Projects that are Off Track as at Period 3 - 30 June 2024
ITEM 9 -
APPENDIX 2
Service Project
Approved
Project Life
Cost
Revised
Project
Life Cost Project Life Variance
Initial
Completion
Date
Revised
Completion
Date
£'000 £'000 £'000
RR3 Installation of Solar PV at Clydebank Leisure Centre 61 61 0 31/03/2023 31/03/2025
RR4 Replace failed heating controls/valves & recommission 20 20 0 31/03/2023 31/03/2025
RR11 Levelling Up Capacity 320          320 0 31/03/2025 31/03/2026
R&N6 Auld Street Clydebank - Bond 256          256 0 31/03/2019 31/03/2025
R&N7 River Bank Erosion Repair - Levenhowe 801          801 0 31/03/2024 31/03/2025
R&N11 Pavement Improvements 1,000   1,000 0 31/03/2024 31/03/2025
R&N22 Waste Transfer Station 1,980   1,980 0 31/03/2025 31/03/2026
R&N27 Park Improvements and Multi Games Area - Goldenhill Park 150          150 0 31/03/2025 31/03/2025
R&N30 Kilmaronock Cemetery Expansion 50 50 0 31/03/2024 31/03/2025
Project Name: Installation of Solar PV at Clydebank Leisure Centre
Initial End Date: 31/3/23 Revised End Date: 31/3/25
How was this project initially funded: Prudential Borrowing Please Detail any additional funding
Why is the project classified as off track and what has caused the issues identified?
The project has been delayed due to resourcing issues. Resources redirected to District Heating Network in the absence of District Heating Project Lead.
What action will be taken to rectify the position?
Additional Funding Requested:  £0
New Completion Date:31/3/25
What are the implications on the actions proposed?
Revenue Implications
Virement Implications
Project Name: Replace failed heating controls/valves & recommission - Original
Initial End Date: 31/3/23 Revised End Date: 31/3/25
How was this project initially funded: Prudential Borrowing Please Detail any additional funding
Why is the project classified as off track and what has caused the issues identified?
The project has been delayed due to resourcing issues. Resources redirected to District Heating Network in the absence of District Heating Project Lead.
What action will be taken to rectify the position?
Additional Funding Requested:  £0
New Completion Date:31/3/25
What are the implications on the actions proposed?
Revenue Implications
Virement Implications
Project Name: Levelling Up Capacity
Initial End Date: 31/3/25 Revised End Date: 31/3/26
How was this project initially funded: SG funded Please Detail any additional funding
N/A
Why is the project classified as off track and what has caused the issues identified?
The funding has been realigned to match the Level Up Funding project
What action will be taken to rectify the position?
Additional Funding Requested:  £0
New Completion Date:31/3/26
What are the implications on the actions proposed?
Revenue Implications
Virement Implications
Project Name: Auld Street Clydebank - Bond
Initial End Date: 31/3/24 Revised End Date: 31/3/25
How was this project initially funded: Funded via road bond provided by Developer Please Detail any additional funding
Why is the project classified as off track and what has caused the issues identified?
What action will be taken to rectify the position?
Additional Funding Requested:  £0
New Completion Date:31/3/25
What are the implications on the actions proposed?
Revenue Implications
Virement Implications
Project Name: River bank erosion repair - Levenhowe
Initial End Date: 31/3/24 Revised End Date:31/3/25
How was this project initially funded: Capital Investment Please Detail any additional funding
Why is the project classified as off track and what has caused the issues identified?
What action will be taken to rectify the position?
Additional Funding Requested:  £0
New Completion Date:
What are the implications on the actions proposed?
Revenue Implications
Virement Implications
Chief Officer RNT
Chief Officer RNT
Initial road bond was used to complete the drainage and street lighting installations as well as road construction. Remaining funding was not enough to complete the
installation of remote footway. Additional funding now available through Jubilee developer contributions to complete.
Source of Funding
N/A
Some river bank repair was undertaken through existing capital budget for Levenhowe however, delayed whilst survey and recommendations report undertaken.
Works identified for progress 24/25 and await outcome of SEPA approval
Source of Funding
Chief Officer Regulatory and Regeneration
Source of Funding
Chief Officer Regulatory and Regeneration
Source of Funding
Chief Officer Regulatory and Regeneration
Source of Funding

Page 2

Project Name: Pavement Improvements
Initial End Date: 31/3/2024 Initial End Date: 31/3/2025
How was this project initially funded: Prudential Borrowing Please Detail any additional funding
N/A
Why is the project classified as off track and what has caused the issues identified?
Projects are complete however this budget is required for retentions due to be paid in 24/25.
What action will be taken to rectify the position?
Additional Funding Requested:  £0
New Completion Date:31/3/25
What are the implications on the actions proposed?
Revenue Implications
Virement Implications
Project Name: Waste Transfer Station
Initial End Date: 31/3/25 Revised End Date: 31/3/26
How was this project initially funded: Prudential Borrowing Please Detail any additional funding
N/A
Why is the project classified as off track and what has caused the issues identified?
Project has been delayed as it has inter-dependencies with the wider depots/office rationalisation projects
What action will be taken to rectify the position?
Additional Funding Requested:  £0
New Completion Date:31/3/26
What are the implications on the actions proposed?
Revenue Implications
Virement Implications
Project Name: Park Improvements and Multi Games Area - Goldenhill Park - Original
Initial End Date: 31/3/24 Revised End Date: 31/3/25
How was this project initially funded: Please Detail any additional funding
Why is the project classified as off track and what has caused the issues identified?
Project delayed due to longer than anticipated lead times for MUGA materials
What action will be taken to rectify the position?
Additional Funding Requested:  £0
New Completion Date:31/3/25
What are the implications on the actions proposed?
Revenue Implications
Virement Implications
Project Name: Kilmaronock Cemetery Expansion
Initial End Date: 31/3/24 Revised End Date: 31/3/25
How was this project initially funded: Prudential Borrowing Please Detail any additional funding
N/A
Why is the project classified as off track and what has caused the issues identified?
Unable to deliver project as originally planned due to unforeseen adverse ground conditions.
What action will be taken to rectify the position?
Additional Funding Requested:  £0
New Completion Date:31/3/25
What are the implications on the actions proposed?
Revenue Implications
Virement Implications
Chief Officer RNT
Source of Funding
Source of Funding
Chief Officer RNT
N/A
Source of Funding
Source of Funding
Chief Officer RNT
Chief Officer RNT