WEST DUNBARTONSHIRE COUNCIL
Report by the Chief officer Housing and Employability
Housing and Communities Committee: 21 August 2024
______________________________________________________________
Subject:   Building Services Procurement Provision update
1. Purpose
1.1 The purpose of this report is to advise Committee of updated tender
requirements information for Building Services.
1.2 To seek Committee approval to continue with necessary procurement
and tender processes.
1.3 To seek Committee approval to allow subsequent award of contract by
the Chief officer of Housing & Employability.
2. Recommendations
2.1 It is recommended that Members:
i. note the contents of this report.
ii. approve the procurement processes to tender the requirements
listed within the table in section 4.2 of this report; and
iii. delegate approval to award contracts to successful bidders to the
Chief officer of Housing & Employability.
3. Background
3.1 Good progress has been made in letting necessary contracts to ensure
full compliance with Council Standing Orders, Council Financial
Regulations and all Procurement Regulation.
3.2 Committee Members are requested to refer to these reports which
included information on the services Building Services provides on
behalf of the Council, the need to progress tenders that support the
section’s deliver of a high quality repairs and maintenance service for
the Council’s housing and non-housing properties.
4. Main Issues
4.1 A review of the historic spend on the previous versions of these
contracts and estimated volumes of known and expected works has
taken place, costs identified are expected to have increased over the
ITEM 15

Page 2

intervening period and projected costs are as detail in the table below.
4.2 The following contracts will be required to deliver a comprehensive
repairs and repairs and maintenance service for a period of up to four
years from the date of let. They will be of sufficient size, scope and
duration to cover the estimated volume of work for the period in
question and will be awarded to suitably qualified and competent
suppliers and contractors.
Requirement Total
Estimated
Annual
Value
Funded By
HRA
Revenue /
Capital and
CRA
Priority
Property maintenance
contract; focusing on gas
maintenance 
£2.5m
Revenue /
Capital High
Specialist Roofing Repairs,
Maintenance and Renewal £1.5m
Revenue /
Capital High
Ventilation, Condensation and
Associated Works for West
Dunbartonshire Domestic and
Non Domestic Properties  
£0.5m
Revenue /
Capital High
4.3 All procurement activity carried out by the Council in excess of £50,000 
is subject to a contract strategy. The strategy for the contracts as 
listed in the table at 4.2 will include but may not be limited to; contract 
scope, service forward plan, the market, procurement model and
routes – including existing delivery vehicles, roles and responsibilities,
risks,  issues and opportunities and on-going contract management.    
4.4 Where necessary officers will adopt procurement processes in line with 
European, UK and Scottish Government Procurement Regulation and 
Council Standing Orders. 
4.5 All tenders will be advertised on the Public Contracts Scotland Portal or
use of appropriate subscribed frameworks will be used such as
Scotland Excel or Scottish procurement alliance. 
5. People Implications
5.1 Progressing these procurement processes will require significant
Officer time resource from Building Services, Consultancy Services,
Housing Operations and Corporate Procurement teams.
6. Financial Implications
6.1  Costs of the support contracts will be funded by both Capital and
Revenue budgets through the Housing Revenue Account, Central

Page 3

Repairs Account and Housing Maintenance Trading Account. 
6.2 Costs of contracts listed under 4.2 are included within existing budgets. 
7. Risk Analysis
7.1 On-going investment, in-line with business plans, will allow the Council
to meet its landlord, health and safety and quality standards obligations
whilst providing appropriate asset management.
7.2 Procurement related risks and mitigation/management measures will
be identified as part of the development of tendering strategies for the
individual requirements.
8. Equalities Impact Assessment (EIA)
8.1 An Equalities Impact Assessment screening has been carried out
which did not identify any significant issues. The report does not alter
any existing policy or pattern of service delivery.
9. Strategic Assessment
9.1 This report contributes to the Council’s Strategic Priorities and in
particular towards:
i. improving economic growth and employability.
ii. improving local housing and environmentally sustainable
infrastructure; and
iii. improving the wellbeing of communities.
10. Consultation
10.1 Finance and Legal have been consulted regarding the set up of the
contracts referred to in this report.
10.2 The Corporate Procurement team have been consulted in the
development of this report.  They will provide assistance and
professional guidance with the administration of the tender exercises.
Peter Barry
Chief Officer Housing & Employability
Date: 6 August 2024

Page 4

______________________________________________________________
Persons to Contact: Martin Feeney – Building Services Manager,