Appendix 1: Resources Delivery Plan 2024/25 – Asset Management Mid-year Progress
1. Our Communities
Our residents are supported to increase life and learning skills
Action Status Progress Due Date Note Owner
Progress the redevelopment of
Glencairn House
31-Mar-
2025
Progressing as planned. Project currently on
programme to be delivered on the contractual
completion date.  Handover of the refurbished facility
will take place April 2025.
Michelle Lynn
2. Our Environment
Our neighbourhoods are sustainable and attractive
Action Status Progress Due Date Note Owner
Progress the building upgrades
programme
31-Mar-
2025
Progressing as planned. A number of projects are
complete as per programme. The progress of the
building upgrades programme is reflected in the
performance of the associated PIs including the
proportion of operational buildings that are suitable for
their current use, the proportion of internal floor area of
operational buildings in satisfactory condition, and the
percentage of council buildings in which all public
areas are suitable for and accessible to people with a
disability, all of which met or exceeded targets at year-
end 2023/24. We also continue to perform favourably
against other local authorities.
Michelle Lynn
ITEM 9 -
APPENDIX 1

Page 2

4. Our Council
Our Council is adaptable and focused on delivering best value for our residents
Action Status Progress Due Date Note Owner
Progress the disposal of key
strategic sites
31-Mar-
2025
Progressing as planned. Capital receipts on
programme to deliver anticipated income. Michelle Lynn
Progress the depot refurbishment
programme
31-Mar-
2025
Progressing as planned. Consultants engaged in
relation to new build garage design, project board has
been reconvened, and amended scope has
commenced with service areas.
Michelle Lynn
Develop and implement plans and
support services to achieve the
asset related options agreed by
Council
31-Mar-
2025
Progressing as planned with all actions on target to
assist deliver of savings across a number of service
areas.
Michelle Lynn
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Maintaining
Council Assets
that are fit for
purpose
The risk that the Council's
assets and facilities are not fully
fit for purpose with consequent
adverse impact on our ability to
deliver efficient and effective
services. Assets included in this
assessment are the Council’s
property portfolio.
19-Sep-
2024
The risk score remains low due
to the ongoing capital
programme of works on
operational buildings.
Michelle Lynn
Action Status Risk Status
In progress and on track OK