WEST DUNBARTONSHIRE COUNCIL
Report by Chief Officer – Supply, Distribution & Property
Chief Officer - Housing and Communities
Housing and Communities Committee
23 August 2023
Subject: Progress to re-let empty council house properties
1 Purpose
1.1 The purpose of this report is to provide Committee with an update on progress to
improve on the approach to re-let of empty council house properties. 
2 Recommendations
2.1 It is recommended that Committee note the contents of the report and progress to date.
3 Background
3.1 Members are aware of the service challenges faced by housing and building services
teams during and following the covid pandemic, where significant types and levels of
work could not be undertaken.  In relation to empty houses (also known as voids) this
resulted in a significant backlog of work and exceptionally high numbers of properties
requiring to be refurbished, repaired and re-let.
3.2 Following a review of the re-let process from end to end, an improvement plan is in
place with various actions across housing and building services. 
4 Main Issues
4.1 It is a key priority of Housing and Building Services to ensure the numbers of empty
properties are minimised given the significant impact on the housing options for tenants
and families, notwithstanding the potential loss of income.   
4.2 As reported to members previously, the total number of empty properties in August
2022 was approximately 380 and this number reached a peak of 425 in November. 
This included those empty properties which require significant major works. This is in
comparison to the pre-covid numbers which were below 150 at any given time.
4.3 As well as the ongoing actions contained within the over empty properties improvement
plan referred to in paragraph 3.2, it was very clear that the rising numbers of empty
properties was a significant concern. This became a significant priority which in turn
required a focused plan to urgently address this and reduce the numbers.  As a result,
to support this, the following key actions were agreed and undertaken:
• the development of a visual dashboard lead by the integrated housing
management system (IHMS) team with live management data and a weekly
report available to chief officer(s);
• a joined up approach to information sharing using a single source of data
management from IHMS between housing and building services teams and
weekly meetings to review progress, identify issues and take immediate action;
ITEM 13

Page 2

• the re-allocation of resources within building services to ensure maximum
capacity and input into this priority;
• the revised categorisation of empty properties to allow understanding of scale and
complexity of work and in turn allocation of resources;
• weekly meetings with Chief Officer and BS management team to review and
scrutinise progress;
• the appointment and management of back up contractors as required to support
capacity.
• the engagement of contractor “Help to move” to provide additional support in
tackling the (national) issue of utilities supplies.
4.4 During the period from August 2022 until July 2023, at total of 762 empty properties
were received and referred to Building Services for repair.  The current position as at
7 August is as follows:
•Operational properties with building services 136
(including 17 extensive works)
•Ready to let with housing services  40
• Major works empty properties  51
4.5 Although positive progress has been made in reducing the overall number of empty
properties, the challenges remain and there is much work still to be done to ensure a
return to a sustained pre-covid position.  Progress will continue to be tracked, monitored
and reported through the Housing and Building Services management teams and to
committee members through service delivery plans / performance plans.
5 People Implications
5.1 There are no people implications with this report.  
6 Financial & Procurement Implications
6.1 There are no procurement implications with this report.
6.2 While there are no financial implications with this update report for noting, the
overall costs have increased due to the number of empty properties requiring
to be refurbished.  However, it is anticipated that there will be a reduction in
costs in line with continuous positive progress and elimination of the backlog.
This will be monitored and reported within the budgetary control report to
committee members.
7 Risk Analysis
7.1 There are no risks with this update report for noting, however in relation to the
improvement plan, actions must continue to be monitored and managed, otherwise there
is a risk that the numbers of empty properties will not reduce sufficiently and timeously
and costs will continue to rise.
8 Equalities Impact Assessment
8.1 An equalities impact assessment is not required with this report.
9. Consultation

Page 3

9.1 Consultation has taken place with appropriate services.
10. Strategic Assessment
10.1 The timeous re-let of empty properties is a significant priority and supports the
successful delivery of the strategic priorities and objectives of the Council.
Chief Officer: Angela Wilson, Peter Barry
Service Area: Supply Distribution & Property, Housing and Communities
Date: 7 August 2023
Person to Contact: Martin Feeney – Building Services Manager, Supply
Distribution & Property: Telephone 07768657718, email
martin.feeney@west-dunbarton.gov.uk