WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer, Housing and Employability
Housing and Communities Committee: 21 August 2024
___________________________________________________________________
Subject:  Home at the Heart - West Dunbartonshire’s Rapid Re-Housing
Transition Plan update and new approaches to homelessness
progress report.
1. Purpose
1.1 The purpose of this report is to provide members with an update on “Home at the
Heart” our Rapid Re-housing Transition Plan (RRTP) for the period 2019-24 and
new approaches to homelessness, including.
- Progress update for Year 5 and Year 6 plans,
- An update on Scottish Government funds to assist in the delivery of the RRTP,
- Lettings requirements for Year 6 of the plan 2024/25,
- Housing Emergency Declaration and Action Plan update.
2. Recommendations
2.1 It is recommended that the Housing and Communities Committee:
(i) Note the progress and challenges made in the five years of “Home at the
Heart”, which will inform a report to the Scottish Government at the end of
August 2024 and note the main objectives for Year 6 in sections 4.17 -
4.32 of this report;
(ii) Note that the Council’s housing allocation letting target for homeless
households remains at 64% for 2024/25 as set out in section 4.25 of this
report and note the Chief Officer, Housing and Employability will keep this
target under close review based on current modelling projections;
(iii) Note the continued uncertainty around future funding and specifically the
risk to the embedded Housing First approach;
(iv) Note that Scottish Government funding of £261,000 has been awarded for
2024/25 for the specific delivery of the West Dunbartonshire Rapid
Rehousing Transition Plan;
(v) Note the Housing Emergency Declaration and Action Plan update
provided in a separate committee paper.
3. Background
3.1 Our current approach to tackling homelessness is outlined in our RRTP “Home at
the Heart” and reinforced within the new Local Housing Strategy approved by the
Housing and Communities Committee in November 2021. This approach builds on
the good progress made within West Dunbartonshire by previous strategies, most
ITEM 9

Page 2

recently our “More than a Roof” approach which covered the period 2017/2020,
whilst also acknowledging the challenges set by the renewed Scottish
Government national commitments to tackle homelessness, to end rough sleeping
and to transform temporary accommodation.
3.2 “Home at the Heart” was developed in response to a key recommendation from
the Homelessness and Rough Sleeping Action Group (HARSAG) that was
adopted by the Scottish Government, for Local Authorities to develop and
submit a RRTP for the period 2019-2024.
3.3 It was developed in partnership with key stakeholders, including HSCP and the
wider Housing Solutions Partnership, which includes local Registered Social
Landlords.  It was submitted to the Scottish Government on 31 December 2018
and retrospectively approved by the Housing and Communities Committee on 6
February 2019.
3.4 Regular reports have been provided to the Housing and Communities
Committee, initially detailing, and seeking approval for our RRTP and
subsequently providing updates in terms of progress being made and approving
the use of Scottish Government funding to deliver our key objectives.
4. Main Issues
4.1 The aims of “Home at the Heart” in terms of tackling homelessness are
influenced by the Scottish Social Housing Charter and consistent with the
Scottish Government’s “Ending Homelessness Together” approach and are
structured around the following four strategic objectives:
 Deliver a whole systems approach to the prevention of homelessness;
 Enable service users with low or no support needs to access settled housing
quickly;
 Develop interim housing options which enable independent living and
tenancy sustainment; and
 Implement a Housing First model which enables the most excluded service
users to secure sustainable housing.
“Home at the Heart” Year 5 Progress
Objective 1: Deliver a whole systems approach to the prevention of
homelessness.
4.2 The Prevention Officer has continued to engage with households at risk of
homelessness. This has included managing the pilot prevention fund which in
the 4 years has made payments directly to households totalling £27,600 and
has helped ensure that 69 existing tenancies were sustained in both social and
private rented sectors.
4.3 The overall number of approaches to our Housing Options service had
increased significantly in 2021/22 linked to the Tenant Hardship Fund but we
have continued to see high demand in 2022/23 and despite a 16% decrease in

Page 3

approaches during 2023/24, request for assistance remains high. We have
prevented 67% of cases from becoming homeless.
2018/19 2019/20 2020/21 2021/22 2022/23 2023/24
Prevent1 approaches 178 240 332 576 455 384
Prevent1 closures 177 221 249 378 654 385
% homelessness prevented 64% 57% 51% 52% 72% 67%
% closed with presentation 24% 26% 27% 31% 18% 25%
4.4 Since the end of emergency legislation banning evictions taking place in both
the social and private rented sector, there has been an increase in Section 11
notices, from 20 in 2020/21 to 155 in 2023/24. Of those where contact was
made and there was engagement with the household, homelessness was
prevented in 83% of cases, up from 80% last year.
Objective 2: Enable service users with low or no support needs to access
settled housing quickly.
4.5 One of the key objectives of our RRTP is to ensure that homeless households
can access settled accommodation as quickly as possible. Our key target is
reducing the length of time homeless households with no/low support needs
spend in temporary accommodation.
4.6 We have developed a RRTP model which considers the level of new homeless
decisions, the backlog of homeless households, projected future demand, the
number of lets made to homeless households and projected letting activity. The
RRTP model uses this data to determine the number of lets that will be required
for homeless households on an annual basis and determines a projected lettings
% target.
Calculation of homeless lets required and % of expected letting
activity required to meet need - split by LA & RSL
Year 5 target Year 5 actual
Lets required to meet demand 932 746
Split LA 621 543
Split RSL 311 203
% Allocation of lets required
LA 69% 62%
RSL 69% 52%
4.7 Despite an improvement from last year, the turnover of available properties was
lower than projected, thus impacting available lets and affecting void times.
4.8 There are as of 31st July 2024 281 households in temporary accommodation,
including 95 children in West Dunbartonshire. 73 households have been waiting
longer than a year to be housed and 34 of these households are in temporary
accommodation.

Page 4

4.9 As a result, our average times for 2023/24 increased and failed to meet the
target of 15 weeks, we reported 19 weeks for this period.
Objective 3: Develop interim housing options which enable independent living
and tenancy sustainment.
4.10 We continue to provide a range of interim housing options for those homeless
households with more complex support needs. This includes supported
tenancies in the community, as well as residential supported accommodation
where this need is identified.
4.11 Residential supported accommodation offers temporary accommodation and on-
site support to alleviate homelessness and enable homeless households to
make a planned transition to settled accommodation. We began to take forward
the key recommendations of the review of Supported Accommodation at the end
of Year 5. This involved consulting with current providers and reviewing current
needs.
Objective 4: Implement a Housing First model which enables the most excluded
service users to achieve housing sustainment.
4.12 A key objective in Year 5 of our RRTP was to further extend our Housing First
approach for those households with the most complex needs. The available
funding allowed to fund the 8 housing first workers but did not allow to expand
the service further.
4.13 By the end of 2023/24, we had created 2 new Housing First tenancies, a further
13 clients are awaiting an offer of settled accommodation being made.
4.14 We have 4 tenancies being sustained where the Housing First support has
been “stepped down”, meaning a planned full exit from the Housing First
Service.
4.15 We have created additional capacity by carrying out a tendering exercise in
which Blue Triangle Housing Association were successful in a yearlong
contract for 7 clients. However, long term future funding for the initiative is still
to be clarified.
4.16 Whilst our Housing First approach continues to have a high tenancy overall
sustainment rate at 78%. Sadly, five of these tenancies have ended due to the
death of tenants, with a further seven ending due to other reasons notably
households moving out with the West Dunbartonshire area.
.
Year 6 main objectives
4.17 Originally our Rapid Rehousing Transition Plan (RRTP) was to be delivered
over a 5-year period but in December 2023 the Scottish Government confirmed
a one-year extension to allow for its continued delivery for a 6th year due to
challenges around implementation, with further funding being allocated in
March 2024.

Page 5

Objective 1: Deliver a whole systems approach to the prevention of
homelessness.
4.18 We will continue to use a variety of measures to prevent homelessness within
WDC including the following: -
 Our Housing Options approach proactively identifies those at risk of
homelessness, provides advice and assistance on preventing
homelessness;
 Linking in with the money advice service where there are financial
pressures and offering professional mediation services where there are
relationship breakdowns;
 Our enhanced homelessness prevention service involves a dedicated
officer responding proactively to Section 11 referrals by engaging with
households at risk of homelessness and offering support through the
pilot prevention fund; and
 Our revised allocations policy creates young people at risk of
homelessness as an additional group given a reasonable preference
within the policy.
4.19 To enable the prevention fund to be a tool to prevent homelessness we have
allocated £15,000 from this years’ RRTP Scottish Government funds to top up
the carry-over of £4,263 not spent last year.
4.20 The changes to the allocations policy with the creation of a youth priority has
now been fully embedded and will begin to have a positive impact by reducing
homeless presentation for those who now benefit from the youth priority list.
4.21 Following on from the pilot Section 11 programme, we will review if extending
earlier Section 11 referrals fits with new proposed prevention duties being
introduced within the current Housing Bill.
4.22 We will take appropriate actions, including assisting other services when new
prevention duties are enacted.
Objective 2: Enable service users with low or no support needs to access
settled housing quickly.
4.23 Due to lower letting activity and an increase in the length of time spent in
temporary accommodation we have reviewed and adjusted our target time to
16 weeks.
4.24 Currently modelling suggests that due to an increased backlog, increased
demand and reduced available turnover that for 2024/25 for West
Dunbartonshire, 127% of all available social tenancies, inclusive of conversions
and housing first will require to be allocated to homeless households to ensure
targeted reductions in temporary accommodation and faster access to settled
accommodation is achieved.
4.25 While this cannot be achieved, and recognising other housing need factors it
would not be practical to have 100% allocation of lets to homeless households.
Therefore, we asked our partners to agree to 69% lettings target to homeless

Page 6

households. This objective was supported by the Housing Improvement Board
in terms of lets made by WDC and a similar commitment was sought from our
RSL partners via their annual RRTP Contribution Statements.
Calculation of homeless lets required and % of expected letting
activity required to meet need - split by LA & RSL
Year 6
Lets required for to meet demand 760
Split LA 518
Split RSL 242
Projected turnover  Year 6
Split LA 750
Split RSL 350
% Allocation of lets required Year 6
LA 69%
RSL 69%
4.26 As 69% is not enough to fully meet demand and clear the increased backlog of
households in temporary accommodation, this will result in a shortfall of around
688 lets and 110 additional units required for temporary accommodation.
4.27 If we require additional temporary accommodation units this reduces lets
available for mainstream offers and would also require additional staff
resources to manage the additional units.
Objective 3: Develop interim housing options which enable independent living
and tenancy sustainment.
4.28 It is expected that the keys findings of the review of Residential Supported
Accommodation will continue to progress in Year 6, with the new project plan
being approved, embedding the timescales for the recommendations and the
project board being established.
4.29 To deliver the optimum service model for residential supported accommodation,
it is anticipated that a three-year plan will be required. This will include the
potential for decommissioning of some existing services, the commissioning of
new provision to better meet identified need and a full financial impact
assessment. To develop and lead on the development and implementation of
this plan we are seeking to recruit an additional resource to lead on the delivery
of new residential supported accommodation.
Objective 4: Implement a Housing First model which enables the most
excluded service users to achieve housing sustainment.
4.30 The available funding does not allow to expand the service further but ensure
we operate with 8 housing first support workers enabling support to continue to
be provided to the 42 active tenancies and the 15 waiting to be housed carried
over into Year 6.

Page 7

4.31 We will assess the impact of the additional tendered Housing First service and
considering whether to extend beyond 2024/25.
4.32 A full review of the Housing First service will also be carried out during Year 6,
including stakeholder and service user consultation to help frame the future of
the service.
Rapid Rehousing Transition Plan funding update
4.33 In December 2023, the Scottish Government confirmed in its Programme for
Government that a further £8 million would be provided to local authorities to
support Rapid Rehousing Plans and scale up the Housing First approach
nationally for 2024/25.
4.34 The formula still being used to allocate local authorities share of this funding is
based on the number of homeless assessments made in a local authority area
over a three-year period. There has been some criticism of this approach as it
does not consider homelessness prevention work within the assessment. It can
therefore act as a disincentive to make the wider system changes advocated
within Ending Homelessness.
4.35 Additional funding was made available in 2023/24 targeted at those who have
“sustained temporary accommodation pressures”. This is defined as the local
authorities who consistently appear in the top five areas for the number of
households in temporary accommodation in recent years according to Scottish
Government official homelessness statistics. Therefore, the larger local
authorities benefited from this and will continue to do so unless the way in
which any additional funds are distributed is reviewed.  If they were to take
account of the number of households in temporary accommodation per 10,000
of households, then other local authorities including WDC would benefit from
any additional funding.
4.36 The Scottish Government and COSLA had hoped to explore the possibility of
joining up the funding stream for preventing and responding to homelessness
with the rapid rehousing funding stream and to look at alternative distribution
formulas. However, this work was delayed due to conflicting pressures and
there is currently no indicated intention to change.
4.37 The same formula has therefore been used for the funding allocation for
2024/25. This formula has resulted in an allocation for West Dunbartonshire
Council of £261,000 to deliver Year 6 of our RRTP which was announced on 5th
March 2024.  In addition, the Scottish Government have also confirmed the
funding allocation of £644,579 to West Dunbartonshire Council for the provision
of homelessness prevention and response services.
RRTP Year 6 funding
Year 5 underspend £4,263
SG funding for Year 6 £261,000
Housing and Homelessness contribution £290,000
Year 6 total funding £555,263

Page 8

4.38 The increased housing and homelessness contribution allows for a slight
overspend in Year 6, which accounts for ongoing increased costs in areas such as
the increased conversion programme. We have carried out a full review of Year 5
activities and refreshed our plan for Year 6 to take account of available funding.
RRTP Year 6 costings
Housing First West Dunbartonshire £368,880
Blue Triangle Housing First project £46,000
Pilot Prevention Fund £15,000
Conversion Programme £124,000
Year 6 total cost £553,880
Whilst the additional RRTP funding allows us to continue our Housing First
service it does not allow for us to expand the service to meet the identified
need within West Dunbartonshire. We also have no confirmed funding
beyond Year 6 for Housing First.
Housing Emergency
4.39 The Council declared a housing emergency on 1st May 2024 due to the
extreme pressures facing housing and homelessness services within West
Dunbartonshire. A national housing emergency was declared by the
Scottish Government on 15th May 2024. We will await an update on the
further actions the Scottish Government plan to take to address the national
housing emergency.
4.40 A draft action plan to tackle the housing emergency in West Dunbartonshire
has been developed and will be presented to the Housing and Communities
Committee on the 21st August 2024.
5. People Implications
5.1 An additional post required to strengthen the team will be recruited in line with the
Council’s existing recruitment policy and will be funded from the Scottish
Government funding for the provision of homelessness prevention and response.
6. Financial and Procurement Implications
6.1 The Housing Minister wrote to West Dunbartonshire on 5th March 2024
advising of the Council’s Rapid Rehousing Transition Plan funding allocation
for 2024/25 of £261,000. This funding will be included in the weekly payment of
the 2024/25 General Revenue Grant.
6.2 In addition the Scottish Government also confirmed the funding allocation of
£644,579 to West Dunbartonshire Council for the provision of homelessness
prevention and response, this funding will be paid as part of the General
Revenue Grant payment, with the first payment in 2024/25 made on 1 April
2024.

Page 9

6.3 The Rapid Rehousing Transition Plan has been continued for a 6th year. This is
due to be the final year of the Plan and dedicated funding. Conversations have
begun about the future, but no confirmed decisions have been made.
Committee will be updated at a future meeting once we receive confirmed
plans beyond Year 6.
6.4 We are aware of some national discussions looking at reviewing funding to
deliver homelessness and housing option services, however, there remains
some financial uncertainty in terms of how the Housing First approach can be
funded in the longer term.
6.5 The delivery of the wider Rapid Rehousing Transition Plan will be within
existing budgets noting the increases in such because of the Scottish
Government funding for 2024/25.
6.6 There are no procurement implications in terms of this report.
7. Risk Analysis
7.1 There are financial and regulatory risks associated with not being able to fully
deliver our Rapid Rehousing Transition Plan, including the Housing First
element of the approach.
7.2 The decision to award funding in Year 6 was based again on a formula which
focuses on homelessness assessments (and not the content of the RRTP’s),
which benefits larger local authorities who receive a higher proportion of
homeless assessments and could discourage local authorities from
implementing initiatives aimed at preventing homelessness.
7.3 There is no confirmation of funding for RRTP past Year 6 (2024/25) therefore
long-term funding is required to be sourced to continue our Housing First
service.
8 Environmental Sustainability
8.1 The delivery of our housing investment programmes is consistent with the
approved More Homes zero carbon approach. Our current and future approach
to strategic housing asset management will continue to prioritise a ‘zero
carbon’ approach to decision making and deliverability and this will be done the
aims of the Housing Asset Management Strategy and the Council’s Climate
Change Strategy.
9. Equalities Impact Assessment (EIA)
9.1 There are no negative equalities impacts due to this update to our RRTP however
preventing and responding to homelessness has a significant positive impact on
individuals and communities. There are potential positive impacts for some groups
as noted in the EIA conducted when our RRTP was updated in July 2024, EIA
1028.
10. Consultation

Page 10

10.1 The first draft of our RRTP was developed in collaboration with key partners,
including the Health and Social Care Partnership, local Registered Social
Landlords and third sector organisations, via a series of well attended
stakeholder events held in November and December 2018.
10.2 Consultation and communication have continued since the submission of the
first iteration of the RRTP through the Housing Solutions Partnership. Further
engagement has also taken place with other local landlords via the Strategic
Housing Providers Forum. Engagement has continued with the Health and
Social Care Partnership and a dialogue with the WDTRO regarding the
implementation of the RRTP and Housing First has also taken place.
11. Strategic Assessment
11.1 Having considered the Council's strategic priorities, this report contributes
significantly to all strategic priorities.
Peter Barry
Chief Officer, Housing and Employability
Date: 6 August 2024
___________________________________________________________________
Person to Contact: John Kerr – Housing Development and Homelessness
Manager, Housing Development and Homelessness Team,
Housing and Employability, telephone: 07793717981, email:
john.kerr@west-dunbarton.gov.uk
Donna Kirkwood, Senior Housing Development Officer,
Housing Development and Homelessness Team,
Housing and Employability: email donna.kirkwood@west-
dunbarton.gov.uk
Appendices: None
Background Papers:
Ending Homelessness Together – High Level Action Plan;
Scottish Government/COSLA
https://www.gov.scot/binaries/content/documents/govscot/
publications/publication/2018/11/ending-homelessness-
together-high-level-action-plan/documents/00543359-
pdf/00543359-pdf/govscot%3Adocument
HARSAG2 recommendations tracker, West
Dunbartonshire Council Housing Development and
Homelessness Team, June 2024;
Housing and Communities Committee Report 24th August
2023 “Rapid Rehousing Transition Plan and new
approaches to homeless update”.

Page 11

Letter from Paul McLennan, MSP, Minister for Housing on
Rapid Rehousing Transition Plan funding and the
Homelessness Prevention Fund for 2024/25; 22
December 2023;
Letter from Paul McLennan, MSP, Minister for Housing on
Distribution of Funding for Rapid Rehousing Transition
Plans for 2024/25; 5 March 2024;
“More than a Roof” West Dunbartonshire Council’s
Homelessness Prevention and Temporary
Accommodation Strategy 2017-2020.
West Dunbartonshire Council’s Local Housing Strategy
2022-2027;
West Dunbartonshire Council’s Revised Rapid Rehousing
Transition Plan including Action Plan and Equalities
Impact Assessment, Home at the Heart
Wards Affected:  All