WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer, Housing and Employability
Housing and Communities Committee: 3 May 2023 
___________________________________________________________________
Subject: Enhanced Standards for Multi Storey Living – A strategy for
enhancing the experience of living in a multi storey home in West
Dunbartonshire 2023/28
1. Purpose
1.1 The purpose of this report is to provide the Housing and Communities
Committee with an update on the recent resident consultation which gathered
ideas on how to enhance our 19 multi storey homes and seek approval to
implement a strategy to enhance living standards in these homes by
delivering a number of improvement actions.
2. Recommendations
2.1 It is recommended that the Housing and Communities Committee:
(i) note the contents of this report and the feedback received from current and
future tenants regarding their experiences of living in our multi storey flat
homes across the local authority area: and
(ii) approve the strategic approach  outlined with the Strategy
document and improvement action plan developed to address the
findings of the consultative exercise; and
(iii) instruct the Chief Officer Housing and Employability to fully
implement the strategy and associated action plan;
3. Background
3.1 West Dunbartonshire Council have 19 multi storey blocks of flats containing
1,232 homes. The blocks contain one, two and three bedroom flats. The
blocks were built in the 1960s using concrete panels and were insulated and
received new double glazing between 2010 and 2015 to make the homes
more energy efficient.  Apart from the three blocks at Littleholm, which are
connected to the gas network, the remaining blocks use electric storage
heaters as their main form of heating.
3.2 All blocks with the exception of one block are mixed tenure, while the Council
is the majority owner in each of the blocks, the presence of owner occupiers
and private landlords’ means any major works have got to be agreed by all
parties.
3.3 The homes are now around 60 years old and we have committed to review
investment to ensure that we are putting in place the appropriate resource to
enable them to continue to be attractive homes which contribute positively to
our communities.
ITEM 14

Page 2

3.4 Indeed, the recent resident survey showed that residents liked the views and
the generous sizes and storage space offered by the flats, however the survey
also offered up numerous areas for improvement which this survey will look
to take forward.  In the appendixes of this paper there is a report detailing the
survey findings in detail. 
4. Main Issues
4.1 Consultation
We surveyed residents using survey monkey for 12 weeks between October
and December 2022.  We received a good response from all blocks and the
residents have provided us with a clear steer in terms of what they would like
to see improved in their home and block.
4.2 A challenge which emerged from the consultation findings is that many of the
improvements people would like do not represent an enhanced living standard
but are planned investment through the Housing Capital Investment
Programme.  For example, similarly to the recent rent consultation exercises
kitchens and bathroom renewals and heating upgrades figured high in terms
of priorities within the responses.
4.3 We also surveyed those on the Council housing waiting list and 40% of those
who responded indicated that they would like to live in a multi storey flat and
provided improvement suggestions, many of which aligned with what tenants
would like to see such as improved estate management of the blocks.
4.4 Identifying priorities and creating an action plan
Taking the survey findings we identified key themes across the blocks which
will form the overarching structure of the wider strategic approach and action
plan. These tackle the common requests from our residents such as
improving heating and hot water and deep cleaning and reimagining the
common areas.
4.5 The wider approach will continue to be developed with tenants and residents
to ensure that they reflect the needs of each block.  As we have also reviewed
findings on a block by block basis to ensure that we are identifying block
specific requests and these can be captured within the wider strategic
approach to enhance the living standards in all our multi story flats across
West Dunbartonshire.
4.6 An improvement action plan has been developed to deliver the enhanced
standards and this is attached as Appendix 1a of this report.
5. People Implications
5.1 A Senior Housing Development Officer will be tasked with effective project
management to deliver the strategic aims contained within the strategy
document and associated action plan. In addition, developing appropriate

Page 3

service responses in areas where improvements actions have been identified
will be managed from within existing resources within the Housing Revenue
Account.
6. Financial and Procurement Implications
6.1 Financial
On 1 March 2023 Council approved the Housing Capital Programme 2023-
2028 which committed resources of £4.25m to deliver an enhanced standard
for multi storey living within the HRA Capital Programme. Housing and
Finance Officers will continue to assess the ongoing affordability of future
developments within the context of the Housing Revenue Account Business
Plan.
Procurement
6.2  Where any contract award is less than £213,000 to deliver this strategy,
authority is delegated to the Chief Officer, Housing and Employability in
consultation with the Procurement Manager to instruct the award of contracts
for the planned revenue and capital spend detailed in this report to suppliers
providing the most economically advantageous offer to the Council.
6.5 All procurement activity carried out by the Council in excess of £2m is
subject to a contract strategy. The contract strategy for new housing
development within the HRA Capital Programme will be developed by the
Corporate Procurement Unit in consultation with Housing Development
Officers. The contract strategy will include, but is not limited to; contract
scope, service forward plan, the market, procurement model and routes –
including existing delivery vehicles, roles and responsibilities, risks, issues
and opportunities and on-going contract management. Opportunities to
maximise the positive social, economic and environmental impact for the
Council through the relevant procurement processes will be developed in line
with procurement policy.
7. Risk Analysis
7.1 There is a risk that failure to invest strategically in our multi storey flats will have
a negative impact on their ongoing viability and in turn would lead to a loss of
rental income and could potentially impact on the ongoing sustainability of the
HRA Business Plan.  In addition an ineffective approach to strategic asset
management of our housing stock would attract an adverse reaction from the
Scottish Housing Regulator.
7.2 We maintain risk registers for each project which highlights the risk within and
out-with the project team’s control. These are maintained and adjusted on an
on-going basis.
8. Equalities Impact Assessment (EIA)

Page 4

8.1  An EIA screening has been undertaken by officers and no issues were
identified.
9 . Consultation
9.1      As above, we carried out a 12 week consultative exercise and received a
good response from residents and those on the waiting list.  We will
continue to develop the plans in conjunction with tenants and residents as
we further develop a wider investment programme and a monitoring
framework.
10. Strategic Assessment
10.1 The proposals contained in this report directly address all of the Council’s
strategic priorities. The investment in, and provision of attractive affordable
housing will also indirectly support the objective of economic growth and
employability through supporting employment and improving place
attractiveness.
Peter Barry
Chief Officer, Housing and Employability
Date:  18 April 2023
__________________________________________________________________
Person to Contact: John Kerr – Housing Development and Homelessness
Manager, Housing Development and Homelessness,
Housing and Employability, telephone: 07793717981,
email: John.Kerr@west-dunbarton.gov.uk
Appendices: Appendix 1/1a: Enhanced Living Standards Strategy and
Improvement Action Plan 
Background Papers: EIA. March 2023 
Survey findings report, Housing Development 2022
Wards Affected: All