WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer, Housing and Employability
Housing and Communities Committee: 21 August 2024
__________________________________________________________________
Subject: More Homes West Dunbartonshire – West Dunbartonshire Council
Affordable Housing Supply Delivery Programme
1. Purpose
1.1  This purpose of this report is to provide the Housing and Communities
Committee an update on progress with West Dunbartonshire’s More Homes
Programme which oversees the delivery of the Council’s new home building
programme.
2. Recommendations
2.1 It is recommended that the Housing and Communities Committee:
(i) Notes the content of the report and the progress made to date in the
delivery of the Council’s More Homes West Dunbartonshire approach,
including the forthcoming handover of new homes at the Clydebank East
and Gilmour Avenue development;
(ii) Approve the updated estimated costs for Braehead and Campbell Street
(Bonhill gap sites) and Bank Street development;
(iii) Approve the procurement exercise and to award the contract up to the
updated estimated costs for the projects above;
(iv) Approve the procurement exercise of a multi-disciplinary design team for
Clydebank Health Centre and to award the contract up to the approved
costs for the project;
(v) Approve the procurement and award of the Queen Mary Avenue Design
and Build development contract by the Chief Officer – Housing and
Employability in consultation with the Procurement Manager, to appoint a
suitably experienced contractor to deliver the new homes within the
approved budget through an appropriate procurement framework.
3. Background
3.1 In West Dunbartonshire the Affordable Housing Supply Programme (AHSP) is
delivered through a More Homes West Dunbartonshire strategic approach
which has successfully delivered over one thousand new affordable homes in
West Dunbartonshire to date and includes the Council’s own ambitious New
House Building Programme.
ITEM 8

Page 2

3.2 The Council’s last practical completion took place at the Queens Quay
development in September 2022 delivering twenty-nine new Council homes in
a key regeneration area as part of a wider development which has delivered
146 new social rented homes. The homes were the first residential properties
to be heated from the Council’s Queens Quay District Heating Network. This
development has been recognised at recent national housing sector awards
winning the following: -
 Best Residential Regeneration Project – Herald Property Awards
 Inside Housing Best Residential Development (Scotland)
3.3 These 29 new homes, are in addition to the completion of the Council’s first
fully dementia designed development at Creveul Court, Alexandria and other
exemplar developments in Haldane, Aitkenbar, Bellmsyre, Dumbarton
Harbour and St Andrews, Clydebank. The Council have now completed
twelve new build developments since 2013 and are the largest developer of
social homes in West Dunbartonshire delivering 496 new homes and 128
acquisitions through our buyback scheme to date as outlined in Table 1
below. The 500th new build home in the More Homes West Dunbartonshire
delivery programme will be delivered in October 2024 at our Clydebank East
development:
Table 1:  Completed Council New Build and Acquisitions
Project No. of
Units
Completion
Date
Granville Street (Phase 1), Clydebank 24 July 2013
Miller Road, Alexandria 15 October 2013
Granville Street (Phase 2), Clydebank 9 February 2014
Central Bellsmyre, Dumbarton 36 December 2014
Hillstreet Square, Dumbarton 37 August 2015
Second Avenue, Clydebank 40 April 2018
Creveul Court, Alexandria 22 April 2021
Aitkenbar Primary School 55 July2021
Haldane Primary School 58 August 2021
St Andrews, Clydebank 126 October 2021
Dumbarton Harbour, Dumbarton 45 December 2021
Queens Quay, Site B, Clydebank 29 August 2022
Buyback Acquisitions 128 Ongoing
Totals 624
3.4     The Strategic Housing Investment Plan (SHIP) 2024-2029, outlining West
Dunbartonshire’s Affordable Housing Supply Programme through the More
Homes West Dunbartonshire approach was approved by the Housing and
Communities Committee in November 2023. The SHIP outline plans to meet
the Council Administration’s aim of delivering 2500 new affordable and social
rented homes over the next 10 years.

Page 3

4. Main Issues
More Homes West Dunbartonshire - Delivery Programme
4.1 Building new affordable homes has a significant role to play in revitalising
local economies and assisting with post-pandemic and economic recovery
plans, negating the impacts of the current cost of living crisis and combatting
poverty including child poverty. It is also clear that the need for affordable
homes has and will increase in the current ongoing economic environment.
4.2 Our More Homes West Dunbartonshire approach is an ambitious plan that
aims to continue the positive momentum of the delivery of much needed
Council homes in West Dunbartonshire and will significantly assist the
Council’s aim to deliver 2500 new social and affordable homes by 2032.
4.3 As the biggest affordable housing developer in West Dunbartonshire, the
Council has identified several future development sites for new council homes
to address existing and new housing need. The design of these homes will
further develop, improve, and exceed current best practice, providing
sustainable homes using innovative technology and delivering on our low
carbon ambitions including passivhaus and other net zero carbon
opportunities.
4.4 The Strategic Housing Investment Plan and HRA Capital Plan outlined the
plans the Council have for meeting their new build ambitions. Some of the
initial plans were and continue to be impacted because of global issues
revised new build targets for the Council are outlined below:
Table 2: Council New Build Programme
Project Number
of Units
Number of
Specialist
Provision
Site
Start/Est
Site Start
Est Completion
Date
Clydebank East,
Clydebank 88 9
On Site
January
2023
Spring 2025
(First handovers
– October 2024)
Pappert, Bonhill
Alexandria 26 3
On site
March
2024
Spring 2025
Mount Pleasant 19 19 On site
April 24
Spring 2025
Gilmour Avenue 2 1 Autumn 24 Autumn 2024
Willox Park Phase 1 17 17 Winter 24 Winter 2025
Bonhill Gap Sites 34 4 Winter 24 Winter 2025
Bank Street,
Alexandria
22 22 Jan/Feb 25 Jan/Feb 26
Clydebank Health
Centre*
38 22 Spring 25 Autumn 2026
Queen Mary Avenue* 16 4 Winter 25 Winter 26
Dennystoun Forge 20 20 TBC TBC

Page 4

*Current Planning figures
4.5 Updates for each site are noted below:
Clydebank East:
This development will deliver eighty-eight new homes and has been designed
to meet the housing need within the wider West Dunbartonshire area. The
table below shows the housing mix:
House Type Sustainability Standard Number of New
Homes
Wheelchair Bungalow
3bed/4person
Net Zero 3
House 3bed/5person Net Zero 15
House 4 bed/7person Net Zero 12
House 5 bed/8 person Net Zero 8
Wheelchair Cottage Flat
1bed/2 person
Net Zero 4
Cottage Flat 2 bed/4 person Net Zero 4
Flat 1 bed/2person Net Zero 16
Flat 2 bed/4 person Net Zero 24
Wheelchair Flat 1 bed/2person Net Zero 2
Works commenced on this development in January 2023 and the first homes
are scheduled to be handed over in October 2024.
All houses are designed to the Housing for Various Needs Standard (HfVN).
There will be nine fully Wheelchair (WCH) accessible properties. The 4- and 5
-bedroom homes will all have ground floor double bedrooms.
The development at Clydebank East will see the completion of a major
housing led regeneration of a key priority regeneration area identified in the
Local Housing Strategy and will be the first fully zero carbon housing
development in West Dunbartonshire and marks a significant milestone in our
transition to net zero new homes approved at the August 2022 meeting of the
Housing and Communities Committee.  Plans are being developed to mark
the significance of the net zero element of the development and the
development will see the 500th new home delivered through the More Homes
West Dunbartonshire approach.
Silverton
Regeneration*
10 2 TBC TBC
Willox Park Phase 2* 25 25 TBC TBC
Queens Quay Site C* 100 10 TBC TBC
Buyback Scheme (60
per year)
300 36 2023/24 2027/28
717 units 194 units
Previous units 710 – Planning figures amended.
(Silverton Regen, Willox Park Phase 2, Gilmour Ave added –
Clydebank Gap sites removed)
Previously 172, increase in
sheltered provision

Page 5

We have previously reported award of above benchmark grant due to the
complexities of the development at Clydebank East this resulted in a total
grant award of £12.6m, this equates to over £143k grant per home and
around £4.68m more than the benchmark grant award this ensured the
delivery of the development without any negative impact on the wider Housing
Revenue Account.
Pappert, Bonhill
This project enjoyed a site start date in early March, delivering the housing
mix as follows: -
House Type Sustainability Standard Number of New
Homes
House 3bed/5 person Passivhaus 6
House 3bed/5 person Net Zero 6
House 4bed/6person Net Zero 4
House 4bed/7person Net Zero 1
Flat 2bed/3person w/c Net Zero 3
Flat 1 bed/2person Net Zero 6
Mount Pleasant, Old Kilpatrick
CCG have been appointed as the main contractor following the Tendering
Committee in September, having been directly appointed from the Scotland
Excel Framework. The site started15th April 2024 and construction will last
approximately one year.
This is a 19-unit complex which is designed for elderly residents and will
deliver high quality amenity housing, the housing mix is outlined below for
information.
House Type Sustainability Standard Number of New
Homes
Bungalow 1bed/2person Net Zero 3
Flat 1bed/2person w/c Net Zero 4
Flat 1bed/2person Net Zero 4
Flat 2bed/4person Net Zero 8
Willox Park, Doveholm, Dumbarton
The development of seventeen new homes to be delivered at the former care
home site.
House Type Sustainability Standard Number of New
Homes
Flat 2bed/3person Net Zero 2
Flat 1 bed/2person Net Zero 15

Page 6

This development has now been granted planning permission and a
contractor, McTaggart Construction, has been appointed to begin the
construction phase.
The net zero heat strategy will be delivered by ground source heat pump, as it
was felt that this solution to be preferable than an air source heat pump for
each home.
Bonhill Gap Site Strategy
The pre-planning application process has commenced on the development of
the three separate gap sites which are contained within this wider
development project.
Planning has been submitted for both the Campbell St and Braehead sites.
We ask the committee to note and approve the updated estimated costs for
these projects of £9,751,388 and to appoint a contractor up to this estimated
cost. The previous estimated costs were £9,354,809.18. This is a 4.2%
increase and takes into account more detailed drainage and landscape design
and 0.5% framework levy increase.
We have amended the housing mix for the O’Hare gap site and will now
deliver six one-bedroom cottage flats, this revised housing mix meets housing
need and demand projections within the wider area. The projected costs of
delivery meet our affordability threshold which the previous housing mix that
was stopped could not.
Bank Street, Alexandria
The development will consist of twenty-two sheltered/amenity housing units in
partnership with the HSCP. Planning has been submitted.
House Type Sustainability Standard Number of New
Homes
Flat 1bed/2person w/c Net Zero 22
Communal Room Net Zero 1
Site Braehead Campbell St O’Hare
1 bed 8
(4 WCH + 4 GN)
6 6
2 bed 3 (WCH)
3 bed 3
4 bed 2
5 bed 4
6 bed
7 bed 2
Total 17 11 6

Page 7

Staff Office Net Zero 1
We ask the committee to note and approve the updated estimated costs for
this projects of £7,793,677. We also seek approval to procure a contractor up
to this estimated cost. The previous estimated cost was £6,187,281. This is
an increase of £1,606,369 (26%). The reasons behind this are due to an
increased gross internal floor area (GIFA) of 27%, construction inflationary
increase, additional soft landscaped area, the requirement for an additional lift
within the development, and includes a saving from installing exhaust air heat
pumps instead of ground source heat pumps.
Clydebank Health Centre
Having received the feasibility report for the site, we aim to develop twenty
units of sheltered housing to reprovision existing sheltered housing currently
provided at Young Street, therefore strategically improving the provision of
sheltered accommodation within Clydebank. We also aim to build around
eighteen units of mostly family housing.
We are seeking to appoint a multidisciplinary design team through the
Scottish Procurement Alliance framework to carry forward the above-
mentioned site proposal designs. This would consist of an architect-led
multidisciplinary team inclusive of engineering, energy, landscaping, and fire
consultants. Approval is sought by the Housing and Communities Committee
to accept the tender price for this project of £540,651.90 which is around 4.9%
of the estimated project delivery budget.
The demolition of the Health Centre was awarded to Caskie Ltd and works
commenced on the 3rd June and the demolition programme is scheduled for
around 20 weeks.
Gilmour Avenue, Hardgate
As part of the wider development of our Clydebank Gap Site strategy we
identified a Housing Revenue Account site in the Hardgate area at Gilmour
Avenue. The site was previously the location of timber garages on concrete
bases. These have long since been demolished and the site has been beset
with fly tipping issues for several years.
The proposed development has now been granted planning permission for
two three bed semi-detached homes to be delivered utilising modular
construction methods. The houses should be completed in October 2024.
Dennystoun Forge Gypsy/Traveller Site
We continue to engage with the Scottish Government over the possibility of
accessing support through the Gypsy/Traveller Accommodation Fund. There
remains a hope that a further tranche of funding will be released. AHSP
funding may be an alternative funding option, and we have included the
project in the current SHIP and HRA Capital Programme. In the meantime, we

Page 8

are refining our plans for the development through engagement with other
local authorities and ongoing consultation with site residents.
Queen Mary Avenue, Clydebank (Clydebank Gap Sites)
The transfer of the site at Queen Mary Avenue, Clydebank with vacant
possession at the cost of £140,000 from the Council’s General Fund to the
Housing Revenue Account for the delivery of new Council homes was
approved at the February meeting of the Housing and Communities
Committee and has now been concluded.
The demolition contract for the units was awarded to Caskie Ltd. The
programme started on 6th July and will take approximately 6 weeks. Initial
feasibility for this site had identified the potential for around sixteen new
homes.
Considering the Council’s housing emergency declaration in May 2024 and
the pressures on the affordable housing supply programme funding outlined in
more detail within section 4.6 – 4.13 of this report, we are seeking to
accelerate elements of new housing delivery. We have identified the
development at Queen Mary Avenue as one possible development that we
would seek to accelerate through a design and build delivery route. This is
based on our experience at the Mount Pleasant and a strategy has been
developed to appoint an experienced and capable contractor to undertake the
delivery of these new homes through a procurement Framework up to the
approved budget.
Silverton Regeneration
The two identified sites in Smollett Road and Dumbuie Avenue are
progressing towards demolition and building warrants for demolition in place.
The tender for demolition went out on 24/7/2024 for 3 weeks. Tenders are due
back on 7/8/2024 with an estimated start date one month later (7/9/2024) with
an expected completion date six weeks thereafter.
Queens Quay, Site C, Clydebank
The Council has been developing a design to deliver a projected twenty units
on this site to complement the housing mix within sites A and B. This
development will also be designed to meet low/zero carbon principles and
linked to the Queens Quay district heating network.
.
Pre-planning response was received on the 25 February highlighting concern
of the WDC development proceeding in isolation. We have adopted a
proactive response to this issue and have developed masterplan diagrams
incorporating the surrounding sites and have conducted valuations on the
adjacent site to Queens Quay C with a view to purchasing additional land to
deliver more affordable housing in the Queens Quay regeneration site. If this
is achieved, we would seek to develop a mixed tenure approach to any
expanded development site delivering one hundred new affordable homes.

Page 9

We are seeking discussion with CRL (Clydeside Regeneration Limited) to
progress the possibility of acquiring this additional land and will be able to
draw down Scottish Government grant to enable this. However, because of
the uncertainties surrounding potential delivery timescales for this project and
the reduced funding it is no longer allocated funding within the current
Strategic Housing Investment Programme.
Buyback Programme
The Council’s buyback programme which incorporates the Mortgage to Rent
Scheme purchased sixteen new homes in 2022/23. In 2023/24 we purchased
thirty-five new homes at an average purchase cost of £100,000. 26/35 were
larger family homes with 3+ bedrooms. The housing mix is shown in the table
below:
In 2022/23 16 properties were purchased 3 of which were 3+ bedroom larger
family homes.
In 2023/24 and following approval of the Strategic Housing Investment Plan
by the Housing and Communities Committee in November 2022 and
subsequently the decision by West Dunbartonshire Council in March 2023 to
deliver an enhanced Housing Capital Investment Programme including
additional funding for buyback purchases we are now scaling up ambition
around our buyback programme. In 2024/25 and in each of the subsequent
years up to and including 2027/28 our ambition is to deliver sixty new homes
each year meaning a minimum of three hundred new Council homes to meet
identified need will be added to the Council housing stock.
4.6 In December 2023, the Deputy First Minister and Cabinet Secretary for
Finance set out the Scottish Government’s proposed spending and tax plans
for the Scottish Budget 2024/2025. The announcement revealed that the
Scottish Government was proposing a reduction in the overall Housing and
Buildings Standards budget from £738m to £533m. This represents a cut of
around £200m or 26%.
Number Number Bedrooms House type
5 Semi detached
2 Detached
4 Mid Terrace
7 End Terrace
3 Tenement
2 Maisonette
3
3+ bedrooms
4-in-a-block
6 4-in-a-block
1 Maisonette
1 Tenement
1
1 or 2 bedroom
Bungalow

Page 10

4.7     The More Homes budget, which provides grant aid for affordable new homes
and the buyback programme, was reduced from £564.6m in 2023/24 to
£375.8m in 2024/25.
4.8    The West Dunbartonshire Strategic Housing Investment Plan 2024/25 –
2028/29 (SHIP) was approved by West Dunbartonshire’s Housing and
Communities Committee in November 2023 and submitted to the Scottish
Government. Our Council Annual Resource Planning Assumption (RPA) from
the Scottish Government supporting the delivery of the SHIP was £10.795m.
The budget cut has reduced this figure to £8.167m for 2024/25, a cut of 24%.
4.9   The national capital resources available for future RPAs will depend on future
budget decisions by the Scottish Parliament. In the absence of future year
budget assumptions, and to aid programme management, we have been
advised by the Scottish Government to operate carry-forward limits for the
years 2025-26 – 2027-28 of 80%/60%/40% of current year RPA levels.
4.10    The budget cuts have implications for the SHIP and how it will be
programmed over the years ahead. We propose to manage spend on
individual projects to ameliorate the budget cuts and to maximise the delivery
of the new build and buy-back programmes.
4.11    We are exploring with partner RSLs opportunities to support the programme
with funding from their financial reserves or other sources. Some development
partners are known to hold significant reserves that could be employed to
assist in the funding crisis.
4.12   In joint discussions with the Scottish Government we are considering the use
of front funding, whereby the developer, the Council or RSL, would meet the
costs in the early part of the project with the SG guaranteeing their
contribution later. Such an arrangement would require agreement from the
Scottish Government and careful management of the programme, but it is an
approach that has been employed in the past when funding was also
previously constrained. We have so far reached agreement with one RSL
over their front funding during 2024/25, on the understanding that the grant
will be guaranteed payable on 1st April 2025. We have also assessed front
funding arrangements within the HRA Capital Investment Programme and
Budget for our Bonhill Gap Site development which presents no risk to the
wider investment programme.
4.13   As a first step we have remodelled the SHIP programme to address the
immediate priority of the financial shortfall in 2024/25. The table below shows
our current proposal on how the revised SHIP can be programmed for this
year as an interim measure. We are confident that the projects listed can be
accommodated within this year’s reduced budget with the help of front
funding. However, if there is no improvement to the AHSP funding awards,
significant amendments and possibly delays will ensue from 2025/26
onwards. This will be subject to ongoing discussions with all partners with a
view to protecting the programme as far as possible. There is an ongoing
element of exceeding the revised Resource Planning Assumption by

Page 11

£901,307, however we anticipate additional monies being made available to
support both the Councils and partner housing association ROTS
programmes (Buyback schemes).
4.14 Details of the new programme will be set out fully in the new SHIP 2025/26 –
2029/30, which will be presented to Housing and Communities Committee in
November 2024 for approval, where hopefully there will be more clarity on
future ASHP funding following the Scottish Government’s new Programme for
Government.
4.15 The Housing Development Team are continuously looking for opportunities to
provide additional new build council homes and will bring any potential site to
the Housing and Communities Committee with as much information as
possible as part of the regular More Homes update paper.
5. People Implications
5.10 The delivery of the More Homes delivery programme is managed through
existing resource within the Housing Development & Homelessness team
funded from the Housing Capital Investment Programme.
6. Financial and Procurement Implications
Financial
6.1 On 6 March 2024 Council approved the Housing Capital Programme 2023-
2028 which saw significant resources committed to the delivery of new council
West Dunbartonshire Council Units 2024-25
WDC - Pappert, Alexandria - P43626 26 £2,302,859.76
WDC - ROTS 2023-24 & 2024-25 - Non-Larger
Family - P46998
31 £450,000.00
WDC - ROTS 2023-24 & 2024-25 - Larger Family -
P47242
64 £1,408,000.00
WDC - Mount Pleasant, Old Kilpatrick - P45125 19 £1,370,448.19
WDC - Willox Park, Dumbarton - P45124 17 £1,075,000.00
WDC - Gilmour Avenue, Hardgate, Clydebank -
P46873
2 £195,000.00
WDC - Knowes HA - Faifley Bowling Club - P43600 27 £119,000.00
WDC - Caledonia HA - Bellsmyre Regeneration
Phase 1 - P43960
138 £1,348,000
WDC - Clydebank Health Centre - P45783 38 £200,000.00
DPHA/KHA ROTS (National Acquisition) 12 £600,000.00
Total 374 £9,068,307.95
Resource Planning Assumption £8,167,000.00
Difference £901,307.95

Page 12

homes in West Dunbartonshire. An expenditure budget of £155m for the
affordable housing supply programme is factored into the HRA Capital
Programme this will be updated to reflect the income and expenditure
highlighted within this report. As it currently stands, it is anticipated that this
programme will complete on project life budget.
6.2 Housing and Finance Officers will continue to assess the ongoing affordability
of future developments within the context of the Housing Revenue Account
Business Plan.
6.3 The proposed actions as a result in the reduction of Scottish Government
Affordable Housing Supply Programme funding is outlined in Section 4 of this
report.
Procurement
6.4 All new development sites will be subject to new detailed procurement
strategies and the opportunities highlighted within 4.5 of this report will
continue to be prioritised. Where the contract award is less than £213,000,
authority is delegated to the Chief Officer in consultation with the Procurement
Manager to instruct the award of contracts for the planned revenue and
capital spend detailed in this report to suppliers providing the most
economically advantageous offer to the Council.
6.5 All procurement activity conducted by the Council more than £2m is
subject to a contract strategy. The contract strategy for new housing
development within the HRA Capital Programme will be developed by the
Corporate Procurement Unit in consultation with Housing Development
Officers. The contract strategy will include, but is not limited to; contract
scope, service forward plan, the market, procurement model and routes –
including existing delivery vehicles, roles and responsibilities, risks, issues
and opportunities and on-going contract management. Opportunities to
maximise the positive social, economic, and environmental impact for the
Council through the relevant procurement processes will be developed in line
with procurement policy.
7. Risk Analysis
7.1 All Council new build projects have their own Risk Register which highlights
the risk within and out-with the project team’s control. These are maintained
and adjusted on an on-going basis.
7.2 With any new build project there is a risk that as the projects develop the cost
increases beyond the estimated contract cost. Any additional borrowing
requirements, or conversely, cost savings will be reported to future meetings
of the Housing and Communities Committee. However, this is mitigated
through a target cost model approach in our current contract arrangements
within the Scottish Procurement Alliance (SPA) framework and Scotland
Excel.

Page 13

8 Environmental Sustainability
8.1 The delivery of new homes is within the approved More Homes zero carbon
approach. Our current and future approach to strategic housing asset
management will continue to prioritise a ‘zero carbon’ approach to decision
making and deliverability and this will be done the aims of the Housing Asset
Management Strategy and the Council’s Climate Change Strategy.
9. Equalities Impact Assessment (EIA)
9.1 The proposal does not alter any existing policy or pattern of service delivery
and so is not considered to require an equalities impact assessment.
10. Consultation
10.1 As part of a rent consultation exercise, 92% of respondents indicated their
support for the Council’s ambitious plans to deliver the Housing Revenue
Account (HRA) new council house build programme. In addition, there was
positive support for the wider delivery of new build housing as part of the
recent Local Housing Strategy. Regular updates on new build development
are provided to the West Dunbartonshire Tenants and Residents Organisation
at the bi-monthly liaison meetings.
11. Strategic Assessment
11.1 The Local Housing Strategy is the overarching document setting out the
strategic direction for housing across all tenures and informs the future
investment in housing and related services across West Dunbartonshire.
11.2 Having considered all the Council’s strategic priorities, this report, and the
provision of new supply social housing for rent contributes to all the Council’s
strategic priorities.
Peter Barry
Chief Officer, Housing and Employability
Date: 7 August 2024
Person to Contact: John Kerr – Housing Development and Homelessness
Manager, Housing Development and Homelessness
Team, Housing and Employability, telephone:
07793717981, email: john.kerr@west-dunbarton.gov.uk
Mikayla Deeley, Senior Housing Development Officer,
Housing Development and Homelessness Team,
Housing and Employability: email mikayla.deeley@west-
dunbarton.gov.uk

Page 14

Appendices: None
Background Papers: West Dunbartonshire Council’s Local Housing Strategy
Local Housing Strategy, Health Inequalities Impact
Assessment
Wards Affected: All