All Approved Projects at Period 3 - 30 June 2024
Service Project
Initial End
Date
Revised End
Date
Project Life
Budget
Spend to
31 /3/24 Spend to
Date
Projected
Future
Spend
Total
Projected
Spend
Project
Variance Approved
Budget
2024/25
Actual to
date
2024/25
Revised
Forecast
2024/25 
In Year
Variance 
£'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000
RES 9 Strathleven Place (formerly part of Glencairn House project) 31/03/2025 1,590 -                -   1,590                  1,590 -   1,540         - 1,590         50
RES 10
New Sports Changing Facility Dumbarton West (Old OLSP
site)  31/03/2025 349 9 9 340 349 -   340 - 340 -
RES 11
Building Upgrades and H&S - lifecycle & reactive building
upgrades 31/03/2033 25,370         - 305 25,065          25,370 -   2,791         305 3,122         331
RES 13 Depot Rationalisation 31/03/2024 8,500 649 831 7,669                  8,500 -   500 182 262 (238)
Total Resources 35,810         658 1,145         34,665        35,810     - 5,171         487 5,314         143
RR 3 Installation of Solar PV at Clydebank Leisure Centre 31/03/2023 31/03/2025 61 4 4 57 61 -   - - 57 57
RR 4 Replace failed heating controls/valves & recommission 31/03/2023 31/03/2025 20 14 14 6 20 -   - - 6 6
RR 5
Leisure Energy projects - air handling units, upgrade lighting,
circulating pumps, and draught proofing 31/03/2023 31/03/2025 290 64 64 226 290 -   226 - 226 -
RR 6 Regeneration/Local Economic Development 31/03/2033 7,922 5,991        6,043 1,879                  7,922 -   1,100         52 1,100         -
RR 7 Regeneration Fund 31/03/2028 10,931         7,107        7,144 3,787            10,931 -   350 37 615 265
RR 8 Place Based Investment 31/03/2027 2,650 1,398        1,400 526         1,926 (723) 310 3 529 219
RR 9 Clydebank Can on the Canal 31/12/2022 31/12/2025 757 40 40 757 757 -   757 - 757 -
RR 10 Level Up Funding 31/03/2025 31/03/2026 22,100         7,553        8,542 13,558          22,100 -   11,959       989 11,959       -
RR 11 Level Up Capacity Funding 31/03/2025 31/03/2026 320 161 161 159 320 -   161 - 161 -
RR 12 District Heating Network Expansion 31/03/2024 31/03/2028 11,104         40- 141 10,963          11,104 -   2,500         182 1,500         (1,000)
RR 13 Clyde Mission Catalyst Fund 31/03/2024 31/03/2026 2,000 415 415 1,585                  2,000 1,197         - 1,197         -
Total Regulatory and Regeneration 58,154         22,706      23,968       33,503        57,431     (723) 18,560       1,262        18,107       (453)
R&N 1 Infrastructure - Roads 31/03/2033 22,806         -                -   22,806          22,806 -   2,544         - 2,454         (90)
R&N 2 Flood Risk Management 31/03/2033 2,315 -                -   2,315                  2,315 -   500 - 500 -
R&N 3 Street lighting and associated electrical infrastructure 31/03/2033 914 - 13 901 914 -   100 13 114 14
R&N 4 Flood Prevention 31/03/2033 500 160 180 320 500 - 0 150 20 339 189
R&N 5 Vehicle Replacement 31/03/2033 12,219         - 27 12,192          12,219 -   3,000         27 2,865         (135)
R&N 6 Auld Street Clydebank - Bond 31/03/2019 31/03/2025 256 214 214 42 256 -   - - 42 42
R&N 7 River Bank Erosion Repair - Levenhowe 31/03/2024 31/03/2025 20 -                -   20 20 -   - - 20 20
R&N 8 Clydebank Charrette, A814 31/03/2022 4,300 4,215        4,215 85         4,300 -   88 - 88 -
R&N 9 Roads Plant 31/03/2023 31/03/2025 80 14 14 66 80 -   - - 66 66
R&N 10 A813 Road Improvement Phase 1 31/03/2026 31/03/2025 1,700 1,057        1,366 334         1,700 -   493 309 643 150
R&N 11 Pavement Improvements 31/03/2024 31/03/2025 1,000 958 958 42         1,000 -   - - 42 42
R&N 12 Traffic Signal Updates 31/03/2023 31/03/2025 300 274 274 26 300 -   - - 26 26
R&N 13 Gruggies Burn Flood Prevention 31/03/2022 31/03/2028 15,028         576 696 14,332          15,028 -   7,270         120 550 (6,720)
R&N 14 Electrical Charging Points - Rapid Charge 31/03/2026 31/03/2025 314 299 299 15 314 -   - - 15 15
R&N 15 River Leven Flood Prevention Scheme 31/03/2025 31/03/2026 801 181 181 620 801 -   - - - -
R&N 16 Vehicle Replacement Strategy 31/03/2033 900 -                -   900 900 -   900 - 1,400         500
R&N 17
Posties Park Sports Hub - New sports hub to include Gym &
running track 31/03/2021 31/03/2027 6,021 5,878        6,008 13         6,021 -   143 130 143 -
R&N 18 Public non-adopted paths and roads 31/03/2033 2,419 -                -   2,419                  2,419 -   225 - 619 394
R&N 19 Cemetery Extension, North Dalnotter 31/03/2025 264 14 14 250 264 -   250 - 250 -
R&N 20 Vale of Leven Cemetery 31/03/2025 31/03/2025 817 741 760 40 801 (16) - 19 60 60
R&N 21 Allotment Development 31/03/2022 492 215 341 151 492 -   186 126 150 (36)
Full Project Life In Year
ITEM 9 -
APPENDIX 4

Page 2

Service Project
Initial End
Date
Revised End
Date
Project Life
Budget
Spend to
31 /3/24 Spend to
Date
Projected
Future
Spend
Total
Projected
Spend
Project
Variance Approved
Budget
2024/25
Actual to
date
2024/25
Revised
Forecast
2024/25 
In Year
Variance
Full Project Life In Year
R&N 22 Waste Transfer Station 31/03/2025 31/03/2026 1,980           -                           41 1,939                  1,980                -   1,780         41             200            (1,580)
R&N 23 Play Area Upgrade Programme 31/03/2033 1,399           149                        282 1,117                  1,399                -   449            133           417            (32)
R&N 24 Nature Restoration Fund 31/03/2024 31/03/2025 608              574                        608 0                            608                -   34              34             34              0                     
R&N 25 Whitecrook Tennis Court 31/03/2024 59                44                            44 15                            59                -   -            -            15              15                   
R&N 26 East End Park Resurfacing 03/04/2021 31/03/2025 385              6                                6 379                        385                -   385            -            379            (6)
R&N 27 Park Improvements and Multi Games Area - Goldenhill Park 31/03/2025 31/03/2025 150              -                           -   150                        150                -   -            -            150            150                 
R&N 28 Balloch Mountain Bike Track 31/03/2024 30/09/2024 600              -                           -   600                        600                -   590            -            600            10                   
R&N 29 Pappert 2G Pitch 31/03/2025 250              8                                8 242                        250                -   230            -            242            12                   
R&N 30 Kilmaronock Cemetery Extension 31/03/2024 31/03/2025 50                45                            45 5                              50                -   -            -            13              13                   
R&N 31 Exxon City Deal 31/03/2028 44,325         6,235                  7,424 36,901              44,325                -   9,845         1,188        2,500         (7,345)
R&N 32 Cycling Walking & Safer Streets 31/03/2025 389              -                           15 374                        389 389            15             389            0
Total Roads and Neighbourhood 123,662       21,859      24,034       99,611        123,645   (17) 29,551       2,175        15,323       (14,228)
Total IRED 217,626       45,222      49,147       167,779      216,886   (740) 53,282 3,924 38,744 (14,538)
Note: Due to previous approvals there are some projects with revised end dates that are not off track at period.