Democracy Spraffa

Item 10 - Socttish Social Housing Charter-Regulation Update

West Dunbartonshire Council · 22 November 2023
Back to Housing & Communities Committee — 22 November 2023 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer, Housing and Employability
Housing and Communities Committee:  22 November 2023
___________________________________________________________________
Subject:   Scottish Social Housing Charter/Regulation of Social Housing in
Scotland Progress Report
1. Purpose
1.1 The purpose of this report is to provide members with a mid-year update in terms
of how we are performing against the Scottish Social Housing Charter indicators
and to provide an update into how we are meeting the requirements of the
Scottish Housing Regulator’s Regulatory Framework.
2. Recommendations
2.1 It is recommended that the Housing and Communities Committee:
(i) Notes the contents of this report recognising the mid-year progress in terms
of meeting the Outcomes of the Scottish Social Housing Charter;
(ii) Notes that following the approval of our Annual Assurance Statement by
the Committee on 25 October 2023 that this has now been submitted to
the Scottish Housing Regulator as per our regulatory requirement;
(iii) Notes that our annual Charter Performance Report has now been published
and a summary will be provided to all tenants with the winter edition of the
Housing News; and
(iv) Notes that a full annual progress report on the Scottish Social Housing
Charter will be submitted to the August 2024 meeting of the Housing and
Communities Committee this will include our Annual Assurance
Statement.
3. Background
3.1 The Scottish Government’s first Scottish Social Housing Charter (SSHC) came into
force in April 2012. This was reviewed during 2016 and again in 2021 and the
resulting revised SSHC was subsequently approved by the Scottish Parliament and
has effect from 1 November 2022.
3.2 The purpose of the SSHC is to help improve the quality and value of the
services that social landlords provide by:
• Stating clearly what tenants and other customers can expect from social
landlords and helping them to hold landlords to account;
• Focusing the efforts of social landlords on achieving outcomes that matter to
their customers; and
ITEM 10

Page 2

• Providing the basis for the Scottish Housing Regulator (SHR) to assess
and report on how well landlords are performing.
3.3 A revised Regulatory Framework and reporting timetable for the SSHC came
into effect on 1st April 2019 is outlined below:
When Who What
Throughout year Housing Services
/Tenants
Assess performance against the Charter
Outcomes
May each year Housing Development Submission of Annual Return on the Charter
to Scottish Housing Regulator
August each year Scottish Housing
Regulator
Publishes a report about each social landlord
with key data from its ARC on their website
October each year
Convener of Housing
and Communities
Committee
Submission of Annual Assurance Statement
to the Scottish Housing Regulator
October each year Housing Development Publication of annual Charter Performance
Report for tenants and other customers
by April each year
Scottish Housing
Regulator 
Publish an Engagement Plan for each
landlord, based on performance against
Charter Indicators and outcomes
by April each year Scottish Housing
Regulator 
Publish a report on the analysis of the
sector’s performance in achieving the Charter
outcomes
3.4 On the 6 August 2014, Members of the Housing and Communities Committee
agreed that twice yearly reports be provided as follows:
• August Committee - Scottish Social Housing Charter Annual Update
Report; and
• November Committee - Scottish Social Housing Charter Annual
Benchmarking Report and Mid-Year Progress Report – (April-September).
3.5 As our AAS needs to be approved by the Committee and submitted to the SHR
by 31 October each year, a special meeting of the Committee was arranged on
25 October 2023 to ensure that we met this timescale. It was agreed that a
further progress report with a mid-year update would be provided to the
November 2023 Committee meeting.
4. Main Issues
4.1 The key areas of focus in relation to the SSHC highlighted in this report are as
follows:
• Mid-year progress in relation to how well we are achieving the Charter
Outcomes;
• An update on the submission of our AAS to the SHR; and
• An update on the publication of our annual Charter Performance Report
for tenants and other customers.

Page 3

Mid-year progress achieving the Charter Outcomes
4.2 The SHR now uses 32 Charter Performance Indicators to monitor the
performance of all social landlords against the Charter outcomes and standards.
4.3 A comprehensive assessment of 2022/23 performance against the Charter has
been carried out which informed a Charter Improvement Plan which is being
implemented across all areas of the housing service with the objective of continuing
to improve services for our tenants and customers.
4.4 Based on this exercise and the content of our most recent Engagement Plan, the
HIB is monitoring on a monthly basis key work-streams aimed at driving
improvements in the following areas:
• Compliance with the Scottish Housing Quality Standard (SHQS);
• Services for people who are homeless, including breaches of the UAO;
• Tenant satisfaction;
• Void management; and
• Complaints response times.
4.5 Detailed benchmarking was provided to the HACC on 25 October 2023 and the
table below provides a more local analysis comparing West Dunbartonshire
Council’s performance against comparable neighbouring housing organisations (3
neighbouring local authorities Renfrewshire, East Dunbartonshire and Stirling and
River Clyde Homes operating in Inverclyde).
Indicator
West
Dunbartonshire
Council
East
Dunbartonshire
Council
Renfrewshire
Council
Stirling
Council
River Clyde
Homes
HOMES AND RENT
Total Number of Homes
10,422 3,725 12,216 6,035 6,140
Rent increase
5.0% 4.2% 5.5% 2.9% 5.0%
TENANT SATISFACTION
% of overall satisfaction with the service
61.3% 75.9% 82.4% 90.9% 91.3%
% of tenants who feel their landlord is good at keeping them informed about their services
75.8% 82.6% 91.1% 98.4% 96.2%
% of tenants satisfied with the opportunities given to participate in decision making
69.2% 78.9% 99.0% 97.5% 94.9%
QUALITY AND MAINTENANCE OF HOMES
% of homes meeting the SHQS
32.2% 53.5% 67.9% 87.0% 79.2%
Emergency Repairs - average number of hours
4.5 hours 4.0 hours 9.8 hours 7.4 hours 3.1 hours

Page 4

Non-Emergency Repairs - average number of days
9.3 days 11.7 days 6.1 days 6.6 days 10.3 days
Repairs – Right First Time
85.7% 81.9% 90.0% 92.2% 86.7%
% of tenants who have had repairs carried out on the last 12 months who were satisfied with
repairs and maintenance service
87.3% 91.6% 73.3% 88.1% 92.2%
Indicator
West
Dunbartonshire
Council
East
Dunbartonshire
Council
Renfrewshire
Council
Stirling
Council
River Clyde
Homes
NEIGHBOURHOODS
% of anti-social behaviour cases resolved within locally agreed targets in the last year
97.1% 100% 98.0% 84.6% 95.9%
VALUE FOR MONEY
Rent collected as % of rent due
98.5% 99.0% 100.0% 99.9% 97.8%
% of Rent due not collected  through homes being empty
1.3% 1.0% 1.9% 1.5% 4.8%
Average length of time in days taken to re-let homes in the last year
33.6 days 59.5 days 60.6 days 76.9 days 209.9 days
4.6 Performance improvement targets for 2023/24 for all the Charter Indicators
have been agreed based on robust benchmarking information and previous
performance. These targets challenge the housing service to meet our
ambition to be one of Scotland’s top performing landlord organisations.
4.7 Of the 32 Charter Indicators, 10 are reported on a six monthly basis to the
Housing and Communities Committee, alongside 3 indicators relating to
homelessness (which are not currently part of the Charter return).
4.8 A summary of performance for the period April 2023 – September 2023 for these
indicators is outlined in the table below:
Status Key
Scottish Social Housing Charter
Mid-year Performance Report
(Apr 2023 – Sep 2023)Target Met or
exceeded
Target narrowly
missed (within
agreed range)
Target missed
Estate Management, Anti-Social Behaviour,
Neighbour Nuisance and Tenancy Disputes
Mid-year
Target
Mid-year
Value Status
% of anti-social behaviour cases resolved 91% 91.5%
Repairs, Maintenance and Improvements Mid-year
Target
Mid-year
Value Status
Average length of time taken to complete
emergency repairs 6 hours 5.35 hours
Average length of time taken to complete non-
emergency repairs 8.4 days 11.8 days

Page 5

% of reactive repairs carried out completed right
first time 90% 85.6%
How many times in the reporting period did you not
complete a gas safety check within 12 months 0 0
% of tenants satisfied with the repairs and
maintenance service 86% 99.6%
Value for Money Mid-year
Target
Mid-year
Value Status
Average time to re-let properties 30 days 45 days
% of rent due lost through homes being empty
during the last year 1.0% 1.08%
Gross rent arrears as a % of total rent due 10.0% 9.84%
Tenancy Sustainability Mid-year
Target
Mid-year
Value Status
% of new tenants who maintained their tenancy for
at least 12 months 94% 94.6%
Homeless People Mid-year
Target
Mid-year
Value Status
% of all homeless cases who received a decision
within 28 day target 95% 99.2%
% of households requiring temporary
accommodation, to whom an offer was made 100% 100%
Breaches of the Unsuitable Accommodation Order 0 60
4.9 Of these 13 key indicators, 8 are meeting the targets set, with another 2
narrowly missing this target. Overall this translates to 77% of these key
indicators either meeting or almost achieving target.
4.10 Whilst not usually reported on a six monthly basis to Committee, given that
they are a key area of focus for the Housing Improvement Board, the table
below gives an update in terms of performance on complaints response times
and on compliance with the Scottish Housing Quality Standard:
Status Key
Scottish Social Housing Charter
Mid-year Performance Report
(Apr 2023 – Sep 2023)Target Met or
exceeded
Target narrowly
missed (within
agreed range)
Target missed
Communication Mid-year
Target
Mid-year
Value Status
Average time in working days to respond to a
Stage 1 complaint 5 days 6 days
Average time in working days to respond to a
Stage 2 complaint 20 days 11 days
Quality of housing Mid-year
Target
Mid-year
Value Status
% of properties compliant with Scottish Housing
Quality Standard 69% 42.5%

Page 6

Annual Assurance Statement (AAS)
4.11 The AAS requires landlords to state they are meeting regulatory requirements
and that they are compliant with the legal requirements and statutory guidance
relevant to the sector. Any areas of material non-compliance should be
highlighted, alongside actions being taken to address these.
4.12 As reported to the special meeting of the HACC on 25 October 2023, we have
highlighted the following areas in this years’ AAS:
• Low level of compliance with SHQS;
• Low levels of tenant satisfaction; and
• Reported breaches of the UAO
4.13 Following the approval by the special meeting of the HACC of the content of
our AAS, it was signed by the Convener on behalf of the Committee and
submitted to the SHR as per the regulatory requirement.
4.14 As per the SHR guidance, our AAS will be published to ensure that it is
accessible to tenants and other customers.
Charter Performance Report
4.15 The SHR requires all social landlords to produce an Annual Charter
Performance Report for their tenants and other customers no later than 31
October each year.
4.16 The statutory regulatory framework states that that this report should include:
• An assessment of performance in delivering the Charter Outcomes;
• Relevant comparisons with previous years, other landlords and national
performance; and
• How and when the landlord intends to address areas for improvement.
4.17 In preparation for our first report in 2014, a working group of tenants and
officers was established and successfully:
• Agreed how tenants wished to be involved;
• Agreed which indicators will feature in the report; and
• Agreed the best style and format to ensure that the report is user friendly
and easy to understand.
4.18 Further engagement was carried out with tenant representatives during 2019
to review and update this report, in line with the revised Charter coming into
effect. This consultation influenced the style, content and format of our Annual
Charter Report and also the update of the Service Standards that are in place
across housing services and which are reported regularly to tenants and other
service users (via the Council website and by a performance insert provided
with Housing News).

Page 7

4.19 This years’ report was published online within the required timescale. The
narrative in the report is based on the annual self-assessment exercise of our
performance and a summary of the report will be sent to every tenant with the
winter edition of the Housing News.
5. People Implications
5.1 There are no people implications as a result of the report. Delivery on the
requirements of the SSHC is managed from within existing staffing resources
within the Housing Development Team.
6. Financial and Procurement Implications
6.1 There are no direct financial or procurement implications in relation to this report.
The improvement plan informed by the Charter self-assessment exercise will be
delivered from within existing budgets.
7. Risk Analysis
7.1 There is a significant risk that failure to respond appropriately to the
requirements of the SSHC would attract an adverse reaction from the SHR and
may have wider consequences for the Council in the context of Best Value.
7.2 At the time of writing we expect out next Engagement Plan to be published in
March 2024.
8. Equalities Impact Assessment (EIA)
8.1 Equalities legislation requires that new or significantly changing policies or
services and financial decisions should be subject to an assessment of their
impact on the wellbeing of certain groups of people.  The recommendations
within this report do not alter any existing policy or pattern of service delivery
and so is not considered to require an equalities impact assessment.
9. Consultation
9.1 The Council has in place a well-established and proactive tenants and residents
organisational structure.  The WDTRO meet with the Council (chaired by the
Convener of the Housing and Communities Committee) on a bi-monthly basis to
discuss all issues relating to the Housing Service.
9.2 There remains a strong appetite among tenants and customers to continue to
participate actively to improve housing services in West Dunbartonshire. This
is reflected in the successful partnership approach adopted to develop the
Charter Performance Report and the on-going activities of the WDTRO, the
Joint Rent Group and the West Dunbartonshire Scrutiny Panel.
9.3 The Council is committed to ensure effective consultation continues and will
support arrangements to increase tenant scrutiny activities and assess our
performance in line with the statutory requirements under the SSHC and the

Page 8

SHR’s regulatory framework.  Our approach was again commended via an
external validation exercise by the Tenant Participation Advisory Service
(TPAS) Scotland, which again awarded West Dunbartonshire Council a Gold
Accreditation for excellence in tenant participation in early 2023.
10. Strategic Assessment
10.1 Having considered the Council's strategic priorities, this report contributes
significantly to all five strategic priorities and specifically to improve local
housing and environmentally sustainable infrastructure.
Peter Barry
Chief Officer, Housing and Employability
Date: 8 November 2023
___________________________________________________________________
Person to Contact:  John Kerr – Housing Development and Homelessness
Manager, Housing and Employability, telephone:
07793717981, email: john.kerr@west-dunbarton.gov.uk
Appendices: None
Background Papers: Scottish Housing Regulator WDC Landlord Report 2022-23
West Dunbartonshire Council | Scottish Housing Regulator
WDC Annual Assurance Statement October 2023
Annual Charter Performance Report for Tenants and    
other Customers 2022/23, West Dunbartonshire Council,
October 2023
https://www.west-dunbarton.gov.uk/council/our-
performance/service-performance/housing-services-
performance-information/charter-performance-report/  
West Dunbartonshire Tenant Participation Strategy 2021-2024
“Involving You”
https://www.west-dunbarton.gov.uk/council/strategies-plans-
and-policies/housing/tenant-participation-strategy/ 
Scottish Social Housing Charter – West Dunbartonshire
Council Annual Assurance Statement,
Report by Chief Officer, Housing and Employability,
Housing and Communities Committee, 
25 October 2023
Wards Affected:   All