WEST DUNBARTONSHIRE COUNCIL Report by the Chief Officer, Housing and Employability Housing and Communities Committee: 23 August 2023 __________________________________________________________________ Subject: More Homes West Dunbartonshire – West Dunbartonshire Council Affordable Housing Supply Delivery Programme 1. Purpose 1.1 This purpose of this report is to provide the Housing and Communities Committee an update on progress with West Dunbartonshire’s More Homes Programme which oversees the delivery of the Council’s new home building programme. 2. Recommendations 2.1 It is recommended that the Housing and Communities Committee: (i) Note the content of the report and the progress made to date in the delivery of the Council’s More Homes West Dunbartonshire approach; and (ii) Note the revised Affordable Housing Supply Programme benchmark assumptions outlined in paragraph 6.2 of this report. 3. Background 3.1 In West Dunbartonshire the Affordable Housing Supply Programme (AHSP) is delivered through a More Homes West Dunbartonshire strategic approach which has successfully delivered over 1000 new affordable homes in West Dunbartonshire to date and includes the Council’s own ambitious New House Building Programme. 3.2 The Council’s latest practical completion took place at the Queens Quay development in September 2022 delivering 29 new Council homes in a key regeneration area as part of a wider development which has delivered 146 new social rented homes. These are first residential properties to be heated from the Council’s Queens Quay District Heating Network. This development has been recognised at recent housing sector awards winning the won a Silver Medal at the Scottish Design Awards and a finalist at both the Scottish Homes Awards and Homes for Scotland Awards 2023. 3.3 These 29 new homes, are in addition to the completion of the Council’s first fully dementia designed development at Creveul Court, Alexandria and other exemplar developments in Haldane, Aitkenbar, Bellmsyre, Dumbarton ITEM 8
Page 2
Harbour and St Andrews, Clydebank. The Council have now completed 12 new build developments since 2013 and are the largest developer of social homes in West Dunbartonshire delivering 496 new homes to date as outlined in Table 1 below: Table 1: Completed Council New Build Project No. of Units Completion Date Granville Street (Phase 1), Clydebank 24 July 2013 Miller Road, Alexandria 15 October 2013 Granville Street (Phase 2), Clydebank 9 February 2014 Central Bellsmyre, Dumbarton 36 December 2014 Hillstreet Square, Dumbarton 37 August 2015 Second Avenue, Clydebank 40 April 2018 Creveul Court, Alexandria 22 April 2021 Aitkenbar Primary School 55 July2021 Haldane Primary School 58 August 2021 St Andrews, Clydebank 126 October 2021 Dumbarton Harbour, Dumbarton 45 December 2021 Queens Quay, Site B, Clydebank 29 August 2022 Totals 496 3.4 The Strategic Housing Investment Plan (SHIP) 2023-2027, outlining West Dunbartonshire’s Affordable Housing Supply Programme through the More Homes West Dunbartonshire approach was approved by the Housing and Communities Committee in November 2022. The SHIP outline plans to meet the Council Administration’s aim of delivering 2500 new affordable and social rented homes over the next 10 years. The Council has recently received positive feedback from the Scottish Government in respect of our SHIP. Work has now commenced on the delivery of the new Strategic Housing Investment Plan which will be submitted to the Housing and Communities Committee in November 2023. 4. Main Issues More Homes West Dunbartonshire - Delivery Programme 4.1 Building new affordable homes has an important role to play in revitalising local economies and assisting with post-pandemic and economic recovery plans, negating the impacts of the current cost of living crisis and combatting poverty including child poverty. It is also clear that the need for affordable homes has and will increase in the current ongoing economic environment. Our More Homes West Dunbartonshire approach is an ambitious plan that aims to continue the positive momentum of the delivery of much needed Council homes in West Dunbartonshire and will significantly assist the Council’s aim to deliver 2500 new social and affordable homes by 2032. 4.2 As the biggest affordable housing developer in West Dunbartonshire, the Council has identified a number of future development sites for new council homes to address existing and new housing need. The design of these homes will further develop, improve and exceed current best practice, providing sustainable homes using innovative technology and delivering on our low
Page 3
carbon ambitions including passivhaus and other net zero carbon opportunities. 4.3 The Strategic Housing Investment Plan and HRA Capital Plan outlined the plans the Council have for meeting their new build ambitions. Some of the initial plans were and continue to be impacted as a result of global issues revised new build targets for the Council are outlined below: Table 2: Council New Build Programme *Current Planning figures Site/Developer Number of Units Number of Specialist Provision Est Site Start Est Completion Date Clydebank East, Clydebank 88 9 On Site January 2023 Spring 2025 Pappert, Bonhill Alexandria 26 3 Winter 2023/24 Winter 2024/25 Willox Park 17 17 Winter 2023/24 Winter 2024/25 Bonhill Gap Sites* 34 4 Winter 2023/24 Winter 2024/25 Bank Street, Alexandria 22 22 Winter 2023/24 Winter 2024/25 Mount Pleasant 19 19 Winter 2023/24 Spring 2025 Queens Quay Site C 100 10 Spring 2024 Spring 2025 Clydebank Health Centre* 38 5 Spring 2024 Spring 2025 Dennystoun Forge 20 20 Spring 2024 Winter 2024 Clydebank Gap Sites* (Gilmour Avenue) 50 10 Spring 2024 Summer 2025 Silverton Regeneration tbc tbc tbc tbc Buyback Scheme (60 per year) 300 36 2023/24 2027/28 714 units 155 units
Page 4
4.4 Updates for each site are noted below: Clydebank East: Works commenced on this development on 23 January 2023, as reported to the Housing and Communities Committee in February 2023 the initial programme is for the remedial works and external drainage and this being progressed in close collaboration with the Council’s wider regulatory role, a construction site start will commence in early August. The total programme for the works will be 116 weeks. This development will deliver 88 new homes and has been designed to meet the housing need within the wider West Dunbartonshire area, the table below shows the housing mix: House Type Sustainability Standard Number of New Homes Wheelchair Bungalow 3bed/4person Net Zero 3 House 3bed/5person Net Zero 15 House 4 bed/7person Net Zero 12 House 4 bed/9 person Net Zero 8 Cottage Flat 1 bed/2 person Net Zero 4 Cottage Flat 2 bed/3 person Net Zero 4 Flat 1 bed/2person Net Zero 16 Flat 2 bed/4 person Net Zero 24 Wheelchair Flat 1 bed/2person Net Zero 2 All houses are designed to the Housing for Various Needs Standard (HfVN). There will be 9 fully Wheelchair (WCH) accessible properties. The 4 and 5 bedroom homes will all have ground floor double bedrooms. The development at Clydebank East will see the completion of a major housing led regeneration of a key priority area identified in the Local Housing Strategy and will be the Council’s first fully zero carbon housing development and marks a significant milestone in our transition to net zero approved at the August 2022 meeting of the Housing and Communities Committee. Publicity is planned to mark the significant milestone on terms of a site start. We are still currently engaged with the Scottish Government in terms of finalising the grant award, as reported previously we have sought above benchmark grant and our submission is currently being assessed by the Scottish Government’s technical team. Our request is proportionate based on the high levels of remediation costs but in terms of context our ask is comparable with the grant awards made to the 2 housing association who partnered the Council in the delivery of the new housing at Queens Quay. We anticipate that following the decision by the Planning Committee on 2 August to delegate authority for the street names in respect of this development, this will be completed in advance of the 1st September this will
Page 5
allow application for utility connections for the project, a critical element of the development process. Pappert, Bonhill Following the review of the design proposals for the Pappert development the housing mix is as follows:- House Type Sustainability Standard Number of New Homes House 3bed/5 person Passivhaus 6 House 3bed/5 person Net Zero 6 House 4bed/6person Net Zero 4 House 4bed/7person Net Zero 1 Flat 2bed/3person w/c Net Zero 3 Flat 1 bed/2person Net Zero 6 A planning application has been submitted and we anticipate planning permission for this development at the Planning Committee of 20th September 2023, this will then enable a site start later this year or early in 2024. Willox Park, Doveholm, Dumbarton The development of 17 new homes to be delivered at the former care home site continues within the design phase towards a full planning application. We have appointed an engineering consultant that will allow the project to be advanced to planning and building warrant. We have now revised our project timescales and anticipate a site start in March 2024. Bonhill Gap Site Strategy The pre-planning application process has commenced on the development of the 3 separate gap sites which are contained within this wider development. We are in the process of procuring engineering consultants as we move closer to a full planning application. We have altered some of the initial design plans to incorporate a number of adaptable 6/7 bed homes within the development to meet identified housing need. Bank Street, Alexandria The council is currently developing a proposal for 22 sheltered/amenity housing units in partnership with the HSCP. This will include an options appraisal in terms of the existing provision within the local area. A landscape architect has been procured for the design team and engineering consultants (structural, civil, mechanical and electrical) will be procured shortly.
Page 6
Mount Pleasant, Old Kilpatrick The demolition of the former care home at the site completed in December 2022 ahead of schedule. We have had an initial consultation with the Old Kilpatrick Community Council where we presented our concept of providing housing in a similar style to Creveul Court, Alexandria. This was accompanied by a leaflet distributed to all residents adjacent to the site. The development will consist of 19 new homes. The construction procurement strategy has been signed off by relevant Council Chief Officers and will be presented to the Tendering Committee of 20 September 2023. A pre-planning application was submitted in June and we anticipate a planning application to be submitted in August. Queens Quay, Site C, Clydebank The Council has been developing a design to deliver a projected 20 units on this site to complement the housing mix within sites A and B. This development will also be designed to meet low/zero carbon principles and linked to the Queens Quay district heating network . Pre-planning response was received on the 25 February highlighting concern of the WDC development proceeding in isolation. We have adopted a proactive response to this issue and have developed masterplan diagrams incorporating the surrounding sites and have carried out valuations on the adjacent site to Queens Quay C with a view to purchasing additional land to deliver more affordable housing in the Queens Quay regeneration site. If this is achieved we would seek to develop a mixed tenure approach to any expanded development site delivering 100 new affordable homes. We are urgently seeking discussion with CRL (Clydeside Regeneration Limited) to progress the possibility of acquiring this additional land and will be able to draw down Scottish Government grant to enable this. Clydebank Health Centre As approved by the Housing and Communities Committee on 3 May 2023, the acquisition of the site was completed on 22nd June. A Security contractor has been engaged and will be in place until demolition strategy can be completed. We are currently developing an optimum housing mix for this development which meets the requirements of the Planning brief. Dennystoun Forge Gypsy/Traveller Site A submission was made to the Scottish Government for support funding from their Gypsy/Traveller Accommodation Fund for significant improvements to
Page 7
the Dennystoun Forge site, including new energy efficient chalet type accommodation following a consultation exercise with site residents. However, we were notified that this submission was unsuccessful at this point. We have since engaged the Scottish Government following the outcome of this and have provided additional information to the Scottish Government in support of the application. In another positive development the Council’s Housing Development Officer has been providing support to the tenants within the Dennystoun Forge site to establish a registered tenants association, the absence of a recognised tenants group and ongoing site presence was seen as a relative weakness in terms of the initial submission. We anticipate that following the new information provided to support our application for funding Scottish Government officials will reassess the application when parliament commences following recess Queen Mary Avenue, Clydebank (Clydebank Gap Sites) The transfer of the site at Queen Mary Avenue, Clydebank with vacant possession at the cost of £140,000 from the Council’s General Fund to the Housing Revenue Account for the delivery of new Council homes was approved at the February meeting of the Housing and Communities Committee and has now been concluded. We are preparing a demolition programme to allow the site to be cleared as soon as is practically possible. Gilmour Avenue, Hardgate (Clydebank Gap Sites) As part of the wider development of our Clydebank Gap Site strategy we have identified a HRA gap site in the Hardgate area at Gilmour Avenue. The site was previously the location of timber garages on concrete bases. These have long since been demolished and the site has been beset with fly tipping issues for a number of years. We are currently undertaking site investigations, and are proposing to construct 2 semi-detached three bedroom homes at this location. As a result of some of the complexities and the scale of the site we are looking at the potential for a modular construction process and have developed a procurement strategy to deliver this. This would be the first of this type of construction within our wider More Homes West Dunbartonshire approach. We would anticipate submitting a planning application by the end of August. Silverton Regeneration Discussions are ongoing which will allow the Council to purchase the last remaining privately owned property in the defective surplus blocks this will allow us to demolish and consider opportunities to deliver new housing within
Page 8
the Silverton area. We will highlight proposals in future update reports to the Housing and Communities Committee. Buyback Programme The Council’s buyback programme which incorporates the Mortgage to Rent Scheme purchased 16 new homes to date in 2022/23. In 2023/24 to date we have already 9 new homes at an average purchase cost of £101,000. In 2023/24 and following approval of the Strategic Housing Investment Plan by the Housing and Communities Committee in November 2022 and subsequently the decision by West Dunbartonshire Council in March 2023 to deliver an enhanced Housing Capital Investment Programme including additional funding for buyback purchases we are now scaling up ambition around our buyback programme. In 2023/24 and in each of the subsequent years up to and including 2027/28 we plan to deliver 60 new homes each year meaning a minimum of 300 new Council homes to meet identified need. The additional funding that was approved by the West Dunbartonshire Council meeting of 1 March 2023 will target larger family homes to meet this specific need. To meet these defined targets we will add additional resources within the Housing team, and we will also refresh our Buyback Policy. This update policy will be submitted to the meeting of the Housing and Communities Committee in November 2023. The Scottish Government announced on 19 July 2023 in response to the recommendations of the Temporary Accommodation Task and Finish Group that they will invest a minimum of £60 million through the Affordable Housing Supply Programme in 2023-2024 to support a national acquisition plan. The specific targeting of funds within the Affordable Housing Supply Programme for buyback purchases presents an opportunity to further accelerate purchases in 2023/24 and we will work closely with the Scottish Government in maximising this potential. There will require to be a close linkage between the acceleration of buyback purchases and reducing the use of temporary accommodation. At present we are assuming Scottish Government Affordable Housing Supply Programme funding of £3m to assist in meeting our ambitions in 2023/24. 4.5 The Housing Development Team are continuously looking for opportunities to provide additional new build council homes and will bring any potential site to the Housing and Communities Committee with as much information as possible as part of the regular More Homes update paper. 4.6 In June 2023, the Scottish Government published revised guidance in terms of the Affordable Housing Supply Programme. The main changes to the guidance were as follows:- • an uprated set of affordable housing investment benchmarks - these benchmarks are 16.9% higher than the previous set and are detailed in
Page 9
section 6.2 of this report (this percentage increase reflects the Scottish Social Housing Tender Price Index for the year to December 2022) • grant funding through the Affordable Housing Supply Programme are reminded that homes within new build and conversion projects will require to contain zero direct emissions heating systems • an additional 'quality measure’ benchmark for the installation of electric vehicle charge points has been introduced • the quality standards that would require to be met when purchasing ‘second-hand’ residential dwellings with vacant possession have been included • RSL social rent benchmark assumptions are reintroduced for grant assessment purposes, and • information is provided on the Scottish Government’s Heat Network Fund. 5. People Implications 5.1 An additional Senior Housing Development Officer role is required to deliver the increase and scaling up of the Council’s buyback programme. This will be met within the existing resources. We will also review surveying resource within the team. 6. Financial and Procurement Implications Financial 6.1 On 1 March 2023 Council approved the Housing Capital Programme 2023- 2028 which saw significant resources committed to the delivery of new council homes in West Dunbartonshire. An expenditure budget of £155m for the affordable housing supply programme is factored into the HRA Capital Programme this will be updated to reflect the income and expenditure highlighted within this report. As it currently stands, it is anticipated that this programme will complete on project life budget. 6.2 The uprated Affordable Housing Supply Programme grant benchmark assumptions were put in place on the publication of the revised guidance referenced in 4.6 of this report. The new benchmark assumptions are highlighted below:- RSL social rent £91,182 (3 person equivalent) Council social rent £83,584 (3 person equivalent) RSL mid-market rent £62,542
Page 10
(3 person equivalent) Council mid-market rent £57,281 (3 person equivalent) 6.3 In addition the following benchmark grant levels are available for additional quality measures as follows:- Delivering homes to Section 7, Silver Level, of the 2019 Building Regulations in respect of Energy for Space Heating (that is, full Bronze Level plus Aspect 2 of Silver Level). £2,338 per home (3 person equivalent benchmark) Provision of balconies within flatted developments to enable people to sit outside, where the provision of private or communal outdoor space cannot otherwise be accommodated £4,676 per home (3 person equivalent benchmark) ark) Provision of space for home working or study – to note that this benchmark does not apply to projects meeting current Housing for Varying Needs standards. In all other circumstances, grant applicants should demonstrate that additional space is necessary to deliver this measure in order for this benchmark to apply i.e. it is not possible to incorporate this within the design of the homes under current space standards. £4,092 per home (3 person equivalent benchmark) Digitally-enabling – when a tenant gets the keys to their home they should be able to arrange for an internet connection to ‘go live’ without the internet service provider having to provide additional cabling to the premises. £351 per home (3 person equivalent benchmark) Installation of ducting infrastructure for electric vehicle charge point connectors. £585 per connector(3 person equivalent benchmark Installation of electric vehicle charge points (excluding installation of ducting infrastructure) £585 per connector(3 person equivalent benchmark
Page 11
Installation of automatic fire suppression systems. £3,507 per home (3 person equivalent benchmark) Installation of heating systems which produce zero direct emissions at the point of use. £4,676 per home (3 person equivalent benchmark 6.4 Notwithstanding the expected increase in benchmark assumptions Housing and Finance Officers will continue to assess the ongoing affordability of future developments within the context of the Housing Revenue Account Business Plan. Procurement 6.5 All new development sites will be subject to new detailed procurement strategies and the opportunities highlighted within 4.4 of this report will continue to be prioritised. 6.6 Where the contract award is less than £213,000, authority is delegated to the Chief Officer in consultation with the Procurement Manager to instruct the award of contracts for the planned revenue and capital spend detailed in this report to suppliers providing the most economically advantageous offer to the Council. 6.7 All procurement activity carried out by the Council in excess of £2m is subject to a contract strategy. The contract strategy for new housing development within the HRA Capital Programme will be developed by the Corporate Procurement Unit in consultation with Housing Development Officers. The contract strategy will include, but is not limited to; contract scope, service forward plan, the market, procurement model and routes – including existing delivery vehicles, roles and responsibilities, risks, issues and opportunities and on-going contract management. Opportunities to maximise the positive social, economic and environmental impact for the Council through the relevant procurement processes will be developed in line with procurement policy. 7. Risk Analysis 7.1 All Council new build projects have their own Risk Register which highlights the risk within and out-with the project team’s control. These are maintained and adjusted on an on-going basis. 7.2 With any new build project there is a risk that as the projects develop the cost increases beyond the estimated contract cost. Any additional borrowing requirements, or conversely, cost savings will be reported to future meetings of the Housing and Communities Committee. However, this is mitigated through a target cost model approach in our current contract arrangements
Page 12
within the Scottish Procurement Alliance (SPA) framework and Scotland Excel. 8. Equalities Impact Assessment (EIA) 8.1 The proposal does not alter any existing policy or pattern of service delivery and so is not considered to require an equalities impact assessment. 9. Consultation 9.1 As part of our previous rent consultation exercise, 92% of respondents indicated their support for the Council’s ambitious plans to deliver the Housing Revenue Account (HRA) new council house build programme. In addition, there was positive support for the wider delivery of new build housing as part of the recent Local Housing Strategy. Regular updates on new build development are provided to the West Dunbartonshire Tenants and Residents Organisation at the bi-monthly liaison meetings. 10. Strategic Assessment 10.1 The Local Housing Strategy is the overarching document setting out the strategic direction for housing across all tenures and informs the future investment in housing and related services across West Dunbartonshire. 10.2 Having considered all the Council’s strategic priorities, this report and the provision of new supply social housing for rent contributes greatly to all strategic priorities. Peter Barry Chief Officer, Housing and Employability Date: 9 August 2023 Person to Contact: John Kerr – Housing Development and Homelessness Manager, Housing Development and Homelessness Team, Housing and Employability, telephone: 07793717981, email: john.kerr@west-dunbarton.gov.uk Appendices: None Background Papers: West Dunbartonshire Council’s Local Housing Strategy Local Housing Strategy, Health Inequalities Impact Assessment Wards Affected: All