Page 1

WEST DUNBARTONSHIRE COUNCIL
Report by Chief Officer - Regulatory & Regeneration
Committee: Infrastructure, Regeneration and Economic Development
Committee 22 May 2024
Subject: Regulatory & Regeneration Delivery Plan 2023/24 - Economic
Development Year-end Progress &
Regulatory & Regeneration Delivery Plan 2024/25 - Economic
Development
1 Purpose
1.1 This report sets out the year-end progress of the 2023/24 Delivery Plan and
presents the new Delivery Plan for 2024/25 in relation to Economic
Development.
2 Recommendations
2.1 It is recommended that Committee notes the progress achieved at year-end
and the new Plan for 2024/245.
3 Background
3.1 In line with the Strategic Planning & Performance Framework, each Chief
Officer develops an annual Delivery Plan which sets out actions to help deliver
the Strategic Plan and address the performance challenges and service
priorities identified in the planning process. The Plan also provides an
overview of services and resources, including employees and budgets, sets
out the performance indicators (PIs) for monitoring progress and considers the
relevant risks.
4 Main Issues
2023/24 Year-end Performance
4.1 The 2023/24 Delivery Plan was presented to Infrastructure, Regeneration and
Economic Development Committee on 24 May 2023 and mid-year progress
reported on 1 November 2023.
4.2 Full details of year-end progress are set out in Appendix 1.
4.3 The progress of the Plan’s eight Economic Development actions is
summarised below:
Progress No. (%)
Completed 7 (88%)
Delayed 1 (12%)
ITEM 8

Page 2

4.4 Delayed actions relate to the following and will be carried forward and
completed in 2024/25:
• Explore commercial opportunities in our town centres and wider
regeneration sites - 71% complete. 
4.5 Year-end data is available for one of the Plan’s four Economic Development
PIs and this exceeded target. 
4.6 The full set of PIs will be reported through the Council’s annual performance
reporting process once all data becomes available. 
2024/25 Plan 
4.7 An extract from the Regulatory & Regeneration 2024/25 Delivery Plan is
included in Appendix 2. This sets out the achievements and challenges for
Economic Development over the past year, as well as the priorities for the
year ahead, namely:
• delivering sustainable, quality services within the context of significant
financial challenges;
• implementing the Economic Development Action Plan which focuses on
delivering key regeneration sites across West Dunbartonshire, promoting
the next phase of Queens Quay Housing, exploring commercial
opportunities, and supporting business recovery and town centre
revitalisation;
• monitoring and reporting the Climate Change Action Plan; and
• developing a Local Heat and Energy Efficiency Strategy and Delivery Plan. 
4.8 Implementation of the Plan will be monitored by the management team with
mid-year and year-end progress reported to Infrastructure, Regeneration and
Economic Development Committee around November 2024 and May 2025
respectively. A separate report on the Place Based Investment Programme
will be submitted to a future meeting of the IRED committee. 
5 People Implications 
5.1 There are no direct people implications arising from this report. 
6 Financial & Procurement Implications 
6.1  There are no direct financial or procurement implications arising from this
report. 
7 Risk Analysis 
7.1 Failure to deliver on the actions assigned to Economic Development may
have a direct impact on the delivery of the Council’s Strategic Plan. It is
essential that remedial action is taken to ensure strategic delivery plans
achieve the commitments detailed and approved.

Page 3

8 Equalities Impact Assessment 
8.1 Screening and impact assessments will be carried out on specific activities as
required. 
9 Consultation 
9.1  The delivery plans were developed through consultation with officers from the
strategic service areas. 
10 Strategic Assessment 
10.1  The delivery plans set out actions to support the successful delivery of the
strategic priorities and objectives of the Council. 
Chief Officer: Alan Douglas
Service Area:  Regulatory & Regeneration
Date:   2 May 2024
_____________________________________________________________ 
Person to Contact:  Lynn Henderson    
lynn.henderson@west-dunbarton.gov.uk 
Appendices:  Appendix 1: Regulatory & Regeneration Delivery Plan
2023/24 - Economic Development Year-end Progress 
Appendix 2: Regulatory & Regeneration Delivery Plan
2024/25 - Economic Development 
Background Papers: Regulatory & Regeneration Delivery Plan 2023/24 -
Economic Development, Infrastructure, Regeneration and
Economic Development Committee, 24 May 2023 
Regulatory & Regeneration Delivery Plan 2023/24 -
Economic Development Mid-year Progress,
Infrastructure, Regeneration and Economic Development
Committee, 1 November 2023 
Strategic Planning & Performance Framework 2022/27   
Wards Affected: All