WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer, Housing and Employability
Housing and Communities Committee: 22 November 2023
__________________________________________________________________
Subject: More Homes West Dunbartonshire – West Dunbartonshire Council
Affordable Housing Supply Delivery Programme 
1. Purpose
1.1 This purpose of this report is to provide the Housing and Communities
Committee an update on progress with West Dunbartonshire’s More Homes
Programme which oversees the delivery of the Council’s new home building
programme.
2. Recommendations
2.1 It is recommended that the Housing and Communities Committee:
(i) Note the content of the report and the progress made to date in the
delivery of the Council’s More Homes West Dunbartonshire approach;
and
3. Background
3.1 In West Dunbartonshire the Affordable Housing Supply Programme (AHSP) is
delivered through a More Homes West Dunbartonshire strategic approach
which has successfully delivered over 1000 new affordable homes in West
Dunbartonshire to date and includes the Council’s own ambitious New House
Building Programme.
3.2 The Council’s last practical completion took place at the Queens Quay
development in September 2022 delivering 29 new Council homes in a key
regeneration area as part of a wider development which has delivered 146
new social rented homes.  The homes were the first residential properties to
be heated from the Council’s Queens Quay District Heating Network. This
development has been recognised at recent national housing sector awards
winning the following:-
• Best Residential Regeneration Project – Herald Property Awards
• Inside Housing Best Residential Development (Scotland)
3.3 These 29 new homes, are in addition to the completion of the Council’s first
fully dementia designed development at Creveul Court, Alexandria and other
exemplar developments in Haldane, Aitkenbar, Bellmsyre, Dumbarton
Harbour and St Andrews, Clydebank.  The Council have now completed 12
ITEM 9

Page 2

new build developments since 2013 and are the largest developer of social
homes in West Dunbartonshire delivering 496 new homes and 101
acquisitions through our buyback scheme to date as outlined in Table 1
below: 
Table 1:  Completed Council New Build and Acquisitions
Project No. of
Units
Completion
Date
Granville Street (Phase 1), Clydebank 24 July 2013
Miller Road, Alexandria 15 October 2013
Granville Street (Phase 2), Clydebank 9 February 2014
Central Bellsmyre, Dumbarton 36 December 2014
Hillstreet Square, Dumbarton 37 August 2015
Second Avenue, Clydebank 40 April 2018
Creveul Court, Alexandria 22 April 2021
Aitkenbar Primary School 55 July2021
Haldane Primary School 58 August 2021
St Andrews, Clydebank  126 October 2021
Dumbarton Harbour, Dumbarton 45 December 2021
Queens Quay, Site B, Clydebank 29 August 2022
Buyback Acquisitions  101 Ongoing
Totals 597   
3.4 The Strategic Housing Investment Plan (SHIP) 2023-2027, outlining West
Dunbartonshire’s Affordable Housing Supply Programme through the More
Homes West Dunbartonshire approach was approved by the Housing and
Communities Committee in November 2022. The SHIP outline plans to meet
the Council Administration’s aim of delivering 2500 new affordable and social
rented homes over the next 10 years.  The Council has received positive
feedback from the Scottish Government in respect of our SHIP.  The
development of the new SHIP is now complete and will be submitted to the
Housing and Communities Committee in November 2023 for approval. 
4. Main Issues 
More Homes West Dunbartonshire - Delivery Programme 
4.1 Building new affordable homes has an important role to play in revitalising
local economies and assisting with post-pandemic and economic recovery
plans, negating the impacts of the current cost of living crisis and combatting
poverty including child poverty.  It is also clear that the need for affordable
homes has and will increase in the current ongoing economic environment.
Our More Homes West Dunbartonshire approach is an ambitious plan that
aims to continue the positive momentum of the delivery of much needed
Council homes in West Dunbartonshire and will significantly assist the
Council’s aim to deliver 2500 new social and affordable homes by 2032. 
4.2 As the biggest affordable housing developer in West Dunbartonshire, the
Council has identified a number of future development sites for new council
homes to address existing and new housing need. The design of these homes
will further develop, improve and exceed current best practice, providing
sustainable homes using innovative technology and delivering on our low

Page 3

carbon ambitions including passivhaus and other net zero carbon
opportunities. 
4.3 The Strategic Housing Investment Plan and HRA Capital Plan outlined the
plans the Council have for meeting their new build ambitions.  Some of the
initial plans were and continue to be impacted as a result of global issues
revised new build targets for the Council are outlined below:   
Table 2: Council New Build Programme 
*Current Planning figures 
4.4 Updates for each site are noted below: 
Clydebank East: 
Works commenced on this development on 23 January 2023, as reported to
the Housing and Communities Committee in February 2023 the initial
Site/Developer Number of
Units
Number of
Specialist
Provision 
Est Site
Start
Est Completion
Date
Clydebank
East,
Clydebank
88  9 
On Site 
January
2023
Spring 2025
Pappert,
Bonhill
Alexandria
26  3
February
24
Winter 2024/25 
Willox Park 17 17 Spring 24 Winter 2024/25
Bonhill Gap
Sites* 34 4 Spring 24 Winter 2024/25
Mount
Pleasant
19 19 Spring 24 Spring 2025
Queens Quay
Site C
100 10 Spring 24 Spring 2025
Clydebank
Health Centre*
38 5 Spring 24 Spring 2025
Bank Street,
Alexandria
22 22 Summer
24
Spring 25
Dennystoun
Forge
20 20 Summer 
24 
Winter 2024/25
Clydebank
Gap Sites*
(Gilmour
Avenue)
50 10 Summer
24
Summer 2025
Silverton
Regeneration
tbc tbc tbc tbc
Buyback
Scheme (60
per year)
300 36 2023/24 2027/28
714 units 155 units

Page 4

programme is for the remedial works and external drainage and this being
progressed in close collaboration with the Council’s wider regulatory role, a
construction site start will commence in early August.  The total programme
for the works will be 116 weeks. 
This development will deliver 88 new homes and has been designed to meet
the housing need within the wider West Dunbartonshire area, the table below
shows the housing mix: 
House Type Sustainability Standard Number of New
Homes
Wheelchair Bungalow
3bed/4person
Net Zero 3
House 3bed/5person Net Zero 15
House 4 bed/7person Net Zero 12
House 4 bed/9 person Net Zero 8
Cottage Flat 1 bed/2 person Net Zero 4
Cottage Flat 2 bed/3 person Net Zero 4
Flat 1 bed/2person Net Zero 16
Flat 2 bed/4 person Net Zero 24
Wheelchair Flat 1 bed/2person Net Zero 2 
All houses are designed to the Housing for Various Needs Standard (HfVN).
There will be 9 fully Wheelchair (WCH) accessible properties.  The 4 and 5
bedroom homes will all have ground floor double bedrooms.   
The development at Clydebank East will see the completion of a major
housing led regeneration of a key priority area identified in the Local Housing
Strategy and will be the Council’s first fully zero carbon housing development
and marks a significant milestone in our transition to net zero approved at the
August 2022 meeting of the Housing and Communities Committee.  Publicity
is planned to mark the significant milestone on terms of a site start. 
We are still currently engaged with the Scottish Government in terms of
finalising the grant award, as reported previously we have sought above
benchmark grant and our submission is currently being assessed by the
Scottish Government’s technical team. Our request is proportionate based on
the high levels of remediation costs but in terms of context our ask is
comparable with the grant awards made to the 2 housing association who
partnered the Council in the delivery of the new housing at Queens Quay. 
Pappert, Bonhill 
Following the review of the design proposals for the Pappert development the
housing mix is as follows:- 
House Type Sustainability Standard Number of New
Homes
House 3bed/5 person Passivhaus 6
House 3bed/5 person Net Zero 6

Page 5

House 4bed/6person Net Zero 4
House 4bed/7person Net Zero 1
Flat 2bed/3person w/c Net Zero 3
Flat 1 bed/2person Net Zero 6 
Planning permission for this development was granted at the Planning
Committee of 20th September 2023, enabling a site start in February 2024. 
Willox Park, Doveholm, Dumbarton 
The development of 17 new homes to be delivered at the former care home
site continues within the design phase towards a full planning application In
November. 
The net zero heat strategy will be delivered by ground source heat pump, as it
was felt that this solution to be preferable than an air source heat pump for
each home.  The development will also utilise PV panels and a MVHR
system. 
There has been positive dialogue in terms of the current plans with both the
Willox Park residents and also planning officers.  Ongoing engagement will be
maintained with the current Willox Park residents throughout the delivery
process. 
Bonhill Gap Site Strategy 
The pre-planning application process has commenced on the development of
the 3 separate gap sites which are contained within this wider development. 
We have now procured engineering consultants as we move closer to a full
planning application. 
We have altered some of the initial design plans to incorporate a number of
adaptable 6/7 bed homes within the development to meet identified housing
need. 
Bank Street, Alexandria 
The Council is currently developing a proposal for 22 sheltered/amenity
housing units in partnership with the HSCP. This will include an options
appraisal in terms of the existing provision within the local area. 
The delayed appointment of the design team and engineering consultants
have pushed back the anticipated timescales of a planning application being
submitted to April 2024. 
Mount Pleasant, Old Kilpatrick 
The demolition of the former care home at the site completed in December
2022 ahead of schedule.

Page 6

CCG have been appointed as the main contractor following the Tendering
Committee in September, having been directly appointed from the Scotland
Excel Framework.  We await planning permission which will allow the
intended site start of March 2024 to be achieved. 
Queens Quay, Site C, Clydebank 
The Council has been developing a design to deliver a projected 20 units on
this site to complement the housing mix within sites A and B.  This
development will also be designed to meet low/zero carbon principles and
linked to the Queens Quay district heating network
.
Pre-planning response was received on the 25 February highlighting concern
of the WDC development proceeding in isolation. We have adopted a
proactive response to this issue and have developed masterplan diagrams
incorporating the surrounding sites and have carried out valuations on the
adjacent site to Queens Quay C with a view to purchasing additional land to
deliver more affordable housing in the Queens Quay regeneration site.  If this
is achieved we would seek to develop a mixed tenure approach to any
expanded development site delivering 100 new affordable homes. We are
urgently seeking discussion with CRL (Clydeside Regeneration Limited) to
progress the possibility of acquiring this additional land and will be able to
draw down Scottish Government grant to enable this. 
Clydebank Health Centre 
Our appointed design team are doing some feasibility work based on a
housing mix of 20 units of sheltered housing and 20 units to be a mix of family
housing and cottage flats within the development site. 
This is in advance of the demolition of the buildings within the site which is
currently scheduled for March 2024. 
Dennystoun Forge Gypsy/Traveller Site 
A submission was made to the Scottish Government for support funding from
their Gypsy/Traveller Accommodation Fund for significant improvements to
the Dennystoun Forge site, including new energy efficient chalet type
accommodation following a consultation exercise with site residents. 
However, we were notified that this submission was unsuccessful at this point.
We have since engaged the Scottish Government following the outcome of
this and have provided additional information to the Scottish Government in
support of the application.   
In another positive development the Council’s Housing Development Team
has been providing support to the tenants within the Dennystoun Forge site to
establish a registered tenants association, the absence of a recognised
tenants group and ongoing site presence was seen as a relative weakness in
terms of the initial submission.

Page 7

We anticipate that following the new information provided to support our
application for funding Scottish Government officials will reassess the
application before the end of 2023. 
Queen Mary Avenue, Clydebank (Clydebank Gap Sites) 
The transfer of the site at Queen Mary Avenue, Clydebank with vacant
possession at the cost of £140,000 from the Council’s General Fund to the
Housing Revenue Account for the delivery of new Council homes was
approved at the February meeting of the Housing and Communities
Committee and has now been concluded.  We are preparing a demolition
programme to allow the site to be cleared as soon as is practically possible
following the recent departure of Council staff teams who were using the
premises.  The plans for demolition will run in parallel with a feasibility study in
terms of the future development.   
Gilmour Avenue, Hardgate (Clydebank Gap Sites) 
As part of the wider development of our Clydebank Gap Site strategy we
identified a HRA gap site in the Hardgate area at Gilmour Avenue.  The site
was previously the location of timber garages on concrete bases.  These have
long since been demolished and the site has been beset with fly tipping
issues for a number of years. The proposed development would see two three
bed semi-detached homes to be delivered utilising modular construction
methods.  A planning application has been submitted and we await approval. 
Silverton Regeneration 
Discussions are ongoing which will allow the Council to purchase the last
remaining privately owned property in the defective surplus blocks this will
allow us to demolish and consider opportunities to deliver new housing within
the Silverton area.  We will highlight proposals in future update reports to the
Housing and Communities Committee. 
Buyback Programme 
The Council’s buyback programme which incorporates the Mortgage to Rent
Scheme purchased 16 new homes in 2022/23.  In 2023/24 to date we have
already 22 new homes at an average purchase cost of £100,000. 
In 2023/24 and following approval of the Strategic Housing Investment Plan
by the Housing and Communities Committee in November 2022 and
subsequently the decision by West Dunbartonshire Council in March 2023 to
deliver an enhanced Housing Capital Investment Programme including
additional funding for buyback purchases we are now scaling up ambition
around our buyback programme.  In 2023/24 and in each of the subsequent
years up to and including 2027/28 we plan to deliver 60 new homes each year
meaning a minimum of 300 new Council homes to meet identified need.

Page 8

The additional funding that was approved by the West Dunbartonshire Council
meeting of 1 March 2023 will target larger family homes to meet this specific
need.  To meet these defined targets we will add additional resources within
the Housing team, and we will also refresh our Buyback Policy.  This update
policy will be submitted to the meeting of the Housing and Communities
Committee in February 2023. 
4.5 The Housing Development Team are continuously looking for opportunities to
provide additional new build council homes and will bring any potential site to
the Housing and Communities Committee with as much information as
possible as part of the regular More Homes update paper. 
5. People Implications 
5.1 An additional Senior Housing Development Officer role is required to deliver
the increase and scaling up of the Council’s buyback programme.  This will be
met within the existing resources.   
6. Financial and Procurement Implications 
Financial 
6.1 On 1 March 2023 Council approved the Housing Capital Programme 2023-
2028 which saw significant resources committed to the delivery of new council
homes in West Dunbartonshire.  An expenditure budget of £155m for the
affordable housing supply programme is factored into the HRA Capital
Programme this will be updated to reflect the income and expenditure
highlighted within this report.  As it currently stands, it is anticipated that this
programme will complete on project life budget. 
6.2 The uprated Affordable Housing Supply Programme grant benchmark
assumptions were put in place during 2023/24.  The new benchmark
assumptions are highlighted below:- 
RSL social rent  £91,182 
(3 person equivalent) 
Council social rent  £83,584 
(3 person equivalent) 
RSL mid-market rent  £62,542 
(3 person equivalent) 
Council mid-market rent  £57,281 
(3 person equivalent)

Page 9

6.3 In addition the following benchmark grant levels are available for additional
quality measures as follows:-   
Delivering homes to Section 7,
Silver Level, of the 2019  Building
Regulations in respect of Energy for
Space Heating (that is, full Bronze 
Level plus Aspect 2 of Silver Level).
£2,338 per home
(3 person 
equivalent 
benchmark) 
Provision of balconies within flatted
developments to enable people to 
sit outside, where the provision of
private or communal outdoor space 
cannot otherwise be accommodated
£4,676 per home
(3 person 
equivalent 
benchmark)
ark)
Provision of space for home working 
or study – to note that this 
benchmark does not apply to
projects meeting current Housing for 
Varying Needs standards. 
In all other circumstances, grant 
applicants should demonstrate that
additional space is necessary to 
deliver this measure in order for this
benchmark to apply i.e. it is not 
possible to incorporate this within
the design of the homes under 
current space standards. 
£4,092 per home 
(3 person 
equivalent 
benchmark) 
Digitally-enabling – when a tenant
gets the keys to their home they 
should be able to arrange for an
internet connection to ‘go live’ 
without the internet service provider
having to provide additional 
cabling to the premises.
£351 per home
(3 person 
equivalent 
benchmark) 
Installation of ducting infrastructure
for electric vehicle charge point 
connectors. 
£585 per 
connector(3 person 
equivalent 
benchmark 
Installation of electric vehicle charge
points (excluding installation of 
ducting infrastructure)
£585 per 
connector(3 person 
equivalent 
benchmark 
Installation of automatic fire suppression
systems. 
£3,507 per home
(3 person 
equivalent 
benchmark)

Page 10

Installation of heating systems which
produce zero direct emissions at 
the point of use. 
£4,676 per home
(3 person 
equivalent 
benchmark 
6.4 Notwithstanding the expected increase in benchmark assumptions Housing
and Finance Officers will continue to assess the ongoing affordability of future
developments within the context of the Housing Revenue Account Business
Plan. 
Procurement 
6.5 All new development sites will be subject to new detailed procurement
strategies and the opportunities highlighted within 4.4 of this report will
continue to be prioritised. 
6.6 Where the contract award is less than £213,000, authority is delegated to
the Chief Officer in consultation with the Procurement Manager to instruct the
award of contracts for the planned revenue and capital spend detailed in this
report to suppliers providing the most economically advantageous offer to the
Council. 
6.7 All procurement activity carried out by the Council in excess of £2m is
subject to a contract strategy. The contract strategy for new housing
development within the HRA Capital Programme will be developed by the
Corporate Procurement Unit in consultation with Housing Development
Officers. The contract strategy will include, but is not limited to; contract
scope, service forward plan, the market, procurement model and routes –
including existing delivery vehicles, roles and responsibilities, risks, issues
and opportunities and on-going contract management. Opportunities to
maximise the positive social, economic and environmental impact for the
Council through the relevant procurement processes will be developed in line
with procurement policy. 
7. Risk Analysis 
7.1 All Council new build projects have their own Risk Register which highlights
the risk within and out-with the project team’s control.  These are maintained
and adjusted on an on-going basis. 
7.2 With any new build project there is a risk that as the projects develop the cost
increases beyond the estimated contract cost.  Any additional borrowing
requirements, or conversely, cost savings will be reported to future meetings
of the Housing and Communities Committee. However, this is mitigated
through a target cost model approach in our current contract arrangements
within the Scottish Procurement Alliance (SPA) framework and Scotland
Excel. 
8. Equalities Impact Assessment (EIA)

Page 11

8.1 The proposal does not alter any existing policy or pattern of service delivery
and so is not considered to require an equalities impact assessment. 
9. Consultation 
9.1 As part of our previous rent consultation exercise, 92% of respondents
indicated their support for the Council’s ambitious plans to deliver the Housing
Revenue Account (HRA) new council house build programme. In addition,
there was positive support for the wider delivery of new build housing as part
of the recent Local Housing Strategy.  Regular updates on new build
development are provided to the West Dunbartonshire Tenants and Residents
Organisation at the bi-monthly liaison meetings. 
10. Strategic Assessment 
10.1 The Local Housing Strategy is the overarching document setting out the
strategic direction for housing across all tenures and informs the future
investment in housing and related services across West Dunbartonshire. 
10.2 Having considered all the Council’s strategic priorities, this report and the
provision of new supply social housing for rent contributes greatly to all
strategic priorities. 
Peter Barry
Chief Officer, Housing and Employability
Date: 8 November 2023 
Person to Contact: John Kerr – Housing Development and Homelessness
Manager, Housing Development and Homelessness
Team, Housing and Employability, telephone:
07793717981, email: john.kerr@west-dunbarton.gov.uk   
Appendices: None 
Background Papers: West Dunbartonshire Council’s Local Housing Strategy     
Local Housing Strategy, Health Inequalities Impact
Assessment 
Wards Affected: All