WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer, Housing and Employability
Housing and Communities Committee: 23 August 2023
__________________________________________________________________
Subject: More Homes West Dunbartonshire – West Dunbartonshire Council
Affordable Housing Supply Delivery Programme 
1. Purpose
1.1 This purpose of this report is to provide the Housing and Communities
Committee an update on progress with West Dunbartonshire’s More Homes
Programme which oversees the delivery of the Council’s new home building
programme.
2. Recommendations
2.1 It is recommended that the Housing and Communities Committee:
(i) Note the content of the report and the progress made to date in the
delivery of the Council’s More Homes West Dunbartonshire approach;
and
(ii) Note the revised Affordable Housing Supply Programme benchmark
assumptions outlined in paragraph 6.2 of this report.
3. Background
3.1 In West Dunbartonshire the Affordable Housing Supply Programme (AHSP) is
delivered through a More Homes West Dunbartonshire strategic approach
which has successfully delivered over 1000 new affordable homes in West
Dunbartonshire to date and includes the Council’s own ambitious New House
Building Programme.
3.2 The Council’s latest practical completion took place at the Queens Quay
development in September 2022 delivering 29 new Council homes in a key
regeneration area as part of a wider development which has delivered 146
new social rented homes.  These are first residential properties to be heated
from the Council’s Queens Quay District Heating Network. This development
has been recognised at recent housing sector awards winning the won a
Silver Medal at the Scottish Design Awards and a finalist at both the Scottish
Homes Awards and Homes for Scotland Awards 2023. 
3.3 These 29 new homes, are in addition to the completion of the Council’s first
fully dementia designed development at Creveul Court, Alexandria and other
exemplar developments in Haldane, Aitkenbar, Bellmsyre, Dumbarton
ITEM 8

Page 2

Harbour and St Andrews, Clydebank.  The Council have now completed 12
new build developments since 2013 and are the largest developer of social
homes in West Dunbartonshire delivering 496 new homes to date as outlined
in Table 1 below:
Table 1:  Completed Council New Build
Project No. of
Units
Completion
Date
Granville Street (Phase 1), Clydebank 24 July 2013
Miller Road, Alexandria 15 October 2013
Granville Street (Phase 2), Clydebank 9 February 2014
Central Bellsmyre, Dumbarton 36 December 2014
Hillstreet Square, Dumbarton 37 August 2015
Second Avenue, Clydebank 40 April 2018
Creveul Court, Alexandria 22 April 2021
Aitkenbar Primary School 55 July2021
Haldane Primary School 58 August 2021
St Andrews, Clydebank 126 October 2021
Dumbarton Harbour, Dumbarton 45 December 2021
Queens Quay, Site B, Clydebank 29 August 2022
Totals 496
3.4 The Strategic Housing Investment Plan (SHIP) 2023-2027, outlining West
Dunbartonshire’s Affordable Housing Supply Programme through the More
Homes West Dunbartonshire approach was approved by the Housing and
Communities Committee in November 2022. The SHIP outline plans to meet
the Council Administration’s aim of delivering 2500 new affordable and social
rented homes over the next 10 years.  The Council has recently received
positive feedback from the Scottish Government in respect of our SHIP.  Work
has now commenced on the delivery of the new Strategic Housing Investment
Plan which will be submitted to the Housing and Communities Committee in
November 2023.
4. Main Issues
More Homes West Dunbartonshire - Delivery Programme
4.1 Building new affordable homes has an important role to play in revitalising
local economies and assisting with post-pandemic and economic recovery
plans, negating the impacts of the current cost of living crisis and combatting
poverty including child poverty.  It is also clear that the need for affordable
homes has and will increase in the current ongoing economic environment.
Our More Homes West Dunbartonshire approach is an ambitious plan that
aims to continue the positive momentum of the delivery of much needed
Council homes in West Dunbartonshire and will significantly assist the
Council’s aim to deliver 2500 new social and affordable homes by 2032.
4.2 As the biggest affordable housing developer in West Dunbartonshire, the
Council has identified a number of future development sites for new council
homes to address existing and new housing need. The design of these homes
will further develop, improve and exceed current best practice, providing
sustainable homes using innovative technology and delivering on our low

Page 3

carbon ambitions including passivhaus and other net zero carbon
opportunities.
4.3 The Strategic Housing Investment Plan and HRA Capital Plan outlined the
plans the Council have for meeting their new build ambitions.  Some of the
initial plans were and continue to be impacted as a result of global issues
revised new build targets for the Council are outlined below:
Table 2: Council New Build Programme
*Current Planning figures
Site/Developer Number of
Units
Number of
Specialist
Provision
Est Site
Start
Est Completion
Date
Clydebank
East,
Clydebank
88 9
On Site
January
2023
Spring 2025
Pappert,
Bonhill
Alexandria
26 3
Winter
2023/24
Winter 2024/25
Willox Park 17 17 Winter
2023/24
Winter 2024/25
Bonhill Gap
Sites* 34 4 Winter
2023/24
Winter 2024/25
Bank Street,
Alexandria
22 22 Winter
2023/24
Winter 2024/25
Mount
Pleasant
19 19 Winter 
2023/24
Spring 2025
Queens Quay
Site C
100 10 Spring
2024
Spring 2025
Clydebank
Health Centre*
38 5 Spring
2024
Spring 2025
Dennystoun
Forge
20 20 Spring 
2024 
Winter 2024
Clydebank
Gap Sites*
(Gilmour
Avenue)
50 10 Spring
2024
Summer 2025
Silverton
Regeneration
tbc tbc tbc tbc
Buyback
Scheme (60
per year)
300 36 2023/24 2027/28
714 units 155 units

Page 4

4.4 Updates for each site are noted below:
Clydebank East: 
Works commenced on this development on 23 January 2023, as reported to
the Housing and Communities Committee in February 2023 the initial
programme is for the remedial works and external drainage and this being
progressed in close collaboration with the Council’s wider regulatory role, a
construction site start will commence in early August.  The total programme
for the works will be 116 weeks.
This development will deliver 88 new homes and has been designed to meet
the housing need within the wider West Dunbartonshire area, the table below
shows the housing mix:
House Type Sustainability Standard Number of New
Homes
Wheelchair Bungalow
3bed/4person
Net Zero 3
House 3bed/5person Net Zero 15
House 4 bed/7person Net Zero 12
House 4 bed/9 person Net Zero 8
Cottage Flat 1 bed/2 person Net Zero 4
Cottage Flat 2 bed/3 person Net Zero 4
Flat 1 bed/2person Net Zero 16
Flat 2 bed/4 person Net Zero 24
Wheelchair Flat 1 bed/2person Net Zero 2
All houses are designed to the Housing for Various Needs Standard (HfVN).
There will be 9 fully Wheelchair (WCH) accessible properties.  The 4 and 5
bedroom homes will all have ground floor double bedrooms.  
The development at Clydebank East will see the completion of a major
housing led regeneration of a key priority area identified in the Local Housing
Strategy and will be the Council’s first fully zero carbon housing development
and marks a significant milestone in our transition to net zero approved at the
August 2022 meeting of the Housing and Communities Committee.  Publicity
is planned to mark the significant milestone on terms of a site start.
We are still currently engaged with the Scottish Government in terms of
finalising the grant award, as reported previously we have sought above
benchmark grant and our submission is currently being assessed by the
Scottish Government’s technical team. Our request is proportionate based on
the high levels of remediation costs but in terms of context our ask is
comparable with the grant awards made to the 2 housing association who
partnered the Council in the delivery of the new housing at Queens Quay.
We anticipate that following the decision by the Planning Committee on 2
August to delegate authority for the street names in respect of this
development, this will be completed in advance of the 1st September this will

Page 5

allow application for utility connections for the project, a critical element of the
development process.
Pappert, Bonhill
Following the review of the design proposals for the Pappert development the
housing mix is as follows:-
House Type Sustainability Standard Number of New
Homes
House 3bed/5 person Passivhaus 6
House 3bed/5 person Net Zero 6
House 4bed/6person Net Zero 4
House 4bed/7person Net Zero 1
Flat 2bed/3person w/c Net Zero 3
Flat 1 bed/2person Net Zero 6
A planning application has been submitted and we anticipate planning
permission for this development at the Planning Committee of 20th September
2023, this will then enable a site start later this year or early in 2024.
Willox Park, Doveholm, Dumbarton
The development of 17 new homes to be delivered at the former care home
site continues within the design phase towards a full planning application. We
have appointed an engineering consultant that will allow the project to be
advanced to planning and building warrant.  We have now revised our project
timescales and anticipate a site start in March 2024.
Bonhill Gap Site Strategy
The pre-planning application process has commenced on the development of
the 3 separate gap sites which are contained within this wider development. 
We are in the process of procuring engineering consultants as we move
closer to a full planning application.
We have altered some of the initial design plans to incorporate a number of
adaptable 6/7 bed homes within the development to meet identified housing
need. 
Bank Street, Alexandria
The council is currently developing a proposal for 22 sheltered/amenity
housing units in partnership with the HSCP. This will include an options
appraisal in terms of the existing provision within the local area.
A landscape architect has been procured for the design team and engineering
consultants (structural, civil, mechanical and electrical) will be procured
shortly.

Page 6

Mount Pleasant, Old Kilpatrick
The demolition of the former care home at the site completed in December
2022 ahead of schedule.
We have had an initial consultation with the Old Kilpatrick Community Council
where we presented our concept of providing housing in a similar style to
Creveul Court, Alexandria. This was accompanied by a leaflet distributed to all
residents adjacent to the site.  The development will consist of 19 new homes.
The construction procurement strategy has been signed off by relevant
Council Chief Officers and will be presented to the Tendering Committee of 20
September 2023. 
A pre-planning application was submitted in June and we anticipate a
planning application to be submitted in August.
Queens Quay, Site C, Clydebank
The Council has been developing a design to deliver a projected 20 units on
this site to complement the housing mix within sites A and B.  This
development will also be designed to meet low/zero carbon principles and
linked to the Queens Quay district heating network
.
Pre-planning response was received on the 25 February highlighting concern
of the WDC development proceeding in isolation. We have adopted a
proactive response to this issue and have developed masterplan diagrams
incorporating the surrounding sites and have carried out valuations on the
adjacent site to Queens Quay C with a view to purchasing additional land to
deliver more affordable housing in the Queens Quay regeneration site.  If this
is achieved we would seek to develop a mixed tenure approach to any
expanded development site delivering 100 new affordable homes. We are
urgently seeking discussion with CRL (Clydeside Regeneration Limited) to
progress the possibility of acquiring this additional land and will be able to
draw down Scottish Government grant to enable this.
Clydebank Health Centre
As approved by the Housing and Communities Committee on 3 May 2023, the
acquisition of the site was completed on 22nd June. A Security contractor has
been engaged and will be in place until demolition strategy can be completed.
We are currently developing an optimum housing mix for this development
which meets the requirements of the Planning brief. 
Dennystoun Forge Gypsy/Traveller Site
A submission was made to the Scottish Government for support funding from
their Gypsy/Traveller Accommodation Fund for significant improvements to

Page 7

the Dennystoun Forge site, including new energy efficient chalet type
accommodation following a consultation exercise with site residents. 
However, we were notified that this submission was unsuccessful at this point.
We have since engaged the Scottish Government following the outcome of
this and have provided additional information to the Scottish Government in
support of the application.  
In another positive development the Council’s Housing Development Officer
has been providing support to the tenants within the Dennystoun Forge site to
establish a registered tenants association, the absence of a recognised
tenants group and ongoing site presence was seen as a relative weakness in
terms of the initial submission.  
We anticipate that following the new information provided to support our
application for funding Scottish Government officials will reassess the
application when parliament commences following recess 
Queen Mary Avenue, Clydebank (Clydebank Gap Sites)
The transfer of the site at Queen Mary Avenue, Clydebank with vacant
possession at the cost of £140,000 from the Council’s General Fund to the
Housing Revenue Account for the delivery of new Council homes was
approved at the February meeting of the Housing and Communities
Committee and has now been concluded.  We are preparing a demolition
programme to allow the site to be cleared as soon as is practically possible. 
Gilmour Avenue, Hardgate (Clydebank Gap Sites)
As part of the wider development of our Clydebank Gap Site strategy we have
identified a HRA gap site in the Hardgate area at Gilmour Avenue.  The site
was previously the location of timber garages on concrete bases.  These have
long since been demolished and the site has been beset with fly tipping
issues for a number of years.  
We are currently undertaking site investigations, and are proposing to
construct 2 semi-detached three bedroom homes at this location.  As a result
of some of the complexities and the scale of the site we are looking at the
potential for a modular construction process and have developed a
procurement strategy to deliver this.  This would be the first of this type of
construction within our wider More Homes West Dunbartonshire approach.
We would anticipate submitting a planning application by the end of August.
Silverton Regeneration
Discussions are ongoing which will allow the Council to purchase the last
remaining privately owned property in the defective surplus blocks this will
allow us to demolish and consider opportunities to deliver new housing within

Page 8

the Silverton area.  We will highlight proposals in future update reports to the
Housing and Communities Committee.
Buyback Programme
The Council’s buyback programme which incorporates the Mortgage to Rent
Scheme purchased 16 new homes to date in 2022/23.  In 2023/24 to date we
have already 9 new homes at an average purchase cost of £101,000.
In 2023/24 and following approval of the Strategic Housing Investment Plan
by the Housing and Communities Committee in November 2022 and
subsequently the decision by West Dunbartonshire Council in March 2023 to
deliver an enhanced Housing Capital Investment Programme including
additional funding for buyback purchases we are now scaling up ambition
around our buyback programme.  In 2023/24 and in each of the subsequent
years up to and including 2027/28 we plan to deliver 60 new homes each year
meaning a minimum of 300 new Council homes to meet identified need.  
The additional funding that was approved by the West Dunbartonshire Council
meeting of 1 March 2023 will target larger family homes to meet this specific
need.  To meet these defined targets we will add additional resources within
the Housing team, and we will also refresh our Buyback Policy.  This update
policy will be submitted to the meeting of the Housing and Communities
Committee in November 2023.
The Scottish Government announced on 19 July 2023 in response to the
recommendations of the Temporary Accommodation Task and Finish Group
that they will invest a minimum of £60 million through the Affordable Housing
Supply Programme in 2023-2024 to support a national acquisition plan.  The
specific targeting of funds within the Affordable Housing Supply Programme
for buyback purchases presents an opportunity to further accelerate
purchases in 2023/24 and we will work closely with the Scottish Government
in maximising this potential. There will require to be a close linkage between
the acceleration of buyback purchases and reducing the use of temporary
accommodation.  At present we are assuming Scottish Government
Affordable Housing Supply Programme funding of £3m to assist in meeting
our ambitions in 2023/24.
4.5 The Housing Development Team are continuously looking for opportunities to
provide additional new build council homes and will bring any potential site to
the Housing and Communities Committee with as much information as
possible as part of the regular More Homes update paper.
4.6 In June 2023, the Scottish Government published revised guidance in terms
of the Affordable Housing Supply Programme.  The main changes to the
guidance were as follows:-
• an uprated set of affordable housing investment benchmarks - these
benchmarks are 16.9% higher than the previous set and are detailed in

Page 9

section 6.2 of this report (this percentage increase reflects the Scottish
Social Housing Tender Price Index for the year to December 2022)
• grant funding through the Affordable Housing Supply Programme are
reminded that homes within new build and conversion projects will require
to contain zero direct emissions heating systems
• an additional 'quality measure’ benchmark for the installation of electric
vehicle charge points has been introduced
• the quality standards that would require to be met when purchasing
‘second-hand’ residential dwellings with vacant possession have been
included
• RSL social rent benchmark assumptions are reintroduced for grant
assessment purposes,  and
• information is provided on the Scottish Government’s Heat Network Fund.
5. People Implications
5.1 An additional Senior Housing Development Officer role is required to deliver
the increase and scaling up of the Council’s buyback programme.  This will be
met within the existing resources.  We will also review surveying resource
within the team.
6. Financial and Procurement Implications
Financial
6.1 On 1 March 2023 Council approved the Housing Capital Programme 2023-
2028 which saw significant resources committed to the delivery of new council
homes in West Dunbartonshire.  An expenditure budget of £155m for the
affordable housing supply programme is factored into the HRA Capital
Programme this will be updated to reflect the income and expenditure
highlighted within this report.  As it currently stands, it is anticipated that this
programme will complete on project life budget.
6.2 The uprated Affordable Housing Supply Programme grant benchmark
assumptions were put in place on the publication of the revised guidance
referenced in 4.6 of this report.  The new benchmark assumptions are
highlighted below:-
RSL social rent £91,182
(3 person equivalent)
Council social rent £83,584
(3 person equivalent)
RSL mid-market rent £62,542

Page 10

(3 person equivalent)
Council mid-market rent £57,281
(3 person equivalent)
6.3 In addition the following benchmark grant levels are available for additional
quality measures as follows:-
Delivering homes to Section 7,
Silver Level, of the 2019  Building
Regulations in respect of Energy for
Space Heating (that is, full Bronze
Level plus Aspect 2 of Silver Level).
£2,338 per home
(3 person
equivalent
benchmark)
Provision of balconies within flatted
developments to enable people to 
sit outside, where the provision of
private or communal outdoor space 
cannot otherwise be accommodated
£4,676 per home
(3 person 
equivalent 
benchmark)
ark)
Provision of space for home working
or study – to note that this
benchmark does not apply to
projects meeting current Housing for
Varying Needs standards.
In all other circumstances, grant
applicants should demonstrate that
additional space is necessary to
deliver this measure in order for this
benchmark to apply i.e. it is not
possible to incorporate this within
the design of the homes under
current space standards.
£4,092 per home
(3 person
equivalent
benchmark)
Digitally-enabling – when a tenant
gets the keys to their home they 
should be able to arrange for an
internet connection to ‘go live’
without the internet service provider
having to provide additional 
cabling to the premises.
£351 per home
(3 person 
equivalent 
benchmark)
Installation of ducting infrastructure
for electric vehicle charge point
connectors.
£585 per
connector(3 person
equivalent
benchmark
Installation of electric vehicle charge
points (excluding installation of 
ducting infrastructure)
£585 per 
connector(3 person
equivalent 
benchmark

Page 11

Installation of automatic fire suppression
systems.
£3,507 per home
(3 person
equivalent
benchmark)
Installation of heating systems which
produce zero direct emissions at 
the point of use.
£4,676 per home
(3 person 
equivalent 
benchmark
6.4 Notwithstanding the expected increase in benchmark assumptions Housing
and Finance Officers will continue to assess the ongoing affordability of future
developments within the context of the Housing Revenue Account Business
Plan.
Procurement
6.5 All new development sites will be subject to new detailed procurement
strategies and the opportunities highlighted within 4.4 of this report will
continue to be prioritised.
6.6 Where the contract award is less than £213,000, authority is delegated to
the Chief Officer in consultation with the Procurement Manager to instruct the
award of contracts for the planned revenue and capital spend detailed in this
report to suppliers providing the most economically advantageous offer to the
Council.
6.7 All procurement activity carried out by the Council in excess of £2m is
subject to a contract strategy. The contract strategy for new housing
development within the HRA Capital Programme will be developed by the
Corporate Procurement Unit in consultation with Housing Development
Officers. The contract strategy will include, but is not limited to; contract
scope, service forward plan, the market, procurement model and routes –
including existing delivery vehicles, roles and responsibilities, risks, issues
and opportunities and on-going contract management. Opportunities to
maximise the positive social, economic and environmental impact for the
Council through the relevant procurement processes will be developed in line
with procurement policy.
7. Risk Analysis
7.1 All Council new build projects have their own Risk Register which highlights
the risk within and out-with the project team’s control.  These are maintained
and adjusted on an on-going basis.
7.2 With any new build project there is a risk that as the projects develop the cost
increases beyond the estimated contract cost.  Any additional borrowing
requirements, or conversely, cost savings will be reported to future meetings
of the Housing and Communities Committee. However, this is mitigated
through a target cost model approach in our current contract arrangements

Page 12

within the Scottish Procurement Alliance (SPA) framework and Scotland
Excel.
8. Equalities Impact Assessment (EIA)
8.1 The proposal does not alter any existing policy or pattern of service delivery
and so is not considered to require an equalities impact assessment.
9. Consultation
9.1 As part of our previous rent consultation exercise, 92% of respondents
indicated their support for the Council’s ambitious plans to deliver the Housing
Revenue Account (HRA) new council house build programme. In addition,
there was positive support for the wider delivery of new build housing as part
of the recent Local Housing Strategy.  Regular updates on new build
development are provided to the West Dunbartonshire Tenants and Residents
Organisation at the bi-monthly liaison meetings.
10. Strategic Assessment
10.1 The Local Housing Strategy is the overarching document setting out the
strategic direction for housing across all tenures and informs the future
investment in housing and related services across West Dunbartonshire.
10.2 Having considered all the Council’s strategic priorities, this report and the
provision of new supply social housing for rent contributes greatly to all
strategic priorities. 
Peter Barry
Chief Officer, Housing and Employability
Date: 9 August 2023
Person to Contact: John Kerr – Housing Development and Homelessness
Manager, Housing Development and Homelessness
Team, Housing and Employability, telephone:
07793717981, email: john.kerr@west-dunbarton.gov.uk
Appendices: None
Background Papers: West Dunbartonshire Council’s Local Housing Strategy
Local Housing Strategy, Health Inequalities Impact
Assessment
Wards Affected: All