WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer, Housing and Employability
Housing and Communities Committee: 3 May 2023
__________________________________________________________________
Subject: More Homes West Dunbartonshire – West Dunbartonshire Council
Affordable Housing Supply Delivery Programme 
1. Purpose
1.1 This purpose of this report is to provide the Housing and Communities
Committee an update on progress with West Dunbartonshire’s More Homes
Programme which oversees the delivery of the Council’s new home building
programme.
2. Recommendations
2.1 It is recommended that the Housing and Communities Committee:
(i) Note the content of the report and the progress made to date in the
delivery of the Council’s More Homes West Dunbartonshire approach;
(ii) Approve the undertaking to conduct all necessary procurement exercises
for the new identified sites within the Future New Build – West
Dunbartonshire Affordable Housing Supply Programme identified in
section 4.4 of this report to deliver new council homes;
(iii) Approve the acquisition of the former Clydebank Health Centre site at the
cost of £584,500 from NHS Greater Glasgow and Clyde for the delivery of
new Council homes;
(iv) Note the addition of Gilmour Avenue, Hardgate to the More Homes West
Dunbartonshire development programme;
(v) Note the scaling up of the Council’s buyback programme and the actions
required to meet this ambition;
(vi) Note the reduction in housing units within the Pappert development from
27 to 26 and note that this will maintain 112 bedspaces within the
development; and
(vii) Note the success of the Council’s Queens Quay housing development
which has been shortlisted for the Homes for Scotland Awards,
Development of the Year (Large)
ITEM 12

Page 2

3. Background
3.1 In West Dunbartonshire the Affordable Housing Supply Programme (AHSP) is
delivered through a More Homes West Dunbartonshire strategic approach
which has successfully delivered over 1000 new affordable homes in West
Dunbartonshire to date and includes the Council’s own ambitious New House
Building Programme.
3.2 The Council’s latest practical completion took place at the Queens Quay
development in September 2022 delivering 29 new Council homes in a key
regeneration area as part of a wider development which has delivered 146
new social rented homes.  These are first residential properties to be heated
from the Council’s Queens Quay District Heating Network. This development
has also been shortlisted in the prestigious Homes for Scotland Awards 2023
in the Large Development of the Year category, the award will be presented to
the chosen development on 26th May at a ceremony in Edinburgh. 
3.3 These 29 new homes, are in addition to the completion of the Council’s first
fully dementia designed development at Creveul Court, Alexandria and other
exemplar developments in Haldane, Aitkenbar, Bellmsyre, Dumbarton
Harbour and St Andrews, Clydebank.  The Council have now completed 12
new build developments since 2013 and are the largest developer of social
homes in West Dunbartonshire delivering 496 new homes to date as outlined
in Table 1 below:
Table 1:  Completed Council New Build
Project No. of
Units
Completion
Date
Granville Street (Phase 1), Clydebank 24 July 2013
Miller Road, Alexandria 15 October 2013
Granville Street (Phase 2), Clydebank 9 February 2014
Central Bellsmyre, Dumbarton 36 December 2014
Hillstreet Square, Dumbarton 37 August 2015
Second Avenue, Clydebank 40 April 2018
Creveul Court, Alexandria 22 April 2021
Aitkenbar Primary School 55 July2021
Haldane Primary School 58 August 2021
St Andrews, Clydebank 126 October 2021
Dumbarton Harbour, Dumbarton 45 December 2021
Queens Quay, Site B, Clydebank 29 August 2022
Totals 496
3.4 The Strategic Housing Investment Plan (SHIP) 2023-2027, outlining West
Dunbartonshire’s Affordable Housing Supply Programme through the More
Homes West Dunbartonshire approach was approved by the Housing and
Communities Committee in November 2022. The SHIP outline plans to meet
the Council Administration’s aim of delivering 2500 new affordable and social
rented homes over the next 10 years.  The Council has recently received
positive feedback from the Scottish Government in respect of our recent
SHIP.

Page 3

4. Main Issues
More Homes West Dunbartonshire - Delivery Programme
4.1 Building new affordable homes has an important role to play in revitalising
local economies and assisting with post-pandemic recovery plans, negating
the impacts of the current cost of living crisis and combatting poverty.  It is
also clear that the need for affordable homes has and will increase in the
current ongoing economic environment. Our More Homes West
Dunbartonshire approach is an ambitious plan that aims to continue the
positive momentum of the delivery of much needed Council homes in West
Dunbartonshire and will significantly assist the Council’s aim to deliver 2500
new social and affordable homes by 2032.
4.2 As the biggest affordable housing developer in West Dunbartonshire, the
Council has identified a number of future development sites for new council
homes to address existing and new housing need. The design of these homes
will further develop, improve and exceed current best practice, providing
sustainable homes using innovative technology and delivering on our low
carbon ambitions including passivhaus and other net zero carbon
opportunities.
4.3 The Strategic Housing Investment Plan and HRA Capital Plan outlined the
plans the Council have for meeting their new build ambitions.  Some of the
initial plans were and continue to be impacted as a result of global issues
revised new build targets for the Council are outlined below:
Table 2: Council New Build Programme
Site/Developer Number of
Units
Number of
Specialist
Provision
Est Site
Start
Est Completion
Date
Clydebank
East,
Clydebank
88 9
On Site
January
2023
Spring 2025
Pappert,
Bonhill
Alexandria
26 3
Autumn
2023
Winter 2024/25
Willox Park 17 17 Winter
2023/24
Winter 2024/25
Bonhill Gap
Sites* 34 4 Winter
2023/24
Winter 2024/25
Bank Street,
Alexandria
20 20 Winter
2023/24
Winter 2024/25
Mount
Pleasant
19 19 Winter 
2023/24
Spring 2025
Queens Quay
Site C
100 10 Winter
2023/24
Spring 2025

Page 4

*Current Planning figures
4.4 Updates for each site are noted below:
Clydebank East: 
Works commenced on this development on 23 January 2023, as reported to
the Housing and Communities Committee in February 2023 the initial
programme is for the remedial works and external drainage, a construction
site start is programmed for May/June 2023.  The total programme for the
works will be 116 weeks.
This development will deliver 88 new homes and has been designed to meet
the housing need within the wider West Dunbartonshire area, the table below
shows the housing mix:
House Type Sustainability Standard Number of New
Homes
Wheelchair Bungalow
3bed/4person
Net Zero 3
House 3bed/5person Net Zero 15
House 4 bed/7person Net Zero 12
House 4 bed/9 person Net Zero 8
Cottage Flat 1 bed/2 person Net Zero 4
Cottage Flat 2 bed/3 person Net Zero 4
Flat 1 bed/2person Net Zero 16
Flat 2 bed/4 person Net Zero 24
Wheelchair Flat 1 bed/2person Net Zero 2
All houses are designed to the Housing for Various Needs Standard (HfVN).
There will be 9 fully Wheelchair (WCH) accessible properties.  The 4 and 5
bedroom homes will all have ground floor double bedrooms.  
The development at Clydebank East will see the completion of a major
housing led regeneration of a key priority area identified in the Local Housing
Strategy and will be the Council’s first fully zero carbon housing development
and marks a significant milestone in our transition to net zero approved at the
August 2022 meeting of the Housing and Communities Committee.  We will
ensure the construction site planned for May/June this year is communicated
to all stakeholders.
Clydebank
Health Centre*
38 5 Winter
2023/24
Spring 2025
Dennystoun
Forge
20 20 Spring 
2024 
Winter 2024
Clydebank
Gap Sites*
(Gilmour
Avenue)
50 10 Spring
2024
Summer 2025
Buyback
Scheme (60
per year)
308 36 2023/24 2027/28
720 units 153 units

Page 5

Pappert, Bonhill
We have reviewed the design proposals for the Pappert development and
following an assessment of housing demand information we have maximised
the number of the 3 bedroom homes with a ground floor bedroom.  While this
has the net effect of reducing the number of units in the wider development
from 27 to 26, it does not impact on the number of bedspaces within the
development.
House Type Sustainability Standard Number of New
Homes
House 3bed/5 person Passivhaus 6
House 3bed/5 person Net Zero 6
House 4bed/6person Net Zero 4
House 4bed/7person Net Zero 1
Flat 2bed/3person w/c Net Zero 3
Flat 1 bed/2person Net Zero 6
It is anticipated that a planning approval will be granted in August 2023, and a
site start in late 2023/early 2024.
Willox Park, Doveholm, Dumbarton
The development of the new homes to be delivered at the former care home
site continues within the design phase towards a full planning application. A
landscape architect has been procured for the design team, however the
appointment of engineering consultants (structural, civil, mechanical and
electrical) has been delayed as we were unable to appoint following a recent
tendering exercise.  Our development timescales have been updated as a
result of this setback.
Bonhill Gap Site Strategy
The pre-planning application process has commenced on the development of
the 3 separate gap sites which are contained within this wider development. 
We are in the process of procuring engineering consultants as we move
closer to a full planning application.
We have altered some of the initial design plans to incorporate a number of
adaptable 6/7 bed homes within the development to meet identified housing
need.
Bank Street, Alexandria
The council is currently developing a proposal for 21 sheltered/amenity
housing units in partnership with the HSCP. This will include an options
appraisal in terms of the existing provision within the local area.

Page 6

A landscape architect has been procured for the design team and engineering
consultants (structural, civil, mechanical and electrical) will be procured
shortly.
Mount Pleasant, Old Kilpatrick
The demolition of the former care home at the site completed in December
2022 ahead of schedule.
We have had an initial consultation with the Old Kilpatrick Community Council
where we presented our concept of providing housing in a similar style to
Creveul Court, Alexandria. 
An Employers Agent (NBM) have been appointed for this project, they were
previously the EA for the recently completed Queens Quay development.  The
construction procurement strategy is well advanced and will be implemented
following the completion of ongoing site investigations and feasibility studies
for the development. 
Queens Quay, Site C, Clydebank
The Council has been developing a design to deliver a projected 20 units on
this site to complement the housing mix within sites A and B.  This
development will also be designed to meet low/zero carbon principles and
linked to the Queens Quay district heating network
.
Pre-planning response was received on the 25 February highlighting concern
of the WDC development proceeding in isolation. We have adopted a,
proactive response to this issue and have developed masterplan diagrams
incorporating the surrounding sites and have carried out valuations on the
adjacent site to Queens Quay C with a view to purchasing additional land to
deliver more affordable housing in the Queens Quay regeneration site.  If this
is achieved we would seek to develop a mixed tenure approach to any
expanded development site. We anticipate discussions with CRL (Clydeside
Regeneration Limited) in May to progress the possibility of acquiring this
additional land.
Clydebank Health Centre
The Council are continuously looking for opportunities to provide additional
new build council homes and this includes through the Scottish Government’s
trawl process which seeks to utilise public sector land sales for the delivery of
key national ambitions which includes the delivery of new homes. The former
Clydebank Health Centre in Kilbowie Road, Clydebank was identified through
this process and approval was granted to acquire the site from NHS Greater
Glasgow and Clyde at the November meeting of the Housing and
Communities Committee for £707,400.
However, as reported to the February meeting of the Housing and
Communities Committee NHS Greater Glasgow and Clyde chose not to

Page 7

complete the transaction in financial year 2022/23, instead choosing to
conclude the sale of the land in financial year 2023/24.  As a result the
Council and NHS Greater Glasgow and Clyde reinstructed the District Valuer
to revalue the site to allow the acquisition to conclude in 2023/24.
A plan of the area is included as Appendix 1 to this report and has a gross site
area which extends to 0.98 ha (2.43 acres).  A valuation carried out by the
District Valuer in March 2023 placed a valuation of £1.5m for the site.
Tripartite discussions involving the Scottish Government, NHS Greater
Glasgow and Clyde have revised the previous agreement on a financial
assessment on the levels of abnormal costs within the site resulting in an offer
of £584,500 subject to Housing and Communities Committee approval.
If approval is granted the transfer will be carried out using the process set out
in the Scottish Public Finance Manual - Guidelines for the Transfer of Property
within the Scottish Public Sector.
Dennystoun Forge Gypsy/Traveller Site
A submission was made to the Scottish Government for support funding from
their Gypsy/Traveller Accommodation Fund for significant improvements to
the Dennystoun Forge site, including new energy efficient chalet type
accommodation following a consultation exercise with site residents. 
However, we were notified that this submission was unsuccessful at this point.
We have since engaged the Scottish Government following the outcome of
this and have provided additional information to the Scottish Government in
support of the application.  
In another positive development the Council’s Housing Development Officer
has been providing support to the tenants within the Dennystoun Forge site to
establish a registered tenants association, the absence of a recognised
tenants group and ongoing site presence was seen as a relative weakness in
terms of the initial submission.  
We anticipate that following the new information provided to support our
application for funding Scottish Government officials will reassess the
application in advanced of the parliamentary recess 
Queen Mary Avenue, Clydebank (Clydebank Gap Sites)
The transfer of the site at Queen Mary Avenue, Clydebank with vacant
possession at the cost of £140,000 from the Council’s General Fund to the
Housing Revenue Account for the delivery of new Council homes was
approved at the February meeting of the Housing and Communities
Committee and has now been concluded.  We are preparing a demolition
programme to allow the site to be cleared as soon as is practically possible.

Page 8

Gilmour Avenue, Hardgate (Clydebank Gap Sites)
As part of the wider development of our Clydebank Gap Site strategy we have
identified a HRA gap site in the Hardgate area at Gilmour Avenue.  The site
was previously the location of timber garages on concrete bases.  These have
long since been demolished and the site has been beset with fly tipping
issues for a number of years.  We are currently undertaking site
investigations, and are proposing to construct 2 semi-detached three bedroom
homes at this location.  As a result of some of the complexities and the scale
of the site we are looking at the potential for a modular construction process. 
This would be the first of this type of construction within our wider More
Homes West Dunbartonshire approach.
Buyback Programme
The Council’s buyback programme which incorporates the Mortgage to Rent
Scheme purchased 16 new homes to date in 2022/23.  A further 4 completed
in early April 2023.
In 2023/24 and following approval of the Strategic Housing Investment Plan
by the Housing and Communities Committee in November 2022 and
subsequently the decision by West Dunbartonshire Council in March 2023 to
deliver an enhanced Housing Capital Investment Programme including
additional funding for buyback purchases we are now scaling up ambition
around our buyback programme.  In 2023/24 and in each of the subsequent
years up to and including 2027/28 we plan to deliver 60 new homes each year
meaning a minimum of 300 new Council homes to meet identified need.  
The additional funding that was approved by the West Dunbartonshire Council
meeting of 1 March 2023 will target larger family homes to meet this specific
need.  To meet these defined targets we will add additional resource within
the Housing team, and we will also refresh our Buyback Policy.  This update
policy will be submitted to the meeting of the Housing and Communities
Committee in November 2023 
4.5 The Housing Development Team are continuously looking for opportunities to
provide additional new build council homes and will bring any potential site to
the Housing and Communities Committee with as much information as
possible as part of the regular More Homes update paper.
5. People Implications
5.1 An additional Senior Housing Development Officer role is required to deliver
the increase and scaling up of the Council’s buyback programme.  This will be
met within the existing resources outlined in Section 6 of this report.  We will
also review surveying resource within the team.

Page 9

6. Financial and Procurement Implications
Financial
6.1 On 1 March 2023 Council approved the Housing Capital Programme 2023-
2028 which saw significant resources committed to the delivery of new council
homes in West Dunbartonshire.  An expenditure budget of £155m for the
affordable housing supply programme is factored into the HRA Capital
Programme this will be updated to reflect the income and expenditure
highlighted within this report.  As it currently stands, it is anticipated that this
programme will complete on project life budget.
6.2 The acquisition of the Clydebank Health Centre site will be delivered within
the approved expenditure budget outlined in paragraph 6.1 of this report.  The
addition of the Gilmour Avenue is also incorporated within this expenditure
budget.  
6.3 The anticipated uprated Affordable Housing Supply Programme grant
benchmark assumptions will not be in place from 1 April 2023, and we await
clarification from the Scottish Government as to when these will be published
and implemented.  Notwithstanding the expected increase in benchmark
assumptions Housing and Finance Officers will continue to assess the
ongoing affordability of future developments within the context of the Housing
Revenue Account Business Plan.
Procurement
6.3 All new development sites will be subject to new detailed procurement
strategies and the opportunities highlighted with 4.4 of this report will continue
to be prioritised.
6.4 Where the contract award is less than £213,000, authority is delegated to
the Chief Officer in consultation with the Procurement Manager to instruct the
award of contracts for the planned revenue and capital spend detailed in this
report to suppliers providing the most economically advantageous offer to the
Council.
6.5 All procurement activity carried out by the Council in excess of £2m is
subject to a contract strategy. The contract strategy for new housing
development within the HRA Capital Programme will be developed by the
Corporate Procurement Unit in consultation with Housing Development
Officers. The contract strategy will include, but is not limited to; contract
scope, service forward plan, the market, procurement model and routes –
including existing delivery vehicles, roles and responsibilities, risks, issues
and opportunities and on-going contract management. Opportunities to
maximise the positive social, economic and environmental impact for the

Page 10

Council through the relevant procurement processes will be developed in line
with procurement policy.
7. Risk Analysis
7.1 All Council new build projects have their own Risk Register which highlights
the risk within and out-with the project team’s control.  These are maintained
and adjusted on an on-going basis.
7.2 With any new build project there is a risk that as the projects develop the cost
increases beyond the estimated contract cost.  Any additional borrowing
requirements, or conversely, cost savings will be reported to future meetings
of the Housing and Communities Committee. However, this is mitigated
through a target cost model approach in our current contract arrangements
within the Scottish Procurement Alliance (SPA) framework and Scotland
Excel.
8. Equalities Impact Assessment (EIA)
8.1 The proposal does not alter any existing policy or pattern of service delivery
and so is not considered to require an equalities impact assessment.
9. Consultation
9.1 As part of our previous rent consultation exercise, 92% of respondents
indicated their support for the Council’s ambitious plans to deliver the Housing
Revenue Account (HRA) new council house build programme. In addition,
there was positive support for the wider delivery of new build housing as part
of the recent Local Housing Strategy.  Regular updates on new build
development are provided to the West Dunbartonshire Tenants and Residents
Organisation at the bi-monthly liaison meetings.
10. Strategic Assessment
10.1 The Local Housing Strategy is the overarching document setting out the
strategic direction for housing across all tenures and informs the future
investment in housing and related services across West Dunbartonshire.
10.2 Having considered all the Council’s strategic priorities, this report and the
provision of new supply social housing for rent contributes greatly to all
strategic priorities. 
Peter Barry
Chief Officer, Housing and Employability
Date: 18 April 2023

Page 11

Person to Contact: John Kerr – Housing Development and Homelessness
Manager, Housing Development and Homelessness
Team, Housing and Employability, telephone:
07793717981, email: john.kerr@west-dunbarton.gov.uk
Appendices: 1. Clydebank Health Centre site plan
Background Papers: West Dunbartonshire Council’s Local Housing Strategy
Local Housing Strategy, Health Inequalities Impact
Assessment
DVS Valuation Report Development Site:
Clydebank Health Centre
Wards Affected: All