Page 1

Appendix 2: Regulatory & Regeneration Delivery Plan 2024/25 - Economic Development
1. Introduction
Regulatory & Regeneration comprises a wide range of services covering legal, trading standards, licensing, records management,
planning, building standards, environmental health, democratic and registration services, economic development and procurement.
It is one of seven strategic areas responsible for delivering the Council’s Strategic Plan. Key actions to help achieve that are set out
in this Delivery Plan, together with actions to address any performance issues and service priorities identified in the planning
process.
The progress of this Plan will be monitored and managed by the management team and reported to Corporate Services Committee
and Infrastructure, Regeneration & Economic Development Committee (economic development elements only) twice yearly, at mid-
year and year-end.
2. Performance Review
The management team completed a detailed review of 2023/24 performance, focusing on the following:
• 2023/24 Delivery Plan year end progress;
• Local Government Benchmarking Framework comparative data;
• National Planning Improvement Framework;
• Citizens’ Panel feedback;
• Telephone Survey feedback;
• Complaints; and
• Continuous Improvement.
This review highlighted our key achievements and challenges in 2023/24. These are summarised below.
ITEM 8 -
APPENDIX 2

Page 2

Key Achievements in 2023/24
Listed below are some of the major achievements in each service area that were particularly challenging or unusual.  All services
achieve many other fantastic outcomes for the Council and its residents throughout the year which are not recorded here but are
often as important.
Cross Service
• Implemented the Short-Term Let Licence regime with over 90 applications processed within a short time frame, working with
other Council services including Environmental Health and Building Standards to ensure that the accommodation was of a
suitable standard.
• Expansion of the Queens Quay District Heating Network continued, with the connection to 46 Clydebank Housing Association
flats.
• Infrastructure, Regeneration and Economic Development Committee approved the Masterplan for the redevelopment of the
Artizan Centre as part of the Levelling Up Fund programme.
• Infrastructure funding package over £44m and Final Business Case approved for the former Exxon site by the Council and City
Region Cabinet and planning permission secured.
Economic Development and Regeneration
• Stage 1 bid to Glasgow City Region Investment Zone submitted, with the Council now supporting a Stage 2 bid for the Scottish
Marine Technology Park to be part of an Advanced Manufacturing Investment Zone.
• Provided support to 200 new business start-ups and developed and implemented a range of business interventions through the
UK Shared Prosperity Fund to provide growth support to local businesses.
• Developed a new Economic Development Strategy Action Plan for 2022 to 2027, providing a clear strategic approach to
economic development and resource allocation to improve economic performance.
• Delivered improvements in Alexandria Town Centre and launched a Community Grant scheme for community groups and
organisations in West Dunbartonshire using Place Based Investment Programme funding.
• Reinvigorated the Climate Change Action Plan delivery group.
• Upgrading of Building Management Systems across the majority of the Council estate completed.
• Local Heat and Energy Efficiency Strategy was approved by Committee in February 2024 for wider consultation.

Page 3

Key Challenges in 23/24
Economic Development and Regeneration
• Delivering private sector homes at Queens Quay continued to be a challenge in 2023/24 but we meet with our commercial
partner regularly to monitor and encourage development interest.
• Businesses continued to face many economic challenges in 2023/24, including rising inflation and energy costs. The business
interventions developed through the UK Shared Prosperity Fund and the on-going advice and support available through
Business Gateway will continue to provide assistance to help them recover and grow in the year ahead.
• Delivery of the Levelling Up Fund programme of works in Dumbarton town centre against tight funding timescales was
challenging given the multi-disciplinary support and buy-in from a number of different stakeholders required to develop and
deliver projects of this nature.
• With temporary resource challenges, it was challenging to adequately resource all projects and to meet some of the tight
deadlines associated with external funding.
• Despite carbon emissions for 2022/23 showing a reduction from 2021/22, it is becoming increasingly difficult to achieve the
targets as outlined in our Climate Change Strategy. In order to ensure Net Zero targets are met for 2045, additional resources
and finance will require to be considered if we are to meet future targets.
• The Cost of Living crisis has seen a significant uplift in the number of residents requiring Energy Efficiency support. This has
proved challenging to facilitate within our existing resources.
3. Strategic Assessment
The Regulatory & Regeneration management team completed a detailed strategic assessment to determine the major influences
on service delivery and priorities in 2024/25 and beyond. This covered a review of local and national political priorities, new
legislation and technology, Council policies, and our continued recovery from the pandemic, cost of living crisis and the financial
challenges facing the Council. The key issues are outlined below.
Key Factors
Financial Challenges
The entire public sector is continuing to face significant financial challenges due to a range of factors including inflationary cost
increases, pay awards not being fully funded by the Scottish Government and insufficient overall funding to support the delivery of

Page 4

front line and back office services. The Council are currently faced with an estimated cumulative funding gap in 2025/26 of £9.8m
rising to £40.4m by 2028/29.  We will continue to monitor the overall financial position of the Council and updates on estimated
future budget gaps will be reported to Elected Members throughout 2024/25.
These challenges require further action to balance our budget and protect services for residents. Within Regulatory &
Regeneration, this means that available funding will be reduced over time and we will need to reconfigure how we work, what we
do, where we work, and potentially reduce the number of people employed. In this context, we will aim to continue to provide a
sustainable, quality service to internal clients and the public.
Budget Sensitivity Analysis
In reviewing the service budget projections, consideration has been given to the sensitivity of these budgets, in particular for higher
risk/ higher value budgets which may have a significant impact on budgetary control and future budget projections. The analysis
has considered sensitivity around demand, costs and charges, and income levels. 
In Regulatory and Regeneration there were no budgets identified as being more susceptible to fluctuations. However, on a more
Council-wide basis, the Council’s cost of borrowing is susceptible to fluctuations in the bank interest rate due to the level of the
Council’s short-term borrowing.
Economic Development Action Plan
An Economic Development Strategy Action Plan for 2022/27 was approved by Infrastructure, Regeneration and Economic
Development Committee in November 2023. It sets out the vision and priorities for delivering economic growth and improved well-
being in West Dunbartonshire’s communities and is aligned to the Strategic Plan 2022/27, the Glasgow City Region Economic
Strategy and the Scottish Government’s National Strategy for Economic Transformation. The action plan to deliver the strategy has
been developed for implementation in 2024/25. It focuses on delivering key regeneration sites, developing the Queens Quay site,
identifying and developing commercial opportunities, supporting business recovery, and supporting town centre revitalisation
(details below).  The action plan will be implemented throughout 2024/25 and progress monitored and reported to Infrastructure,
Regeneration and Economic Development Committee. 
Action: Implement, monitor and report the progress of the 2024/25 Economic Development action plan

Page 5

Deliver Key Regeneration Sites
A number of key regeneration projects, which span multiple years, will continue to be taken forward in 2024/25. These include:
• Infrastructure delivery on the Exxon site;
• Alexandria Masterplan which will transform the  town centre and surrounding areas;
• Clydebank Town Centre Development Framework which will inform interventions delivered funded through the Long-Term Plan
for Towns over the next 7-10 years;
• Securing planning approval for the Scottish Marine Technology Park (SMTP) at the Carless site, and pursuing funding
opportunities including Vacant and Derelict Land fund and Investment Zone; and
• A range of projects funded through the £20m Levelling Up fund, including the redevelopment of Glencairn House, the
regeneration of the Artizan Shopping centre, and connecting Dumbarton Central to the Town Centre, all of which will have a
significant impact on Dumbarton and the town centre vibrancy.
Actions: Deliver key regeneration sites across West Dunbartonshire; Ensure regeneration sites are progressed to enable high
quality development to be achieved on the ground and; Monitor the development of the key regeneration sites to ensure they
comply with the approved consent
Queens Quay
Infrastructure works for this 80 acre residential waterfront development were completed in 2020/21. In the year ahead, the focus on
securing housing developments across the site in partnership with site owner Clydeside Regeneration Ltd. will continue. This
continues to be a challenge, particularly in relation to flatted private homes which the market is finding commercially challenging.
Discussions will continue with a range of public and private sector parties. 
Action: Promote the next phase of Queens Quay Housing
Deliver Key Commercial Opportunities
Identifying commercial opportunities in conjunction with the private sector will continue to be a priority. Discussions with developers
who may wish to enter a partnership with the Council to achieve joint benefits from a commercial, housing and low carbon

Page 6

perspective will be progressed. The Regeneration Capital Fund with £12.77m has been allocated across a number of projects. The
Fund’s key operating principles and allocations to specific projects agreed by Committee will be progressed. Opportunities include:
• Exxon – as infrastructure works progress, the Council will consider how to promote and deliver the best uses for the site and,
working with the City Region and Scottish Enterprise, will encourage developer interest in the site to meet the growth targets set
out in the City Deal business case.
• NHS Golden Jubilee – we will seek to deliver the extension of the District Heating network to the hospital and explore
opportunities presented by the expansion of the hospital for development and regeneration of Queen Quay and Clydebank,
generally.
• Scottish Marine Technology Park – we will continue to work with the Malin Group in their ambition to deliver the Scottish Marine
Technology Park at the former Carless site near Old Kilpatrick, and assist them in attracting business and funding to the site. A
project board has been established to provide support and direction as the Malin Group progress the development through the
planning and infrastructure implementation stages.
Action: Explore commercial opportunities in our town centres and wider regeneration sites
Supporting Business Recovery
In April 2022 the UK government launched the UK Shared Prosperity Fund, a central pillar of the UK government’s Levelling Up
agenda, providing funding for local investment across the UK by March 2025. A Local Investment Plan has been developed and
approved by the UK Government as part of a wider Glasgow City Region Investment Plan through the Fund. The business support
proposals within the Investment Plan will be available until March 2025 to support business recovery and include a Business
Recovery & Growth fund, Early Stage Growth grants, Towards Net Zero Grant, Enhancing Tourism Events & Attractions Fund,
Business Gateway Expert Help and Shopfront & Small Business Improvement Grants.
Action: Develop and implement business support interventions through the UK Shared Prosperity Fund
Supporting Town Centre Revitalisation
Assisting town centres to recover from the pandemic and cost of living crisis will continue to be a focus in 2024/25, with support for
high street businesses a key priority and in response to community needs. We will continue to develop projects to make our town

Page 7

centres attractive places and take advantage of the external funding, including UK Government’s levelling up programme and
Place-Based Investment Programme funds provided by Scottish Government.
• Clydebank has been awarded £20 million funding from the UK Government as part of the Long-Term Plan for Towns. This
funding will support delivery of the projects which originate from approved Clydebank Development Framework and reflect the
priorities of the local community. The Framework provides a vision for how the town will be transformed, from reducing retail
dominance to a vibrant mixed use and inhabited town centre that meets the needs of the whole community. It includes, among
other interventions, development of the former Playdrome site, a transport hub at Clydebank Station, improved connections
between the town centre and Queens Quay, and related community-led activity. We will look for ways to secure additional
funding and attracting commercial and other development interest. A Clydebank Town Board, chaired by Liz Connolly Principal
of West College Scotland will be established to oversee the Fund and Plans.
• In Dumbarton, the focus for the next year and beyond will be the Levelling Up Fund programme of works including the
refurbishment and reuse of Glencairn House as a library and museum and the revitalisation of the Artizan Centre. Another
levelling up project, Connecting Dumbarton, was completed in early 2024.
• In Alexandria the next phase of the 2021 Masterplan will be implemented, with an emphasis on place based funded projects.
This will include improved walking and cycling routes, town centre building improvements and projects that directly respond to
local community and business priorities.
Action: Support town centre revitalisation
Climate Change Action Plan
The Council developed a Climate Change Strategy in response to the climate emergency and to provide a route map towards
meeting Scotland’s national net zero carbon target by 2045. This Strategy informs annual action plans, with actions devolved to
relevant service areas. Progress against the 2024/25 action plan will be monitored and reported to senior management and Council
on a regular basis.
Action: Co-ordinate, monitor and report the progress of the Council’s Climate Change Action Plan for 2024/25

Page 8

Local Heat and Energy Efficiency Strategy (LHEES)
During 2023/24, the Council commenced works on a Local Heat and Energy Efficiency Strategy (LHEES) which will set out the
long-term plan for heat decarbonisation and improved energy efficiency of buildings throughout the Council area. The consultative
draft Strategy was approved in February 2024.  Scotland’s statutory greenhouse gas emissions reduction and fuel poverty targets
will be the drivers of this area-based approach. When the final strategy is approved, it will set out the changes needed to each
sector of buildings stock, identify strategic heat decarbonisation zones and prioritise delivery areas. A Delivery Plan will accompany
the LHEES, developed in partnership with key stakeholders.   
Action: Develop Local Heat and Energy Efficiency Strategy and Delivery Plan
Continuous Improvement
Continuous improvement is central to all that we do. The actions set out in this section, as well as those at an operational level not
included in this Delivery Plan, demonstrate our commitment to continuous improvement and take account of the wider Best Value
focus on vision and leadership; governance and accountability; effective use of resources; partnerships and collaborative working;
working with communities; sustainability; and fairness and equality. 
Action Plan
The challenges identified in Section 2 and the key factors identified in Section 3 have informed Regulatory & Regeneration priorities
for 2024/25. Appendix 1 sets out the action plan to address them. It also includes:
• performance indicators that will enable progress to be monitored and reported to stakeholders;
• strategic workforce actions to address workforce issues identified in the planning process; and
• strategic and/or service risks.
In relation to the latter, strategic risks represent the potential for the Council to take advantage of opportunities or fail to meet stated
strategic objectives and those that require strategic leadership. Service risks relate to service delivery and represent the potential
for impact on individual services, or the experience of those who work within the services, i.e. employees, partners, contractors and
volunteers, or service users and clients in receipt of the services provided. In identifying the relevant risks for 2024/25 and actions
to mitigate them, we aim to improve or maintain the current position (i.e. the current risk score) set out in the appendix.

Page 9

4. Resources
Finance
The Finance team are currently creating the detailed service budgets to accurately reflect all savings, management adjustments
and other budget adjustments agreed by Council on 6 March 2024. Once this is complete the service plans will be updated with
each Service’s Gross Expenditure, Gross Income and Net Revenue Expenditure Budgets. 
Employees
Employee Numbers
The headcount and full time equivalent (FTE) staff in each service area (as of 31st March 2024) are as follows:
Absence
The 2023/24 quarterly absence figures for Regulatory & Regeneration are shown below together with the Council average for the
same periods for comparison. Absence was significantly lower the Council average throughout 2023/24:
Absence in 2023/24 Quarter 1 Quarter 2 Quarter 3 Quarter 4 Annual FTE days lost
per FTE employee
Regulatory and Regeneration Headcount FTE
Democratic and Registration Services 21 18.36
Economic Development 16 15.03
Legal Services 21 20.26
Planning, Building Control 36 34.30
Regulatory Management 3 2.80
Procurement 10 9.86
TOTAL 107 100.61

Page 10

Regulatory &
Regeneration
0.86 1.72 1.53 2.52 5.94
COUNCIL WIDE TOTAL 3.64 3.36 4.67 5.01 13.74
Appendix 1: Action Plan
Please Note: PI targets for 2024/25 are indicative until 2023/24 year-end data becomes available.
Our Environment
Our resources are used in an environmentally sustainable way
Performance Indicator
2024/25
Owner
Target
Tonnage of carbon dioxide emissions from Council operations and assets 19,342 Rachel Moir
Action Due Date Owner
Co-ordinate, monitor and report the progress of the Council’s Climate Change Action Plan for
2024/25 31-Mar-2025 Rachel Moir
Develop Local Heat and Energy Efficiency Strategy and Delivery Plan 31-Mar-2025 Rachel Moir

Page 11

Risk Description Current
Assessment
Target
Assessment Owner
Inability to reduce
carbon footprint in line
with targets
The risk that the Council will be unable to achieve net
zero emissions by 2045, both in relation to mitigating
carbon emissions and adapting to the impacts of climate
change. Net zero refers to achieving an overall balance
between emissions produced and emissions taken out of
the atmosphere. This target has been developed in a
way that mirrors the emission reduction trajectory set by
the Scottish Government in light of the Climate
Emergency.
Gillian
McNamara
Our neighbourhoods are sustainable and attractive
Action Due Date Owner
Promote the next phase of Queens Quay Housing 31-Mar-2025
Pamela Clifford;
Gillian
McNamara
Our Economy
Our area has the infrastructure for sustainable and inclusive growth where businesses can flourish
Performance Indicator
2024/25
Owner
Target
Number of businesses given advice and assistance to start up through Business Gateway 180 Gillian Scholes

Page 12

Performance Indicator
2024/25
Owner
Target
No of business gateway start-ups per 10,000 population 19.78 Gillian Scholes
Proportion of properties receiving superfast broadband 100% Gillian Scholes
Action Due Date Owner
Implement, monitor and report the progress of the 2024/25 Economic Development action plan 31-Mar-2025 Gillian McNamara
Deliver key regeneration sites across West Dunbartonshire 31-Mar-2025 Gillian McNamara
Explore commercial opportunities in our town centres and wider regeneration sites 31-Mar-2025 Magda Swider
Develop and implement business support interventions through the UK Shared Prosperity Fund 31-Mar-2025 Gillian Scholes
Support town centre revitalisation 31-Mar-2025 Magda Swider
Risk Description Current
Assessment
Target
Assessment Owner
Failure to deliver
Queens Quay
Masterplan
Following completion of Council investment there is a
risk the housing plot sales do not materialise in the next
3-7 years, with implications for the return on investment
and the business case for the District Heating Network.
Pamela Clifford;
Gillian
McNamara
Inability to meet
demands of Council to
progress regeneration
projects within desired
timescales
The number and complexity of regeneration projects is
putting considerable strain on the resources available
which can be exacerbated by delays out with the control
of the service and when pinch points on different
projects occur at roughly the same time.
Pamela Clifford;
Alan Douglas;
Gillian
McNamara

Page 13

No embedded text on this page.