Democracy Spraffa

Document Pack (Bookmarked) IRED 14 08 24

West Dunbartonshire Council · 14 August 2024
Back to Infrastructure, Regeneration & Economic Development Committee — 14 August 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Agenda
Infrastructure, Regeneration and
Economic Development Committee
Date:  Wednesday, 14 August 2024
___________________________________________________________________
Time:  10:00 
___________________________________________________________________
Format:  Hybrid meeting
___________________________________________________________________
Contact:  Nicola Moorcroft, Committee Officer
nicola.moorcroft@west-dunbarton.gov.uk
committee.admin@west-dunbarton.gov.uk
Dear Member
Please attend a meeting of the Infrastructure, Regeneration and Economic
Development Committee as detailed above. 
Members will have the option to attend the meeting remotely, or in person, at the Civic
Space, 16 Church Street, Dumbarton, G82 1QL.
The business is shown on the attached agenda.
Yours faithfully
PETER HESSETT
Chief Executive
Page 1

Page 2

Distribution:-
Councillor David McBride (Chair)
Councillor Jonathan McColl
Councillor Michelle McGinty
Councillor John Millar 
Councillor Lawrence O’Neill (Vice Chair)
Councillor Lauren Oxley
Councillor Chris Pollock
Councillor Martin Rooney
Councillor Gordon Scanlan
Councillor Hazel Sorrell
Councillor Clare Steel
Councillor Sophie Traynor
All other Councillors for information
Chief Executive
Chief Officer – Regulatory and Regeneration
Chief Officer – Roads and Neighbourhood
Chief Officer – Resources
Date of Issue: 1 August 2024
Audio Streaming
Audio recordings of the meeting (including the attendance or contribution of any party
participating or making a contribution) will be published on the Council’s website and the
Council’s host’s webcast/audio stream platform.
You should be aware that the Council is a Data Controller under the General Data
Protection Regulation.  Data collected during this audio stream will be retained in
accordance with the Council’s Privacy Notice* and Retention Schedules including, but not
limited to, for the purpose of keeping historical records and making those records available
via the Council’s internet site.
*http://www.west-dunbarton.gov.uk/privacy/privacy-notice/
Page 2

Page 3

INFRASTRUCTURE, REGENERATION AND ECONOMIC
DEVELOPMENT COMMITTEE
WEDNESDAY, 14 AUGUST 2024
AGENDA
1 STATEMENT BY CHAIR – AUDIO STREAMING
The Chair will be heard in connection with the above.
2 APOLOGIES
3 DECLARATIONS OF INTEREST
Members are invited to declare if they have an interest in any of the items of
business on this agenda and the reasons for such declarations.
4 RECORDING OF VOTES
The Committee is asked to agree that all votes taken during the meeting be done by
roll call vote to ensure an accurate record.
5 OPEN FORUM
The Committee is asked to note that no open forum questions have been
submitted by members of the public.
6 MINUTES OF PREVIOUS MEETINGS 5 - 11
Submit for approval as a correct record, the Minutes of the Meeting of the
Infrastructure, Regeneration and Economic Development Committee held on 22 May
2024
7 ALEXANDRIA BUSINESS IMPROVEMENT DISTRICT 13 - 25
Submit report by the Chief Officer – Regulation and Regeneration providing
information on the proposed Business Improvement District (BID) in Alexandria and
seeking authorisation to formally approve the BID Proposal.
Page 3

Page 4

8 INFRASTRUCTURE, REGENERATION AND ECONOMIC    27 - 38
DEVELOPMENT REVENUE MONITORING REPORT 2024/25
TO PERIOD 3 (30 JUNE 2024)
Submit report by the Chief Officer – Resources providing an update on the capital
financial performance to 30 June 2024 of those services under the auspices of the
Infrastructure, Regeneration and Economic Development Committee (IRED).
9 INFRASTRUCTURE, REGENERATION AND ECONOMIC  39 - 53  
DEVELOPMENT CAPITAL MONITORING REPORT 2024/25
TO PERIOD 3 (30 JUNE 2024)
Submit report by the Chief Officer – Resources providing and update on the revenue
financial performance to 30 June 2024 of those services under the auspices of the
Infrastructure, Regeneration an Economic Development Committee (IRED).
Page 4

Page 5

INFRASTRUCTURE, REGENERATION AND ECONOMIC DEVELOPMENT
COMMITTEE
At a Hybrid Meeting of the Infrastructure, Regeneration and Economic Development
Committee held in the Civic Space, 16 Church Street, Dumbarton on Wednesday, 
22 May 2024 at 10.00 a.m.
Present: Councillors David McBride, Jonathan McColl, Michelle McGinty,
John Millar, Lawrence O’Neill, Lauren Oxley, Chris Pollock,
Martin Rooney and Sophie Traynor.
Attending: Gail Macfarlane, Chief Officer – Roads and Neighbourhood;
Laurence Slavin, Chief Officer – Resources; Alan Douglas, Chief
Officer – Regulatory and Regeneration; Craig Jardine,
Corporate Asset Manager; Michelle Lynn, Assets Coordinator;
Gillian McNamara, Economic Development Manager; Liam
Greene, Roads and Transportation Manager; Michael
McDougall, Manager of Legal Services and Nicola Moorcroft
and Lauren Simeon, Committee Officers.
Apologies: Apologies for absence were intimated on behalf of Councillors
Gordon Scanlan, Hazel Sorrell and Clare Steel.
Councillor David McBride in the Chair
STATEMENT BY CHAIR – AUDIO STREAMING
Councillor David McBride, Chair, advised that the meeting was being audio streamed
and broadcast live to the internet and would be available for playback.
DECLARATIONS OF INTEREST
It was noted that there were no declarations of interest in any of the items of
business on the agenda.
RECORDING OF VOTES
The Committee agreed that all votes taken during the meeting be done by roll call
vote to ensure an accurate record.
ITEM 6
Page 5

Page 6

OPEN FORUM 
The Committee noted that no open forum questions had been submitted by
members of the public. 
MINUTES OF PREVIOUS MEETINGS 
The Minutes of Meetings of the Infrastructure, Regeneration and Economic
Development Committee held on 7 February 2024 (Ordinary) and 21 February 2024
(Special) were submitted and approved as correct records. 
ROADS AND NEIGHBOURHOOD 2023/24 DELIVERY PLAN YEAR-END REPORT
AND ROADS AND NEIGHBOURHOOD 2024/25 DELIVERY PLAN 
A report was submitted by the Chief Officer – Roads and Neighbourhood setting out
the year-end progress of the 2023/24 Delivery Plan and presenting the new Delivery
Plan for 2024/25. 
After discussion and having heard the Chief Officer – Roads and Neighbourhood, the
Chief Officer – Resources and the Corporate Asset Manager in further explanation
and in answer to Members’ questions, the Committee agreed to note the progress
achieved at year-end and the new plan for 2024/25. 
REGULATORY AND REGENERATION DELIVERY PLAN 2023/24 - ECONOMIC
DEVELOPMENT YEAR-END PROGRESS & REGULATORY AND
REGENERATION DELIVERY PLAN 2024/25 - ECONOMIC DEVELOPMENT 
A report was submitted by the Chief Officer – Regulatory and Regeneration setting
out the year-end progress of the 2023/24 Delivery Plan and presenting the new
Delivery Plan for 2024/25 in relation to Economic Development. 
After discussion and having heard the Chief Officer – Regulatory and Regeneration
and the Economic Development Manager, in further explanation and in answer to
Members’ questions, the Committee agreed to note the progress achieved at year-
end and the new Plan for 2024/245. 
RESOURCES DELIVERY PLAN 2023/24 YEAR-END PROGRESS (ASSET
MANAGEMENT) AND RESOURCES DELIVERY PLAN 2024/25 (ASSET
MANAGEMENT) 
A report was submitted by the Chief Officer – Resources providing setting out the
year-end progress of the 2023/24 Delivery Plan and presenting the new Delivery
Plan for 2024/25 in relation to Asset Management. 
Page 6

Page 7

The Chief Officer – Resources explained that the Finance element of the Resources
Delivery Plan 2024/25 (Asset Management) had been omitted from the report and
that would be updated and included in the Delivery Plan for 2024/25 when presented
at future meetings of this Committee. 
After discussion and having heard the Chief Officer – Resources in further
explanation and in answer to Members’ questions, the Committee agreed to note the
progress achieved at year-end and the new Plan for 2024/245. 
PROTOCOL FOR ROAD WORKS ON TRAFFIC SENSITIVE ROADS 
A report was submitted by the Chief Officer – Roads and Neighbourhood providing
the procedures and protocols that Officers will follow in regard to management of
road works on traffic sensitive roads. 
After discussion and having heard the Chief Officer – Roads and Neighbourhood the
Roads and the Transportation Manager in further explanation and in answer to
Members’ questions, the Committee agreed:- 
(1) to note the duty of the Roads Authority and the responsibilities of those
undertaking works on the road network as set out within the report; 
(2) to approve, with amendments suggested by Members, namely; that clear a
explanation as to the extent of the Protocol (roads, public footpaths and
verges) and information as to how a member of the public reports non-
compliance with the protocol, be included, the protocols set out in the Protocol
for the Management and Coordination of Road Works on Traffic Sensitive
Roads (Appendix A to the report); and 
(3) to note that the Roads Authority will engage with all Statutory Undertakers
and Stakeholders to make them aware of the requirements set out within the
protocol. 
GLASGOW CITY REGION: ELECTRIC VEHICLE CHARGING INFRASTRUCTURE
COLLABORATION 
A report was submitted by the Chief Officer – Roads and Neighbourhood providing
an update on work undertaken to develop a collaborative approach to expanding the
public electric vehicle charging infrastructure network, across the eight local
authorities of Glasgow City Region and seeking approval for the next steps required
to progress towards a commercial delivery arrangement. 
After discussion and having heard the Roads and Transportation Manager in further
explanation and in answer to Members’ questions Councillor McBride moved:- 
(1) to note the content of the report and the collaborative work undertaken to
date;
Page 7

Page 8

(2) to note the content of the West Dunbartonshire Public Electric Vehicle
Charging Strategy and Expansion Plan (Appendix 1 to the report) and the
forecast number of required charging units and cost of installation; 
(3) to approve the participation of West Dunbartonshire Council in a collaborative
procurement, to engage a commercial partner via a concession type contract,
through a partnership with all eight local authorities in Glasgow City Region, to
deliver the benefits set out in the report; 
(4) in principle to enter into an Inter-Authority Agreement among the eight local
authorities, and delegate the subsequent nomination of a lead authority for the
service delivery period as well as procurement and commercial decisions,
relating to the commencement and conclusion of the procurement process to
the Chief Officer – Regulatory and Regeneration, in line with the approach set
out in the report; 
(5) that Glasgow City Region Programme Management Office, through Glasgow
City Council, will utilise local authorities Electric Vehicle Infrastructure Fund
external grant allocations, to engage programme management and expert
technical consultancy support, that will assist in taking a Glasgow City Region
proposition to market and subsequent appointment of a commercial partner; 
(6)  to note Officers would provide update reports on the progress of the work to
Members as required throughout the development of the project; and 
(7) to note the importance of accessible charging bays and to assess the
implication and application of relevant legislation and national guidance when
it becomes available. 
UPDATE TO PARK MANAGEMENT RULES 
A report was submitted by the Chief Officer – Regulatory and Regeneration seeking
approval to consult upon the proposed revised Management Rules for the
Administration of Parks and Open Spaces. 
After discussion and having heard the Manager of Legal Services in further
explanation and in answer to Members’ questions, the Committee agreed:- 
(1) to consider and approve the terms of the proposed Management Rules,
incorporating a rule prohibiting the possession of alcohol in a park or open
space, further to a failure to comply with request from a Council Officer to
remove said alcohol from the park or open space or to dispose of said
alcohol; 
(2) that the authority be delegated to officers to consult upon the terms of the
proposed Management Rules and advertise as required in terms of the Civic
Government (Scotland) Act 1982 (the 1982 Act); 
Page 8

Page 9

(3) that officers specifically to consult with Community Councils, the National Park
Authority, Police Scotland, and any other relevant bodies; and 
(4) thereafter, a report be brought back to a future meeting of this Committee to
consider the consultation responses. 
LEASE OF WEST DUNBARTONSHIRE ACTIVITY CENTRE, 73 ARDOCH
CRESCENT, BRUCEHILL, DUMBARTON. 
A report was submitted by the Chief Officer – Resources seeking approval for the
lease of West Dunbartonshire Activity Centre to West Dunbartonshire Gymnastics
Club. 
After discussion and having heard the Assets Co-ordinator in further explanation and
in answer to Members’ questions, the Committee agreed:- 
(1) to approve the lease of West Dunbartonshire Activity Centre for a period of 10
years to West Dunbartonshire Gymnastics Club; 
(2) to authorise the Chief Officer – Resources to conclude negotiations; and 
(3) to authorise the Chief Officer – Regulatory and Regeneration to conclude the
transaction on such conditions as considered appropriate. 
SALE OF SITE AT BURROUGHS WAY, VALE OF LEVEN INDUSTRIAL ESTATE,
DUMBARTON. 
A report was submitted by the Chief Officer – Resources seeking approval to
dispose of development site at Burroughs Way, Dumbarton (the Site) to Hargreaves
Land Ltd. 
After discussion and having heard the Assets Co-ordinator in further explanation and
in answer to Members’ questions, the Committee agreed:- 
(1) to approve the disposal of the Site to Hargreaves Land Ltd for £500,000 plus
VAT; 
(2) to authorise the Chief Officer – Resources to conclude negotiations; and 
(3) to authorise the Chief Officer – Regulatory and Regeneration to conclude the
transaction on such conditions as considered appropriate. 
Page 9

Page 10

SALE OF WDC GROUND LEASE INTER EST AT 578 GLASGOW ROAD,
CLYDEBANK G81 1NH 
A report was submitted by the Chief Officer – Resources seeking approval to
dispose of the Council’s ground lease interest at 578 Glasgow Road, Clydebank to
Condie Investments Ltd. 
After discussion and having heard the Assets Co-ordinator in further explanation and
in answer to Members’ questions, the Committee agreed:- 
(1) to approve the sale of the Land to Condie Investments Ltd for the price of
£138,000; 
(2) to authorise the Chief Officer –Resources to conclude negotiations; and 
(3) to authorise the Chief Officer – Regulatory and Regeneration to conclude the
transaction on such conditions as considered appropriate. 
Councillor Rooney left the meeting at this point in the meeting. 
DISPOSAL OF LAND BETWEEN 44 - 48 TOWNEND ROAD, DUMBARTON G82
2AN 
A report was submitted by the Chief Officer – Resources seeking approval to enter
into a contract for the disposal of land at 44 - 48 Townend Road Dumbarton to Mr
Peter Doherty. 
After discussion and having heard the Assets Co-ordinator in further explanation and
in answer to Members’ questions, the Committee agreed:- 
(1) to approve the disposal of 44 - 48 Townend Road Dumbarton to Mr Peter
Doherty for the price of £25,000; 
(2) to authorise the Chief Officer – Resources to conclude negotiations; and 
(3) to authorise the Chief Officer – Regulatory and Regeneration to conclude the
transaction on such conditions as considered appropriate. 
INFRASTRUCUTRE, REGENERATION AND ECONOMIC DEVELOPMENT
BUDGETARY CONTROL REPORT 2023/24 TO PERIOD 10 (31 JANUARY 2024) 
A report was submitted by the Chief Officer – Resources providing an update on the
financial performance to 31 January 2024 (Period 10) of those services under the
auspices of the Infrastructure, Regeneration and Economic Development Committee
(IRED). 
After discussion and having heard the Chief Officer – Resources in further
explanation the Committee agreed:-
Page 10

Page 11

(1) to note the contents of the report which showed the revenue budget forecast
to overspend against budget by £1.350m (9.33%) at the year-end taking into
account that this is subject to change;
(2) to note the net projected annual position in relation to relevant capital projects
highlighted a projected variance of £52.110m (42.28%) due to re-profiling; and
(3) to note that future meetings of the IRED Committee would be presented with
separate revenue and capital budgetary control reports.
The meeting closed at 11.48 a.m.
Page 11

Page 12

Page 12

Page 13

WEST DUNBARTONSHIRE COUNCIL
Report by Chief Officer (Regulatory & Regeneration)
Infrastructure, Regeneration & Economic Development Committee
14 August 2024
Subject: Business Improvement District (BID) Proposal - Alexandria
1 Purpose
1.1 The purpose of this report is to provide information on the proposed Business
Improvement District (BID) in Alexandria.  It seeks Members’ authorisation to
formally approve the BID Proposal.
2 Recommendations
2.1.1 It is recommended that Committee:
(i) notes that a Business Improvement District (BID) is proposed for
Alexandria town centre
(ii) authorises the Chief Officer for Regulatory and Regeneration to approve
the BID Proposal by the statutory deadline of 29th August 2024, subject
to it being compliant with the relevant Sections of the Planning etc.
(Scotland) Act 2006
(iii)notes that the BID Ballot will be scheduled for November 2024 (date
tbc)
3 Background
3.1 Over recent years Alexandria Town centre, like many other small towns, has
been facing challenges related to increased competition from online shopping
and out of town developments. It has struggled to secure the right investment
and retain sustainable level of footfall.  Alexandria Town Centre Masterplan
was developed by the Council in cooperation with the local community and
approved by IRED Committee in September 2021. The objective of the
Masterplan reflects the desire amongst the local business and community to
see Alexandria prosper and become once again the Heart of the Vale. To
make it happen there is a need for the local community and the local authority
to work together.
3.2 Alexandria Traders Association is a self-funded group of local business which
has been meeting on regular basis to discuss the challenges facing the Main
Street and the town centre. It is made up of local business owners as well as
local Elected Members,  Central Alexandria Tenants & Residents Association
ITEM 7
Page 13

Page 14

(CATRA) and Vale of Leven trust (VOLT), with Officers from West
Dunbartonshire Council also in attendance. Meetings are held every six
weeks to discuss and organise initiatives around the improvement of
Alexandria. The group have concluded that a continued coordinated response
from all businesses is required to address the ongoing challenges, raise the
profile of the town, and make it more attractive to residents and visitors. In
order to create a platform for businesses to work together, the group have
agreed to pursue establishment of a Business Improvement District (BID)
3.3 A Business Improvement District (BID) is a geographically defined area where
businesses come together and agree to invest collectively in projects and
services that the businesses identify will improve the trading environment over
and above those provided by statutory authorities. The activities undertaken
by the BID are funded with the money collected through the compulsory
investment levy set and paid by all the property owners and property
occupiers in the BID area (unless exempt in full or part). Each business liable
to contribute to the project is able to vote on whether or not the BID goes
ahead. 
3.4 BIDs are supported by Scotland’s Improvement Districts (SID) which forms
part of Scotland’s Towns Partnership and is supported by the Scottish
Government. SID works with partner organisations to foster the growth of
improvement districts. It is also a hub for expertise and advice which can help
communities to achieve their ambitions, working democratically and
collaboratively.
3.5 In November 2023 the Traders Association successfully applied for and
received a £20k Seedcorn Grant from the Scottish Government to support the
development of a Business Improvement District (BID) and subsequently a
BID Steering Group has been established. 
3.6 In July 2024 the BID Steering Group wrote to the Chief Executive of West
Dunbartonshire Council with a notice of intent to go to Ballot. Following
discussions with the Council’s officers, it was agreed that the ballot would be
undertaken in November 2024 (date tbc). 
3.7 The statutory BID development timescale is as follows:
Days to Ballot Action Status
At least 196 days (28
Weeks) Notice of intention to put BID
Proposals to ballot
Completed
At least 126 days
(18 Weeks)
BID Proposal Review by SID (non-
statutory)
Completed
At least 98 days
(14 Weeks) 
Submission of BID Proposals to
the Local Authority and Scottish
Government
70 days
(10 Weeks)
Last day the Local Authority can
veto BID Proposals
Page 14

Page 15

At least 56 days
(8 Weeks) 
The local authority instructs the
ballot holder to hold BID ballot.
42 days
(6 Weeks)
Issue of ballot papers to all eligible
businesses within the BID area
Ballot Day
4 Main Issues
4.1 The proposed BID will cover the area on Main Street from the Esso Garage at
the north end to beyond Mitchell Way, and the areas along Bank Street and
Mitchell Way. For detailed map please refer to Appendix One (to follow after
pre-agenda)
4.2 The BID Steering Group (BID Proposer) have consulted with all businesses
within the proposed BID area to find out about their priorities for the town
centre and raise awareness of the proposed BID and benefits it could
generate for the town centre. Scottish Improvement Districts (SID) provided
their support through the process and the Regeneration team facilitated
liaison between the Steering Group and the relevant Local Authority Service
areas. 
4.3 The findings from consultation with local business owners have led to creation
of the five CORE THEMES which will form the basis of BID’s Business Plan
and provide a road map towards tangible, deliverable results for Alexandria.
PROFILE  – raise the profile of the town centre
VISITORS  – attract more visitors
SUPPORT  – support businesses and promote innovation
CLEAN  – make town centre clean and attractive
ACCESS  – improve access and visibility from the surrounding areas
4.4 The proposed BID will support and complement delivery of the actions which
originate from the Alexandria Town Centre Masterplan, Some  actions have
already been delivered with funding from the Council and external grants
(Smollett Fountain refurbishment, Christie Park improvements, Main Street
property improvements), and others are at various stages of project
development. BID’s focus will be on additional town centre improvements
delivered through small capital investment, events and initiatives as well as
marketing. The proposals include but are not limited to regular market,
Halloween parade, Spring Fayre, Christmas Lights switch-on, flower basket
campaign, marketing campaign in social and traditional media, signage
improvements, and measures designed to support local business and
encourage new investment.
4.5 There are approximately 109 commercial properties in the BID area which will
generate a BID investment levy income of approximately £51,272 per annum
and an estimated total levy income of £256,360 over the 5 years BID term. The
BID improvement levy will be paid by the occupier (the eligible person liable to
pay the non-domestic rate), however, the property owner will be liable to pay
the levy where a property is vacant on the day the levy invoice is issued and
Page 15

Page 16

for all the period thereafter when the property is vacant. The minimum levy
payment will be £312 annually / £6 per week for small businesses which is
believed to be affordable. A maximum payment of £5200 is proposed to be
levied for businesses at the higher end of the banding. In addition the Council
will provide a £10k grant from the Local Economic Development budget to
support the BID’s capital projects.
4.6 Certain types of premises as listed below will be excluded from the levy
payment obligation:
• premises that have a rateable value of under £1,000. These premises
can pay a voluntary levy and become an “associate member” should
they wish, details of which are given in the BID Business Plan.
• the following categories of property: non-retail charities, Police Stations
and Schools.
4.7 The BID will be managed by a Board of Directors which will be established
following a successful ballot. Every eligible person that pays the levy will have
the opportunity to nominate themselves or someone else from within the BID
area to be elected to the Company Board. The Board will include one
representative from West Dunbartonshire Council and non-voting
representatives from Police Scotland, Christie Park Primary School, and the
Bank Street Medical Centre. Other non-voting members or local groups may
be co-opted onto the Board at the Board’s discretion.
4.8 The Board plans recruit a BID Manager to ensure the efficient delivery of the
projects and effective communications with the levy payers. This would be
financed from the levy income. 
4.9 Throughout the lifetime of the BID, all activities will be monitored by the Board
to ensure that the objective of the BID Business Plan are achieved to the
satisfaction of the businesses that form the BID. The Board will agree on an
annual basis how funds for subsequent years will be allocated. This will be
based on business feedback during the previous year and the priorities for the
coming year, which allows the BID the flexibility to respond to changing
business needs and requirements.
4.10 The Local Authority, on officially receiving the BID proposals has up to 70
days before the date of ballot, to decide if the authority is approving or vetoing
the BID proposals. The grounds on which the Local Authority can veto the
proposals are limited. The BID Proposal will also be reviewed by the Scottish
Government who will provide their feedback and comments to the Local
Authority. 
4.11 Where a local authority has BID arrangements in place, under legislation, they
must comply with them. The key Local Authority tasks and responsibilities are:
• Compliance with the statutory timescales including for review, approval
or veto of the BID proposals
Page 16

Page 17

• Provision of information from non-domestic rates billing records
• Provision of the statutory and non-statutory baseline statements
(Baseline Service Agreement)
• Arranging and running of BID ballot
• Management, collection and enforcement of the BID Levy
5 People Implications
5.1 BID Ballot management will be outsourced to a qualified third-party
organisation, with the fee paid by the BID Proposer. Limited election related
activities will be undertaken by the existing Election team staff. 
5.2 If the BID is established following a successful ballot, existing staff within
Regeneration will continue to support the BID and provide liaison between the
BID and relevant Council’s Services if required.
5.3 Levy collection will be undertaken by the existing revenue team staff, with the
fee for levy collection being waved in Year 1. The Council will review this
arrangement for future years. 
6 Financial & Procurement Implications
6.1 The Council is a landlord for a number pf properties within the BID area. The
Council will be liable for laying the BID Levy for those properties which are
vacant on the day the levy invoice is issued.
6.2 The fee for collecting the levy in Year 1 will be waived. The Council will be
able to charge a fee for levy collection in future years. 
7 Risk Analysis
7.1 There is a risk that the BID will have insufficient finances to meet its liabilities
and will have to be dissolved. 
8  Environmental Sustainability
8.1 A more attractive, vibrant and economically sustainable town centre will
support local living and contribute towards delivery of wider sustainability
goals and the Council’s Climate Change Strategy
9 Equalities Impact Assessment
9.1 An Equalities Impact Assessment is being undertaken (report to follow after
pre-agenda)
11  Consultation
Page 17

Page 18

11.1 The BID Steering Group has undertaken consultations with the local business
during the BID development process. The outcome of these consultations will
be summarised in the BID Proposal and reflected in the BID Business Plan. 
11.2 The following Council Services have been involved as part of the BID
development process: Democratic Services, Finance, Asset Management,
Legal and Economic Development. A number of other Services including
Roads, Greenspace, Fleet & Waste, Communities, Housing and Planning
contributed to the Baseline Services Agreement. 
12 Strategic Assessment
12.1 The Council has agreed its five main strategic priorities for 2022 –
2027. The BID is consistent with the following objectives:
• Our neighbourhoods are sustainable and attractive.
• Our area has the infrastructure for sustainable and inclusive growth where
businesses can flourish.
• Our residents are engaged and empowered.
Alan Douglas
Chief Officer - Regulatory &Regeneration
14 August 2024
________________________________________________________________
Person to Contact:  Gillian McNamara
Appendices: Appendix A: BID Map (to follow)
Appendix Two: EIA (to follow)
Background Papers:
Wards Affected: Leven
Page 18

Page 19

¯
Reproduced by permission of Ordnance Survey on behalf of HMSO. (C) Crown copyright and database right 23/07/2024.
All rights reserved. West Dunbartonshire OS Licence Number 100020790.
ITEM 7 - APPENDIX 1
Proposed Alexandria Business Improvement District  (BID) Area Map
Page 19

Page 20

Assessment No 1035 Owner mswider
Resource Regeneration, Environment and
Growth
Service Regeneration
FirstName Surname Job Title
Head Officer magdalena swider Regeneration Coordinator
Members Gillian McNamara
(Please note: the word 'policy' is used as shorthand for strategy policy
function or financial decision)
Policy Title Proposed Business Improvement District, Alexandria
The aim, objective, purpose and intended out come of policy
A group of Businesses in Alexandria (BID Steering Group) are working to establish a
Business Improvement District (BID). A Business Improvement District (BID) is a
geographically defined area where businesses come together and agree to invest
collectively in projects and services that the businesses identify will improve the
trading environment over and above those provided by statutory authorities. The
activities undertaken by the BID are funded with the money collected through the
compulsory investment levy set and paid by all the property owners and property
occupiers in the BID area (unless exempt in full or part). BID’s focus will be on town
centre improvements delivered through small capital investment, events and initiatives
as well as marketing. It will complement the delivery of actions from the Alexandria
Town Centre masterplan approved in 2021.
The key Local Authority tasks and responsibilities related to BID are:
- Compliance with the statutory timescales including for review, approval or veto of the
BID proposals
- Provision of information from non-domestic rates billing records
- Provision of the statutory and non-statutory baseline statements (Baseline Service
Agreement)
- Arranging and running of BID ballot
- Management, collection and enforcement of the BID Levy
Service/Partners/Stakeholders/service users involved in the development
and/or implementation of policy.
Businesses within Alexandria
WDC Finance team (levy collection)
WDC Democratic Services team (BID ballot)
WDC Regeneration (BID lisaison)
WDC Services which contribute to the Service Level Agreement (Roads and
Neighborhood, Regulatory & Regeneration, Communities)
Does the proposals involve the procurement of any goods or services? Yes
If yes please confirm that you have contacted our procurement services to
discuss your requirements.
No
SCREENING
You must indicate if there is any relevance to the four areas
Duty to eliminate discrimination (E), advance equal opportunities (A) or
foster good relations (F)
Yes
Relevance to Human Rights (HR) Yes
ITEM 7 - APPENDIX 2
Page 20

Page 21

Relevance to Health Impacts (H) Yes
Relevance to Social Economic Impacts (SE) Yes
Who will be affected by this policy?
Local businesses in Alexandria
Alexandria Community
WDC Asset Management as a landlord
WDC Finance
WDC Democratic Services
WDC Regeneration
Who will be/has been involved in the consultation process?
Have Community Councils been engaged yet? have the Communities Team been involved in discussions?
Local businesses have been consulted by the BID Steering Group. The BID will be established only if it is
supported by a majority of businesses, as per the relevant legislation.
BID Steering group liaised with WDC Regeneration throughout the BID development process.
WDC Council Services which will have an obligation to support the BID have been consulted and are
aware of the additional workload. Some of the services can be outsources by the Council or a fee can be
charged to cover the costs.
On receipt of the BID proposal the Council can either support of veto the BID however there are only
specific ground for vetoing.
Page 21

Page 22

Please outline any particular need/barriers which equality groups may have in relation to
this policy list evidence you are using to support this and whether there is any negative
impact on particular groups.
Specific group to
consider
Needs Evidence Impact
Age                           Alexandria lacks services or
events which would attract
families with young children.
Feedback from the local
community and businesses.
Town centre attractive
for people of all ages.
Positive impact for
health and wellbeing for
all members of the
community.
Disability                    The Council needs to take
into account accessibility
when making decisions that
are relevant to this
Business are required to
make reasonable
adjustments to make
services accessible to
disabled people
The Alexandria masterplan
notes the importance of
increasing accessibility
There is an opportunity
to discuss accessibility
Gender Reassign              
Marriage & Civil
Partnership 
Pregnancy &
Maternity        
Race                         
Religion and Belief          
Sex                          
Sexual Orientation 
Human Rights                  The Council needs to
consider if  Human Rights
issues are relevant: This
includes UNCRC rights in
terms of Children and
Young people, and cross
cuts with Article 8 of the
ECHR on Family life which
is broad interpreted in case
law.
Christie Park Primary School
will be a non voting  member
on the board. The School has
recently been awarded stage
one of of UNICEFS Rights
Respecting Schools Bronze
Award
Positive as there is an
opportunity through
board membership to
ensure that children's
and young peoples are
taken into consideration
Health                      Health and well being is a
focus of the Council's
Strategic plan.
Increased town center
attractiveness
Positive impact for
health and wellbeing for
all members of the
community.
Page 22

Page 23

Social & Economic
Impact     
We need to have regard to
the Community
Empowerment Act
We need to have regards to
the Fairer Scotland Duty
Alexandria Town centre, like
many other small towns,
has been facing challenges
related to increased
competition from online
shopping and out of town
developments. It has
struggled to secure the right
investment and retain
sustainable level of footfall.
Feedback from the local
community and businesses
has feed into the process.
Vibrant, economically
sustainable and
attractive town centre.
Positive social and
economic impact for all
members of the
community from all age
ranges.
Cross Cutting          It good practice for the
Council to consider how
various factors interact. The
Council have
Feedback from the local
community and businesses.
Alexandria Town centre, like
many other small towns, has
been facing challenges related
to increased competition from
online shopping and out of
town developments. It has
struggled to secure the right
investment and retain
sustainable level of footfall.
The Council have place on the
board.
BID will deliver
improvements in the
town centre, paid for
levy on all businesses.
Levy has been
established at a
sustainable level and will
be affordable to all
businesses.
Page 23

Page 24

Actions
Page 24

Page 25

Policy has a negative impact on an equality group,but is still to be implemented, please
provide justification for this.
N/A
Will the impact of the policy be monitored and reported on an ongoing bases?
Once established, the BID will be managed by a Board of Directors. The Council's involvement will be
limited to levy collection and liaison with BOD as a partner.
Q7 What is you recommendation for this policy?
Intoduce
Please provide a meaningful summary of how you have reached the recommendation
EIA 1035: Potential positive impacts in terms of age for younger and older people and health, as
well as economic benefits.  The masterplan for the area identifies the importance of accessibility
and this can be discussed among stakeholders through the board for example.  The proposal has
the potential to benefit the local town Centre, wider community and businesses. The impact on the
businesses is minimal and levy has been established at a sustainable level. The impact on Council
services can be absorbed within the existing resources, and cost of some of the services will be
covered by BID.
Page 25

Page 26

Page 26

Page 27

WEST DUNBARTONSHIRE COUNCIL
• Report by Chief Officer - Resources
Infrastructure, Regeneration & Economic Development Committee:
14 August 2024
ITEM 8
Subject: Infrastructure, Regeneration & Economic Development Revenue
Budgetary Control Repo_rt 2024/25 to Perl�d 3 (30 June 2024)
1. .Purpose
1.1 This report provides an update on the revenue financial performance to 30
June 2024 of those services under the auspices of the Infrastructure,
Regeneration & Economic Development Comm�ee (IRED).
2. Recommendations
2.1 Members are asked to:
i} note the contents of this report showing the revenue budget forecast to
overspend ·against budget by £2.37Qm (17.95%) at the year-end taking
into account that this Is subject to change.
3. Background
Revenue
3.1 At the meeting of West Dunbartonshire Council on 6 March 2024, Members
agreed the revenue estimates for 2024/25. A total net budget of £14.722m was·
approved for IRED services. The budget has been reduced to reflect the decrease in
Strathclyde pension fund contributions in the year. This ·budget has been vired to a
central reserve to be used to balance the budget over the next four years as agreed
at the Council meeting on 6.Marct, 2024.
Starting Position
Superannuation Saving
Revised Budget
4. Main Issues
Revenue Budget
£m
14.722
-1.487
13.235
4.1 The current budgetary position is summarised in Appendix 1. A more detailed
analysis by service is given in Appendix 2. 
Page 27

Page 28

4.2 Of the 14 services monitored 7 are showing either a favourable or nil variance,
with 7 services showing an adversevariance. Comments are shown in
Appendix 3 when there are projected net annual variances greater than
£0.050m and also where the net variance is below £0.050m but there are
offsetting variances of (?Ver £0.050m within the service.
4,3 Appendix 1 shows the probable outtum for the' services at £15.611 m. As the
annual budget is £13.235m there is currently a projected adverse variance ·for
the year of £2.376m.
4.4 A working group has been established to review where any anticipated
overspends can be reduced and wh�re they may be the option for additional
income Qeneration. • •
4.5 Appendix 4 to the report summarises· the current position ·against the saving
options agreed by council as part of setting the 2024/25 budget.
5. People Implications
5.1 There are no people implications.
6. Financial Implications
6.1 Other than the financial position noted-above, there are no financial
implications of the budgetary control report. Officers are currently reviewing
budgets and projections with a view to improving the position by financial year
arid and progress will be highlighted in future reports to committee.
7, Risk Analysis
7.1 The present variances should be viewed in the knowledge that there are.a
number of variable factors which could arise between now and 31 March and
which could affect the 'year end results. • • •
8. Equalities Impact Assessment (EIA)
8.1 The report is for noting and therefore no Equalities Impact Assessment was
completed for this report.
9 Consultation
9.1 The views of both Finance and Legal services have been requested on this
report and both have advised there are neither any issues nor concerns with
the proposal. As the report is for noting no further consultation is envisaged.
10. Strategjc Assessment
10.1 Proper budgetary control and sound financial-practice are cornerstones of
go� governance and support Council and officers to pursue the five strategic 
Page 28

Page 29

priorities of the Council's Strategic Plan. This report forms part of the financial.
governance of the Council. This report _is for noting and, therefore, does not
directly affect any of the strategic priorities.
Laurence Slavin
Chief Officer - Resources
Date: 19 July 2024
Person to Contact:
Appendices:
Background Papers:
Wards Affected:
Jackie Thomson - Business Unit Finance Partner, 16
Church Street, Dumbarton, G81-1 QL,
e-mail jackie.nicol-thomson@west-dunbarton.gov.uk
Appendix 1 - Summary Budgetary Position {Revenue)
Appendix 2- Detailed Budgetary Position (Revenue)
Appendix 3;,.. Variance Analysis (Revenue)
Appendix 4 - Efficiencies &. Management Adjustments
None
All 
Page 29

Page 30

WEST DUNBARTONSHIRE COUNCIL
REVENUE BUDGETARY CONTROL 2024/25
IRED SUMMARY
MONTH END DATE 30 June 2024
Total Budget
2024/25
Spend to
Date 2024/25
Forecast
Spend
2024/25
Annual
RAG
Status
£000 £000 £000 £000 %
0 (49) 0 0 0% 
(807) 548 (470) 337 -42% 
758 0 738 (20) -3% 
2,544 1,001 3,319 775 30% 
7,414 1,854 7,414 0 0% 
205 18 192 (13) -6% 
(313) (128) (157) 156 -50% 
(1,234) (160) (1,033) 201 -16% 
8,916 1,673 9,612 695 8% 
(1,705) 2,135 (1,726) (21) 1% 
Capital Investment Programme 7 67 1 (6) -81% 
(68) 196 (50) 18 -27% 
Depots 0 0 0 0 0% 
(2,484) 1,592 (2,230) 254 -10% 
13,235 8,746 15,611 2,376 17.95% 
Transport, Fleet & Maintenance Services
Service / Subjective Summary Annual Variance 2024/25
Corporate Asset Maintenance
Consultancy Services
Roads Services
Grounds Maintenance & Street Cleaning Client
Outdoor Services
Burial Grounds
Crematorium
Waste Services
Corporate Assets
Economic Development
Ground Maintenance & Street Cleaning Trading A/c
Total Net Expenditure
ITEM 8 -
APPENDIX 1
Page 30

Page 31

WEST DUNBARTONSHIRE COUNCIL
REVENUE BUDGETARY CONTROL 2024/25
IRED COMMITTEE DETAIL
PERIOD END DATE 30 June 2024
PERIOD 3
Actual
Outturn
2023/24
Total
Budget
2024/25
Spend to
Date 2024/25
Forecast
Spend
2024/25
RAG
Status
£000 £000 £000 £000 £000 %
19,445 Employee 18,617 4,020 19,282 665 4% 
5,077 Property 5,333 314 5,413 81 2% 
5,417 Transport and Plant 4,266 844 4,736 470 11% 
12,169 Supplies, Services and Admin 10,978 2,096 11,861 883 8% 
9,503 Payments to Other Bodies 9,292 1,935 9,395 102 1% 
1,557 Other 562 0 562 0 0% 
53,168 Gross Expenditure 49,049 9,208 51,249 2,200 4% 
(33,044) Income (35,821) (529) (35,639) 182 1% 
20,123 Net Expenditure 13,228 8,679 15,610 2,382 18% 
£000 £000 £000 £000 £000 %
2,067 Employee 1,803 486 2,003 200 11% 
75 Property 18 4 18 0 0% 
48 Transport and Plant 130 33 130 0 0% 
723 Supplies, Services and Admin 561 180 611 50 9% 
0 Payments to Other Bodies 98 25 98 0 0% 
0 Other 0 0 0 0 0% 
2,913 Gross Expenditure 2,610 728 2,860 250 10% 
(2,952) Income (2,610) (777) (2,860) (250) -10% 
(39) Net Expenditure 0 (49) 0 0 0% 
£000 £000 £000 £000 £000 %
2,024 Employee 1,866 471 2,092 226 12% 
108 Property 99 0 93 (6) -6% 
1,688 Transport and Plant 1,826 329 1,702 (124) -7% 
821 Supplies, Services and Admin 509 108 665 156 31% 
1 Payments to Other Bodies 0 0 0 0 30% 
0 Other 0 0 0 0 0% 
4,642 Gross Expenditure 4,300 908 4,553 253 6% 
(4,578) Income (5,107) (360) (5,023) 84 2% 
64 Net Expenditure (807) 548 (470) 337 -42% 
£000 £000 £000 £000 £000 %
1,026 Employee 747 0 733 (14) -2% 
0 Property 0 0 0 0 0% 
3 Transport and Plant 7 0 1 (6) -81% 
7 Supplies, Services and Admin 4 0 4 0 0% 
0 Payments to Other Bodies 0 0 0 0 0% 
0 Other 0 0 0 0 0% 
1,035 Gross Expenditure 758 0 738 (20) -3% 
(0) Income 0 0 0 0 0% 
1,034 Net Expenditure 758 0 738 (20) -3% 
£000 £000 £000 £000 £000 %
2,946 Employee 2,698 579 2,865 167 6% 
254 Property 250 (0) 251 1 0% 
890 Transport and Plant 555 125 901 346 62% 
3,104 Supplies, Services and Admin 2,665 390 3,110 444 17% 
893 Payments to Other Bodies 811 10 907 96 12% 
0 Other 0 0 0 0 0% 
8,088 Gross Expenditure 6,980 1,103 8,033 1,053 15% 
(4,194) Income (4,436) (102) (4,714) (279) -6% 
3,894 Net Expenditure 2,544 1,001 3,319 775 30% 
Service Summary Annual Variance
2024/25
All Services
Corporate Asset Maintenance
Transport, Fleet & Maintenance Services
Consultancy Services
Roads Services
ITEM 8 -
APPENDIX 2
Page 31

Page 32

WEST DUNBARTONSHIRE COUNCIL APPENDIX 2
REVENUE BUDGETARY CONTROL 2024/25
IRED COMMITTEE DETAIL
PERIOD END DATE 30 June 2024
PERIOD 3
Actual
Outturn
2023/24
Total
Budget
2024/25
Spend to
Date 2024/25
Forecast
Spend
2024/25
RAG
Status Service Summary Annual Variance
2024/25
£000 £000 £000 £000 £000 %
23 Employee 0 0 0 0 0% 
0 Property 0 0 0 0 0% 
322 Transport and Plant 0 0 0 0 0% 
0 Supplies, Services and Admin 0 0 0 0 0% 
7,415 Payments to Other Bodies 7,414 1,854 7,414 0 0% 
839 Other 0 0 0 0 0% 
8,599 Gross Expenditure 7,414 1,854 7,414 0 0% 
0 Income 0 0 0 0 0% 
8,599 Net Expenditure 7,414 1,854 7,414 0 0% 
£000 £000 £000 £000 £000 %
74 Employee 127 15 68 (59) -46% 
179 Property 151 0 172 21 14% 
0 Transport and Plant 0 0 0 0 0% 
144 Supplies, Services and Admin 117 70 143 25 22% 
17 Payments to Other Bodies 37 (15) 37 0 1% 
0 Other 0 0 0 0 0% 
414 Gross Expenditure 433 70 420 (13) -3% 
(117) Income (228) (53) (228) 0 0% 
298 Net Expenditure 205 18 192 (13) -6% 
£000 £000 £000 £000 £000 %
0 Employee 0 0 0 0 0% 
29 Property 28 1 33 5 17% 
0 Transport and Plant 0 0 0 0 0% 
0 Supplies, Services and Admin 0 0 0 0 0% 
442 Payments to Other Bodies 469 0 469 0 0% 
0 Other 0 0 0 0 0% 
471 Gross Expenditure 497 1 502 5 1% 
(689) Income (810) (128) (659) 151 19% 
(218) Net Expenditure (313) (128) (157) 156 -50% 
£000 £000 £000 £000 £000 %
215 Employee 181 46 211 30 16% 
265 Property 291 35 288 (2) -1% 
0 Transport and Plant 0 0 0 0 0% 
21 Supplies, Services and Admin 18 8 20 2 13% 
6 Payments to Other Bodies 33 0 33 0 0% 
0 Other 0 0 0 0 0% 
507 Gross Expenditure 523 88 553 30 6% 
(1,460) Income (1,757) (248) (1,585) 172 10% 
(952) Net Expenditure (1,234) (160) (1,033) 201 -16% 
£000 £000 £000 £000 £000 %
3,583 Employee 3,086 768 3,345 260 8% 
200 Property 152 10 154 2 1% 
1,504 Transport and Plant 992 246 1,204 213 21% 
6,503 Supplies, Services and Admin 6,367 1,146 6,364 (3) 0% 
27 Payments to Other Bodies 22 28 28 6 29% 
0 Other 0 0 0 0 0% 
11,817 Gross Expenditure 10,618 2,198 11,095 478 5% 
(1,362) Income (1,701) (525) (1,484) 217 13% 
10,455 Net Expenditure 8,916 1,673 9,612 695 8% 
Grounds Maintenance & Street Cleaning Client
Outdoor Services
Crematorium
Burial Grounds
Waste Services
Page 32

Page 33

WEST DUNBARTONSHIRE COUNCIL APPENDIX 2
REVENUE BUDGETARY CONTROL 2024/25
IRED COMMITTEE DETAIL
PERIOD END DATE 30 June 2024
PERIOD 3
Actual
Outturn
2023/24
Total
Budget
2024/25
Spend to
Date 2024/25
Forecast
Spend
2024/25
RAG
Status Service Summary Annual Variance
2024/25
£000 £000 £000 £000 £000 %
864 Employee 938 154 821 (117) -12% 
2,401 Property 3,337 145 3,325 (12) 0% 
4 Transport and Plant 5 0 5 0 0% 
(19) Supplies, Services and Admin (14) 4 (7) 7 -51% 
65 Payments to Other Bodies 62 34 62 0 0% 
0 Other 0 0 0 0 0% 
3,315 Gross Expenditure 4,328 337 4,205 (122) -3% 
(5,065) Income (6,032) 1,798 (5,931) 101 2% 
(1,750) Net Expenditure (1,705) 2,135 (1,726) (21) 1% 
£000 £000 £000 £000 £000 %
321 Employee 227 66 271 44 20% 
0 Property 0 0 0 0 0% 
0 Transport and Plant 0 0 0 (0) -24% 
0 Supplies, Services and Admin 1 0 1 (0) -9% 
0 Payments to Other Bodies 0 0 0 0 0% 
0 Other 0 0 0 0 0% 
321 Gross Expenditure 229 67 273 44 19% 
(321) Income (221) 0 (271) (50) -23% 
1 Net Expenditure 7 67 1 (6) -81% 
£000 £000 £000 £000 £000 %
620 Employee 747 176 765 18 2% 
489 Property 24 4 24 0 0% 
2 Transport and Plant 1 0 1 0 0% 
13 Supplies, Services and Admin 87 1 87 0 0% 
618 Payments to Other Bodies 345 0 345 0 0% 
0 Other 0 0 0 0 0% 
1,743 Gross Expenditure 1,204 181 1,222 18 2% 
(976) Income (1,272) 15 (1,272) 0 0% 
767 Net Expenditure (68) 196 (50) 18 -26% 
£000 £000 £000 £000 £000 %
0 Employee 0 0 0 0 0% 
657 Property 631 85 655 24 4% 
0 Transport and Plant 0 0 0 0 0% 
(1) Supplies, Services and Admin 15 1 6 (9) -60% 
0 Payments to Other Bodies 0 0 0 0 0% 
0 Other 0 0 0 0 0% 
656 Gross Expenditure 646 86 660 15 2% 
(656) Income (646) (86) (660) (15) -2% 
(0) Net Expenditure 0 0 0 0 0% 
£000 £000 £000 £000 £000 %
6,003 Employee 6,424 1,325 6,379 (46) -1% 
419 Property 352 30 401 49 14% 
957 Transport and Plant 751 111 791 40 5% 
852 Supplies, Services and Admin 649 188 859 210 32% 
19 Payments to Other Bodies 0 0 0 0 0% 
718 Other 562 0 562 0 0% 
8,968 Gross Expenditure 8,738 1,654 8,992 254 3% 
(10,997) Income (11,222) (62) (11,222) 0 0% 
(2,029) Net Expenditure (2,484) 1,592 (2,230) 254 -10% 
Economic Development
Depots
Ground Maintenance & Street Cleaning Trading A/c
Corporate Assets
Capital Investment Programme
Page 33

Page 34

WEST DUNBARTONSHIRE COUNCIL
REVENUE BUDGETARY CONTROL 2024/25
ANALYSIS FOR VARIANCES OVER £50,000
PERIOD END DATE
Total Budget Forecast
Spend RAG Status
Transport, Fleet & Maintenance
Services (807) (470) 337 -42% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Roads Services 2,544 3,319 775 30% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
30 June 2024
Budget Details
Variance Analysis
Variance
Overspend anticipated although may reduce following review
Transport services across WDC
Income is anticipated to be less than budgeted due to number of external
users of MOT station being low.  Although currently showing and under
recovery of full costs a review of service requirements is being undertaken
to ensure all applicable costs are recovered.
Service User Review
Overspend anticipated although may reduce following review
This service relates to Roads operations, design, structures, street lighting,
road safety and school crossing patrols
Employee costs are anticipated to overspend by £167k mainly due to
essential overtime. Plant hire costs and material costs have increased due
to higher inflation than anticipated. The overspend anticipated on this is
£384k.  Winter gritting is anticipated to overspend £60k due to costs of salt
and quantity required. Diesel is anticipated to overspend by £40k due to
increased fuel costs. Street lighting is overspending due increased utility
costs. The remaining overspend anticipated is in relation to general
increased costs and inflationary pressures to undertake works required.
Costs within the service are recharged to capital however, costs recharged
are not sufficient to offset all costs incurred by the service.
A review of the delivery of how capital projects are delivered will be
undertaken. 
ITEM 8 -
APPENDIX 3
Page 34

Page 35

WEST DUNBARTONSHIRE COUNCIL APPENDIX 3
REVENUE BUDGETARY CONTROL 2024/25
ANALYSIS FOR VARIANCES OVER £50,000
PERIOD END DATE
Total Budget Forecast
Spend RAG Status
30 June 2024
Budget Details
Variance Analysis
Variance
Ground Maintenance & Street Cleaning
Trading A/c (2,484) (2,230) 254 -10% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Burial Grounds (313) (157) 156 -50% 
Service Description This service provides burial services within the Council area
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Crematorium (1,234) (1,033) 201 -16% 
Service Description This service provides crematorium services within the Council area
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Trading operation providing grounds maintenance and street cleaning
services
Supplies and services is showing an anticipated overspend of £210k. £60k
is  due to cost of parts for repairs which is demand led. The remaining
overspend is mainly in relation to overspending on contractors. A review of
all contractor spend is underway to identify any opportunities to reduce or
mitigate the anticipated overspend.
None at the moment.
overspend anticipated
Income from burials is less than budgeted. This is demand led and may
change throughout the year.
Under recovery of income anticipated
Income from cremations is less than budgeted. This is demand led and may
change throughout the year.
None at the moment.
None at the moment.
Under recovery of income anticipated
Page 35

Page 36

WEST DUNBARTONSHIRE COUNCIL APPENDIX 3
REVENUE BUDGETARY CONTROL 2024/25
ANALYSIS FOR VARIANCES OVER £50,000
PERIOD END DATE
Total Budget Forecast
Spend RAG Status
30 June 2024
Budget Details
Variance Analysis
Variance
Waste Services 8,916 9,612 695 8% 
Service Description Waste Collection and Refuse disposal services
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Corporate Assets (1,705) (1,726) (21) 1% 
Service Description This service provides asset and estate management
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Employee costs are underspent due to current vacancies however, these
are offset by lower income than budgeted as recharges will be less.
None required.
Small overall underspend on budget
overspend anticipated
All refuse vehicles will be received by September so hires will cease.
Transport costs, are anticipating an overspend of £213k principally due to
hire costs being greater than anticipated when the budgets were set
because of delays in acquiring new refuse vehicles. This is a part year issue
as the majority of vehicles have now been received and hire costs for these
vehicles will cease. Employee costs are overspending by £260k mainly due
to overtime costs due to requirement to cover public holidays and periods of
annual leave or sickness. In addition overtime budgets do not include pay
award increase. The garden waste permit sale is anticipated to be lower
than budgeted however will be partly offset by reduced disposal costs.
Leaving an anticipated under  recovery of £50k . The remaining underspend
is mainly due to an anticipated reduction in income received based on
previous years income received.
Page 36

Page 37

WEST DUNBARTONSHIRE COUNCIL
MONITORING OF EFFICIENCIES AND MANAGEMENT ADJUSTMENTS 2024/25
Efficiency Detail Ref Chief Officer
Budgeted Amount
£000 
Projection of Total
Saved £000 
Projection of Total
Not Saved £000 Comment
December 2023 Management Adjustments - -
Seek commercial opportunities for Balloch Park kiosk RES12 L Slavin 15 15 -
Rightsize income budgets as consequence of historical lease
review RES15 L Slavin 25 25 -
Procure vehicles considered permanently required rather than
hiring  them RN17 G Macfarlane 100 100 in progress
- -
December 2023 Saving Options - -
Two week Christmas closedown bar delivery of essential services RES07 L Slavin 7 7 -
- -
March 2024 Saving Options - -
Remove one Council officer RES09 L Slavin 26 26 -
School crossing patrollers - adhere to best practice RN01 G Macfarlane 24 24 - Implemented Aug
Introduce £60 Garden Waste Charge RN02 G Macfarlane 180 130 50
Implemented Aug, 4000 permits to date.
The smoothing fund will be used to cover
the variance for 2024/25 and it is
anticipated that the full saving will be
made in 2025/26
Amend roads service activities to support education to statutory
level RN04 G Macfarlane 37 37 - complete
Reduce the Consultancy Services/Capital Investment Team by 25% RN18 G Macfarlane 10 10 - In progress
Reduce the roads operations service from 29 FTE to 26 FTE which
will reduce resilience in the team RN21 G Macfarlane 80 80 - complete
Reduce maintenance costs through replacing 6 under utilised
grass pitches with 3 new 4G pitches RN22 G Macfarlane 10 10 - in progress
Implement new approach to road defect repairs which will
capitalise costs previously charged to revenue RN23 G Macfarlane 200 200 - complete
Reduce weed killing from twice a year to once a year RN26 G Macfarlane 50 50 - in progress, in design stage
Increase commercial waste fees by 14% RN27 G Macfarlane 45 45 - complete
- -
March 2024 Management Adjustments - -
Remove vacant posts in asset management RES22 L Slavin 99 99 complete
Remove facility assistants at Aurora House bringing service in line
with that provided at Clydebank Town Centre Office RES23 L Slavin 54 54 - complete
ITEM 8 -
APPENDIX 4
Page 37

Page 38

WEST DUNBARTONSHIRE COUNCIL APPENDIX 4
MONITORING OF EFFICIENCIES AND MANAGEMENT ADJUSTMENTS 2024/25
Efficiency Detail Ref Chief Officer
Budgeted Amount
£000 
Projection of Total
Saved £000 
Projection of Total
Not Saved £000 Comment
Generate income from Levengrove Pavilion and ass land RES25 L Slavin 63                             63                              -                                complete
1,025                             975                                   50 TOTAL EFFICIENCIES/MANAGEMENT ADJUSTMENTS
Page 38

Page 39

WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer – Resources
Council – 14 August 2024
___________________________________________________________________
Subject: Infrastructure, Regeneration & Economic Development Capital
Budgetary Control Report 2024/25 to Period 3 (30 June 2024)
1. Purpose
1.1 This report provides an update on the capital financial performance to 30 June
2024 of those services under the auspices of the Infrastructure, Regeneration
& Economic Development Committee (IRED).
2. Recommendations
2.1 Committee is asked to:
i) Note the current position of the 2024/25 IRED capital budget.
ii) Approve the revised completion dates detailed in appendix 3.
iii) Note an in-year variance of £14.538m due to reprofiling of projects.
3. Background
3.1 On 6 March 2024 the Council approved the updated General Services Capital
Plan for 2024/2025 to 2032/33.  The three years from 2024/25 to 2026/27
were approved in detail with the remaining years being indicative. The budget
agreed under the auspice of IRED Committee was £51.612m for 2024/25 and
£215.153m for the project life budget.
3.2 Since then budget adjustments have taken place which result in a revised
IRED capital budget as set out in Exhibit 1.
Exhibit 1: Revised Capital Budget
2024/25
(£m)
Project Life
(£m)
Capital Budget Agreed 6 March 2024 51.612 215.153
Capital Project Added (Para 4.6) 1.197 2.000
Developers Contributions for Clydebank Can on
the Canal
0.050 0.050
New Scottish Government Funding – Nature
Restoration
0.034 0.034
New Scottish Government Funding – Cycling,
Walking and Safer Streets
0.389 0.389
Revised Capital Budget as at Period 3 53.282 217.626
ITEM 9
Page 39

Page 40

4. Main Issues
4.1 Progress against the 2024/25 capital plan is detailed in:
Appendix 1 – Project Life Summary by Chief Officer
Appendix 2 – Off Track Projects
Appendix 3 – Changes to Capital Plan for Noting
Appendix 4 – All Approved Projects
4.2 Appendix 2 highlights nine projects currently showing as off-track due to
revised completion dates. These are:
 Installation of Solar PV at Clydebank Leisure Centre,
 Replace Failed Heating Controls,
 Levelling Up Capacity,
 Auld Street Bond
 Riverbank Erosion Repair,
 Pavement Improvements
 Waste Transfer Station,
 Park Improvements
 Kilmaronock Cemetery Expansion.
Appendix 3 highlights twenty six projects where the project expenditure
requires to be reprofiled but there is no need for additional budget.
4.3 Appendix 4 shows all projects with approved in year and project life budgets
as well as anticipated expenditure. It highlights that the 2024/25 budget is
£53.282m with current forecast spend of £38.744m, a variance of £14.538m,
(27.29%) relating to projects which require reprofiling.  The spend as at period
3 is £3.924m (10.13%) of the current forecast spend of £38.744m. 
4.6 Other minor changes to the capital plan already included in the summarised
plan in appendix 4 are:
 The Clyde Mission Catalyst Fund has been added onto the Capital Plan.
This is not a new project and funding for it was received 16 April 2021 from
Scottish Government. It was omitted from the Capital Plan in March 2024
as it has been managed through a different method. However. The
presentation has been corrected and the project will be monitored through
the capital plan moving forward. This has no impact on funding as it is fully
funded.
5. Option Appraisal
5.1 No option appraisal was required for this report.
6. People Implications
6.1 There are no people implications.
7. Financial and Procurement Implications
7.1 The report notes the projected in-year financial position for capital budgets.
8. Risk Analysis
8.1 The main risks are as follows:
Page 40

Page 41

(a) The reported variances should be viewed in the knowledge that there are
a number of variable factors which could arise between now and 31
March which could affect the year end results for capital budgets.
(b) As a consequence of current market conditions, inflation is at an all-time
high and interest rates continue to be volatile. To forecast for the full year
costs budget assumptions have been required. These assumptions
continue to change regularly and therefore it is likely the projected year
end budgetary position will change from that reported.
9. Equalities Impact Assessment (EIA)
9.1 No equalities impact assessment was required in relation to this report.
10. Environmental Sustainability
10.1 No assessment of environmental sustainability was required in relation to this
report.
11. Consultation
11.1 All services involved in delivering the capital budgets have been consulted in
the compilation of this report.
12. Strategic Assessment
12.1 Proper budgetary control and sound financial practice are cornerstones
of good governance and support Council and officers to pursue the
strategic priorities of the Council’s current Strategic Plan. This report
forms part of the financial governance of the Council.
________________
Laurence Slavin
Chief Officer – Resources
Date: 30 July 2024
Person to Contact: Jackie Thomson
Council Offices, Church Street, Dumbarton
E-mail: jackie.nicolthomson@west-dunbarton.gov.uk
Appendices: Appendix 1 - Project Life Summary
Appendix 2- Off Track Projects
Appendix 3 - Reprofiling and Acceleration of Projects
Appendix 4 - Details of all Projects.
Background Papers:
General Services Capital Plan Update - Council 6 March 2024.
Wards Affected  All Wards
Page 41

Page 42

Period 3 - 30 June 2024 ITEM 9 - APPENDIX 1
Summary
Project Life
Budget
Project
Life
Forecast
Spend
Project
Life
Variance
On
Track/Complete Off Track
£'000 £'000 £'000
Chief Officer Resources       35,810   35,810 -   4 -  
Chief Officer Regulatory and Regeneration       58,154   57,431 - 723 8 3
Chief Officer Roads and Neighbourhoods 123,662 123,645  -   26 6
Total 217,626   216,886 - 723 38 9
Page 42

Page 43

Projects that are Off Track as at Period 3 - 30 June 2024
ITEM 9 -
APPENDIX 2
Service Project
Approved
Project Life
Cost
Revised
Project
Life Cost Project Life Variance
Initial
Completion
Date
Revised
Completion
Date
£'000 £'000 £'000
RR3 Installation of Solar PV at Clydebank Leisure Centre 61 61 0 31/03/2023 31/03/2025
RR4 Replace failed heating controls/valves & recommission 20 20 0 31/03/2023 31/03/2025
RR11 Levelling Up Capacity 320          320 0 31/03/2025 31/03/2026
R&N6 Auld Street Clydebank - Bond 256          256 0 31/03/2019 31/03/2025
R&N7 River Bank Erosion Repair - Levenhowe 801          801 0 31/03/2024 31/03/2025
R&N11 Pavement Improvements 1,000   1,000 0 31/03/2024 31/03/2025
R&N22 Waste Transfer Station 1,980   1,980 0 31/03/2025 31/03/2026
R&N27 Park Improvements and Multi Games Area - Goldenhill Park 150          150 0 31/03/2025 31/03/2025
R&N30 Kilmaronock Cemetery Expansion 50 50 0 31/03/2024 31/03/2025
Project Name: Installation of Solar PV at Clydebank Leisure Centre
Initial End Date: 31/3/23 Revised End Date: 31/3/25
How was this project initially funded: Prudential Borrowing Please Detail any additional funding
Why is the project classified as off track and what has caused the issues identified?
The project has been delayed due to resourcing issues. Resources redirected to District Heating Network in the absence of District Heating Project Lead.
What action will be taken to rectify the position?
Additional Funding Requested:  £0
New Completion Date:31/3/25
What are the implications on the actions proposed?
Revenue Implications
Virement Implications
Project Name: Replace failed heating controls/valves & recommission - Original
Initial End Date: 31/3/23 Revised End Date: 31/3/25
How was this project initially funded: Prudential Borrowing Please Detail any additional funding
Why is the project classified as off track and what has caused the issues identified?
The project has been delayed due to resourcing issues. Resources redirected to District Heating Network in the absence of District Heating Project Lead.
What action will be taken to rectify the position?
Additional Funding Requested:  £0
New Completion Date:31/3/25
What are the implications on the actions proposed?
Revenue Implications
Virement Implications
Project Name: Levelling Up Capacity
Initial End Date: 31/3/25 Revised End Date: 31/3/26
How was this project initially funded: SG funded Please Detail any additional funding
N/A
Why is the project classified as off track and what has caused the issues identified?
The funding has been realigned to match the Level Up Funding project
What action will be taken to rectify the position?
Additional Funding Requested:  £0
New Completion Date:31/3/26
What are the implications on the actions proposed?
Revenue Implications
Virement Implications
Project Name: Auld Street Clydebank - Bond
Initial End Date: 31/3/24 Revised End Date: 31/3/25
How was this project initially funded: Funded via road bond provided by Developer Please Detail any additional funding
Why is the project classified as off track and what has caused the issues identified?
What action will be taken to rectify the position?
Additional Funding Requested:  £0
New Completion Date:31/3/25
What are the implications on the actions proposed?
Revenue Implications
Virement Implications
Project Name: River bank erosion repair - Levenhowe
Initial End Date: 31/3/24 Revised End Date:31/3/25
How was this project initially funded: Capital Investment Please Detail any additional funding
Why is the project classified as off track and what has caused the issues identified?
What action will be taken to rectify the position?
Additional Funding Requested:  £0
New Completion Date:
What are the implications on the actions proposed?
Revenue Implications
Virement Implications
Chief Officer RNT
Chief Officer RNT
Initial road bond was used to complete the drainage and street lighting installations as well as road construction. Remaining funding was not enough to complete the
installation of remote footway. Additional funding now available through Jubilee developer contributions to complete.
Source of Funding
N/A
Some river bank repair was undertaken through existing capital budget for Levenhowe however, delayed whilst survey and recommendations report undertaken.
Works identified for progress 24/25 and await outcome of SEPA approval
Source of Funding
Chief Officer Regulatory and Regeneration
Source of Funding
Chief Officer Regulatory and Regeneration
Source of Funding
Chief Officer Regulatory and Regeneration
Source of Funding
Page 43

Page 44

Project Name: Pavement Improvements
Initial End Date: 31/3/2024 Initial End Date: 31/3/2025
How was this project initially funded: Prudential Borrowing Please Detail any additional funding
N/A
Why is the project classified as off track and what has caused the issues identified?
Projects are complete however this budget is required for retentions due to be paid in 24/25.
What action will be taken to rectify the position?
Additional Funding Requested:  £0
New Completion Date:31/3/25
What are the implications on the actions proposed?
Revenue Implications
Virement Implications
Project Name: Waste Transfer Station
Initial End Date: 31/3/25 Revised End Date: 31/3/26
How was this project initially funded: Prudential Borrowing Please Detail any additional funding
N/A
Why is the project classified as off track and what has caused the issues identified?
Project has been delayed as it has inter-dependencies with the wider depots/office rationalisation projects
What action will be taken to rectify the position?
Additional Funding Requested:  £0
New Completion Date:31/3/26
What are the implications on the actions proposed?
Revenue Implications
Virement Implications
Project Name: Park Improvements and Multi Games Area - Goldenhill Park - Original
Initial End Date: 31/3/24 Revised End Date: 31/3/25
How was this project initially funded: Please Detail any additional funding
Why is the project classified as off track and what has caused the issues identified?
Project delayed due to longer than anticipated lead times for MUGA materials
What action will be taken to rectify the position?
Additional Funding Requested:  £0
New Completion Date:31/3/25
What are the implications on the actions proposed?
Revenue Implications
Virement Implications
Project Name: Kilmaronock Cemetery Expansion
Initial End Date: 31/3/24 Revised End Date: 31/3/25
How was this project initially funded: Prudential Borrowing Please Detail any additional funding
N/A
Why is the project classified as off track and what has caused the issues identified?
Unable to deliver project as originally planned due to unforeseen adverse ground conditions.
What action will be taken to rectify the position?
Additional Funding Requested:  £0
New Completion Date:31/3/25
What are the implications on the actions proposed?
Revenue Implications
Virement Implications
Chief Officer RNT
Source of Funding
Source of Funding
Chief Officer RNT
N/A
Source of Funding
Source of Funding
Chief Officer RNT
Chief Officer RNT
Page 44

Page 45

Changes to Capital Plan and Implications ITEM 9 -
APPENDIX 3
RESOURCES
Project  - Res 9
2023/24
Reprofiling 
Current
Year
2024/25  2025/26  2026/27  2027/28 
Future
Years 
Total Capital
Plan
Strathleven Place (formerly part of Glencairn House project) - Original 50 1,540          - -         -         - 1,590
Strathleven Place (formerly part of Glencairn House project) - Revised 1,590          - -         -         - 1,590
Explanation
Project delayed due to internal resources and impact of Glencairn House project completion.
Project  - Res 11
2023/24
Reprofiling 
Current
Year
2024/25  2025/26  2026/27  2027/28 
Future
Years 
Total Capital
Plan
Building Upgrades and H&S - lifecycle & reactive building upgrades - original
331 2,791          2,781      2,781     2781 13,905     25,370
Building Upgrades and H&S - lifecycle & reactive building upgrades -
Revised 3,122          2,781      2,781     2,781     13,905     25,370
Explanation
Carry forward required for retentions for projects and projects agreed in pipeline
Project - RES13
2023/24
Reprofiling 
Current
Year
2024/25  2025/26  2026/27  2027/28 
Future
Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Depot Rationalisation - Original 238 500 3,000      4,590     -         - 8,328
Depot Rationalisation - Revised 500 3,000      4,828     -         - 8,328
Explanation
Awaiting feasibility report on garage replacement. Once received the will be reviewed by services and progress to detailed design.
Page 45

Page 46

Project - RR7
2023/24
Reprofiling 
Current
Year
2024/25  2025/26  2026/27  2027/28 
Future
Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Regeneration Fund - Original 265              350             1,530      974        970                    4,089
Regeneration Fund - Revised 615             1,530      974        970                            4,089
Explanation
These are multi-year programmes of work/projects that are subject to external factors.
Project - RR8
2023/24
Reprofiling 
Current
Year
2024/25  2025/26  2026/27  2027/28 
Future
Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Place Based Investment - Original 219              310             471         471        0 -                               1,471
Place Based Investment - Revised 529             -         -                                  529
Explanation
Project - RR10
2023/24
Reprofiling 
Current
Year
2024/25  2025/26  2026/27  2027/28 
Future
Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000
Level Up Funding - Original 1,171           11,959        2,200      -         -         -                             15,330
Level Up Funding - Revised 11,959        3,371      -         -         -                             15,330
Explanation
These are multi-year programmes of work/projects that are subject to external factors.
Project - RR12
2023/24
Reprofiling 
Current
Year
2024/25  2025/26  2026/27  2027/28 
Future
Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000
District Heating Network Expansion - Original 140              2,500          4,609      3,095     760        -                             11,104
District Heating Network Expansion - Revised 1,500          5,000      3,595     1,009     -                             11,104
Explanation
Unable to commence construction works until agreements are in place with Golden Jubilee Hospital and other partners.
These are multi-year programmes of work/projects that are subject to external factors. Project has been reduced as it is not clear yet whether there will be further funding
provided.
Page 46

Page 47

ROADS & NEIGHBOURHOOD
Project - R&N1
2023/24
Reprofiling 
Current
Year
2024/25  2025/26  2026/27  2027/28 
Future
Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Infrastructure - Roads (90) 2,544          2,544      2,544     2,544     12,720                       22,806
Infrastructure - Roads 2,454          2,544      2,544     2,544     12,720                       22,806
Explanation
Acceleration of Works
Project - R&N3
2023/24
Reprofiling 
Current
Year
2024/25  2025/26  2026/27  2027/28 
Future
Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  R  £'000
Street lighting and associated electrical infrastructure - Original 14                -              -          -         -         -                                    14
Street lighting and associated electrical infrastructure - Revised 14               -          -         -         -                                    14
Explanation
Rolling programme of column upgrade works. Some delay in finalising programme for last year but will continue into 24/25
Project - R&N4
2023/24
Reprofiling 
Current
Year
2024/25  2025/26  2026/27  2027/28 
Future
Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Flood Prevention - Original 189              150 -          -         -         -                                  339
Flood Prevention - Revised 339 -          -         -         -                                  339
Explanation
Limited uptake on property level protection however scheme will be continued into 24/25. Additional evaluation of Clydebank Surface Water Plan and River Leven
Study planned for 2024/25
Project - R&N5
2023/24
Reprofiling 
Current
Year  2025/26  2026/27  2027/28 
Future
Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Vehicle Replacement - Original (135) 3,000 1,939      1,040     1,040     5,200                         12,084
Vehicle Replacement - Revised 2,865 1,939      1,040     1,040     5,200                         12,084
Explanation
Acceleration of Project
Page 47

Page 48

Project - R&N9
2023/24
Reprofiling 
Current
Year
2024/25  2025/26  2026/27  2027/28 
Future
Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Roads Plant - Original 66                -              -          -         -         -                                    66
Roads Plant - Revised 66                                        66
Explanation
Plant purchased, awaiting invoices
Project - R&N10
2023/24
Reprofiling 
Current
Year
2024/25  2025/26  2026/27  2027/28 
Future
Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
A813 Road Improvement Phase 1 - Original 150              493 -          -         -         -                                  643
A813 Road Improvement Phase 1 - Revised 643 -          -         -         -                                  643
Explanation
Project - R&N12
2023/24
Reprofiling 
Current
Year
2024/25  2025/26  2026/27  2027/28 
Future
Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Traffic Signal Upgrades - Original 26                -              -          -         -         -                                    26
Traffic Signal Upgrades - Revised 26               -          -         -         -                                    26
Explanation
Works delayed awaiting funding decision from LUF.Further lighting upgrades will be completed this year.
Project - R&N13
2023/24
Reprofiling 
Current
Year
2024/25  2025/26  2026/27  2027/28 
Future
Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Gruggies Burn Flood Prevention - Original 363              7,270 6,820 -         -         -                             14,453
Gruggies Burn Flood Prevention - Revised 550             742         6,340     6,821     -                             14,453
Explanation
Priority given to progressing consultation and concept design due to notification submission target of March 2024. Outline design will be delivered over 2024/25 with detailed
design also progressed with planned delivery December 2025. Significant costs associated with design elements.
Road Upgrade completed however delay in undertaking footway extension whilst land ownership resolved. Designs ready to go to start construction on the footway upgrade
Page 48

Page 49

Project - R&N14
2023/24
Reprofiling 
Current
Year
2024/25  2025/26  2026/27  2027/28 
Future
Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Electrical Charging Points - Rapid Charge Original 15                -              -          -         -         -                                    15
Electrical Charging Points - Rapid Charge Revised 15               -          -         -         -                                    15
Explanation
New chargers installed however delay to commissioning and testing. Will be delivered 24/25
Project - R&N16
2023/24
Reprofiling 
Current
Year
2024/25  2025/26  2026/27  2027/28 
Future
Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Vehicle Replacement Strategy - Original 500              900             -          -         -         -                               1,400
Vehicle Replacement Strategy - Revised 1,400          -          -         -         -                               1,400
Explanation
This budget complement the wider vehicle replacement budget with a focus this year on Greenspace plant/vehicles.
Project - R&N18
2023/24
Reprofiling 
Current
Year
2024/25  2025/26  2026/27  2027/28 
Future
Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Public non-adopted paths and roads - Original 394              225             225         225        225        1,125                           2,419
Public non-adopted paths and roads - Revised 619             225         225        225        1,125                           2,419
Explanation
Projects have been identified and are currently being developed for tendering.
Project - R&N20
2023/24
Reprofiling 
Current
Year
2024/25  2025/26  2026/27  2027/28 
Future
Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Vale of Leven Cemetery - original 60                -              -          -         -         -                                    60
Vale of Leven Cemetary - revised 60               -          -         -         -                                    60
Explanation
Retentions for project have extended inti 24/25. The project works are complete.
Page 49

Page 50

Project - R&N21
2023/24
Reprofiling 
Current
Year
2024/25  2025/26  2026/27  2027/28 
Future
Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Allotment Development - Original 91                186                           277
Allotment Development  - Revised 150 127         -         -         -                                  277
Explanation
Tender documents currently being developed.
Project - R&N23
2023/24
Reprofiling 
Current
Year
2024/25  2025/26  2026/27  2027/28 
Future
Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Play Area Upgrade Programme - Original 32                449 100         100        100        534                              1,315
Play Area Upgrade Programme - Revised 481 100         100        100        534                              1,315
Explanation
Longer than anticipated lead time for steel used in construction of play equipment.
Project - R&N25
2023/24
Reprofiling 
Current
Year
2024/25  2025/26  2026/27  2027/28 
Future
Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Whitecrook Tennis Court Upgrade - Original 15                -              -          -         -         -                                    15
Whitecrook Tennis Court Upgrade - Revised 15               -          -         -         -                                    15
Explanation
Retentions to be paid 24/25
Project - R&N26
2023/24
Reprofiling
Current
Year
2024/25 2025/26 2026/27 2027/28
Future
Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
East End Park Resurfacing - Original (6) 385             -          -         -         -                                  379
East End Park Resurfacing - Revised 379             -          -         -         -                                  379
Explanation
Acceleration of Project
Page 50

Page 51

Project - R&N28
2023/24
Reprofiling
Current
Year
2024/25 2025/26 2026/27 2027/28
Future
Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Balloch Mountain Bike Track - Original 10                590 -          -         -         -                                  600
Balloch Mountain Bike Track - Revised 600 -          -         -         -                                  600
Explanation
Awaiting match funding decision from Sportscotland
Project - R&N29
2023/24
Reprofiling
Current
Year
2024/25 2025/26 2026/27 2027/28
Future
Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Pappert 2G Pitch - Original 12                230 -          -         -         -                                  242
Pappert 2G Pitch - Revised 242 -          -         -         -                                  242
Explanation
Tender documents are currently being developed
Project - R&N31
2023/24
Reprofiling
Current
Year
2024/25 2025/26 2026/27 2027/28
Future
Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Exxon City Deal - Original 10,797         9,845 10,820 4,277 1,162                   36,901
Exxon City Deal - Revised 3,000          20,000 11,067   2,834     -                             36,901
Explanation
The reason for reprofiling is that the construction start was delayed due to acdelay of the Esso Remediation and third party land  acquisitions. The 28 May 2023 Council paper
confirms that the  increased project cost of £44.325m, which will be split between City Deal £23.991m and Council £20.334m. The original total budget has not been
reprofiled to reflect on the Council paper
Page 51

Page 52

All Approved Projects at Period 3 - 30 June 2024
Service Project
Initial End
Date
Revised End
Date
Project Life
Budget
Spend to
31 /3/24 Spend to
Date
Projected
Future
Spend
Total
Projected
Spend
Project
Variance Approved
Budget
2024/25
Actual to
date
2024/25
Revised
Forecast
2024/25 
In Year
Variance 
£'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000
RES 9 Strathleven Place (formerly part of Glencairn House project) 31/03/2025 1,590 -                -   1,590                  1,590 -   1,540         - 1,590         50
RES 10
New Sports Changing Facility Dumbarton West (Old OLSP
site)  31/03/2025 349 9 9 340 349 -   340 - 340 -
RES 11
Building Upgrades and H&S - lifecycle & reactive building
upgrades 31/03/2033 25,370         - 305 25,065          25,370 -   2,791         305 3,122         331
RES 13 Depot Rationalisation 31/03/2024 8,500 649 831 7,669                  8,500 -   500 182 262 (238)
Total Resources 35,810         658 1,145         34,665        35,810     - 5,171         487 5,314         143
RR 3 Installation of Solar PV at Clydebank Leisure Centre 31/03/2023 31/03/2025 61 4 4 57 61 -   - - 57 57
RR 4 Replace failed heating controls/valves & recommission 31/03/2023 31/03/2025 20 14 14 6 20 -   - - 6 6
RR 5
Leisure Energy projects - air handling units, upgrade lighting,
circulating pumps, and draught proofing 31/03/2023 31/03/2025 290 64 64 226 290 -   226 - 226 -
RR 6 Regeneration/Local Economic Development 31/03/2033 7,922 5,991        6,043 1,879                  7,922 -   1,100         52 1,100         -
RR 7 Regeneration Fund 31/03/2028 10,931         7,107        7,144 3,787            10,931 -   350 37 615 265
RR 8 Place Based Investment 31/03/2027 2,650 1,398        1,400 526         1,926 (723) 310 3 529 219
RR 9 Clydebank Can on the Canal 31/12/2022 31/12/2025 757 40 40 757 757 -   757 - 757 -
RR 10 Level Up Funding 31/03/2025 31/03/2026 22,100         7,553        8,542 13,558          22,100 -   11,959       989 11,959       -
RR 11 Level Up Capacity Funding 31/03/2025 31/03/2026 320 161 161 159 320 -   161 - 161 -
RR 12 District Heating Network Expansion 31/03/2024 31/03/2028 11,104         40- 141 10,963          11,104 -   2,500         182 1,500         (1,000)
RR 13 Clyde Mission Catalyst Fund 31/03/2024 31/03/2026 2,000 415 415 1,585                  2,000 1,197         - 1,197         -
Total Regulatory and Regeneration 58,154         22,706      23,968       33,503        57,431     (723) 18,560       1,262        18,107       (453)
R&N 1 Infrastructure - Roads 31/03/2033 22,806         -                -   22,806          22,806 -   2,544         - 2,454         (90)
R&N 2 Flood Risk Management 31/03/2033 2,315 -                -   2,315                  2,315 -   500 - 500 -
R&N 3 Street lighting and associated electrical infrastructure 31/03/2033 914 - 13 901 914 -   100 13 114 14
R&N 4 Flood Prevention 31/03/2033 500 160 180 320 500 - 0 150 20 339 189
R&N 5 Vehicle Replacement 31/03/2033 12,219         - 27 12,192          12,219 -   3,000         27 2,865         (135)
R&N 6 Auld Street Clydebank - Bond 31/03/2019 31/03/2025 256 214 214 42 256 -   - - 42 42
R&N 7 River Bank Erosion Repair - Levenhowe 31/03/2024 31/03/2025 20 -                -   20 20 -   - - 20 20
R&N 8 Clydebank Charrette, A814 31/03/2022 4,300 4,215        4,215 85         4,300 -   88 - 88 -
R&N 9 Roads Plant 31/03/2023 31/03/2025 80 14 14 66 80 -   - - 66 66
R&N 10 A813 Road Improvement Phase 1 31/03/2026 31/03/2025 1,700 1,057        1,366 334         1,700 -   493 309 643 150
R&N 11 Pavement Improvements 31/03/2024 31/03/2025 1,000 958 958 42         1,000 -   - - 42 42
R&N 12 Traffic Signal Updates 31/03/2023 31/03/2025 300 274 274 26 300 -   - - 26 26
R&N 13 Gruggies Burn Flood Prevention 31/03/2022 31/03/2028 15,028         576 696 14,332          15,028 -   7,270         120 550 (6,720)
R&N 14 Electrical Charging Points - Rapid Charge 31/03/2026 31/03/2025 314 299 299 15 314 -   - - 15 15
R&N 15 River Leven Flood Prevention Scheme 31/03/2025 31/03/2026 801 181 181 620 801 -   - - - -
R&N 16 Vehicle Replacement Strategy 31/03/2033 900 -                -   900 900 -   900 - 1,400         500
R&N 17
Posties Park Sports Hub - New sports hub to include Gym &
running track 31/03/2021 31/03/2027 6,021 5,878        6,008 13         6,021 -   143 130 143 -
R&N 18 Public non-adopted paths and roads 31/03/2033 2,419 -                -   2,419                  2,419 -   225 - 619 394
R&N 19 Cemetery Extension, North Dalnotter 31/03/2025 264 14 14 250 264 -   250 - 250 -
R&N 20 Vale of Leven Cemetery 31/03/2025 31/03/2025 817 741 760 40 801 (16) - 19 60 60
R&N 21 Allotment Development 31/03/2022 492 215 341 151 492 -   186 126 150 (36)
Full Project Life In Year
ITEM 9 -
APPENDIX 4
Page 52

Page 53

Service Project
Initial End
Date
Revised End
Date
Project Life
Budget
Spend to
31 /3/24 Spend to
Date
Projected
Future
Spend
Total
Projected
Spend
Project
Variance Approved
Budget
2024/25
Actual to
date
2024/25
Revised
Forecast
2024/25 
In Year
Variance
Full Project Life In Year
R&N 22 Waste Transfer Station 31/03/2025 31/03/2026 1,980           -                           41 1,939                  1,980                -   1,780         41             200            (1,580)
R&N 23 Play Area Upgrade Programme 31/03/2033 1,399           149                        282 1,117                  1,399                -   449            133           417            (32)
R&N 24 Nature Restoration Fund 31/03/2024 31/03/2025 608              574                        608 0                            608                -   34              34             34              0                     
R&N 25 Whitecrook Tennis Court 31/03/2024 59                44                            44 15                            59                -   -            -            15              15                   
R&N 26 East End Park Resurfacing 03/04/2021 31/03/2025 385              6                                6 379                        385                -   385            -            379            (6)
R&N 27 Park Improvements and Multi Games Area - Goldenhill Park 31/03/2025 31/03/2025 150              -                           -   150                        150                -   -            -            150            150                 
R&N 28 Balloch Mountain Bike Track 31/03/2024 30/09/2024 600              -                           -   600                        600                -   590            -            600            10                   
R&N 29 Pappert 2G Pitch 31/03/2025 250              8                                8 242                        250                -   230            -            242            12                   
R&N 30 Kilmaronock Cemetery Extension 31/03/2024 31/03/2025 50                45                            45 5                              50                -   -            -            13              13                   
R&N 31 Exxon City Deal 31/03/2028 44,325         6,235                  7,424 36,901              44,325                -   9,845         1,188        2,500         (7,345)
R&N 32 Cycling Walking & Safer Streets 31/03/2025 389              -                           15 374                        389 389            15             389            0
Total Roads and Neighbourhood 123,662       21,859      24,034       99,611        123,645   (17) 29,551       2,175        15,323       (14,228)
Total IRED 217,626       45,222      49,147       167,779      216,886   (740) 53,282 3,924 38,744 (14,538)
Note: Due to previous approvals there are some projects with revised end dates that are not off track at period.