Appendix 1: Regulatory & Regeneration Delivery Plan 2024/25 - Economic Development Mid-year Progress
2. Our Environment
Our resources are used in an environmentally sustainable way
Action Status Progress Due Date Note Owner
Co-ordinate, monitor and report
the progress of the Council’s
Climate Change Action Plan for
2024/25
31-Mar-
2025
Progressing as planned. A detailed delivery plan for
2024/25 has now been added to our performance
management system, setting out actions and milestones.
Delivery of this plan is monitored on an ongoing basis
and formally on a quarterly basis by the Climate Change
Action Group.
Rachel Moir
Develop a Local Heat and Energy
Efficiency Strategy and Delivery
Plan
31-Mar-
2025
Progressing as planned. Public consultation on the draft
strategy closed in June 2024. The strategy, with outline
delivery plan, was published at the end of September
2024. Work is ongoing to develop a detailed delivery
plan, with publication due March 2025.
Rachel Moir
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Inability to
reduce
carbon
footprint in
line with
targets
The risk that the Council will be unable to achieve
net zero emissions by 2045, both in relation to
mitigating carbon emissions and adapting to the
impacts of climate change. Net zero refers to
achieving an overall balance between emissions
produced and emissions taken out of the
atmosphere. This target has been developed in a
way that mirrors the emission reduction trajectory
set by the Scottish Government in light of the
Climate Emergency.
26-Sep-
2024
The risk of non-delivery of
carbon emissions targets
remains moderate. Progress is
being made through the
delivery of the Climate Change
Action Plan. However, pace of
delivery has been, and will
continue to be, impeded due to
a lack of internal resource and
additional funding to deliver.
Gillian
McNamara
ITEM 7 -
APPENDIX 1

Page 2

Our neighbourhoods are sustainable and attractive
Action Status Progress Due Date Note Owner
Promote the next phase of Queens
Quay Housing
31-Mar-
2025
Under the terms of the Joint Venture agreement, the
owner and agent of Queens Quay are responsible for the
commercial discussions on future housing development.
The Council meets with the owner and agent regularly to
review progress. There is some frustration, and also
some valid reasons, for lack of progress but options to
accelerate progress are being considered.
Alan
Douglas;
Gillian
McNamara
3. Our Economy
Our area has the infrastructure for sustainable and inclusive growth where businesses can flourish
Q1 2024/25 Q2 2024/25
Performance Indicator Status Value Target Short
Trend
Long
Trend Status Value Target Short
Trend
Long
Trend Note Owner
Number of businesses
given advice and
assistance to start up
through Business
Gateway
47 45 56 45
Both Q1 and Q2
targets exceeded and
on track to meet year-
end target.
Gillian Scholes
Action Status Progress Due Date Note Owner
Implement, monitor and report the
progress of the 2024/25 Economic
Development Action Plan
31-Mar-
2025
Progressing as planned. The Action Plan, which relates
to the Economic Development Strategy 2022-27 and
provides the annual direction for the Regeneration and
Business Support teams, is progressing as planned.
Gillian
McNamara

Page 3

Action Status Progress Due Date Note Owner
Deliver key regeneration sites
across West Dunbartonshire
31-Mar-
2025
Progressing as planned. Key regeneration sites across
the Council area include the three town centres, and the
strategic sites of Queens Quay, Exxon and the Carless
site. Milestones relating to the Scottish Marine
Technology Park, Exxon Infrastructure Project and our
three town centres are progressing as planned and due
for completion in the second half of the year.
Gillian
McNamara
Explore commercial opportunities
in our town centres and wider
regeneration sites
31-Mar-
2025
Completed. Artizan masterplan planning application was
submitted in July. The Long Term Plan and the
accompanying 3 Year Investment Plan have been mostly
completed and reviewed by the Town Board. Some final
edits remain before the plans are submitted to the UK
Government in October/November.
Magda
Swider
Develop and implement business
support interventions through the
UK Shared Prosperity Fund
31-Mar-
2025
Progressing as planned. UK Shared Prosperity Fund
interventions have been developed and widely promoted
through the Council website, social media, partner
organisations and directly to eligible businesses. The
Business Support team are continuing to promote the
grant support and appraise applications.
Gillian
Scholes
Support town centre revitalisation 31-Mar-
2025 Progressing as planned with projects on track. Magda
Swider

Page 4

Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Failure to
deliver Queens
Quay
Masterplan
Following completion of Council
investment there is a risk the housing
plot sales do not materialise in the
next 3-7 years, with implications for
the return on investment and the
business case for the District Heating
Network.
20-Sep-
2024
Risk remains unchanged. Focus
continues on landowner agreeing
a housing proposal with the
developer. Delivery embedded
into planning workstreams to
promote development at site.
Gillian
McNamara;
Michael
Mulgrew
Inability to meet
demands of
Council to
progress
regeneration
projects within
desired
timescales
The number and complexity of
regeneration projects is putting
considerable strain on the resources
available which can be exacerbated
by delays out with the control of the
service and when pinch points on
different projects occur at roughly the
same time.
20-Sep-
2024
Risk remains unchanged.
Individual projects continue to
progress, reducing the likelihood
of undesirable outcomes.
Embedded into planning
workstreams to ensure sufficient
resource to support delivery of
projects within required
timescales.
Michael
McDougall;
Gillian
McNamara;
Michael
Mulgrew
Action Status
In Progress and on track
Completed
PI Status
Target met or exceeded
Risk Status
Warning
OK
Long Term Trends
Improving
Declining
Short Term Trends
Improving
Declining