WEST DUNBARTONSHIRE COUNCIL 
Report by Chief Officer Roads and Neighbourhood 
Infrastructure, Regeneration and Economic Development 
on 19 August 2026 
Subject: Clydebank Surface Water Management Plan 
1. Purpose 
1.1 The purpose of this report is to present the findings of the Clydebank Surface
Water Management Plan (SWMP) and to seek Members' agreement of the
proposed strategic approach to managing surface water flood risk across
Clydebank. 
1.2 The report provides an overview of the principal flooding mechanisms
identified within the catchment area, summarises the updated hotspot
assessment, and outlines the recommended future actions required to
develop a coordinated and sustainable flood risk management programme. 
2. Recommendations 
2.1 It is recommended that the Committee: 
a) Note the completion of the Clydebank Surface Water Management
Plan;
b) Note that surface water flooding and the sewer network capacity have
been identified as the principal causes of flooding at a number of
locations across Clydebank;
c) Note the revised hotspot assessment following publication of the 2025
SEPA Flood Maps;
d) Agree the recommendation that future flood mitigation measures are
developed through a collaborative catchment-wide approach involving
West Dunbartonshire Council, Scottish Water, SEPA, Network Rail and
Scottish Canals;
e) Support continued collaboration with Scottish Water through
development of the Dalmuir System Plan and associated sewer flood
investigations; and
f) Note that future capital projects will be subject to detailed appraisal,
design development, funding allocation and committee approval. 
ITEM 7

Page 2

Unmarked
3. Background 
3.1 Under the Flood Risk Management (Scotland) Act 2009, local authorities are
required to undertake Surface Water Management Planning within areas
identified through Scotland's Flood Risk Management Planning process.
Clydebank was identified within the Clyde and Loch Lomond Local Flood
Risk Management Plan as requiring further assessment of surface water
flood risk. 
3.2 West Dunbartonshire Council commissioned a consultant to undertake a
Surface Water Management Plan for Clydebank. The original report was
completed in April 2024 and subsequently reviewed following publication of
updated SEPA Flood Maps in 2025, stakeholder workshops and ongoing
Scottish Water investigations. 
3.3 The study area forms part of a Potentially Vulnerable Area (PVA) where
approximately 1,800 people and 1,200 homes and businesses are currently
estimated to be at risk of flooding. Climate change projections indicate this
could increase to approximately 2,700 people and 1,700 homes and
businesses by 2080. 
3.4 Responsibility for flood risk management in Clydebank is shared across a
number of partners as well as individual property owners. 
3.5 West Dunbartonshire Council is responsible for: 
• Road drainage and gullies;
• Local flood risk management duties under the Flood Risk
Management (Scotland) Act 2009;
• Emergency planning and response;
• Planning and development management; and
• Maintenance of Council owned drainage assets and watercourses
where applicable. 
3.6 Scottish Water responsibilities include: 
• Public sewer networks;
• Investigating sewer flooding;
• Delivering investment through programmes such as the Dalmuir
System Plan; and 
• Maintaining public freshwater infrastructure. 
3.7 SEPA responsibilities include: 
• National flood mapping;
• Flood forecasts and alerts; and
• Strategic flood risk management planning. 
3.8 Other stakeholders such as Network Rail, Scottish Canals and developers
will also have a key role to play where their assets influence drainage or
flooding patterns.

Page 3

Unmarked 
3.9 Additionally local property owners can take measures to address flood risks
locally through proper maintenance of private drains and drainage systems
within their boundary, taking reasonable steps to protect their property from
flooding and through continued reporting of flooding incidents to the Authority
to support and develop the understanding of flood risk in the area. 
3.10 The Surface Water Management Plan was developed in accordance with
Scottish Government guidance and follows the recognised approach of: 
• Understanding flood risk;
• Identifying flood hotspots;
• Establishing objectives;
• Appraising mitigation measures; 
• Developing recommendations and future actions. 
4. Main Issues 
4.1 A comprehensive assessment of flood risk was undertaken to identify the
vulnerable locations, understand the likelihood and potential impacts of
flooding and to identify the root cause at each identified hotspot. By
developing a clear understanding of underlying flood mechanisms, it allows
the service to ensure that appropriate and effective mitigation and adaption
measures can be implemented. Historic flooding records, stakeholder
information and hydraulic modelling outputs are essential when assessing
flood risk and prioritising investment. 
The assessment included review of: 
• Historic flood records;
• Scottish Water sewer data;
• SEPA Flood Maps;
• Hydraulic modelling;
• Stakeholder information;
• Site observations. 
4.2 The study confirms that flood risk in Clydebank is not solely attributable to
surface water runoff. Instead, flooding is often influenced by complex
interactions between: 
• Surface water runoff; 
• Combined sewer network exceedance; 
• Watercourse interactions; 
• Highway drainage systems; 
• Local topography. 
4.3 As part of the initial assessment potential surface water flood risk locations
were identified using SEPA flood maps. Surface water occurs when rainfall
generated runoff exceeds the capacity of the watercourse or drainage system
resulting in water collecting on the surface and flowing overland.

Page 4

Unmarked 
The initial Surface Water Management Plan identified eleven flooding
hotspots: 
1. Second Avenue / Ramsay Street
2. Western Isles Road
3. Duntocher Road
4. Livingstone Street
5. Melbourne Avenue
6. Low Crescent
7. Dumbarton Road
8. Dunedin Terrace
9. Kilbowie Road
10. Station Road
11. Dumbarton Road (West) 
4.4 The hotspots are defined as areas containing six or more residential and/or
commercial properties which are located within areas which have a medium
likelihood of experiencing a 1 in 200 year (0.5 Annual Exceedance
Probability) event. In addition, any location where flooding could cause
significant disruption to transport, access for emergency services or wider
economic activity were also included. 
4.5 As more data and understanding of flood risk is collected SEPA review and
update the Flood Maps on a regular basis. After the publication of updated
SEPA Flood Maps in 2025 the hotspots were reviewed to determine any
changes to the extent and severity of surface water flooding.

Page 5

Unmarked
4.6 As a result of these revisions some hotspots identified from the initial
assessment no longer met the required screening criteria. The updated maps
highlighted the flood risk at several locations to be lower than previously
understood. It should be noted that flood risk will remain present at these
locations albeit at a reduced level than previously considered. 
Locations where flood risk is now considered lower than previously
understood include: 
• Low Crescent;
• Dumbarton Road;
• Dunedin Terrace;
• Livingstone Street (currently subject to further Scottish Water
investigation). 
4.7 The Linnvale area has been identified as a high impact area by Scottish
Water and they are leading investigations to better understand the causes of
flooding in this area. The outcome of these investigations will be crucial in
understanding the flooding and identifying long term solutions. Despite the
reduced risk at Livingstone Street flood risk remains an important
consideration within the area and should be reviewed again after Scottish
Water investigations are concluded. 
4.8 From the original list, 6 locations were still considered to present significant
flood risk. These include: 
Location Main Flooding Issue
Second Avenue / Ramsay Street Surface water and sewer flooding
Western Isles Road Surface water and drainage
capacity issues
Duntocher Road Surface water and sewer flooding
Melbourne Avenue Surface water and sewer flooding
Kilbowie Road Surface water flooding affecting
commercial areas
Station Road Surface water flooding affecting a
key transport route 
4.9 Full details of the root causes for each location are highlighted within section
4 of the Surface Water Management Plan however a review of the principal
flooding mechanisms at each location highlights sewer capacity as a major
contributor at all locations. 
4.10 The report concludes that sewer capacity constraints within the wider Dalmuir
catchment have a significant influence on flood risk. At Second Avenue,
hydraulic modelling identified approximately 1,500m³ of predicted sewer
flooding during a 1 in 30-year rainfall event, highlighting the significance of
sewer capacity limitations in the area.

Page 6

Unmarked
4.11 The flooding experienced in Clydebank is increasingly understood to be a
catchment-wide issue rather than a series of isolated local problems.
Significant sewer flooding is a major contributing factor at several hotspots
highlighting the importance of partnership working with Scottish Water.
Ongoing investigations by Scottish Water may further improve our
understanding of flood mechanisms, particularly within the Duntocher Road
and Livingstone Street areas. 
4.12 The Surface Water Management Plan highlights the need for a coordinated
catchment-wide approach due to the interconnected nature of flooding
mechanisms within Clydebank. 
Partnership working has already been established between: 
• West Dunbartonshire Council;
• Scottish Water;
• SEPA;
• Scottish Canals;
• Network Rail. 
The report recommends that future investment and intervention planning is
aligned with Scottish Water's Dalmuir System Plan to maximise opportunities
for joint funding and delivery. 
4.13 The Surface Water Management Plan considered a wide range of structural
and non-structural flood mitigation measures to develop appropriate solution
options at each of the hotspot locations. The interventions considered
included: 
• Sustainable Drainage Systems (SuDS); 
• Swales; 
• Surface water attenuation basins; 
• Rain gardens; 
• Permeable paving; 
• Surface water separation; 
• Underground storage; 
• Enhanced maintenance regimes; 
• Blue-green infrastructure.
• Additional investigation and study
• Opportunities for property level protection
• Flood forecasting and warning 
4.14 These solutions were further assessed against a multi-criteria assessment to
reduce the number of priority measures taken forward and focus the options
on those which will provide the most viable means of managing flood risk.

Page 7

Unmarked 
Multi-Criteria Assessment Scoring 
4.15 The categorisation reflects the latest understanding of flood risk based on
historic flooding records, hydraulic modelling, stakeholder engagement and
the updated 2025 SEPA Flood Maps. The categorisation will be reviewed
regularly as further information becomes available through Scottish Water
investigations and future flood events. 
4.16 To support decision making and future investment planning, the hotspots
were prioritised against set criteria to identify which factors should be
addressed first (short term) and which factors can be addressed in the
medium and long term. 
4.17 This initial list of prioritise has been reviewed as part of the option appraisal
process. Whilst detailed appraisals were undertaken for high priority
hotspots, medium and low priority actions were also subject of a high-level
assessment to identify potential future actions and investigations. 
Hotspot Interventions and costs 
Hotspot
Name
Priority Preferred Option Indicative
Capital Cost
Range
Short Term
Actions
(0-2 years)
Indicati
ve Cost
Second
Ave/Ramsay
Street
High Attenuation basin at
junction and school-
based storage
measures
£0.8m-
£2.0m
Detailed flood
study and design
scoping 
£0.10m
Western Isle
Road
High Roadside swales
and attenuation
measures
£0.3m -
£0.8m
Detailed flood
study and design
scoping
£0.05m
Duntocher
Road
High SuDS basin
adjacent to Kilbowie
Roundabout
£0.8m -
£1.8m
Detailed flood
study and design
scoping
£0.10m
Livingstone
Street
High SuDS basin and
associated drainage
works
£0.5m –
£1.2m
Detailed flood
study and design
scoping
depending on SW
investigations
£0.08m
Station
Road
Medium Consider future
appraisal of options
focused on
protecting access
and transport
resilience if flooding
continues to affect
the route. 
n/a Detailed flood
study and options
appraisal
£0.05m

Page 8

Unmarked
Kilbowie
Road
Medium Consider future
appraisal of options
n/a Detailed flood
study and options
appraisal
£0.05m
Melbourne
Avenue
Low Swale and
underground
geocellur storage
£0.6m -
£1.5m
Detailed flood
study and design
scoping
£0.07m
Low
Crescent
Low Not included in
option appraisal but
should be reviewed
as more information
is received
n/a Monitor and
continue data
collection
n/a
Dumbarton
Road
Low Not included in
option appraisal but
should be reviewed
as more information
is received
n/a Monitor and
continue data
collection
n/a 
4.18 In the short term it would also be recommended to continue to develop a
better understanding of flooding in the area through partnership working. 
Proposed actions would also include: 
• Completion of Scottish Water investigations at Duntocher Road,
Livingstone Street and the wider Dalmuir catchment.
• Developing opportunities for joint investment with Scottish Water.
• Continued flood recording and monitoring.
• Updating of emergency response procedures.
• Continuing to review 2025 SEPA mapping and hotspots as new data is
collected. 
4.19 The report points towards a medium to long-term programme of investment
rather than a single flood scheme 
Period Actions
Medium Term
Programme
(2 – 5 years)
Reassess the preferred options using updated understanding
of flood mechanisms
Develop outline design and update cost estimates for
interventions
Seek funding opportunities/decisions and align to Scottish
Water Investment plans
Deliver any “quick win” interventions where appropriate,
including SuDS, drainage improvements and runoff
reductions
Long Term
Programme
(5 to 15
years)
Progress major flood alleviation schemes
Deliver integrated sewer and surface water management
projects
Implement wider blue-green infrastructure
Align with regeneration, roads and capital investment
programmes
Build resilience to projected climate change impacts

Page 9

Unmarked
4.20 The report advises that these options should not proceed directly to
implementation until ongoing Scottish Water investigations are complete and
flood modelling has been reviewed using the latest available information. 
4.21 The Surface Water Management Plan is intended to provide a strategic
framework for future flood risk management rather than an immediate
construction programme. The next 2 to 3 years are likely to focus on ongoing
investigations, partnership working and development of funding opportunities.
Subject to the outcomes of Scottish Water's investigations and future capital
programming, delivery of significant flood mitigation measures is likely to
occur over a medium to long-term period of approximately 5 to 15 years. 
4.22 Surface water flooding remains one of the most significant climate resilience
challenges facing Clydebank. The combination of increasingly intense
rainfall, ageing drainage infrastructure, urban development pressures and
local topography continue to place pressure on existing drainage systems. 
4.23 The Surface Water Management Plan provides a structured approach to
understanding flood mechanisms, prioritising investment and identifying
sustainable, long-term solutions. Through targeted infrastructure investment,
nature-based drainage measures and continued partnership working, the
Council can improve resilience, reduce flood risk and support the long-term
wellbeing of communities across Clydebank. 
5.  People Implications 
5.1  There are no direct staffing implications arising from adoption of the SWMP 
6. Financial and Procurement Implications 
6.1  There are no immediate financial implications arising from this report
.
6.2 Future flood mitigation projects will require detailed design, appraisal and
separate funding approvals. 
Potential funding sources may include: 
• Council capital budgets;
• Flood Risk Management funding;
• Scottish Water investment programmes;
• Developer contributions;
• External grant funding.

Page 10

Unmarked
7. Risk Analysis
7.1  If the SWMP recommendations are not progressed there is a risk of: 
• Continued flood damage to property and infrastructure;
• Increased disruption to transport networks;
• Reduced resilience to climate change impacts;
• Increased maintenance liabilities;
• Missed opportunities for partnership investment.
. 
7.2 Uncertainty remains regarding some flood mechanisms pending completion
of ongoing Scottish Water investigations within the Dalmuir catchment 
8. Equalities Impact Assessment (EIA) 
8.1  An Equality Impact Assessment is not required for this report as it relates to
the adoption of a strategic study and recommendations. 
8.2 Individual mitigation projects will be assessed separately as they progress 
9. Consultation 
9.1 Preparation of the SWMP included consultation and engagement with: 
• Scottish Water;
• SEPA;
• Scottish Canals;
• Network Rail;
• West Dunbartonshire Council services.
.
9.2 A stakeholder workshop was undertaken in December 2025 to consider flood
mechanisms, opportunities for collaboration and future investment priorities 
10. Strategic Assessment 
10.1 The review sets out actions to support the successful delivery of the strategic  
priorities and objectives of the Council, in particular: 
• sustainable communities and resilient infrastructure 
Chief Officer  Gail Macfarlane
Service Area Roads and Neighbourhood
Date:  5 August 2026

Page 11

Unmarked
Person to Contact: Liam Greene, 
Roads and Transport Manager, 
Liam.greene@west-dunbarton.gov.uk 
Appendix Surface Water Management Plan   
Wards Affected: Clydebank Central 
Clydebank Waterfront