Appendix 1 - R&N Delivery Plan Year-end Progress 23/24
1. Our communities
Objective 1. Our neighbourhoods are safe, resilient and inclusive
Performance Indicator
2022/23 2023/24
Owner
Value Status Value Target Short Trend Long Trend Note
Percentage of non serious road related defects
repaired within 7 working days of being reported 92.65% 91.4% 85% Target achieved. Liam Greene
Percentage of routine road related defects repaired
within 28 working days of being reported 37.7% 69.25% 85%
Target missed. Significant
improvement on previous year and
steady improvement over this year
with a higher percentage being
permanently repaired through the
structural patching programme.
Liam Greene
Percentage of emergency road related defects
repaired within 4 hours of being reported 96% 96.9% 95% Target achieved. Liam Greene
Percentage of all traffic light repairs completed
within 48 hours 100% 100% 98% Target achieved. Liam Greene
Percentage of all street light repairs completed
within 7 days 98.75% 98% 95% Target achieved. Liam Greene
Objective 2. Our residents health and wellbeing remains a priority
Action Status Progress Due Date Note Owner
Upgraded play parks and recreation facilities 31-Mar-2024
First phase complete, with 8 play parks identified in
Dumbarton, Bonhill, Alexandria, Clydebank and Old
Kilpatrick. The contracts have been awarded with
upgraded play parks expected to be delivered during
Ian Bain
ITEM 7 -
APPENDIX 1

Page 2

Action Status Progress Due Date Note Owner
summer of 2024.
Completion of delivery of  new sport facilities at
Posties Park 31-Mar-2024 Action successfully completed. New sport facility
now open. Ian Bain
Objective 3. Our residents are supported to increase life and learning skills
Action Status Progress Due Date Note Owner
Progress Faifley Campus in line with agreed
programme 31-Mar-2024
Action progressing as planned. Design complete and
approved at Learning Estate Project Board. Pre-
planning Members Seminar complete with Planning
application submitted following seminar. Planning
application now approved and Faifley tendering
report approved. Next phase will progress in
2024/25.
Craig Jardine
2. Our Environment
Objective 4. Our local environment is protected, enhanced and valued
Performance Indicator
2022/23 2023/24
Owner
Value Status Value Target Short Trend Long Trend Note
% Residents satisfied with the Waste service
overall 82% 82% 82% Target achieved. Performance
consistent with previous year. Ian Bain
Percentage of missed bins collected within 3
working days of being reported 98.7% 97% 95% Target achieved. Ian Bain
Percentage of offensive graffiti removed within 24
hours of being reported 100% 100% 100% Target achieved. Ian Bain
Percentage of non offensive graffiti removed within
5 working days of being reported 100% 100% 100% Target achieved. Ian Bain
% of total household waste that is recycled 38.1% 60% 2023/24 year-end data not yet Ian Bain

Page 3

Performance Indicator
2022/23 2023/24
Owner
Value Status Value Target Short Trend Long Trend Note
available.
% residents satisfied with the street cleaning
service 72% 78% 73% Target exceeded. Performance
improved from previous year. Ian Bain
% Residents satisfied with Parks & open spaces 84% 77% 85%
Target marginally missed, with
improved performance in quarter 4.
The progress of a number of
initiatives which are underway
including improving play parks should
continue to increase satisfaction.
Ian Bain
Percentage of abandoned vehicles that require to
be removed by the council that are removed within
14 days
100% 100% 100% Target achieved. Ian Bain
Action Status Progress Due Date Note Owner
Prepare for introduction of Deposit Return
Scheme 31-Mar-2024
Action complete. All preparatory work has been
done. The introduction of deposit return scheme has
been delayed to 2025/26. Options Appraisal and
Communications Strategy will be implemented in
advance of introduction.
Gail Macfarlane
Develop Strategy for transition to electric fleet 31-Mar-2024
Action complete. Review of vehicle replacement
programme to identify opportunities to move to
electric fleet, and reflect budget decision on
reduction in hire vehicles. Procurement route to
market underway. Next phase will progress in
2024/25.
Craig Jardine
Finalise the delivery of suitable new allotment
sites 31-Mar-2024
This action will be carried forward into 2024/25. The
contract has been awarded and work is underway.
Expected completion of the Dillichip Loan site is
Summer 2024. Residents on the allotment waiting
list have been informed and offered the opportunity
of a plot at Dillichip loan on completion
Ian Bain
Develop a new local bio diversity action plan 31-Mar-2024
This action will be carried forward into 2024/25.
Progress of this action has been delayed.
Consultation is complete and the plan will be
developed into 2024/25.
Ian Bain
Continue to explore alternative methods of
weed control 31-Mar-2024
This action is complete. Evaluation has identified
that there are currently no operationally cost
effective alternatives available. We will continue to
Ian Bain

Page 4

Action Status Progress Due Date Note Owner
pursue alternatives.
Develop Ash die back action plan 31-Mar-2024
This action has been delayed and will carry over into
2024/25. Operational process agreed to deal with
cases that are identified on a risk based approach.
Plans underway to procure a consultant to carry out
full audit to inform the Council wide action plan.
Ian Bain
Objective 5. Our resources are used in an environmentally sustainable way
Performance Indicator
2022/23 2023/24
Owner
Value Status Value Target Short Trend Long Trend Note
Tonnage of biodegradable municipal waste
landfilled 16,402 13,300 2023/24 year-end data not yet
available. Ian Bain
Action Status Progress Due Date Note Owner
Develop proposal for resource recycling and
reuse centre (RRRC) 31-Mar-2024
Action complete. Committee approved preferred
location and to proceed to detailed design. Tender
Route approved and appointment of consultant
underway. Next phase will progress in 2024/25.
Ian Bain
Develop Long term waste strategy 31-Mar-2024 Action complete. Waste Strategy and Action Plan
approved at August Committee. Ian Bain
Develop an Implementation Strategy and
expansion plan for EV charging points 31-Mar-2024
Action complete. Service working closely with GCC
group to progress. The strategy will be reported at
the next suitable committee. Next phase will
progress in 2024/25.
Liam Greene
Introduce charging for the use of Council owned
EV charging points 30-Jun-2023
Action complete. New charging tariff introduced and
implemented to Council owned charging points.
Charging tariff will be reviewed regularly going
forward.
Liam Greene
Objective 6. Our neighbourhoods are sustainable and attractive
Performance Indicator 2022/23 2023/24 Owner

Page 5

Value Status Value Target Short Trend Long Trend Note
% of Special Needs Adaptation projects completed
by consultancy services from receipt of referral to
carrying out survey, design and submission of
building warrant within 60 day target for type 3
projects
36% 93% 70%
Target of 70% surpassed in each
quarter helped by having a full time
architectural resource on this work
stream
Craig Jardine
% of capital projects supported by capital
investment team, delivered within agreed plan
Not
measured
for 22/23
83% 80% Target achieved. Craig Jardine
% of Class A roads that should be considered for
maintenance treatment 16.81% 19.2% 24% Target achieved. Liam Greene
% of Class B roads that should be considered for
maintenance treatment 14.6% 19.9% 24.5% Target achieved. Liam Greene
% of Class C roads that should be considered for
maintenance treatment 21.42% 23.3% 30% Target achieved. Liam Greene
Percentage of unclassified roads that should be
considered for maintenance treatment 30.19% 30.2% 37% Target achieved. Liam Greene
% Residents satisfied with roads maintenance 29% 22% 40%
Target significantly missed with
performance down on previous year.
A full review of a road maintenance
plan and roads communication and
engagement strategy is underway
with a priority action in the 2024/25
delivery plan.
Liam Greene
Action Status Progress Due Date Note Owner
Progress new Vale of Leven Cemetery extension 31-Mar-2024
Action complete. Project works progressing. Planned
final completion date end of May 2024. Ian Bain
Pavement parking, investigate and develop a
strategy in line with Scottish guidance next
phase
31-Mar-2024
Action complete. Procurement of Consultant
underway and costs for undertaking work reported
to Transport Scotland. Next phase will progress in
2024/25.
Liam Greene
Prepare a plan to introduce Parking
Enforcement 31-Mar-2024
Action progressing as planned. Application submitted
to Scottish Government, additional information has
been requested and a response is being prepared.
Consultants have been appointed and scope of work/
agreed. Next phase will progress into 2024/25.
Liam Greene
Finalise design plan for Gruggies Burn Flood 31-Mar-2024 Notification of the scheme has been provided to Liam Greene

Page 6

Action Status Progress Due Date Note Owner
Management Scottish Government and all stakeholders and
consultation has been undertaken. Funding
agreement and commencement of works will
progress in 2025.
Undertake flood management Improvement
Study for Dumbarton and Vale 31-Mar-2024
This action will carry into 2024/25. Offer for free
property level protection to high risk properties
circulated. Vegetation cutback completed and culvert
improvement works undertaken to reduce risk of
flooding to neighbouring properties.  A study has
been undertaken of the burn and will be submitted
to SEPA for consideration and permission.
Liam Greene
Undertake survey works to support the
development of a Surface Water Management
Plan for Clydebank
31-Mar-2024
This action is complete. Consultation undertaken
between WDC and Scottish Water to understand if
there are any synergies between the work they are
doing and the work that the SWMP proposes.
Options modelling is being undertaken for the top 5
hotspots. Results presented to management team.
Next phase will progress in 2024/25.
Liam Greene
Risk Description Current
Assessment Target Assessment Date Reviewed Note Owner
Impact of major adverse
weather incidents on
services
A significant period of adverse weather
may result on failure to deliver key
operational functions of R&N services
31-Mar-2024
The Business Continuity Plan would
come into effect in the event of a
major adverse weather incident.
No change to risk matrix
Ian Bain
Failure to maintain road
network during adverse
weather
A significant period of adverse weather
may result in failure to deliver key
operational functions of R&T services and
other Council services.
31-Mar-2024
Winter training programme is in place,
and business continuity plan is in
place.
No change to Risk Matrix.
Liam Greene
Failure to manage and
maintain the road network
effectively
Failure to manage and maintain the road
network effectively will have an adverse
impact on user safety, traffic movement,
air quality, economic growth and reduce
access to facilities and amenities. The
Council’s reputation as a place to live
and work with access to employment,
31-Mar-2024
Significant investment in resurfacing
works over the course of the year with
programme almost complete. Service
continues to respond to reported
defects across the network.
No change to Risk Matrix.
Liam Greene

Page 7

Risk Description Current
Assessment Target Assessment Date Reviewed Note Owner
education, leisure and health
opportunities would be adversely
affected.
Challenges in delivering
effective services in relation
to Roads & Neighbourhoods
The risk that the Council’s fails to deliver
on the three services within Roads &
Neighbourhood: Roads & Transportation,
Fleet & Waste and Greenspace. These
areas provide services across a range of
areas including managing and maintain
roads, footpaths and associated
infrastructure, managing flood risk,
grounds maintenance, street cleaning,
burial and cremation, outdoor facilities,
waste and recycling and vehicle fleet
management. Failing to ensure these
services are not fully fit for purpose could
result in adverse consequences in
relation to delivering efficient and
effective services.
31-Mar-2024
Service continues to provide full
service, monitoring in place to ensure
any adverse issues are highlighted and
appropriate actions taken.
No change to Risk Matrix.
Gail Macfarlane
3. Our Economy
Objective 7. Our area has the infrastructure for sustainable and inclusive growth where businesses can flourish
Action Status Progress Due Date Note Owner
Progress demolition of Artizan Centre within
agreed timeframes 31-Mar-2024
Action complete. Building warrant approval granted.
Tender evaluation complete and preferred contractor
appointed. We will progress the next phase 2024/25
Craig Jardine;
Support the progress of Exxon City Deal Project 31-Mar-2024
Action complete. The full business case has been
prepared, approved by Council and approved by City
Deal. Stage 1 consultation complete. We will
progress the next phase 2024/25.
Craig Jardine
District Heating Network Expansion Programme
( Golden Jubilee Hospital) 31-Mar-2024 Action complete. Project manager allocated to
provide technical support to project. Craig Jardine

Page 8

4. Our Council
Objective 10. Our workforce is resilient and skilled where digital technology supports service delivery for our residents
Action Status Progress Due Date Note Owner
Develop and implement wellbeing, employee
engagement, equality and learning and
development plans to enable capabilities,
improve resilience and promotion of a diverse
workforce
31-Mar-2024
Action complete. Team informed of plans to upskill
and support development opportunities. Provided
training and employment opportunities for 12
modern apprentices across R&N.
All Managers
Develop and implement employee life cycle
plans in line with the People First Strategy to
attract and retain the workforce.
31-Mar-2024
Action complete. Roads - Service Review now
complete, progressing to developing implementation
plan. Fleet - Service Review undertaken and
approval to move to recruitment.
All Managers
Implement service review process including role
design, use of new technology and new ways of
working to add resilience, address gaps, and
establish opportunities for efficiencies
31-Mar-2024
Action completed. For Corporate Assets team, all
required savings made for 23/24 and posts removed
from system as required. Roads and Transport
service review is underway, including role profiles to
ensure resources in place to address future needs.
Review underway to incorporate Fleet Services
within the Capital Assets manager structure.
All Managers
Develop and implement learning and
development plan and development
opportunities to improve capabilities and
resilience within the workforce.
31-Mar-2024
Action completed. All training needs identified.
Statutory Compliance training covering asbestos &
legionella has been completed for the first 6 months
of the year for Capital Assets Team.
Increased Heavy Goods Vehicle (HGV) drivers with
training and upskilling to alleviate the shortage of
qualified HGV drivers and improve our resilience.
All Managers
Objective 11. Our Council is adaptable and focused on delivering best value for our residents
Performance Indicator 2022/23 2023/24 Owner

Page 9

Value Status Value Target Short Trend Long Trend Note
% Consultancy Services project deliverables for
Housing and General Services projects that were
delivered to programme
84% 83% 80%
Target achieved. The team will
continue to support the development
of a plan for project delivery.
Craig Jardine
Action Status Progress Due Date Note Owner
R&N service review including a strategic and
structural review of roles and responsibilities
across the service.
31-Mar-2024
Action progressing as planned. A review of the full
role profile of Service Managers has been
undertaken and the reviewed reporting structure has
been implemented. The effectiveness of the
reviewed structure will be monitored.
Gail Macfarlane
Continue to identify opportunities to work
jointly with partnership in the City Region both
through procurement and service delivery
31-Mar-2024
Action complete. Council represented on City Region
Senior Officers group carrying out further work on
determining recommendation on model. A
recommendation on the EV delivery model has been
developed. The strategy and expansion plan will
follow in 2024/25.
Gail Macfarlane
Progress development of a best value proposal
for the management of biodegradable municipal
waste
31-Mar-2024
Action progressing as planned. Market testing and
interviews with prospective suppliers undertaken.
The recommended route to market is being
considered in 2024/25.
Ian Bain; Gail
Macfarlane
Complete phase 2 of the Fit for Service review
of waste services 31-Mar-2024
Action complete. Significant improvement actiosn
have been undertake, including full route review
,agreed recommendations and action now
implemented. Next phase will progress in 2024/25.
Ian Bain; Gail
Macfarlane
Undertake Greenspace Service Review 31-Mar-2024
Action complete. A full review of service staff change
against service provision has been completed. Plans
for 24/25 season in development.
Ian Bain
Progress construction of new Salt Dome 31-Mar-2024
Action complete. Construction began in January
2024 and is progressing well, following addition
works identified after site investigation. Next phase
including completion and hand over will be
progressed in 2024/25.
Liam Greene
Progress capital projects managed by
consultancy services in line with agreed plans 31-Mar-2024
Action complete. Projects continue to be reviewed
and monitored each quarter via progress meetings
and or project boards.
Craig Jardine;
Stewart Paton
Progress Depots Refurbishment Programme in
line with agreed timeframe 31-Mar-2024
Action complete. Evaluation of essential repairs to all
depots done and essential upgrade works to offices
with depots complete. Scope of garage work and
route to market for specialist approach agreed. Next
Craig Jardine

Page 10

Action Status Progress Due Date Note Owner
phase will progress in 2024/25.
Implement revised CAM team structure 31-Mar-2024 Action completed successfully with saving proposals
met. Craig Jardine
Risk Description Current
Assessment Target Assessment Date Reviewed Note Owner
Challenge to delivery of
burial and cremation
services
A number of factors may impact on
ability to deliver these services.  For
example a pandemic would create
significant immediate demand on
services.
31-Mar-2024
We have completed extensions to
Dumbarton and North Dalnottar
cemeteries, and work is almost
complete on the development of the
new Vale Of Level Cemetery. This will
mitigate the impact of any challenges
to the burial and cremation services.
No change to risk matrix.
Ian Bain
Inability to deliver priority
services as a result of fuel
shortages
A fuel shortage would significantly
impacting on our ability to provide
priority service across West
Dunbartonshire.
31-Mar-2024
Council participates in the Scottish
Government Liquid Fuels Framework
and contributes to the work of the
Scottish Government Fuel Resilience
Group. There are no issues with fuel at
this time.
No change to risk matrix.
Gail Macfarlane
Action Status
Cancelled
Overdue
Not on track
In Progress and on track
Completed
PI Status Long Term Trends Short Term Trends

Page 11

Target significantly missed
Target narrowly missed
Target met or exceeded
Risk Status
Alert
High risk
Warning
OK
Unknown
Improving
No change
Declining
Improving
No change
Declining