency @ 15% £79,559
£609,954
Design fees @ 20% £121,991
Inflation to assumed project midpoint of 3Q 2025 £24,355
Total £756,300
Basis of High Level Costs
1. Costs are high level estimates based on limited information currently available.
2. Threesixty Architecture sketch drawing reference 24013-SK-102 Canalside Activity Centre
3. Discussion on scope with Threesixty Architecture.
4. It is assumed the works can be carried out in a single continuous phase.
5. It is assumed the existing building shell is capable of refurbishment without significant    
structural changes.
6. Inflation is based on high level programme indicated by TTPM.
Exclusions From High Level Costs
1. External drainage, external works / external services.
2. Any work in connection with utility services or diversion of same.
3. Any work not stated or implied on drawings.
4. VAT on works or fees.
Promotes Activity – Health and Well Being
Increased activity / vibrancy in heart of town – Greater
Safety
Diversionary and positive activity for young people in
particular
Expected Outcomes
and Benefits
Approval / Utility Considerations
High Level Cost Estimate (option 2)

Page 35

The greening of Clydebank town
centre and the promotion of
greater biodiversity was a key aim
of the recently published Vision
and the provision of a new ctown
centre greenspace was one of the
most popular responses received
from the community through the 
engagement process.
The proposals introduce a new
greenspace at the heart of the town
centre for the benefit of the entire
community regardless of age or ability.
Compliance with UK Government
Guidance
The creation of a new all ages
Greenspace is ‘on menu’, as outlined
by criteria H3:
‘Creation of, and improvement to,
local green spaces, community
gardens, watercourses and
embankments.’
6968 Three Year Investment Plan Chosen Interventions
There is a lack of greenspace
generally within the town
centre.
The largest greenspaces are
outwith the town centre area
and so the potential to introduce
some new greenspace that
could incorporate seating and
play areas would be a welcome
addition.
Context:
Lack of Town Centre Greenspace
Active Greenspace
(Sport etc)
Park / Greenspace
Allotments
Priority Intervention 3: A New
Town Centre Greenspace
HIGH ST R EETS, HERITAGE & REGENERATIO
N
Pound’s Park,
Sheffield
Pound’s Park, a new urban
greenspace at the heart of Sheffield
city centre is accessible, inclusive
and multi-generational, including
spaces for play, relaxation and
socialising.
With families in mind, Pound’s Park
features a three-by-eight-metre
climbing boulder, reminiscent of a
Peak District rockface, a significant
new children’s playground and a
number of water play features.
Seating and new accessible public
toilets are located within the park
and extensive evening lighting and
CCTV ensures it remains a safe
environment that can be enjoyed into
the evening.
“The Council is investing in truly
unique and high-quality public
spaces across the city centre,
bringing ‘The Outdoor City’ ethos
right into the heart of Sheffield.
Creating these spaces is not only
about giving people free and
attractive places to enjoy and relax
in, it helps reduce vehicle congestion
and emissions in the city centre,
as well as creating an attractive
environment that will see us attract
new residents, businesses and
retail and leisure brands into the
city centre – driving more footfall
and helping the city centre thrive for
decades to come.”
Councillor Mazher Iqbal, Co-Chair Transport,
Regeneration and Climate Policy Committee
Community Feedback:
‘Activate the Canalside
for All’
Community Feedback:
‘New Greenspace at the
Canal’
Community Feedback:
‘New Parks / Green
Spaces’

Page 36

7170 Three Year Investment Plan Chosen Interventions
The chosen space is located
on the north bank of the canal,
directly adjacent to the Clyde
Shopping Centre. The selection of
this location also responds to the
engagement feedback where the
community called for proposals
that ‘activate the canalside for all’.
Conceived as a multi-functional
greenspace, it provides water
management, biodiversity, access and
recreation, benefitting both the local
population and visitors.
It is envisaged that it would incorporate
new areas of seating and shelter,
a sensory garden and raised
community planters. The opportunity
to expand the space into a section
of the adjacent car park would
effectively double its size and allow
the incorporation of more facilities
including a MUGA pitch and small
skate park. For the purposes of high
level costing / programme etc. the 
basic proposals have been referred
to as Option A , with the expanded
greenspace Option B.
Note:
The delivery of the Option A proposals
would result in no loss of parking
within the adjacent surface parking
area.
The expansion of the Greenspace as
described in option B would result in
the loss of approximately 80 parking
spaces.
Proposals
Proposed
Greenspace
Potential
additional area
Included Elements
• Resin bound gravel pathways
• 2 x 50sqm areas of high quality
paving forming seating areas
• New Planting: Trees, shrubs,
border planting
• Raised planters for community
growing
• Benches (precast concrete base
with slatted timber seat top)
• Timber Pergola shelters (2no.
20sqm each)
• New illuminated bollards to
pathways
• Refuse / dog waste bins
• Signage / wayfinding totems at
entry points (3 no.)

Page 37

7372 Three Year Investment Plan Chosen Interventions
A New Town Centre Greenspace
New canalside Piazza
with public artwork,
seating and lighting
Existing glazed screens
to Sylvania Way mall
removed to provide
access to square
Potential to expand area
of new greenspace into
adjacent surface parking
zone
Upgraded canalside
greenspace with new
trees, planting, seating,
shelter and pathways
Potential extended
path to Retail Park
and Cinema
Upgraded canalside
greenspace with new
trees, planting, seating,
shelter and pathways
New large format mural
to enliven existing blank
facade (note: design
shown is indicative only)
Pop-up power /
services bollards to
service food / coffee
trucks

Page 38

Risk
1.   Interventions are limited in area and result in less than
anticipated impact / usage.
2.   New interventions attract anti-social behaviour.
3.  Part of the Land may not be in council ownership.
4.   Any required power supplies not easily accessible and
diversions/ new supplies may be required.
Mitigation
Ensure proposals maximise potential of site and provide a
number of varied uses attractive to all in the community.
Ensure robust design of any elements to minimise damage
from vandalism. The combined stategies of the Vision
(with a particular focuas on the canalside) will lead to more
activity and passive surveillance.
Carry out land ownership check and liaise with shopping
centre owners / Scottish Canals.
Utilities surveys of intervention locations to be undertaken
at earliest opportunity and proposals amended to minimise
cost / requirement for diversions.
7574 Three Year Investment Plan Chosen Interventions
Preliminary Programme, Risk
and Approval Considerations
Approval / Utility   Required (Yes / No)
Planning   Y
Warrant   Y (Canopy structures)
RCC   N
Utility Diversion / Supply  Y (Power for signage 
& bollards)
Landlord Approval   N
Other Approvals   N
High Level Cost Estimate:
Option A
Client Confidential#
Clydebank LTP Options - Sketch 100 - New Greenspace
Item Unit Qty Total
Option A
General downtakings / Site preparation Item 1 £50,000
New Greenspace area primarily soft
landscaping (adapting existing surfaces)
m2 1,695 £169,500
Existing beech hedging to boundary of
greenspaces to car park to be retained
Item 1 £20,000
Resin bound gravel pathways m2 350 £43,750
High quality paving formed in seating areas m2 100 £45,000
New Planting, trees, shrubs border
planting - budget allowance
Item 1 £80,000
Raised Planters - budget allowance Item 1 £45,000
Benches (precast concrete base with
slatted timber seat Broxap or similar) -
assumed quantity
Nr 12 £36,000
Timber Pergola shelters Nr 2 £70,000
New illuminated bollards to pathways -
assumed quantity
Nr 15 £22,500
Refuse / dog waste bins / general site
furniture
Item 1 £20,000
Signage / wayfinding totems at entry
points
Nr 3 £9,000
General modifications - street lighting Item 1 £50,000
General modifications - drainage Item 1 £75,000
£735,750
Add
Prelims @ 17.5% £128,756
Contingency @ 15% £129,676
£994,182
Design fees @ 20% £198,836
Inflation to assumed project midpoint of 3Q 2025 £39,681
Total £1,232,700
Basis of High Level Costs
1. Costs are high level estimates based on limited information currently available.
2. Threesixty Architecture sketch drawing reference 24013-SK-100 New Greenspace
3. Discussion on scope with Threesixty Architecture.
4. We have incorporated budget allowances (based on benchmarking of similar projects) for the    
majority of the work scope as detailed.
5. It is assumed the works can be carried out in a single continuous phase.
6. Inflation is based on high level programme indicated by TTPM.
Exclusions From High Level Costs
1. Any work in connection with utility services or diversion of same.
2. Any work not stated or implied on drawings.
3. VAT on works or fees.
© Turner & Townsend Project Management. All rights reserved 21/08/2024. This document is expressly provided to and solely for the use of West Dumbartonshire Council and must not be quoted from, referred to,
used by or distributed to any other party without the prior consent of Turner & Townsend Project Management who accept no liability of whatsoever nature for any use by any other party.
Clydebank 3 year plan options
Programme
Notes:
Gantt Chart Ref: C:\Users\youngdav1\OneDrive - Turner & Townsend Group Limited\Desktop\Clydebank LTP\3 Year plan options\Programmes\Clydebank 3 year plan options.pp
Border Ref: C:\Users\youngdav1\OneDrive - Turner & Townsend Group Limited\Desktop\1. T&T MASTER Landscape.B
Programme No:01                             
Revision:   on date: 
Origin Date: 21/08/2024  page 1 of 1
Turner & Townsend Project Management
Clydebank 3 year plan options 
Programme
Originator: David Young
Checked by: David Crombie
Approved by:           
Clydebank 3 year plan options
making the difference  1
Line Name Duration Start Finish
2024 2025
September October November December January February March April May June July August September October NovemberA Dec
2 9 16 23 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
3 year plan options
Town centre trails
Assemble design team
Design period inc
surveys
Client approval
Utility diversions inc
procurement and works
Procurement
Construction inc
mobilisation
Completion
Three Queens Square
Assemble design team
Design period inc
surveys
Client approval
Planning
Landlord approval
Scottish Water approval
for new drainage
Procurement inc
containers
Construction inc
mobilisation
Completion
Canalside Activity
Centre
Assemble design team
Design period inc
surveys
Client approval
Planning
Building Warrant
Landlord approval/ AfL
Scottish Canals approval
Procurement
Construction inc
mobilisation and lift
procurement
Completion
Greenspace Option 1
Assemble design team
Design period inc
surveys
Client approval
Utility diversions inc
procurement and works
Planning
Procurement
Construction inc
mobilisation and lift
procurement
Completion
Greenspace Option 2
Assemble design team
Design period inc
surveys
Client approval
Utility diversions inc
procurement and works
Planning
Building Warrant for
skatepark and MUGA
Landlord approval for
car park alterations (not
inc land sale)
RCC for car park
alterations/ stopping up
Scottish Water approval
for new drainage
Procurement
Construction inc MUGA
and skatepark
procurement
Completion
Connecting
Communities - Queens
Quay, Golden Jubilee
and Wider Communities
Assemble design team
Design period inc
surveys
Client approval
Roads authority
approval for road
painting
Procurement
Construction
Completion
Meanwhile space - Basic
works
Assemble design team
Design period inc
surveys
Client approval
Planning/ advertisement
consent
Landlord approval/ AfL
Procurement
Construction
Completion
Meanwhile space -
Intensite strategy
Assemble design team
Design period inc
surveys
Client approval
Planning/ advertisement
consent
Building Warrant
Landlord approval/ AfL
Procurement
Construction
Completion
62w
40w
2w
6w
2w
20w
4w
12w
52w
2w
12w
2w
12w
8w
8w
20w
16w
48w
2w
12w
2w
12w
12w
8w
12w
12w
20w
42w
2w
8w
2w
20w
12w
16w
12w
62w
2w
16w
2w
20w
12w
12w
8w
12w
8w
16w
24w
38w
2w
10w
2w
8w
12w
12w
24w
2w
4w
2w
12w
8w
6w
6w
42w
2w
10w
2w
12w
12w
8w
12w
16w
02/09/2024
02/09/2024
02/09/2024
16/09/2024
28/10/2024
28/10/2024
11/11/2024
31/03/2025
27/06/2025
02/09/2024
02/09/2024
16/09/2024
09/12/2024
06/01/2025
06/01/2025
09/12/2024
06/01/2025
30/05/2025
22/09/2025
02/09/2024
02/09/2024
16/09/2024
09/12/2024
09/12/2024
09/12/2024
06/01/2025
09/12/2024
06/01/2025
31/03/2025
22/08/2025
02/09/2024
02/09/2024
16/09/2024
11/11/2024
11/11/2024
11/11/2024
25/11/2024
14/04/2025
11/07/2025
02/09/2024
02/09/2024
16/09/2024
20/01/2025
20/01/2025
20/01/2025
20/01/2025
03/02/2025
20/01/2025
20/01/2025
03/02/2025
13/06/2025
01/12/2025
02/09/2024
02/09/2024
16/09/2024
25/11/2024
25/11/2024
09/12/2024
17/03/2025
13/06/2025
02/09/2024
02/09/2024
16/09/2024
14/10/2024
14/10/2024
28/10/2024
28/10/2024
20/01/2025
03/03/2025
02/09/2024
02/09/2024
16/09/2024
25/11/2024
25/11/2024
25/11/2024
09/12/2024
09/12/2024
17/03/2025
11/07/2025
01/12/2025
27/06/2025
13/09/2024
25/10/2024
08/11/2024
28/03/2025
06/12/2024
26/06/2025
27/06/2025
22/09/2025
13/09/2024
06/12/2024
20/12/2024
28/03/2025
28/02/2025
14/02/2025
29/05/2025
19/09/2025
22/09/2025
22/08/2025
13/09/2024
06/12/2024
20/12/2024
14/03/2025
14/03/2025
28/02/2025
14/03/2025
28/03/2025
21/08/2025
22/08/2025
11/07/2025
13/09/2024
08/11/2024
22/11/2024
11/04/2025
14/02/2025
28/03/2025
10/07/2025
11/07/2025
01/12/2025
13/09/2024
17/01/2025
31/01/2025
12/06/2025
11/04/2025
11/04/2025
28/03/2025
11/04/2025
14/03/2025
29/05/2025
28/11/2025
01/12/2025
13/06/2025
13/09/2024
22/11/2024
06/12/2024
31/01/2025
14/03/2025
12/06/2025
13/06/2025
03/03/2025
13/09/2024
11/10/2024
25/10/2024
17/01/2025
20/12/2024
06/12/2024
28/02/2025
03/03/2025
11/07/2025
13/09/2024
22/11/2024
06/12/2024
28/02/2025
28/02/2025
14/02/2025
14/03/2025
10/07/2025
11/07/2025
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
Milestone Appearances
Start Milestone
© Turner & Townsend Project Management. All rights reserved 21/08/2024. This document is expressly provided to and solely for the use of West Dumbartonshire Council and must not be quoted from, referred to,
used by or distributed to any other party without the prior consent of Turner & Townsend Project Management who accept no liability of whatsoever nature for any use by any other party.
Clydebank 3 year plan options
Programme
Notes:
Gantt Chart Ref: C:\Users\youngdav1\OneDrive - Turner & Townsend Group Limited\Desktop\Clydebank LTP\3 Year plan options\Programmes\Clydebank 3 year plan options.pp
Border Ref: C:\Users\youngdav1\OneDrive - Turner & Townsend Group Limited\Desktop\1. T&T MASTER Landscape.B
Programme No:01                             
Revision:   on date: 
Origin Date: 21/08/2024  page 1 of 1
Turner & Townsend Project Management
Clydebank 3 year plan options 
Programme
Originator: David Young
Checked by: David Crombie
Approved by:           
Clydebank 3 year plan options
making the difference  1
Line Name Duration Start Finish
2024 2025
September October November December January February March April May June July August September October NovemberA Dec
2 9 16 23 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
3 year plan options
Town centre trails
Assemble design team
Design period inc
surveys
Client approval
Utility diversions inc
procurement and works
Procurement
Construction inc
mobilisation
Completion
Three Queens Square
Assemble design team
Design period inc
surveys
Client approval
Planning
Landlord approval
Scottish Water approval
for new drainage
Procurement inc
containers
Construction inc
mobilisation
Completion
Canalside Activity
Centre
Assemble design team
Design period inc
surveys
Client approval
Planning
Building Warrant
Landlord approval/ AfL
Scottish Canals approval
Procurement
Construction inc
mobilisation and lift
procurement
Completion
Greenspace Option 1
Assemble design team
Design period inc
surveys
Client approval
Utility diversions inc
procurement and works
Planning
Procurement
Construction inc
mobilisation and lift
procurement
Completion
Greenspace Option 2
Assemble design team
Design period inc
surveys
Client approval
Utility diversions inc
procurement and works
Planning
Building Warrant for
skatepark and MUGA
Landlord approval for
car park alterations (not
inc land sale)
RCC for car park
alterations/ stopping up
Scottish Water approval
for new drainage
Procurement
Construction inc MUGA
and skatepark
procurement
Completion
Connecting
Communities - Queens
Quay, Golden Jubilee
and Wider Communities
Assemble design team
Design period inc
surveys
Client approval
Roads authority
approval for road
painting
Procurement
Construction
Completion
Meanwhile space - Basic
works
Assemble design team
Design period inc
surveys
Client approval
Planning/ advertisement
consent
Landlord approval/ AfL
Procurement
Construction
Completion
Meanwhile space -
Intensite strategy
Assemble design team
Design period inc
surveys
Client approval
Planning/ advertisement
consent
Building Warrant
Landlord approval/ AfL
Procurement
Construction
Completion
62w
40w
2w
6w
2w
20w
4w
12w
52w
2w
12w
2w
12w
8w
8w
20w
16w
48w
2w
12w
2w
12w
12w
8w
12w
12w
20w
42w
2w
8w
2w
20w
12w
16w
12w
62w
2w
16w
2w
20w
12w
12w
8w
12w
8w
16w
24w
38w
2w
10w
2w
8w
12w
12w
24w
2w
4w
2w
12w
8w
6w
6w
42w
2w
10w
2w
12w
12w
8w
12w
16w
02/09/2024
02/09/2024
02/09/2024
16/09/2024
28/10/2024
28/10/2024
11/11/2024
31/03/2025
27/06/2025
02/09/2024
02/09/2024
16/09/2024
09/12/2024
06/01/2025
06/01/2025
09/12/2024
06/01/2025
30/05/2025
22/09/2025
02/09/2024
02/09/2024
16/09/2024
09/12/2024
09/12/2024
09/12/2024
06/01/2025
09/12/2024
06/01/2025
31/03/2025
22/08/2025
02/09/2024
02/09/2024
16/09/2024
11/11/2024
11/11/2024
11/11/2024
25/11/2024
14/04/2025
11/07/2025
02/09/2024
02/09/2024
16/09/2024
20/01/2025
20/01/2025
20/01/2025
20/01/2025
03/02/2025
20/01/2025
20/01/2025
03/02/2025
13/06/2025
01/12/2025
02/09/2024
02/09/2024
16/09/2024
25/11/2024
25/11/2024
09/12/2024
17/03/2025
13/06/2025
02/09/2024
02/09/2024
16/09/2024
14/10/2024
14/10/2024
28/10/2024
28/10/2024
20/01/2025
03/03/2025
02/09/2024
02/09/2024
16/09/2024
25/11/2024
25/11/2024
25/11/2024
09/12/2024
09/12/2024
17/03/2025
11/07/2025
01/12/2025
27/06/2025
13/09/2024
25/10/2024
08/11/2024
28/03/2025
06/12/2024
26/06/2025
27/06/2025
22/09/2025
13/09/2024
06/12/2024
20/12/2024
28/03/2025
28/02/2025
14/02/2025
29/05/2025
19/09/2025
22/09/2025
22/08/2025
13/09/2024
06/12/2024
20/12/2024
14/03/2025
14/03/2025
28/02/2025
14/03/2025
28/03/2025
21/08/2025
22/08/2025
11/07/2025
13/09/2024
08/11/2024
22/11/2024
11/04/2025
14/02/2025
28/03/2025
10/07/2025
11/07/2025
01/12/2025
13/09/2024
17/01/2025
31/01/2025
12/06/2025
11/04/2025
11/04/2025
28/03/2025
11/04/2025
14/03/2025
29/05/2025
28/11/2025
01/12/2025
13/06/2025
13/09/2024
22/11/2024
06/12/2024
31/01/2025
14/03/2025
12/06/2025
13/06/2025
03/03/2025
13/09/2024
11/10/2024
25/10/2024
17/01/2025
20/12/2024
06/12/2024
28/02/2025
03/03/2025
11/07/2025
13/09/2024
22/11/2024
06/12/2024
28/02/2025
28/02/2025
14/02/2025
14/03/2025
10/07/2025
11/07/2025
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
Milestone Appearances
Start Milestone
Revenue funding for ongoing
maintenance and management to be
established in following development
stages and added to budget.
The programme below demonstrates
that the Option A Greenspace
described in this report could be
developed from this initial concept
and delivered in a 42 week period.
This is based on the following key stages:
Assemble Design Team:     2 weeks
Design Development (incl. surveys):   8 weeks
Planning, Utility Diversions, Scottish Water Approval
and Procurement (mainly concurrent)   20 weeks
Construction (incl. mobilisation period)   12 weeks
Client Confidential#
Clydebank LTP Options - Sketch 100 - New Greenspace
Item Unit Qty Total
Option A
General downtakings / Site preparation Item 1 £50,000
New Greenspace area primarily soft
landscaping (adapting existing surfaces)
m2 1,695 £169,500
Existing beech hedging to boundary of
greenspaces to car park to be retained
Item 1 £20,000
Resin bound gravel pathways m2 350 £43,750
High quality paving formed in seating areas m2 100 £45,000
New Planting, trees, shrubs border
planting - budget allowance
Item 1 £80,000
Raised Planters - budget allowance Item 1 £45,000
Benches (precast concrete base with
slatted timber seat Broxap or similar) -
assumed quantity
Nr 12 £36,000
Timber Pergola shelters Nr 2 £70,000
New illuminated bollards to pathways -
assumed quantity
Nr 15 £22,500
Refuse / dog waste bins / general site
furniture
Item 1 £20,000
Signage / wayfinding totems at entry
points
Nr 3 £9,000
General modifications - street lighting Item 1 £50,000
General modifications - drainage Item 1 £75,000
£735,750
Add
Prelims @ 17.5% £128,756
Contingency @ 15% £129,676
£994,182
Design fees @ 20% £198,836
Inflation to assumed project midpoint of 3Q 2025 £39,681
Total £1,232,700
Basis of High Level Costs
1. Costs are high level estimates based on limited information currently available.
2. Threesixty Architecture sketch drawing reference 24013-SK-100 New Greenspace
3. Discussion on scope with Threesixty Architecture.
4. We have incorporated budget allowances (based on benchmarking of similar projects) for the    
majority of the work scope as detailed.
5. It is assumed the works can be carried out in a single continuous phase.
6. Inflation is based on high level programme indicated by TTPM.
Exclusions From High Level Costs
1. Any work in connection with utility services or diversion of same.
2. Any work not stated or implied on drawings.
3. VAT on works or fees.
Client Confidential#
Clydebank LTP Options - Sketch 100 - New Greenspace
Item Unit Qty Total
Option A
General downtakings / Site preparation Item 1 £50,000
New Greenspace area primarily soft
landscaping (adapting existing surfaces)
m2 1,695 £169,500
Existing beech hedging to boundary of
greenspaces to car park to be retained
Item 1 £20,000
Resin bound gravel pathways m2 350 £43,750
High quality paving formed in seating areas m2 100 £45,000
New Planting, trees, shrubs border
planting - budget allowance
Item 1 £80,000
Raised Planters - budget allowance Item 1 £45,000
Benches (precast concrete base with
slatted timber seat Broxap or similar) -
assumed quantity
Nr 12 £36,000
Timber Pergola shelters Nr 2 £70,000
New illuminated bollards to pathways -
assumed quantity
Nr 15 £22,500
Refuse / dog waste bins / general site
furniture
Item 1 £20,000
Signage / wayfinding totems at entry
points
Nr 3 £9,000
General modifications - street lighting Item 1 £50,000
General modifications - drainage Item 1 £75,000
£735,750
Add
Prelims @ 17.5% £128,756
Contingency @ 15% £129,676
£994,182
Design fees @ 20% £198,836
Inflation to assumed project midpoint of 3Q 2025 £39,681
Total £1,232,700
Basis of High Level Costs
1. Costs are high level estimates based on limited information currently available.
2. Threesixty Architecture sketch drawing reference 24013-SK-100 New Greenspace
3. Discussion on scope with Threesixty Architecture.
4. We have incorporated budget allowances (based on benchmarking of similar projects) for the    
majority of the work scope as detailed.
5. It is assumed the works can be carried out in a single continuous phase.
6. Inflation is based on high level programme indicated by TTPM.
Exclusions From High Level Costs
1. Any work in connection with utility services or diversion of same.
2. Any work not stated or implied on drawings.
3. VAT on works or fees.
Increased activity and vibrancy in heart of town –
greater safety
Promotes shared, multi-generational activity and
interactions – Inclusion and Health
Approval / Utility Considerations
Expected Outcomes
and Benefits
Potential Risks

Page 39

Risk
1.     Car park owner is reluctant to sell or lease area of car 
park to enable additional interventions to be developed.
Resistance to loss of any parking in town centre.
2.    Future maintenance of new activity spaces cannot be
funded.
3.   New surface water drainage required for MUGA and
skate park resulting in need to seek Scottish Water
approval and carry out diversion works.
Mitigation
Initiate dialogue with car park owners at earliest
opportunity to discuss. Wider assessment of parking
provision and consultation on impact of localised loss to be
undertaken.
Allow for revenue funding to permit maintenance /
management of space for duration of Ten Year Vision.
Undertake utilities survey of location and begin preliminary
dialogue with Scottish water at earliest opportunity.
7776 Three Year Investment Plan Chosen Interventions
High Level Cost Estimate:
Option B
Clydebank LTP Options - Sketch 100 - New Greenspace
Item Unit Qty Total
Option B
General downtakings / Site preparation Item 1 £90,000
New Greenspace area primarily soft
landscaping (adapting existing surfaces)
m2 1,695 £169,500
Existing beech hedging to boundary of
greenspaces to car park to be retained
Item 1 £20,000
Resin bound gravel pathways m2 350 £43,750
High quality paving formed in seating areas m2 100 £45,000
New Planting, trees, shrubs border
planting - budget allowance
Item 1 £90,000
Raised Planters - budget allowance Item 1 £55,000
Benches (precast concrete base with
slatted timber seat Broxap or similar) -
assumed quantity
Nr 14 £42,000
Timber Pergola shelters Nr 2 £70,000
New illuminated bollards to pathways -
assumed quantity
Nr 15 £22,500
Refuse / dog waste bins / general site
furniture
Item 1 £20,000
Signage / wayfinding totems at entry
points
Nr 3 £9,000
General modifications - street lighting Item 1 £75,000
General modifications - drainage Item 1 £100,000
Provision of new 35x18m Muga pitch,
complete - budget allowance
m2 630 £126,000
Provision of new skate park - budget
allowance of £350/m2
m2 595 £208,250
Potential expansion into car park area;
comprising soft landscaping / paths
m2 1,410 £211,500
£1,397,500
Add
Prelims @ 17.5% £244,563
Contingency @ 15% £246,309
£1,888,372
Design fees @ 20% £377,674
Inflation to assumed project midpoint of 3Q 2025 £75,554
Total £2,341,600
Basis of High Level Costs
1. Costs are high level estimates based on limited information currently available.
2. Threesixty Architecture sketch drawing reference 24013-SK-100 New Greenspace
3. Discussion on scope with Threesixty Architecture.
4. We have incorporated budget allowances (based on benchmarking of similar projects) for the    
majority of the work scope as detailed.
5. It is assumed the works can be carried out in a single continuous phase.
6. Inflation is based on high level programme indicated by TTPM.
Exclusions From High Level Costs
1. Any work in connection with utility services or diversion of same.
2. Any work not stated or implied on drawings.
3. VAT on works or fees.
© Turner & Townsend Project Management. All rights reserved 21/08/2024. This document is expressly provided to and solely for the use of West Dumbartonshire Council and must not be quoted from, referred to,
used by or distributed to any other party without the prior consent of Turner & Townsend Project Management who accept no liability of whatsoever nature for any use by any other party.
Clydebank 3 year plan options
Programme
Notes:
Gantt Chart Ref: C:\Users\youngdav1\OneDrive - Turner & Townsend Group Limited\Desktop\Clydebank LTP\3 Year plan options\Programmes\Clydebank 3 year plan options.pp
Border Ref: C:\Users\youngdav1\OneDrive - Turner & Townsend Group Limited\Desktop\1. T&T MASTER Landscape.B
Programme No:01                             
Revision:   on date: 
Origin Date: 21/08/2024  page 1 of 1
Turner & Townsend Project Management
Clydebank 3 year plan options 
Programme
Originator: David Young
Checked by: David Crombie
Approved by:           
Clydebank 3 year plan options
making the difference  1
Line Name Duration Start Finish
2024 2025
September October November December January February March April May June July August September October NovemberA Dec
2 9 16 23 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
3 year plan options
Town centre trails
Assemble design team
Design period inc
surveys
Client approval
Utility diversions inc
procurement and works
Procurement
Construction inc
mobilisation
Completion
Three Queens Square
Assemble design team
Design period inc
surveys
Client approval
Planning
Landlord approval
Scottish Water approval
for new drainage
Procurement inc
containers
Construction inc
mobilisation
Completion
Canalside Activity
Centre
Assemble design team
Design period inc
surveys
Client approval
Planning
Building Warrant
Landlord approval/ AfL
Scottish Canals approval
Procurement
Construction inc
mobilisation and lift
procurement
Completion
Greenspace Option 1
Assemble design team
Design period inc
surveys
Client approval
Utility diversions inc
procurement and works
Planning
Procurement
Construction inc
mobilisation and lift
procurement
Completion
Greenspace Option 2
Assemble design team
Design period inc
surveys
Client approval
Utility diversions inc
procurement and works
Planning
Building Warrant for
skatepark and MUGA
Landlord approval for
car park alterations (not
inc land sale)
RCC for car park
alterations/ stopping up
Scottish Water approval
for new drainage
Procurement
Construction inc MUGA
and skatepark
procurement
Completion
Connecting
Communities - Queens
Quay, Golden Jubilee
and Wider Communities
Assemble design team
Design period inc
surveys
Client approval
Roads authority
approval for road
painting
Procurement
Construction
Completion
Meanwhile space - Basic
works
Assemble design team
Design period inc
surveys
Client approval
Planning/ advertisement
consent
Landlord approval/ AfL
Procurement
Construction
Completion
Meanwhile space -
Intensite strategy
Assemble design team
Design period inc
surveys
Client approval
Planning/ advertisement
consent
Building Warrant
Landlord approval/ AfL
Procurement
Construction
Completion
62w
40w
2w
6w
2w
20w
4w
12w
52w
2w
12w
2w
12w
8w
8w
20w
16w
48w
2w
12w
2w
12w
12w
8w
12w
12w
20w
42w
2w
8w
2w
20w
12w
16w
12w
62w
2w
16w
2w
20w
12w
12w
8w
12w
8w
16w
24w
38w
2w
10w
2w
8w
12w
12w
24w
2w
4w
2w
12w
8w
6w
6w
42w
2w
10w
2w
12w
12w
8w
12w
16w
02/09/2024
02/09/2024
02/09/2024
16/09/2024
28/10/2024
28/10/2024
11/11/2024
31/03/2025
27/06/2025
02/09/2024
02/09/2024
16/09/2024
09/12/2024
06/01/2025
06/01/2025
09/12/2024
06/01/2025
30/05/2025
22/09/2025
02/09/2024
02/09/2024
16/09/2024
09/12/2024
09/12/2024
09/12/2024
06/01/2025
09/12/2024
06/01/2025
31/03/2025
22/08/2025
02/09/2024
02/09/2024
16/09/2024
11/11/2024
11/11/2024
11/11/2024
25/11/2024
14/04/2025
11/07/2025
02/09/2024
02/09/2024
16/09/2024
20/01/2025
20/01/2025
20/01/2025
20/01/2025
03/02/2025
20/01/2025
20/01/2025
03/02/2025
13/06/2025
01/12/2025
02/09/2024
02/09/2024
16/09/2024
25/11/2024
25/11/2024
09/12/2024
17/03/2025
13/06/2025
02/09/2024
02/09/2024
16/09/2024
14/10/2024
14/10/2024
28/10/2024
28/10/2024
20/01/2025
03/03/2025
02/09/2024
02/09/2024
16/09/2024
25/11/2024
25/11/2024
25/11/2024
09/12/2024
09/12/2024
17/03/2025
11/07/2025
01/12/2025
27/06/2025
13/09/2024
25/10/2024
08/11/2024
28/03/2025
06/12/2024
26/06/2025
27/06/2025
22/09/2025
13/09/2024
06/12/2024
20/12/2024
28/03/2025
28/02/2025
14/02/2025
29/05/2025
19/09/2025
22/09/2025
22/08/2025
13/09/2024
06/12/2024
20/12/2024
14/03/2025
14/03/2025
28/02/2025
14/03/2025
28/03/2025
21/08/2025
22/08/2025
11/07/2025
13/09/2024
08/11/2024
22/11/2024
11/04/2025
14/02/2025
28/03/2025
10/07/2025
11/07/2025
01/12/2025
13/09/2024
17/01/2025
31/01/2025
12/06/2025
11/04/2025
11/04/2025
28/03/2025
11/04/2025
14/03/2025
29/05/2025
28/11/2025
01/12/2025
13/06/2025
13/09/2024
22/11/2024
06/12/2024
31/01/2025
14/03/2025
12/06/2025
13/06/2025
03/03/2025
13/09/2024
11/10/2024
25/10/2024
17/01/2025
20/12/2024
06/12/2024
28/02/2025
03/03/2025
11/07/2025
13/09/2024
22/11/2024
06/12/2024
28/02/2025
28/02/2025
14/02/2025
14/03/2025
10/07/2025
11/07/2025
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
Milestone Appearances
Start Milestone
© Turner & Townsend Project Management. All rights reserved 21/08/2024. This document is expressly provided to and solely for the use of West Dumbartonshire Council and must not be quoted from, referred to,
used by or distributed to any other party without the prior consent of Turner & Townsend Project Management who accept no liability of whatsoever nature for any use by any other party.
Clydebank 3 year plan options
Programme
Notes:
Gantt Chart Ref: C:\Users\youngdav1\OneDrive - Turner & Townsend Group Limited\Desktop\Clydebank LTP\3 Year plan options\Programmes\Clydebank 3 year plan options.pp
Border Ref: C:\Users\youngdav1\OneDrive - Turner & Townsend Group Limited\Desktop\1. T&T MASTER Landscape.B
Programme No:01                             
Revision:   on date: 
Origin Date: 21/08/2024  page 1 of 1
Turner & Townsend Project Management
Clydebank 3 year plan options 
Programme
Originator: David Young
Checked by: David Crombie
Approved by:           
Clydebank 3 year plan options
making the difference  1
Line Name Duration Start Finish
2024 2025
September October November December January February March April May June July August September October NovemberA Dec
2 9 16 23 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
3 year plan options
Town centre trails
Assemble design team
Design period inc
surveys
Client approval
Utility diversions inc
procurement and works
Procurement
Construction inc
mobilisation
Completion
Three Queens Square
Assemble design team
Design period inc
surveys
Client approval
Planning
Landlord approval
Scottish Water approval
for new drainage
Procurement inc
containers
Construction inc
mobilisation
Completion
Canalside Activity
Centre
Assemble design team
Design period inc
surveys
Client approval
Planning
Building Warrant
Landlord approval/ AfL
Scottish Canals approval
Procurement
Construction inc
mobilisation and lift
procurement
Completion
Greenspace Option 1
Assemble design team
Design period inc
surveys
Client approval
Utility diversions inc
procurement and works
Planning
Procurement
Construction inc
mobilisation and lift
procurement
Completion
Greenspace Option 2
Assemble design team
Design period inc
surveys
Client approval
Utility diversions inc
procurement and works
Planning
Building Warrant for
skatepark and MUGA
Landlord approval for
car park alterations (not
inc land sale)
RCC for car park
alterations/ stopping up
Scottish Water approval
for new drainage
Procurement
Construction inc MUGA
and skatepark
procurement
Completion
Connecting
Communities - Queens
Quay, Golden Jubilee
and Wider Communities
Assemble design team
Design period inc
surveys
Client approval
Roads authority
approval for road
painting
Procurement
Construction
Completion
Meanwhile space - Basic
works
Assemble design team
Design period inc
surveys
Client approval
Planning/ advertisement
consent
Landlord approval/ AfL
Procurement
Construction
Completion
Meanwhile space -
Intensite strategy
Assemble design team
Design period inc
surveys
Client approval
Planning/ advertisement
consent
Building Warrant
Landlord approval/ AfL
Procurement
Construction
Completion
62w
40w
2w
6w
2w
20w
4w
12w
52w
2w
12w
2w
12w
8w
8w
20w
16w
48w
2w
12w
2w
12w
12w
8w
12w
12w
20w
42w
2w
8w
2w
20w
12w
16w
12w
62w
2w
16w
2w
20w
12w
12w
8w
12w
8w
16w
24w
38w
2w
10w
2w
8w
12w
12w
24w
2w
4w
2w
12w
8w
6w
6w
42w
2w
10w
2w
12w
12w
8w
12w
16w
02/09/2024
02/09/2024
02/09/2024
16/09/2024
28/10/2024
28/10/2024
11/11/2024
31/03/2025
27/06/2025
02/09/2024
02/09/2024
16/09/2024
09/12/2024
06/01/2025
06/01/2025
09/12/2024
06/01/2025
30/05/2025
22/09/2025
02/09/2024
02/09/2024
16/09/2024
09/12/2024
09/12/2024
09/12/2024
06/01/2025
09/12/2024
06/01/2025
31/03/2025
22/08/2025
02/09/2024
02/09/2024
16/09/2024
11/11/2024
11/11/2024
11/11/2024
25/11/2024
14/04/2025
11/07/2025
02/09/2024
02/09/2024
16/09/2024
20/01/2025
20/01/2025
20/01/2025
20/01/2025
03/02/2025
20/01/2025
20/01/2025
03/02/2025
13/06/2025
01/12/2025
02/09/2024
02/09/2024
16/09/2024
25/11/2024
25/11/2024
09/12/2024
17/03/2025
13/06/2025
02/09/2024
02/09/2024
16/09/2024
14/10/2024
14/10/2024
28/10/2024
28/10/2024
20/01/2025
03/03/2025
02/09/2024
02/09/2024
16/09/2024
25/11/2024
25/11/2024
25/11/2024
09/12/2024
09/12/2024
17/03/2025
11/07/2025
01/12/2025
27/06/2025
13/09/2024
25/10/2024
08/11/2024
28/03/2025
06/12/2024
26/06/2025
27/06/2025
22/09/2025
13/09/2024
06/12/2024
20/12/2024
28/03/2025
28/02/2025
14/02/2025
29/05/2025
19/09/2025
22/09/2025
22/08/2025
13/09/2024
06/12/2024
20/12/2024
14/03/2025
14/03/2025
28/02/2025
14/03/2025
28/03/2025
21/08/2025
22/08/2025
11/07/2025
13/09/2024
08/11/2024
22/11/2024
11/04/2025
14/02/2025
28/03/2025
10/07/2025
11/07/2025
01/12/2025
13/09/2024
17/01/2025
31/01/2025
12/06/2025
11/04/2025
11/04/2025
28/03/2025
11/04/2025
14/03/2025
29/05/2025
28/11/2025
01/12/2025
13/06/2025
13/09/2024
22/11/2024
06/12/2024
31/01/2025
14/03/2025
12/06/2025
13/06/2025
03/03/2025
13/09/2024
11/10/2024
25/10/2024
17/01/2025
20/12/2024
06/12/2024
28/02/2025
03/03/2025
11/07/2025
13/09/2024
22/11/2024
06/12/2024
28/02/2025
28/02/2025
14/02/2025
14/03/2025
10/07/2025
11/07/2025
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
Milestone Appearances
Start Milestone
Preliminary Programme, Risk
and Approval Considerations
Potential Risks
Approval / Utility Considerations
Approval / Utility   Required (Yes / No)
Planning   Y
Warrant   Y (Canopy structures / 
MUGA / Skatepark)
RCC   Y (Car park alterations)
Utility Diversion / Supply  Y (Power for signage, 
bollards, MUGA & 
Skatepark)
Landlord Approval   Y (Assume Mall owns 
car park
Other Approvals   Scottish Water     
approval for additonal 
drainage
The programme below demonstrates
that the Option B Greenspace
described in this report could be
developed from this initial concept
and delivered in a 62 week period.
This is based on the following key
stages:
Assemble Design Team:     2 weeks
Design Development (incl. surveys):   16 weeks
Planning, Warrant, Landlord Approval, Scottish Water
Approval, RCC for car park alterations and Procurement
(mainly concurrent):      20 weeks
Construction (incl. mobilisation period and
procurement of MUGA and Skatepark):   24 weeks
Clydebank LTP Options - Sketch 100 - New Greenspace
Item Unit Qty Total
Option B
General downtakings / Site preparation Item 1 £90,000
New Greenspace area primarily soft
landscaping (adapting existing surfaces)
m2 1,695 £169,500
Existing beech hedging to boundary of
greenspaces to car park to be retained
Item 1 £20,000
Resin bound gravel pathways m2 350 £43,750
High quality paving formed in seating areas m2 100 £45,000
New Planting, trees, shrubs border
planting - budget allowance
Item 1 £90,000
Raised Planters - budget allowance Item 1 £55,000
Benches (precast concrete base with
slatted timber seat Broxap or similar) -
assumed quantity
Nr 14 £42,000
Timber Pergola shelters Nr 2 £70,000
New illuminated bollards to pathways -
assumed quantity
Nr 15 £22,500
Refuse / dog waste bins / general site
furniture
Item 1 £20,000
Signage / wayfinding totems at entry
points
Nr 3 £9,000
General modifications - street lighting Item 1 £75,000
General modifications - drainage Item 1 £100,000
Provision of new 35x18m Muga pitch,
complete - budget allowance
m2 630 £126,000
Provision of new skate park - budget
allowance of £350/m2
m2 595 £208,250
Potential expansion into car park area;
comprising soft landscaping / paths
m2 1,410 £211,500
£1,397,500
Add
Prelims @ 17.5% £244,563
Contingency @ 15% £246,309
£1,888,372
Design fees @ 20% £377,674
Inflation to assumed project midpoint of 3Q 2025 £75,554
Total £2,341,600
Basis of High Level Costs
1. Costs are high level estimates based on limited information currently available.
2. Threesixty Architecture sketch drawing reference 24013-SK-100 New Greenspace
3. Discussion on scope with Threesixty Architecture.
4. We have incorporated budget allowances (based on benchmarking of similar projects) for the    
majority of the work scope as detailed.
5. It is assumed the works can be carried out in a single continuous phase.
6. Inflation is based on high level programme indicated by TTPM.
Exclusions From High Level Costs
1. Any work in connection with utility services or diversion of same.
2. Any work not stated or implied on drawings.
3. VAT on works or fees.
Clydebank LTP Options - Sketch 100 - New Greenspace
Item Unit Qty Total
Option B
General downtakings / Site preparation Item 1 £90,000
New Greenspace area primarily soft
landscaping (adapting existing surfaces)
m2 1,695 £169,500
Existing beech hedging to boundary of
greenspaces to car park to be retained
Item 1 £20,000
Resin bound gravel pathways m2 350 £43,750
High quality paving formed in seating areas m2 100 £45,000
New Planting, trees, shrubs border
planting - budget allowance
Item 1 £90,000
Raised Planters - budget allowance Item 1 £55,000
Benches (precast concrete base with
slatted timber seat Broxap or similar) -
assumed quantity
Nr 14 £42,000
Timber Pergola shelters Nr 2 £70,000
New illuminated bollards to pathways -
assumed quantity
Nr 15 £22,500
Refuse / dog waste bins / general site
furniture
Item 1 £20,000
Signage / wayfinding totems at entry
points
Nr 3 £9,000
General modifications - street lighting Item 1 £75,000
General modifications - drainage Item 1 £100,000
Provision of new 35x18m Muga pitch,
complete - budget allowance
m2 630 £126,000
Provision of new skate park - budget
allowance of £350/m2
m2 595 £208,250
Potential expansion into car park area;
comprising soft landscaping / paths
m2 1,410 £211,500
£1,397,500
Add
Prelims @ 17.5% £244,563
Contingency @ 15% £246,309
£1,888,372
Design fees @ 20% £377,674
Inflation to assumed project midpoint of 3Q 2025 £75,554
Total £2,341,600
Basis of High Level Costs
1. Costs are high level estimates based on limited information currently available.
2. Threesixty Architecture sketch drawing reference 24013-SK-100 New Greenspace
3. Discussion on scope with Threesixty Architecture.
4. We have incorporated budget allowances (based on benchmarking of similar projects) for the    
majority of the work scope as detailed.
5. It is assumed the works can be carried out in a single continuous phase.
6. Inflation is based on high level programme indicated by TTPM.
Exclusions From High Level Costs
1. Any work in connection with utility services or diversion of same.
2. Any work not stated or implied on drawings.
3. VAT on works or fees.

Page 40

7978 Three Year Investment Plan Chosen Interventions
Strengthening connectivity
between surrounding communities
and their town centre is a key
ambition of the Long Term Plan for
Clydebank. Coupled with this is the
desire to better connect both the
emerging community and essential
services (health, education, leisure)
located at Queens Quay and the
Golden Jubilee Hospital.
Routes have been identified
connecting the following surrounding
neighbourhoods / facilities to the heart
of the town centre, all of which fall
within the designated LTP boundary:
1.  Queens Quay
2.  Golden Jubilee Hospital
3.  Surrounding Communities 
• Parkhall & Kilbowie
• Dalmuir
• Radnor Park
• Drumry & Linnvale
• Whitecrook
These routes have been illustrated
on a series of maps included later on
page xx of this report.
Compliance with UK Government
Guidance
Improvements to wider connectivity
within Clydebank for active travel is ‘on
menu’, as outlined by criteria T1:
‘Support for active travel
enhancements in the local area.’
and T6:
‘Reducing vehicle emissions.’
Priority Intervention 4: Connecting
Communities & Facilities
TRANSPORT
&
CONNECTIVITY
Precedent Imagery
A number of physical interventions are
proposed to all routes, including the
periodic employment of new double
sided banners, wayfinding signage,
new pavement / pathway finishes and
bench seating. Precedent images of
relevant examples are shown above..
There may also be requirements for
localised strategic improvements to
surfaces to widen areas etc. to ensure
safe use by wheelchair users, cyclists
and prams. Identifying the extent of
these works is beyond the scope
of this study but will be determined
as part of the next stages of design
development.
Beyond the physical, the Town Board,
in response to the feedback received
from the community engagement
are exploring, with SPT, how public
transport provision could be improved
to further strengthen connections to
and from the heart of Clydebank.
Leicester ‘Hospital Hopper’ electric bus
service connecting the city’s hospitals
Community Feedback:
‘Better Connectivity of
Train / Bus Travel Options’
Community Feedback:
‘Upgrade or Create New
Footpaths / Cycle paths’
Community Feedback:
‘Better Maintenance of
Roads / Pavements’

Page 41

Queens Quay is one of the most
significant regeneration projects
in Scotland. It is transforming the
former John Brown shipyard into
a vibrant waterside community
providing access and activity to the
Clyde from Clydebank for the first
time.
The 23 Hectare site is focused around
the Titan Crane, a powerful symbol of
Clydebank’s proud shipbuilding past
now repurposed as a tourist attraction
and viewing platform.
Queens Quay is home to a number
of key facilities set within a new
high quality public realm including
the Clydebank Campus of West
College Scotland, Clydebank Leisure
Centre, Queens Quay Energy Centre,
Clydebank NHS Health Centre, Queens
Quay House 84 Bed Care Home and
the Titan Business Centre
The first elements of residential have
recently been completed. These new
blocks have provided commercial units
at ground floor with 146 homes for
social rent above.
The ultimate ambition is to provide
around 1500 new residential units with
supporting commercial, leisure and
retail uses.
A key ambition of the Long Term
Plan is to better connect Queens
Quay to the heart of the town centre.
8180 Three Year Investment Plan Chosen Interventions
1. Connecting Queens Quay
Context:
Queens Quay
The proposals take advantage
of the recently completed Titan
Boulevard as the principle first
stage in the link from the Queens
Quay Neighbourhood.
The recent positive changes to the
environment on Dumbarton Road,
with the introduction of high quality
paving, lighting and safe crossing
points also form a key component.
Beyond this, the first interventions
seek to use the existing International
Asbestos memorial space as a
node leading to the town centre
via Alexander Street and Hume
Street, both of which extend toward
Chalmers Street. Improvements
are proposed to all of these
aforementioned areas as noted on the
next page.
The biggest physical challenge to
better connecting Queens Quay more
effectively to the town centre  is the
challenge to visibility posed by the
existing elevated railway line. The
proposals suggest improvements to
the environment beneath this line on
both Alexander and Hume Streets
through the introduction of new
artwork / signage and lighting. The
integration of these impovements
would alow the Town Board to include
another item that was previously
considered on the ‘Long List’ and had
garnered strong support.
These combined interventions are
illustrated on pages 76-77 of this
report.
Proposals
Asbestos Memorial Improvements
• New Raised Planters (30 sqm
area each approx.) with semi
mature trees to enclose and
define space, complete with
wayfinding information
• New Decorative Mural to existing
wall (150 sqm approx)
• New Metal Fencing complete with
decorative mesh panels (40 sqm
approx)
Alexander Street Improvements
• New vinyl signage banners to
existing lampposts (5no.)
• New wayfinding graphics and
lighting to underside of railway
bridge (120sqm wall / 160sqm
ceiling)
Hume Street Improvements
• New vinyl signage banners to
existing lampposts (3no.)
• New painted cycle lane (150 linear
metres approx.)
• New wayfinding graphics and
lighting to underside of railway
bridge (120sqm wall / 160sqm
ceiling)
Proposed connecting routes

Page 42

8382 Three Year Investment Plan Chosen Interventions
1. Connecting Queens Quay
Raised planter beds
with integrated bench
seating to take semi
mature trees and
shrubs. Incorporates
heritage / directional
totem
New street art
murals and canopy
lighting to railway
viaduct undercroft
Wayfinding
banners to existing
street lights
Decorative full
height perforated
metal boundary
screen
Raised planter beds
with integrated bench
seating to take semi
mature trees and
shrubs. Incorporates
heritage / directional
totem
New Heritage
themed mural to
existing building
gable (note:
design shown is
indicative only)
Wayfinding
banners to existing
street lights
New painted
cycle lane to
Hume Street
Railway viaduct concept
image
A
L E X A
N
D
E R   
S
T R
E E T
H
U
M
E   
S T R E E T

Page 43

*
NHS Golden Jubilee Campus is the
family of facilities which includes the
Golden Jubilee National Hospital,
Research Institute and Conference
Hotel.
The facility combines a top quality
hospital with hotel, and conference
facilities and centres for research,
clinical skills and innovation. This
integrated approach, with a focus on
continuous learning and strong links
to academia and industry, creates a
crucible for innovation and a vibrant
network for the spread of learning and
best practice.
A leading centre for heart procedures,
the facility has been expanded to form
Scotland’s first ‘National Treatment
Centre’. Phase one, the new Eye
Centre opened in 2020.
The second phase of the National
Treatment Centre was completed
in June 2023.  Patient and visitor
numbers have increased significantly
as a consequence of the expansion, as
have staff numbers.
A key ambition of the Long Term
Plan is to better connect the Golden
Jubilee National Hospital to the
heart of the town centre.
8584 Three Year Investment Plan Chosen Interventions
2. Connecting the Golden Jubilee Hospital
Context:
Golden Jubilee Hospital
The proposals identify both an active
travel route along the tow path of the
canal and a clearly signposted route
along Dumbarton Road as shown
in the map above. In both cases,
as with the proposed town centre
‘trails’ existing streets and paths
make up the entirety of the routes,
with no requirement (apart from at
key wayfinding locations) to change
surface finishes or introduce new
sections)
Agamemnon Street Improvements
• New vinyl signage banners to
existing lampposts (3no.)
• New wayfindingTotem signs (2no.)
• New painted cycle lane (220 linear
metres approx.)
Boquhanran Road Improvements
New thermoplastic decorative paint
finish to be appied to surface of
access route, ramp and risers of stairs
leading to canal towpath (approx. 400
sqm area)
Canal Towpath Interventions
New wayfinding points. Allow for
bonded resin path insert (2m x 2m)
directional totem, coordinated bench
and cycle stand at each location (5no,
ie. 1 per 200m)
Dumbarton Road Interventions
New vinyl signage banners to every
other existing lamppost on one side of
the road only (10no.)
Proposals
*
*
Proposed works to Agamemnon Street and
link to the Canal Towpath
Vinyl banner to
existing lamppost
Painted cycle lane
Directional signage
and information totem
Proposed connecting routes
Canal towpath route
Dumbarton Road route
Three Queens Square
Canal towpath intervention
Golden
Jubilee
Hospital

Page 44

8786 Three Year Investment Plan Chosen Interventions
3. Connecting Surrounding Communities
Proposed connecting routes
Three Queens Square Dalmuir route
Parkhall & Kilbowie route
Radnor Park route
Drumry & Linnvale route
Whitecrook route
Dalmuir
Parkhall
Radnor Park
Drumry
Whitecrook
A number of routes that connect
the communities of Clydebank
within the defined Long Term Plan
boundary with the heart of the town
centre have been identified and are
illustrated in the adjacent map.
Each route begins at a significant
location within each community, (train
station, Library etc.) and lead to Three
Queens Square and the Forth and
Clyde Canal.
Again, as with the proposed trails and
routes from Queens Quay and the
Golden Jubilee Hospital, the proposed
routes take advantage of established
roads, streets and paths, minimising
the need for the creation of new areas
of hard landscaping.
A number of physical interventions are
proposed to all routes, including the
periodic employment of new double
sided banners, wayfinding signage,
new pavement / pathway finishes and
bench seating. Precedent images of
relevant examples are shown on page
73 of this report.
West Dunbartonshire Council are in
the process of developing an Active
Travel Strategy for Clydebank and the
opportunity exists for this to influence
the final routes of these connections
to surrounding communities and may
permit the introduction of safe cyclling
routes and improved public transport
links.
Route Starting Points
Dalmuir: Dalmuir Train Station Parkhall & Kilbowie: Parkhall
Library
Radnor Park:  Clydebank High
School
Drumry & Linnvale: Drumry
Train Station
Whitecrook:  St. Margaret
of Scotland
Hospice
Linnvale
Kilbowie

Page 45

8988 Three Year Investment Plan Chosen Interventions
High Level Cost Estimate
Client Confidential#
Clydebank LTP Options - Clydebank Long Term Plan
Item Unit Qty Total
Alexander Street Improvements
New vinyl signage banners to existing
lampposts
Nr 5 £7,500
Allowance for paint treatment to
existing walls - railway bridge area
m2 120 £9,000
Extra over above for wayfinding
graphics
Item 1 £2,000
New lighting canopy to underside of
railway bridge
m2 160 £32,000
Hume Street Improvements
New vinyl signage banners to existing
lampposts
Nr 3 £4,500
New painted cycle lane m2 300 £30,000
Allowance for paint treatment to
existing walls - railway bridge area
m2 120 £9,000
Extra over above for wayfinding
graphics
Item 1 £2,000
New lighting to underside of railway
bridge
m2 160 £32,000
Asbestos Memorial Improvements
New Raised Planters with semi mature
trees to enclose and define space,
complete with wayfinding information
Nr 2 £110,000
New Decorative Mural to existing wall m2 150 £15,000
New Metal Fencing complete with
decorative mesh panels
m2 40 £8,000
Agamemnon Street Improvements
New vinyl signage banners to existing
lampposts
Nr 3 £4,500
New wayfinding totem signs Nr 4 £30,000
New painted cycle lane m2 440 £44,000
Canal Path Connector
New thermoplastic decorative paint
finish to be applied to surface of access
route, ramp and risers of stairs leading
to canal towpath
m2 400 £40,000
Canal Towpath Interventions
New wayfinding points - Allow for
bonded resin path insert (2mx2m)
m2 20 £7,000
New wayfinding points - Allow for
directional totem
Nr 5 £7,500
New wayfinding points - Allow for
coordinated bench
Nr 5 £10,000
New wayfinding points - Allow for cycle
stand at each location
Nr 5 £6,250
Client Confidential#
Dumbarton Road Interventions
New vinyl signage banners to existing
lampposts
Nr 10 £15,000
New wayfinding totem signs every
250m
Nr 5 £37,500
Parkhall
Allow for bonded resin pavement insert,
directional totem, coordinated bench /
planter
Nr 6 £45,000
Dalmuir
Allow for bonded resin pavement insert,
directional totem, coordinated bench /
planter
Nr 10 £75,000
Radnor Park
Allow for bonded resin pavement insert,
directional totem, coordinated bench /
planter
Nr 4 £30,000
Drumry
Allow for bonded resin pavement insert,
directional totem, coordinated bench /
planter
Nr 5 £37,500
Whitecrook
Allow for bonded resin pavement insert,
directional totem, coordinated bench /
planter
Nr 8 £60,000
£710,250
Add
Prelims @ 17.5% £124,294
Contingency @ 15% £125,182
£959,725
Design fees @ 20% £191,945
Consultancy costs to support discussions with SPT @ 5% £47,986
Inflation to assumed project midpoint of 3Q 2025 £38,343
Total £1,238,000
Basis of High Level Costs
1. Costs are high level estimates based on limited information currently available.
2. Threesixty Architecture Three Year Investment Plan Information sketches 1 to 4
3. Discussion on scope with Threesixty Architecture.
4. It is assumed the works at the various locations can be carried out in a single continuous phase.
5. It is assumed that power would be readily available at each location.
6. Assume no issues in relation to ownership / wayleaves etc.
7. Inflation is based on high level programme indicated by TTPM.
Exclusions From High Level Costs
1. General drainage or street lighting works.
2. Any work in connection with utility services or diversion of same.
3. Any work not stated or implied on drawings.
4. VAT on works or fees.
Client Confidential#
Dumbarton Road Interventions
New vinyl signage banners to existing
lampposts
Nr 10 £15,000
New wayfinding totem signs every
250m
Nr 5 £37,500
Parkhall
Allow for bonded resin pavement insert,
directional totem, coordinated bench /
planter
Nr 6 £45,000
Dalmuir
Allow for bonded resin pavement insert,
directional totem, coordinated bench /
planter
Nr 10 £75,000
Radnor Park
Allow for bonded resin pavement insert,
directional totem, coordinated bench /
planter
Nr 4 £30,000
Drumry
Allow for bonded resin pavement insert,
directional totem, coordinated bench /
planter
Nr 5 £37,500
Whitecrook
Allow for bonded resin pavement insert,
directional totem, coordinated bench /
planter
Nr 8 £60,000
£710,250
Add
Prelims @ 17.5% £124,294
Contingency @ 15% £125,182
£959,725
Design fees @ 20% £191,945
Inflation to assumed project midpoint of 3Q 2025 £38,330
Total £1,190,000
Basis of High Level Costs
1. Costs are high level estimates based on limited information currently available.
2. Threesixty Architecture Three Year Investment Plan Information sketches 1 to 4
3. Discussion on scope with Threesixty Architecture.
4. It is assumed the works at the various locations can be carried out in a single continuous phase.
5. It is assumed that power would be readily available at each location.
6. Assume no issues in relation to ownership / wayleaves etc.
7. Inflation is based on high level programme indicated by TTPM.
Exclusions From High Level Costs
1. General drainage or street lighting works.
2. Any work in connection with utility services or diversion of same.
3. Any work not stated or implied on drawings.
4. VAT on works or fees.
Client Confidential#
Dumbarton Road Interventions
New vinyl signage banners to existing
lampposts
Nr 10 £15,000
New wayfinding totem signs every
250m
Nr 5 £37,500
Parkhall
Allow for bonded resin pavement insert,
directional totem, coordinated bench /
planter
Nr 6 £45,000
Dalmuir
Allow for bonded resin pavement insert,
directional totem, coordinated bench /
planter
Nr 10 £75,000
Radnor Park
Allow for bonded resin pavement insert,
directional totem, coordinated bench /
planter
Nr 4 £30,000
Drumry
Allow for bonded resin pavement insert,
directional totem, coordinated bench /
planter
Nr 5 £37,500
Whitecrook
Allow for bonded resin pavement insert,
directional totem, coordinated bench /
planter
Nr 8 £60,000
£710,250
Add
Prelims @ 17.5% £124,294
Contingency @ 15% £125,182
£959,725
Design fees @ 20% £191,945
Inflation to assumed project midpoint of 3Q 2025 £38,330
Total £1,190,000
Basis of High Level Costs
1. Costs are high level estimates based on limited information currently available.
2. Threesixty Architecture Three Year Investment Plan Information sketches 1 to 4
3. Discussion on scope with Threesixty Architecture.
4. It is assumed the works at the various locations can be carried out in a single continuous phase.
5. It is assumed that power would be readily available at each location.
6. Assume no issues in relation to ownership / wayleaves etc.
7. Inflation is based on high level programme indicated by TTPM.
Exclusions From High Level Costs
1. General drainage or street lighting works.
2. Any work in connection with utility services or diversion of same.
3. Any work not stated or implied on drawings.
4. VAT on works or fees.
Note:
Additional budget may be required for the local making good of existing surface
finishes as a consequence of the proposed installation works

Page 46

Risk
1.   Interventions in remote/ poorly surveilled locations could
be subject to vandalism if not designed robustly and with
security in mind.
2.   Adaptions to roads / active travel routes clash with
ongoing council activity.
3.   Future maintenance of new interventions cannot be
funded.
4.   Power supplies not easily accessible for illuminated
totems or feature lighting and extensive diversions/ new
supplies may be required.
5.   Extensive repairs / making good required to existing
route surfaces to achieve consistent acceptable
standard.
Mitigation
Ensure robust design of any elements to minimise damage
from vandalism. The combined stategies of the Vision will
lead to more activity and passive surveillance.
Road service to be a member of the project group for any
elements that are footpath/road related.
Allow for revenue funding to permit maintenance for
duration of Ten Year Vision.
Utilities surveys of intervention locations to be undertaken at
earliest opportunity and proposals amended accordingly to
minimise cost / requirement for diversions.
Subsequent design stages to include detailed survey once
exact routes agreed and update budget / programme.
9190 Three Year Investment Plan Chosen Interventions
© Turner & Townsend Project Management. All rights reserved 21/08/2024. This document is expressly provided to and solely for the use of West Dumbartonshire Council and must not be quoted from, referred to,
used by or distributed to any other party without the prior consent of Turner & Townsend Project Management who accept no liability of whatsoever nature for any use by any other party.
Clydebank 3 year plan options
Programme
Notes:
Gantt Chart Ref: C:\Users\youngdav1\OneDrive - Turner & Townsend Group Limited\Desktop\Clydebank LTP\3 Year plan options\Programmes\Clydebank 3 year plan options.pp
Border Ref: C:\Users\youngdav1\OneDrive - Turner & Townsend Group Limited\Desktop\1. T&T MASTER Landscape.B
Programme No:01                             
Revision:   on date: 
Origin Date: 21/08/2024  page 1 of 1
Turner & Townsend Project Management
Clydebank 3 year plan options 
Programme
Originator: David Young
Checked by: David Crombie
Approved by:           
Clydebank 3 year plan options
making the difference  1
Line Name Duration Start Finish
2024 2025
September October November December January February March April May June July August September October NovemberA Dec
2 9 16 23 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
3 year plan options
Town centre trails
Assemble design team
Design period inc
surveys
Client approval
Utility diversions inc
procurement and works
Procurement
Construction inc
mobilisation
Completion
Three Queens Square
Assemble design team
Design period inc
surveys
Client approval
Planning
Landlord approval
Scottish Water approval
for new drainage
Procurement inc
containers
Construction inc
mobilisation
Completion
Canalside Activity
Centre
Assemble design team
Design period inc
surveys
Client approval
Planning
Building Warrant
Landlord approval/ AfL
Scottish Canals approval
Procurement
Construction inc
mobilisation and lift
procurement
Completion
Greenspace Option 1
Assemble design team
Design period inc
surveys
Client approval
Utility diversions inc
procurement and works
Planning
Procurement
Construction inc
mobilisation and lift
procurement
Completion
Greenspace Option 2
Assemble design team
Design period inc
surveys
Client approval
Utility diversions inc
procurement and works
Planning
Building Warrant for
skatepark and MUGA
Landlord approval for
car park alterations (not
inc land sale)
RCC for car park
alterations/ stopping up
Scottish Water approval
for new drainage
Procurement
Construction inc MUGA
and skatepark
procurement
Completion
Connecting
Communities - Queens
Quay, Golden Jubilee
and Wider Communities
Assemble design team
Design period inc
surveys
Client approval
Roads authority
approval for road
painting
Procurement
Construction
Completion
Meanwhile space - Basic
works
Assemble design team
Design period inc
surveys
Client approval
Planning/ advertisement
consent
Landlord approval/ AfL
Procurement
Construction
Completion
Meanwhile space -
Intensite strategy
Assemble design team
Design period inc
surveys
Client approval
Planning/ advertisement
consent
Building Warrant
Landlord approval/ AfL
Procurement
Construction
Completion
62w
40w
2w
6w
2w
20w
4w
12w
52w
2w
12w
2w
12w
8w
8w
20w
16w
48w
2w
12w
2w
12w
12w
8w
12w
12w
20w
42w
2w
8w
2w
20w
12w
16w
12w
62w
2w
16w
2w
20w
12w
12w
8w
12w
8w
16w
24w
38w
2w
10w
2w
8w
12w
12w
24w
2w
4w
2w
12w
8w
6w
6w
42w
2w
10w
2w
12w
12w
8w
12w
16w
02/09/2024
02/09/2024
02/09/2024
16/09/2024
28/10/2024
28/10/2024
11/11/2024
31/03/2025
27/06/2025
02/09/2024
02/09/2024
16/09/2024
09/12/2024
06/01/2025
06/01/2025
09/12/2024
06/01/2025
30/05/2025
22/09/2025
02/09/2024
02/09/2024
16/09/2024
09/12/2024
09/12/2024
09/12/2024
06/01/2025
09/12/2024
06/01/2025
31/03/2025
22/08/2025
02/09/2024
02/09/2024
16/09/2024
11/11/2024
11/11/2024
11/11/2024
25/11/2024
14/04/2025
11/07/2025
02/09/2024
02/09/2024
16/09/2024
20/01/2025
20/01/2025
20/01/2025
20/01/2025
03/02/2025
20/01/2025
20/01/2025
03/02/2025
13/06/2025
01/12/2025
02/09/2024
02/09/2024
16/09/2024
25/11/2024
25/11/2024
09/12/2024
17/03/2025
13/06/2025
02/09/2024
02/09/2024
16/09/2024
14/10/2024
14/10/2024
28/10/2024
28/10/2024
20/01/2025
03/03/2025
02/09/2024
02/09/2024
16/09/2024
25/11/2024
25/11/2024
25/11/2024
09/12/2024
09/12/2024
17/03/2025
11/07/2025
01/12/2025
27/06/2025
13/09/2024
25/10/2024
08/11/2024
28/03/2025
06/12/2024
26/06/2025
27/06/2025
22/09/2025
13/09/2024
06/12/2024
20/12/2024
28/03/2025
28/02/2025
14/02/2025
29/05/2025
19/09/2025
22/09/2025
22/08/2025
13/09/2024
06/12/2024
20/12/2024
14/03/2025
14/03/2025
28/02/2025
14/03/2025
28/03/2025
21/08/2025
22/08/2025
11/07/2025
13/09/2024
08/11/2024
22/11/2024
11/04/2025
14/02/2025
28/03/2025
10/07/2025
11/07/2025
01/12/2025
13/09/2024
17/01/2025
31/01/2025
12/06/2025
11/04/2025
11/04/2025
28/03/2025
11/04/2025
14/03/2025
29/05/2025
28/11/2025
01/12/2025
13/06/2025
13/09/2024
22/11/2024
06/12/2024
31/01/2025
14/03/2025
12/06/2025
13/06/2025
03/03/2025
13/09/2024
11/10/2024
25/10/2024
17/01/2025
20/12/2024
06/12/2024
28/02/2025
03/03/2025
11/07/2025
13/09/2024
22/11/2024
06/12/2024
28/02/2025
28/02/2025
14/02/2025
14/03/2025
10/07/2025
11/07/2025
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
Milestone Appearances
Start Milestone
© Turner & Townsend Project Management. All rights reserved 21/08/2024. This document is expressly provided to and solely for the use of West Dumbartonshire Council and must not be quoted from, referred to,
used by or distributed to any other party without the prior consent of Turner & Townsend Project Management who accept no liability of whatsoever nature for any use by any other party.
Clydebank 3 year plan options
Programme
Notes:
Gantt Chart Ref: C:\Users\youngdav1\OneDrive - Turner & Townsend Group Limited\Desktop\Clydebank LTP\3 Year plan options\Programmes\Clydebank 3 year plan options.pp
Border Ref: C:\Users\youngdav1\OneDrive - Turner & Townsend Group Limited\Desktop\1. T&T MASTER Landscape.B
Programme No:01                             
Revision:   on date: 
Origin Date: 21/08/2024  page 1 of 1
Turner & Townsend Project Management
Clydebank 3 year plan options 
Programme
Originator: David Young
Checked by: David Crombie
Approved by:           
Clydebank 3 year plan options
making the difference  1
Line Name Duration Start Finish
2024 2025
September October November December January February March April May June July August September October NovemberA Dec
2 9 16 23 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
3 year plan options
Town centre trails
Assemble design team
Design period inc
surveys
Client approval
Utility diversions inc
procurement and works
Procurement
Construction inc
mobilisation
Completion
Three Queens Square
Assemble design team
Design period inc
surveys
Client approval
Planning
Landlord approval
Scottish Water approval
for new drainage
Procurement inc
containers
Construction inc
mobilisation
Completion
Canalside Activity
Centre
Assemble design team
Design period inc
surveys
Client approval
Planning
Building Warrant
Landlord approval/ AfL
Scottish Canals approval
Procurement
Construction inc
mobilisation and lift
procurement
Completion
Greenspace Option 1
Assemble design team
Design period inc
surveys
Client approval
Utility diversions inc
procurement and works
Planning
Procurement
Construction inc
mobilisation and lift
procurement
Completion
Greenspace Option 2
Assemble design team
Design period inc
surveys
Client approval
Utility diversions inc
procurement and works
Planning
Building Warrant for
skatepark and MUGA
Landlord approval for
car park alterations (not
inc land sale)
RCC for car park
alterations/ stopping up
Scottish Water approval
for new drainage
Procurement
Construction inc MUGA
and skatepark
procurement
Completion
Connecting
Communities - Queens
Quay, Golden Jubilee
and Wider Communities
Assemble design team
Design period inc
surveys
Client approval
Roads authority
approval for road
painting
Procurement
Construction
Completion
Meanwhile space - Basic
works
Assemble design team
Design period inc
surveys
Client approval
Planning/ advertisement
consent
Landlord approval/ AfL
Procurement
Construction
Completion
Meanwhile space -
Intensite strategy
Assemble design team
Design period inc
surveys
Client approval
Planning/ advertisement
consent
Building Warrant
Landlord approval/ AfL
Procurement
Construction
Completion
62w
40w
2w
6w
2w
20w
4w
12w
52w
2w
12w
2w
12w
8w
8w
20w
16w
48w
2w
12w
2w
12w
12w
8w
12w
12w
20w
42w
2w
8w
2w
20w
12w
16w
12w
62w
2w
16w
2w
20w
12w
12w
8w
12w
8w
16w
24w
38w
2w
10w
2w
8w
12w
12w
24w
2w
4w
2w
12w
8w
6w
6w
42w
2w
10w
2w
12w
12w
8w
12w
16w
02/09/2024
02/09/2024
02/09/2024
16/09/2024
28/10/2024
28/10/2024
11/11/2024
31/03/2025
27/06/2025
02/09/2024
02/09/2024
16/09/2024
09/12/2024
06/01/2025
06/01/2025
09/12/2024
06/01/2025
30/05/2025
22/09/2025
02/09/2024
02/09/2024
16/09/2024
09/12/2024
09/12/2024
09/12/2024
06/01/2025
09/12/2024
06/01/2025
31/03/2025
22/08/2025
02/09/2024
02/09/2024
16/09/2024
11/11/2024
11/11/2024
11/11/2024
25/11/2024
14/04/2025
11/07/2025
02/09/2024
02/09/2024
16/09/2024
20/01/2025
20/01/2025
20/01/2025
20/01/2025
03/02/2025
20/01/2025
20/01/2025
03/02/2025
13/06/2025
01/12/2025
02/09/2024
02/09/2024
16/09/2024
25/11/2024
25/11/2024
09/12/2024
17/03/2025
13/06/2025
02/09/2024
02/09/2024
16/09/2024
14/10/2024
14/10/2024
28/10/2024
28/10/2024
20/01/2025
03/03/2025
02/09/2024
02/09/2024
16/09/2024
25/11/2024
25/11/2024
25/11/2024
09/12/2024
09/12/2024
17/03/2025
11/07/2025
01/12/2025
27/06/2025
13/09/2024
25/10/2024
08/11/2024
28/03/2025
06/12/2024
26/06/2025
27/06/2025
22/09/2025
13/09/2024
06/12/2024
20/12/2024
28/03/2025
28/02/2025
14/02/2025
29/05/2025
19/09/2025
22/09/2025
22/08/2025
13/09/2024
06/12/2024
20/12/2024
14/03/2025
14/03/2025
28/02/2025
14/03/2025
28/03/2025
21/08/2025
22/08/2025
11/07/2025
13/09/2024
08/11/2024
22/11/2024
11/04/2025
14/02/2025
28/03/2025
10/07/2025
11/07/2025
01/12/2025
13/09/2024
17/01/2025
31/01/2025
12/06/2025
11/04/2025
11/04/2025
28/03/2025
11/04/2025
14/03/2025
29/05/2025
28/11/2025
01/12/2025
13/06/2025
13/09/2024
22/11/2024
06/12/2024
31/01/2025
14/03/2025
12/06/2025
13/06/2025
03/03/2025
13/09/2024
11/10/2024
25/10/2024
17/01/2025
20/12/2024
06/12/2024
28/02/2025
03/03/2025
11/07/2025
13/09/2024
22/11/2024
06/12/2024
28/02/2025
28/02/2025
14/02/2025
14/03/2025
10/07/2025
11/07/2025
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
Milestone Appearances
Start Milestone
Preliminary Programme, Risk
and Approval Considerations
Potential Risks
Approval / Utility Considerations
Approval / Utility   Required (Yes / No)
Planning   N
Warrant   N
RCC   Y (New cycle lanes)
Utility Diversion / Supply  N
Landlord Approval   N
Other Approvals   N
The programme below demonstrates
that the interventions to key routes
described in this report could be
developed from this initial concept
and delivered in a 38 week period.
This is based on the following key stages:
Assemble Design Team:     2 weeks
Design Development (incl. surveys):   10 weeks
Planning, RCC for cycle lane components
and Procurement (mainly concurrent):   14 weeks
Construction (incl. mobilisation period):   12 weeks
Encourages active travel – Health and Well Being
Greater physical and emotional connection to town
centre and heritage – Shared Identity and Pride
Expected Outcomes
and Benefits

Page 47

9392 Three Year Investment Plan Chosen Interventions
Intervention Investment Theme
1
2a
2b
3
Summary of Priority Interventions
4
Town Centre
Walking and Cycling
Trails
Improving Three
Queens Square
Canalside Activity
Centre
A New Town Centre
Greenspace
Connecting
Communities &
Facilities
TRANSPORT
&
CONNECTIVITY
HIGH ST R EETS, H
E
R
ITAGE & REGENERATIO
N
HIGH ST R EETS, H
E
R
ITAGE & REGENERATIO
N
HIGH ST R EETS, H
E
R
ITAGE & REGENERATIO
N
HIGH ST R EETS, H
E
R
ITAGE & REGENERATIO
N
Programme
Revenue Funding 
Indicative Costs (Provided by WDC) Other
38 weeks
42-62 weeks
48 weeks
52-76 weeks
40 weeks
Subject to establishing scope
of making good works at
each intervention
Subject to establishing extent
of strengthening works
to council owned hard-
landscaped areas
For alterations / fit-out of unit
in Clyde Shopping Centre
option
Dependent on option chosen
Core Option A:
42 weeks
Expanded Option B:
62 weeks
£75,000 (£25,000 per annum)
Programmes and interventions to
support healthy habits, walking and
cycling.
£TBC (£tbc per annum)
Maintenance costs for the new
infrastructure, to be established in
subsequent development stages.
£150,000 (£50,000 per annum)
Events and other interventions to bring
activity to 3 Queens Square
£TBC (£tbc per annum)
Maintenance costs for the new
infrastructure, to be established in
subsequent development stages.
£420,000 (£140,000 per annum)
Indicative budget to support running
of the Activity Centre for up to 3
years.
It is expected that the Centre would
become self sufficient in Year 4 and/
or secure external funding.
£TBC (£tbc per annum)
Maintenance costs for the new
infrastructure, to be established in
subsequent development stages.
Maintanance costs to be secured for
the duration of the fund (10 years)
£TBC (£tbc per annum)
Maintenance costs for the new
infrastructure, to be established in
subsequent development stages.
Maintanance costs to be secured for
the duration of the fund (10 years)
Develop detailed design in collaboration with
proposed CCTV roll-out
In later design stages, co-ordinate with
proposed CCTV roll-out and existing lighting
and maintence, identify any shortfall, establish
responsibility and adjust capital and revenue
budget accordingly
£1.3 million (majority secured from RCFG, for
stand alone option)
Option B dependent on collaboration with
existing shopping centre owners and wider
agreement to commute identified area of parking
to community facilities
Subsequent design stages to include detailed
survey once exact routes agreed and update
budget / programme
£993,600
Option 1:  £1,524,600
Option 2:  £1,824,273
Option 1:  £0
Option 2:  £0
Capital funding secured
from other sources, subject
to approval by Scottish
Government.
Core Option A:
£1,232,700
Expanded Option B:
£2,341,600
£1,238,000
Capital Funding
High Level Cost Estimate
1
2

Page 48

www.360architecture.com