WEST DUNBARTONSHIRE COUNCIL
Report by Chief Officer - Roads and Neighbourhood 
Infrastructure, Regeneration and Economic Development 22 May 2024
Subject: Glasgow City Region: 
Electric Vehicle Charging Infrastructure Collaboration
1 Purpose
1.1 This report provides Members with an update on work undertaken to develop
a collaborative approach to expanding the public electric vehicle charging
infrastructure network across the eight local authorities of Glasgow City
Region and seeks approval for the next steps required to progress towards a
commercial delivery arrangement.
2 Recommendations
2.1 It is recommended that Committee:
a) Note the content of the report and the collaborative work undertaken to date;
b) Note the content of the West Dunbartonshire Public Electric Vehicle Charging
Strategy and Expansion Plan (Appendix 1) and the forecast number of required
charging units and cost of installation;
c) Approve the participation of West Dunbartonshire Council in a collaborative
procurement to engage a commercial partner via a concession type contract
through a partnership with all eight local authorities in Glasgow City Region, to
deliver the benefits set out in the report;
d) Agree in principle to entering into an Inter Authority Agreement among the eight
local authorities, and delegate the subsequent nomination of a lead authority
for the service delivery period as well as procurement and commercial
decisions relating to the commencement and conclusion of the procurement
process to the Chief Officer – Regulatory and Regeneration, in line with the
approach set out in the report;
e) Agree that Glasgow City Region Programme Management Office, through
Glasgow City Council, will utilise local authorities Electric Vehicle Infrastructure
Fund external grant allocations to engage programme management and expert
technical consultancy support, that will assist in taking a Glasgow City Region
proposition to market and subsequent appointment of a commercial partner;
and,
f) Note Officers will provide update reports on the progress of the work to
Members as required throughout the development of the project.
ITEM 11

Page 2

3 Background 
3.1 This section summarises the work that has been undertaken to date to support
the expansion of the electric vehicle changing infrastructure network across the
eight local authorities in Glasgow City Region.
3.2 In January 2022, the Scottish Government launched the Electric Vehicle
Infrastructure Fund with the objective of unlocking private sector investment to
expand the publicly accessible charging network on local authority land and
assets.  A requirement to access this fund was to develop an Electric Vehicle
Strategy and Expansion Plan.  £140k was allocated to each local authority to
undertake this activity with a further £300k unlocked upon completion to support
the implementation of the electric charging units.
3.3     Transport Scotland engaged the Scottish Futures Trust to support local 
authorities in the development of each council’s electric vehicle strategies and 
is also actively encouraging local authorities to collaborate in their strategy and    
delivery activity to expand the charging network. 
3.4 In December 2021 the Glasgow City Region Cabinet agreed to progress an initial
report into current electric vehicle charging provision, tariffs, and forecast future
needs of the eight Glasgow City Region local authorities, jointly funded using the
external funding allocations from Transport Scotland for each local authority. 
The report was concluded in June 2022. 
3.5 It was further agreed by the Glasgow City Region Cabinet in August 2022 that
the Glasgow City Region Programme Management Office would engage
consultants on behalf of the local authorities to develop local Electric Vehicle
Strategy and Expansion Plans.   
3.6 Following the development of the strategy and expansion plans, the Glasgow
City Region Electric Vehicle Senior Officers’ Group was established with senior
officer representation from each of the eight Glasgow City Region member
authorities. 
3.7 The Senior Officers’ Group oversaw a Prior Information Notice, published in June
2023, to engage with the Charge Point Operators, explore market appetite and
inform Glasgow City Region’s approach to the expansion of the electric vehicle
charging infrastructure. There was significant private sector interest with 33
responses received and a clear preference expressed by most Charge Point
Operators to engage collaboratively with all eight Glasgow City Region local
authorities as part of a planned and strategic approach. 
3.8 In August 2023, the Glasgow City Region Cabinet agreed that a collaboration
between the local authorities to expand the electric vehicle charging
infrastructure network should be based upon a clear set of agreed principles: 
a) To deliver a just transition, we must ensure equitable access to electric
vehicle charging infrastructure, with a clear recognition of geographical
characteristics and the different solutions that may be applicable.

Page 3

b) Ensure that all residents are able to access electric vehicle charge points
close to their home.
c) Align with the priorities of the sustainable travel hierarchy to ensure that
public transport, walking, wheeling and cycling options are prioritised
wherever possible.
d) Collaborate across the Glasgow City Region member authorities to
identify cost savings and ways to deliver a high standard of customer
experience.
e) Work together to identify and overcome grid capacity issues.
f) Identify opportunities to develop joint public and fleet electric vehicle
charging infrastructure projects, and where there are opportunities to align
with HGV, hydrogen refuelling and the introduction of rapid and ultra-rapid
charging stations. 
3.9 At the request of the Glasgow City Region Chief Executives’ Group, further
commercial and financial analysis was undertaken during the summer of 2023,
to more fully understand the risks and opportunities of the different commercial
arrangements that local authorities could use to expand the network of electric
vehicle charging infrastructure. On 7 November 2023, the Cabinet was advised
of the conclusion of this stage of the work, and that the Chief Executive’s Group
proposed a preferred approach to progress through a continued collaboration
among the eight local authorities on the basis of a concessionary-type
commercial model. 
4 Main Issues 
4.1  The work to date indicates clear advantages of progressing with the expansion   
of the public electric vehicle charging infrastructure network as a collaboration 
of Glasgow City Regions’ eight local authorities. 
4.2   Collaborating to expand the electric vehicle charging infrastructure offers a               
range of benefits for the local authorities’ wider policy objectives and these are 
described in the following paragraphs.    
4.3 Leveraging Private Sector Investment 
Proceeding with a collaborative concession type contract provides the
opportunity to maximise the amount of private sector investment to pay for the
majority or totality of the new electric vehicle charging infrastructure.  The market
testing exercise indicated an appetite from a number of Chargepoint operators
to fully fund the expansion of the network, with none of the capital costs being
provided by the local authorities (this was dependent on other contract
conditions, such as the contract term).   
4.4 The additional charge points forecast in the Strategy and Expansion Plan
indicated a total capital cost of £71 million across the City Region. There will be
an amount of capital grant available from the Electric Vehicle Infrastructure Fund
to assist in the delivery.  The amount has not yet been agreed by Transport
Scotland. It will be an objective to develop a proposal that can be fully funded by
the commercial partner along with any Electric Vehicle Infrastructure Fund grant

Page 4

from Transport Scotland with no requirement upon the local authorities to fund
the infrastructure and service delivery costs.   
4.5 Financial and Commercial Considerations
A concession-type commercial arrangement would allow the local authorities to
transfer the potentially significant commercial, financial, technical, and regulatory
risks to a commercial partner.  It is proposed that a private sector partner would
be invited to take on the operation, maintenance, and ownership of the existing
network of 600 (approx.) local authority owned charge points in Glasgow City
Region, as well as providing the investment required to significantly expand the
number and location of charge points equitably across the City Region. 
4.6 Generating an Income Stream 
Allowing a commercial partner to operate electric vehicle charging infrastructure
on local authority land and assets has the potential to generate an income stream
for the Glasgow City Region local authorities.  This could be through a variety of
different arrangements, for example income share, revenue share, a rental fee,
or a combination. The amount and type of income stream will be influenced by
the broader commercial arrangements of a contract, such as the contract term
and where the risks and responsibilities are assigned between the local
authorities and private partners. Collaborating regionally will allow the Glasgow
City Region local authorities to pool resources generated through revenue to
meet ongoing contract management costs, as described later in this report.
However the intention would be to transfer most of the risk to the private partner
and as a consequence the level of income potential for the Council must take
this into account. Although it is not possible to determine at this stage what level
of income could potentially be delivered, what must be recognised is that the
principle intention of this proposal is to increase, at pace, the level of electric
vehicle charging infrastructure across the Glasgow City Region which in turn will
encourage the shift to electric vehicles. This will by default assist with the
Council’s net zero ambitions. In summary therefore, although there may be a
level of income generated from the proposal it will not be at a level which will
significantly address any future saving requirements for the Council. 
4.7 Economies of Scale and Reduced Duplication of Effort
While the objective of this project is to expand the electric vehicle charging
infrastructure network at no/minimal cost to the local authorities, collaboration
offers significant economies of scale and financial savings during the
developmental and delivery phases. The cost of technical consultancy support,
procurement, and programme management will be shared among the eight local
authorities.  Discussions between the Programme Management Office and
consultants during initial soft market testing prior to going to the market indicate
that this saving could be in the region of £500,000 across the authorities.   
4.8 There will be other, currently unquantified, savings in an arrangement where one
lead local authority, acting on behalf of all eight, enters into a contract with a
commercial partner, avoiding the need for eight individual procurement and
contracting exercises and the costs associated with this. It is also proposed the
long-term contract management arrangements could be undertaken by a central

Page 5

team, with the ongoing costs of this met through the pooling of an element of the
local authority income stream generated by the contract. 
4.9 Ensuring All Communities Can Access the Chargepoint Network
Through collaboration we can take a strategic approach to locating electric
vehicle charging infrastructure that supports a just transition.  Operators will be
able to make commercial decisions looking across a much larger number of
chargers and will be able to balance high usage sites against lower usage areas.
The scale of a Glasgow City Region collaboration will enable private investment
in the network where individual local authority initiatives on their own may be too
small to be commercially attractive. 
4.10 Collaborating will also offer benefits to service users through opportunities to
establish a consistent approach across Glasgow City Region to service delivery
and ‘back-office’ functions such as payment mechanisms and charging policy. 
4.11 Taking a package of sites across all local authority areas within the City Region
to the market will also avoid a situation where local authorities are going
individually and competing to secure engagement with Charge Point Operators.
This would disadvantage those areas seen as less attractive and wouldn’t meet
the objective of making electric vehicle chargers available to all, especially more
disadvantaged communities within the City Region. Taking a Glasgow City
Region collaborative approach will allow Glasgow City Region to go to the market
at scale, giving a stronger voice in the sequencing of installation and the locations
in which chargers are sited, ensuring that no communities are neglected. 
4.12 Community and Supply Chain Benefits 
Responses to the Prior Information Notice, issued in June 2023, indicated that
given the scale and commercial attractiveness of a Glasgow City Region
collaboration, some Charge Point Operators were explicit in their intention to
work with local supply chains during the installation and the ongoing
maintenance of such a large electric vehicle charging network. These
opportunities will be explored during the procurement process. As with all major
contracts, there will be a requirement for the inclusion of community benefit
clauses in the tender and procurement process.   
4.13 Charge Place Scotland 
At present the back office support (payments, fault reporting, mapping etc.) for
all the current publicly owned electric vehicle charging network is managed by
the publicly funded Charge Place Scotland. The Scottish Government have
made it clear that this funding will cease December 2025 and all back-office
support will be removed. It is critical therefore that an appropriate solution is in
place for this time and the consortium approach being proposed would include
the provision of this support and avoid each individual local authority delivering
their own back office solution. 
4.14 Potential Shape of a Glasgow City Region Electric Vehicle Charging           
Infrastructure Collaboration     
In early January 2024, the Scottish Futures Trust and officers from Glasgow

Page 6

City Region Programme Management Office undertook a series of workshops     
with officers from each of the eight local authorities.  The workshops were     
structured around discussion of key issues relating to potential: 
• commercial arrangements with a private sector partner; 
• joint working arrangements between the local authorities; and
• procurement options and routes to market. 
4.15  A number of the key technical aspects of a future commercial arrangement with
the private sector were discussed at the workshops, providing a firm basis to
develop joint tender documents that would be used in the procurement process
to identify a private partner. 
4.16 The total number of residential, destination, and journey charge points that were
forecast in the Glasgow City Region area are set out in the table below and
broken down by local authority. 
Residential AC
(7kW)
Destination AC
(7 – 22kW)
Journey - Rapid DC
(50kW +)
East Dunbartonshire 105 66 17
East Renfrewshire 143 122 29
Glasgow City 1,317 207 53
Inverclyde 172 93 36
North Lanarkshire 481 276 34
Renfrewshire 405 258 51
South Lanarkshire 467 242 33
West Dunbartonshire 141 81 9
GCR Totals 3,231 1,345 262 
4.17 Following discussions among the local authorities, Scottish Futures Trust and
Transport Scotland, and informed by the consultation with the market through
the Prior Information Notice issued in June 2023, the proposed approach
discussed with the Electric Vehicle Senior Officers’ Group and the Chief
Executives’ Group, is to split the total number of forecast charge points into a
series of phases.  This pragmatic approach will help to align installation with the
capacity of the market and of local authorities to deliver across the proposed
sites. Prior to going to market we are unable to put a time on when works will
be completed but anticipate that works will be completed in a three year period
from commencement. 
4.18 The proposed approach for the Glasgow City Region is that the first phase of
charge points should include: 
- all existing EVCI (approximately 600);
- all destination AC (7-22kW) charge points (approximately 1,345);
- all rapid DC (50kW) charge points (approximately 262); and,
- 20-25% of the forecast residential charge points (approximately 650-800). 
The indicative figures for new infrastructure for West Dunbartonshire is as
follows: 
- all destination AC (7–22KW) charge points (approximately 81);

Page 7

- all rapid DC (50KW) charge points (approximately 9); and
- 20-25% of the forecast residential charge points (approximately 28-35).
4.19 In addition, it is also proposed that the first phase will also include sites where
there is the opportunity to install Ultra Rapid Charging (100kW to 350kW). A
number of sites have been identified that meet a set of basic criteria where they
may be attractive as ultra-rapid charging stations. Further work will be required
to identify which of these sites can be progressed. At present West
Dunbartonshire has identified approximately eight sites. 
4.20 The exact number of locations and charge points will be determined during the
site selection process.  Each local authority will require to undertake their own
analysis about the suitability of the proposed locations for charging
infrastructure included in the Strategy and Expansion Plan and to provide a list
of sites within their area to be included in the package that is offered to a
commercial partner.  Each local authority will also be asked to prioritise these
sites.  Charge Point Operators may suggest alternative sites based upon
experience in delivering Electric Vehicle Hubs and this may assist the local
authorities in identifying and agreeing alternative charging locations as
required. 
4.21 It is anticipated that subsequent phases will be weighted towards the remaining
residential charging infrastructure, and any additional journey and destination
sites that are identified. During the development of the procurement documents
a strategy for bringing future phases to the market will also be considered. 
4.22 Joint Working and Procurement Options
The feedback from the officer workshops demonstrated support for a
collaboration across Glasgow City Region through the planning, procurement
and delivery stages.  There was also a recognition of the need to put in place
an Inter-Authority Agreement to facilitate this collaboration. 
4.23 There was a consensus view expressed in the workshops that one local
authority should contract with a commercial partner on behalf of all eight
member authorities, with a preference for a single procurement, rather than
establishing a framework for local authorities to draw down from. This learning
has been taken from the successful Clyde Valley Residual Waste partnership. 
4.24  Draft Timeline 
The operational timeline for delivery of the project is indicative at this time and
the key milestones are set out below: 
Action/Milestone Estimated Date/Timescale
Appoint Consultants to Support Development
of Tender and Proposal
May/June 2024
Preparation of Tender Documents  June to November 2024
Commence Procurement December 2024/January to
April 2025
Evaluation of Tenders  May to June 2025

Page 8

Contract Awarded to CPO July to August 2025
Charge Place Scotland Transition  
Network Planning & Mobilisation
September to December 2025 
New Chargepoint Installations January 2026 onwards 
4.25 Governance and Support Arrangements  
A collaboration of the eight Glasgow City Region local authorities will require a
clear governance and decision-making process. In addition to endorsement by
the Glasgow City Region Cabinet, the key decisions will require the approval
through the relevant local governance structures of each of the eight authorities. 
In West Dunbartonshire’s reports will be presented to the Infrastructure,
Regeneration and Economic Development Committee for consideration and
approval. 
4.26 The collaboration will also require an Inter Authority Agreement to be put in
place and signed off by all eight Glasgow City Region local authorities.  In order
to allow the project to meet the proposed timeline set out above, this report
proposes that: 
- the approval of the Inter Authority Agreement;
- issuing of the tender documents; and,
- approval of the preferred bidder and agreement to enter into a contract;
is delegated to the Chief Officer – Regulatory and Regeneration on behalf of
the Council.
4.27 All eight local authorities will require to approve the proposed approach through
their own local governance structures prior to any contract being entered into.
A longer-term agreement between the eight Glasgow City Region local
authorities will be finalised at the point of entering into a contract with a
commercial partner and this will include the ongoing contract management
arrangements. 
4.28 In order to support the development of the tender documents, site selection
process, and development of the Glasgow City Region Electric Vehicle
Charging Infrastructure proposal, the Programme Management Office will
continue to provide support to the Electric Vehicle Senior Officers’ Group.
Expert technical consultancy support will be engaged and funded by
contributions from each local authority through their allocations from Transport
Scotland’s Electric Vehicle Infrastructure Fund. 
4.29 To ensure each local authority is engaged in the development process and able
to influence the development of the tender, officer support groups will be
established to provide expert advice and to update their own organisations as
required. In addition to the existing Electric Vehicle Senior Officers’ Group, it
would also require groups with a focus on legal, procurement, and technical
aspects.

Page 9

5 People Implications 
5.1 Resources within Procurement, Legal, Finance, Assets and the Roads
Service will be required to both develop and monitor the Inter Authority
Agreement, review and shape the Procurement Strategy and undertake a site
selection process to ensure that the needs and requirements of the council
are reflected within the tender scope. 
6 Financial, Legal & Procurement Implications 
6.1  The Transport Scotland’s Electric Vehicle Improvement Fund to meet the costs
of the development of the Glasgow City region proposal, development of the
procurement documents, specialist external legal advice, and other costs
associated with the development of the collaboration. Each local authority will
contribute a portion of their grant award which will be pooled by the Glasgow
City Region Programme Management Office who will engage the required
consultancy and advice services on behalf of the eight local authorities as
required. 
6.2     The overarching aim of the approach set out in this report is to leverage private 
sector investment so that no/or minimal capital investment is required from the 
local authorities to deliver the expansion in electric vehicle charging          
infrastructure.  On this basis there is not anticipated to be any requirement for          
capital investment.   
6.3      It is anticipated that the long-term contract management of the commercial     
arrangement will be met by the collective income stream that is generated.  It is     
suggested that the income stream from a commercial partner is pooled to meet 
the central contract management costs, with the surplus income then being 
distributed among the local authorities based upon an agreed formula. 
6.4      Overall, there should be no cost to the local authorities from this proposed     
approach.  However, this will depend on the market appetite to engage with     
Glasgow City Region and can only be confirmed on conclusion of the 
procurement process.   
6.5      The main legal requirement will be the establishment of an Inter Authority     
Agreement that allows one local authority to act as lead in the process to 
procure and contract with a commercial partner on behalf of the other eight     
authorities. 
6.6      There will be a requirement for expert external legal advice to support the     
development of the proposal and this will be engaged by the Programme     
Management Office. 
6.7      A legal support group, consisting of solicitors from each of the eight local 
authorities, will be established to support the development of the project.

Page 10

7        Risk Analysis 
7.1 Due to Transport Scotland’s decision not to renew the Charge Place Scotland
contract all local authorities are required to put in place an alternative
arrangement for the back-office and maintenance of their charge points before
December 2025.  Glasgow City Region’s proposal is to have these 600
(approx.) existing charge points included within the scope of the first phase of
implementation, however there is a significant risk that the timing of this new
arrangement being in place will fail to align with Transport Scotland’s ending of
the Charge Place Scotland service. 
The Programme Management Office is liaising closely with Transport Scotland
to identify potential mitigations for this risk. 
8        Equalities Impact Assessment 
8.1      Screening and impact assessments will be carried out as required as detail is 
available on the phased implementation of the electric vehicle charging 
infrastructure. 
9        Consultation 
9.1  The preparation of the Inter Authority Agreement and tender documents will
be undertaken in consultation with the appropriate Officers. 
10       Strategic Assessment 
10.1  The project will support the successful delivery of the strategic priorities and
objectives of the Council. 
Chief Officer: Gail Macfarlane
Service Area:  Roads and Neighbourhood
Date:   23 April 2024
_____________________________________________________________ 
Person to Contact:  Liam Greene    
Roads and Transportation Manager    
Liam.greene@west-dunbarton.gov.uk 
Appendices:  Appendix 1: Public Electric Vehicle Charging Strategy
and Expansion Plan

Page 11

Wards Affected: All