WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer, Housing and Employability
Housing and Communities Committee: 1 May 2024
__________________________________________________________________
Subject: More Homes West Dunbartonshire – West Dunbartonshire Council
Affordable Housing Supply Delivery Programme 
1. Purpose
1.1  This purpose of this report is to provide the Housing and Communities
Committee an update on progress with West Dunbartonshire’s More Homes
Programme which oversees the delivery of the Council’s new home building
programme.
2. Recommendations
2.1 It is recommended that the Housing and Communities Committee:
(i) Notes the content of the report and the progress made to date in the
delivery of the Council’s More Homes West Dunbartonshire approach
including the recent site starts at the Pappert and Mount Pleasant
developments which means 133 new council homes are at construction
stage;
(ii) Notes the amended housing mix within the Bonhill Gap Site (O’Hare)
development project;
(iii) Notes the anticipated 27% reduction in Affordable Housing Supply
Programme funding available in 2024/25 in West Dunbartonshire and the
ongoing work to refresh the Strategic Housing Investment Programme
because of the funding reduction; and
(iv) Approve the undertaking to conduct all necessary procurement exercises
for the identified sites within the Future New Build – West Dunbartonshire
Affordable Housing Supply Programme in section 4.4 of this report to
deliver new council homes;
3. Background
3.1 In West Dunbartonshire the Affordable Housing Supply Programme (AHSP) is
delivered through a More Homes West Dunbartonshire strategic approach
which has successfully delivered over 1000 new affordable homes in West
Dunbartonshire to date and includes the Council’s own ambitious New House
Building Programme.
ITEM 9

Page 2

3.2 The Council’s last practical completion took place at the Queens Quay
development in September 2022 delivering 29 new Council homes in a key
regeneration area as part of a wider development which has delivered 146
new social rented homes.  The homes were the first residential properties to
be heated from the Council’s Queens Quay District Heating Network. This
development has been recognised at recent national housing sector awards
winning the following: -
• Best Residential Regeneration Project – Herald Property Awards
• Inside Housing Best Residential Development (Scotland)
3.3 These 29 new homes, are in addition to the completion of the Council’s first
fully dementia designed development at Creveul Court, Alexandria and other
exemplar developments in Haldane, Aitkenbar, Bellmsyre, Dumbarton
Harbour and St Andrews, Clydebank.  The Council have now completed 12
new build developments since 2013 and are the largest developer of social
homes in West Dunbartonshire delivering 496 new homes and 122
acquisitions through our buyback scheme to date as outlined in Table 1
below.  The 500th new build home in the More Homes West Dunbartonshire
delivery programme will be delivered in late Summer 2024 at our Clydebank
East development:
Table 1:  Completed Council New Build and Acquisitions
Project No. of
Units
Completion
Date
Granville Street (Phase 1), Clydebank 24 July 2013
Miller Road, Alexandria 15 October 2013
Granville Street (Phase 2), Clydebank 9 February 2014
Central Bellsmyre, Dumbarton 36 December 2014
Hillstreet Square, Dumbarton 37 August 2015
Second Avenue, Clydebank 40 April 2018
Creveul Court, Alexandria 22 April 2021
Aitkenbar Primary School 55 July2021
Haldane Primary School 58 August 2021
St Andrews, Clydebank 126 October 2021
Dumbarton Harbour, Dumbarton 45 December 2021
Queens Quay, Site B, Clydebank 29 August 2022
Buyback Acquisitions 130 Ongoing
Totals 626
3.4   The Strategic Housing Investment Plan (SHIP) 2024-2029, outlining West 
Dunbartonshire’s Affordable Housing Supply Programme through the More
Homes West Dunbartonshire approach was approved by the Housing and
Communities Committee in November 2023. The SHIP outline plans to meet
the Council Administration’s aim of delivering 2500 new affordable and social
rented homes over the next 10 years. 
4. Main Issues
More Homes West Dunbartonshire - Delivery Programme
4.1 Building new affordable homes has an important role to play in revitalising
local economies and assisting with post-pandemic and economic recovery

Page 3

plans, negating the impacts of the current cost of living crisis and combatting
poverty including child poverty.  It is also clear that the need for affordable
homes has and will increase in the current ongoing economic environment. 
4.2 Our More Homes West Dunbartonshire approach is an ambitious plan that
aims to continue the positive momentum of the delivery of much needed
Council homes in West Dunbartonshire and will significantly assist the
Council’s aim to deliver 2500 new social and affordable homes by 2032.
4.3 As the biggest affordable housing developer in West Dunbartonshire, the
Council has identified several future development sites for new council homes
to address existing and new housing need. The design of these homes will
further develop, improve and exceed current best practice, providing
sustainable homes using innovative technology and delivering on our low
carbon ambitions including passivhaus and other net zero carbon
opportunities.
4.4 The Strategic Housing Investment Plan and HRA Capital Plan outlined the
plans the Council have for meeting their new build ambitions.  Some of the
initial plans were and continue to be impacted as a result of global issues
revised new build targets for the Council are outlined below:
Table 2: Council New Build Programme
Site/Developer Number of
Units
Number of
Specialist
Provision
Est Site
Start
Est Completion
Date
Clydebank
East,
Clydebank
88 9
On Site
January
2023
Spring 2025
(First handovers
– August 2024)
Pappert,
Bonhill
Alexandria
26 3
On site
March
2024
Spring 2025
Mount
Pleasant
19 19 On site
April 24
Spring 2025
Willox Park 17 17 Summer
24
Autumn 2025
Bonhill Gap
Sites* 29 4 Autumn 24 Winter 2025
Queens Quay
Site C
100 10 TBC TBC
Clydebank
Health Centre*
38 22 Spring 25 Spring 2026
Bank Street,
Alexandria
22 22 Autumn 24 Autumn 2025
Dennystoun
Forge
20 20 TBC  TBC
Clydebank
Gap Sites*
50 10 Summer
24
Summer 2025

Page 4

*Current Planning figures
4.5 Updates for each site are noted below:
Clydebank East:
This development will deliver 88 new homes and has been designed to meet
the housing need within the wider West Dunbartonshire area. The table below
shows the housing mix:
House Type Sustainability Standard Number of New
Homes
Wheelchair Bungalow
3bed/4person
Net Zero 3
House 3bed/5person Net Zero 15
House 4 bed/7person Net Zero 12
House 5 bed/8 person Net Zero 8
Cottage Flat 1 bed/2 person
(Wheelchair)
Net Zero 4
Cottage Flat 2 bed/3 person Net Zero 4
Flat 1 bed/2person Net Zero 16
Flat 2 bed/4 person Net Zero 24
Wheelchair Flat 1 bed/2person Net Zero 2
Works commenced on this development in January 2023 and the first homes
are scheduled to be handed over in August 2024. 
All houses are designed to the Housing for Various Needs Standard (HfVN).
There will be 9 fully Wheelchair (WCH) accessible properties.  The 4 and 5
bedroom homes will all have ground floor double bedrooms.  
The development at Clydebank East will see the completion of a major
housing led regeneration of a key priority regeneration area identified in the
Local Housing Strategy and will be the first fully zero carbon housing
development in West Dunbartonshire and marks a significant milestone in our
transition to net zero new homes approved at the August 2022 meeting of the
Housing and Communities Committee.  Plans are being developed to mark
the significance of the net zero element of the development and the
development will see the 500th new home delivered through the More Homes
West Dunbartonshire approach.
We have now finalised the engagement with the Scottish Government for the
above benchmark grant request dues to the complexities of the development
(Gilmour
Avenue)
Silverton
Regeneration
Tbc Tbc tbc Tbc
Buyback
Scheme (60
per year)
300 36 2023/24 2027/28
709 units 172 units

Page 5

at Clydebank East and have been awarded £12,604,632.37 in Affordable
Housing Supply Programme grant funding, this equates to over £143k grant
per home.  This is a positive outcome and ensures the delivery of the
development without any potential negative impact on the wider Housing
Revenue Account.
Pappert, Bonhill
This project enjoyed a site start date in early March, delivering the housing
mix as follows: -
House Type Sustainability Standard Number of New
Homes
House 3bed/5 person Passivhaus 6
House 3bed/5 person Net Zero 6
House 4bed/6person Net Zero 4
House 4bed/7person Net Zero 1
Flat 2bed/3person w/c Net Zero 3
Flat 1 bed/2person Net Zero 6
Mount Pleasant, Old Kilpatrick
This is a 19-unit complex which is designed for elderly residents and will
deliver high quality amenity housing. CCG have been appointed as the main
contractor following the Tendering Committee in September, having been
directly appointed from the Scotland Excel Framework. The site start date was
successfully achieved on 15th April 2024 and construction will last
approximately one year. 
Willox Park, Doveholm, Dumbarton
The development of seventeen new homes to be delivered at the former care
home site continues within the design phase and planning has been
submitted by Housing Officers. A decision is expected, via delegated
authority, at the end of February. 
The net zero heat strategy will be delivered by ground source heat pump, as it
was felt that this solution to be preferable than an air source heat pump for
each home.  The development will also utilise PV (Photovoltaic) panels and a
MVHR (Mechanical Ventilation with Heat Recovery) system.
There has been positive dialogue in terms of the current plans with both the
Willox Park residents and planning officers.  Ongoing engagement will be
maintained with the current Willox Park residents throughout the delivery
process and the development will be tied to the wider regeneration plans for
the Willox Park Sheltered Housing Complex which were approved by the
Housing and Communities Committee in February 2024.
Bonhill Gap Site Strategy

Page 6

The pre-planning application process has commenced on the development of
the 2/3 separate gap sites which are contained within this wider development. 
We have now procured engineering consultants as we move closer to a full
planning application. We are scheduled to submit planning week beginning
29th April 2024. 
We have amended the housing mix for the O’Hare gap site and will now
deliver 6 one-bedroom cottage flats instead of the previous planned 5 three-
bedroom terraced homes, this revised housing mix meets housing need and
demand projections within the wider area.  The projected costs of delivery
meet our affordability threshold which the previous housing mix could not. 
We have also altered some of the initial design plans to incorporate two
adaptable 6/7 bed homes within the development to meet identified housing
need for larger families who are experiencing overcrowding. 
Bank Street, Alexandria
The Council is currently developing a proposal for 22 sheltered/amenity
housing units in partnership with the HSCP. This will include an options
appraisal in terms of the existing provision within the local area.
Engineering works will be starting in January. The delay in appointing
engineering consultants has pushed back the anticipated timescales of a
planning application being submitted in May 2024. We are looking to appoint
a contractor after May with an anticipated site start date in November 2024
Queens Quay, Site C, Clydebank
The Council has been developing a design to deliver a projected 20 units on
this site to complement the housing mix within sites A and B.  This
development will also be designed to meet low/zero carbon principles and
linked to the Queens Quay district heating network.
.
Pre-planning response was received on the 25 February 2023 highlighting
concern of the WDC development proceeding in isolation. We have adopted a
proactive response to this issue and have developed masterplan diagrams
incorporating the surrounding sites and have conducted valuations on the
adjacent site to Queens Quay C with a view to purchasing additional land to
deliver more affordable housing in the Queens Quay regeneration site and
seek to develop a mixed tenure approach to any expanded development site
delivering one hundred new affordable homes. The discussions with CRL
(Clydeside Regeneration Limited) to progress the possibility of acquiring this
additional land have not yielded a positive conclusion and the reduction in
funding highlighted later in this report in respect of the wider Affordable
Housing Supply Programme will add a further challenge to the viability of this
development.  An options appraisal will be carried out over the next couple of
months and the outcome of this will be reported to the next meeting of
Housing and Communities Committee.

Page 7

Clydebank Health Centre
Our appointed design team are doing some feasibility work based on a
housing mix of 20 units of sheltered housing and 18 units to be a mix of family
housing and cottage flats within the development site. The aim of the 20 units
of sheltered housing is to introduce the potential; to reprovision existing
sheltered housing currently provided at Young Street, therefore strategically
improving the provision of sheltered accommodation within Clydebank. 
This is in advance of the demolition of the buildings within the site which is
currently scheduled to start imminently. 
Dennystoun Forge Gypsy/Traveller Site
A submission was made to the Scottish Government for support funding from
their Gypsy/Traveller Accommodation Fund for significant improvements to
the Dennystoun Forge site, including new energy efficient chalet type
accommodation following a consultation exercise with site residents. 
However, we were notified that this submission was unsuccessful at this point.
We have since engaged the Scottish Government following the outcome of
this and have provided additional information to the Scottish Government in
support of the application. 
Unfortunately, we have since been informed that no new projects will receive
funding until April 2025 at the earliest, as a result we are proposing that the
development forms part of the wider Affordable Housing Supply Programme
and have engaged with the Scottish Government to progress this.  This will
mean the development is included within the Strategic Housing Investment
Programme pending a successful conclusion to current discussions with the
Scottish Government’s More Homes Team.
Queen Mary Avenue, Clydebank (Clydebank Gap Sites)
The transfer of the site at Queen Mary Avenue, Clydebank with vacant
possession at the cost of £140,000 from the Council’s General Fund to the
Housing Revenue Account for the delivery of new Council homes was
approved at the February meeting of the Housing and Communities
Committee and has now been concluded.  
The Council is preparing a demolition programme to allow the site to be
cleared as soon as possible following the recent departure of Council staff
teams who were using the premises. 
A feasibility study is being undertaken to inform how best to develop the site,
taking into consideration housing need and demand for the area. This
programme is running parallel with the pre-demolition works.

Page 8

Gilmour Avenue, Hardgate (Clydebank Gap Sites)
As part of the wider development of our Clydebank Gap Site strategy we
identified a Housing Revenue Account site in the Hardgate area at Gilmour
Avenue.  The site was previously the location of timber garages on concrete
bases.  These have long since been demolished and the site has been beset
with fly tipping issues for several years. The proposed development would see
two three bed semi-detached homes to be delivered utilising modular
construction methods.  A planning application was submitted in early February
2024, and we await approval.
Silverton Regeneration
The 2 identified sites in Smollett Road and Dumbuie Avenue are progressing
towards demolition and building warrants for demolition in place.  We are
currently undertaking a feasibility development study to assess the suitability
and potential capacity for the delivery of new homes within these sites.  
Buyback Programme
The Council’s buyback programme which incorporates the Mortgage to Rent
Scheme purchased 16 new homes in 2022/23.  In 2023/24 we purchased 40
new homes at an average purchase cost of £100,000.
In 2023/24 and following approval of the Strategic Housing Investment Plan
by the Housing and Communities Committee in November 2022 and
subsequently the decision by West Dunbartonshire Council in March 2023 to
deliver an enhanced Housing Capital Investment Programme including
additional funding for buyback purchases we are now scaling up ambition
around our buyback programme.  In 2024/25 and in each of the subsequent
years up to and including 2027/28 we plan to deliver 60 new homes each year
meaning a minimum of 300 new Council homes to meet identified need will be
added to the Council housing stock.  
4.6 In December 2023, the Deputy First Minister and Cabinet Secretary for
Finance set out the Scottish Government’s proposed spending and tax plans
for the Scottish Budget 2024/2025. The announcement revealed that the
Scottish Government was proposing a reduction in the overall Housing and
Buildings Standards budget from £738m this year to £533m next.   This
represents a cut of around £200m or 26%.  These proposals were agreed in
February 2024.
4.7 The More Homes budget, which provides grant aid for affordable new homes,
is shown to reduce from £564.6m this year to £375.8m in 2024/25. While the
capital funding side of this budget which supports the delivery of Strategic
Housing Investment Plans was expected to be protected from such a
significant reduction with a smaller reduction of £75m or 14%, it appears that

Page 9

this is no longer the case, and while we await formal notification of the
Affordable Housing Supply Programme budget in early May there is likely to
be a significant negative impact on new social housing delivery. 
4.8 The planned West Dunbartonshire Council Annual Resource Planning
Assumption (RPA) from the Scottish Government to help the delivery of the
Council’s Strategic Housing Investment Plan (SHIP) and subsequently the
Council’s own new build programme was £10.795m.  We have since been
notified that the revised RPA for 2024/25 will be £7.922m, this represents a
reduction of 27%.
4.9 Our SHIP 2024/25 – 2028/29 uses this projected budget to plan the wider
development programme.  We are in ongoing discussion with our colleagues
in the Scottish Government’s More Homes Division over what the reduction in
funding will mean for our programme and a programme meeting is scheduled
for 7th May 2024 to agree a revised programme.
4.10 In advance of the programme meeting we are scenario planning the impact of
the 27% reduction in the 2024/25 RPA this may have the following impacts: -
• No new projects being approved in 2024/25 because of existing
commitments within the programme without the developing
organisations front funding their development;
• A reduced RPA allocation of £2.873m (27%), this also represents a
loss of a minimum of that figure to the wider West Dunbartonshire
economy;
• A potential 32 less homes being delivered on an annual basis in West
Dunbartonshire because of the reduction in funding (160 within the
lifecycle of the current Strategic Housing Investment Plan);
• High levels of homelessness and housing need
4.11 While the proposed reduction in funding presents a challenge to realising the
Council’s new housing ambition, it is one that we will strive to manage
effectively with strategic planning.  The Strategic Housing Investment Plan will
be managed through the More Homes Project Board to minimise the impact of
the reduction in funding and to maximise delivery of the programme priorities.
To mitigate the impact of the cuts it may be necessary to delay some projects
and to stretch the programme.  It is intended that Council Officers will refresh
the Strategic Housing Investment Plan after the programme meeting in May
and will report the revised to the Housing and Communities Committee
meeting in August with additional proposed actions to mitigate the impact of
the significant reduction in funding.
4.12 The Housing Development Team are continuously looking for opportunities to
provide additional new build council homes and will bring any potential site to
the Housing and Communities Committee with as much information as
possible as part of the regular More Homes update paper.

Page 10

5. People Implications
5.1 The delivery of the More Homes delivery programme is managed through
existing resource within the Housing Development & Homelessness team
funded from the Housing Capital Investment Programme.
6. Financial and Procurement Implications
Financial
6.1 On 6 March 2024 Council approved the Housing Capital Programme 2023-
2028 which saw significant resources committed to the delivery of new council
homes in West Dunbartonshire.  An expenditure budget of £155m for the
affordable housing supply programme is factored into the HRA Capital
Programme this will be updated to reflect the income and expenditure
highlighted within this report.  As it currently stands, it is anticipated that this
programme will complete on project life budget.
6.2 Housing and Finance Officers will continue to assess the ongoing affordability
of future developments within the context of the Housing Revenue Account
Business Plan.
6.3 The proposed actions as a result in the reduction of Scottish Government
Affordable Housing Supply Programme funding is outlined in Section 4 of this
report.
6.4 As previously reported to Committee as of 1st April 2024, Local Authorities are
now exempted from LBTT ADS (Land and Building Tax Additional Dwelling
Supplement).  This will have a positive impact on the buyback budget.
Procurement
6.10 All new development sites will be subject to new detailed procurement
strategies and the opportunities highlighted within 4.5 of this report will
continue to be prioritised. Where the contract award is less than £213,000,
authority is delegated to the Chief Officer in consultation with the Procurement
Manager to instruct the award of contracts for the planned revenue and
capital spend detailed in this report to suppliers providing the most
economically advantageous offer to the Council.
6.11 All procurement activity conducted by the Council more than £2m is.
subject to a contract strategy. The contract strategy for new housing
development within the HRA Capital Programme will be developed by the
Corporate Procurement Unit in consultation with Housing Development
Officers. The contract strategy will include, but is not limited to; contract
scope, service forward plan, the market, procurement model and routes –
including existing delivery vehicles, roles and responsibilities, risks, issues

Page 11

and opportunities and on-going contract management. Opportunities to
maximise the positive social, economic and environmental impact for the
Council through the relevant procurement processes will be developed in line
with procurement policy.
7. Risk Analysis
7.1 All Council new build projects have their own Risk Register which highlights
the risk within and out-with the project team’s control.  These are maintained
and adjusted on an on-going basis.
7.2 With any new build project there is a risk that as the projects develop the cost
increases beyond the estimated contract cost.  Any additional borrowing
requirements, or conversely, cost savings will be reported to future meetings
of the Housing and Communities Committee. However, this is mitigated
through a target cost model approach in our current contract arrangements
within the Scottish Procurement Alliance (SPA) framework and Scotland
Excel.
8 Environmental Sustainability
8.1 The delivery of new homes is within the approved More Homes zero carbon
approach. Our current and future approach to strategic housing asset
management will continue to prioritise a ‘zero carbon’ approach to decision
making and deliverability and this will be done the aims of the Housing Asset
Management Strategy and the Council’s Climate Change Strategy.
9. Equalities Impact Assessment (EIA)
9.1 The proposal does not alter any existing policy or pattern of service delivery
and so is not considered to require an equalities impact assessment.
10. Consultation
10.1 As part of a rent consultation exercise, 92% of respondents indicated their
support for the Council’s ambitious plans to deliver the Housing Revenue
Account (HRA) new council house build programme. In addition, there was
positive support for the wider delivery of new build housing as part of the
recent Local Housing Strategy.  Regular updates on new build development
are provided to the West Dunbartonshire Tenants and Residents Organisation
at the bi-monthly liaison meetings. 
10. Strategic Assessment
10.1 The Local Housing Strategy is the overarching document setting out the
strategic direction for housing across all tenures and informs the future
investment in housing and related services across West Dunbartonshire.

Page 12

10.2 Having considered all the Council’s strategic priorities, this report and the
provision of new supply social housing for rent contributes greatly to all the
Council’s strategic priorities.
Peter Barry
Chief Officer, Housing and Employability
Date: 17th April 2024
Person to Contact: John Kerr – Housing Development and Homelessness
Manager, Housing Development and Homelessness
Team, Housing and Employability, telephone:
07793717981, email: john.kerr@west-dunbarton.gov.uk
Mikayla Deeley, Senior Housing Development Officer,
Housing Development and Homelessness Team,
Housing and Employability: email mikayla.deeley@west-
dunbarton.gov.uk
Appendices: None
Background Papers: West Dunbartonshire Council’s Local Housing Strategy
Local Housing Strategy, Health Inequalities Impact
Assessment
Wards Affected: All