Page 1

Agenda
Housing and Communities
Committee
Date:  Wednesday, 28 February 2024
___________________________________________________________________
Time:  10:00 
___________________________________________________________________
Format:  Hybrid Meeting
___________________________________________________________________
Contact: Nicola Moorcroft, Committee Officer
Email: nicola.moorcroft@west-dunbarton.gov.uk     
committee.admin@west-dunbarton.gov.uk
Dear Member
Please attend a meeting of the Housing and Communities Committee as detailed
above.
Members will have the option to attend the meeting remotely or in person at the Civic
Space, 16 Church Street, Dumbarton, G82 1QL.
The business is shown on the attached agenda.
Yours faithfully
PETER HESSETT
Chief Executive
Page 1

Page 2

Distribution:-
Councillor Ian Dickson 
Councillor Gurpreet Singh Johal (Chair)
Councillor David McBride
Councillor Jonathan McColl
Councillor Michelle McGinty
Councillor Jim McElhill
Councillor John Millar 
Councillor Lawrence O’Neill
Councillor Lauren Oxley 
Councillor Martin Rooney
Councillor Hazel Sorrell (Vice Chair)
Councillor Sophie Traynor
All other Councillors for information
Chief Executive
Chief Officer – Housing and Employability
Chief Officer – Regulation and Regeneration
Chief Officer – Resources
Date issued: 15 February 2024
Audio Streaming
Audio recordings of the meeting (including the attendance or contribution of any party
participating or making a contribution) will be published on the Council’s website and
the Council’s host’s webcast/audio stream platform.
You should be aware that the Council is a Data Controller under the General Data
Protection Regulation.  Data collected during this audio stream will be retained in
accordance with the Council’s Privacy Notice* and Retention Schedules including,
but not limited to, for the purpose of keeping historical records and making those
records available via the Council’s internet site.
*http://www.west-dunbarton.gov.uk/privacy/privacy-notice/
Page 2

Page 3

HOUSING AND COMMUNITIES COMMITTEE
WEDNESDAY, 28 FEBRUARY 2024
AGENDA
1 STATEMENT BY CHAIR – AUDIO STREAMING
The Chair will be heard in connection with the above.
2 APOLOGIES
3 DECLARATIONS OF INTEREST
Members are invited to declare if they have an interest in any of the items of
business on this agenda and the reasons for such declarations.
4 RECORDING OF VOTES
The Committee is asked to agree that all votes taken during the meeting be
done by roll call vote to ensure an accurate record.
5 OPEN FORUM
The Committee is asked to note that no open forum questions have been
submitted by members of the public.
6 MINUTES OF PREVIOUS MEETING  5 - 10
Submit for approval, as a correct record, the Minutes of Meeting of the
Housing and Communities Committee held on 22 November 2023.
7 SCRUTINY REPORTS
a) POLICE SCRUTINY REPORT 11 - 21
Submit report by the Divisional Commander, Police Scotland providing
Members with an update Quarter 3 on local policing in West
Dunbartonshire.
b/
Page 3

Page 4

b) FIRE AND RESCUE SCRUTINY REPORT To Follow
Submit report by the Local Senior Officer, Scottish Fire and Rescue
Service providing appropriate performance data measured against
priorities in the West Dunbartonshire Local Fire and Rescue Plan. 
8 MORE HOMES WEST DUNBARTONSHIRE – WEST      23 - 35
DUNBARTONSHIRE COUNCIL AFFORDABLE HOUSING
SUPPLY DELIVERY PROGRAMME 
Submit report by the Chief Officer - Housing and Employability providing an
update on progress with West Dunbartonshire’s More Homes Programme
which oversees the delivery of the Council’s new home building programme.
9 WEST DUNBARTONSHIRE BUY BACK SCHEME POLICY 37 - 48
REVIEW
Submit report by the Chief Officer - Housing and Employability providing the
outcomes of the review of the Council’s Buyback Scheme. 
10 WILLOX PARK SHELTERED HOUSING COMPLEX 49 - 68
OPTIONS APPRAISAL
Submit report by the Chief Officer - Housing and Employability providing an 
update on the recent options appraisal consultation exercise at Willox Park.
11 HOUSING REVENUE ACCOUNT BUDGETARY CONTROL 69 - 88
REPORT TO 31 OCTOBER 2023 (PERIOD 7)
Submit report by the Chief Officer - Resources providing an update on the
financial performance to 31 October 2023 (Period 7) of the HRA revenue and
capital budgets for 2023/24.
12 GENERAL FUND HOUSING AND COMMUNITIES 89 - 98
FINANCIAL REPORT 2023/24 AS AT PERIOD 7
(31 OCTOBER 2023)
Submit report by the Chief Officer - Resources providing an update on the
financial performance to 31 October 2023 (Period 7) of General Fund services
under the auspices of the Housing and Communities Committee.
Page 4

Page 5

HOUSING AND COMMUNITIES COMMITTEE
At a Hybrid Meeting of the Housing and Communities Committee held in the Civic
Space, 16 Church Street, Dumbarton on Wednesday, 22 November 2023 at 10.00
a.m.
Present: Councillors Ian Dickson, Gurpreet Singh Johal, David McBride,
Jonathan McColl, James McElhill, Michelle McGinty, Lawrence
O’Neill, Lauren Oxley, Martin Rooney, Hazel Sorrell* and Sophie
Traynor.
*Arrived later in the meeting
Attending: Peter Hessett – Chief Executive; Peter Barry – Chief Officer,
Housing and Employability; John Kerr, Housing Development
and Homelessness Manager; Nicola Pettigrew, Housing
Operations Manager; Alan Young, Housing Asset and
Investment Manager; Martin Feeney, Building Services
Manager; Nigel Ettles, Legal Officer; Nicola Moorcroft and
Ashley MacIntyre, Committee Officers.
Also Attending: Chief Superintendent Lynn Ratcliff and Chief Inspector Ryan
McMurdo, Police Scotland; Group Commander Neil Willerton
and Station Commander Anthony Mallon, Argyll and Bute, East
and West Dunbartonshire, Scottish Fire and Rescue Service.
Apology: An apology for absence was intimated on behalf of Councillor
John Millar.
Councillor Gurpreet Singh Johal in the Chair
STATEMENT BY CHAIR – AUDIO STREAMING
Councillor Singh Johal, Chair, advised that the meeting was being audio streamed
and broadcast live to the internet and would be available for playback.
DECLARATIONS OF INTEREST
It was noted that there were no declarations of interest in any of the items of
business on the agenda.
ITEM 6
Page 5

Page 6

RECORDING OF VOTES 
The Committee agreed that all votes taken during the meeting would be done by roll
call vote to ensure an accurate record. 
OPEN FORUM 
The Committee noted that no open forum questions had been submitted by
members of the public. 
MINUTES OF PREVIOUS MEETING 
The Minutes of the Meeting of the Housing and Communities Committee held on 23
August 2023 (Ordinary) and 25 October 2023 (Special) were submitted and
approved as a correct record. 
SCRUTINY REPORTS 
(A) POLICE SCRUTINY REPORT 
A report was submitted by the Divisional Commander, Police Scotland
providing Members with an update for Quarter 2 (April to September 2023) on
local policing in West Dunbartonshire. 
After discussion and having heard the Chief Superintendent and Chief
Inspector in answer to Members’ questions, the Committee agreed to note the
update provided for Quarter 2. 
(B) FIRE AND RESCUE SCRUTINY REPORT 
A report was submitted by the Local Senior Officer, Scottish Fire and Rescue
Service providing and update on Quarter 2 performance data measured
against priorities in the West Dunbartonshire Local Fire and Rescue Plan. 
After discussion and having heard the Group Commander in answer to
Members’ questions, the Committee agreed to note the update provided for
Quarter 2. 
HOUSING AND EMPLOYABILITY DELIVERY PLAN 2023/24 MID-YEAR REPORT 
A report was submitted by the Chief Officer – Housing and Employability, providing
the Housing and Employability Delivery Plan for 2023/24 mid-year progress report. 
Page 6

Page 7

After discussion and having heard the Chief Officer – Housing and Employability, the
Housing Development and Homelessness Manager, the Housing Asset and
Investment Manager and the Building Services Manager in further explanation and in
answer to Members’ questions, the Committee agreed to note the progress
achieved. 
MORE HOMES WEST DUNBARTONSHIRE - WEST DUNBARTONSHIRE
COUNCIL AFFORDABLE HOUSING SUPPLY DELIVERY PROGRAMME 
A report was submitted by the Chief Officer – Housing and Employability providing
an update on progress with West Dunbartonshire’s More Homes Programme, which
oversees the delivery of the Council’s new home building programme. 
After discussion and having heard the Chief Officer – Housing and Employability and
the Housing Development and Homelessness Manager in further explanation and in
answer to Members’ questions, the Committee agreed to note the content of the
report and the progress made to date in the delivery of the Council’s More Homes
West Dunbartonshire approach. 
SCOTTISH SOCIAL HOUSING CHARTER/REGULATION OF SOCIAL HOUSING
IN SCOTLAND, UPDATE REPORT 
A report was submitted by the Chief Officer – Housing and Employability providing a
mid-year update in terms of how the Council is performing against the Scottish
Social Housing Charter indicators and an update into how the Council is meeting the
requirements of the Scottish Housing Regulator’s Regulatory Framework. 
After discussion and having heard the Chief Officer – Housing and Employability in
further explanation, the Committee agreed:- 
(1) to note the contents of the report recognising the mid-year progress in terms
of meeting the Outcomes of the Scottish Social Housing Charter; 
(2) to note that, following the approval of the Annual Assurance Statement by the
Committee on 25 October 2023, this has now been submitted to the Scottish
Housing Regulator as per the regulatory requirement; 
(3) to note that the Annual Charter Performance Report has now been published
and a summary would be provided to all tenants with the winter edition of the
Housing News; and 
(4) to note that a full annual progress report on the Scottish Social Housing
Charter will be submitted to the August 2024 meeting of the Housing and
Communities Committee, this would include the Annual Assurance Statement. 
Page 7

Page 8

LOCAL HOUSING STRATEGY 2022-27 ANNUAL PROGRESS REPORT 
A report was submitted by the Chief Officer – Housing and Employability providing a
progress report on the West Dunbartonshire Local Housing Strategy 2022 –
2027. 
After discussion and having heard the Chief Officer – Housing and Employability and
the Development and Homelessness Manager in further explanation and in answer
to Members’ questions, the Committee agreed the progress made in meeting the
aims and objectives of The More Homes Better Homes West Dunbartonshire Local
Housing Strategy 2022 - 2027 and notes the contents of the Local Housing Strategy
Progress Report – October 2023. 
STRATEGIC HOUSING INVESTMENT PLAN 2024/25 - 2028/29 
A report was submitted by the Chief Officer – Housing and Employability seeking
approval for the More Homes West Dunbartonshire Strategic Housing Investment
Plan (SHIP) for 2024/25 – 2028/29 which requires to be submitted to the Scottish
Government. 
After discussion and having heard the Chief Officer – Housing and Employability and
the Housing Development and Homelessness Manager in further explanation and in
answer to Members’ questions, the Committee agreed:- 
(1) the draft SHIP 2024/25 - 2028/29 as appended to the report, designed to
continue the delivery of an ambitious programme of new affordable homes in
compliance with the West Dunbartonshire Local Housing Strategy 2022 -2027
(Approved November 2021); and 
(2) to delegate authority to the Chief Officer  – Housing and Employability to
implement the investment plan in partnership with relevant stakeholders. 
REVIEW OF WEST DUNBARTONSHIRE AFFORDABLE HOUSING DESIGN
STANDARD 
A report was submitted by the Chief Officer – Housing and Employability seeking
approval for a revision to the current West Dunbartonshire Design Standard for
Housing Supported by the Affordable Housing Supply Programme, which has been
in place since April 2019, to improve the quality of new affordable homes being built
in West Dunbartonshire. 
After discussion and having heard the Chief Officer – Housing and Employability in
further explanation and in answer to Members’ questions, the Committee agreed:- 
(1) to note the content of the report which outlined the progress in developing the
revised Design Standard; 
Page 8

Page 9

(2) in principle the revised West Dunbartonshire Design Standard 2023 as
appended to the report; 
(3) that the new Standard be applied to any new projects receiving funding from
the Affordable Housing Supply Programme from 1 April 2024; and 
(4) to delegate authority to the More Homes Board to consider any proposed
variations to the Design Standard. 
HOME AT THE HEART 2019-24 - WEST DUNBARTONSHIRE’S RAPID RE-
HOUSING TRANSITION PLAN UPDATE AND NEW APPROACHES TO
HOMELESSNESS PROGRESS REPORT 
A report was submitted by the Chief Officer – Housing and Employability providing
an update on “Home at the Heart” – West Dunbartonshire’s Rapid Re-housing
Transition Plan (RRTP) for the period 2019-24 and new approaches to
homelessness. 
After discussion and having heard the Chief Officer – Housing and Employability, the
Housing Development and Homelessness Manger and the Housing Operations
Manager, in further explanation and in answer to Members’ questions, the
Committee agreed:- 
(1) to note the progress and challenges made in the first four years of “Home at
the Heart”, which will informed a report to the Scottish Government at the end
of August 2023 and note the main objectives for Year 5 in paragraphs 4.16 -
4.26 of the report; 
(2) to note that the Council’s housing allocation letting target for homeless
households is 69% for 2023/24 as set out in paragraph 4.20 of the report and
note the Chief Officer – Housing and Employability, will keep the target under
close review based on current modelling projections; 
(3) to note the continued uncertainty around future funding and specifically the
risk to the Housing First approach; 
(4) to note and approve that the Scottish Government funding of £251,146 was
awarded for 2023/24 for the specific delivery of the West Dunbartonshire
Rapid Rehousing Transition Plan; 
(5) to approve the new Monitoring Template of West Dunbartonshire Rapid
Rehousing Transition Plan including spend, attached as Appendix 1 to the
report; and 
(6) to note impact of legislative changes around Local Connection. 
Page 9

Page 10

HOUSING REVENUE ACCOUNT BUDGET CONTROL REPORT 2023/24 TO 31
AUGUST (PERIOD 5) 
A report was submitted by the Chief Officer – Resources providing an update on the
financial performance to 31 August 2023 (Period 5) of the HRA revenue and capital
budgets for 2023/24. 
Having heard the Chief Officer – Housing and Employability, in further explanation,
the Committee agreed:- 
(1) to note the revenue analysis shows projected adverse variances of £2.309m;
and 
(2) to note the net projected annual position in relation to the capital plan
highlighted an in-year adverse variance of £63.776m (51.1%) which is made
up of re-profiling of £64.176m (51.4%) and overspend of £0.401m (0.3%) as
detailed in Appendix 4 of the report. 
It should be noted that these are the financial projections as at Period 5 which were
reported to Council on 25 October 2023. Since they were produced, the Chief Officer
for Housing and Employability, in conjunction with the Council’s Chief Officer for
Resources has progressed work to identify options to reduce the projected revenue
overspend. This work is still being progressed however, current indications are that
there will be viable options to reduce the in year overspend to the extent that no
contribution from the General Fund will be required. 
GENERAL FUND HOUSING AND COMMUNITIES FINANCIAL REPORT 2023/24
PERIOD 5 (31 AUGUST 2023) 
A report was submitted by the Chief Officer – Resources providing an update on the
financial performance to 31 August 2023 (Period 5) of General Fund services under
the auspices of the Housing and Communities Committee. 
Having heard the Chief Officer – Housing and Employability in further explanation,
the Committee agreed:- 
(1)  to note the contents of the report which showed the revenue budget forecast
to overspend against budget by £0.070m(2.1%) at the year end. 
(2) to note the net projected annual position in relation to relevant capital projects
which is showed no projected variance; and 
(3) to note the progress on efficiencies incorporated into budgets for 2023/24. 
The meeting closed at 11.48 a.m.
Page 10

Page 11

OFFICIAL
OFFICIAL
West Dunbartonshire
Performance Summary Report
Reporting Period: Q3 – April to December 2023
Total Crime 765 Crimes
Incidents Overall Dishonesty Domestic Abuse
Incidents
+12.2 +37.5 +7.2%
+12.3 +5.1% +75%*
Road Deaths and
Serious Injuries
+3.6%*
Sexual Crime
+2504*PYTD, - +95*PYTD, +164*5YR +409*PYTD, +347*5YR +65*PYTD, -20*5YR
+17*PYTD, +25*5YR AVG +7*PYTD, -4*5YR AVG +12*on PYTD +105*PYTD
Violent Crime
Missing Counter Terrorism
+1*PYTD
+0.2%*
+17*PYTD, +1*5YR
Common Assault
+15.5%
Housebreaking
Disorder 
Complaints
The National Terrorism Threat level is
SUBSTANTIAL
This means that an attack is likely. 
*PYTD = Previous Year to Date
*5YR = 5 year average
+10.8%
+13.3%
ITEM 7a
Page 11

Page 12

OFFICIAL
SECTION PAGE NUMBER 
Introduction 2 
Executive Summary 3
Demand Analysis 4
Acquisitive Crime 5
Public Protection 6
Road Safety 7
Serious Organised Crime 8
Violence 9
Antisocial Behaviour 10
Public Confidence - Complaints & Allegations 11
Introduction
I am pleased to present this performance summary report to the West Dunbartonshire Housing
Committee for its information and consideration. The Reporting Period for this report is cumulative for
Quarters 1, 2 & 3 of 2023, with figures being shown from 1st April 2023 through to 31st December 2023.
Please note that all data included in this report are management information and not official statistics.
All data are sourced from Police Scotland internal systems and are correct as of date of publication.
Unless stated otherwise numerical comparisons are against the previous year to date and the previous
five year average for the same data period specified.
Crimes and offences are grouped under recognised categories for statistical purposes.  The Scottish
Government defines these categories, as follows: 
Group 1 - Non Sexual Crimes of Violence Group 6 - Miscellaneous Offences
Group 2 - Sexual Crimes Group 7 - Offences relating to motor vehicles
Group 3 - Crimes of Dishonesty PYTD  - Previous Year to Date
Group 4 - Fire Raising, Malicious Mischief CYTD - Current Year to Date
Group 5 - Other (pro activity) Crimes
Page 12

Page 13

OFFICIAL
PRIORITY
AREA EXECUTIVE SUMMARY
Acquisitive
Crime
At the end of Quarter 3, acquisitive crime shows an increase of 409 crimes
compared to the same period last year. This is largely due to notable increases
in shoplifting, vehicle crime and common theft. 
Public
Protection
Group 2 sexual crimes have seen an increase of 5.1% with 143 crimes recorded
compared to 136 at the end of Quarter 3 last year. The number of Rape crimes
recorded has risen slightly from 24 to 28.  Sexual assaults have also seen a slight
increase from 43 to 50 (+7) year on year.  
Road Safety
& Road Crime
The number of fatal road traffic collisions within West Dunbartonshire has
reduced with 1 fatality recorded during the current reporting period compared to
2 in the same period last year. 
Road traffic collisions involving serious injuries have increased from 14 to 27,
while collisions involving slight injuries have seen a reduction from 30 to 22.
Serious
Organised
Crime
At the end of Quarter 3, drugs supply crimes had increased from 53 to 70, while
possession charges have seen a reduction from 470 to 449.
Across Argyll & West Dunbartonshire 39 persons linked to serious and organised
crime (SAOC) have been arrested and £496,551 seized under the Proceeds of
Crime Act 2002 (POCA).
Violence &
ASB
At the end of Quarter 3, Group 1 crimes of violence have increased with 155
crimes compared to 138 the previous year to date. Anti-social behaviour (ASB)
related crimes have also seen increase from 1913 to 1969 (+2.9%).
1. Acquisitive Crime
2. Public Protection
3. Road Safety & Road Crime
4. Serious Organised Crime
5. Violence & Anti-social behaviour
WEST DUNBARTONSHIRE POLICING PRIORITIES 2023-2026
Page 13

Page 14

OFFICIAL
CRIME PYTD CYTD INCIDENTS PYTD CYTD
Total Crimes &
Offences 7107 7872 Total number of 
incidents 18,884 21,388
DEMAND ANALYSIS - * PYTD - PREVIOUS YEAR TO DATE CYTD - CURRENT YEAR TO DATE
The total volume of crimes and offences recorded within West Dunbartonshire has increased by
10.8% from the previous year and is currently 9.4% above the previous 5 year average. All crime
groups have seen a notable rise in figures from the PYTD with acquisitive crimes experiencing
highest increase (+37.5%) followed by Police proactive crimes such as weapon carrying and drug
offences (+13.9%). Acquisitive crimes have also seen an increase of 30.1% on the previous 5
year average.  
Despite the overall increase in crime levels Group 2 sexual crimes and Miscellaneous offences
both remain below the 5 year average. 
Page 14

Page 15

OFFICIAL
OFFICIAL   
ACQUISITIVE CRIME
Shoplifting crimes have seen the highest increase (335 to 533) and remain above the
previous 5 year average. Year to date there have been 91 more shoplifting crimes that
have been detected. This is a national picture which may be increasing as a result of
the cost of living.
At the end of Quarter 3, domestic housebreakings have increased by 15 year to date. 
Housebreakings at commercial properties have seen a reduction and are down by 9
crimes. 
There has been an increase in motor vehicle crimes with 147 recorded compared to 74
last year. Thefts from motor vehicles have the highest increase (35 to 99). Theft of
motor vehicles has also risen from 39 to 48. Much of the increase in these thefts are
attributed to one repeat offender who has subsequently been arrested and remanded
in custody. The detection rate for vehicle crimes has increased from 28.4% to 59.2%.
Common thefts have increased from 319 to 411, while fraud crimes have seen a slight
reduction from 176 to 163. Both figures remain above the 5 year average. 
To address the increase in domestic housebreakings, officers have shared material from our “After Dark”
campaign on social media assisted by letter drops by our Police Scotland Youth Volunteers (PSYV). PSYV handed
out over 2000 leaflets in our local communities which relate to protecting homes and property.
Officers are engaging with victims of theft by housebreaking and providing security advice while also providing
contact details for Secure by Design where residents can access approved security advice, systems and
equipment.
The Preventions & Partnerships team have been working with retailers within Clydebank Shopping Centre
providing advice on stock security and how to better prevent being the victims of theft. This work has also
included promoting a system called ‘Retail Watch’ which is an email based alert facility that warns retailers of
specific risks such as an organised team of shoplifters operating in a particular vicinity.
We continue to provide bicycle marking kits which are also available from every Divisional Police Office front
desk, the uptake is very positive and is improving bike security.
Community Police Officers, during the most recent cold spell, were out early to identify and warn numerous
persons who had left a vehicle running unattended to defrost in their drives. Easy pickings for opportunist
thieves. Social media was utilised before and after the operation to highlight how common this practice is and
how easy it could be to take a vehicle in such circumstances. 37 vehicles identified in a short period of time and
all owners warned and given safety advice.        
Page 15

Page 16

OFFICIAL
OFFICIAL 
We fully supported the Violence Against Women & Girls (VAWG) 16 days of action campaign raising awareness of
the issues faced and encouraging reporting of same. We promoted positive messaging from male role models from
SFRS and Dumbarton FC. Youth Engagement Officers are delivering inputs at Community Hubs addressing internet
safety. Inputs were targeted more towards parents looking at their responsibilities and what securities can be put
in place to best protect the children.       
A muti-agency project has commenced involving The National Society for the Prevention of Cruelty to Children
(NSPCC) and Y Sort-IT where NSPCC will deliver inputs to youth groups specifically targeting online sexualised
conduct, misogyny, and the dangers of inappropriate online conduct. Inputs will include how to be safe, how to
report inappropriate content or conduct, encourage users to speak to someone if they are encountering issues
online of any form and to better understand what acceptable behaviour is. The inputs will address how the effects
of online abuse or pressure can manifest in an individual. Work is ongoing within both the child and adult care
sectors to further address missing persons and how best to firstly prevent such a scenario but also how to better
deal with certain missing person reports to maximise the safety of those within the care system.  
At the end of Quarter 3, Group 2 crimes show an increase of 5.1% compared to the same period last
year. Rape crimes have risen from 24 to 28, while sexual assaults have also increased by 7 crimes.
The number of domestic abuse incidents reported to the police has risen by 7.2% however the total
number of domestic related crimes recorded has reduced by 2.1% YTD, in accordance with a slight
reduction in the percentage of incidents that have resulted in a crime being recorded (-2.3%).
Approximately 86% of rape crimes occurred in a private place and 86% were committed by persons
known to the victim. Similarly, around 77% of sexual assaults also occurred in a private place with
90% committed by persons known to the victim. Approximately half of all sexual assaults during this
reporting period relate to non-recent reports. The detection rate for rape crime has increased by
28.6% and is currently 78.6%, while the detection rate for sexual assaults has reduced from 95.3%
to 60% year on year.
Crimes relating to indecent images/communications have remained fairly consistent compared to last
year with almost 25% being committed by persons known to the victim.
A total of 235 missing person reports have been recorded by the end of Quarter 3, which is a reduction
from 251 last year. Adult missing person reports have increased from 84 to 101, while reports relating
to children have seen a decrease from 125 to 98 (-27) year on year. 
PUBLIC PROTECTION
Page 16

Page 17

OFFICIAL 
Across the reporting period, there has been 1 road death in West Dunbartonshire.  Serious injuries
have almost doubled from 14 to 27 while slight injuries have reduced slightly.
Offences relating to motor vehicles have increased slightly by 1.6% (an increase of 35 offences)
compared to the previous year. Much of the increase is due to notable rises in insurance offences
(+71), neglecting traffic directions (+34) and driving without a licence (+28), which have all been
proactively detected. 
Road Traffic Casualties 2022/23 2023/24
Number of persons killed on our roads 2 1
Number of persons seriously injured 14 27
Number of persons slightly injured 30 22
Number of children seriously injured 0 0 
The Road Policing Unit within West Dunbartonshire remains committed to detecting offences within the Key
Performance Indicators of the fatal 5, careless/dangerous driving, speed, mobile phones, seatbelts and
drink/drug driving. Of particular note, the detection of disqualified drivers has doubled compared with the five-
year average in West Dunbartonshire, an indication of the proactive work carried out by the unit.  In the final
quarter of the year there are national campaigns targeting seatbelts, mobile phone use and speeding along with
Vulnerable Road User’s focus at the end of the period.        
The Road Policing Unit will carry out activities locally with particular focus on these behaviours during the
national campaign.      
Police Scotland’s annual festive drink and drug driving campaign took place from 1 December 2023 to 2 January
2024. The total number of roadside tests carried out by police officers increased by 21 per cent compared to
the previous year. There were 3,219 breath tests (2,568 in 2022) and 481 drug wipes (481 in 2022). Scotland-
wide, detected offences increased, from 722 in 2022 to 831 in 2023.        
The Preventions & Partnerships Unit are currently arranging a series of road safety events to take place across
West Dunbartonshire. The events will include input and advice from Police Scotland and also the opportunity
for drivers to take a drive with a member of the Institute of Advanced Motorists (IAM) sitting alongside who will
provide the driver with advice and guidance relating to the driver’s driving standards. It is part of the ‘I Am Road
Smart’ campaign which has proved to be very effective across the country.          
ROAD SAFETY AND ROAD CRIME
Page 17

Page 18

OFFICIAL
OFFICIAL
Across Argyll & West Dunbartonshire, 39 persons linked to serious and organised crime have been
arrested and £496,551 has been seized under POCA since 1st April 2023.
At the end of Quarter 3, drug supply charges have increased from 53 to 70 crimes, but remains
below the previous 5 year average (84.4). Drug possession charges have seen a slight reduction of
4.5% from 470 to 449. 
SERIOUS & ORGANISED CRIME
Drug supply statistics evidence the work of both the Dumbarton based Crime Team & the Divisional Community
Policing Teams who have been targeting those involved in the supply of controlled drugs, focussed, planned
operations disrupting criminal activities and removing illegal and harmful drugs from the communities.       
Officers seized a commercial scale cannabis cultivation in Dumbarton, removing and destroying a large quantity
of plants and growing equipment in the process. Officers are following a positive line of enquiry to identify those
responsible.       
Thanks to our partners from West Dunbartonshire Health & Social Care Partnership (HSCP) our S3 year groups
across West Dunbartonshire had the opportunity to learn and talk about choices, risks and consequences of
talking MDMA (Ecstasy). The Daniel Spargo Mabbs Foundation performed live theatre productions across all
secondary schools of ‘I Love You Mum I Promise I Won’t Die’ which is based on a true story of schoolboy Daniel
who took MDMA at a party and consequently died. The production is followed by a workshop to bring out the
main learning points and to encourage discussion. We know this will be very thought provoking. We also hope it
will positively influence future decisions.      
Town Centre officers carried out some partnership work with Trading Standards. 1 person was reported by
Trading Standards for licensing and trademark offences. Such partnership working has a positive impact on
other local retailers.        
Police Officers also participated in a successful partnership operation working with The Driver & Vehicle
Licensing Agency (DVLA) targeting premises trading in vehicle license plates (which can subsequently be used in
the commission of crime). 8 persons/companies charged under Vehicle Crime Act 2001. 
Page 18

Page 19

OFFICIAL
OFFICIAL 
VIOLENCE
After 27 years, the killers of 14-year-old Caroline Glachan have been convicted. Caroline was violently attacked
and murdered in August 1996. Officers from the MITs worked diligently to piece together what happened.
Officers re-examined and researched all documentation from the original inquiry. More than 200 statements
were taken from people who had not previously provided a statement to police. 
The Preventions & Partnerships Team have had an initial meeting with the team from the West Dunbartonshire
Harm Reduction Mobile Service. We are looking at how to best engage with service users to offer personal safety
advice without negatively impacting on the unit’s service. We are also exploring avenues to provide advice on
domestic violence and also take any opportunity to make disclosures under the Disclosure Scheme for Domestic
Abuse Scotland to better protect persons at risk of violence in a domestic setting.  
Addressing the increase in robberies, a dedicated team was assembled. Through intelligence and reviewing of
crimes they targeted specific areas and individuals. Very positive results with 3 x offensive weapon & multiple
drug offences detected, 4 people arrested breaching bail. Results show criminal activity impacted upon greatly.
Some violent crime types have increased across West Dunbartonshire resulting in an overall
increase of 12.3% from 138 to 155 crimes.  58% of all crimes took place in a private place, and
44% of those in a public space were committed by persons known to the victim. Whilst we
continue to prioritise violence prevention strategies, sporadic violence taking place behind doors
or between individuals known to each other is challenging to prevent.  
Threats and extortion offences show the highest increase (+18), however this is due to a rise in
“sextortion” offences with around 90% being committed online involving threats to post indecent
images shared between victims and suspects. Many of these offences are committed out with the
country reducing the investigative opportunities available. 
There has been an increase in attempted murders (from 0 to 5) and robberies (from 18 to 27)
compared to last year. Three of five attempted murders occurred within public space and two in
private places. It is important to note that all attempted murders were committed by persons
known to the victim (1 domestic related). The 5 attempted murders have been detected.
Sixteen of the 27 robberies occurred in a public place (12 on a public street, 3 at commercial
stores and 1 on public transport). The other 11 crimes occurred in private places. Sixteen
robberies were committed by strangers and 11 were committed by persons known to the victim.
The detection rate for robbery has reduced from 72.2% to 48%. 
Page 19

Page 20

OFFICIAL 
Across the recording period the number of ASB related calls to Police Scotland has increased
by 4.7%. Group 6 crimes, which include ASB related offences have also seen a slight increase
of 2.9% from 1913 to 1969. Common assaults have increased by 12.2% from 780 to 875. 
Approximately 54% of crimes occurred in public spaces and 46% in private spaces. In 44% of
public space crimes, offenders were known to victims. Much of the increase is due to a rise in
domestic assaults (+24), youth fighting (+18) and neighbour disputes (+10). The detection rate
for common assaults overall has reduced by 7.8% from 71.2 to 63.3% (1 fewer crime). 
ANTI-SOCIAL BEHAVIOUR 
We pride ourselves in our close partnerships, and in preparation for bonfire weekend, our officers worked
closely with colleagues from Scottish Fire & Rescue Service and West Dunbartonshire Council ASB and
Housing teams and Trading Standards to promote safety and prevention. 
Our Youth Engagement Officers carried out joint inputs in local schools, and Community Policing Teams
visited premises selling fireworks to ensure they are complying with strict guidelines. We worked with our
Green Space colleagues at West Dunbartonshire Council and our communities responding to information
about possible stockpiles of rubbish or wood being gathered which could be used to create unsafe fires
removing same.
We continue to engage daily with our partners at West Dunbartonshire Council pro-actively disclosing incidents
of anti-social behaviour (ASB) to best address recurring issues. This disclosure protocol can also assist in specific
tenant issues and highlights repeat locations.
From this continual assessment and review of ASB we adjust our policing plan through extra attention patrols,
action plans, individual warnings to problematic tenants. It identifies ‘hot-spots’ that are added to the patrol
matrix for scheduled recorded police activity and monitoring.  
Community Police Teams are tasked to concentrate their efforts on the areas and issues causing the greatest
disruption and upset within the communities. Clydebank Shopping Centre, Chalmers Street currently subject of
increased police and partner focus. 
Moving forward, Operation Balaton already being planned to combat any rise in ASB during the better weather.
Page 20

Page 21

OFFICIAL
OFFICIAL
PUBLIC CONFIDENCE: COMPLAINTS & USER SATISFACTION
Overall satisfaction with Police Scotland
User Satisfaction results show that locally, public confidence levels remain high with overall
satisfaction levels at 70.9%, which is in line with the position in 2022/23. 
At the end of Quarter 3, 71 complaints against the police had been recorded within West
Dunbartonshire which is a marginal increase from 68 last year. The number of allegations against
officers has reduced year on year from 134 to 125. 
999 Call Data – December 2023
Police Scotland were in the top five UK Forces for Total Received 999 calls for the month of December 2023, with
85.6% of calls answered within 10 secs.
Police Scotland is currently managing a marked increase in 999 emergency calls and this unfortunately, does
affect wait times for 101 calls. Calendar year to date when compared with the previous year we have experienced
a 14% increase. 
Control room staff are now triaging calls relating to mental health matters and when appropriate, and when
circumstances allow, signposting callers directly to the most appropriate NHS service negating the need to send a
police resource. This is reducing the demand on front line police resources while also allowing quicker access to
the most appropriate professional to those in need.   
The table shows almost 71% of those asked
were either satisfied or very satisfied with
the service they received from Police
Scotland. 20.36% of respondents were
dissatisfied with the service they received. 
We are continuing to ensure all officers are
engaging in all available training and
receiving the maximum level of supervision
and guidance to improve these figures and
ensure we are providing the maximum
service across the area in all aspects of
policing. We have commenced a review and
training programme to improve the quality of
reports being submitted to COPFS to
improve the outcome for victims.     
Total of
501
responses
Page 21

Page 22

Page 22

Page 23

WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer, Housing and Employability
Housing and Communities Committee: 28 February 2024
__________________________________________________________________
Subject: More Homes West Dunbartonshire – West Dunbartonshire Council
Affordable Housing Supply Delivery Programme 
1. Purpose
1.1  This purpose of this report is to provide the Housing and Communities
Committee an update on progress with West Dunbartonshire’s More Homes
Programme which oversees the delivery of the Council’s new home building
programme.
2. Recommendations
2.1 It is recommended that the Housing and Communities Committee:
(i) Note the content of the report and the progress made to date in the
delivery of the Council’s More Homes West Dunbartonshire approach;
(ii) Note the temporary reduction in the number of homes to be delivered
within the Bonhill Gap Site development project, and
(iii) Authorise the Chief Officer, Housing and Employability to establish two
Housing Revenue Account subsidiary organisations in partnership with
Scottish Futures Trust Investment (SFTi) and bring back proposed
alternative tenure projects to the Committee for authority permission to
proceed.
3. Background
3.1 In West Dunbartonshire the Affordable Housing Supply Programme (AHSP) is
delivered through a More Homes West Dunbartonshire strategic approach
which has successfully delivered over 1000 new affordable homes in West
Dunbartonshire to date and includes the Council’s own ambitious New House
Building Programme.
3.2 The Council’s last practical completion took place at the Queens Quay
development in September 2022 delivering 29 new Council homes in a key
regeneration area as part of a wider development which has delivered 146
new social rented homes.  The homes were the first residential properties to
be heated from the Council’s Queens Quay District Heating Network. This
development has been recognised at recent national housing sector awards
winning the following: -
ITEM 8
Page 23

Page 24

• Best Residential Regeneration Project – Herald Property Awards
• Inside Housing Best Residential Development (Scotland)
3.3 These 29 new homes, are in addition to the completion of the Council’s first
fully dementia designed development at Creveul Court, Alexandria and other
exemplar developments in Haldane, Aitkenbar, Bellmsyre, Dumbarton
Harbour and St Andrews, Clydebank.  The Council have now completed 12
new build developments since 2013 and are the largest developer of social
homes in West Dunbartonshire delivering 496 new homes and 122
acquisitions through our buyback scheme to date as outlined in Table 1
below.  The 500th new build home in the More Homes West Dunbartonshire
delivery programme will be delivered in late Summer 2024 at our Clydebank
East development:
Table 1:  Completed Council New Build and Acquisitions
Project No. of
Units
Completion
Date
Granville Street (Phase 1), Clydebank 24 July 2013
Miller Road, Alexandria 15 October 2013
Granville Street (Phase 2), Clydebank 9 February 2014
Central Bellsmyre, Dumbarton 36 December 2014
Hillstreet Square, Dumbarton 37 August 2015
Second Avenue, Clydebank 40 April 2018
Creveul Court, Alexandria 22 April 2021
Aitkenbar Primary School 55 July2021
Haldane Primary School 58 August 2021
St Andrews, Clydebank 126 October 2021
Dumbarton Harbour, Dumbarton 45 December 2021
Queens Quay, Site B, Clydebank 29 August 2022
Buyback Acquisitions 122 Ongoing
Totals 618
3.4   The Strategic Housing Investment Plan (SHIP) 2024-2029, outlining West 
Dunbartonshire’s Affordable Housing Supply Programme through the More
Homes West Dunbartonshire approach was approved by the Housing and
Communities Committee in November 2023. The SHIP outline plans to meet
the Council Administration’s aim of delivering 2500 new affordable and social
rented homes over the next 10 years. 
4. Main Issues
More Homes West Dunbartonshire - Delivery Programme
4.1 Building new affordable homes has an important role to play in revitalising
local economies and assisting with post-pandemic and economic recovery
plans, negating the impacts of the current cost of living crisis and combatting
poverty including child poverty.  It is also clear that the need for affordable
homes has and will increase in the current ongoing economic environment. 
4.2 Our More Homes West Dunbartonshire approach is an ambitious plan that
aims to continue the positive momentum of the delivery of much needed
Page 24

Page 25

Council homes in West Dunbartonshire and will significantly assist the
Council’s aim to deliver 2500 new social and affordable homes by 2032.
4.3 As the biggest affordable housing developer in West Dunbartonshire, the
Council has identified several future development sites for new council homes
to address existing and new housing need. The design of these homes will
further develop, improve and exceed current best practice, providing
sustainable homes using innovative technology and delivering on our low
carbon ambitions including passivhaus and other net zero carbon
opportunities.
4.4 The Strategic Housing Investment Plan and HRA Capital Plan outlined the
plans the Council have for meeting their new build ambitions.  Some of the
initial plans were and continue to be impacted as a result of global issues
revised new build targets for the Council are outlined below:
Table 2: Council New Build Programme
Site/Developer Number of
Units
Number of
Specialist
Provision
Est Site
Start
Est Completion
Date
Clydebank
East,
Clydebank
88 9
On Site
January
2023
Spring 2025
(First handovers
– August 2024)
Pappert,
Bonhill
Alexandria
26 3
February
2024
Spring 2025
Willox Park 17 17 Summer
24
Autumn 2025
Bonhill Gap
Sites* 29 4 Autumn 24 Winter 2025
Mount
Pleasant
19 19 Spring 24 Spring 2025
Queens Quay
Site C
100 10 TBC TBC
Clydebank
Health Centre*
38 22 Spring 25 Spring 2026
Bank Street,
Alexandria
22 22 Autumn 24 Autumn 2025
Dennystoun
Forge
20 20 TBC  TBC
Clydebank
Gap Sites*
(Gilmour
Avenue)
50 10 Summer
24
Summer 2025
Silverton
Regeneration
tbc Tbc tbc Tbc
Page 25

Page 26

*Current Planning figures
4.5 Updates for each site are noted below:
Clydebank East:
This development will deliver 88 new homes and has been designed to meet
the housing need within the wider West Dunbartonshire area. The table below
shows the housing mix:
House Type Sustainability Standard Number of New
Homes
Wheelchair Bungalow
3bed/4person
Net Zero 3
House 3bed/5person Net Zero 15
House 4 bed/7person Net Zero 12
House 5 bed/8 person Net Zero 8
Cottage Flat 1 bed/2 person Net Zero 4
Cottage Flat 2 bed/3 person Net Zero 4
Flat 1 bed/2person Net Zero 16
Flat 2 bed/4 person Net Zero 24
Wheelchair Flat 1 bed/2person Net Zero 2
Works commenced on this development in January 2023 and the first homes
are scheduled to be handed over in August 2024. 
All houses are designed to the Housing for Various Needs Standard (HfVN).
There will be 9 fully Wheelchair (WCH) accessible properties.  The 4 and 5
bedroom homes will all have ground floor double bedrooms.  
The development at Clydebank East will see the completion of a major
housing led regeneration of a key priority regeneration area identified in the
Local Housing Strategy and will be the first fully zero carbon housing
development in West Dunbartonshire and marks a significant milestone in our
transition to net zero new homes approved at the August 2022 meeting of the
Housing and Communities Committee.  Plans are being developed to mark
the significance of the net zero element of the development and the
development will see the 600th new home delivered through the More Homes
West Dunbartonshire approach.
We are still currently engaged with the Scottish Government in terms of
finalising the grant award, as reported previously we have sought above
benchmark grant and our submission continues to be assessed by the
Scottish Government’s technical team. Our request is proportionate based on
the high levels of remediation costs but in terms of context our ask is
Buyback
Scheme (60
per year)
300 36 2023/24 2027/28
709 units 172 units
Page 26

Page 27

comparable with the grant awards made to the 2 housing association who
partnered the Council in the delivery of the new housing at Queens Quay.
Pappert, Bonhill
Following the review of the design proposals for the Pappert development the
housing mix is as follows: -
House Type Sustainability Standard Number of New
Homes
House 3bed/5 person Passivhaus 6
House 3bed/5 person Net Zero 6
House 4bed/6person Net Zero 4
House 4bed/7person Net Zero 1
Flat 2bed/3person w/c Net Zero 3
Flat 1 bed/2person Net Zero 6
Planning permission for this development was granted at the Planning
Committee of 20th September 2023, enabling a site start in February 2024 if
planning conditions are discharged. These are currently being finalised and
are working towards the start date of 26th February 2024 to begin the 53-week
contract. 
Willox Park, Doveholm, Dumbarton
The development of seventeen new homes to be delivered at the former care
home site continues within the design phase and planning has been
submitted by Housing Officers. A decision is expected, via delegated
authority, at the end of February. 
Tender documentation is being prepared and will be ready at the end of
January. This will be advertised via the SPA framework and the tender return
period will be 10 weeks. We are working towards the appointment of a
contractor at the June 2024 tendering committee. 
The net zero heat strategy will be delivered by ground source heat pump, as it
was felt that this solution to be preferable than an air source heat pump for
each home.  The development will also utilise PV (Photovoltaic) panels and a
MVHR (Mechanical Ventilation with Heat Recovery) system.
There has been positive dialogue in terms of the current plans with both the
Willox Park residents and planning officers.  Ongoing engagement will be
maintained with the current Willox Park residents throughout the delivery
process and the development will be tied to the wider regeneration plans for
the Willox Park Sheltered Housing Complex.
Bonhill Gap Site Strategy
The pre-planning application process has commenced on the development of
the 2/3 separate gap sites which are contained within this wider development. 
Page 27

Page 28

We have now procured engineering consultants as we move closer to a full
planning application. We are hoping to submit planning at the end of April. 
We have temporarily removed the O’Hare gap site (5x 3-bedroom terraced
homes) at the moment due to the exceptionally high projected development
costs for developing in this area. We are currently exploring a design
alternative which will deliver high quality homes within a prudent cost
envelope. 
We have altered some of the initial design plans to incorporate two adaptable
6/7 bed homes within the development to meet identified housing need for
larger families who are experiencing overcrowding. 
Bank Street, Alexandria
The Council is currently developing a proposal for 22 sheltered/amenity
housing units in partnership with the HSCP. This will include an options
appraisal in terms of the existing provision within the local area.
Engineering works will be starting in January. The delay in appointing
engineering consultants has pushed back the anticipated timescales of a
planning application being submitted in May 2024. We are looking to appoint
a contractor after May with an anticipated site start date in November 2024
Mount Pleasant, Old Kilpatrick
This is a 19-unit complex which is designed for elderly residents and will
deliver high quality amenity housing. CCG have been appointed as the main
contractor following the Tendering Committee in September, having been
directly appointed from the Scotland Excel Framework. The site start date is
subject to prestart planning conditions, but estimated to be on 15th April 2024
and construction will last approximately one year. 
Queens Quay, Site C, Clydebank
The Council has been developing a design to deliver a projected 20 units on
this site to complement the housing mix within sites A and B.  This
development will also be designed to meet low/zero carbon principles and
linked to the Queens Quay district heating network.
.
Pre-planning response was received on the 25 February highlighting concern
of the WDC development proceeding in isolation. We have adopted a
proactive response to this issue and have developed masterplan diagrams
incorporating the surrounding sites and have conducted valuations on the
adjacent site to Queens Quay C with a view to purchasing additional land to
deliver more affordable housing in the Queens Quay regeneration site. If this
is achieved, we would seek to develop a mixed tenure approach to any
expanded development site delivering one hundred new affordable homes.
We are seeking discussion with CRL (Clydeside Regeneration Limited) to
Page 28

Page 29

progress the possibility of acquiring this additional land and will be able to
draw down Scottish Government grant to enable this.
Clydebank Health Centre
Our appointed design team are doing some feasibility work based on a
housing mix of 20 units of sheltered housing and 18 units to be a mix of family
housing and cottage flats within the development site. The aim of the 20 units
of sheltered housing is to introduce the potential; to reprovision existing
sheltered housing currently provided at Young Street, therefore strategically
improving the provision of sheltered accommodation within Clydebank. 
This is in advance of the demolition of the buildings within the site which is
currently scheduled to start in March 2024. 
Dennystoun Forge Gypsy/Traveller Site
A submission was made to the Scottish Government for support funding from
their Gypsy/Traveller Accommodation Fund for significant improvements to
the Dennystoun Forge site, including new energy efficient chalet type
accommodation following a consultation exercise with site residents. 
However, we were notified that this submission was unsuccessful at this point.
We have since engaged the Scottish Government following the outcome of
this and have provided additional information to the Scottish Government in
support of the application.  
In another positive development the Council’s Housing Development Team
has been providing support to the tenants within the Dennystoun Forge site to
establish a registered tenants association, the absence of a recognised
tenants group and ongoing site presence was seen as a relative weakness in
terms of the initial submission.  
We anticipate that following the new information provided to support our
application for funding Scottish Government officials will reassess the
application before the end of 2023/24. 
Queen Mary Avenue, Clydebank (Clydebank Gap Sites)
The transfer of the site at Queen Mary Avenue, Clydebank with vacant
possession at the cost of £140,000 from the Council’s General Fund to the
Housing Revenue Account for the delivery of new Council homes was
approved at the February meeting of the Housing and Communities
Committee and has now been concluded.  
The Council is preparing a demolition programme to allow the site to be
cleared as soon as possible following the recent departure of Council staff
teams who were using the premises. 
Page 29

Page 30

A feasibility study is being undertaken to inform how best to develop the site,
taking into consideration housing need and demand for the area. This
programme is running parallel with the pre-demolition works.   
Gilmour Avenue, Hardgate (Clydebank Gap Sites)
As part of the wider development of our Clydebank Gap Site strategy we
identified a Housing Revenue Account site in the Hardgate area at Gilmour
Avenue.  The site was previously the location of timber garages on concrete
bases.  These have long since been demolished and the site has been beset
with fly tipping issues for several years. The proposed development would see
two three bed semi-detached homes to be delivered utilising modular
construction methods.  A planning application was submitted in early February
2024, and we await approval.
Silverton Regeneration
The 2 identified sites in Smollett Road and Dumbuie Avenue are progressing
towards demolition and building warrants for demolition in place.  We are
currently undertaking a feasibility development study to assess the suitability
and potential capacity for the delivery of new homes within these sites.  
Buyback Programme
The Council’s buyback programme which incorporates the Mortgage to Rent
Scheme purchased 16 new homes in 2022/23.  In 2023/24 we anticipate
purchasing around 44 new homes at an average purchase cost of £100,000.
In 2023/24 and following approval of the Strategic Housing Investment Plan
by the Housing and Communities Committee in November 2022 and
subsequently the decision by West Dunbartonshire Council in March 2023 to
deliver an enhanced Housing Capital Investment Programme including
additional funding for buyback purchases we are now scaling up ambition
around our buyback programme.  In 2024/25 and in each of the subsequent
years up to and including 2027/28 we plan to deliver 60 new homes each year
meaning a minimum of 300 new Council homes to meet identified need will be
added to the Council housing stock.  
Alternative affordable housing models
4.6 Affordable housing includes housing for social rent provided by registered
social landlords (RSLs) and Councils, housing for affordable home ownership
such as the HOME model developed by Scottish Futures Trust (SFT) and
mid-market rented housing (i.e., housing above social rent levels but below
market rent levels).
4.7 Previously local authorities could only access grants to build new homes for
social rent.  Recent changes to the grant system mean that local authorities
can now access financial support to deliver mid-market rent homes, albeit at a
lower grant entitlement rate.  Offering alternative affordable tenures would
Page 30

Page 31

represent an opportunity to deliver additional affordable homes in West
Dunbartonshire rather than reduce from our existing programme as set out in
the SHIP. 
4.8 These alternative tenures require less, or no, grant support but still deliver
additional affordable homes.  This may be a positive strategy for providing
affordable homes in West Dunbartonshire considering the recently announced
reduction on the Affordable Housing Supply Programme national funding
highlighted in Section 6 of this report.
4.9 However, to access the grant funding and deliver alternative affordable tenure
homes, West Dunbartonshire Council Housing Revenue Account requires to
establish two subsidiary companies. The first would be a Limited Liability
Partnership (LLP) with SFTi (Scottish Futures Trust Investment) and would
allow us to develop homes to provide Home Ownership Made Easy (HOME)
shared ownership properties for older households.  These types of homes
could help us accommodate our growing older population which is forecast to
increase to 25% of households by 2030 and this would also increase this
group’s housing options.  It also does not qualify for any Scottish Government
grant funding.
4.10 The second would be another LLP to allow us to develop mid-market rent
homes and offer private residential tenancies (PRTs) which we cannot
currently offer due to the limitations placed on social landlords.  It is proposed
SFTi would be our LLP partner.   These types of homes would help us
accommodate demands from a variety of households who may struggle to
access other types of housing such as the private rented sector or owner
occupation.  We can access grant for these homes, albeit at a lower rate
within the wider Affordable Housing Supply Programme funding.
4.11 The establishment of these two entities would be complimentary and owned
entirely by the West Dunbartonshire Council’s HRA thus protecting all our
current, and future, tenants/ co-owners.
4.12 The Housing Development Team are continuously looking for opportunities to
provide additional new build council homes and will bring any potential site to
the Housing and Communities Committee with as much information as
possible as part of the regular More Homes update paper.
5. People Implications
5.1 There is now a Full Time Officer in place with sole responsibility for the Buy
Back Scheme within the Housing Development & Homelessness team funded
from the Housing Capital Investment Programme.  
5.2 Staff resource is required from Housing Development and Legal Services
primarily to establish the proposed Housing Revenue Account subsidiary
organisations in partnership with Scottish Futures Trust Investment (SFTi).
Page 31

Page 32

6. Financial and Procurement Implications
Financial
6.1 On 1 March 2023 Council approved the Housing Capital Programme 2023-
2028 which saw significant resources committed to the delivery of new council
homes in West Dunbartonshire.  An expenditure budget of £155m for the
affordable housing supply programme is factored into the HRA Capital
Programme this will be updated to reflect the income and expenditure
highlighted within this report.  As it currently stands, it is anticipated that this
programme will complete on project life budget.
6.2 Housing and Finance Officers will continue to assess the ongoing affordability
of future developments within the context of the Housing Revenue Account
Business Plan.
6.3 In December 2023, the Deputy First Minister and Cabinet Secretary for
Finance set out the Scottish Government’s proposed spending and tax plans
for the Scottish Budget 2024/2025. The announcement revealed that the
Scottish Government was proposing a reduction in the overall Housing and
Buildings Standards budget from £738m this year to £533m next.   This
represents a cut of around £200m or 26%.
6.4 The More Homes budget, which provides grant aid for affordable new homes,
is shown to reduce from £564.6m this year to £375.8m next year. While the
capital funding side of this budget which supports the delivery of Strategic
Housing Investment Plans is potentially protected with a smaller reduction of
£75m or 14%, there is still likely to be a significant negative impact on new
social housing delivery. 
6.5 The current West Dunbartonshire Council Annual Resource Planning
Assumption (RPA) from the Scottish Government to help the delivery of the
Council’s Strategic Housing Investment Plan (SHIP) and subsequently the
Council’s own new build programme is £10.795m.  Our SHIP 2024/25 –
2028/29 uses this projected budget to plan the wider development
programme.  We are in ongoing discussion with our colleagues in the Scottish
Government’s More Homes Division over what the reduction in funding will
mean for our programme and await a revised RPA which will cover 2024/25.
6.6 In advance of the revised RPA we have projected a 15% reduction in the
2024/25 RPA this may have the following impacts: -
• A reduced RPA allocation of around £1.6m to £9.2m in 2024/25.
• 15 less homes being delivered on an annual basis in West
Dunbartonshire as a result of the reduction in funding (75 within the
lifecycle of the current Strategic Housing Investment Plan)
Page 32

Page 33

6.8 While the proposed reduction in funding presents a challenge to realising the
Council’s new housing ambition, it is one that can be managed effectively with
strategic planning.  The Strategic Housing Investment Plan will be managed
through the More Homes Project Board to minimise the impact of the
reduction in funding and to maximise delivery of the programme priorities. To
mitigate the impact of the cuts it may be necessary to delay some projects
and to stretch the programme.  It is intended that Council Officers will refresh
the Strategic Housing Investment Plan after the revised Resource Planning
Assumption is known.
6.9 As of 1st April 2024, Local Authorities will exempt from LBTT ADS (Land and
Building Tax Additional Dwelling Supplement).  At present the Council is liable
for the Additional Dwelling Supplement for most home purchases through our
buyback scheme.  The Council has campaigned strongly for the removal of
this requirement and the decision reflects the strong case put forward by West
Dunbartonshire Elected Members and Council Officers. In 2023/24 the
Council has so far paid over £155k in Additional Dwelling Supplement close to
£6k per property purchased through the buyback scheme.  With the Additional
Dwelling Supplement being no longer applicable to local authorities from the
1st April 2024 this will avoid costs of around £1.8m over the next 5-year
period.    
Procurement
6.10 All new development sites will be subject to new detailed procurement
strategies and the opportunities highlighted within 4.5 of this report will
continue to be prioritised. Where the contract award is less than £213,000,
authority is delegated to the Chief Officer in consultation with the Procurement
Manager to instruct the award of contracts for the planned revenue and
capital spend detailed in this report to suppliers providing the most
economically advantageous offer to the Council.
6.11 All procurement activity conducted by the Council more than £2m is.
subject to a contract strategy. The contract strategy for new housing
development within the HRA Capital Programme will be developed by the
Corporate Procurement Unit in consultation with Housing Development
Officers. The contract strategy will include, but is not limited to; contract
scope, service forward plan, the market, procurement model and routes –
including existing delivery vehicles, roles and responsibilities, risks, issues
and opportunities and on-going contract management. Opportunities to
maximise the positive social, economic and environmental impact for the
Council through the relevant procurement processes will be developed in line
with procurement policy.
7. Risk Analysis
7.1 All Council new build projects have their own Risk Register which highlights
the risk within and out-with the project team’s control.  These are maintained
and adjusted on an on-going basis.
Page 33

Page 34

7.2 With any new build project there is a risk that as the projects develop the cost
increases beyond the estimated contract cost.  Any additional borrowing
requirements, or conversely, cost savings will be reported to future meetings
of the Housing and Communities Committee. However, this is mitigated
through a target cost model approach in our current contract arrangements
within the Scottish Procurement Alliance (SPA) framework and Scotland
Excel.
8 Environmental Sustainability
8.1 The delivery of new homes is within the approved More Homes zero carbon
approach. Our current and future approach to strategic housing asset
management will continue to prioritise a ‘zero carbon’ approach to decision
making and deliverability and this will be done the aims of the Housing Asset
Management Strategy and the Council’s Climate Change Strategy.
9. Equalities Impact Assessment (EIA)
9.1 The proposal does not alter any existing policy or pattern of service delivery
and so is not considered to require an equalities impact assessment. 
10. Consultation
10.1 As part of a rent consultation exercise, 92% of respondents indicated their
support for the Council’s ambitious plans to deliver the Housing Revenue
Account (HRA) new council house build programme. In addition, there was
positive support for the wider delivery of new build housing as part of the
recent Local Housing Strategy.  Regular updates on new build development
are provided to the West Dunbartonshire Tenants and Residents Organisation
at the bi-monthly liaison meetings. 
10. Strategic Assessment
10.1 The Local Housing Strategy is the overarching document setting out the
strategic direction for housing across all tenures and informs the future
investment in housing and related services across West Dunbartonshire.
10.2 Having considered all the Council’s strategic priorities, this report and the
provision of new supply social housing for rent contributes greatly to all the
Council’s strategic priorities.
Peter Barry
Chief Officer, Housing and Employability
Date: 13 February 2024
Person to Contact: John Kerr – Housing Development and Homelessness
Manager, Housing Development and Homelessness
Page 34

Page 35

Team, Housing and Employability, telephone:
07793717981, email: john.kerr@west-dunbarton.gov.uk
Mikayla Deeley, Senior Housing Development Officer,
Housing Development and Homelessness Team,
Housing and Employability: email mikayla.deeley@west-
dunbarton.gov.uk
Appendices: None
Background Papers: West Dunbartonshire Council’s Local Housing Strategy
Local Housing Strategy, Health Inequalities Impact
Assessment
Wards Affected: All
Page 35

Page 36

Page 36

Page 37

WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer, Housing and Employability
Housing and Communities Committee: 28 February 2024   
__________________________________________________________________
Subject: West Dunbartonshire Buy Back Scheme Policy Review – More
Homes West Dunbartonshire
1. Purpose
1.1 The purpose of this report is to provide members of the Housing and
Communities Committee with the outcomes of the review of the Council’s
Buyback Scheme.  The scheme has increased the housing supply by over
100 new homes in the last 5 years and is planned to deliver a further 300 over
the next 5 years assisting in meeting housing need and combatting
homelessness in West Dunbartonshire.
2. Recommendations
2.1 It is recommended that the Housing and Communities Committee:
(i) Note the content of the report and approve the refreshed West
Dunbartonshire Buy Back Policy; and
(ii) Note from 1st April 2024, the Council will be exempt from LBTT ADS (Land
and Building Tax Additional Dwelling Supplement) following effective
interventions by West Dunbartonshire Council Elected Members.
3. Background
3.1 The introduction of a Buy Back scheme was approved at the Housing,
Environment and Economic Development Committee meeting on 8 May 2013.
Initially the scheme was relatively modest looking to secure 5 new homes on
an annual basis before expanding in 2017 to deliver 15 homes on an annual
basis.
3.2 At the March 2023 West Dunbartonshire Council Meeting it was agreed to
scale up the ambition and vision of the scheme to meet housing need and
help combat homelessness by securing 300 new homes for social rent over a
5-year period averaging 60 purchases per annum over that period.
3.3 The Buy Back Policy has now been reviewed in light of the increased budget
and targets and to ensure that we continue to purchase the most suitable
properties within a prescribed budgetary allocation. 
ITEM 9
Page 37

Page 38

4. Main Issues 
4.1 The Buy Back Policy has the key aim of ensuring the Council has an
increased supply of homes to meet housing need and to support our wider
strategic housing asset management aims. 
4.2 West Dunbartonshire’s Local Housing Strategy (LHS) highlighted a range of
factors which have led to an increased demand for rented accommodation in
both social and private sectors including accessing mortgage finance.  In
addition, there is a national shortage of Social Housing in Scotland.  This has
led to an all-time high in homelessness applications and demand for social
housing both locally and nationally. 
4.3  In West Dunbartonshire we are experiencing a need for larger family housing
and 1-bedroom properties. The Policy (Appendix 1) and how we assess each
property (Appendix 2) reflects these needs. 
4.4 The Council has built 496 new properties in the past 10 years and has an
ambitious new build programme going forward.  Together with the Buy Back
Scheme, all properties built and purchased will help in addressing the
mismatch between the properties required to meet the needs identified within
the Local Housing Strategy.   
4.5 Since 2020/21 the Council has had access to Scottish Government Affordable
Housing Supply Grant to supplement the scheme. 
4.6 The main aims of the Buy Back Scheme are: 
• Deliver the key objectives of the Local Housing Strategy by 
o Accelerating the supply of new housing of the right size and type
to meet housing need. 
o Reducing the need for Temporary Accommodation 
o Reduce the number of Empty Homes 
o Help maintain and create vibrant communities. 
• Deliver the key objectives of the Housing Asset Management Strategy 
o Improve the standard of housing across the Council areas 
o  Assist the Council with SHQS/Capital Works obligations. 
4.7 In December 2023 the Scottish Government released Guidance on a National
Acquisition Programme. The Council’s Policy complies with this Guidance
where both have similar aims. 
Page 38

Page 39

4.8 The review of the Buyback policy has assessed the current policy to be robust
and fit for purpose, as a result there are no significant policy changes,
however there are several refinements made to the policy and these are
summarised below: 
• Policy is amended to reflect the increased number of buy backs proposed. 
• Policy is amended to reflect the increased budgetary provision; to enable
the purchases. 
• Governance has been strengthened through the ongoing focus at the More
Homes Project Board. 
• Policy highlights clear focus on larger properties for families to reduce the
housing waiting list; and 
• Scoring Matrix has been adapted to reflect the type & size of properties we
require including our net zero ambitions. 
4.9 As of 1st April 2024, Local Authorities will now be exempted from LBTT ADS
(Land and Building Tax Additional Dwelling Supplement).  At present the
Council is liable for the Additional Dwelling Supplement for most home
purchases through our buyback scheme.  The Council has campaigned
strongly for the removal of this requirement and the decision reflects the
strong case put forward by West Dunbartonshire Elected Members and
Council Officers. In 2023/24 the Council has so far paid over £155k in
Additional Dwelling Supplement close to £6k per property purchased through
the buyback scheme.           
5. People Implications 
5.1 A Senior Housing Development Officer was appointed in January 2024 to lead
the Council’s Buy Back Scheme; this post is funded from the Housing Capital
Investment Programme.   
5.2 Staff resource is required from Housing Development and Legal Services
Teams primarily to ensure the delivery of the ambitions of the Council’s
Buyback Policy. 
6. Financial and Procurement Implications 
Financial 
6.1 An annual budget of £4m each year from 2023/24 until 2027/28 was approved
at the meeting of West Dunbartonshire Council in February 2023 within the
Housing Capital Investment Programme.  From years 2028/29 the annual
budget is assumed to be £2m. 
6.2 With the Additional Dwelling Supplement being no longer applicable to local
authorities from the 1st April 2024 as highlighted in 4.9 of this report this will
avoid costs of around £1.8m over the next 5-year period.  This will be
assessed by the Lead Officer and may result in increased targeting of larger
homes through the buyback scheme.
Page 39

Page 40

Procurement  
6.3 There are no Procurement issues within this Report. 
7. Risk Analysis 
7.1 All Council housing projects have their own Risk Register which highlights the
risk within and out-with the control of the Council’s Lead Officer.  These are
maintained and adjusted on an on-going basis and reported regularly to the
More Homes Project Board. 
8 Environmental Sustainability 
8.1  The policy reflects an enhanced zero carbon approach. Our current and future
approach to strategic housing asset management will also prioritise a ‘zero
carbon’ approach to decision making and deliverability and this will be further
reflected in a refreshed Housing Asset Management Strategy and will also
reflect the aims of the Council’s Climate Change Strategy. 
8. Equalities Impact Assessment (EIA) 
8.1 The proposal does not alter any existing policy or pattern of service delivery
and so is not considered to require an equalities impact assessment. 
9. Consultation 
9.1 In December 2023 the WDTRO were consulted on the revised Policy and
presented to them. The group were very supportive of the scheme and the
direction of the policy and have supported the scaling up of the scheme. 
10. Strategic Assessment 
10.1 The Local Housing Strategy is the overarching document setting out the
strategic direction for housing across all tenures and informs the future
investment in housing and related services across West Dunbartonshire. In
addition, having considered all the wider Council’s strategic priorities, this
report and the provision of high-quality homes contributes greatly to all
strategic priorities. 
Peter Barry
Strategic Lead, Housing and Employability
Date: 13th February 2024 
Person to Contact: John Kerr – Housing Development and Homelessness
Manager, Housing Development & Homelessness Team,
Page 40

Page 41

Housing & Employability, telephone: 07793717981,
email: john.kerr@west-dunbarton.gov.uk 
Jackie McRory – Senior Housing Development Officer,
Housing Development & Homelessness Team, Housing
& Employability, email: jackie.mcrory@west-
dunbarton.gov.uk 
Laura Hanna – Senior Housing Development Officer,
Housing Development & Homelessness Team, Housing
& Employability, email: laura.hanna@west-
dunbarton.gov.uk 
Appendices: 1 – Draft More Homes West Dunbartonshire BuyBack
Policy – January 2024  
2 – Buyback Scheme Scoring Matrix 
Background Papers: None 
Wards Affected: All 
Page 41

Page 42

Appendix 1 – More homes West Dunbartonshire BuyBack Policy – January 2024
1. Purpose of Buy Back Scheme
1.1 West Dunbartonshire Council’s Buy Back Scheme will assist in increasing the
provision of Council housing in the area by purchasing primarily but not
exclusively former Council Right to Buy properties using a robust assessment
criteria.
1.2 This Policy has the key aim of ensuring the Council has an increased supply
of homes to meet housing need and to support our wider strategic housing
asset management aims. The Policy will lead to an improved situation for
existing and future Council tenants.  This Scheme is also not designed to
specifically assist owners and as such we will maintain a right of refusal at any
point in the process.
1.3 In March 2023, the Council agreed to provide £4m of Housing Capital
Investment funding each year to support the delivery of the buyback scheme.
This meant the scheme could purchase more than it ever has in the past and
make a real impact on assisting with the Aims outlined below which feed into
wider Housing priorities.
1.4 We have established access to Scottish Government Affordable Housing
Supply Grant towards these purchases and recently the Scottish Government
have supported our proposal to increase the amount of grant  for the
purchase of larger family homes.
2. Background
2.1 Since the introduction of the Right to Buy (RTB) legislation in 1981,
approximately 12,000 properties have been sold to sitting tenants in West
Dunbartonshire.  The RTB ended on 31 July 2016.  All sales through the RTB
legislation have a detrimental impact on the Council’s ability to meet the
housing needs of the wider community and its ability to meet its statutory
responsibilities in respect of homelessness.
2.2 West Dunbartonshire’s Local Housing Strategy (LHS) highlighted a range of
factors which have led to an increased demand for rented accommodation in
both social and private sectors including accessing mortgage finance.
2.3 There is a national shortage of Social Housing in Scotland.  This has led to an
all-time high in homelessness applications and demand for social housing
both locally and nationally.
2.4 In West Dunbartonshire in particular we are experiencing a need for larger
family housing and 1 bedroom properties. This Scheme will seek to prioritise
to alleviate these issues.
2.5 The Council has built 496 new properties in the past 10 years and has an
ambitious new build programme going forward.  Together with the Buy Back
Scheme, all properties built and purchased will help in re-dressing the
ITEM 9 -
APPENDIX 1
Page 42

Page 43

Appendix 1 – More homes West Dunbartonshire BuyBack Policy – January 2024
mismatch between the properties required to meet the needs identified within
the Local Housing Strategy.   
3. Strategic Context 
3.1 The Council’s Strategic Priorities outlined in the strategic Plan 2022-27
explain how the Council will work to improve the lives of residents. The
priorities are: 
Any increased provision of social rented housing contributes to these strategic
priorities. 
3.2 The Housing and Employability Delivery Plan sets out the actions that the
Division will undertake to help deliver the Strategic Plan.  The Buy Back
Scheme will help to meet the following Actions:  
• Deliver the Council’s Affordable Housing Supply Programme
• Review the Council’s Buy Back Scheme 
Page 43

Page 44

Appendix 1 – More homes West Dunbartonshire BuyBack Policy – January 2024
3.3 One of the key LHS aims is to ensure that people have access to affordable
housing of all tenures which is in the right location and is suitable for their
needs.   
3.4 The Strategic Housing Investment Plan (SHIP) sets out how resources will be
used over a 5 year period to deliver affordable housing priorities set out in the
LHS.  
4. Aims and Objectives 
4.1 The main objective of the Buy Back Scheme is to:  
‘Assist the Council in meeting and delivering its strategic housing objectives’ 
4.2 The main aims of the Buy Back Scheme are: 
• Deliver the key objectives of the Local Housing Strategy by 
o Accelerating the supply of new housing of the right size and type
to meet housing need 
o Reducing the need for Temporary Accommodation 
o Reduce the number of Empty Homes 
o Help maintain and create vibrant communities 
• Deliver the key objectives of the Housing Asset Management Strategy 
o Improve the standard of housing across the Council areas 
o  Assist the Council with SHQS/Capital Works obligations,
including future compliance with the Social Housing Net Zero
Standard 
4.3 The Scottish Government recently released guidance on the National
Acquisition Programme. While the Council’s Policy does not fully adopt all
aspects of this Guidance, where it does, the Policy fully complies. 
5. Principles of the Buy Back Scheme 
5.1 All properties will be assessed using a methodology adopted within a Scoring
Matrix.  The Scoring Matrix which has been developed in consultation with
Tenants will be fully outlined within the Buy Back Scheme Policy. 
5.2 The Scoring Matrix has been developed based upon the following principles: 
Capital Funds
Page 44

Page 45

Appendix 1 – More homes West Dunbartonshire BuyBack Policy – January 2024
There must be Capital funds available at the time of any enquiry.  If, on
consulting the HRA Business Plan, it is established that it is not financially
viable then the Council will decline any request. 
Housing Need and Demand 
Any acquisition of properties for social housing use must be of the right size
and type as informed by our Housing Need analysis.  Therefore, any
purchase must assist the Council in achieving the aims outlined above 
Scottish Housing Quality Standard/Investment Requirements 
The valuation must reflect the current market value and any costs associated
with ensuring that the property achieves the SHQS can be justified in line with
the aims of this Policy. 
Empty Homes 
The Scheme will assist with the Empty Homes Initiative to work in partnership
to bring back properties into the Council’s housing stock in line with the Policy
Aims. 
Former Right to Buy or Specific Purchase
The majority of properties that are purchased will be former Council properties
bought through the Right to Buy (RTB) Scheme and will therefore be a similar
style and construction to those that the Council already maintain and will be in
areas that the Council has a presence.   
However, if there is a specific need that cannot be met through existing stock
or planned new build that the market can provide the solution too, then so
long as the principles outlined above are fulfilled, this purchase would be
justified. 
6. Financial Approach 
6.1 From 23/24 to 27/28 The Scheme has a budget of £4m each year. 
6.2 The Housing Development Team have a target of 60 purchases within each of
these financial years. 
7. Monitoring and Review 
7.1 More Homes Board
The actual spend of the Buy Back Scheme will be monitored by the More
Homes Board.  The details of the sales, including address, size and type and
purchase price will be recorded and reported to the More Homes Board on a
monthly basis. 
7.2 Housing and Communities Committee
An update on progress will be reported quarterly to the Housing and
Communities Committee as part of the More Homes Committee Report 
7.3 Policy Review 
Page 45

Page 46

Appendix 1 – More homes West Dunbartonshire BuyBack Policy – January 2024
The Buy Back Policy and Procedure will be reviewed on an annual basis and
report to the More Homes Project Board each May. 
8. Further Information 
8.2 If you require further information on the Buy Back Policy or Procedure visit the
Councils website - https://www.west-dunbarton.gov.uk/housing/private-
housing/buy-back-scheme/ or Email: Buy.Back@west-dunbarton.gov.uk 
or call: 07551 422 581 
Lead Officer - Laura Hanna – Senior Housing Development Officer, Housing
Development & Homelessness Team, Housing & Employability, email:
laura.hanna@west-dunbarton.gov.uk 
Page 46

Page 47

Appendix 1 – More homes West Dunbartonshire BuyBack Policy – January 2024 
9. Glossary of Terms 
Right to Buy (RTB)
The Housing (Scotland) Act 1987 gave tenants the right to purchase the
Council home they lived in.  The RTB has been altered several times since
and will be abolished in 2017. 
Local Housing Strategy (LHS)
The Local Housing Strategy (LHS) sets out our understanding of the housing
issues over the coming five year period and indicates how the Council and its
partners address them. 
The LHS provides the strategic direction for housing across all tenures and
informs the future investment in housing and related services across West
Dunbartonshire. 
Strategic Housing Investment Plan (SHIP)
The Strategic Housing Investment Plan (SHIP) sets out the funding priorities
for affordable housing in West Dunbartonshire for a three year period. 
The LHS and SHIP together guide the application of Scottish
Government and other housing funding. The main focus of the SHIP is
the targeting of the Scottish Government’s Affordable Housing Supply
Programme Funding and the Council House Building
Programme. 
Housing Revenue Account Capital Programme
The Housing Revenue Account Capital Programme is part of Housing’s 30
year Business Plan and sets out how the Council will improve and repair its
housing and estates.  Meeting and maintaining the Scottish Housing Quality
Standard (SHQS) is part of this investment. 
Scottish Housing Quality Standard (SHQS)
This is the standard that all social landlords in Scotland have to meet by 2015. 
Empty Homes Initiative
This initiative is called Homes Again West Dunbartonshire.  The aim is to
bring private sector homes that have been empty for over six months back
into use. 
Page 47

Page 48

Appendix 2 – Buyback Scheme Scoring Matrix
Capital Funds Available
Yes
No
Property meets Aims of policy
Yes
No
Property with vacant possession
Yes
No
If Yes:-
Housing Need Score
1 bed or 3 bed + 10
Wheelchair Adapted Property 10
Ground floor bedroom & bathroom within a House 10
Ground Floor Property with fewer than 2 stairs 5
Housing Demand Score
High Demand 10
Medium Demand 5
Low Demand 0
SHQS/Investment Requirements Score
£10,000 & above 2
£5,000 - £9,999 5
£0 - £4,999 10
Score
Property referred by Empty Homes 15
Completes block of flats into full WDC ownership 15
Property Meets New Zero Assessment 15
Owner ratio exceeds tenant ratio -15
Scoring over 20 – property will be considered for purchase
ITEM 9 -
APPENDIX 2
Page 48

Page 49

WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer, Housing and Employability
Housing and Communities Committee: 28 February 2024
__________________________________________________________________
Subject: Willox Park Sheltered Housing Complex Options Appraisal
1. Purpose
1.1 This purpose of this report is to provide the Housing and Communities
Committee an update on the recent options appraisal consultation exercise at
Willox Park.
2. Recommendations
2.1 It is recommended that the Housing and Communities Committee:
(i) Note the content of the report and the actions that have been taken to
consult with the Willox Park Sheltered Housing Complex tenants.
(ii) Approve Option 3 – Redevelopment which would see the existing homes
replaced with new modern energy efficient homes through a master
planning approach agreed in full consultation with existing tenants;
(iii) Agree to designate all 36 properties within the Willox Park Sheltered
Housing Complex as surplus to requirements.
(iv) Authorise the Chief Officer, Housing & Employability to commence all
associated procurement activity to achieve the delivery of Option 3 –
Redevelopment.
(v) Invite the Chief Officer, Housing & Employability to take the next steps
with all remaining tenants
a) To ensure that all tenants have a personalised housing plan
prepared;
b) To ensure that all tenants have the necessary priority identification
through the Council’s Allocation Policy;
c) To develop a lettings plan for the new homes being delivered at the
adjacent former care homes site to ensure priority is given to the
existing tenants of the Willox Park Sheltered Housing complex as
either a temporary or permanent housing solution; and
d) To authorise Home Loss and Disturbance Payments with all
tenants throughout the master planning delivery process
ITEM 10
Page 49

Page 50

(vi) Invite the Chief Officer, Housing and Employability to provide the Housing
and Communities Committee with regular update reports.
3. Background
3.1 Willox Park Sheltered Housing Complex comprises 36 terraced bungalows
offering sheltered housing in Dumbarton. It was built in the 1960s and is
typical of the building and space standards of that time.  Whilst the tenants
like having their own front door and a little outside space, the internal layout is
not conducive to healthy living for those with limited mobility.
3.2 The existing homes have received replacement roof and external wall
insulation over the last twenty years alongside investment in kitchens,
bathrooms, and windows.  However, tenants have complained of dampness
and draughts and some of the homes are affected by mould.
3.3 Damp surveys found several causes of the dampness, but some homes are
more affected than others, indeed some have no evidence of dampness.
Consequently, we have moved all but one of the most affected tenants out
and we intend to prioritise the installation of environmental sensors in all other
homes so we can keep a close eye on the remaining occupied properties.
3.4 The Housing Revenue Account previously acquired the adjacent site to the
Sheltered Housing Complex which formerly sited a Council Care Home, it has
been reported previously to the Housing and Communities Committee that
this site will be developed to 17 new homes (15 one-bedroom homes and two
two-bedroom homes). These homes offer modern accessibility standards and
are designated.
4. Main Issues
4.1 The extent of the problems with the homes at Willox Park necessitated an
options appraisal to review the future of the homes.  Consequently, we have
consulted with tenants on four options;
• do nothing;
• refurbishment;
• redevelopment, and
• hybrid.
More details on each of these are below alongside the consultation outcomes.
The consultation received 14 votes which constitutes 56% percent of tenants.
Details of the consultative exercise; can be found in the appendix, but it
involved several drop-in sessions alongside phone calls to make sure
everyone had a chance to ask questions in terms of the consultation. 
4.2 Option 1: Do nothing
This option represented maintaining the status quo; repairs will continue to be
carried out for occupied homes and empty homes will not be relet. This
Page 50

Page 51

represents the least disruption to sitting tenants but would see the complex
become less vibrant and run down as more homes become vacant.  
Of those who voted:  7% of tenants voted for this option (one vote).
The tenants who voted for this told us they did so because they don’t want to
move and they like their current home.
4.3 Option 2: Refurbishment
This option would maintain the current properties by refurbishing them. The
refurbishment would involve stripping the properties back to brick internally
and externally, removing cavity wall insulation, applying a damp-proof
membrane to the floors, structural works to improve the fire compliance of the
homes, and replacing doors, windows, kitchens, bathrooms etc.  
We anticipate the works would be completed on a block-by-block basis and
would take around 12 months. Tenants would be unable to live in their homes
whilst work was carried out.  Work would not start until the new homes were
complete on the care site so that tenants could be relocated to these which
would keep the community together and minimise disruption to care.  The
Council committed to tenants having the option to return to their cottages and
refurbish the common room. 
This option would be expensive due to the amount of work needed, and we
would not be able to access grant funding to reduce the cost to the Housing
Revenue Account (HRA). There are also several risks including damp
proofing solutions only offer a maximum 20-year guarantee and whilst we
might be able to do some structural work to improve the layouts to make them
more accessible, we will be constrained by the unusual property footprints. 
Of those who voted:  21% of tenants voted for this option (three votes) 
The tenants who voted for this told us they did so because they like their
homes and having their front door and garden.  Those who picked this option
suggested that the layout of the houses could be improved by removing walls/
cupboards, creating wet rooms, and improving windows and roof
maintenance. They would like to return to their home after works are
completed and would like to be involved in choosing the décor.  
4.4 Option 3: Redevelopment
This option would see the existing cottages demolished and a master
planning approach developed to deliver new homes on the site. As with option
2 above, demolition and redevelopment would not start until the new homes
on the care home site were completed to allow tenants to move into the new
homes and keep the community together.  This will likely require phased
demolition and redevelopment to achieve this. 
The types of homes and master planning approach would be developed in
collaboration with the tenants. We expect it would be like the care home site
Page 51

Page 52

and designed with accessibility and design features to suit older households
to help us plan for housing our growing elderly population. 
The masterplan will also include a new, modern common room which will be
able to provide better meeting and gathering space for the community.  The
homes will be very energy efficient which should reduce running costs for
tenants. We can also access Scottish Government grant funding through the
Affordable Housing Supply Programme to reduce the cost to the HRA. 
Of those who voted:  57% of tenants voted for this option (eight votes) 
The tenants who voted for this told us they did so because whilst they like
their home, they could see from their own experiences the new homes could
offer a lot of benefits in terms of energy efficiency and layout.  They did
however note keenness to be involved in the development of the masterplan
and would like to see some replacement bungalows, where possible, because
some were hesitant about living in a flat.  
4.5 Option 4: Hybrid
This option offered tenants a bit of both redevelopment and refurbishment and
as with both options work would not start until the homes at the care home
site were completed so that tenants could move into these, we would
minimise disruption and the community would stay together. 
It is unclear at present which parts of the site would keep their homes and
which parts would be redeveloped but this option brings both the risks and
opportunities of both the above options.  
Of those who voted:  14% of tenants voted for this option (two votes) 
The tenants who voted for this didn’t expand upon their thought process, but
the rationale is likely to be like those expressed for the refurbishment and
redevelopment options. 
4.6 Based upon the consultation exercise completed with the tenants at Willox
Park the recommendation would be to take forward option 3: Redevelopment
and work with the tenants to develop a masterplan to deliver modern older
people’s housing to meet current and future demand from this demographic
group.
5. People Implications
5.1 If the redevelopment option is approved it will require a staffing resource to
ensure a full collaborative approach with the existing tenants in delivering the
master planning approach.  It is proposed that a temporary Housing
Development Officer post within the existing structure is made permanent to
support this delivery.
Page 52

Page 53

6. Financial and Procurement Implications
Financial
6.1 As outlined within the options appraisal exercise there are financial
implications with all the options.  Declaring the properties surplus to
requirement, rehoming tenants and the delivery of the chosen option will be
funded from the Housing Revenue Account Capital Investment Programme.  If
the recommend option of Redevelopment is chosen, this will be funded form
the Affordable Housing Supply Programme future new build element of the
Housing Capital Investment Programme.  As with all Capital works developing
new homes will require prudential borrowing for the HRA but the
redevelopment option will allow the Council to access Scottish Government
grant funding which will support the delivery and reduce the overall cost to the
HRA. The new homes will have a long income-earning life as an income
generating asset for a minimum of 100 years.
Procurement
6.3 The next phase of Willox Park will require several procurement exercises
these will include various consultants to support the development of the
master plan and design including engineers alongside contractors including
demolition and building contractors. This report seeks permission to procure
and appoint the appropriate consultants and contractors using existing
Council policies and procedures.
7. Risk Analysis
7.1 We maintain risk registers for each project which highlights the risk within and
out-with the project team’s control.  These are maintained and adjusted on an
on-going basis.
8 Environmental Sustainability
8.1 The delivery of new homes will be consistent with our wider More Homes zero
carbon approach. Our current and future approach to strategic housing asset
management will continue to prioritise a ‘zero carbon’ approach to decision
making and deliverability and this will be further reflected in the master
planning approach adopted consistent with the aims of the Housing Asset
Management Strategy and the Council’s Climate Change Strategy.
9. Equalities Impact Assessment (EIA)
9.1 The proposal does not alter any existing policy or pattern of service delivery
and so is not considered to require an equalities impact assessment.
Page 53

Page 54

10. Consultation
10.1 We have consulted with the tenants at Willox Park throughout this process.
We have kept them up-to-date best we can with the findings of the surveys
and then consequently the consultation into the future of the homes.  They
have also been involved the new development of the care home site into new
homes and they are looking forward to seeing that come forward and moving
into it.  
10.2 We have utilised newsletters, letters, drop-in events in the common room,
phoning the tenants who we hadn’t heard from, and the housing officer has
continued to officer support and answer questions at her weekly surgeries.
The Registered Tenants Organisation at Willox Park has also been actively
encouraging participation in the consultation process too and officers have
attended their meetings.
10.3 All existing tenant and their families will be impacted by the decision taken by
the Housing and Communities Committee.  We will contact tenants and other
stakeholders and let them know the outcome of Housing and Communities
Committee.  This communication will reinforce a continued collaborative
approach to deliver the agreed outcomes.
11. Strategic Assessment
11.1 The Local Housing Strategy is the overarching document setting out the
strategic direction for housing across all tenures and informs the future
investment in housing and related services across West Dunbartonshire.
Having considered all the Council’s strategic priorities, this report and the
provision of high-quality social housing for rent contributes greatly to all
strategic priorities. 
Peter Barry
Chief Officer, Housing and Employability
Date: 13th February 2024
Person to Contact: John Kerr – Housing Development and Homelessness
Manager, Housing Development and Homelessness
Team, telephone: 07793717981, email: john.kerr@west-
dunbarton.gov.uk
Emily Dorrian – Senior Housing Development Officer,
Housing Development and Homelessness Team, email:
emily.dorrian@west-dunbarton.gov.uk
Appendices: 1. Willox Park Options Appraisal Document
2. Willox Park Consultation Summary
Page 54

Page 55

Background Papers: Report to Housing and Communities Committee, August
2023 
Wards Affected: 3
Page 55

Page 56

Willox Park
OPTIONS APPRAISAL CONSULTATION DOCUMENT
ITEM 10 - APPENDIX 1
Page 56

Page 57

Please tell us what you think:
Following recent surveys we have found a
number of problems with the homes at Willox
Park. We now need to decide on the future of
the complex.
This document sets out the options that we are
asking tenants to give us their thoughts on.
You will have 8 weeks to tell us your thoughts
and we will have drop in sessions in the
common room and will happily speak to you in
person or on the phone. 
We will then present the findings from this
consultation to elected members in the new
year in a paper and the elected members will
make the final decision.
8 weeks consultation:
closes 10th January
Dates of drop in sessions
(Willox Park Common Room):
Tuesday 28 November – 10am – 12pm
Wednesday 13 December  - 10am – 12pm
Friday 5 January  – 10am – 12pm
My contact details:
Emily Dorrian
Emily.Dorrian@west-dunbarton.gov.uk
07785656625
Page 57

Page 58

Option A: maintain current status
The works will involve:
•Only works identified in existing asset plans will be done
when they reach the end of life e.g. kitchens, bathrooms,
and windows etc. 
•Repairs and maintenance to continue for occupied
homes.
•Empty homes will not be re-let because of ongoing
concerns about dampness.
Pros and cons:
•Wider complex will become less vibrant as homes slowly
become empty and contrast with new build homes
when they are built.
•Properties will continue to deteriorate due to dampness
and other defects
•The council will lose rental income but will need to
maintain and invest in less homes.
•Presented here because it is an option which offers the
least disturbance to existing tenants. 
Page 58

Page 59

Option B: Refurbishment
The works will involve:
•Strip back to brick internally & externally
•Apply damp proof solution to floors and walls
•Potential structural works to add second fire exit off bedroom/
improve layouts
•replace doors, windows, roofs, gutters, kitchens, bathrooms,
external wall insulation, new plastered ceilings and walls
internally, loft insulation, rewire, heating systems replaced with
heat pumps & radiators.
•Tenants would need to move out of their home and works
completed on a block by block basis.
•Works to each block will take around a year done so it will be a
multi year project.
•Existing common room would be refurbished.
Some pros and cons:
•These works are disruptive to tenants and expensive to
complete.
•Refurbishment works would not start until phase 1 new build
homes are completed.
•Only 10 to 20 year guarantee on damp proof solutions risks
problems returning.
•May find additional structural or other problems once work starts
•Homes will be much more energy efficient with new insulation.
•Homes will be different after works are completed.
•There is a risk that homes no longer meet modern building
standards for older households due to layout and we will not be
allowed to let them to this group.
Page 59

Page 60

Option B: Refurbishment photos
Picture showing a room stripped back to brick internally.
Picture showing a house stripped back to brick externally,
new windows fitted and roofing works underway
Page 60

Page 61

Option C: Redevelopment
The works will involve:
•Demolish the existing homes in phases
•Build new energy efficient homes, the properties will be larger
and meet modern accessibility standards for older households.
•A new common room would be built, phasing of this is to be
confirmed but a temporary solution will be found if needed.
•Tenants would move into the phase 1 new homes (care
homes site) to allow phased demolition and redevelopment.
•Exact design to be consulted on with tenants but based on
similar to phase 1 then could get a further 20-25 new homes on
the site.
Some pros and cons:
•Demolishing and redeveloping is disruptive to tenants.
•Demolition and redevelopment works would not start
until phase 1 new build homes are completed.
•Developing new homes is expensive.  However, we can
access Scottish Government grant funding towards new
homes to reduce costs for the council..
•A new common room will provide better meeting and
gathering space.
•New homes will have better layouts and will have more
energy efficient building fabric which should reduce running
costs.
•New homes would be expected to last 100+ years.
Page 61

Page 62

Option C: Redevelopment photos
Artist impression of phase 1 development showing potential entrance to
new development
Artist impression showing courtyard area for
residents on phase 1 development.
Page 62

Page 63

Option D: Hybrid
The works will involve:
•Demolishing some homes, keeping some of the existing homes
and building some new homes.
•This will require all the same steps which are listed in the both the
refurbishment options and in the redevelopment options.
•Common room may stay in existing location or may be able to
develop a new one.
Some pros and cons:
•Both refurbishing and demolishing/ redeveloping is disruptive to
tenants.
•Existing homes may wane in popularity in comparison to newer
ones with better layouts.
•Unknown at the moment which houses would be kept and
which would be demolished.
Page 63

Page 64

Option form:
Please tell us your house number:
Please tell us which option you’d like to
choose:
You may tick or cross one option.
Option A: Maintain current status
Option B: Refurbishment
Option C: Redevelopment
Option D: Hybrid (bit of both 2&3)
Comment box:
Please use this to tell us any thoughts you have
about the future of Willox Park.
Page 64

Page 65

Option form:
Please tell us your house number:
Please tell us which option you’d like to
choose:
You may tick or cross one option.
Option A: Maintain current status
Option B: Refurbishment
Option C: Redevelopment
Option D: Hybrid (bit of both 2&3)
Comment box:
Please use this to tell us any thoughts you have
about the future of Willox Park.
Page 65

Page 66

Housing Services Consultation Summary Sheet
Housing Service: Housing Strategy
Person responsible Emily Dorrian
Consultation  Start date: Friday 17 November 2023
End Date: Friday 12 January 2024
1. Title of consultation /
participation exercise
Willox Park Options appraisal
2. Aims and objectives The consultation aimed to gather the opinions of the
tenants who live in Willox Park regarding the options
appraisal exercise for their homes.  
The tenant’s options appraisal follows a period of
significant tenant engagement due to investigations
into damp and mould in the homes during which we
found that some homes were badly affected
meanwhile others were fine, but we are going to
keep an eye on all homes. 
Therefore, tenants were knowledgeable about the
need for options appraisal because it had become
apparent that remediation would be very expensive
and disruptive. 
The options appraisal aimed to understand if the
tenants thought remediation was worthwhile or if
they thought another option would be better.  We
presented them with four options in total; do nothing,
remediation, redevelopment, or hybrid.  
3. Invited to get involved:   
(e.g. all tenants, tenant from
the interested tenants
register, RTOs, staff)
We delivered tenants a printed in colour options
appraisal document setting out why were doing the
consultation and information about each option
including some pros and cons. 
We had three drop-in sessions in the common room
where a range of officers were available to answer
any queries tenants had.  We lettered tenants
between Christmas and new year to remind them of
the last one at the start of January.  
In addition, we phoned all tenants (or their families)
who had not yet engaged with us and asked them if
they had any questions, offered to go to their homes
to talk them through it and encouraged them to
attend the drop-in sessions.  
We also spoke to a number of tenants via email who
asked questions and we responded best we could.  
ITEM 10 -
APPENDIX 2
Page 66

Page 67

We attended the Willox Park Tenants Association
meetings so that we  
4. Methods used to
promote/invite stakeholders
to get involved? (e.g. letters,
posters, website)
• Options appraisal documents delivered to
each tenants
• Letters
• Drop in events
• Phone calls
• Emails
5. Who took part
(Actual number of individuals
and or number of tenant
organisations represented)
• 10 tenants or tenant representatives attended
in person events.
• 3 tenants were communicated via email
• 21 tenants or tenant representatives were
contacted by telephone
• 14 tenants voted.
6. Method(s) used to obtain
views? (e.g. focus/working
group, newsletter, survey)
Why ?
• Drop in events.
• Letters
• Phonecalls
• Attending TRA meetings
We were engaging with 25 tenants/ tenant
representatives so we wanted officers to feel
accessible so questions could be easily accessed,
and questions asked because it is complex
consultation, and all tenants would be impacted by
the result.  
The survey results were gathered in paper into a
sealed ballot box. 
7. What good practice or
minimum standards can you
evidence as part of your
consultation?
We can evidence clear documentation and multiple
channels of communication. 
8. Outcome of consultation? The recommendation in the committee paper was
the most popular one with tenants; redevelopment.
Page 67

Page 68

9.  How did the consultation
influence decision making?
Tenants voted for the four options and one option
was preferred and that is the option we are
recommending be taken forward. 
Tenants want to be involved going forward to shape
the mix of homes on the site so they will continue to
influence this project. 
10.  Are you able to demonstrate this?                                                 YES            NO
11.  How was feedback about the
consultation and final
decision given?
We will share the committee papers once they are
public and once a decision is made at the committee
then communicate this to tenants via letter,
demonstrating how they have shaped the outcome.  
Officers will also attend the next TRA and make our
contact details available so that questions can be
answered. 
12.  Was the eight week timescale observed?                                       YES            NO
If no please say why?  
13.  Was equal opportunities information collected?                              YES            NO
14.  Did you check with
participants that they were
happy with the opportunities
given to make their views
known and that they felt that
they were listened to and
acted upon?
We worked hard to give all tenants an opportunity to
participate and make their views known.   
We have not completed a post-consultation survey
or similar to ask if tenants were happy but will
consider doing this so we can continue to hone our
approach but they will continue to be involved as a
masterplan developed. 
What worked well, what didn’t work well – or any other comments you have.
Comments:  
The drop-in events worked well as did the printed-out options appraisal documents although
we did have to get a number re-printed because they had been lost or recycled. 
Due to the historic damp and mould issues some tenants weren’t sure if we were listening
but we have hopefully demonstrated that we are, and were, in the relaying of the findings of
the options appraisal consultation as clearly as we could. 
Page 68

Page 69

WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer - Resources 
Housing and Communities Committee: 28 February 2024
___________________________________________________________________
Subject: Housing Revenue Account Budgetary Control Report
to 31 October 2023 (Period 07)
1. Purpose
1.1 The purpose of the report is to provide members with an update on the
financial performance to 31 October 2023 (Period 07) of the HRA revenue
and capital budgets for 2023/24.
2. Recommendations
2.1 Members are asked to:
i) note the revenue analysis shows projected adverse variances of
£3.371m. However this will be offset by removing the £1.729m budgeted
contribution from revenue to capital (CFCR) and using £1.642m of the
HRA reserves resulting in a net revenue break even position ; and
ii) note the net projected annual position in relation to the capital plan is
highlighting an in-year adverse variance of £61.826m (49.5%) which is
made up of re-profiling of £66.481m (53.2%) and overspend of £4.656m
(0.4%) as detailed in Appendix 4.
3. Background
Revenue
3.1 At the meeting of West Dunbartonshire Council on 01 March 2023, Members
agreed the revenue estimates for 2023/24 and a total budget of £49.643m.
Capital
3.2 At the meeting of Council on 01 March 2023, Members also agreed the
updated Capital Plan for 2023/24 which has been augmented by re-profiling
and from 2022/23 and budget adjustment to produce a total planned spend for
2023/24 of £124.846m.
ITEM 11
Page 69

Page 70

4. Main Issues
Revenue
4.1  The budgetary position for HRA Revenue is provided in Appendix 1 with
information on projected variances valued at more than £0.050m being
provided as Appendix 2.
4.2 The HRA revenue account has come under severe financial pressure in
2023/24. In order to achieve a break even position in 2023/24 it is forecast
that there will need to be a transfer of £1.642m from the available £2.634M
HRA reserves which will leave £0.992m in reserves. Note the recommended
prudential reserves for the HRA is £0.984m.
4.3 The main pressure areas are repairs and loan charges interest payments.
Repairs overspend has arisen due to several factors including inflationary
increases in materials and labour and large numbers of voids at start of
financial year. Void numbers have now significantly reduced therefore it is
expected costs will start to reduce in this area in the coming years. Also the
efficiency of the work carried will continue to be assessed with a view to
minimising the costs of repairs through improved productivity. The recent large
increases in interest rates has led to a substantial increase in interest
payments for loans outstanding.
Capital
4.4 The HRA capital summary position is shown in Appendix 3. Information on
projects that are highlighted as being within the Red category is provided in
Appendix 4 and Appendix 5 provides information on the projects at Green.  A
summary of anticipated resources is shown in Appendix 6. The analysis
shows that there is currently a projected in-year adverse variance of
£61.826m (49.5%), which is made up of re-profiling of £66.481m (53.2%) and
overspend of £4.656m (0.4%).
4.5 From the analysis within the appendices it can be seen that the main projects
with forecast material re- profiling being required are:
Project Name Re-profiling
(£m)
Affordable Housing Supply Programme 63.432
EESH compliance work 1.746
Reasons/ factors for needing re – profiling in respect of each new build site for
slippage are explained in Appendix 4, project 8
Page 70

Page 71

5. People Implications
5.1 There are no people implications.
6. Financial and Procurement Implications
6.1 Other than the financial position noted above, there are no financial
implications of the budgetary control report. There are no procurement
implications arising from this report.
7. Risk Analysis
7.1 The main financial risks to the ongoing financial position relate to unforeseen
cost being identified between now and the end of the financial year.  This can
affect all service areas.
8. Equalities Impact Assessment (EIA)
8.1 The report is for noting and therefore no Equalities Impact Assessment was
completed for this report.
9. Consultation
9.1 The views of both Housing management and Legal services have been
requested on this report and both have advised there are neither any issues
nor concerns with the proposal.
10. Strategic Assessment
10.1 Proper budgetary control and sound financial practice are cornerstones of
good governance and support Council and officers to pursue the five strategic
priorities of the Council’s Strategic Plan. This report forms part of the financial
governance of the Council. This report is for noting and, therefore, does not
directly affect any of the strategic priorities.
Laurence Slavin
Chief Officer – Resources
Date: 18 January 2024
___________________________________________________________________
Person to Contact: Janice Rainey - Business Unit Finance Partner (HEED),
16 Church Street, Dumbarton, G82 1QL,     
Telephone: 01389 737704, e-mail janice.rainey@west-
dunbarton.gov.uk
Appendices: Appendix 1 - Budgetary Position (Revenue)
Page 71

Page 72

Appendix 2 - Variance analysis (Revenue) 
Appendix 3 - Budgetary Position (Capital)
Appendix 4 - Variance analysis Red (Capital)
Appendix 5 - Variance analysis Green Projects (Capital)
Appendix 6 - Resources (Capital)
Appendix 7 - Analysis of Affordable Housing Supply 
Programme (Capital)
Background Papers: None
Wards Affected: All
Page 72

Page 73

WEST DUNBARTONSHIRE COUNCIL ITEM 11 - APPENDIX 1
HRA REVENUE BUDGETARY CONTROL 2023/24
PERIOD END DATE
Subjective Summary
Total Budget
2023/24 
£000
Spend to
Date
2023/24 
£000
Forecast
Spend
£000
Annual RAG
Status
Employee Costs 7,669 3,922 7,955 286 4% 
Property Costs 2,377 1,288 2,217 (160) -7% 
Transport Costs 142 55 141 (1) 0% 
Supplies, Services And Admin 389 119 397 8 2% 
Support Services 2,720 1,564 2,681 (39) -1% 
Other Expenditure 534 465 585 51 10% 
Repairs & Maintenance 16,257 7,675 16,147 (110) -1% 
Bad Debt Provision 1,089 52 960 (129) -12% 
Void Loss (Council Tax/Lost Rents) 1,261 958 1,475 214 17% 
Loan Charges 15,476 11,049 18,829 3,353 22% 
CFCR 1,729 0 0 (1,729) -100% 
Total Expenditure 49,643 27,147 51,387 1,744 4% 
House Rents 47,729 26,861 47,652 77 0% 
Lockup Rents 217 116 202 15 7% 
Factoring/Insurance Charges 1,434 1,494 1,494 (60) -4% 
Other rents 117 59 120 (3) -3% 
Interest on Revenue Balance 30 0 146 (116) -387% 
Transfer from Reserves 0 0 1,642 (1,642) 0% 
Miscellaneous income 116 37 131 (15) -13% 
Total Income 49,643 28,567 51,387 (1,744) -4% 
Net Expenditure 0 (1,420) (0) (0) 
Forecast Variance 2023/24
£000               %
31/10/2023
Page 73

Page 74

WEST DUNBARTONSHIRE COUNCIL APPENDIX 2
HRA REVENUE BUDGETARY CONTROL 2023/24
ANALYSIS FOR VARIANCES OVER £50,000
MONTH END DATE 31/10/2023
PERIOD 7
Budget Forecast
Spend
RAG
Status
£000 £000 £000 %
EMPLOYEE COSTS 7,669 7,955 286 4% 
Main Issues
Mitigating Action
Anticipated Outcome
Budget Forecast
Spend
RAG
Status
£000 £000 £000 %
PROPERTY COSTS 2,377 2,217 (160) -7% 
Main Issues
Mitigating Action No mitigating action is required.
Anticipated Outcome
Budget Forecast
Spend
RAG
Status
£000 £000 £000 %
SUPPORT SERVICES 2,720 2,681 (39) -1% 
Main Issues
Mitigating Action No mitigating action is required.
Anticipated Outcome
Budget Forecast
Spend
RAG
Status
£000 £000 £000 %
REPAIRS & MAINTENANCE 16,257 16,147 (110) -1% 
Main Issues
Mitigating Action
Anticipated Outcome
Service Description
Budget Details Variance Analysis
Subjective Analysis forecast Variance
Budget Details Variance Analysis
Subjective Analysis forecast Variance
Budget Details Variance Analysis
Subjective Analysis forecast Variance
Subjective Description
This budget covers all employees charged directly to the HRA including caretakers.
Variance Narrative
This adverse variance is mainly due to additional posts being approved, after time of budget
setting to meet the demands of the service. In addition to this , the pay award for 2324 is
expected to be higher than the budgeted 4%.
A favourable variance is expected with the assumption that the 2023/24 forecast outturn for
support services is expected  to be in line with the 2022/23 outturn adjusted for pay uplifts
etc. This charge is calculated each year end based on HRA's percentage usage of the total
cost of WDC support services. The 2023/24 HRA budget was set before this 2022/23
outturn was known so was based on 2021/22 charge which was higher.
Managers will continue to consider ways to keep staffing costs down including considering
each vacancy as it arises re need / urgency to fill.
High volume of jobs and inflationary increases in materials and labour have resulted in the
budget for jobbing repairs being insufficient to meet current demand. However this had been
more than offset by an underspend in the electrical installation inspection reports ( EICR)
budget due to the contract only being awarded half way through the year.
Variance Narrative
Variance Narrative
This budget covers all repair and maintenance expenditure to houses and lockups
Subjective Description
A year end underspend is anticipated
A year end small underspend is anticipated
There are uncontrollable costs, such as materials and inflation as well as the demand for
repairs which continues to increase.  However as we continue to progress with the building
services improvement plan, we expect costs to reduce particularly in relation to void houses.
The later than anticipated start on EICR work  at present covers these costs but we need to
continue to ensure the costs remain contained.
Budget Details
A year end overspend is anticipated
This budget covers central support recharges to the HRA
Variance Analysis
Subjective Analysis forecast Variance
Subjective Description
This budget covers electricity, gas, rates, rents, cleaning  and insurance costs.
Variance Narrative
A favourable variance is expected due to the assumption that office accommodation and
utility costs will be similar to last year which is lower than anticipated at time of budget
setting, resulting in a favourable variance.
A year end underspend is anticipated
Page 74

Page 75

WEST DUNBARTONSHIRE COUNCIL
ITEM 11 - APPENDIX 2HRA REVENUE BUDGETARY CONTROL 2023/24
ANALYSIS FOR VARIANCES OVER £50,000
MONTH END DATE 31/10/2023
PERIOD 7
Budget Forecast
Spend
RAG
Status
£000 £000 £000 %
BAD DEBT PROVISION 1,089 960 (129) -12% 
Main Issues
Mitigating Action No mitigating action is required.
Anticipated Outcome
Budget Forecast
Spend
RAG
Status
£000 £000 £000 %
VOID LOSS 1,261 1,475 214 17% 
Main Issues
Mitigating Action
Anticipated Outcome
Budget Forecast
Spend
RAG
Status
£000 £000 £000 %
LOAN CHARGES 15,476 18,829 3,353 22% 
Main Issues
Mitigating Action
Anticipated Outcome
Budget Forecast
Spend
RAG
Status
£000 £000 £000 %
CFCR 1,729 0 (1,729) -100% 
Main Issues
Mitigating Action
Anticipated Outcome
Budget Forecast
Spend
RAG
Status
£000 £000 £000 %
Rents 47,729 47,652 77 0% 
Main Issues
Mitigating Action
Anticipated Outcome
Variance Narrative
The main reason for the projected adverse variance relates to the number of void properties
being higher than expected at time of budget setting.  The budget was set on the
assumption that backlogs following COVID delays  in getting voids turned around would be
resolved  however the  numbers continued to be high at the beginning of this financial year.
They have now lowered considerably
Budget Details Variance Analysis
Service Description
Budget Details Variance Analysis
Subjective Analysis forecast Variance
Service Description
This budget allows for the provision for bad and doubtful debts to be maintained at an appropriate level
Subjective Analysis forecast Variance
A year end underspend is anticipated
Variance Narrative
The Bad Debt Provision expected to be required for 2023/24 is less than estimated at time
of budget setting, resulting in a favourable variance. This assumes that the provision
required in 2023/24  will be similar to the 2022/23 provision.
A year end underspend is anticipated
Service Description
This budget covers the contribution from revenue to Capital
Variance Narrative
In order to offset the cost pressures on the revenue HRA in 2023/24 , it is anticipated that
there will be no contribution to capital spend in 2023/24.
None available
Budget Details Variance Analysis
Subjective Analysis forecast Variance
A year end overspend is anticipated
Subjective Analysis forecast Variance
Service Description
Loan Charges is made up of repayments of principle sums, and the payments of interest and expenses
A void working group has been reviewing the issues and have been implementing actions
and working with Housing Maintenance managers to improve the situation and it is expected
that the void figures will continue to decrease  over the next few months.
This budget covers the rents lost on void houses and lockups and the cost of council tax on void properties.
Variance Narrative
The main reason for this variance is the due to interest payments being higher than
anticipated at time of budget setting. The recent increase in bank interest rates has to led to
a significant increase in loan interest payments.
None available
Budget Details Variance Analysis
A year end overspend is anticipated
Service Description
This budget covers the rental income due from tenants
Variance Narrative
Timing of buy backs and new builds being ready for letting is slightly behind that budgeted
Turn around of buy backs continues to be monitored to maximise income
Budget Details Variance Analysis
Subjective Analysis forecast Variance
Small adverse variance
Budget Details Variance Analysis
Page 75

Page 76

WEST DUNBARTONSHIRE COUNCIL APPENDIX 2
HRA REVENUE BUDGETARY CONTROL 2023/24
ANALYSIS FOR VARIANCES OVER £50,000
MONTH END DATE 31/10/2023
PERIOD 7
Budget Forecast
Spend
RAG
Status
£000 £000 £000 %
Factoring/Insurance Charges 1,434 1,494 (60) -4% 
Main Issues
Mitigating Action
Anticipated Outcome
Budget Forecast
Spend
RAG
Status
£000 £000 £000 %
Interest on Revenue Balance 30 146 (116) -387% 
Main Issues
Mitigating Action
Anticipated Outcome
Budget Forecast
Spend
RAG
Status
£000 £000 £000 %
Transfer from Reserves 0 1,642 (1,642) 0% 
Main Issues
Mitigating Action
Anticipated Outcome
Service Description
Income received from insurance and factoring
Variance Narrative
10% increases were applied to fees 2324 in line with the councils sales fees charges
increase approved in March 2023. The budget only assumed 4% increase
Subjective Analysis forecast Variance
Service Description
Income received from insurance and factoring
Variance Narrative
This income is dependant on bank interest rates . The revised forecast takes account of the
high interest rate  rises in past year
None required
Small favourable variance
Budget Details Variance Analysis
Subjective Analysis forecast Variance
If costs reduce below the forecast at P7 then the call on reserves can be reduced
Reduction in reserves
Service Description
Utilisation of reserves to fund forecast overspend
Variance Narrative
In order to achieve a break even position within the HRA , it is necessary to draw down the
shortfall from the current HRA reserves . The current reserve is £2.634M therefore this will
reduce reserves to £0.992M which is just above the prudential reserve target of £0.984M
None required
Small favourable variance
Budget Details Variance Analysis
Subjective Analysis forecast Variance
Page 76

Page 77

ITEM 11 -
APPENDIX 3
WEST DUNBARTONSHIRE COUNCIL
HRA CAPITAL PROGRAMME
OVERALL PROGRAMME SUMMARY
MONTH END DATE
PERIOD 7
Spend to
Date Spend to Date
£000 £000
Red
10 33.3% 21,667 74.2% 10 33.3% 21,667 74.2%
Green
20 66.7% 7,516 25.8% 20 66.7% 7,519 25.8%
30 100% 29,183 100% 30 100% 29,186 100%
Budget Spend to
Date
Forecast
Spend Forecast Variance Budget Spend to Date Forecast
Spend
Forecast
Variance Reprofiled Over/
(Under)
£000 £000 £000 £000 £000 £000 £000 £000 £000 £000
255,713 21,667 263,181 7,468 100,479 21,667 42,526 (57,953) (66,243) 8,290
111,016 7,516 107,381 (3,634) 24,367 7,519 20,494 (3,873) (238) (3,634)
366,729 29,183 370,562 3,834 124,846 29,186 63,020 (61,826) (66,481) 4,656
366,729 29,183 370,562 (3,834) 124,846 29,186 63,020 61,826
0 0 0 0 0 0 0 0
TOTAL RESOURCES
NET EXPENDITURE
Projects are forecast to be overspent and/or significant delay to
completion
Green
Projects are on target both in relation to overall budget and the forecast
stages in the project life cycle and no issues are anticipated at this time
TOTAL EXPENDITURE
Project Status Analysis
Project Life Financials Current Year Financials
Red
Projects are on target both in relation to overall budget and the forecast
stages in the project life cycle and no issues are anticipated at this time
31 October 2023
Project Status Analysis
Project Life Status Analysis Current Year Project Status Analysis
Number of
Projects at
RAG Status
% Projects at
RAG Status
% Project Spend at
RAG Status
Number of
Projects at
RAG Status
% Projects at
RAG Status
% Project
Spend at RAG
Status
Red
Projects are forecast to be overspent and/or experience material delay
to completion
Green
Page 77

Page 78

WEST DUNBARTONSHIRE COUNCIL ITEM 11 -
APPENDIX 4
HRA CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
MONTH END DATE
PERIOD 7
Budget Forecast Spend
£000 £000 % £000 £000 %
1
Project Life Financials 3,216 269 8% 3,216 0 0%
Current Year Financials 600 269 45% 655 55 9%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
2
Project Life Financials 2,814 1,536 55% 5,409 2,595 92%
Current Year Financials 525 1,536 293% 3,120 2,595 494%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
3
Project Life Financials 10,000 0 0% 10,000 0 0%
Current Year Financials 2,000 0 0% 1,000 (1,000) -50%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
4
Project Life Financials 96 0 0% 96 0 0%
Current Year Financials 96 0 0% 0 (96) -100%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
31 October 2023
Budget Details Project Life Financials
Spend to Date Variance
Special needs adaptations
Officers in discussion to identify possible mitigation.
Anticipated Outcome
Project to complete over budget.
Capitalised minor works
Gypsy/ Traveller Site improvements 
Planned End Date  Forecast End Date 
Adaptations to Housing for Special Needs 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Budget is expected to overspend due to costs and demand for budget being higher than anticipated at time of budget setting.
Mitigating Action
Main Issues / Reason for Variance
Budget is expected to overspend due to costs and demand for budget being higher than anticipated at time of budget setting.
Mitigating Action
Officers in discussion to identify possible mitigation.
Anticipated Outcome
Project to complete over budget.
Environmental Sensors Programme 
Environmental sensors programme, funded by enhanced housing investment programme 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Project introduced as part of the enhanced capital programme, with aim to install an environmental sensor in every Council owned property. 
Council appointed supply and fit contractor at the Tendering Committee in October 2023 and the pre start meeting has been scheduled,
with start before end of 2023 expected.
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Airport Noise
Noise Insulation Project 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
West Dunbartonshire Council are no longer eligible for match funding from Glasgow Airport Association, following assessment of properties
within West Dunbartonshire.  West Dunbartonshire is not deemed to have any commercial or residential properties that fall within the scope
of the scheme to be eligible for match funding, and budget therefore has been reduced from £0.192m to £0.096m.  The remaining budget
will be used to develop a programme of works following engagement with an aircraft noise consultant, who will work with Officers to make
adaptations to previously identified properties.  The budget will be reprofiled as required.
Mitigating Action
None required
Anticipated Outcome
Full budget spend in future year
Page 78

Page 79

WEST DUNBARTONSHIRE COUNCIL APPENDIX 4
HRA CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
MONTH END DATE
PERIOD 7
Budget Forecast Spend
£000 £000 % £000 £000 %
31 October 2023
Budget Details Project Life Financials
Spend to Date Variance
5
Project Life Financials 32,986 2,603 8% 32,986 0 0%
Current Year Financials 6,146 2,603 42% 4,400 (1,746) -28%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
6
Project Life Financials 242 8 3% 242 0 0%
Current Year Financials 45 8 18% 22 (23) -51%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
7
Project Life Financials 9,872 1,176 12% 10,332 460 5%
Current Year Financials 1,840 1,176 64% 2,300 460 25%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
Targeted SHQS /EESSH compliance works
This budget is to focus on work required to maintain the SHQS compliance and energy efficiency  with
WDC housing stock.   
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Works progressing well, however some rephasing may be required to 24/25.
Mitigating Action
None available at this time
Anticipated Outcome
Full budget spend over project life
Secure entry component renewals
This budget is to focus on secure door entry component renewals as identified and recommended from
the housing stock condition survey and appropriate council officer referrals. 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
This programme always presents challenges with owner liaison and reaching agreements to install door entry where none exists, this
contributes directly to achieving SHQS compliance for this element.  Any underspend in current year will be carried forward to future years.
Mitigating Action
Officers continue to liaise with owners to encourage agreement for install.
Anticipated Outcome
It is likely that this will not to meet full spend in the current year despite best efforts but officers will endeavour to gain owners agreement.
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Demand has exceeded expectations.  Due to the nature of this project (ensuring heating and hot water availbility) there is no option for a
conscious reduction of installs.
Mitigating Action
Whilst demand is leading spend, officers will work to minimise any budget overspend.
Heating improvement works
Carry out works to renew inefficient boilers/full systems as identified from the stock condition survey and
renewal of obsolete/damaged boilers. 
Anticipated Outcome
Full budget spend, likely overspend.
Page 79

Page 80

WEST DUNBARTONSHIRE COUNCIL APPENDIX 4
HRA CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
MONTH END DATE
PERIOD 7
Budget Forecast Spend
£000 £000 % £000 £000 %
31 October 2023
Budget Details Project Life Financials
Spend to Date Variance
8
Project Life Financials 13,900 4,245 31% 18,235 4,335 31%
Current Year Financials 3,000 4,245 142% 7,335 4,335 144%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
9
Project Life Financials 5,454 1,447 27% 5,454 0 0%
Current Year Financials 1,017 1,447 142% 1,840 823 81%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
10
Project Life Financials 177,132 10,382 6% 177,209 77 0%
Current Year Financials 85,209 10,382 12% 21,854 (63,355) -74%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
Variance to
22/23 Budget
Site/ Spend £000  Overspend   Underspend  Reprofiling
Haldane Primary School 77 77
Clydebank East (19,566) (19,566)
Queens Quay Site C (7,425) (7,425)
Pappert (10,193) (10,193)
Bank Street (3,508) (3,508)
Clydebank Health Centre (3,858) (3,858)
Variance Category
Void house strategy programme
Spend on Void Properties to bring them up to letting standard 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Void works to continue into 23/24 to bring void properties up to a lettable standard.  Based on current projections using updated anticipated
numbers it looks likely that the budget will be insufficient , resulting in a projected overspend in 23/24. 
Mitigating Action
This is a significant priority and we continue to make positive progress against internal plan and targets to reduce the number of void
houses.  We expect this to continue to reduce.
Anticipated Outcome
The cost of bringing void properties up to lettable standard will result in a overspend.
Main Issues / Reason for Variance
Work progressing well and ahead of spend targets, at this pace likely to exceed budget to meet tenant demand. Officers currenty working to
manage workload and prioritise to minimise overspend.
Mitigating Action
Officers currenty working to manage workload and prioritise to minimise overspend.
Anticipated Outcome
Full budget spend, likley to overspend.
Environmental renewal works, paths/fences/walls/parking area's
Environmental renewal works, paths/fences/walls/parking areas 
Planned End Date  Forecast End Date 
Forecast End Date
Main Issues / Reason for Variance
The £63.355m variance is made up of £0.077m overspend, and reprofiling of £63.432m into 2024/25 onwards . Summary of reprofiled sites
together with site specific updates as follows:-
Affordable Supply Programme
Affordable Housing Supply Programme 
Planned End Date
Page 80

Page 81

WEST DUNBARTONSHIRE COUNCIL APPENDIX 4
HRA CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
MONTH END DATE
PERIOD 7
Budget Forecast Spend
£000 £000 % £000 £000 %
31 October 2023
Budget Details Project Life Financials
Spend to Date Variance
Willox Park Phase1 (5,022) (5,022)
Mount Pleasant (8,467) (8,467)
Gap sites (5,393) (5,393)
TOTAL OF ALL PROJECTS (63,355) 77 0 (63,432)
TOTAL OF RED PROJECTS
Project Life Financials 255,713 21,667 8% 263,181 7,468 3%
Current Year Financials 100,479 21,667 22% 42,526 (57,953) -58%
Haldane - Site complete, retention paid in 2023/24
Clydebank Health Centre - Demolitions planned for 2023/24, Design and Build development and contractors will be procured also  this year,
however physical site start will not be achieved until 2024/25.
Mount Pleasant -19 units to be completed on site by March 2025.  Demolition now complete and contractor award appointment made in
September.  £0.250m estimated to be spent this financial year with remaining current year budget to be reprofiled to 2024/25 for site start in
March 2024.
Bonhill Gap Site - Spend reprofiled from 2023/24 to 2024/25 as design team procurement was delayed.  Projected spend in 2023/24 will be
design and statutory fees.
Mitigating Action
Staff will work closely with all stakeholders to try and ensure timely resolutions of issues as they arise.
Anticipated Outcome
Project will still complete and will meet revised spend profiles .
Clydebank East - 88 units to be completed by March 2025.  Project delivery reprofiled due to extensive groundworks. Project on site and
programme adhering to amended delivery plan.
Queens Quay Site B - 29 units completed on site in 2022/23.  Project completed, retention figure included and associated costs in terms
with road construction.
Queens Quay Site C - 20 units to be completed on site, however no further progress due to land owner issue.  At the time it is assumed
approximately £2m will be spent on land purchase, but this will be reviewed in early 2024, with the remaining current year budget to be
reprofiled to 2024/25.
Pappert - 26 units to be completed on site by April 2025.  Planning delay negated anticipated spend profile for 2023/24, however Planning
approval received 20 September 2023 and site start in early 2024 planned.
Bank Street - 22 units to be completed on site.  Spend reprofiled from 2023/24 to 2024/25 as design team procurement was delayed. 
Projected spend in 2023/24 will be design and statutory fees.
Willox Park Phase1 - 17 units to be completed on site.   Spend reprofiled from 2023/24 to 2024/25 as design team procurement was
delayed.  Projected spend in 2023/24 will be design and statutory fees.
Page 81

Page 82

WEST DUNBARTONSHIRE COUNCIL ITEM 11 -
APPENDIX 5
HRA CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
MONTH END DATE
PERIOD 7
Budget Forecast Spend
£000 £000 % £000 £000 %
1
Project Life Financials 1,493 15 1% 1,493 0 0%
Current Year Financials 529 18 3% 529 0 0%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
2
Project Life Financials 750 0 0% 750 0 0%
Current Year Financials 250 0 0% 250 0 0%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-25
3
Project Life Financials 203 0 0% 203 0 0%
Current Year Financials 116 0 0% 116 0 0%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
4
Project Life Financials 209 0 0% 209 0 0%
Current Year Financials 71 0 0% 71 0 0%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
Anticipated Outcome
Full budget spend
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No Issues, programme being progressed andanticipated to meet full spend and targets.
Mitigating Action
None required
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Gypsy Travellers Site
Gypsy/ Traveller Site improvements
QL Development
This budget relates to the costs associated with the development of the Integrated Housing
Management System 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No issues. Development of QL system to carry on through 23/24.
Main Issues / Reason for Variance
Works to progress as part of enhanced capital programme for 23/24 and to be led by Council CCTV team.
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Housing CCTV Installation Programme
CCTV Installation Programme, funded by enhanced housing investment programme 
Planned End Date  Forecast End Date
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Better Homes Priority Budget
Priority projects as prioritised by the Better Homes Group 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
A number of priority initiatives, supported by the Better Homes Project Board,  are being investigated and are envisaged to have a
positive impact on the current council housing stock and budget, with works expected to progress in 23/24.
31 October 2023
Budget Details Project Life Financials
Spend to Date Variance
Page 82

Page 83

WEST DUNBARTONSHIRE COUNCIL APPENDIX 5
HRA CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
MONTH END DATE
PERIOD 7
Budget Forecast Spend
£000 £000 % £000 £000 %
31 October 2023
Budget Details Project Life Financials
Spend to Date Variance
5
Project Life Financials 17 0 0% 17 0 0%
Current Year Financials 17 0 0% 17 0 0%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
6
Project Life Financials 36 36 99% 36 (1) -1%
Current Year Financials 36 36 99% 36 (1) -1%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
7
Project Life Financials 19,286 1,466 8% 16,107 (3,179) -16%
Current Year Financials 5,679 1,466 26% 2,500 (3,179) -56%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
8
Project Life Financials 17,937 2,111 12% 17,937 0 0%
Current Year Financials 4,547 2,111 46% 4,250 (297) -7%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
Anticipated Outcome
Full budget spend
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Project is progressing well in 23/24, however may incur an underspendpend in the current year.
Mitigating Action
None required at this time
Mitigating Action
None required
Anticipated Outcome
Scheduled works to complete under current year budget.
Doors/window component renewals
Doors/Windows Component Renewals
Roof Coverings
Building external component renewals, roofs/chimneys/flashings/fascias/gutters/svp 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Works expected to meet revised timescales which will be less than current year budget and therefore project will report an in year
underspend.
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Redployable CCTV Cameras
Purchase of 5 redeployable CCTV cameras for Housing use 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Works for this project complete in April 23/24.
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Community Safety Projects
Community Safety Projects 
Planned End Date  Forecast End Date
Page 83

Page 84

WEST DUNBARTONSHIRE COUNCIL APPENDIX 5
HRA CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
MONTH END DATE
PERIOD 7
Budget Forecast Spend
£000 £000 % £000 £000 %
31 October 2023
Budget Details Project Life Financials
Spend to Date Variance
9
Project Life Financials 6,400 0 0% 6,400 0 0%
Current Year Financials 0 0 #DIV/0! 0 0 #DIV/0!
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
10
Project Life Financials 242 30 12% 242 0 0%
Current Year Financials 45 30 65% 42 (3) -7%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
11
Project Life Financials 606 14 2% 606 0 0%
Current Year Financials 113 14 12% 110 (3) -3%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
12
Project Life Financials 303 0 0% 303 0 0%
Current Year Financials 57 0 1% 57 0 0%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
Anticipated Outcome
Full budget spend
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.
Mitigating Action
None required
Energy improvements/energy efficiency works
Energy improvements/ efficiency works (e.g. loft insulation, pipe/tank insulation, draught
exclusion)
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets, with possible underspend to be carried forward to future years.
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Statutory/regulatory compliance works (lifts/electrical/legionnella/fire etc)
This budget will be used to upgrade / replace components / installations in order to comply with
the relevant standards / legislation / health and safety in relation to housing stock. 
Planned End Date  Forecast End Date
Mitigating Action
None required
Anticipated Outcome
Full budget spend
External stores/garages/bin stores/drainage component renewals
This budget is to focus on external stores/garages/bin stores etc. component renewals as
identified and recommended from the housing stock condition survey. 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets, with possible underspend to be carried forward to future years.
Main Issues / Reason for Variance
Works expected to commence next financial year, therefore no Issues to report at this time.  Project anticipated to meet full spend
and targets.
Mitigating Action
None required
Anticipated Outcome
Full budget spend
District Heating 
District Heating Connection to the Dalmuir and Littleholm multi storey flats 
Planned End Date  Forecast End Date
Page 84

Page 85

WEST DUNBARTONSHIRE COUNCIL APPENDIX 5
HRA CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
MONTH END DATE
PERIOD 7
Budget Forecast Spend
£000 £000 % £000 £000 %
31 October 2023
Budget Details Project Life Financials
Spend to Date Variance
13
Project Life Financials 17,775 1,793 10% 17,775 0 0%
Current Year Financials 3,235 1,793 55% 3,300 65 2%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
14
Project Life Financials 103 0 0% 103 0 0%
Current Year Financials 103 0 0% 103 0 0%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
15
Project Life Financials 500 0 0% 500 0 0%
Current Year Financials 100 0 0% 100 0 0%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
16
Project Life Financials 3,835 117 3% 3,380 (455) -12%
Current Year Financials 877 117 13% 422 (455) -52%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
Mitigating Action
None required
Anticipated Outcome
Scheduled works to complete under current year budget.
Defective structures/component renewals
Defective structures 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Works expected to meet revised timescales which will be less than current year budget and therefore project will report an in year
underspend.
Main Issues / Reason for Variance
Contingent budget held for unplanned spend.
Mitigating Action
None required
Anticipated Outcome
Spend as required
Contingencies
This is a contingent budget for unforeseen matters which may arise during the year. 
Planned End Date  Forecast End Date
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Improvement works (Risk St)
Risk Street Over clad 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.
Main Issues / Reason for Variance
Pace of installations are ahead of targets as increased budget was anticipated. Officers will work to manage outturn to revised
budget and targets with likelihood of exceeding budget as demand and cost is higher than projected.
Mitigating Action
Officers will work to minimise any overspend whilst being mindful of tenant demand.
Anticipated Outcome
Full budget spend, possibility of overspend.
Modern facilities and services
New Kitchens, Bathrooms and Showers 
Planned End Date  Forecast End Date
Page 85

Page 86

WEST DUNBARTONSHIRE COUNCIL APPENDIX 5
HRA CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
MONTH END DATE
PERIOD 7
Budget Forecast Spend
£000 £000 % £000 £000 %
31 October 2023
Budget Details Project Life Financials
Spend to Date Variance
17
Project Life Financials 1,212 38 3% 1,212 0 0%
Current Year Financials 226 38 17% 226 0 0%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
18
Project Life Financials 5,050 4 0% 5,050 0 0%
Current Year Financials 1,300 4 0% 1,300 0 0%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
19
Project Life Financials 21,073 1,892 9% 21,073 0 0%
Current Year Financials 4,435 1,892 43% 4,435 0 0%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
20
Project Life Financials 13,984 0 0% 13,984 0 0%
Current Year Financials 2,629 0 0% 2,629 0 0%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
TOTAL OF RED PROJECTS
Project Life Financials 111,016 7,516 7% 107,381 (3,635) -3%
Current Year Financials 24,367 7,519 31% 20,494 (3,873) -16%
Main Issues / Reason for Variance
No Issues, budget for salaries and support
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Salaries/central support/offices
Allocation of costs from other WDC services who support the HRA capital programme 
Planned End Date  Forecast End Date
Anticipated Outcome
Budget spend anticipated, should criteria be met.
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
The main objective of the Buy Back Scheme is to bring former council properties that were sold through the RTB scheme, back
into council use.  These properties must assist the council with reducing housing need on the waiting list and where appropriate
assist with external capital works.  From 23/24, over 5 years, the buy back back scheme is benefiting from an additional £2m
investment each year, included in this revised budget, totaling £10m over 5 years, to futher reduce the waiting list.  The progress
will be monitored and reported as the financial year progresses.
Mitigating Action
None required.
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Buy Backs
This is a budget to undertake specific projects that will deliver housing policies/strategies,
example: Ex local authority and mortgage to rent buy-back scheme
Multi Story Flats  ( including Fire Risk Assessment Works)
High Rise Fire Safety Measures 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No Issues, anticipated to meet spend and revised targets.
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Asbestos management works
This budget is to fund work associated with the management of current asbestos legislation and 
Planned End Date  Forecast End Date
Page 86

Page 87

ITEM 11 -
APPENDIX 6
WEST DUNBARTONSHIRE COUNCIL
HRA CAPITAL PROGRAMME
ANALYSIS OF RESOURCES
MONTH END DATE
PERIOD 7
Budget Forecast Spend
£000 £000 % £000 £000 %
1
Project Life Financials (46,875) (585) 1% (46,875) 0 0%
Current Year Financials (28,055) (585) 2% (7,442) 20,613 -73%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
2
Project Life Financials (8,646) (432) 5% (6,917) 1,729 -20%
Current Year Financials (1,729) (432) 25% 0 1,729 -100%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
3
Project Life Financials (311,208) (28,323) 9% (271,723) 39,485 -13%
Current Year Financials (94,267) (28,323) 30% (55,577) 38,690 -41%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
TOTAL RESOURCES
Project Life Financials (366,729) (29,357) 8% (325,516) 41,213 -11%
Current Year Financials (124,051) (29,357) 24% (63,020) 61,031 -49%
Prudential borrowing incurred as required
None required
Anticipated Outcome
Income to Capital
Prudential Borrowing
Prudential borrowing is long term borrowing from financial institutions that has been approved
for the purposes of funding capital expenditure
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Prudential borrowing is impacted by programme delivery.
Mitigating Action
None available at this time.
Anticipated Outcome
Mitigating Action
Income due to be received in line with spend incurred.
Mitigating Action
None required
Anticipated Outcome
Income due to be received
CFCR
This is capital spend which is funded by revenue budgets
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Contribution to Capital from Revenue in 23/24
Main Issues / Reason for Variance
31 October 2023
Budget Details Project Life Financials
Spend to Date Variance
New Build Grant
Grant to facilitate the building of new build housing 
Planned End Date  Forecast End Date
Page 87

Page 88

WEST DUNBARTONSHIRE COUNCIL
ITEM 11 -
APPENDIX 7
HRA CAPITAL PROGRAMME
ANALYSIS OF AFFORDABLE HOUSING SUPPLY PROGRAMME
MONTH END DATE
PERIOD 7
Budget Spend to Date Forecast Spend
£000 £000 £000 £000 %
RAG
Status
Haldane Primary School - 77 77 77 #DIV/0! 
Clydebank East 37,992 9,190 37,992 - 0% 
Queens Quay Site B 660 0 660 - 0% 
Queens Quay Site C 25,175 - 25,175 - 0% 
Pappert 13,276 196 13,276 - 0% 
Bank Street 5,751 2 5,751 - 0% 
Clydebank Health Centre 11,016 601 11,016 - 0% 
Willox Park Phase1 6,185 84 6,185 - 0% 
Willox Park Phase2 7,500 - 7,500 - 0% 
Mount Pleasant 8,717 183 8,717 - 0% 
Silverton 2,590 27 2,590 - 0% 
Gap sites
Gap sites budget remaining 9,182 - 9,182 - 0% 
Bonhill Gap Site - all Bonhill Sites 245 0 245 - 0% 
Clydebank Gap Sites ( prev Lilac Avenue) - unallocated 13,622 - 13,622 - 0% 
Clydebank Gap Sites ( prev Lilac Avenue) - 7-9 Gilmour Avenue 50 13 50 - 0% 
Clydebank Gap Sites ( prev Lilac Avenue) - Queen Mary Avenue 50 9 50 - 0% 
Future New build sites 27,000 - 27,000 - 0% 
28 Bridge Street Alexandria 23 - 23 - 0% 
Fees, Staffing Costs, contingency 8,097 - 8,097 - 0% 
Total Expenditure 177,132 10,382 177,209 77 
31 October 2023
Site
Project Life Financials
Variance
Page 88

Page 89

WEST DUNBARTONSHIRE COUNCIL
Report by Chief Officer – Resources
Housing and Communities Committee: 28 February 2024
___________________________________________________________________
Subject:  General Fund Housing and Communities Financial Report 2023/24
as at Period 7 (31 October 2023)
1. Purpose
1.1 The purpose of the report is to provide the Committee with an update on the
financial performance to 31 October 2023 (Period 7) of General Fund services
under the auspices of the Housing and Communities Committee.
2. Recommendations
2.1 Members are asked to:
i) note the contents of this report which shows the revenue budget forecast
to overspend against budget by £0.284m (8.6%) at the year end.
ii) note the net projected annual position in relation to relevant capital
projects which is showing no projected variance; and
iii) note the progress on efficiencies incorporated into budgets for 2023/24.
3. Background
3.1      Revenue Budget
At the meeting of West Dunbartonshire Council on 01 March 2023, Members
agreed the revenue estimates for 2023/24.
A total net budget of £3.303m was approved for services under the remit for
Housing and Communities services at that time.
Capital
3.2 At the meeting of Council on 01 March 2023, Members also agreed the
updated 10 year General Services Capital Plan for 2023/2024 to 2032/33.
The next three years from 2023/24 to 2025/26 have been approved in detail
with the remaining 7 years being indicative at this stage. The total project life
budget approved for projects that have either commenced or are due to
commence in that period total for Housing and Communities services was
£0.006m.
ITEM 12
Page 89

Page 90

4. Main Issues
Revenue Budget
4.2 Appendix 1 shows the probable outturn for the services at £3.587m. As the
annual budget is £3.303m there is a projected adverse variance currently
projected of £0.284m. A more detailed analysis by service is given in
Appendix 2. Comments are shown in Appendix 3 when there are projected net
annual variances greater than £0.050m and also where the net variance is
below £0.050m but there are offsetting variances of over £0.050m within the
service. Appendix 4 shows progress on the achievement of saving options
adopted as part of the 2023/24 budget.
It should be noted that £0.191m of the Council’s smoothing fund has been
allocated to Communities to offset the in-year reduced savings now expected
due to delay around restructure implementation. After taking account of this,
there is a net overspend of £0.093m.
Capital Budget
4.3 The overall programme summary report is shown in Appendix 5. The analysis
shows that for the in-year planned spend there is currently no projected
variance.
5. People Implications
5.1 There are no people implications.
6. Financial Implications
6.1 Other than the financial position noted above, there are no financial
implications of the budgetary control report.
6.2  Agreed efficiencies for 2023/24 are monitored with current indications being
that £1.895m of the savings budgeted of £2.086m will be achieved (see
Appendix 4). As noted in 4.2 above, the smoothing fund will be used to offset
this £0.191m shortfall.
7. Risk Analysis
7.1 The present variances should be viewed in the knowledge that there are a
number of variable factors which could arise between now and 31 March and
which could affect the year end results for both the revenue and capital
budgets.
7.2 Assumptions around service demand and timing of nationally agreed changes
through the phasing out of lockdown change regularly and therefore there is a
significant risk that the projected year end budgetary position will change from
that reported.
Page 90

Page 91

8. Equalities Impact Assessment (EIA)
8.1 The report is for noting and therefore no Equalities Impact Assessment was
completed for this report.
9. Consultation
9.1 The views of both Finance and Legal services have been requested on this
report and both have advised there are neither any issues nor concerns with
the proposal. As the report is for noting no further consultation is envisaged.
10. Strategic Assessment
10.1 Proper budgetary control and sound financial practice are cornerstones of
good governance and support Council and officers to pursue the five strategic
priorities of the Council’s Strategic Plan. This report forms part of the financial
governance of the Council. This report is for noting and, therefore, does not
directly affect any of the strategic priorities.
Laurence Slavin
Chief Officer, Resources
Date: 19 January 2024
___________________________________________________________________
Person to Contact: Janice Rainey - Business Unit Finance Partner, 16
Church Street, Dumbarton, G82 1QL, telephone: 01389
737707, e-mail janice.rainey@west-dunbarton.gov.uk
Appendices: Appendix 1 - Summary Budgetary Position (Revenue)
Appendix 2 - Detailed Budgetary Position (Revenue)
Appendix 3 - Variance Analysis (Revenue)
Appendix 4 - Monitoring of Efficiencies/Savings Options
(Revenue)
Appendix 5 - Budgetary Position (Capital)
Appendix 6 - Variance Analysis Green (Capital)
Background Papers: None
Wards Affected: All
Page 91

Page 92

WEST DUNBARTONSHIRE COUNCIL ITEM 12 -
APPENDIX 1REVENUE BUDGETARY CONTROL 2023/24
HOUSING & COMMUNITIES SUMMARY
MONTH END DATE 31 October 2023
Actual
Outturn
2022/23
Total Budget
2023/24
YTD Spend
2023/24
Forecast
Spend
2023/24
Annual
RAG
Status
£000 £000 £000 £000 £000 %
3,126 2,238 1,456 2,192 (46) -2% 
1,007 917 1,171 1,098 181 20% 
826 482 860 744 262 54% 
44 18 8 18 0 0% 
64 Private Sector Housing Grant 81 0 83 2 2% 
322 392 79 348 (44) -11% 
0 Housing Asset and Investment 50 1 0 (50) -100% 
(454) (875) (730) (896) (21) -2% 
4,935 3,303 2,846 3,587 284 8.60% 
Service / Subjective Summary Annual Variance 2023/24
Communities
Homeless Persons
Private Sector Housing
Anti Social Behaviour
Housing Maintenance Trading A/c
Total Net Expenditure
Working 4 U/ UK shared Prosperity
Page 92

Page 93

WEST DUNBARTONSHIRE COUNCIL ITEM 12 -
APPENDIX 2
REVENUE BUDGETARY CONTROL 2023/24
HOUSING AND COMMUNITIES COMMITTEE DETAIL
YEAR END DATE 31 October 2023
PERIOD 7
Actual Outturn
2022/23 Service Summary
Total
Budget
2023/24
YTD Spend
2023/24
Forecast
Spend
2023/24
RAG Status
£000 £000 £000 £000 £000 %
22,781 Employee 20,870 11,943 21,371 502 2% 
2,469 Property 2,375 1,233 2,455 80 3% 
1,258 Transport and Plant 1,265 732 1,257 (8) -1% 
7,660 Supplies, Services and Admin 6,286 3,647 6,465 178 3% 
5,141 Payments to Other Bodies 4,517 2,245 4,713 196 4% 
209 Other 0 0 0 0 0% 
39,517 Gross Expenditure 35,313 19,800 36,262 948 3% 
(34,582) Income (32,010) (16,954) (32,676) (666) -2% 
4,935 Net Expenditure 3,303 2,846 3,587 283 9% 
£000 £000  £000  £000  £000 %
3,083 Employee 2,738 1,390 2,734 (5) 0% 
0 Property 0 0 0 0 0% 
14 Transport and Plant 13 6 14 1 6% 
191 Supplies, Services and Admin 65 36 64 (2) -2% 
2,566 Payments to Other Bodies 2,018 631 1,978 (40) -2% 
250 Other 0 0 0 0 0% 
6,104 Gross Expenditure 4,835         2,063         4,789 (46) -1% 
(2,978) Income (2,597) (607) (2,597) 0 0% 
3,126 Net Expenditure 2,238         1,456         2,192 (46) -2% 
£000 £000  £000  £000  £000 %
963 Employee 927 1,044 1,044 116 13% 
70 Property 17 0 17 0 0% 
8 Transport and Plant 4 2 5 0 0% 
9 Supplies, Services and Admin 106 35 88 (18) -17% 
146 Payments to Other Bodies 246 141 345 99 40% 
0 Other 0 0 0 0 0% 
1,197 Gross Expenditure 1,300         1,223         1,499 199 15% 
(190) Income (384) (51) (401) (17) -5% 
1,007 Net Expenditure 917 1,171         1,098 181 20% 
£000 £000 £000 £000 £000 %
2,793 Employee 2,951 1,662 2,981 30 1% 
2,075 Property 1,924 1,123 2,023 99 5% 
37 Transport and Plant 31 15 24 (7) -23% 
121 Supplies, Services and Admin 71 57 99 28 39% 
1,100 Payments to Other Bodies 882 787 1,041 159 18% 
0 Other 0 0 0 0 0% 
6,126 Gross Expenditure 5,859 3,644 6,169 309 5% 
(5,300) Income (5,378) (2,784) (5,426) (48) -1% 
826 Net Expenditure 482 860 743 262 54% 
£000 £000 £000 £000 £000 %
0 Employee 0 0 0 0 0% 
0 Property 0 0 0 0 0% 
0 Transport and Plant 0 0 0 0 0% 
26 Supplies, Services and Admin 0 0 0 0 0% 
18 Payments to Other Bodies 18 8 18 0 0% 
0 Other 0 0 0 0 0% 
44 Gross Expenditure 18 8 18 0 0% 
0 Income 0 0 0 0 0% 
44 Net Expenditure 18 8 18 0 0% 
Private Sector Housing
Annual Variance
2023/24
All Services
Working 4 U/ UK shared Prosperity
Communities
Homeless Persons
Page 93

Page 94

WEST DUNBARTONSHIRE COUNCIL Appendix 2
REVENUE BUDGETARY CONTROL 2023/24
HOUSING AND COMMUNITIES COMMITTEE DETAIL
YEAR END DATE 31 October 2023
PERIOD 7
Actual Outturn
2022/23 Service Summary
Total
Budget
2023/24
YTD Spend
2023/24
Forecast
Spend
2023/24
RAG Status Annual Variance
2023/24
£000 £000 £000 £000 £000 %
42 Employee 42 24 43 2 5% 
223 Property 241 0 241 0 0% 
0 Transport and Plant 0 0 0 0 0% 
(0) Supplies, Services and Admin 0 0 0 0 0% 
246 Payments to Other Bodies 245 136 245 0 0% 
0 Other 0 0 0 0 0% 
510 Gross Expenditure 527 160 529 2 0% 
(446) Income (446) (160) (446) 0 0% 
64 Net Expenditure 81 0 83 2 2% 
£000 £000 £000 £000 £000 %
341 Employee 289 120 289 0 0% 
0 Property 89 48 70 (19) -21% 
9 Transport and Plant 0 0 0 0 0% 
3 Supplies, Services and Admin 0 0 0 0 0% 
141 Payments to Other Bodies 178 0 156 (22) -12% 
0 Other 0 0 0 0 0% 
494 Gross Expenditure 556 168 514 (41) -7% 
(173) Income (163) (89) (166) (3) -2% 
322 Net Expenditure 392 79 348 (44) -11% 
………………………………………………………………………………………………………………………………………………………………………………………….
£000 £000 £000 £000 £000 %
339 Employee 457 216 416 (41) -9% 
0 Property 0 0 0 0 0% 
3 Transport and Plant 5 2 3 (2) -40% 
0 Supplies, Services and Admin 0 0 0 0 0% 
0 Payments to Other Bodies 0 0 0 0 0% 
0 Other 0 0 0 0 0% 
342 Gross Expenditure 462 218 419 (43) -9% 
(342) Income (412) (217) (419) (7) -2% 
- Net Expenditure 50 1 0 (50) -100% 
£000 £000 £000 £000 £000 %
15,221 Employee 13,465 7,487 13,865 400 3% 
100 Property 105 62 105 0 0% 
1,185 Transport and Plant 1,211 706 1,211 0 0% 
7,311 Supplies, Services and Admin 6,044 3,518 6,214 170 3% 
923 Payments to Other Bodies 930 543 930 0 0% 
(41) Other 0 0 0 0 0% 
24,699 Gross Expenditure 21,755 12,316 22,325 570 3% 
(25,153) Income (22,630) (13,046) (23,221) (591) -3% 
(454) Net Expenditure (875) (730) (896) (21) 2% 
Housing Maintenance Trading A/c
Private Sector Housing Grant
Anti Social Behaviour
Housing  Asset and Investment
Page 94

Page 95

WEST DUNBARTONSHIRE COUNCIL ITEM 12 -
APPENDIX 3
REVENUE BUDGETARY CONTROL 2023/24
ANALYSIS FOR VARIANCES OVER £50,000
YEAR END DATE
Total Budget Forecast
Spend RAG Status
£000 £000 £000 %
Communities 917 1,098 181 20% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Homeless Persons 482 744 262 54% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Housing Maintenance Trading A/c (875) (896) (21) 2% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
This service delivers maintenance and investment services to the council's housing stock
Employee costs are showing an adverse variance due to agency recruitment being higher than
planned. The  supplies and services adverse variance is due to the service undertaking high
material content works, namely windows and heating systems. The increased expenditure is
offset by higher recharges.
None Required
Slight underspend / favourable variance at year end
Budget Details
Variance Analysis
Variance
This service seeks to prevent homelessness occurring across the authority and improves
access to support services
The adverse variance is due to the inflationary effect on costs of white goods and furniture
together with requirement to retain bed and breakfast places due to demand / delay in having
WDC properties available,
It is expected that the need for bed and breakfast contingency will cease later in year as more
WDC properties become ready for occupancy
A year end overspend is anticipated
31 October 2023
This service provides support to communities
There have been delays in achieving the communities restructure saving of £383k. The delay
is due to time taken for consultation/ job evaluation panel.  Revised savings expected are for 6
months only.
Adverse variance will be covered from the "smoothing fund".
Nil variance after use of "smoothing fund".
Page 95

Page 96

WEST DUNBARTONSHIRE COUNCIL
MONITORING OF EFFICIENCIES AND MANAGEMENT ADJUSTMENTS 2023/24
Efficiency Detail Reference
Budgeted
Amount £
Projection of
Total Saved £
Projection of
Total Not
Saved £
Comment
1 Reduce anti-social behaviour service HE01 127,000 127,000 0
2 Reduce the Modern Apprenticeship Pathway Scheme HE02 50,000 50,000 0
3 Increase amouint charged to DWP for Ashton View Rent HE03 10,000 10,000 0
4 Reduce Community budgeting grants HE05 6,000 6,000 0
5 Stop free driving lessons HE06 48,000 48,000 0
6 Reduce the Working 4U Service HE07 1,145,000 1,145,000 0
7 Reduce funding provided to West Dunbartonshire Citizen Advice Bureau HE08 87,000 87,000 0
8 WFU - Withdraw Flexible Options HE09 39,000 39,000 0
9 Reduce funding provided to Y-Sort-it HE10 39,000 39,000 0
10 Reduce the number of Tenant Liaison Officers from four to two HE11 99,000 99,000 0
11 Cost of Mitchell Way Office Accommodation moved to HRA HE12 42,000 42,000 0
12 Reduce the level of  funding available to Community Councils HE13 11,000 11,000 0
1,703,000 1,703,000 0
1
Reduce the Communities Team by 50% or Restructure Communities Team by
bringing W4U Youth Learning Team and wider Community Planning support into the
Communities Team HE04 383,000 191500 191,500
restructure in progress ,
awaiting job evaluations
383,000 191,500 191,500
TOTAL 2,086,000 1,894,500 191,500
STATUS: COMPLETE
STATUS: IN PROGRESS
ITEM 12 -
APPENIDX 4
Page 96

Page 97

WEST DUNBARTONSHIRE COUNCIL
ITEM 12 -
APPENDIX 5
GENERAL SERVICES CAPITAL PROGRAMME
OVERALL PROGRAMME SUMMARY
PERIOD END DATE
PERIOD 7
Spend to Date Spend to
Date
£000 £000
Red
0 0.0% 0 0.0% 0 0.0% 0 0.0%
Amber
0 0.0% 0 0.0% 0 0.0% 0 0.0%
Green
1 100.0% 912 100.0% 1 100.0% 0 100.0%
1 100% 912 100% 1 100% 0 100%
Budget Spend to
Date
Forecast
Spend
Forecast
Variance Budget Spend to
Date
Forecast
Spend
Actual
Variance Re-profiling Over/ (Under)
£000 £000 £000 £000 £000 £000 £000 £000 £000 £000
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
912 912 912 0 6 0 6 (0) (0) 0
912 912 912 0 6 0 6 (0) (0) 0
Projects are on target both in relation to overall budget and the forecast
stages in the project life cycle and no issues are anticipated at this time
TOTAL EXPENDITURE
Projects are forecast to be overspent and/or significant delay to
completion
Amber
Projects are either at risk of being overspent and/or delay in completion
(although this is unquantifiable at present) or the project has any issues
that require to be reported at this time
Green
TOTAL EXPENDITURE
Project Status Analysis
Project Life Financials Current Year Financials
Red
Projects are on target both in relation to overall budget and the forecast
stages in the project life cycle and no issues are anticipated at this time
31 October 2023
Project Status Analysis
Project Life Status Analysis Current Year Project Status Analysis
Number of Projects
at RAG Status
% Projects at
RAG Status
% Project
Spend at
RAG Status
Number of
Projects at RAG
Status
% Projects at
RAG Status
% Project
Spend at
RAG Status
Red
Projects are forecast to be overspent and/or experience material delay
to completion
Amber
Projects are either at risk of being overspent and/or delay in completion
(although this is unquantifiable at present) or the project has any issues
that require to be reported at this time
Green
Page 97

Page 98

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
PERIOD END DATE
PERIOD 7
Budget Forecast
Spend
£000 £000 % £000 £000 %
1
Project Life Financials 912 912 100% 912 0 0%
Current Year Financials 6 0 0% 6 (0) 0%
Project Description
Project Manager Elaine Troup
Chief Officer Amanda Graham
Project Lifecycle 31-Mar-24 31-Mar-24
Main Issues / Reason for Variance
The budget will continue to support and contribute to building capacity in communities.
Mitigating Action
Project complete
Anticipated Outcome
Project complete
Invest in "Your Community Initiative"
Capital budget to support the roll out of Your Community,  an initiative designed to achieve coordinated service delivery in
response to community need. This is complimented by community capacity building, empowering WD citizens to do more
for their own communities (leading to less reliance on council).  Also included is the implementation of participatory
budgeting to support and build capacity in communities.
Planned End Date Forecast End Date
31 October 2023
Budget Details
Project Life Financials
Spend to Date Variance
ITEM 12 -         
APPENDIX 6
Page 98