Appendix 1 – 23-24 H&E Delivery Plan year-end progress
1. Our communities
Objective 1. Our neighbourhoods are safe, resilient, and inclusive
Action Status Progress Due Date Note Owner
Develop and implement the
revised Antisocial Behaviour
Strategy
31-Mar-
2024
Significant progress has been made to develop the ASB
strategy. A draft version has been completed with further
consultation planned for April. It is anticipated that the final
strategy will be presented to committee for approval in early
Autumn.
Nicola
Pettigrew
Develop CCTV transmission
strategy
31-Mar-
2024
This action has been successfully completed. We have
developed a CCTV strategy bringing together public space
CCTV and housing CCTV cameras under the one contract.
Work to identify new cameras and locations has been carried
out to inform the transmission technical survey identifying
upgrade and modernisation requirements for the system as a
whole.
Nicola
Pettigrew
Upgrade CCTV infrastructure
(phase 1)
31-Mar-
2024
Significant progress has been made to date. We have secured
UK shared prosperity funding, carried out all of the preparatory
work to allow a full technical survey of the system identifying
upgrade requirements. Work is underway to review
recommendations and costings from the survey before we can
begin the procurement of the upgrade. Phase 2 of this action
Nicola
Pettigrew
ITEM 8 -
APPENDIX 1

Page 2

Action Status Progress Due Date Note Owner
will commence in 24/25 where the technical upgrade will be
implemented.
Objective 2. Our residents health and wellbeing remains a priority
Action Status Progress Due Date Note Owner
Respond to the findings of
the Homelessness
Prevention and Temporary
Accommodation Task and
finish Group
recommendations
31-Mar-
2024
This action has been successfully completed. Local response
developed and incorporated within Rapid Rehousing Transition
Plan (RRTP) performance framework.
John Kerr
Carry out a review of the
Council’s approach to
Homelessness prevention
31-Mar-
2024
This action has been successfully completed and service is
being redesigned to meet needs.  We will look at developing a
more holistic approach to access to housing following the
publication of the Housing Bill.
John Kerr
Implement Year 5 of the
Home at the Heart – Rapid
Rehousing Transition Plan
31-Mar-
2024
This action has been successfully completed. Year 6 of the
transition plan will be the focus of 24/25 with progress reported
through the Housing and Improvement Board.
John Kerr
Review and provide greater
integration within Housing
Support
31-Mar-
2024
This action has been successfully completed and will be
implemented within the wider Housing Solutions service refresh
and redesign.
John Kerr
Objective 3. Our residents are supported to increase life and learning skills

Page 3

Action Status Progress Due Date Note Owner
Ensure no one left behind by
supporting skills and learning
for work, life and learning
31-Mar-
2024
This action has been successfully completed. We have secured
funds for No One Left Behind, Parental Employability Support
and UK Shared prosperity. We have identified activity to
develop skills among people targeted for the use of these funds
and established a set of SMART targets. We have undertaken
grant distribution and engaged specialist employability support
providers to support our aims.
Stephen
Brooks
Review and implement
revised service provision for
W4U and Communities –
youth learning
31-Mar-
2024
This action has been successfully completed. We have
identified service priorities for the remaining members of staff
and a plan for the Youth Learning Team will emerge as a result
of the consultation for the restructure of the Communities
Team.
We are currently working on a partnership agreement with
Education Services. This identifies activities being delivered
within and beyond the schools and has input from both W4U
and the Communities Team and we are preparing for an HMIE
Inspection of Community Learning and Development activities
that will take place in mid-April.
Stephen
Brooks
2. Our Environment
Objective 5. Our resources are used in an environmentally sustainable way

Page 4

Action Status Progress Due Date Note Owner
Develop new Housing Design
Standard incorporating
proposed changes to
specifications for new social
housing
31-Mar-
2024
This action has been successfully completed. New Design
Standard approved by Housing and Communities Committee in
November and in place for 1st April 2024
John Kerr
Deliver an approach to meet
Energy Efficiency Standard
for Social Housing (EESSH
2)
31-Mar-
2024
This action has been successfully completed through the
response to the Social Housing Net Zero Standard.  The
publication of this will require a refreshed action in the 24/25
Delivery Plan
John Kerr
Deliver a Greener, Fairer
revised HRA Capital
Investment Plan
31-Mar-
2024
Progress on this action has been delayed as the national
publication of the EESSH2 standard was delayed. To date, we
have contributed to the national consultation and the Social
Housing Net Zero Standard strategy. We anticipate the national
guidance and standards to be published later this year where
we will work to complete this action throughout 2024/25.
John Kerr
Objective 6. Our neighbourhoods are sustainable and attractive
Action Status Progress Due Date Note Owner
Deliver the HRA Capital
Improvement programme for
2023/24
31-Mar-
2024
The action has been successfully completed. Core projects
were delivered in line with expectation and budget. This
includes improvements such as, external wall insulation (EWI),
heating, environmentals (paths), kitchens, uPVC window and
door installations. 
Martin
Feeney
Improve customer
satisfaction with Building
Services
31-Mar-
2024
Significant progress has been made to improve satisfaction
with Building services. To date, we have implemented a self-
service portal to allow tenants to report a repair online, view
Martin
Feeney

Page 5

Action Status Progress Due Date Note Owner
repair history and check on any active repairs. Work continues
to develop the portal which we anticipate will provide an
improved service. In addition to this the service has focused on
clearing out of target repairs whilst servicing the continuing
repairs raised. We will use tenant feedback to develop and
shape further improvements which will be captured in the
customer satisfaction improvement plan for 2024/25.
Improve maintenance &
repairs performance
31-Mar-
2024
This action has been successfully completed. Significant
progress has been made over the year to improve the
performance on a range of key areas. At the end of quarter
three, four of the PIs met or exceeded target with the remaining
four showing improvement within year despite not meeting
target. The service has focused on clearing out of target repairs
whilst servicing the continuing repairs raised. We will continue
to implement the improvement plan and monitor progress in
2024/25.
Martin
Feeney
Reduce the number of empty
properties under repair
31-Mar-
2024
This action has been completed. Very good progress has been
made over the year to reduce the number of void properties.
The service has significantly reduced the number of void
properties subcontracted with most now completed by in-house
teams. As the number of void properties under repair reduces
and older properties are returned ready for the let; the average
days to inspect and repair void properties is also reducing, we
will continue to monitor progress in 2024/25.
Martin
Feeney
Improve progress on Electric
Installation Condition Reports
31-Mar-
2024
Significant progress has been made to improve progress on
completion of EICRs focusing on improving access rates and
contractor capacity. To date, we have reviewed our
communication with tenants and tenant groups on the
requirement to complete EICRs including review of notification /
Martin
Feeney

Page 6

Action Status Progress Due Date Note Owner
appointment letters to ensure these are clear, consistent with a
resilient message, we will continue to review the effectiveness
of our communication and modify where necessary to improve
access rates. To meet compliance targets, we carried out a
review of contractor capacity and appointed an additional
contractor in January 2024.
We anticipate the measures we have taken thus far will
improve our compliance rates and we will continue to work to
improve performance over the coming year.
Implement revised process
and monitor performance to
address dampness and
mould in Tenant Homes
31-Mar-
2024
Action completed on target. Work has progressed to effectively
manage dampness within the Councils' housing properties.
Monitoring of performance highlighted additional PIs were
required to better understand the overall performance and
effectiveness of the new processes and policy. This has shown
areas where improvements will be required in 2024/2025 and
future years. 
Martin
Feeney
Ensure the Council’s Housing
stock maintains compliance
with the Scottish Housing
Quality Standard and reduce
the number of properties held
in abeyance.
31-Mar-
2024
This action is complete for 23-24. Monitoring on contributing
work streams show good progress in excess of targets on
energy efficiency projects, kitchens, paths, and heating
however progress in bathrooms, showers, roofs is less than
anticipated due to tenant agreement, owner agreement and
EICR is much less than planned due to tenants providing
access. Building Services have procured an additional delivery
contractor in efforts to improve completions of EICR's. This has
been in place from January 2024 and shows signs of early
improvements, albeit monthly numbers still need to increase to
meet planned targets. Officers are working to improve this
position.
Alan Young

Page 7

Action Status Progress Due Date Note Owner
Ensure the Council’s Housing
stock progresses towards the
achievement of the energy
efficiency standard for social
housing.
31-Mar-
2024
This action is complete for 23-24. Monitoring on contributing
work streams show progress in excess of targets on the
external wall insulation (EWI) project and going very well at this
stage. Work will continue into 24-25 along with further
development of additional energy related measures contributing
to Net Zero standards.
Alan Young
Develop Housing Capital
Investment Plan for 2023/28.
31-Mar-
2024
This action has been successfully completed. A consultation
was undertaken with tenant groups and areas for additional
capital investment have been developed and agreed. A full
report was presented and approved at August Housing and
Communities Committee.  Additional budget incorporated into
main programme and additional target numbers have been
added to progress monitoring.
Alan Young
Deliver Year 2 local Housing
Strategy Objectives
31-Mar-
2024
This action has been successfully completed. A full report of
progress will be presented to the Housing and Communities
Committee
John Kerr
Deliver the Council’s
Affordable Housing Supply
Programme
31-Mar-
2024
This action has been successfully completed. Positive progress
and as planned two new developments now on site at
Clydebank East and Pappert.
John Kerr
Review Council buyback
policy
31-Mar-
2024
This action has been successfully completed and approved at
February 2024 Housing and Communities Committee. John Kerr
Develop an approach to
delivering alternative housing
tenures
31-Mar-
2024
This action has been successfully completed and approved at
February 2024 Housing and Communities Committee. John Kerr
Increase tenant participation
in relations to housing ops
(response rates)
31-Mar-
2024
This action has been successfully completed. We are exploring
opportunities to engage with key groups this includes working
with Tenant Participation Team/WDTRO to understand existing
methods and opportunities.   IHMS issue resolved for surveys
Nicola
Pettigrew

Page 8

Action Status Progress Due Date Note Owner
and will now be backdated to be sent from April 2024.  Agreed
that incentives will be offered to encourage increased uptake of
returns.
Implement digital
improvement for housing
operations (mobile app)
31-Mar-
2024
This action has been successfully completed. New Tenant Visit
pilot working well, mobile app now fully extended to all Housing
Officers.  Further operational areas in progress for deployment
to mobile app roll out including, Pre-term tenant visit,
succession, and new arrear management reports.  Work will
continue throughout 24/25 to complete all 76 individual areas
onto mobile app.
Nicola
Pettigrew
Implement digital
improvement for housing
operations (self-serve portal)
31-Mar-
2024
This action has been successfully completed. Self-portal
available for tenants to manage rent account and repairs.
Further work will continue throughout 2024/25
Nicola
Pettigrew
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Failure to meet
citizen
expectation and
service
standards
Risk of citizen dissatisfaction
due to us not doing what we say
we will when we say we will or
not completing required works
first time. 
27-Mar-
2024
Mid-year figures show satisfaction
performance on target and
improved from previous year.
Satisfaction is based on face-to-
face interviews and may present a
bias. Work is ongoing with IHMS to
include automated satisfaction
surveys to reduce any potential
bias.
Martin
Feeney

Page 9

Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Failure to
secure funding
to invest in
WDC’s CCTV
infrastructure.
The public space CCTV
infrastructure covers the three
main townships of Alexandria,
Dumbarton and Clydebank with
a mix of fixed space and
redeployable cameras. Until
resources can be secured and
improvements made the Council
does remain at risk from
reputational damage, should the
system fail.
02-Apr-
2024
We have secured funding from the
UK shared prosperity funding and
HRA to allow for the upgrade of the
CCTV system. Work will progress
over 24/25 to complete the
upgrade.
Nicola
Pettigrew
Failure to
deliver medical
adaptations in
agreed target
timescales
This is monitored to ensure
target timescale of 79 days
average for housing medical
adaptations is adhered to
ensure satisfaction with the
service and support those in
need of this service.
26-Mar-
2024
Q1, Q2 Good overall progress in-
year so far and continuing to clear
legacy jobs helping to improve the
overall position. Average days
performance continues to improve
and in target for Q1 (46 days) & Q2
(32 days) On track overall for
improvement and reducing risk.
Alan Young
Failure to
achieve the
outcomes of the
Scottish Social
Housing Charter
The Scottish Social Housing
Charter sets out the standards
and outcomes that tenants and
customers should expect from
social landlords, in terms of the
quality and value for money of
the services they receive.
Failure to continue to meet
these could place the Council at
01-Apr-
2024
Assessment remains as previous,
however increased risk concerns
have been identified and included
within the Councils Annual
Assurance Statement which was
submitted to the Housing Regulator
in October
Peter Barry;
John Kerr

Page 10

Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
risk of the intervention powers of
the Scottish Housing Regulator
Failure to
maintain
Housing Stock
The risk that Council’s Housing
Stock are not fully fit for purpose
with consequent adverse impact
on our ability to deliver efficient
and effective housing for
Council tenants.
26-Mar-
2024
No change to risk score,
programme for investment and
upgrades to council housing
continues into 24-25 and a further
five-year programme to 27-28.
Alan Young
3. Our Economy
Objective 7. Our area has the infrastructure for sustainable and inclusive growth where businesses can flourish
Action Status Progress Due Date Note Owner
Engage with W4 business
to explore the potential for
access to green jobs for
local residents
31-Mar-
2024
This action has been successfully completed. We have
established a steering group for the management of the delivery
of UKSPF priorities and the development of a monitoring
framework. We will use this group to explore the potential for
improving access to green jobs. In addition, we are preparing for
the second year of UKSPF delivery.
Stephen
Brooks
Objective 8. We will support our residents to access employment and training opportunities

Page 11

Action Status Progress Due Date Note Owner
Support and implement
CLD, Employability and
Welfare benefit three-year
plans to promote quality
frameworks and
partnership working to
enhance work, learn,
money service provision
31-Mar-
2024
This action has been successfully completed. We have compiled
the three-year plans for each of the services. We are now
approaching the end of the CLD Planning period and will
undertake a consultation process to identify the priorities for the
forthcoming planning period. This will take into account the
changing operating environment and will focus on existing
services and the opportunities emerging from No One Left
Behind and UK shared prosperity funds.
Stephen
Brooks
Maximise income from
employment – supporting
residents into employability
31-Mar-
2024
This action has been successfully completed. The local child
poverty plan is based on addressing the drivers of poverty.
These include supporting people to maximise income from
employment. We have established our employability plan and
will deliver activities through the use of UK Shared Prosperity
Funding and No One Left Behind Funding.
We have engaged a number of external service providers to
deliver specialist support that will address barriers to
employment and complement the work that the W4U Teams are
carrying out. To date we have supported almost 300 people into
employment during this financial year and are on track to
achieve our target of 400.
Stephen
Brooks
Promote inclusive growth
through access to training
and apprenticeship
opportunities
31-Mar-
2024
This action has been successfully completed. We have
established our annual Modern Apprenticeship and Foundation
Apprenticeship courses and we have developed out learning
centre accredited courses to ensure that we have the capacity to
deliver appropriate training that will meet the demands of
employers in the local labour market.
Our Modern Apprenticeship provides access to opportunities in
social care and childcare, business admin and construction and
Stephen
Brooks

Page 12

Action Status Progress Due Date Note Owner
we are currently supporting more than 120 Modern and
Foundation apprentices. This is complemented with support for
those who wish to progress in the labour market through training
and development. To do this we are working with social service
teams to support their workforce development requirements.
In addition, we have submitted our proposal to SDS where we
have requested a contract to deliver 90 MAs. We will be
informed of the outcome of that proposal in March.  Meanwhile,
we have engaged with school pupils and leavers to promote
foundation and modern apprentices for the forthcoming year.
Review and implement
revised service provision
W4U – adult learning
31-Mar-
2024
This action has been successfully completed. We have reviewed
service provision and have a plan in place to deliver adult
learning services throughout West Dunbartonshire. Our focus will
be placed on the delivery of:
• Adult Literacies: Rolling programmes of support based
on individual needs as well as an Additional Learning
Support Needs (ALSN) group run in partnership with Unity
Empower.
• Community based Vocational Courses: SQA
accredited units, SCQF levels 4 - 6 in a range of subject
areas including Humanities, Childcare, IT, Practical skills
such as Fashion and Textiles, Horticulture and Cookery
as well as British Sign Language.
• Digital Learning: Rolling programmes of Digital Friends
which offers complete beginners one-to-one support.
• ESOL: Rolling programme of community classes.
Stephen
Brooks

Page 13

Action Status Progress Due Date Note Owner
• Family Learning: Rolling programme of short Family
Learning activities, for the most part in partnership with
Primary schools.
• In addition, we are exploring ways to incorporate 'Multiply'
(UKSPF) objectives into our work.
Objective 9. We will work with partners to support economic development to deliver increased prosperity for our area
Action Status Progress Due Date Note Owner
Establish the monitoring
and reporting framework
for UK Shared prosperity.
31-Mar-
2024
This action has been successfully completed. We have
completed the required documentation to draw down the first
year of UK Shared Prosperity Funding. This includes a clear
description of the activities with associated outputs and
outcomes for all the activity. We have established methods for
gathering that information and this will be used to inform future
claims and reporting.
The outcomes centre on the UKSPF priorities: 'community and
place'; 'business development'; 'people and skills' and 'Multiply'.
The Communities Team will take forward actions within
'communities and place' priority. Along with addressing
perceptions of community safety, the Communities Team will be
developing activity around participatory budgeting,
empowerment and representation. The Youth Learning Team,
that’s transferred to Communities will focus on encouraging
Stephen
Brooks

Page 14

Action Status Progress Due Date Note Owner
young people to participate in the processes and activity.
Working4U will take forward the 'People and Skills' priority and
'Multiply'. This is a significant funding investment and will require
input from the employability teams (youth and adult), welfare
rights (addressing barriers that prevent people from considering
work as an option) and the adult learning teams (providing
access to community-based learning to assist their pathway to
work.
Produce Local Child
Poverty annual report
31-Mar-
2024
This action has been successfully completed. The Annual Child
poverty report has been compiled and distributed for comment.
The final draft is published on West Dunbartonshire Council's
website and will be distributed to the NHS Board and Elected
Members for full endorsement in August. The report highlights
our approach to addressing the drivers of poverty: maximising
income from work; maximising income from benefits; reducing
costs and supporting families through trigger events that could
undermine their well-being. There are key roles in this for the
welfare/benefits advice team (maximising benefit); the
employability teams (youth and adult) (maximising employment
opportunities) and the community learning teams (supporting
families to become more resilient).
Meanwhile, we have compiled applications for Scottish
Government funding for ‘cash first’ approaches, if successful will
provide additional resources to address food insecurity. We have
also submitted a proposal for child poverty accelerator funding.
Through this we will establish a Family Prosperity Group. This
will consist of key partners seeking ways to stimulate joint
initiatives that will address child poverty. Key partners will be
those delivering frontline services such as: employability,
Stephen
Brooks

Page 15

Action Status Progress Due Date Note Owner
benefits, community learning and development, education,
criminal justice and health and social care.
Review and implement
revised service provision
W4U – Welfare support
31-Mar-
2024
This action has been successfully completed. We have a new
Team structure in place, and we have reviewed all sources of
income to ensure we meet funder priorities. We have reviewed
referral routes into the service and implemented a triage system
to ensure we are responding high priorities. We have worked
with OD& Change to review the referral pathway and established
outward referrals to external organisations where appropriate.
In addition, we have agreed a service specification with HSCP.
This will centre on additional welfare/benefit/debt management
support being made available for carers and their families.
Stephen
Brooks
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Failure to respond to child
poverty
The Local Child Poverty Plan sets
out what we will do to respond to
child poverty, failure to respond will
have a significant impact on the
Council’s reputation, more
importantly an opportunity to raise
issues and respond more
effectively to child poverty issues
will be lost.
03-Apr-2024
We have established a
process for developing
the local child poverty
report and will undertake
a self-evaluation to
assess the effectiveness
of our approach. The
self-evaluation will
inform future
developments
Stephen
Brooks

Page 16

Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
The cost-of-living crisis will
lead to a substantial
demand for access to
welfare/debt support
services.
We will monitor the changing
levels of demand and target our
resources to individuals and areas
that are most in need. We will seek
to work with partners to ensure we
receive appropriate referrals who
can benefit from our support. 03-Apr-2024
We have reviewed our
processes for dealing
with referrals and
carrying out
assessments. This
emphasises the need to
respond quickly to those
most in need while
directing those with
lower levels of need to
appropriate partner and
alternative sources of
support.
Stephen
Brooks
4. Our Council
Objective 10. Our workforce is resilient and skilled where digital technology supports service delivery for our residents
Action Status Progress Due Date Note Owner
Develop and implement
wellbeing, employee
engagement, equality and
learning and development
plans to enable capabilities,
improve resilience and
31-Mar-
2024
Across the service we have been focused on a number of key
areas to support this workforce action; this includes:
Review of the management training update on console to
identify previous participation and raise awareness of
opportunities.
Peter Barry

Page 17

Action Status Progress Due Date Note Owner
promotion of a diverse
workforce (workforce action)
Encouraging employees to complete the iLearn equality and
diversity courses and other learning and development
opportunities in this area.
Conducting Be the Best conversations with employees on a
regular basis, using it as an opportunity to review training and
development requirements and general wellbeing as well as
reinforcing awareness of the wellbeing resources that are
available to employees.
Develop and implement
employee life cycle plans in
line with the People First
Strategy to attract and retain
the workforce (workforce
action)
31-Mar-
2024
Across the service we have been focused on a number of key
areas to support this workforce action; this includes:
In Building Services, we actively encourage applicants into non-
traditional roles for craft vacancies including apprenticeships;
we will continue to progress this action in future years as the
service develops strategies to deal with aging workforce and
succession planning. There were a number of craft worker who
completed their apprenticeships in 2023/2024 and others will
also complete in 2024/2025 and future years. We continue to
recruit these trades as vacancies occur and any shortages by
appropriate workforce planning.
In Housing, we have relaunched the housing graduate scheme
and will begin recruitment in 2024/25.
In W4U, we have provided staff with access to training that will
qualify them to deliver SQA accredited modules. These
modules focus on core and basic skills that will assist our
services users to address the barriers they face when
considering work as an option.
Peter Barry

Page 18

Action Status Progress Due Date Note Owner
Implement service review
process including role
design, use of new
technology and new ways of
working to add resilience,
address gaps, and establish
opportunities for efficiencies
(workforce action)
31-Mar-
2024
Significant progress has been made towards this workforce
action, in 2024/25 we will continue to progress the review of
transformation of Housing Development & Homelessness
service area to ensure it meets strategic objectives; and the
introduction of a Housing academy; and complete the service
review for Building Services.
Peter Barry
Develop and implement
learning and development
plans and development
opportunities to improve
capabilities and resilience
within the workforce
(workforce action)
31-Mar-
2024
Across the service we have been focused on a number of key
areas to support this workforce action; this includes:
In W4U, we have established processes to ensure all staff are
aware of emerging opportunities. These opportunities form the
basis of ongoing discussions with staff about CPD. Volunteer
and Staff Personal learning and Development plan for CLD
staff, tutors and volunteers was reinstated post Covid and
includes opportunity for upskilling in a range of topics which
support learners.  As well as mandatory WDC training,
members of staff (and tutors and volunteers) have undertaken
training as follows - Adult Learning National Occupation
Standards Workshop; National Trauma Training Programme
webinar; West Alliance Adult Literacies and ESOL Sharing
Practice; Engagement with Asylum Seekers; Post School
Education, Research and Skills CLD session; SAMH Mental
Health Supporting Others; SQA Assessing and Verifying units
and SQA standardisation meetings.
Peter Barry
Objective 11. Our Council is adaptable and focused on delivering best value for our residents

Page 19

Action Status Progress Due Date Note Owner
Implement improvement
plan for Building services –
year 3
31-Mar-
2024
Progress on this action has been delayed. To date we have
devised a training plan and reviewed job profiles and
structures. Unfortunately, the review in the Councils' Job
Evaluation processes has significantly impacted on the
progress to implement phase 2 of the restructure of Building
Services.
Martin
Feeney
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Failure to
implement
IHMS system
across building
services
The effective implementation of the IHMS
system will delivery efficiency, improve case
tracking, capture customer satisfaction, and
improve service delivery.
27-Mar-
2024
Good progress has
continued to be made in
2022/2023 on Building
Services IHMS
improvement action
plan. Work and
development will
continue in 2023/2024.
Martin
Feeney
Action Status
Cancelled
Delayed
Not on track
In Progress and on track
Completed
Risk Status
Alert
High risk
Warning
OK
Unknown