Democracy Spraffa

DOCUMENT PACK (Housing and Communities Committee 030523) BOOKMARKED

West Dunbartonshire Council · 3 May 2023
Back to Housing & Communities Committee — 3 May 2023 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Agenda
Housing and Communities
Committee
Date:  Wednesday, 3 May 2023
___________________________________________________________________
Time:  10:00 
___________________________________________________________________
Format:  Hybrid Meeting
___________________________________________________________________
Contact: Email: Nicola.moorcroft@west-dunbarton.gov.uk     
committee.admin@west-dunbarton.gov.uk
Dear Member
Please attend a meeting of the Housing and Communities Committee as detailed
above.
Members will have the option to attend the meeting remotely or in person at the Civic
Space, 16 Church Street, Dumbarton.
The business is shown on the attached agenda.
Yours faithfully
PETER HESSETT
Chief Executive
Page 1

Page 2

Distribution:-
Councillor Ian Dickson 
Councillor Gurpreet Singh Johal (Chair)
Councillor David McBride
Councillor Jonathan McColl
Councillor Michelle McGinty
Councillor Jim McElhill
Councillor John Millar 
Councillor Lawrence O’Neill
Councillor Lauren Oxley 
Councillor Martin Rooney
Councillor Hazel Sorrell (Vice Chair)
Councillor Sophie Traynor
All other Councillors for information
Chief Executive
Chief Officer – Housing and Employability
Chief Officer – Regulation and Regeneration
Chief Officer – Supply, Distribution and Property
Date issued: 19 April 2023
Audio Streaming
Audio recordings of the meeting (including the attendance or contribution of any party
participating or making a contribution) will be published on the Council’s website and
the Council’s host’s webcast/audio stream platform.
You should be aware that the Council is a Data Controller under the General Data
Protection Regulation.  Data collected during this audio stream will be retained in
accordance with the Council’s Privacy Notice* and Retention Schedules including,
but not limited to, for the purpose of keeping historical records and making those
records available via the Council’s internet site.
*http://www.west-dunbarton.gov.uk/privacy/privacy-notice/
Page 2

Page 3

HOUSING AND COMMUNITIES COMMITTEE
WEDNESDAY, 3 MAY 2023
AGENDA
1 STATEMENT BY CHAIR – AUDIO STREAMING
The Chair will be heard in connection with the above.
2 APOLOGIES
3 DECLARATIONS OF INTEREST
Members are invited to declare if they have an interest in any of the items of
business on this agenda and the reasons for such declarations.
4 RECORDING OF VOTES
The Committee is asked to agree that all votes taken during the meeting be
done by roll call vote to ensure an accurate record.
5 OPEN FORUM
The Committee is asked to note that no open forum questions have been
submitted by members of the public.
6 MINUTES OF PREVIOUS MEETING 7 - 11
Submit for approval, as a correct record, the Minutes of Meeting of the
Housing and Communities Committee held on 22 February 2022. 
7 SCRUTINY REPORTS
(A) POLICE SCRUTINY REPORT To Follow
Submit report by the Divisional Commander, Police Scotland providing
Members with an update.  
(B)/
Page 3

Page 4

(B) FIRE AND RESCUE SCRUTINY REPORT To Follow
Submit report by the Local Senior Officer, Scottish Fire and Rescue
Service providing appropriate performance data measured against
priorities in the West Dunbartonshire Local Fire and Rescue Plan. 
8 HOUSING & EMPLOYABILITY DELIVERY PLAN 2022/23  13 - 62
YEAR END PROGRESS AND HOUSING & EMPLOYABILITY
DELIVERY PLAN 2023/24
Submit report by the Chief Officer – Housing and Employability setting out the
year-end progress of the 2022/23 Delivery Plan and presenting the new
Delivery Plan for 2023/24.
9 SUPPLY, DISTRIBUTION & PROPERTY DELIVERY PLAN  63 - 87
2022/23 HOUSING ASSET & INVESTMENT AND BUILDING
SERVICES YEAR END PROGRESS AND SUPPLY,
DISTRIBUTION & PROPERTY DELIVERY PLAN 2023/24
HOUSING ASSET & INVESTMENT AND BUILDING SERVICES
Submit report by the Chief Officer – Supply, Distribution and Property setting
out the Housing Asset & Investment and Building Services priorities of the
Supply Distribution & Property (SD&P) year-end progress 2022/23 and
presenting the new Delivery Plan for 2023/24.
10 HOUSING REVENUE ACCOUNT CAPITAL PROGRAMME 89 - 95
UPDATE – BETTER HOMES WEST DUNBARTONSHIRE
Submit report by the Chief Officer – Housing and Employability providing an
update on the development of a revised Housing Revenue Account Capital
Programme following the decision taken by West Dunbartonshire Council to
agree a weekly rent increase of 5% in 2023/24.
11 HOUSING REPAIRS – ADDRESSING DAMPNESS AND 97 - 109
MOULD IN COUNCIL HOUSES
Submit report by the Chief Officer – Supply, Distribution and Property and
Chief Officer – Housing and Employability providing an overview of the
services’ approach to the management and future prevention of dampness
and mould in council houses.
12/
Page 4

Page 5

12 MORE HOMES WEST DUNBARTONSHIRE COUNCIL 111 - 123
AFFORDABLE HOUSING SUPPLY DELIVERY PROGRAMME
Submit report by the Chief Officer – Housing and Employability providing
an update on progress with West Dunbartonshire’s More Homes Programme
which oversees the delivery of the Council’s new home building programme.
13 WILLOX PARK SHELTERED HOUSING COMPLEX 125 - 129
Submit report by the Chief Officer – Housing and Employability providing 
an update on the action we are taking to understand the damp and mould
problems experienced by the tenants at Willox Park, Dumbarton and also the
delivery of a wider masterplan approach to the future provision of sheltered
housing within the location.
14 ENHANCED STANDARDS FOR MULTI STOREY LIVING – 131 - 153
A STRATEGY FOR ENHANCING THE EXPERIENCE OF
LIVING IN A MULTI-STOREY HOME IN WEST 
DUNBARTONSHIRE 2023/28 
Submit report by the Chief Officer – Housing and Employability providing an
update on the recent resident consultation which gathered ideas on how to
enhance our 19 multi-storey homes and seeking approval to implement a
strategy to enhance living standards in these homes by delivering a number of
improvement actions.
15 TENANT SATISFACTION SURVEY 155 - 164
Submit report by the Chief Officer – Housing and Employability providing the
results of a comprehensive Tenant Satisfaction Survey on the Housing and
Homelessness Services that has been carried out and the results of which will
be reported to the Scottish Housing Regulator as part of our 2022/23 Scottish
Social Housing Charter requirements.
Page 5

Page 6

Page 6

Page 7

HOUSING AND COMMUNITIES COMMITTEE
At a Hybrid Meeting of the Housing and Communities Committee held in the Civic
Space, 16 Church Street, Dumbarton on Wednesday, 22 February 2023 at 
10.00 a.m.
Present: Councillors Ian Dickson, Gurpreet Singh Johal, David McBride,
Jonathan McColl, James McElhill, Michelle McGinty, Lawrence
O’Neill, Lauren Oxley, Martin Rooney, Hazel Sorrell and Sophie
Traynor.
Attending: Peter Hessett, Chief Executive; Peter Barry, Chief Officer –
Housing and Employability; Angela Wilson, Chief Officer –
Supply, Distribution and Property; John Kerr, Housing
Development and Homelessness Manager; Martin Feeney,
Building Services Manager; Alan Young, Housing Asset and
Investment Manager; Michael McDougal, Legal Officer and
Nicola Moorcroft and Lynn Straker, Committee Officers.
Also Attending: Chief Superintendent Lynn Ratcliff and Chief Inspector Ryan
McMurdo, Police Scotland; Area Commander Joe McKay, Argyll
and Bute, East and West Dunbartonshire, Scottish Fire and
Rescue Service.
Apology: An apology for absence was intimated on behalf of Councillor
John Millar.
Councillor Gurpreet Singh Johal in the Chair
STATEMENT BY CHAIR – AUDIO STREAMING
Councillor Singh Johal, Chair, advised that the meeting was being audio streamed
and broadcast live to the internet and would be available for playback.
DECLARATIONS OF INTEREST
It was noted that, there were no declarations of interest in any of the items of
business on the agenda.
ITEM 6
Page 7

Page 8

RECORDING OF VOTES 
The Committee agreed that all votes taken during the meeting would be done by roll
call vote to ensure an accurate record. 
OPEN FORUM 
The Committee noted that no open forum questions had been submitted by
members of the public. 
MINUTES OF PREVIOUS MEETING 
The Minutes of the Meeting of the Housing and Communities Committee held on 23
November 2022 were submitted and approved as a correct record. 
WEST DUNBARTONSHIRE - LOCAL POLICING PLAN (LLP) RENEWAL 
A report was submitted by the Divisional Commander, Police Scotland setting out the
West Dunbartonshire Local Policing Plan 2023 – 2026. 
After discussion and having heard Chief Superintendent Ratcliff in further
explanation and in answer to Members’ questions, the Committee agreed to approve
the contents of the West Dunbartonshire - Local Policing Plan (LLP) 2023 – 2026. 
SCRUTINY REPORTS 
(A) POLICE SCRUTINY REPORT QUARTER 3 2022/23 
A report was submitted by the Divisional Commander, Police Scotland
providing members with an update for Quarter 3 2022/23. 
After discussion and having heard Chief Superintendent Ratcliff and Chief
Inspector McMurdo, Police Scotland, the Committee agreed to note the
update provided. 
(B) FIRE AND RESCUE SCRUTINY REPORT 
A report was submitted by the Local Senior Officer, Scottish Fire and Rescue
Service providing appropriate performance data measured against priorities in
the West Dunbartonshire Local Fire and Rescue Plan. 
After discussion and having heard Area Commander McKay, Argyll and Bute,
East and West Dunbartonshire, Scottish Fire and Rescue Service, the
Committee agreed to note the content of the Scottish Fire and Rescue
Service West Dunbartonshire Council Report. 
Page 8

Page 9

HOUSING AND EMPLOYABILITY DELIVERY PLAN 2022/23 INTERIM REPORT 
A report was submitted by the Chief Officer – Housing and Employability, setting out
the interim progress of the Housing and Employability Delivery Plan 2022/23. 
After discussion and having heard the Chief Officer – Housing and Employability, in
further explanation and in answer to Members’ questions, the Committee agreed to
note the progress achieved. 
SUPPLY, DISTRIBUTION AND PROPERTY DELIVERY PLAN 2022/23 –
HOUSING ASSET AND INVESTMENT AND BUSINESS SERVICES 
A report was submitted by the Chief Officer – Supply, Distribution and Property,
setting out the interim progress of the Housing Asset and Investment and Building
Services priorities within the Supply, Distribution and Property Delivery Plan
2022/23. 
After discussion and having heard the Chief Officer – Supply, Distribution and
Property, in further explanation and in answer to Members’ questions, the Committee
agreed to note the progress achieved. 
MORE HOMES WEST DUNBARTONSHIRE – WEST DUNBARTONSHIRE
COUNCIL AFFORDABLE HOUSING SUPPLY DELIVERY PROGRAMME 
A report was submitted by the Chief Officer – Housing and Employability providing
an update on the progress of West Dunbartonshire’s More Homes Programme,
which oversees the delivery of the Council’s new home building programme. 
After discussion and having heard the Chief Officer – Housing and Employability and
the Housing Development and Homelessness Manager, in further explanation and in
answer to Members’ questions, the Committee agreed:- 
(1) to note that following the issue of the papers for the meeting, an erratum
notice had been issued which contained a revised version of the report; 
(2) to note the content of the revised report and the progress made to date, in the
delivery of the Council’s More Homes West Dunbartonshire approach,
including the practical completion and handover of the latest development
project at Queens Quay (Site B); 
(3) to note the commencement of groundworks at the Clydebank East Housing
Development in January 2023; 
(4) to note the successful funding application to the Scottish Government’s
Vacant and Derelict Land Fund of £1.25m to support the Pappert Housing
Development;
Page 9

Page 10

(5) to approve the transfer of the site at Queen Mary Avenue, Clydebank, with
vacant possession, at the cost of £140,000, from the Council’s General Fund,
to the Housing Revenue Account for the delivery of new Council homes; and 
(6) to note the delay in the acquisition of the former Clydebank Health Centre
site, at the cost of £707,400, from NHS Greater Glasgow and Clyde, for the
delivery of new Council homes. 
WILLOX PARK SHELTERED HOUSING COMPLEX 
A report was submitted by the Chief Officer – Housing and Employability providing
an update on the action the Council has taken to understand the damp and mould
problems experienced by the tenants at Willox Park. 
After discussion and having heard the Chief Officer – Housing and Employability 
and the Housing Development and Homelessness Manager, in further explanation
and in answer to Members’ questions, the Committee agreed:- 
(1) to note the content of the report and the progress made to date, in carrying
out initial surveys and approve spend for future surveys and required works at
Willox Park Sheltered Housing Complex. 
(2) to approve the temporary suspension of letting activity at the complex whilst
further surveys are completed. 
(3) to note the expected timescales for completion of surveys (Q1 2023) and
expected information and recommendations for the future of the homes (Q2
2023, subject to findings of surveys); and 
(4) to note that a further update report will be provided to the next meeting of the
Housing and Communities Committee. 
HOUSING REVENUE ACCOUNT BUDGETARY CONTROL REPORT TO 
31 DECEMBER 2022 (PERIOD 9) 
A report was submitted by the Chief Officer – Resources providing an update on the
financial performance to 31 December 2022 (Period 9) of the Housing Revenue
Account (HRA) revenue and capital budgets for 2022/23. 
After discussion and having heard the Chief Officer – Housing and Employability in
further explanation, the Committee agreed:- 
(1) to note the revenue analysis showed projected adverse variances of £2.116m
however, this would be offset by reducing the contribution from revenue to
capital (CFCR) therefore netting to a revenue break-even position ; and 
Page 10

Page 11

(2) to note the net projected annual position in relation to the capital plan was
highlighted as an in-year adverse variance of £27.772m (42.33%) which was
made up of re-profiling of £31.671m (48.27%) and overspend of £3.899m
(5.94%) as detailed in Appendix 4 of the report.
FINANCIAL REPORT 2022/23 AS AT PERIOD 9 (31 DECEMBER 2022)
A report was submitted by the Chief Officer – Resources providing an update on the
financial performance to 31 December 2022 (Period 9) of those services under the
auspices of the Housing and Communities Committee.
After discussion and having heard the Chief Officer – Housing and Employability in
further explanation, the Committee agreed:-
(1) to note the contents of the report which showed the revenue budget forecast
to overspend against budget by £0.079m (1.71%) at the year-end.
(2) to note the net projected annual position in relation to relevant capital projects
showed no projected variance; and
(3) to note the progress on efficiencies incorporated into budgets for 2022/23.
The meeting closed at 11.48 a.m.
Page 11

Page 12

Page 12

Page 13

WEST DUNBARTONSHIRE COUNCIL
Report by Chief Officer – Housing and Employability
Housing and Communities Committee 3 May 2023
Subject: Housing & Employability Delivery Plan 2022/23 - Year-end Progress &
Housing & Employability Delivery Plan 2023/24
1 Purpose
1.1 This report sets out the year-end progress of the 2022/23 Delivery Plan and
presents the new Delivery Plan for 2023/24.
2 Recommendations
2.1 It is recommended that Committee notes the progress achieved at year-end
and the new plan for 2023/24.
3 Background
3.1 In line with the Strategic Planning & Performance Framework, each Chief
Officer develops an annual Delivery Plan which sets out actions to help deliver
the Strategic Plan and address the performance challenges and service
priorities identified in the planning process. The Plan also provides an
overview of services and Housing & Employability, including employees and
budgets, sets out the performance indicators (PIs) for monitoring progress and
considers the relevant risks.
4 Main Issues
2022/23 Year-end Performance
4.1 The 2022/23 Delivery Plan was presented to Housing and Communities
Committee on 23 November 2022 and interim progress reported on 22
February 2023.
4.2 Full details of year-end progress are set out in Appendix 1.
4.3 Of the 28 actions due to be completed by 31 March, 26 were completed as
planned with 2 outstanding. Outstanding actions relate to the following and will
be carried forward and completed in 2023/24:
• High rise Living Strategy - 75% complete, if approved at HAC committee in
May this action will be complete; and
• ASB strategy - 37% complete, this action will remain a priority in 2023/24
4.4 Data for the full suite of PIs set out in the plan will not be available until June
2023.  The full set of PIs will be reported through the Council’s annual
performance reporting process once all data becomes available.
ITEM 8
Page 13

Page 14

2023/24 Delivery Plan 
4.5 The 2023/24 Delivery Plan is set out at Appendix 2.
4.6 Key priorities include: Community Planning & Community Empowerment;
Supporting vulnerable people; ASB Strategy; CCTV infrastructure; Delivering
on the UK Shared Prosperity Fund; Maximising employment opportunities;
Preventing Homelessness; Improving the tenant and prospective tenant
journey; Reducing Child Poverty; and Implementing changes in accordance
with the Housing Bill Scotland 2023.
4.7 Implementation of the Plan will be monitored by the management team with
mid-year and year-end progress reported to Housing and Communities
Committee around November 2023 and May 2024 respectively.
4.8   It should be noted, that the resource data, which includes budget allocation,
employee absence and establishment is not yet available. 
5 People Implications
5.1 There are no direct people implications arising from this report.
6 Financial & Procurement Implications
6.1 There are no direct financial or procurement implications arising from this
report.
7 Risk Analysis
7.1 Failure to deliver on the actions assigned to Housing & Employability may
have a direct impact on the delivery of the Council’s Strategic Plan. It is
essential that remedial action is taken to ensure strategic delivery plans
achieve the commitments detailed and approved.
8 Equalities Impact Assessment
8.1 Screening and impact assessments will be carried out on specific activities as
required.
9 Consultation
9.1 The delivery plans were developed through consultation with officers from the
strategic service areas.
10 Strategic Assessment
10.1 The delivery plans set out actions to support the successful delivery of the
strategic priorities and objectives of the Council.
Page 14

Page 15

Chief Officer: Peter Barry
Service Area: Housing & Employability
Date:  18 April 2023
_____________________________________________________________
Person to Contact:  Nicola Docherty
Nicola.docherty@west-dunbarton.gov.uk
Appendices: Appendix 1: Housing & Employability Delivery Plan
2022/23 – Year-end Progress
Appendix 2: Housing & Employability Delivery Plan
2023/24
Background Papers: Housing & Employability Delivery Plan 2022/23 –
Housing and Communities Committee, 23 November
2022
Strategic Planning & Performance Framework 2022/27
Wards Affected: All
Page 15

Page 16

Page 16

Page 17

Appendix 1 - H&E Delivery Plan Year-end Progress
1. Our communities
Objective 1. Our neighbourhoods are safe, resilient and inclusive
Action Status Progress Due
Date Note Owner
Build community resilience
and advance community
empowerment including the
development of a training
programme to support the
Community empowerment
agenda
31-Mar-
2023
The actions from the approved Community Engagement Strategy
(2019) are being delivered with oversight from the Community
Empowerment Project Board.  Priority projects are all well
underway. Projects include corporate mainstreaming approach to
Participatory Budgeting; Communication Plan; Review of
Community Asset Transfer and a programme of awareness raising
and training to Support the Community Empowerment Agenda.
The projects ensure community based work to continue to raise
awareness of the empowerment agenda, focus on the Cost of
Living Crisis and the opportunities open to communities. Key to
raising awareness is a video, which focuses on the engaging with
communities framework filmed in March, this will be launched in
April 2023. It should be noted that additional projects have been
added to the delivery plan incorporating the UKSPF investment,
including the development of the CCTV network. The Delivery Plan
will be up-dated regularly highlighting progression.
Elaine
Troup
Continue to improve and
develop the Councils CCTV
processes and infrastructure
31-Mar-
2023
This action has been successfully completed. The Communities
Team are included within the proposals for the United Kingdom
Shared Prosperity Fund (UKSPF) programme that will deliver a
series of actions from 2022 to March 2025. The primary goal of the
Elaine
Troup
Appendix 1
Page 17

Page 18

Action Status Progress Due
Date Note Owner
UKSPF is to build pride in place and increase life chances across
the UK. With a key theme being Communities and Place the
investment will allow for Improving Community Safety by upgrading
of the current CCTV system for public space surveillance to
provide support in the protection of the public, the deterrence of
and the detection of crime and to provide support in the
investigation of such crimes. Improvements will seek to link
enhanced public space, social housing and Council establishment
cameras to one network with access from one control centre. This
action will go beyond the due date of March 2023 in line with the
UKSPF allocation to 2025.Procurement route will include a
procured CCTV survey leading to a transmission strategy in order
to inform a tender. The CCTV Delivery group has been re-
established and will be directed by the Community Empowerment
Project Board.
Explore alternative forms of
funding to encourage less
reliance on mainstream
council funding
31-Mar-
2023
This action has been successfully completed. The Communities
Team are a key part of the proposals for the United Kingdom
Shared Prosperity Fund (UKSPF) programme that will deliver a
series of actions from 2022 to March 2025. The primary goal of the
UKSPF is to build pride in place and increase life chances across
the UK. These focus on: communities and place; capital projects;
people and skills and multiply (functional numeracy).
Within the communities and place category the West
Dunbartonshire plan will focus on: Improving Community Safety by
upgrading of the current CCTV  system for public space
surveillance; Pride in Place Project will focus on building on pride
in place centred round a Community Garden supporting
neighbourhood and partnerships working to reduce anti-social
Elaine
Troup
Page 18

Page 19

Action Status Progress Due
Date Note Owner
behaviour (Housing/ Fire Scotland/ Communities/ Police Scotland/
Greenspace; Participatory Budgeting - Awareness /training
resource;  West Dunbartonshire Pantry Network -community
pantries offer a dignified and sustainable approach to addressing
food insecurity and food poverty; Community Soup Engagement to
develop small community-based projects that will improve the
quality of life in local areas. Equating to additional funding of
£744,222 for 2023 - 2025 and a commercial viable CCTV network.
Deliver the objectives set
out in the Community
Empowerment Strategy and
Action Plan through
identified priority projects
31-Mar-
2023
The actions from the approved Community Engagement Strategy
(2019) are being delivered with direction from the Community
Empowerment Project Board. The Board agreed Year 1 & 2 priority
projects that are progressing well including the completion of the
Participatory Budgeting Mainstreaming Pilot. It should be noted
that with the allocation of UKSPF, additional projects have been
included within the delivery plan; Pride in Place; Food Pantry
network; PB awareness; Community Soup and development of a
CCTV network upgrade by March 2025.The projects ensure
community based work to continue to raise awareness of the
empowerment agenda and of the opportunities open to
communities.
The board agreed that priority projects ensure a focus on the Cost
of Living Crisis. In doing so the Delivery Plan will be up-dated
regularly highlighting progression.
Elaine
Troup
Lead on the Council’s
approach to Participatory
Budgeting Mainstreaming
across the organisation
31-Mar-
2023
The PB Mainstreaming pilot and evaluation have been successfully
completed. The team continue to encourage and embed a culture
of participation across the authority, with a PB ilearn
module developed for WDC staff use; Community Budgeting Six
roll out; and establishing PB spend and service champions across
Elaine
Troup
Page 19

Page 20

Action Status Progress Due
Date Note Owner
all WD service areas. HSCP PB budget for 2023/24 has been
identified.
Develop an Employee
Volunteering Policy to
support the ambitions of the
Community Empowerment
(Scotland) Act 2015
31-Mar-
2023
An Employee Volunteering framework approach has been adapted
as the pilot progresses. The framework will link with the TU
learning agreement and offer employee volunteering as a learning
opportunity, work is ongoing lead by the Communities and
Organisational Development teams. A Pilot scheme was to be
developed by year end, this has now been extended to April 2023
with a launch date to be agreed by the Community Empowerment
Board.
Elaine
Troup
Identify and implement
improvements in partnership
working between the CCTV
team and key partners to
promote feelings of safety in
the area
31-Mar-
2023
Partnership working is well established with Police Scotland to
promote feelings of safety across the area, with the CCTV team
being highly commended for outstanding partnership working at
the Police Scotland - Argyll and West Dunbartonshire, Partner of
the Year Awards in December 2022. Work will continue to
incorporate CCTV information on the Twenty Minute
Neighbourhood mapping system to support safe routes for
residents. The reestablishment of the CCTV working group in line
with the UKSPF will support progression of the action as the new
CCTV network develops.
Elaine
Troup
Development and
implementation of revised
Anti-Social Behaviour
strategy
31-Mar-
2023
This action has not been completed in year. Agreement reached at
Safe DIG that partners of this group would collectively contribute to
development of revised strategy.  However, the action has been
delayed due to Safe DIG Strategy currently under review by same
partners, also required to wait outcome of budget saving options
for ASB Team to inform direction and content of ASB Strategy.
Nicola
Pettigrew
Page 20

Page 21

Action Status Progress Due
Date Note Owner
Work has already commenced on the Equality Impact Assessment,
gathering data and partner service information to shape content of
ASB Strategy.  We will begin the first stage of consultation with key
stakeholders and the public in Spring 2023. Action will require to
be taken forward into 23/24 Delivery Plan for completion as this is
a significant partnership piece of work.
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Failure to
secure
community and
partner buy-in
for the emerging
Community
Empowerment
Strategy and
Action Plan.
In order to deliver on the
ambitions of the Community
Empowerment Strategy and
associated action plan, it is vital
that a partnership approach is
promoted to ensure best use of
resources, skills and expertise.
26 Mar-
2023
The risk profile will remain the
same despite significant progress
being made with a number of
priority projects and the addition
of the UKSPF projects (managed
by Communities team).
Elaine
Troup
Failure to
deliver on the
capacity
building of the
Community
Empowerment
(Scotland) Act
As communities continue to
recover from the impact of
Covid-19 there is an ever
greater need to support and
develop communities.
Community capacity building
and community development
work continues within existing
resources.
26 Mar-
2023
The risk levels remain the same
despite significant progress being
made to support communities
across the authority through
increased levels of capacity
building. Further progress will be
made with the launch of the new
geographical Community Voice
Groups G8123 and the
awareness raising video (with a
Elaine
Troup
Page 21

Page 22

Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
focus on the Engaging
Communities Framework) and
training programme.
Failure to
deliver sufficient
community
capacity
building /
community
development
support to
groups
impacted by
COVID-19.
COVID-19 has had a huge
impact on communities across
the authority. A focused
approach is needed to
understand the impact on
community groups and to
support them to re-start and re-
build. Failure to do this would
impact on the individual and
community resilience of citizens.
26 Mar-
2023
The Communities Team
continues to support a range of
community organisations to re-
start or develop on the back of
the pandemic. The team have a
dedicated capacity building
resource available to support.
Elaine
Troup
Engaging
positively with
Residents,
Communities &
Partnerships
The risk that the Council fails to
adequately engage, establish
and maintain positive
relationships with local residents
and communities in addition to
partnership bodies.
26-Mar-
2023
Citizens & Communities &
Partnerships were previously two
separate risks but have been
combined for the next 5 year
Strategic Plan. Whilst the
Community Planning
Partnership has been managed
under a shared service
agreement, it is well established
with strong partnership working
arrangements in place reducing
likelihood of this risk being
realised. This approach will
continue with the Communities
team leading on West
Elaine
Troup
Page 22

Page 23

Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Dunbartonshire Community
Planning support from April 23.
We continue to promote and
ensure strong communications
and engagement through the
Engaging Communities
Framework. Development of the
Community Empowerment
Strategy priority projects including
a Communication strategy is
progressing well and includes a
Community led transition from the
Community Alliance, in the shape
of Geographical Community
Voice groups. As well as
gathering resident feedback, we
ensure that key information is
communicated through a variety
of media channels including
online, social media and
publications such as Housing
News
Page 23

Page 24

Objective 3. Our residents are supported to increase life and learning skills
Action Status Progress Due Date Note Owner
Digital inclusion – progress
the opportunities for
provision of wi-fi
infrastructure into new
build properties and priority
areas of deprivation
31-Mar-
2023
Digital inclusion capabilities are incorporated into our new build
design standard and all new housing will benefit from this
infrastructure.  We have connected with 2 telecommunications
companies in terms of the provision of social tariffs for broadband
connectivity and plans are in place to install infrastructure across
our housing estate.
John Kerr
2. Our Environment
Objective 6. Our neighbourhoods are sustainable and attractive
Action Status Progress Due Date Note Owner
Develop and implement
Housing regeneration
approaches to improve our
communities
31-Mar-
2023
Priority areas referenced in the current local housing strategy, and
an area based approach has been launched from this which will
cover the 5 year period of the strategy.  Some key initiatives that
are underway include Clydebank East, Pappert, Alexandria and
Bellsmyre, Dumbarton
John Kerr
Develop our Housing
Asset Management to
ensure sustainability and
deliver new Housing
Capital Investment
Programme
31-Mar-
2023
A New Housing Asset Management Strategy is in development
and will be submitted to a Housing and Communities Committee
in November 2023.  Regular progress updates continue to be
provided to the Council's Better Homes Project Board
John Kerr
Page 24

Page 25

Action Status Progress Due Date Note Owner
Implement new Local
Housing Strategy & council
wide response to 2040
31-Mar-
2023
This action has been successfully completed. High level steering
group tasked with ensuring delivery continues to meet and
prioritise key objectives.  Scottish Government has now fedback
on the strategy in a positive manner.
John Kerr
Implement year 4 of rapid
rehousing plan (Home at
the Heart)
31-Mar-
2023
This action will continue to progress and deliver Year 5 outcomes.
While we continue to roll out the plan in a positive manner in
respect of the key actions, delivery on some of the key
performance measures are not being realised as a result of slower
than anticipated housing access system and notably around void
turnaround times.  This has led to an increase in the use of
temporary accommodation and the time spent in such
accommodation
John Kerr
Deliver New build Housing
programme
31-Mar-
2023
The Council’s More Homes West Dunbartonshire approach has
now delivered more than 500 new homes in the local authority
area.  A key deliverable within 2022/23 was the completion of the
affordable housing development at Queens Quay, Clydebank
delivering 29 new council homes and the site start at the 88 home
housing development at Clydebank East.
John Kerr
Deliver high rise
accommodation strategy
31-Mar-
2023
This action did not complete within the target timescale, however
is progressing well. Based on the responses at an early point of
the consultative phase we decided to extend this phase to allow
us to further develop and improve the strategy, which will now be
presented to the Housing and Communities Committee in May
2023.
John Kerr
Page 25

Page 26

Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Failure to
secure funding
to invest in
WDC’s CCTV
infrastructure.
The public space CCTV
infrastructure covers the three
main townships of Alexandria,
Dumbarton and Clydebank with
a mix of fixed space and
redeployable cameras. Until
resources can be secured and
improvements made the Council
does remain at risk from
reputational damage, should the
system fail.
26-Mar-
2023
CCTV investment to upgrade the
current network is a key element
of the UK Shared Prosperity
Funding applied for through the
Theme - Communities and
Place. The Investment Plan has
been approved and the
drawdown of funds process is
being finalised by Glasgow City
Council as lead partner. The
procurement process for the new
network is underway.
Elaine
Troup
Failure to
achieve the
outcomes of the
Scottish Social
Housing Charter
The Scottish Social Housing
Charter sets out the standards
and outcomes that tenants and
customers should expect from
social landlords, in terms of the
quality and value for money of
the services they receive.
Failure to continue to meet
these could place the Council at
risk of the intervention powers of
the Scottish Housing Regulator 
03-Apr-
2023
Areas of non-compliance in terms
of Housing Quality will be
highlighted within Annual
Assurance process.
John Kerr
3. Our Economy
Objective 7. Our area has the infrastructure for sustainable and inclusive growth where businesses can flourish
Page 26

Page 27

Action Status Progress Due
Date Note Owner
Develop investment plan
for shared prosperity fund
31-Mar-
2023
The UK Shared Prosperity Fund (UKSPF) is the UK Government’s main
method replacing for EU Structural Funds and has a potential value to
West Dunbartonshire of £3.8m. The fund has three core investment
priorities that will be funded on the basis of an Investment Plan.  West
Dunbartonshire has worked in partnership with Glasgow City Region
Partners to develop and submit a Regional Investment Plan. The final
decision on the funds allocated to West Dunbartonshire has been
announced and the City Region is negotiating first payments with the UK
Government.
The next stage, following, award notice will be the preparation for
delivery. This will include the development of grant fund opportunities
and processes for acquiring/procuring the services we require to meet
the SPF aims. Some of this work is underway and we anticipate project
spend to begin in April 2023.
Stephen
Brooks
Objective 8. We will support our residents to access employment and training opportunities
Action Status Progress Due
Date Note Owner
Ensure no one left behind
by supporting skills and
learning for work, life and
learning
31-Mar-
2023
We have established a three year CLD plan with associated actions and
activities that are designed to support skills for life, learning and work.
This includes: the delivery of community based vocational courses that
are accredited by SQA; supporting digital skills; and assisting the
delivery of ESOL (English for Speakers of Other languages). During the
course of the year we reinforced our partnership working by reviewing
the Adult Learning Partnership and Youth Alliance terms of reference
and we devised and delivered the summer programme for school
pupils.  In addition, we have developed our proposal for Multiply
Stephen
Brooks
Page 27

Page 28

Action Status Progress Due
Date Note Owner
activities (Adult numeracy). This was included in our plans for the use of
UK Shared Prosperity Funds which have now been agreed.
Promote inclusive growth
through access to
training and
apprenticeship
opportunities
31-Mar-
2023
This action centres on developing and delivering the apprenticeship
programme in West Dunbartonshire. Beyond having the appropriate
staff to ensure apprentices receive appropriate and good quality training,
the activity relies on securing a training contract from SDS - this has
been done. The activity also relies on the continuation of the West
Dunbartonshire Council's investment in apprenticeships (paying salaries
for apprentices; this was continued. As a result, there are 122 MA's
being supported through the W4U SDS MA programme over this period.
The apprentices are combination of MA's within the Council and Private
Sector, as well as upskilling opportunities offered to existing council
employees in Childcare, Business Admin, Digital Analytics and Social
care sectors.  The team has secured the training contract for a further
year. As such, we will continue to support MAs and FAs through
2024/25.
Stephen
Brooks
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Failure to
prepare for
changes
associated with
No One Left
Behind
No One Left Behind represents
a transformational change in
employability service provision,
failing to prepare and reaching a
state of readiness will lead to
lost opportunities for investment
in employability services.
23-Mar-
2023
This risk has been managed. We
have secured No One Left behind
funding and are delivering services.
Stephen
Brooks
Objective 9. We will work with partners to support economic development to deliver increased prosperity for our area
Page 28

Page 29

Action Status Progress Due
Date Note Owner
Support and implement
CLD, Employability and
Welfare benefit three
year plans to promote
quality frameworks and
partnership working to
enhance work, learn,
money service provision
31-Mar-
2023
We have completed the three year plans for CLD, Information and
Advice Services and Employability Services. Each plan has a set
of actions that focus on continuous improvement that we will monitor
on an ongoing basis. Allied to this are a set of service activities with
associated performance indicators. These reports will be used to
gauge progress and provide evidence for the various quality
standard assessments.
Our three year employability plan has been endorsed by the Scottish
Government and will serve as a guide for the use of No One Left
Behind resources. This plan will also inform the development of our
proposals for UK Shared Prosperity Funds 'People and Skills'
priority. Meanwhile the CLD Plan will inform our approach to UK
Shared Prosperity 'Multiply' objectives.
These plans were used to inform the local child poverty annual
report which was circulated to the key stakeholders (Council,
Community planning, NHS Greater Glasgow and Clyde) in
September and published on-line in October (meeting our statutory
requirement to publish an annual local child poverty report.
Stephen
Brooks
Maximise income from
employment
13-Mar-
2023
We are delivering support through the use of European Social
Funds, No One Left Behind and Parental Employability Support.
These funds are intended to improve people's prospects by
developing confidence, self-esteem, skills and understanding of the
labour market. As such progression towards the labour market is a
key indicator. We have supported approximately 350 people to
secure employment in the first three quarters of the current financial
year (22/23). This is consistent with our overall aim of supporting 399
people to secure employment over the course of the year.
Stephen
Brooks
Page 29

Page 30

Action Status Progress Due
Date Note Owner
Maximise income from
benefits
13-Mar-
2023
We are delivering support through the use of European Social
Funds, No One Left Behind and Parental Employability Support.
These funds are intended to improve people's prospects by
developing confidence, self-esteem, skills and understanding of the
labour market. As such progression towards the labour market is a
key indicator. We have supported approximately 350 people to
secure employment in the first three quarters of the current financial
year (22/23). This is consistent with our overall aim of supporting 399
people to secure employment over the course of the year.
Stephen
Brooks
Ensure no one left
behind by addressing
life challenges and
reducing costs
13-Mar-
2023
We are reviewing our activity and associated targets in the light of
our experience of service delivery during and beyond COVID-19
restrictions. In addition, we are also reviewing how we gather
information to demonstrate how we support people to reduce costs
by managing debt. We have set an interim target while we review the
approach and in the first quarter of the current financial year we have
supported our service users to manage approximately £364,941 of
debt.
In addition, we are developing approaches as part of the aim to
address the cost of living crisis. This includes supporting local food
banks to develop their services and address food insecurity. We are
also supporting activity to address fuel poverty through our
Improving the Cancer Journey project, family opportunity hub and
information and advice partnership.
Stephen
Brooks
Page 30

Page 31

Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Failure to
respond to child
poverty
legislation
The Local Child Poverty Plan
sets out what we will do to
respond to child poverty, failure
to respond will have a significant
impact on the Council’s
reputation, more importantly an
opportunity to raise issues and
respond more effectively to child
poverty issues will be lost
23-Mar-
2023
The Local Child Poverty Annual
report was written and published
in October 2022. Work is
progressing on the 22/23 annual
report.
Stephen
Brooks
Universal Credit
Full Service
changes
breadth and
depth of
demand for
services.
Migration of all claims to
Universal Credit may lead to
increased service demand from
people who would not have
used Working 4U service
otherwise.
23-Mar-
2023
This risk has been reduced
because of the implementation of
UC, which was made easier by
DWP during the COVID
pandemic.
Stephen
Brooks
Failure to
secure
alternative funds
to replace
European
funding
Failure to identify alternative
funds to replace European
Structural funds will increase
uncertainty and loss of staff to
other services 
23-Mar-
2023
The UKSPF investment plan has
been submitted and agreed and
we will deliver services using this
fund from April 2023.
Stephen
Brooks
The cost of
living crisis will
lead to a
substantial
demand for
access to
We will monitor the changing
levels of demand and target our
resources to individuals and
areas that are most in need. We
will seek to work with partners to
ensure we receive appropriate
23-Mar-
2023
We are working to ensure we
focus our efforts on those most
affected by the cost of living
crisis. This includes managing
food insecurity and fuel debt
funds.
Stephen
Brooks
Page 31

Page 32

Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
welfare/debt
support
services.
referrals who can benefit from
our support. 
4. Our Council
Objective 10. Our workforce is resilient and skilled where digital technology supports service delivery for our residents
Action Status Progress Due
Date Note Owner
Develop and implement
wellbeing, employee
engagement, equality
and training plans to
enable capabilities,
improved resilience and
promotion of a diverse
workforce.
31-Mar-
2023
Regular team meetings and employee engagement continues across
all H&E service areas, which includes invite to teams to contribute to
agenda items/areas of focus.
Trickle champions within the service have been identified to promote
the use of the corporate tool for employee engagement.
Peter Barry
Develop and implement
employee life cycle
plans in line with the
People First Strategy to
attract and retain the
workforce.
31-Mar-
2023
Job shadowing has been offered to Housing Officer and Assistant
Housing Officer roles, this includes on job shadowing between these
roles for staff development and up-skilling.  Employees across all
services are encouraged to undertake any professional training related
to their post to keep skills and learning up to date and relevant.
Peter Barry
Implement service
review process including
role design, use of new
31-Mar-
2023
Housing Operations have carried out a Fit for Future review and within
that a review of a range of processes to improve service delivery. This
includes the establishment of a number of working groups to review
Peter Barry
Page 32

Page 33

Action Status Progress Due
Date Note Owner
technology and new
ways of working to add
resilience, address
gaps, and establish
opportunities for
efficiencies
areas such as: mobile app; 28 day estate work; Housing stock
availability/turnover tool; development of online housing application;
reviews started for Arrears and ASB service areas, in addition to this
the Void working group continues to meet 6 weekly.
Communities’ team are adopting the Scottish Approach to Service
design in key areas of their work. This will simplify their work streams
allow for collaboration with partners and establish opportunities for
efficiencies. Advice Pro Management Information system continues to
be developed in line with CLD/HMIE audit requirements.
Develop and implement
training plans and
development
opportunities to improve
capabilities and
resilience within the
workforce.
31-Mar-
2023
Training continues to be a key focus for H&E and in the last year we
have reviewed training needs and will continue to ensure these are
met. This includes ensuring professional training is kept up to date as
well as strengthening partnership working internally. Forthcoming
UKSPF investment will require training and development for all teams
involved.
Peter Barry
Objective 11. Our Council is adaptable and focused on delivering best value for our residents
Action Status Progress Due Date Note Owner
Carry out review of
housing policies and
processes across
housing
management areas
including void
management and
re-let standards
31-Mar-
2023
This action has been successfully completed. The void working group has
been established and meets 6 weekly, range of processes have been
reviewed in line with Fit For Future recommendations.  Options paper
presented to HIB with recommendations for revised re-let standards will
be further discussed at WDTROA Range of short term working groups
established across Housing Operations service areas and undertaken
review of existing operational processes with staff.
Nicola
Pettigrew
Page 33

Page 34

Objective 12. Our residents are engaged and empowered
Action Status Progress Due Date Note Owner
Explore digital
opportunities to
develop housing
management
customer service
and experience
(such as near me
technology and
mobile app)
31-Mar-
2023
New mobile app working group established and 4 HO undertaking pilot
on 28 day estate work , 4 staff have app on phones for testing and
meetings to continue to feedback any improvements/issues, prior to
wider roll out in service and moving to wider service areas on app. 
Housing stock availability/turnover tool is in test environment, positive
feedback obtained from staff and in process of releasing tool to staff in
order to support housing options discussions with tenants and
applicants upon contact for assistance.  Work underway to adapt tool to
sit alongside online application form, which will support information for
applicants at point of completing online housing application to make
informed housing preference decisions based on stock turnover.
Development of online housing application form underway which will
allow ability to upload verification documents by applicants at point of
application, meetings scheduled March to discuss linking to IHMS
data.
Walk process reviews started for Arrears and ASB service areas - work
will be carried forward into new financial year on any recommendations
and improvements identified.
Void working group continues to meet 6 weekly, void RAG dashboard
now in place for Housing Operations and Building Services staff to use
to monitor and progress voids through to ready to let stages with
applicants.
Nicola
Pettigrew
Action Status
Page 34

Page 35

Risk Status
Alert
High risk
Warning
OK
Unknown
Overdue
Not on track
In Progress and on track
Completed
Page 35

Page 36

Page 36

Page 37

2023-24
DELIVERY PLAN
Housing and Employability
Appendix 2
Page 37

Page 38

Contents
1. INTRODUCTION .............................................................................................................................................................................................................................. 2
2. PERFORMANCE REVIEW ................................................................................................................................................................................................................. 2
3. STRATEGIC ASSESSMENT ................................................................................................................................................................................................................ 5
4. RESOURCES ................................................................................................................................................................................................................................... 16
FINANCE .......................................................................................................................................................................................................................................................... 16
EMPLOYEES ...................................................................................................................................................................................................................................................... 17
5. APPENDIX 1: ACTION PLAN ........................................................................................................................................................................................................... 17
Page 38

Page 39

1. Introduction
Housing & Employability comprises a wide range of services covering Communities, Housing Development and Homelessness,
Housing Operations and Working 4U. It is one of 8 strategic areas responsible for delivering the Council’s Strategic Plan. Key
actions to help achieve that are set out in this Delivery Plan, together with actions to address any performance issues and
service priorities identified in the planning process.
The progress of this Plan will be monitored and managed by the management team and reported to Housing & Communities
Committee twice yearly, at mid-year and year-end.
2. Performance Review
The management team completed a detailed review of 2022/23 performance, focusing on the following:
• 2022/23 Delivery Plan year-end progress;
• Local Government Benchmarking Framework (LGBF) comparative data;
• Association for Public Service Excellence (APSE) comparative data;
• Scottish Housing Regulator
• Citizens’ Panel feedback;
• Telephone Survey feedback;
• Complaints;
• Continuous Improvement (Fit for Future reviews)
• Other benchmarking/feedback/ etc.
This review highlighted our key achievements in 2022/23 as well as the challenges to be addressed in 2023/24. These are
summarised below.
Key Achievements 2022/23
Page 39

Page 40

Communities
• Secured UK Shared Prosperity Funding for the upgrade of  CCTV infrastructure; for three Community projects, Pride in
Place, Community Soups, Community Pantry network; and to support the development of a dynamic approach to
awareness raising and promotion of Participatory Budgeting across West Dunbartonshire Council
• Delivered Community Empowerment priority projects
• Developed Community Voice groups based on the findings from the Community Engagement Communications plan
survey, this community-led approach will support a  transition from the Community Alliance
• Development of the COSLA led Consul digital platform to support Participatory Budgeting across West Dunbartonshire
Housing Development and Homelessness
• Our approach to tenant participation retained the Gold accreditation from TPAS Scotland, making it the first local authority
to do so.
• We delivered our 500th new council home through the More Homes West Dunbartonshire strategic approach
• Our new housing development at Queens Quay, Clydebank was completed delivering 146 new homes
• New key housing policies were implemented during the year included our Local Housing Strategy and a new Domestic
Abuse Policy; we also reviewed and implemented a review of our housing allocation policy
• Our Home at the Heart, Rapid Rehousing Transition Plan’s Year 4 objectives were delivered
• Our Homelessness and Housing Options service supported 500 households to prevent an episode of homelessness
• Our resettlement service welcomed our first Ukrainian families to be settled in West Dunbartonshire in council tenancies
• Delivered a range of sustainability improvements to our housing stock to inform future retrofit programmes
• We were awarded £1.25m from the Scottish Government’s Vacant and Derelict Land Fund
• Delivered a new Strategic Housing Investment Plan which will begin to deliver on the vision to deliver 2500 new homes in
the next 10 years
• Delivered a range of key improvements in respect of the QL housing management system including the launch of the
tenant self-service portal and improving system capability and performance for Housing Operations and Building Services
Teams
Housing Operations
• Reduced our re-let times by 12% compared to the previous year-end figure
• Achieved consistent tenancy sustainment rate of 94% against the background of cost of living and energy crisis
Page 40

Page 41

• Supported new and existing tenants with financial/income maximisation, assistance from our Tenancy Sustainment Fund
and continued to support tenants via our Tenancy Hardship Fund to prevent homelessness
• Introduced new stock availability and turnover tool for staff use when providing housing options advice for applicants and
tenants.  Further work in progress and will continue in 2023/24 to rollout web support to the online housing application
process for applicants
• Introduced a mobile app pilot for Housing Officers to enable real-time community-based working which will be further
developed in 23/24
• Delivered proactive and visible ASB service 7 days per week until 2 am and Neighbourhood Service 7 days per week until
1 am
• Worked jointly with Building Services to review and enhance dampness and mould processes
W4U
• Secured UK Shared Prosperity Funding to support People and Skills, Local Businesses, Communities and Place and
Adult numeracy projects
• Developed the local employability partnership and established a joint commissioning approach for the use of No One Left
Behind and Parental Employability Funds
• Delivered the Apprenticeship programme supporting 180 young people through Modern and Foundation Apprenticeships
• Addressed poverty by supporting residents to maximising income from work and benefits
• To support the advancement of equalities within West Dunbartonshire we secured English to Speakers of Other
Languages (ESOL) funding for adult learning and delivered ASN education programme & summer programme for young
people
Challenges
• Across Housing and Employability, there were several challenges relating to increased demand for support from
communities, which is anticipated to be an ongoing challenge in future years, largely exacerbated by the ongoing increased
cost of living. The cost of living crisis should be seen as more than an economic squeeze, as well as not being able to afford
the essentials, such as food, rent, heating or transport, there is a wide range of negative impacts on mental and physical
health and well-being which will require a great deal of concerted support across all of the H&E services.
• The workforce levels of the Communities Team and W4U youth learning service has reduced in line with budget constraints
Page 41

Page 42

which will put pressure on services to meet competing demands and support communities. In addition to this the team will
face significant challenges supporting employees through the restructures at the same time as delivering on additional
service remits such as the West Dunbartonshire Community planning and the transition from European funding to UK Shared
Prosperity Funding. The impact of the reduced resources across the wider council also poses challenges to the H&E services
to get buy-in from other services to deliver on initiatives. 
• Housing services face operational challenges relating to a significant backlog of voids impacting the movement of the
housing waiting list, re-let times, void rent loss, and temporary accommodation demands. 
• There are a number of key strategic housing challenges which the Council will be required to negotiate over the next 12-
month period. Similar to other Scottish Local authority areas, we have a record number of homeless households in temporary
accommodation, and access to suitable housing is proving to be extremely challenging.  Added to the challenges around
homelessness and housing access will be the impact of the cost of living pressures on local communities, as well as recent
cuts to the Affordable Housing Supply Programme and challenges to the future financing of Energy Efficient Standards for
Social Housing (EESSH2), given that our current business plan proposes to maintain rent levels below the current rate of
inflation in respect of any uplifts, we will have significant challenges to overcome in the coming year. 
3. Strategic Assessment 
The Housing & Employability team completed a strategic assessment and performance review to determine the major influences
on service delivery and strategic priorities going forward into 2023/24. As a result of this assessment, the following factors were
recognised as having a significant influence on the work of service in 2023/24: 
Financial Challenges
The entire public sector is continuing to face significant financial challenges due to a range of factors including inflationary cost
increases, rising utility costs and insufficient funding. The Council are currently faced with an estimated cumulative funding gap in
2024/25 of £9.7m rising to £29.5m by 2027/28.  We will continue to monitor the overall financial position of the Council and
updates on estimated future budget gaps will be reported to Elected Members throughout 2023/24. 
Page 42

Page 43

These challenges mean further action is required to balance our budget and protect services for residents. This will mean that
within H&E available funding will be reduced over time and we will need to reconfigure how we work, what we do, where we
work, and potentially reduce the number of people employed. In this context, we will aim to continue to provide a sustainable,
quality service to internal clients and the public.
Employability
Future Prosperity Fund 
We have submitted an Investment Plan for the delivery of the ‘Future Prosperity Fund’ and secured funds to deliver a range of
programmes. We have also secured ‘No One Left Behind’ Funds and Parental Employability Support Funds.
The conditions of grants suggest Working4U has to change from a service provider to a lead/managing agency taking
responsibility for co-design and co-commissioning. This has established a range of challenges around the development of
assurance frameworks, procurement and competitive grant management. 
We are establishing the policies and processes for this transition while delivering services. This places challenges on the team
resources. However, we have plans in place to ensure that we achieve this transition as effectively as possible. 
Local Employability Developments / Fair work
The Scottish Government and COSLA have signed the ‘No One Left behind’ partnership agreement with an associated Delivery
Plan that will create an opportunity for transformational change in employability services. This will promote a partnership
approach where West Dunbartonshire Council will act as lead partners with private and third-sector service providers to identify
local needs and make informed decisions about how best to support employability. 
This process will see the transfer of six funding programmes, currently delivered by a range of organisations, into a single, all-
age support service. This process will bring about a range of opportunities; but will require considerable planning to ensure a
smooth transition to the new operating environment.  
To date, we have established a local employability partnership to ensure that we co-ordinate employability service provision in an
effective way. In addition to No One Left Behind, Parental Employability Support and Modern Apprenticeship programme (and
funds) funds additional funds have been made available as a direct result of COVID-19. This includes the ‘Young Persons
Guarantee’. We will integrate strategic management of the funds into the local employability partnership approach in order to
Page 43

Page 44

maximize the benefits for young people in West Dunbartonshire. We are currently developing a three-year plan for delivery of
employability services.
Employment: Green jobs 
Working 4U will continue to monitor labour market policy and direction to capitalise on emerging opportunities in zero
carbon/green energy sectors. This will be carried out in conjunction with Skills Development Scotland and West College
Scotland.  The aim will be to identify any emerging opportunities for zero carbon employment development, including for example
Retro fit housing including internal wall insulation; solar panels; and air source heat pumps.
Supporting Vulnerable People
People are vulnerable if they are unable to live at the standard that most others would expect. For instance, households may
have housing and food, but remain poor if they can’t afford to put the heating on at home, families and children may have mobile
phones, mobile devices and computers, but remain poor if there isn’t sufficient connectivity to use the equipment for the
everyday activity that others take for granted.
Understanding life transitions is important in this regard. These are typically the most significant milestones in people’s lives that
often become our greatest undertakings/challenges and will have a direct impact on the quality of our lives, these can include,
losing a job, having your tenancy ended unexpectedly or imprisonment or release. Our ability to cope with the impact of these
transitions can be significant and will have a bearing on our well-being and prosperity. 
Each of these transitions has an associated cost that, in combination with other factors such as life circumstances, can
exacerbate difficulties, particularly among families with limited resources such as those in our priority groups. It is not sufficient to
focus on particular groups without understanding circumstances, transitions and barriers that affect families and individuals on a
daily basis. Housing and Employability’s approach to addressing vulnerability, disadvantage and poverty in West Dunbartonshire
is based on delivering services and support that can mitigate the negative impact of transitions; address the barriers households
and communities face and address, where possible, the structural drivers of poverty. 
To date, we have established a local employability partnership to ensure that we coordinate employability service provision in an
effective way. In addition to No One Left Behind, Parental Employability Support and Modern Apprenticeship programme funds
we will also manage the delivery of UK shared prosperity priorities. We will integrate strategic management of the funds into the
local employability partnership approach in order to maximize the benefits for West Dunbartonshire residents. We are currently
implementing a three year-plan for the delivery of employability services.
Page 44

Page 45

Child Poverty (Scotland) Act 2017 
The intention of the Child Poverty Bill is to ‘set targets relating to the eradication of child poverty’ as well as making provisions for
plans and reporting relating to achievement of these targets. It requires the Scottish Government to meet four income-based
child poverty targets by 2030 as well as set out and report on the actions they will take to meet those targets. In addition, the Act
places a duty on local authorities and health boards to report annually on what they are doing to contribute to reducing child
poverty. 
The local child poverty action report must set out a range of commitments to address the key drivers of poverty: 
• Increasing income through employment; 
• Maximise income from the social security system; and
• Reducing household costs. 
Community Learning and Development 
The Community Learning and Development (Scotland) Regulations 2013 place a statutory requirement on local authorities to
publish a plan every three years. The plan should outline how the local authority will co-ordinate and secure ‘adequate and
efficient’ Community Learning and Development (CLD) provision with other sector partners. 
The CLD plan 2021-24 specifies: 
• How the provision of community learning and development will be coordinated with other organisations and agencies that
provide community learning and development within West Dunbartonshire; 
• What action will be taken to deliver the community learning and development plan between September 2021 and September
2024; 
• What action other organisations and agencies intend to take to provide community learning and development in West
Dunbartonshire between September 2021 and August 2024; and 
• Any needs for community learning and development that will not be met within the period of the plan. 
We have established the plan and are delivering community-based learning opportunities throughout West Dunbartonshire. 
In 2023/24, we will review and implement revised service provision within W4U and Communities 
Statement of provision for period products 
Page 45

Page 46

The Period Products (Free Provision) (Scotland) Act 2021 received Royal Assent on 12th January 2021. The Act requires local
authorities to ensure period products (like pads and tampons) can easily be picked up free of charge for anyone who needs to
use them. Each responsible body must, as soon as reasonably practicable, prepare a written statement describing the plans for
provision. The statement has been prepared in consultation with relevant individuals, groups and organisations. 
During 2023/24 the Communities Team will take the lead in delivering and continued development of the community-based
provision and will promote the service through the range of Community Planning Partnership and associated networks. 
Community Empowerment (Scotland) Act 2015
The Act sets out clear requirements for public bodies in promoting a greater level of local decision-making and empowerment of
citizens. This includes, for example, Asset Transfers, Participation Requests and Community Planning. All services across WDC
must be engaged in the process of empowering communities and work is underway to ensure awareness of the empowerment
agenda is raised. The West Dunbartonshire Community Empowerment Strategy and Action Plan is far-reaching and sets out
what is required to promote empowered communities. The Strategy was developed by a partnership strategic group and with the
Scottish Community Development Centre (SCDC) leading the consultation with local residents. 
A Project Board and Project Team are now well established to monitor delivery against the actions set out in the Strategy.
Successful delivery will depend on a collaborative approach across the organisation, partnership and wider community to build
more resilient and empowered communities across West Dunbartonshire. This is a long-term agenda that requires a real change
to service delivery to ensure it is responsive to local needs. The additional focus on our communities affected by the cost of living
crisis will also be an additional priority across the newly restructured teams.   
Progress will be driven and monitored by a Project Board that will report to CPWD via the Empowered DIG, during 2023/24 we
will continue the programme of work set out within the WDC Community Empowerment strategy. 
Community Choices 1% Framework agreement / Local Democracy
This joint agreement between COSLA and Scottish Government sets out a framework for at least 1% of local government
budgets to be decided by local residents through a participatory budgeting (PB) approach.   The framework has been refreshed
and now includes the need for greater deliberative and participatory processes that contribute to ensuring equality, inclusion and
social renewal. 
Actively involving local people can make them less passive consumers of public services and more supportive of new models of
delivery. It promotes active participation and increased levels of local decision-making. 
Page 46

Page 47

The key mechanism for meeting this target is the mainstreaming of Participatory Budgeting. This requires service areas across
the Council to consider and agree on how a percentage of their annual budgets can be decided/directed by local people. A PB
Mainstreaming Steering Group has been established to monitor performance, promote a corporate PB approach and ensure
accurate reporting to the Scottish Government on an annual basis. The team have developed the COSLA led Consul digital
platform for West Dunbartonshire, improving the uptake and the ability to report accurately. The team have also focused on
young people supporting the crosscutting of the UNCRC policy and participatory budgeting, both rooted in the principle of
participation. The UNCRC emphasizes the importance of involving children in decisions that affect them, while participatory
budgeting provides an avenue for community members, including children, to participate in decision-making processes.
Community Planning and Locality Planning
Locality planning was introduced in the Community Empowerment (Scotland) Act 2015, under Part 2: Community Planning.
Locality planning has two main functions:
• to tackle inequalities
• to enable community bodies to participate in decision-making at a neighbourhood level
The Community Empowerment (Scotland) Act 2015 requires Community Planning Partnerships to develop at least one Locality
Plan to support communities to identify their unique ambitions. Work is ongoing to support a range of communities to develop
their own neighbourhood plans that will combine with Locality Plans to form Local Place Plans.  This work needs to be led by
local communities and supported by the Community Planning Partnership. The Communities Team will support this process to
ensure both the CPWD and wider communities are fully engaged in the process.  
CCTV infrastructure
The council’s CCTV infrastructure covers the three townships of West Dunbartonshire within our Town Centre’s and housing
estates. Investment is required to bring the estate up to modernization and in 2022/23 the Communities Team secured funding
from the UK Shared Prosperity Fund. In 2023/24 the focus will be to implement improvements identified in the stock condition
survey and to develop the CCTV transmission strategy.  The public space CCTV teams play a crucial role in enhancing
community safety and engagement by deterring criminal activity, providing rapid response to incidents, and there will be a focus
on engaging with the community, building trust, and promoting transparency and accountability in partnership with Police
Scotland.
Housing Bill 2023 - Homelessness Prevention Duty
Page 47

Page 48

Many of the proposals within the recent Homelessness prevention consultation would introduce important and positive changes
for people at risk of homelessness and we had outlined our broad views in our consultation response. Key issues for West
Dunbartonshire will be a need to have sufficient and adequate resources to fund the crucial services to address homelessness,
as well as local flexibility in line with local circumstances. In addition, local democratic oversight and accountability over services
involved. 
Presently, local authority homeless and housing services are stretched and financially challenged across Scotland. The current
situation is also becoming increasingly more challenging in a context of constrained resources, changes to the Unsuitable
Accommodation Order, the humanitarian efforts to accommodate refugees and deliver the more recent Ukrainian schemes, as
well as the risks surrounding the potential increase in homelessness presentations when the schemes come to an end.
A further concern is the recent Court of Session decision in Glasgow on the local authority providing appropriate accommodation,
which could result in an increase in Judicial Reviews across the country with a further impact on resources. Consideration also
needs to be given to the timing of the implementation of changes to local connection which could potentially exacerbate current
pressures. 
Additionally, as part of the process to respond to homelessness that relates to domestic abuse to prioritise the housing rights and
personal safety of those facing abuse are crucial, given they drive a significant proportion of homelessness presentations from
women. As women mainly lead an overwhelming proportion of single-parent families in Scotland this has an impact on children’s
wellbeing and development.
Improving housing options for young people are also vital, along with a need for an improvement in the availability and
effectiveness of support services for those likely to struggle to manage a tenancy. As well as for those individuals at risk of
homelessness when leaving custody.
Local Housing Strategy & Housing to 2040
The Local Housing Strategy (LHS) sets out how West Dunbartonshire Council and its partners plan to address the housing and
housing-related opportunities and challenges over the next five year period 2022/2023 – 2026/2027.
We will implement the new strategy in 2022/23 and this new plan aims to build on the significant progress made on the issues
identified in the previous LHS 2017-2022 and to address newly arising housing matters, particularly in response to the COVID-19
crisis.
Page 48

Page 49

The Housing (Scotland) Act 2001 (‘the 2001 Act’) places a statutory requirement on local authorities to produce a LHS that sets
out its strategy, priorities and plans for the delivery of housing and related services. It should demonstrate the local authority’s
strategic approach to dealing with key housing-related issues such as:
Delivering high quality housing and housing related services across all tenures; setting out its contribution to the effective
integration of health and social care; and showing how the LHS is supporting the Scottish Government National Outcomes and
Targets, whilst reflecting the needs and priorities of the local authority area.
The development of the LHS is at an opportune moment with the publication of the Scottish Government Housing to 2040 Vision
and Principles Route Map publication in March, at the time of writing we await the publishing of the full vision, however the draft
vision established a number of key principles including:
• A well-functioning housing system: people can find, and afford, the right home for their needs. This will involve making the
best out of the housing stock we have, providing people with good investment options and ultimately ensuring the housing
system is fair;
• High-quality sustainable homes: all homes, regardless of the tenure or age of the home, should be well-designed and high
quality.  They should be easily maintained, have clear running costs and be low-carbon.  Further, all homes should be
occupied;
• Sustainable Communities: Places should be vibrant, well connected and well designed. They should include a variety of
houses to enable people to move as their needs change and be designed to promote health and well-being including
quality green space; and
• Homes that meet people's needs: homes should support well-being and areas should offer a diverse range of homes to
allow people to move.  People should be able to easily access information about their housing rights alongside services to
support their independence.
We will respond fully to Housing to 2040 within the wider development of the Local Housing Strategy, including the introduction
of a wider national rented home strategy.
Rapid Rehousing/Housing First/ homeless first
Rapid Rehousing is about taking a housing-led approach for people that have experienced homelessness, making sure they
reach a settled housing option as quickly as possible rather than staying in temporary accommodation for too long. 
Page 49

Page 50

Where homelessness cannot be prevented, Rapid Rehousing means:
• A settled, mainstream housing outcome as quickly as possible;
• Time spent in any form of temporary accommodation reduced to a minimum, with the fewer transitions the better; and
• When temporary accommodation is needed, the optimum type is mainstream, furnished and within a community.
And for people with multiple needs beyond housing:
• Housing First is the first response for people with complex needs and facing multiple disadvantages; and
• Highly specialist provision within small, shared, supported and trauma-informed environments if mainstream housing,
including Housing First, is not possible or preferable.
The need to continually improve the approach to homeless people with the most complex needs is recognised and Housing First
initiatives form part of the wider approach to tackling homelessness and repeat homelessness in Scotland.
Housing First West Dunbartonshire launched in April 2019 and the service is targeted at those with a history of issues such as
repeat homelessness, multiple and complex support needs and previous engagements with support services which have not led
to successful and/or sustainable outcomes. 
New Housing Supply
West Dunbartonshire Council through the Strategic Housing Investment Plan delivered 1000 new homes for the West
Dunbartonshire Communities.  These properties all meet the recently introduced affordable housing design standard which
provides exemplar energy efficiency and space standards.  We will continue to push the boundaries in terms of our housing
building programme putting quality first and driving forward plans to tackle the current climate emergency.
Better Homes/Sustainability
Scotland has set a legally binding target of net-zero greenhouse gas emissions by 2045. Around 14% of emissions in Scotland
come from homes. Around 22% of homes in Scotland are social housing so as a strategic landlord we have a significant part to
play. All future council homes will be built to a net zero carbon standard.
The Climate Change (Scotland) Act 2009 places duties on all public bodies to contribute to emission reduction targets
(Mitigation); deliver programmes to increase resilience against Climate Change (Adaptation), and to act in a ‘Sustainable’ way.
Page 50

Page 51

In response, we intend to further develop our housing asset management strategic approach and commitment to environmental
sustainability which will allow us to build new homes and manage existing stock and assets in a way that will make them fit for
generations to come. Key to this will be developing a new Housing Capital Investment Programme that combines our approach
to decarbonisation and positively impacting on fuel poverty.
In addition to the above, through our Better Homes approach, we are seeking to develop a new strategic vision for the future of
our high-rise accommodation to enhance tenants’ living experiences and we intend to improve connectivity across our housing
stock, again to improve the lives of our tenants.
Housing: Improving the customer journey and support 
During 2022/23, we reviewed the customer journey to ensure the service is able to adapt to change and is reflective of new ways
of engagement and working, this included exploring the opportunity for implementing digital improvements into service delivery.
In 2023/24 we will expand the implementation of digital technologies to drive efficiency and a modernized service, the focus of
this work will include the launch of the mobile app and the self-serve portal. 
In line with the Council’s Strategic priorities, Housing Operations is focused on ensuring continuous improvement across all of
our services. In 2023/24 understanding tenant experience in engaging with our services will be a priority, the focus of this work
will aim to increase tenant feedback with the housing operations processes and encourage participation in tenant satisfaction
surveys.
Antisocial Behaviour
Under the Antisocial Behaviour etc. (Scotland) Act 2004, the Council, together with the relevant chief constable, must prepare,
publish and review a strategy for dealing with antisocial behaviour (ASB). The Antisocial behaviour strategy provides the basis
for promoting coordinated action to prevent and tackle antisocial behaviour in our local communities setting out antisocial
behaviour problems in the area; the services already available for preventing and tackling them; the new services that the council
and other agencies will need to put in place to fill any gaps in services; and how the council and the police will co-ordinate their
work and exchange information. Strategies will be expected to identify those areas where antisocial behaviour problems are
particularly bad and how the council will work with local people on an ongoing basis to tackle the problems. Through Community
Planning West Dunbartonshire, Delivery and Improvement Groups, this work has already started and in 2023/24 the focus will be
on finalising the ASB strategy and associated action plan.
Continuous Improvement
Page 51

Page 52

In 2020, to support continuous improvement, the Council embarked on a programme of Fit for Future service reviews. Using a
range of tools that encapsulates service design, maturity assessments and employee engagement, information is gathered and
reviewed to identify improvements and to ensure our services are efficient and that we make the best use of our resources.
During 2023/24 we will continually assess the performance of the services within Housing and Employability, with a view to
determining if any services would benefit from a Fit for Future service review. 
Within Housing Operations we have already started work on undertaking a review of specific services, such as Voids/Allocations
and Caretaking Services.  As part of our continuous improvement journey, we will continue to review other areas and have
commenced short term working groups to undertake walk the process reviews across arrears, ASB and medical application
processes.  These groups will look at a range of aspects including existing processes, systems and interaction with customers to
identify improvements to our service delivery areas. 
Budget Sensitivity Analysis 
In reviewing the service budget projections, consideration has been given to sensitivity of these budgets, in particular for higher
risk/ higher value budgets which may have a significant impact on budgetary control and future budget projections. The analysis
has considered sensitivity around demand, costs and charges, and income levels. 
Within this service, £0.467m of the budget which has been identified as being more susceptible to fluctuations is: 
• The Homeless income budget of £4.718m is sensitive due to the nature of the service, as the income received will be
dependent on client presentations. 
Action Plan & Risks
The challenges identified at section 2 and the key factors identified in Section 3 have informed Housing & Employability priorities
for 2023/24. Appendix 1 sets out the action plan to address them, including the relevant risks and the performance indicators and
targets that will enable progress to be monitored and reported to stakeholders. It also incorporates the Strategic workforce
actions. 
The Council has identified risks at both a strategic and service level. Strategic risks represent the potential for the Council to take
advantage of opportunities or fail to meet stated strategic objectives and those that require strategic leadership. Service risks
relate to service delivery and represent the potential for impact on individual services, or the experience of those who work within
the services, i.e. employees, partners, contractors and volunteers or service users and clients in receipt of the services provided.
Page 52

Page 53

In planning for 2023/24, the Housing and Employability team considered the Council’s strategic risks and identified risks specific
to the service. These are set out in the action plan at Appendix 1 alongside actions to mitigate these, with the aim of improving or
maintaining the current position (i.e. the current risk score). 
4. Resources
Finance
Housing & Employability has a net General Services revenue budget of £3.344m and a nil capital budget in 2023/24. A
breakdown by service area is set out below. We will make the best use of the resources available to deliver on key priority areas
and secure external/match funding where this is possible.
Service Area Gross Expenditure
2023/24 (£m)
Gross Income
2023/24 (£m)
Net Expenditure
2023/24 (£m)
Capital Budget
2023/24 (£m)
Private Sector Housing 0.033 0 0.033 0
Homeless 5.185 4.718 0.467 0
Community Planning and
Development Team 
1.221 0.125 1.096 0
W4U 2.902 1.416 1.486 0
Anti-Social Behaviour 0.263 0.001 0.262 0
Total 9.604 6.260 3.344 0
Housing and Employability also have responsibility for a considerable HRA, both revenue and capital.
Gross Expenditure (Revenue) £m Capital  £m 
HRA budget 2023/24 49.186 76.056
Page 53

Page 54

Employees
Employee Numbers
The headcount and full time equivalent staff in each service area (as of 31st March 2023) are as follows:
Absence in 2022/23
The quarterly absence statistics for Housing & Employability are shown below together with the Council average for the same
periods for comparison. The figures for Housing & Employability have been lower that the Council average throughout 2022/23:
Absence in 2022/23 Quarter 1 Quarter 2 Quarter 3 Quarter 4 Annual FTE days lost per FTE employee
Housing &
Employability
2.93 3.47 3.73 3.31 12.20
COUNCIL WIDE TOTAL 3.86 3.28 4.42 4.02 14
5. Appendix 1: Action Plan
Service Area Headcount FTE
Community Planning and Development Team 22 21.05
Housing Development & Homelessness 103 87.48
Housing Operations 123 119.27
Working 4U 116 96.05
TOTAL 364 323.85
Page 54

Page 55

1. Our communities
Our neighbourhoods are safe, resilient and inclusive
Performance Indicator 2023/24
Target Owner
% of anti-social behaviour cases resolved 98% Nicola Pettigrew
% of Neighbourhood and Locality Plans supported by the Communities Team 25% Elaine Troup
Number of incidents directed to Police by Public Space CCTV team 400 Elaine Troup
% of Public Space CCTV cameras operational 85% Elaine Troup
Action Due Date Owner
Develop and implement the revised Antisocial Behavior Strategy 31-Mar-24 Nicola Pettigrew
Develop CCTV transmission strategy 31-Mar-24 Elaine Troup
Upgrade CCTV infrastructure 31-Mar-24 Elaine Troup
Build community resilience and advance community empowerment including the development of a training
programme to support the Community empowerment agenda
31-Mar-24 Elaine Troup
Deliver on the provision of period products 31-Mar-24 Elaine Troup
Strategic Risk Description Current
Assessment
Target
Assessment Owner
Engaging positively
with Residents,
Communities &
Partnerships
The risk that the Council fails to adequately engage, establish
and maintain positive relationships with local residents and
communities in addition to partnership bodies.
Elaine Troup
Page 55

Page 56

Service Risk Description Current
Assessment
Target
Assessment Owner
Failure to deliver
sufficient community
capacity building /
community
development support
to groups impacted by
COVID-19.
COVID-19 has had a huge impact on communities across the
authority. A focused approach is needed to understand the
impact on community groups and to support them to re-start
and re-build. Failure to do this would impact on the individual
and community resilience of citizens.
Elaine Troup
Failure to deliver on
the capacity building
of the Community
Empowerment
(Scotland) Act
As communities continue to recover from the impact of Covid-
19 there is an ever greater need to support and develop
communities. Community capacity building and community
development work continues within existing resources.
Elaine Troup
Failure to secure
community and
partner buy-in for the
approved Community
Empowerment
Strategy and Action
Plan.
The risk level remains the same as work continues on the
Delivery Plan. The establishment of a Project Board in 2021/22
has reduced this risk level in relation to service area buy-in.
Elaine Troup
Our residents health and wellbeing remains a priority
Performance Indicator 2023/24
Target Owner
% of youth Homeless levels in West Dunbartonshire 15% John Kerr
Action Due Date Owner
Implement Year 5 of the Home at the Heart – Rapid Rehousing Transition Plan 31-Mar-24 John Kerr
Page 56

Page 57

Performance Indicator 2023/24
Target Owner
Respond to the findings of the Homelessness Prevention and Temporary Accommodation Task and finish
Group recommendations
31-Mar-24 John Kerr
Carry out a review of the Council’s approach to Homelessness prevention 31-Mar-24 John Kerr
Implement Year 5 of the Home at the Heart – Rapid Rehousing Transition Plan 31-Mar-24 John Kerr
Review and provide greater integration within Housing Support 31-Mar-24 John Kerr
Our residents are supported to increase life and learning skills
Action Due Date Owner
Ensure no one left behind by supporting skills and learning for work, life and learning 31-Mar-24 Stephen Brooks
Review and implement revised service provision for W4U and Communities – youth learning 31-Mar-24 Stephen Brooks
2. Our Environment
Our resources are used in an environmentally sustainable way
Action Due Date Owner
Deliver new Housing Asset Management Strategy 31-Mar-24 John Kerr
Develop new Housing Design Standard incorporating proposed changes to specifications for new social
housing
31-Mar-24 John Kerr
Deliver an approach to meet Energy Efficiency Standard for Social Housing (EESSH 2) 31-Mar-24 John Kerr
Deliver a Greener, Fairer revised HRA Capital Investment Plan 31-Mar-24 John Kerr
Our neighbourhoods are sustainable and attractive
Page 57

Page 58

Performance Indicator 2023/24
Target Owner
Number of new supply social housing for rent (all supply) 80 John Kerr
Tenancy Sustainment Levels within Housing First 90% John Kerr
% satisfaction with quality of new build council housing (SHN) 80% John Kerr
% of all homeless cases re-assessed within 12 months (repeat homelessness) 5% John Kerr
The number of incidences of youth homelessness in West Dunbartonshire is reduced 280 John Kerr
Action Due Date Owner
Implement digital improvement for housing operations ( mobile app) 31-Mar-24 Nicola Pettigrew
Implement digital improvement for housing operations ( self-serve portal) 31-Mar-24 Nicola Pettigrew
Increase tenant participation in relations to housing ops (response rates) 31-Mar-24 Nicola Pettigrew
Deliver Year 2 local Housing Strategy Objectives 31-Mar-24 John Kerr
Deliver the Council’s Affordable Housing Supply Programme 31-Mar-24 John Kerr
Review Council buyback policy 31-Mar-24 John Kerr
Develop an approach to delivering alternative housing tenures 31-Mar-24 John Kerr
Service Risk Description Current
Assessment
Target
Assessment Owner
Failure to secure
funding to invest in
WDC’s CCTV
infrastructure.
The public space CCTV infrastructure covers the three main
townships of Alexandria, Dumbarton and Clydebank with a mix
of fixed space and redeployable cameras. Until resources can be
secured and improvements made the Council does remain at
risk from reputational damage, should the system fail.
Elaine Troup
Page 58

Page 59

Failure to achieve the
outcomes of the
Scottish Social
Housing Charter
The Scottish Social Housing Charter sets out the standards and
outcomes that tenants and customers should expect from social
landlords, in terms of the quality and value for money of the
services they receive. Failure to continue to meet these could
place the Council at risk of the intervention powers of the
Scottish Housing Regulator 
John Kerr
3. Our Economy
Our area has the infrastructure for sustainable and inclusive growth where businesses can flourish
Action Due Date Owner
Engage with W4 business to explore the potential for access to green jobs for local residents 31-Mar-2024 Stephen Brooks
We will support our residents to access employment and training opportunities
Performance Indicator 2023/24
Target Owner
Value (£) of debt managed £1,711.520 Stephen Brooks
Number of local people entering employment through Working 4U 407 Stephen Brooks
Number of local people entering education or training 949 Stephen Brooks
Number of local people gaining a full qualification 630 Stephen Brooks
Action Due Date Owner
Support and implement CLD, Employability and Welfare benefit three year plans to promote quality
frameworks and partnership working to enhance work, learn, money service provision
31-Mar-24 Stephen Brooks
Maximise income from employment – supporting residents into employability 31-Mar-24 Stephen Brooks
Promote inclusive growth through access to training and apprenticeship opportunities 31-Mar-24 Stephen Brooks
Page 59

Page 60

Appendix 1
Performance Indicator 2023/24
Target Owner
Review and implement revised service provision  W4U – adult learning 31-Mar-24 Stephen Brooks
We will work with partners to support economic development to deliver increased prosperity for our area
Performance Indicator 2023/24
Target Owner
Total Value (£) of Income Generated £8,110,699 Stephen Brooks
Number of local people receiving support through Working 4U 6,724 Stephen Brooks
Percentage of local people with increased or sustained income through reduced debt liability/debt
management
TBC Stephen Brooks
Number of people receiving support through Working 4U with more than one barrier to employment TBC Stephen Brooks
Action Due Date Owner
Develop and deliver an investment plan for shared prosperity fund 31-Mar-24 Stephen Brooks
Produce Local Child Poverty annual report  31-Mar-24 Stephen Brooks
Review and implement revised service provision  W4U – Welfare support 31-Mar-24 Stephen Brooks
Service Risk Description Current
Assessment
Target
Assessment Owner
Failure to respond to child
poverty legislation
Failure to respond to child poverty legislation will have a
significant impact on the Council’s reputation, more
importantly an opportunity to raise issues and respond
more effectively to child poverty issues will be lost
Stephen Brooks
Page 60

Page 61

Appendix 1
Service Risk Description Current
Assessment
Target
Assessment Owner
The cost of living crisis will
lead to a substantial demand
for access to welfare/debt
support services.
We will monitor the changing levels of demand and
target our resources to individuals and areas that are
most in need. We will seek to work with partners to
ensure we receive appropriate referrals who can benefit
from our support.
Stephen Brooks
4. Our Council
Our workforce is resilient and skilled where digital technology supports service delivery for our residents
Action Due Date Owner
Develop and implement wellbeing, employee engagement, equality and learning and development plans to
enable capabilities, improve resilience and promotion of a diverse workforce 31-Mar-2024 All Managers
Develop and implement employee life cycle plans in line with the People First Strategy to attract and retain
the workforce 31-Mar-2024 All Managers
Develop and implement learning and development opportunities to improve capabilities and resilience
within the workforce 31-Mar-2024 All Managers
Implement service review process including role design, use of new technology and new ways of working 
to add resilience, address gaps, and establish opportunities for efficiencies 31-Mar-2024 All Managers
Our Council is adaptable and focused on delivering best value for our residents
Performance Indicator 2023/24
Target Owner
% of tenants satisfied with the overall service provided by their landlord 84% John Kerr
Average length of time to re-let properties 25 Nicola Pettigrew
% of council rent that was lost due to houses remaining empty 1% Nicola Pettigrew
Action Due Date Owner
Page 61

Page 62

Appendix 1
Our Council is adaptable and focused on delivering best value for our residents
Lead the redesign and restructure of Working4U and Communities Team services to respond to Council
decisions to reduce overall budgets
31-Sept-23 Peter Barry
Our residents are engaged and empowered
Action Due Date Owner
Explore alternative forms of funding to encourage less reliance on mainstream council funding 31-Mar-24 Elaine Troup
Lead on the Council’s approach to Participatory Budgeting Mainstreaming across the organisation 31-Mar-24 Elaine Troup
Deliver the objectives set out in the Community Empowerment Strategy and Action Plan through identified
priority projects
31-Mar-24 Elaine Troup
Work with CPWD and wider communities to develop the Locality Planning Process. 31-Mar-24 Elaine Troup
Page 62

Page 63

WEST DUNBARTONSHIRE COUNCIL
Report by Chief Officer – Supply, Distribution & Property
Housing and Communities Committee 3 May 2023
Subject: Supply, Distribution & Property Delivery Plan 2022/23 Housing Asset
& Investment and Building Services - Year-end Progress & 
Supply, Distribution & Property Delivery Plan 2023/24 Housing Asset
& Investment and Building Services 
1 Purpose
1.1 This report sets out the Housing Asset & Investment and Building Services
priorities of the Supply Distribution & Property (SD&P) year-end progress
2022/23 and presents the new Delivery Plan for 2023/24.
2 Recommendations
2.1 It is recommended that Committee notes the progress achieved at year-end
and the new plan for 2023/24.
3 Background
3.1 In line with the Strategic Planning & Performance Framework, each Chief
Officer develops an annual Delivery Plan which sets out actions to help deliver
the Strategic Plan and address the performance challenges and service
priorities identified in the planning process. The Plan also provides an
overview of services and resources, including employees and budgets, sets
out the performance indicators (PIs) for monitoring progress and considers the
relevant risks.
4 Main Issues
2022/23 Year-end Performance
4.1 The 2022/23 Delivery Plan was presented to Housing and Communities
Committee on 23 November 2022 and interim progress reported on 22
February 2023.
4.2 Full details of year-end progress are set out in Appendix 1.
4.3 Of the eight actions due to be completed by 31 March, all were completed as
planned.  
4.4 Data for the PIs set out in the plan will not be available until the end of April. 
The full set of PIs will be reported through the Council’s annual performance
reporting process once all data becomes available.
ITEM 9
Page 63

Page 64

2023/24 Delivery Plan 
4.5 The 2023/24 Delivery Plan is set out at Appendix 2.
4.6       Key priorities include:
• Develop and deliver the HRA capital investment programme for 2023/24 in
line with agreed budget
• Ensure the housing stock maintains compliance with the Scottish Housing
Quality Standard and progresses to achieve the Energy Efficiency Standard
• Improve performance in the overall delivery of special needs adaptations
• Continue to improve maintenance and repairs service through achievement of
targets for response times, quality and customer satisfaction
• Reduce the number of empty properties under repair
• Implement and monitor the enhanced process for dampness and mould in
tenants homes
• Improve progress on Electrical Installation Condition Reports
• Deliver the council’s buildings upgrades programme
4.7 Implementation of the Plan will be monitored by the management team with
mid-year and year-end progress reported to Housing and Communities
Committee around November 2023 and May 2024 respectively.
4.8 It should be noted, that budget sensitivity analysis, is not yet available.
5 People Implications
5.1 There are no direct people implications arising from this report.
6 Financial & Procurement Implications
6.1 There are no direct financial or procurement implications arising from this
report.
7 Risk Analysis
7.1 Failure to deliver on the actions assigned to SD&P, may have a direct impact
on the delivery of the Council’s Strategic Plan. It is essential that remedial
action is taken to ensure strategic delivery plans achieve the commitments
detailed and approved.
8 Equalities Impact Assessment
8.1 Screening and impact assessments will be carried out on specific activities as
required.
9 Consultation
9.1 The delivery plans were developed through consultation with officers from the
strategic service areas.
Page 64

Page 65

10 Strategic Assessment
10.1  The delivery plans set out actions to support the successful delivery of the
strategic priorities and objectives of the Council.
Chief Officer: Angela Wilson
Service Area: Supply, Distribution & Property
Date:  4 April 2023
_____________________________________________________________
Person to Contact:  Karen Connelly
Performance & Strategy Business Partner
karen.Connelly@west-dunbarton.gov.uk
Appendices: Appendix 1: SD&P Delivery Plan 2022/23 – Housing
Asset & Investment and Building Services Year-end
progress 
Appendix 2: SD&P Delivery Plan 2023/24 - Housing
Asset & Investment and Building Services.
Background Papers: SD&P Delivery Plan 2022/23 – Housing Asset &
Investment and Building Services, 23 November 2022
Strategic Planning & Performance Framework 2022/27
Wards Affected: All
Page 65

Page 66

Page 66

Page 67

Appendix 1 - SD&P (BS&HAI) Delivery Plan Year-end Progress 22/23
2. Our Environment
Objective 6. Our neighbourhoods are sustainable and attractive
Action Status Progress Due Date Note Owner
Ensure the Council’s Housing stock maintains
compliance with the Scottish Housing Quality
Standard and reduce the number of properties held
in abeyance.
31-Mar-2023
The main action related to all work streams contributing to SHQS
compliance for the 22-23 programme phase is complete and work
continues into 23-24. However one of the key areas contributing to
the drop in compliance was in relation to Electric Installation
Condition Report (EICR) being valid in all properties. There has been
significant challenges with the completions due to access to
properties. Building Services continue to work with their specialist
contractor in attempts to improve this. This is currently projected to
be 50 % compliant by end of Mar 23 increasing to 70 - 80% by end
of Aug 23.
Alan Young
Deliver the HRA Capital Investment programme for
2022/23 31-Mar-2023
The HRA Capital Investment programme 22-23 phase projects have
progressed with some workstreams meeting or exceeding targets,
others behind year-end target position. Efforts to improve these
moving into 23-24 are being actioned.
Alan Young
Ensure the Council’s Housing stock progresses
towards the achievement of the energy efficiency
standard for social housing.
31-Mar-2023
ESSH projects are progressing well contributing to an increase in
homes meeting the energy efficiency standard. This will continue
into 23/24.
Alan Young
Appendix 1
Page 67

Page 68

Risk Description Current
Assessment Target Assessment Date Reviewed Note Owner
Failure to deliver medical
adaptations in agreed
target timescales
This is monitored to ensure target
timescale of 79 days average for housing
medical adaptations is adhered to ensure
satisfaction with the service and support
those in need of this service.
31-March-
2023
Good overall progress throughout year
and completion of legacy jobs will improve
the overall position. Average days
performance may be slightly higher than
yearly target due to impact of legacy job
completions, however generally positive
improvement.
Due to continued progress the risk
assessment has reduced in likelihood. Risk
matrix reduced from 3x3 to 3x2
Alan Young
Failure to maintain Housing
Stock
The risk that Council’s Housing Stock are
not fully fit for purpose with consequent
adverse impact on our ability to deliver
efficient and effective housing for Council
tenants.
31-March-
2023
Programme for investment and upgrades
to council housing continues into 23-24
and a further five year programme to 27-
28
No change to risk matrix at year end.
Alan Young
4. Our Council
Objective 10. Our workforce is resilient and skilled where digital technology supports service delivery for our residents
Action Status Progress Due Date Note Owner
Develop and implement wellbeing, employee
engagement, equality and training plans to enable
capabilities, improved resilience and promotion of a
diverse workforce.
31-Mar-2023
Service areas have regular 1-2-1 for teams and training
requirement are also discussed. Statutory training needs are
included in the annual training plan completed via the Councils’
iLearn platform or face to face where this isn’t practicable. Building
Services is continuing to focus on employee wellbeing actions
included setting challenging targets to reduce high absence levels.
In 2023/24 and future years, priority is to progress actions to
support the workforce demographics.
Martin Feeney;
Alan Young
Page 68

Page 69

Action Status Progress Due Date Note Owner
Develop and implement employee life cycle plans in
line with the People First Strategy to attract and
retain the workforce.
31-Mar-2023
Review of workforce is undertaken in consideration of current
workload demands and gaps. Phase 1 of the review of building
services is completed and phase 2 will be implemented within the
next quarter. Role profiles are being reviewed and will be job
evaluated.
Martin Feeney;
Alan Young
Implement service review process including role
design, use of new technology and new ways of
working to add resilience, address gaps, and
establish opportunities for efficiencies
31-Mar-2023
Continue to review service delivery and utilise flexible
wfh/remote/mobile work styles for service resilience, utilising IT
equipment solutions. New technologies including IHMS continue to
be developed resulting in-service improvements.
Martin Feeney;
Alan Young
Develop and implement training plans and
development opportunities to improve capabilities
and resilience within the workforce.
31-Mar-2023
Statutory training is delivered as planned. Discussions on training
needs considered where appropriate. Scheduled or cyclical training
is carried out via iLearn portal or face to face. Consultations are
ongoing with TUs and workforce with a view of the introduction of
general skilling and multi-skilling and a condensed working hours
pilot will be carried out to improve efficiency, resilience and staff
satisfaction levels.
Martin Feeney;
Alan Young
Objective 11. Our Council is adaptable and focused on delivering best value for our residents
Action Status Progress Due Date Note Owner
Implement improvement plan for Building services –
Year 2 31-Mar-2023
Phase 1 and 2 of the restructure of Building Services is complete.
The stores/ workshop review is progressing. Outputs of the staff
survey and working group have been reviewed. The management
team are leading change to improve service. Year 3 of the 5 year
improvement plan for building services will continue in 2023/24.
Martin Feeney
Page 69

Page 70

Risk Description Current
Assessment Target Assessment Date Reviewed Note Owner
Failure to implement
improvement plan to
ensure Building Services
are fit for purpose
The implementation of the improvement
plan will enhance the effectiveness,
efficiency and best value of Building
Services
31-March-
2023
Good progress made in 2022/2023 with
evidence of improvements in many areas.
Actions in Year 2 of Improvement Plan
have been completed. Year 3 to be
delivered in 2023/2024.
No change to risk matrix.
Martin Feeney
Failure to implement IHMS
system across building
services
The effective implementation of the
IHMS system will delivery efficiency,
improve case tracking, capture customer
satisfaction and improve service
delivery.
31-March-
2023
Good progress made in 2022/2023 on
Building Services IHMS improvement
action plan. Work and development will
continue in 2023/2024.
No change to risk matrix.
Martin Feeney
Failure to meet citizen
expectation and service
standards
Risk of citizen dissatisfaction due to us
not doing what we say we will when we
say we will or not completing required
works first time.
31-March-
2023
Full year data not available at time of
update, but it is anticipated it will be
below performance in comparison to
2021/2022. A number of factors are
thought to have contributed and full
analysis will be carried out.
No change to risk matrix.
Martin Feeney
Failure to demonstrate
robust financial and
productivity systems within
building services
The development of new costing model
will mitigate against this financial risk.
Process change and review will improve
the system for charging of works
31-March-
2023
This operational risk will now close as the
new costing model is now in place. Martin Feeney
Action Status
Cancelled
Overdue
Not on track
Page 70

Page 71

In Progress and on track
Completed
Risk Status
Alert
High risk
Warning
OK
Unknown
Page 71

Page 72

Page 72

Page 73

2023/24
SUPPLY,
DISTRIBUTION AND
PROPERTY –
Building Services &
Housing Asset &
Investment Extract
Appendix 2
Page 73

Page 74

Contents
1. Introduction .................................................................................................................................................................................................... 3
2. Performance Review ...................................................................................................................................................................................... 3
3. Strategic Assessment .................................................................................................................................................................................... 5
4. Resources ...................................................................................................................................................................................................... 8
Appendix 1: Action Plan .......................................................................................................................................................................................... 11
Page 74

Page 75

1. Introduction
Supply, Distribution and Property comprises a wide range of services covering Corporate Asset Management, Building Services, Housing Asset
& Investment and the Corporate Procurement Unit (CPU). It is one of 8 strategic areas responsible for delivering the Council’s Strategic Plan.
Key actions to help achieve that are set out in this Delivery Plan, together with actions to address any performance issues and service priorities
identified in the planning process.
The progress of this Plan will be monitored and managed by the management team and reported to Housing and Communities Committee for
Building Services and Housing Asset & Investment, at mid-year and year-end. 
2. Performance Review
The Supply, Distribution and Property management team completed a detailed review of 2022/23 performance, focusing on the following:
• 2022/23 Delivery Plan year end progress;
• Local Government Benchmarking Framework (LGBF) comparative data;
• Association for Public Service Excellence (APSE)
• Scottish Housing Network (SHN)
• Complaints
• Continuous Improvement (Fit for Future reviews)
This review highlighted our key achievements in 2022/23 as well as the challenges to be addressed in 2023/24. These are summarised below.
Key Achievements in 2022/23 
Listed below are some of the major achievements in each service area. The service achieved many other outcomes throughout the year which
are not recorded here but are as important.
Housing Asset & Investment
Monitored the HRA capital investment programme to support the delivery of:
• Over 2000 internal upgrades including; kitchens, bathrooms, showers, adaptations, central heating, smoke detectors, windows and doors.
Page 75

Page 76

• Over 300 environmental improvements including bin stores.
• Over 500 external improvements including; new roof coverings, external insulated render and tenement structural refurbishments.
Building Services
• Delivered the Councils’ programmes for assets capital funded improvement projects for both Housing and Corporate Asset Management.
• Reduced the number of out of target repairs.
• Reduced the number of active response repairs.
• Implemented phase 1 and completed phase 2 of Service review.
• Successfully implemented a revised financial model.
• Improved management and use of the Integrated Housing Management System (IHMS).
Key Challenges from 2022/23
Cross Service 
Workforce.
• The turnover coupled with the time taken to replace, recruit and train employees across Supply Distribution and Property continued to be a
challenge in 2022-23.
• Continuing high levels of sickness in Building Services have an impact on available resource resulting in increased expenditure for sub
contracted works and agency costs.
• The national skills shortage of qualified and experienced officers in Building Services, Procurement and Corporate Asset Management,
resulted in reduced workforce numbers and increased demands on existing teams. For Buildings Services this has resulted in alternative
service delivery models being introduced.
Capital Projects
• Increasing issues relating to supply and cost of labour and materials, due to increased energy, transport and raw material costs, impacted on
supply chains, and third parties and our ability to carry out works within budget and on time.
Page 76

Page 77

Building Services
• As a result of not meeting service demands, there continues to be an increase in enquiries and complaints from tenants, residents and
elected members.
• Efforts to complete the backlog of repairs and difficulty in recruiting resources did impact on the team overall performance, time to respond to
emergency repairs and average days taken to complete non-emergency repairs within the targets continues to be challenging.
• This year has seen a reduction in SHQS failures although they continue to remain higher than target. The key contributing factor is due to the
Electrical Installation Condition Reports (EICRs) programme not being completed as planned due to issues with getting access to undertake
the work.
• The number of void properties due for re-let had increased significantly, due to a number of factors including Covid.
• There was a significant increase in demand for inspections and repairs relating to damp and mould in properties. Policy, processes and
procedures have been reviewed to effectively manage and proactively address this.
3. Strategic Assessment
The management team completed a strategic assessment to determine the major influences on service delivery and priorities in 2023/24. These
are summarised below.
Financial Challenges 
The entire public sector is continuing to face significant financial challenges due to a range of factors including inflationary cost increases, rising
utility costs and insufficient funding. The Council are currently faced with an estimated cumulative funding gap in 2024/25 of £9.7m rising to
£29.5m by 2027/28.  We will continue to monitor the overall financial position of the Council and updates on estimated future budget gaps will be
reported to Elected Members throughout 2023/24. 
These challenges mean further action is required to balance our budget and protect services for residents. This will mean that within the Service
available funding will be reduced over time and we will need to reconfigure how we work and what we do, where we work, and potentially reduce
the number of people employed. 
Page 77

Page 78

Budget Sensitivity Analysis
In reviewing the service budget projections, consideration has been given to sensitivity of these budgets, in particular for higher risk/ higher value
budgets which may have a significant impact on budgetary control and future budget projections. The analysis has considered sensitivity around
demand, costs and charges, and income levels. 
Within this service, budgets which have been identified as being more susceptible to fluctuations include:
• Building Materials.
• Labour costs.
• Transport fuel costs.
• Capital Plan.
Housing Asset & Investment
Housing Capital Investment Programme 
A refreshed Housing Revenue Account (HRA) Capital Plan for period 2023/28, totalling £278m was agreed at Council March 2023. The
programme will help deliver the requirements of the Scottish Housing Quality Standards (SHQS), the Energy Efficiency Standard for Social
Housing (EESSH) its landlord obligations, health and safety responsibilities and deliver the Council’s new build programme. Delivering the
programme in line with the budget, timescales and implementation plan is a significant priority. A revised plan will be agreed to account for the
addition investment. 
Building Services
Housing & Corporate Capital Improvement Projects 
The refreshed Housing Revenue Account (HRA) Capital Plan 2022/26 together with the Corporate Asset capital improvement projects, sets out
the significant operational programme of work for Building Services including;
• Corporate asset upgrades and improvement projects;
• Council housing reroofing programme;
• Council housing kitchen, bathroom, shower, heating, special needs adaptations and uPVC window/ doors programmes.
Page 78

Page 79

Improvement Plan for Building Services  
The action plan is a strategic priority and a critical influencing factor for Building Services. Progress of year 3 of the 5 year plan includes;
Workforce; individual performance and productivity management, resource and succession planning, remuneration and working hours model.
Service Provision; planning, supervision and stores operations, improvements to customer satisfaction, speed of delivery, quality and
consistency of the repairs provision. 
Electric Installation Condition Reports (EICR)
The process to gain access to properties to complete an EICR is under review to increase the number of completed inspections. The target for
completion of EICR has been reviewed for 23/24 to support improved compliance with SHQS.
Housing Voids 
The Void working group, chaired by Housing Operations has been established to reduce the time taken to re-let properties. The significant
priority to reduce the number of void properties will continue into 23/24. Building Services will work with the internal partners to improve relet
times.  
Mould and Dampness in Tenants Home
The process for mould and dampness in tenants’ homes has been revised to effectively manage and eradicate dampness within tenants’ homes.
Building Services will Implement the revised process and monitor performance.
Buildings Upgrades  
The 23/24 programme for delivering Corporate Assets building upgrades includes renovation, remodelling and refreshing corporate buildings in
accordance with the Corporate Asset Management Plan and is a key priority.
Council Wide Climate Change Strategy
The Council has developed a Climate Change Strategy in response to Scotland’s climate emergency and to provide a route map towards
meeting Scotland’s national net zero carbon target by 2045. This Strategy has informed the development of a Climate Change Action Plan for
2023/24 to ensure environmental actions are devolved to relevant service areas and climate change action is mainstreamed across council
policies, operations and the wider public. Progress against the actions assigned to SD&P will be monitored.
Page 79

Page 80

Continuous Improvement
To support continuous improvement, the Council has an established programme of Fit for Future service reviews. Using a range of tools, that
encapsulates service design, maturity assessments and employee engagement, information is gathered and reviewed to identify improvements
and to ensure our services are efficient and that we make best use of our resources. During 2023/2024 we will assess the performance of the
services within SD&P with a view to determining if any service would benefit from a Fit for Future service review.  
Action Plan
The challenges identified in Section 2 and the key factors identified in Section 3 have informed SD&P priorities for 2023/2024. Appendix 1 sets
out the action plan to address them. It also includes:
• performance indicators and targets, that will enable progress to be monitored and reported to stakeholders;
• strategic workforce actions; and
• strategic and/or service risks.
The Council has identified risks at both a strategic and service level. Strategic risks represent the potential for the Council to take advantage of
opportunities or fail to meet stated strategic objectives and those that require strategic leadership; while service risks relate to service delivery
and represent the potential for impact on individual services, or the experience of those who work within the services, i.e. employees, partners,
contractors and volunteers or service users and clients in receipt of the services provided. In identifying the relevant risks for 2023/2024 and
actions to mitigate them, the aim is to improve or maintain the current position (i.e. the current risk score) set out in the appendix.
4. Resources
Finance
Supply Distribution and Property has a net revenue budget of £1.51m credit and a capital budget of £5.898 in 2023/2024. A breakdown by
service area is set out below. We will make the best use of the resources available to deliver on key priority areas and secure external/match
funding where this is possible.
Service Area Gross Expenditure
2022/23 (£m)
Gross Income
2022/23 (£m)
Net Expenditure
2022/23 (£m)
Capital Budget
2022/23 (£m)
Consultancy Services 1.009 -0.784 0.225
Page 80

Page 81

Corporate Assets 3.011 -5.331 -2.320
Capital Investment Team 0.219 -0.224 -0.005 1.72
Private Sector Housing Grant 0.527 -0.446 0.081
Corporate Asset Maintenance 3.300 -3.300 0 4.18
Housing Asset Maintenance &
Investment
0.446 -0.396 0.050
CPU 0.666 -0.500 0.166
HMTA 20.053 -20.928 -0.875
Office Accommodation 1.482 -0.314 1.168
Total 30.713 -32.223 -1.51 5.898
Employees
Employee Numbers 
The headcount and full time equivalent staff in each service area (as of 31st March 2023) are as follows:
Absence in 2022/23
The quarterly absence statistics for Supply Distribution and Property are shown below together with the Council average for the same periods for
comparison. The figures have been higher that the Council average throughout 2022/2023:
Function Headcount FTE
Corporate Asset Management 40 36.97
Housing Asset & Investment 12 10.40
Maintenance & Repairs 360 348.36
CPU 16 15.54
TOTAL 428 411.27
Page 81

Page 82

Absence in 2022/23 Quarter 1 Quarter 2 Quarter 3 Quarter 4 Annual FTE days lost per FTE employee
Supply, Distribution &
Property
3.96 4.56 4.94 4.00 16.52
COUNCIL WIDE TOTAL 3.86 3.28 4.42 4.02 14.00
Page 82

Page 83

Appendix 1: Action Plan
2. Our Environment
Objective 6. Our neighbourhoods are sustainable and attractive
Performance Indicator Target 23-24 Owner
Percentage of repairs appointments kept 90.5% Martin Feeney
% of properties that require a gas safety record which had a gas check and record completed by the
anniversary date
100% Martin Feeney
Percentage of reactive repairs carried out completed right first time 90% Martin Feeney
% of tenants satisfied with the repairs and maintenance service 89% Martin Feeney
Average length of time taken to complete emergency repairs TBC Martin Feeney
Average time taken to complete medical adaptations TBC Alan Young
% of council dwellings that meet the Scottish Housing Quality Standard TBC Alan Young
Average time taken to complete non-emergency repairs 9 days Martin Feeney
% of council houses that are energy efficient 100% Alan Young
Page 83

Page 84

Performance Indicator Target 23-24 Owner
Average time to inspect and repair empty homes TBC Martin Feeney
% of properties returned from repairs within target 80% Martin Feeney
Action Due Date Owner
Ensure the Council’s Housing stock maintains compliance with the Scottish Housing Quality Standard and
reduce the number of properties held in abeyance. 31-Mar-2024 Alan Young
Ensure the Council’s Housing stock progresses towards the achievement of the energy efficiency standard
for social housing. 31-Mar-2024 Alan Young
Develop Housing Capital Investment Plan for 2023/28. 30-Sep-2024 Alan Young
Deliver the HRA Capital Improvement programme for 2023/24 31-Mar-2024 Martin Feeney
Improve customer satisfaction with Building Services 31-Mar-2024 Martin Feeney
Reduce the number of empty properties under repair 31-Mar-2024 Martin Feeney
Improve progress on Electric Installation Condition Reports 31-Mar-2024 Martin Feeney
Improve maintenance & repairs performance 31-Mar-2024 Martin Feeney
Progress building upgrades programme  31-Mar-2024 Martin Feeney
Implement revised process and monitor performance to address dampness and mould in Tenant Homes 31-Mar-2024 Martin Feeney
Page 84

Page 85

Risk Description Current Assessment Target Assessment Owner
Failure to deliver medical
adaptations in agreed
target timescales
This is monitored to ensure target timescale of 60
days average for housing medical adaptations is
adhered to ensure satisfaction with the service and
support those in need of this service.
Alan Young
Failure to maintain
Housing Stock
The risk that Council’s Housing Stock are not fully fit
for purpose with consequent adverse impact on our
ability to deliver efficient and effective housing for
Council tenants.
Martin Feeney
Failure to meet citizen
expectation and service
standards
Risk of citizen dissatisfaction due to us not doing what
we say we will when we say we will or not completing
required works first time.
Martin Feeney
4. Our Council
Objective 10. Our workforce is resilient and skilled where digital technology supports service delivery for our residents
Page 85

Page 86

Action Due Date Owner
Develop and implement wellbeing, employee engagement, equality and learning and development plans to
enable capabilities, improve resilience and promotion of a diverse workforce 31-Mar-2024 Martin Feeney;
Alan Young
Develop and implement employee life cycle plans in line with the People First Strategy to attract and retain
the workforce. 31-Mar-2024 Martin Feeney;
Alan Young
Implement service review process including role design, use of new technology and new ways of working to
add resilience, address gaps, and establish opportunities for efficiencies 31-Mar-2024 Martin Feeney;
Alan Young
Develop and implement learning and development opportunities to improve capabilities and resilience within
the workforce. 31-Mar-2024 Martin Feeney;
Alan Young
Objective 11. Our Council is adaptable and focused on delivering best value for our residents
Action Due Date Owner
Implement improvement plan for Building services – year 3 31-Mar-2024 Martin Feeney
Risk Description Current Assessment Target Assessment Owner
Failure to implement
improvement plan to
ensure Building Services
are fit for purpose
The implementation of the improvement plan will
enhance the effectiveness, efficiency and best value
of Building Services
Martin Feeney
Page 86

Page 87

Risk Description Current Assessment Target Assessment Owner
Failure to implement
IHMS system across
building services
The effective implementation of the IHMS system will
delivery efficiency, improve case tracking, capture
customer satisfaction and improve service delivery.
Martin Feeney
Page 87

Page 88

Page 88

Page 89

WEST DUNBARTONSHIRE COUNCIL
Report by Chief Officer – Housing and Employability
Housing and Communities Committee: 3 May 2023 
___________________________________________________________________
Subject: Housing Revenue Account Capital Programme Update – Better Homes
West Dunbartonshire
1. Purpose
1.1 This purpose of this report is to provide members of the Housing and
Communities Committee with an update on the development of a revised
Housing Revenue Account Capital Programme following the decision taken
by West Dunbartonshire Council to agree a weekly rent increase of 5% in
2023/24.
2. Recommendations
2.1 It is recommended that the Housing and Communities Committee:
(i) Note the content of the report and the progress made to date in the
delivery of the Council’s ambitions around housing investment;
(ii) Approve the undertaking to conduct all necessary procurement
exercises for the delivery of the identified work streams within Section
4 of this report;
(iii) Note the establishment of a Tenant/Officer Short Life Task and Finish
Group to deliver some of the key objectives outlined within this report;
and
(iv) Note that a further progress report will be provided to the next Housing
and Communities Committee.
3. Background
3.1 At the West Dunbartonshire Council meeting on 1 March 2023 a motion was
passed which approved a 5% rent increase in 2023/24. The impact of this 5%
rental increase to the Housing Revenue Account Business Plan is that it
generates an additional £50m of available capital expenditure over the next 5
years (2023/24-2027/28).
3.2 The approved motion supported the Council’s ambitions to develop our
Housing Service to become sector leading in Scotland, meeting and
exceeding the needs and expectations of our tenants, now and into the future.
3.3 Furthermore to deliver on these ambitions, it was recognised that greater
investment was needed in tenants’ priorities such as:
• More new sustainable housing that is attractive, built to the highest
standards and net zero carbon
ITEM 10
Page 89

Page 90

• More homes to suit the needs of larger families
• More homes to address identified medical needs
• Better homes where we respond proactively to damp and mould issues
• Better homes that are energy efficient
• More homes to increase choice and opportunities for families
3.4 The Council decision approved the:-
• Use of £10m to increase the Council’s buyback programme over
the next five years to purchase additional housing on the local
housing market to address identified need; and
• Use the remaining £40m to accelerate the following renewal and
replacement programmes over the next five years that our
tenants have told us are most important to them:-
• Energy efficiency measures including new heating
systems
• Kitchen and Bathroom Renewals
• Window/Door Renewal Programmes
3.5 In addition, there was approval to accelerate a programme to eliminate damp
and mould problems from all tenants’ homes.
4. Main Issues
4.1 As part of the decision made by the Council, on 1 March 2023 it was agreed
that the Chief Officer Housing and Employability provide regular update
reports to the Housing and Communities Committee on the development and
implementation of a programme to deliver the additional £50m of capital
investment which would be delivered in full consultation and involvement of
the West Dunbartonshire Tenants and Residents Organisation (WDTRO)..
This is the first of those regular update reports.
Council Buy Back Programme
4.2 As approved at the West Dunbartonshire Council meeting on 1 March 2023,
additional funding of £10m (£2m each year from 2023/24-2027/28) will be
utilised to scale up the Council’s Buyback programme.  In 2023/24 and in
each of the subsequent years up to and including 2027/28 we plan to acquire
a minimum of 60 new homes each year meaning and additional 300 new
Council homes to meet identified need.
4.3 The additional funding will specifically target larger family homes to meet an
identified housing need.  To meet these defined targets an additional resource
within the Housing team will be committed from Housing Revenue Account
Capital funding to deliver on the acquisition of new homes.  This new resource
will also lead on refreshing our Buyback Policy to maximise opportunities to
help deliver on the defined targets.  An updated policy will be presented to the
meeting of the Housing and Communities Committee in September 2023.
Page 90

Page 91

Proactive Approach to talking Damp and Mould 
4.4 Following the tragic passing of Awaab Ishak which the circumstances
concluded by the Coroner in November 2022 to be as a result of prolonged
exposure to mould within a social housing tenancy in Rochdale, England, The
Council, has taken steps to ensure our approach to treating damp and mould
is as robust and effective as possible and a new improved procedural
approach will be presented to the Housing and Communities Committee in
May 2023.
4.5 However, for the Council to meet the declared ambition to be a sector leading
housing service, a more proactive approach to eliminating damp and mould
issues in council homes is required.  The Housing team have been
investigating technology solutions to help identify, tackle, and prevent damp
and mould issues. 
4.6 A preferred solution has been identified to introduce environmental sensors
into all our homes.  This technology is relatively new but has been
successfully implemented by a number of housing organisations in Scotland
to date.   The technology allows the tracking of temperature, humidity and
Co2 in our homes.  Linked to a gateway, to which we can also connect the
home fire/smoke detection systems we can track the fluctuations in the
home’s temperature and humidity and air quality.
4.7 The gateway links to a dashboard which will provide Housing staff with real
time information. It could identify high levels of humidity, which can create
conditions for mould growth if not managed appropriately, for example if it
peaks in the evening (typically time for cooking, washing etc.) and does not
return to a normal level within a reasonable timeframe then the home is not
being appropriately ventilated. However, if the humidity levels are high at all
times despite ventilation this suggests that moisture may be coming from
elsewhere e.g. a leak or rising or penetrative damp. Air quality data (co2
sensors) will also help us understand if a room is being ventilated because it
will tell us about the freshness of air in a room.  Poor quality air can lead to
headaches, fatigue and support the spread of disease within the home.  This
approach will also have a positive benefit on the health and wellbeing of our
tenants. 
4.8 We propose that a range of housing staff would have access to the dashboard
to help them provide both informed support to tenants and facilitate decisions
about next steps e.g. installing more fans, investigating leaks. However a new
job role within the Housing team would be required to monitor and propose
the necessary action and/or referral.  This additional staffing resource
requirement will be funded within Housing Revenue Account Capital Plan to
ensure the benefits of the new technologies are maximised.
4.9 Another benefit of use of environmental sensors is the tenant mobile app
which also provides tenants with real time information about their home.  This
helps the tenant in managing their home and make the connections between
Page 91

Page 92

their activities and any related damp and mould risk and empowers the tenant
to take action to improve air quality, and ultimately their wellbeing.
4.10 It is proposed that in 2023/24 we roll out an initial programme which would
provide environmental sensors in around 2000 of our council homes, as part
of our wider actions to eliminate damp and mould from all Council Homes. 
This would coincide with the establishment of job role/s within the Housing
team who would have responsibility for monitoring the environmental sensors
and ensuring that the appropriate actions are undertaken and monitored.
4.11 We have identified the following priority house types which would be
prioritised in the first tranche of the rollout of the provision of environmental
sensors as follows:-
• Voids
• Sheltered Housing
• Multi Storey Flats
• Housing First tenancies
• Temporary/Supported Accommodation; and
• Properties identified as at risk by Housing staff
4.12 A procurement strategy would be developed to deliver the roll out of the
environmental sensors and would be fully delivered from within the additional
funding made available through the Council decision taken on 1 March 2023. 
The procurement strategy would be developed in such a way that following an
evaluation of the effectiveness of the environmental sensors before the end of
2023/24 the provision of the sensors could be extended to all council address
before the end of March 2028. 
Housing Capital Programme
4.13 The Council’s annual rent consultation exercise was undertaken between
December 2022 and January 2023 and the outcomes were reported to the
meeting of West Dunbartonshire Council on 1 March 2023.  As part of this
consultative exercise tenant priorities in terms of the acceleration of existing
renewal programmes were identified in the table below:-
4.14 This information gives Council Officers an indication of tenant priorities from
over 800 responses. However before a programme is developed Council
Page 92

Page 93

Officers will establish a short life task and finish group with members of the
WDTRO to develop further our Housing Capital Programme to ensure it
meets the tenant priorities.; This group will meet over May and June and
conclude their work before the Summer recess and this will form a report to
the Housing and Communities Committee in September 2023.  
5. People Implications
5.1 To deliver the ambition outlined within this report additional staff resources will
be required, however this be delivered within the current budgetary resource.
6. Financial and Procurement Implications
6.1  It should be noted that the 30 year HRA business model has been prepared
on the basis that there will be fluctuations in inflation over the period of the
plan. These assumptions would need to be revised in the event of long-term
inflation forecasts being above target. The planning assumption for long-term
inflation in the business model is 1.9% initially rising to 2.5% or
additional pressures on the revenue account becoming apparent. The other
key variable within the business model is the capital expenditure
requirements which can alter depending on circumstances and priorities.
The HRA business model has been updated this year with the revised
proposed capital plan as part of the normal annual review to recognise the
most up-to-date information and to consider affordability.
6.2 In considering affordability, a key output from the HRA business model is the
percentage of rental stream that is required to fund debt charges. This is an
indicator of the amount of prudential borrowing that can be undertaken without
putting undue stress on the remainder of the revenue budget. When the
decision was taken to retain all the housing stock in West Dunbartonshire the
investment requirement needed to achieve the Scottish Housing Quality
Standards, coupled with the historic debt structure of HRA debt, suggested
that the “debt affordability” percentage in West Dunbartonshire should not
exceed 50%. Additionally each year of the 30 year plan must have a surplus
or break even revenue position. The most recent update based on the
recommended 5% rent increase for 2023/24 has an average percentage of
34.7% with a peak of 42.4% in financial year 2030/31.
6.3 As indicated above, to maintain the viability of the HRA Business Plan, the
additional capital investment of £50m requires to be phased appropriately
over the 5 year period.
6.4 As approved by Council on 1 March 2023, £10m of the additional £50m is
allocated to deliver additional housing acquisitions over the next 5 year period.
It is also projected a figure of around £10m will be required to deliver the
ambitions in terms of eliminating damp and mould from all council homes
within the same period.  Therefore that allows the remainder of the additional
investment sum of around £30m to support priority work streams which will be
identified through the Short Life Task and Finish Group to be established
between tenant representative and council officers.   
Page 93

Page 94

6.5 All procurement activity carried out by the Council in excess of £2m is
subject to a contract strategy. The contract strategy for the HRA Capital
Programme will be developed by the Corporate Procurement Unit in
consultation with Housing Development Officers. The contract strategy will
include, but is not limited to; contract scope, service forward plan, the market,
procurement model and routes – including existing delivery vehicles, roles
and responsibilities, risks, issues and opportunities and on-going contract
management. Opportunities to maximise the positive social, economic and
environmental impact for the Council through the relevant procurement
processes will be developed in line with procurement policy.
7. Risk Analysis
7.1 The key driver for determining rents for Council properties is the HRA
investment plan. Failure to set rents consistent with the delivery of this
plan will potentially result in insufficient funding being available to meet
the ambitions within this report.
7.2 In producing the budget a number of assumptions have been made
in relation to performance around rent recovery, voids and the
impact of welfare reform. These issues will be closely monitored
during 2023/24 and members advised of any significant variations
that will impact materially on the sufficiency of the budget as
proposed.
7.3 In terms of the capital programme, the main financial risks relate to:
• whether inflation increases costs, resulting in plans requiring to
be reviewed upwards;
• Longer-term affordability requires to be considered in
determining appropriate levels of capital funding. Ongoing budgetary
control processes will monitor the above issues and any issues will be
reported to a future Council meeting for consideration.
8. Equalities Impact Assessment (EIA)
8.1  An EIA screening has been undertaken by officers and no issues
were identified.
9 . Consultation
9.1 The Council has a statutory requirement to consult with tenants regarding
HRA expenditure, the proposed consultative exercise committed to within
this report builds on the Council’s strong and demonstrable approach to
effective tenant participation.
9.2 The WDTRO supported by the HRA budget scrutiny group (Joint Rent
Group) are well established tenant structures. It is proposed after the
conclusion of the Task and Finish Group the Joint Rent Group will have
responsibility for the ongoing monitoring of the Housing Capital Programme.
Page 94

Page 95

This group meet with Officers and the Convenor monthly and examines the
HRA to ensure increased transparency and demonstrate Value for Money
to tenants.
10. Strategic Assessment
10.1 The proposals contained in this report directly address all of the Council’s
strategic priorities. The investment in, and provision of attractive affordable
housing will also indirectly support the objective of economic growth and
employability through supporting employment and improving place
attractiveness.
10.2 Proper budgetary control and sound financial practice are cornerstones of
good governance and support Council and Officers to pursue the five
strategic priorities of the Council’s Strategic Plan.
Peter Barry
Chief Officer, Housing and Employability
Date:  18 April 2023
__________________________________________________________________
Person to Contact: John Kerr – Housing Development and Homelessness
Manager, Housing and Employability, telephone:
07793717981, email: John.Kerr@west-dunbarton.gov.uk
Appendices: None
Background Papers: HRA Capital Programme EIA, March 2023
Wards Affected: All
Page 95

Page 96

Page 96

Page 97

ITEM 11
WEST DUNBARTONSHIRE COUNCIL
Report by Chief Officer – Supply, Distribution & Property
Chief Officer - Housing and Employability
Housing and Communities Committee
3 May 2023
Subject: Housing Repairs - Addressing Dampness and Mould in Council Houses
1 Purpose
1.1 The purpose of this report is to provide Committee with an overview of the
services’ approach to the management and future prevention of dampness
and mould in council houses.
2 Recommendations
2.1 It is recommended that Committee:
3
3.1
3.2
• Note the contents of the report and the progress to date; and
• Approve the recommendations outlined in 4.3.2   – 4.3.6.
Background
Members are aware of the tragic case of the death of a young child in
Rochdale, England. The young child had suffered prolonged exposure to
mould as concluded by the Coroner in November 2022.
The council agreed at its meeting on 21 December 2022, the following motion:
This avoidable death should be a wake-up call for all social housing providers
including West Dunbartonshire Council, and local, regional and national
Housing Associations. Council therefore asks the Chief Officer of Supply,
Distribution and Property and Chief Officer, Housing and Communities to:
1. Review our approach to dampness in Council properties and how best to
prioritise associated repairs.
2. Introduce a process to ensure all dampness/mould repairs are checked and
signed off by Maintenance Co-ordinator before the case is closed.
This quality control check should ensure the action taken has fully
resolved the complaint.
3. Produce a briefing note setting out the outcome of the review to be sent
to all elected members for information.
Page 97

Page 98

Council further notes that we will take all appropriate actions to address any
concerns tenants may have.
4 Main Issues
4.1 Immediate Response
4.1.1 In November 2022, Housing, Building and Citizens Services taking a joined up
approach, responded immediately to the coroner’s decision. The teams
discussed the current approach to repairs requests, and reviewed ideas and
ways to ensure appropriate, sensitive communication, clear information and
responsive actions to support tenants.
4.1.2 The leaflet for tenants - as provided by Scottish Government and adapted
locally – was updated. This provides information for tenants on how to
address condensation, prevent dampness and importantly report a concern
about mould / dampness
4.1.3 A consistent communication was developed for services dealing directly with
tenants, for example through our contact centre, face to face and via social
media.
4.1.4 A clear system was introduced for collating, monitoring and reporting statistics
in relation to requests for inspection / repair in relation to dampness. Analysis
of housing property data was made available to inform this process.
4.1.5 A triage approach was introduced to respond to tenants’ requests for
inspection and repair with the aim of responding to initial inspection for urgent
cases within 48 hours.
4.1.6 It was agreed there would be a commitment to undertaking a technical survey
within 14 days with priority for those urgent cases.
4.1.7 Resources were prioritised and reviewed on a weekly basis with additional
resource  being progressed to ensure continued commitment to inspect
urgent cases within target timeline.
4.1.8 As agreed by Council, a full review of the process was undertaken. The
revised process is attached at Appendix 1.
4.2 Current Position
4.2.1 The following data provides an overview of the position during 2022/23:
▪ 6,907 repair inspection have been carried out from 1 April 2022 to 31
March 2023
▪ of these, 932  inspections for dampness and condensation, 14% of total
inspections undertaken
▪ following inspection 270 repairs were  raised with 42 remaining active at 31
March 2023
▪ 29% of inspections resulted in further repairs work being required
Page 98

Page 99

As a comparison, In 2021/22 at total of 169 repairs were completed
associated with dampness; this equates to 1% of all response repairs
4.3 Proposals
4.3.1 The revised process as outlined at Appendix 1, includes the following key steps to address
and prevent dampness and mould:
• Housing and Building Services teams will continue to offer advice where appropriate.
• Any employee visiting a tenant will   be vigilant and look for signs of
dampness or mould in every home.
• Dampness inspection requests will be prioritised to be undertaken
within 2 working days.
• Repairs resulting from an inspection will be re-categorised to urgent (10
day) repairs where appropriate.
• Following ithe outcome of all dampness inspections, housing
officers  will arrange a follow up visit within 2 working days.
• Housing solutions and decisions – for example decant - to address
dampness and mould take account of all factors including building
and family circumstances
4.3.2 Housing Development have been investigating technology solutions to help
identify, tackle, and prevent damp and mould issues proactively. The
preferred solution identified are environmental sensors. This technology has
been relatively recently developed and can track temperature, humidity and
Co2 in the home. Linked to a gateway, to which we can also connect the
home’s fire/smoke alarms, we can track the fluctuations in the home’s
temperature and humidity and air quality if we include the Co2 feature (extra
cost, recommended for bedrooms, living rooms etc.).
4.3.3 The gateway links to a dashboard which will provide WDC staff with
information such as.  high levels of humidity, which can create conditions for
mould growth if not managed appropriately, for example if it peaks in the
evening (typically time for cooking, washing etc.) and does not return to a
normal level within a reasonable time frame then the home is not being
appropriately ventilated.
However, if the humidity levels are high at all times despite ventilation this
suggests that moisture may be coming from elsewhere e.g. a leak or rising or
penetrative damp. Air quality data (co2 sensors) can help understand if a
room is being ventilated because it will tell us about the freshness of air in a
room. Poor quality air can lead to headaches, fatigue and support the spread
of disease.
4.3.4 Appropriate officers would have access to the dashboard to help  provide
both informed support to tenants and facilitate decisions about next steps
e.g. installing more fans, investigating leaks and take the necessary action.
Further, a very attractive attribute of the sensors is the tenant app which
allows tenants to receive real time information about their home. This helps
Page 99

Page 100

tenant engage in managing their home and make the connections between
their activities and any related damp and mould risk and take action to
improve air quality.
4.3.5 With the council approved additional funding for the HRA capital programme,
it is proposed to install these sensors in a first tranche of approximately
2,000 homes. These homes will include void properties, multi storey flats,
sheltered homes and those identified as priority homes experiencing damp
and mould.
This programme will be delivered over five years (total budget
£10million)   with sensors installed in all  homes.
In order to deliver this project we will require this to be delivered in
partnership with appropriate contractors.  As outlined in the previous report to
Housing and Communities Committee – HRA Capital Programme, ,  approval
has been sought to proceed and undertake procurement activities. 
5 People Implications
5.1     Implementation of the proposals in relation to the technical solution will require                
appropriate resource allocation which is currently being reviewed and planned. 
6 Financial & Procurement Implications
6.1 The commitment to address dampness and mould was approved by Council
at it’s meeting on 1 March 2023.  The additional funding requirements have
been set out in the previous report to Housing and Communities Committee –
Capital Programme report together with the request to proceed with
procurement activities..
7 Risk Analysis
7.1 Failure to address dampness and mould may have a direct impact on the
delivery of the Council’s Strategic Plan and potentially impact on residents’
health and wellbeing
8 Equalities Impact Assessment
8.1 Screening and impact assessments will be carried out on specific activities as
required.
9 Consultation
9.1 The dampness policy and processes were developed through consultation with
officers from the strategic service areas.
10 Strategic Assessment
Page 100

Page 101

10.1     The dampness policy and processes set out support the successful delivery of
the strategic priorities and objectives of the Council.
Chief Officer: Angela Wilson, Peter Barry
Service Area: Supply Distribution & Property, Housing and Communities
Date:
Person to Contact: Martin Feeney – Building Services Manager, Supply
Distribution & Property: Telephone 07768657718, email
martin.feeney@west-dunbarton.gov.uk
Appendices: Damp Mould Process
Background Papers:
Wards Affected: All
Page 101

Page 102

Page 102

Page 103

West Dunbartonshire Council
Process for Dampness and Mould in Tenants
Homes
Why is this being revised?
This process has been revised after the coroner’s report on the tragic death of
a child who died of a respiratory condition caused by mould in his home. This
case has highlighted the clear link between mould and damp in houses and
serious health conditions.
West Dunbartonshire Council will treat dampness in tenants’ homes with
sensitivity, empathy and not put the onus on the tenant or any inference of
blame.
Ensuring tenant and resident safety is a critical part of the work of social
landlords in Scotland. To meet the tolerable standards the property must
• Be free from serious disrepair
• Be energy efficient
• Have modern facilities and services
• Be healthy, safe and secure
The approach set out below details the process and responsibility of each
service area when dealing with reports of mould and damp. We must deal with
this quickly and effectively and with sensitivity. The current cost of living crisis,
and in particular rising energy costs, mean that many tenants currently face
difficulties in heating their homes.
New Process:
• Teams to offer advice where appropriate.
• All visiting Officers to be vigilant and look for signs of dampness or
mould in every home we enter.
• Dampness Inspection requests prioritised to a maximum of 2 working days.
• Repairs resulting from an inspection will be re-categorised to Urgent (10
day) repairs where appropriate.
• Housing Officers to be made aware of the outcome of all
dampness inspections and will arrange a follow up visit within
2 working days.
Reporting a Repair for Damp/Mould
Citizen Services /CAS covering the repairs centre telephone lines and housing repairs
mailbox for on line reports, will determine the cause of the dampness by asking the tenant to
confirm if the area is wet or could be caused by water ingress by a leaking pipe or roof leak,
if yes appropriate repairs should be raised following up with an inspection request. If there
are no signs of water ingress this is likely to be condensation dampness as per guidance
documents. When receiving requests, we will be empathetic and sensitive to the concerns
Appendix 1
Page 103

Page 104

of tenants who may be anxious and worried for the health and wellbeing of family. If
appropriate we can offer basic advice to tenants by providing the guidance leaflet on “How to
Avoid Dampness & Condensation In the Home” or referring to the section within the repairs
pages on the Council website which also includes a short video.
https://www.west-dunbarton.gov.uk/housing/maintenance-repairs/damp-and-mould/
As well as offering advice, inspection requests should be appointed detailing
the issue, i.e. extent of the mould, location and how long it has taken to
develop. Appointments should be prioritised to the available slots in the
Building Service Officers’ calendar. To allow for prioritisation 2 additional
appointments slots have been added to each of the area based Building
Service Officers appointments per day. These additional slots are to be used
for dampness requests and should ensure we are able to offer an inspection
within 2 working days.
Reports via the Housing Repairs Mailbox – CAS teams should search key
words; Damp or Mould to ensure these are processed timeously.
All Council Officers
All Officers visiting tenants’ homes identifying mould of damp should report this
on behalf of the tenant if not already reported to Building Services. This can be
reported via the Council’s repairs centre on 0800 073 8708 or via
housing.repairs@west- dunbarton.gov.uk, ensuring subject heading details
dampness to allow teams to prioritise requests.
All Officers should also be aware of the Council’s advice by handing out the
damp and mould advice leaflet or referring to the details on the Council website
as above.
Building Service Officers
Building Service Officers whilst visiting tenants’ homes will listen to tenants
concerns, be empathetic towards these concerns, and take cognisance of
family circumstances, for example, health problems.
Taking account of current cost of living/energy crisis we offer advice on how to
effectively use heating in terms of energy efficiency, i.e. maintaining an
ambient temperature and adequate ventilation. Building Service Officers will
liaise with Housing Operations/Energy Advice Officer as required:
Building Service Officers should diagnose issues and make sure there are
options for ventilation:
• Are trickle vents operational?
• Windows opening adequately?
• Extractor fan operational?
• Does the extractor fan require to be serviced or cleaned?
• Is there adequate circulation of air? e.g. position of furniture against walls.
Repairs should be raised by the Building Service Officer where the extent of
the mould cannot be managed as detailed in the guidance leaflet.
Repairs orders should be raised as priority, in majority of cases appointed
Page 104

Page 105

within 10 days and MUST contain damp or mould in the description to allow for
reporting.
If unable to appoint these repairs, the Building Service Officer should liaise with
the Planning Team / Craft Supervisor.
If the repairs are caused by water ingress caused by a neighbouring property,
follow up inspections may be required to ascertain the cause, these should be
treated as a priority.
On completion of a visit the Building Service Officers will ensure a notification
email is sent to Housing Operations Dampness Mailbox within 2 days following
completion of all dampness related inspections and should contain the relevant
findings, proposed actions and any support requirements known of the
household.
dampness@west-dunbarton.gov.uk.
Housing Options
In cases of dampness/mould, the housing solution should not solely be based
upon a technical assessment of the property. It is critical a joined up approach
is taken and should take account of the individual health/support requirement
of the family household. Where it is clear the extent of the work required to
treat damp or mould requires the tenant to be decanted from their property, the
Building Service Officer should follow the decant process ensuring forms are
completed within 2 days where practicably possible by emailing Housing
Operations Dampness mailbox.
Housing Officers upon receipt of this information will prioritise the decant,
review the Housing Management system to confirm composition of the
household, any known support needs and arrange to contact the tenant within
24 hours. The purpose of the contact will be to confirm information obtained
from QL and gather any other relevant information to inform identification of a
suitable decant. A decant should take place within 10 working days once a
suitable property has been identified.
Specialist Survey Required
The Building Service Officer may be required on occasion to request a more in
depth survey from a specialist contractor to ascertain additional
recommendations. Officers should request an estimated completion from the
contractor and monitor for completion, updating Housing Operations
Dampness mailbox with the estimated contractor completion date.
Where there is evidence of mould or damp the Building Service Officer should
arrange the necessary repair order to treat while awaiting the outcome of the
report.
On receipt of the report the Building Service Officer should follow up with
required actions and save the report to the shared drive. An update of the
action being undertaken should be shared with the tenant confirming outcome
of the report and also updating Housing Operations by emailing Housing
Page 105

Page 106

Operations Dampness mailbox to ensure households are supported through
the process.
Housing Operations
On receipt of all dampness inspection notifications from Building Services via
the Housing Operations Dampness mailbox, the Housing Officer will be
responsible for carrying out a follow up visit to the tenant within 2 working days
to determine if there are any additional support needs. Support will be
dependent on the individual needs of the households, however could include:
• Support and referrals for financial assistance via, Working4U, Welfare
Fund, crisis loans, hardship fund, sustainability fund, top up meter or
vouchers (as appropriate).
• Review housing application and any medical application points
awarded (if applicable and underlying health issues), housing
options advice should include review of points, area and house type
preferences.
Energy Advice Officer
Referrals can be made to the Councils Energy Advice Officer who can discuss
energy efficiency of appliances and advise on ways to reduce air humidity,
offer practical solutions to clearing the mould and preventing its rapid regrowth
as well as making referrals to Working4U and CAB for financial advice/energy
vouchers.
Building Services - Follow Up Inspections
Once a dampness repair has been completed, the BSO will require to do a
follow up visit to the property to ensure problems have been fully resolved and
there are no further indications of dampness/mould.
Reports will be run of all completed repairs, Support Teams should make
contact with tenant to arrange the necessary follow up inspections 60 days
after the completed repair. Building Services Officers should record the
outcome in Ql within the inspection screen, noting if issues have been fully
resolved and no further action required. If further issues are identified during
the follow up visit the Building Services Officer will raise the relevant repair
within 2 days, ensuring notifications are is sent to the Housing Operations
Dampness mailbox within 24 hours which will trigger a further follow up visit by
Housing Officer within 2 working days to determine any family support
required.
Monitoring Dampness Inspections/Repairs
Building Services will report monthly to Building Services Board and HIB
on the following, providing the tenancy details on all to housing Operations
dampness mailbox.
Page 106

Page 107

The reporting will be developed further with the proposed implementation of
new technology which can track temperature, humidity and Co2 in homes and
allows us to track fluctuations which are linked to a gateway dashboard which
will provide WDC staff with relevant information.
• Total inspection requests received
• Total appointment requests completed
• Total Inspection requests cancelled no access
• Total active inspections
• Total active dampness repairs
• Total completed dampness repairs
• Total Repairs cancelled no access
Page 107

Page 108

Page 108

Page 109

Start
H.O Review paperwork
contact tenant within a
24hrs, identifying
suitable property decant
to take place within 10
working days
Incoming telephone/
email dampness query
request  to Citizen
Services/CAS
Citizen Services/CAS
refer to Dampness
Guidance Document and
advise appropriately
YesIs inspection Required? BSO to attend within 2
working days
Housing Officer Follow-
up visit  within 2 working
days
Repair Order
Repair order raised and
appointed prioritised as
urgent 10 working days
Repair
Result from inspection
Decant
Survey
Decant
If decant is required
Decant process/
paperwork to be
completed
Recommendations  from
specialist survey relayed
to  BSO
Repair Order completed
operative feedback to
BSO
Specialist Survey
If required request sent
to specialist  contractor,
monitor for completion
Process for Dampness and Mould in Tenants Homes
H.O will review Housing
applications and any
outstanding referrals
made  to O.T including
support for financial
assistance
Is additional support
Required?
BSO follow up inspection
after 3 months to
monitor dampness.
Referral to Energy Advice
Officer
Energy
Energy efficiency and
advice, will contact
Tenant
Notification of actions
from inspection sent to
housing officers via
dampness mailbox
(dampness@wes-
dunbarton.gov.uk)
Appendix 2
Page 109

Page 110

Page 110

Page 111

WEST DUNBARTONSHIRE COUNCIL
Report by Chief Officer – Housing and Employability
Housing and Communities Committee: 3 May 2023
__________________________________________________________________
Subject: More Homes West Dunbartonshire – West Dunbartonshire Council
Affordable Housing Supply Delivery Programme 
1. Purpose
1.1 This purpose of this report is to provide the Housing and Communities
Committee an update on progress with West Dunbartonshire’s More Homes
Programme which oversees the delivery of the Council’s new home building
programme.
2. Recommendations
2.1 It is recommended that the Housing and Communities Committee:
(i) Note the content of the report and the progress made to date in the
delivery of the Council’s More Homes West Dunbartonshire approach;
(ii) Approve the undertaking to conduct all necessary procurement exercises
for the new identified sites within the Future New Build – West
Dunbartonshire Affordable Housing Supply Programme identified in
section 4.4 of this report to deliver new council homes;
(iii) Approve the acquisition of the former Clydebank Health Centre site at the
cost of £584,500 from NHS Greater Glasgow and Clyde for the delivery of
new Council homes;
(iv) Note the addition of Gilmour Avenue, Hardgate to the More Homes West
Dunbartonshire development programme;
(v) Note the scaling up of the Council’s buyback programme and the actions
required to meet this ambition;
(vi) Note the reduction in housing units within the Pappert development from
27 to 26 and note that this will maintain 112 bedspaces within the
development; and
(vii) Note the success of the Council’s Queens Quay housing development
which has been shortlisted for the Homes for Scotland Awards,
Development of the Year (Large)
ITEM 12
Page 111

Page 112

3. Background
3.1 In West Dunbartonshire the Affordable Housing Supply Programme (AHSP) is
delivered through a More Homes West Dunbartonshire strategic approach
which has successfully delivered over 1000 new affordable homes in West
Dunbartonshire to date and includes the Council’s own ambitious New House
Building Programme.
3.2 The Council’s latest practical completion took place at the Queens Quay
development in September 2022 delivering 29 new Council homes in a key
regeneration area as part of a wider development which has delivered 146
new social rented homes.  These are first residential properties to be heated
from the Council’s Queens Quay District Heating Network. This development
has also been shortlisted in the prestigious Homes for Scotland Awards 2023
in the Large Development of the Year category, the award will be presented to
the chosen development on 26th May at a ceremony in Edinburgh. 
3.3 These 29 new homes, are in addition to the completion of the Council’s first
fully dementia designed development at Creveul Court, Alexandria and other
exemplar developments in Haldane, Aitkenbar, Bellmsyre, Dumbarton
Harbour and St Andrews, Clydebank.  The Council have now completed 12
new build developments since 2013 and are the largest developer of social
homes in West Dunbartonshire delivering 496 new homes to date as outlined
in Table 1 below:
Table 1:  Completed Council New Build
Project No. of
Units
Completion
Date
Granville Street (Phase 1), Clydebank 24 July 2013
Miller Road, Alexandria 15 October 2013
Granville Street (Phase 2), Clydebank 9 February 2014
Central Bellsmyre, Dumbarton 36 December 2014
Hillstreet Square, Dumbarton 37 August 2015
Second Avenue, Clydebank 40 April 2018
Creveul Court, Alexandria 22 April 2021
Aitkenbar Primary School 55 July2021
Haldane Primary School 58 August 2021
St Andrews, Clydebank 126 October 2021
Dumbarton Harbour, Dumbarton 45 December 2021
Queens Quay, Site B, Clydebank 29 August 2022
Totals 496
3.4 The Strategic Housing Investment Plan (SHIP) 2023-2027, outlining West
Dunbartonshire’s Affordable Housing Supply Programme through the More
Homes West Dunbartonshire approach was approved by the Housing and
Communities Committee in November 2022. The SHIP outline plans to meet
the Council Administration’s aim of delivering 2500 new affordable and social
rented homes over the next 10 years.  The Council has recently received
positive feedback from the Scottish Government in respect of our recent
SHIP.
Page 112

Page 113

4. Main Issues
More Homes West Dunbartonshire - Delivery Programme
4.1 Building new affordable homes has an important role to play in revitalising
local economies and assisting with post-pandemic recovery plans, negating
the impacts of the current cost of living crisis and combatting poverty.  It is
also clear that the need for affordable homes has and will increase in the
current ongoing economic environment. Our More Homes West
Dunbartonshire approach is an ambitious plan that aims to continue the
positive momentum of the delivery of much needed Council homes in West
Dunbartonshire and will significantly assist the Council’s aim to deliver 2500
new social and affordable homes by 2032.
4.2 As the biggest affordable housing developer in West Dunbartonshire, the
Council has identified a number of future development sites for new council
homes to address existing and new housing need. The design of these homes
will further develop, improve and exceed current best practice, providing
sustainable homes using innovative technology and delivering on our low
carbon ambitions including passivhaus and other net zero carbon
opportunities.
4.3 The Strategic Housing Investment Plan and HRA Capital Plan outlined the
plans the Council have for meeting their new build ambitions.  Some of the
initial plans were and continue to be impacted as a result of global issues
revised new build targets for the Council are outlined below:
Table 2: Council New Build Programme
Site/Developer Number of
Units
Number of
Specialist
Provision
Est Site
Start
Est Completion
Date
Clydebank
East,
Clydebank
88 9
On Site
January
2023
Spring 2025
Pappert,
Bonhill
Alexandria
26 3
Autumn
2023
Winter 2024/25
Willox Park 17 17 Winter
2023/24
Winter 2024/25
Bonhill Gap
Sites* 34 4 Winter
2023/24
Winter 2024/25
Bank Street,
Alexandria
20 20 Winter
2023/24
Winter 2024/25
Mount
Pleasant
19 19 Winter 
2023/24
Spring 2025
Queens Quay
Site C
100 10 Winter
2023/24
Spring 2025
Page 113

Page 114

*Current Planning figures
4.4 Updates for each site are noted below:
Clydebank East: 
Works commenced on this development on 23 January 2023, as reported to
the Housing and Communities Committee in February 2023 the initial
programme is for the remedial works and external drainage, a construction
site start is programmed for May/June 2023.  The total programme for the
works will be 116 weeks.
This development will deliver 88 new homes and has been designed to meet
the housing need within the wider West Dunbartonshire area, the table below
shows the housing mix:
House Type Sustainability Standard Number of New
Homes
Wheelchair Bungalow
3bed/4person
Net Zero 3
House 3bed/5person Net Zero 15
House 4 bed/7person Net Zero 12
House 4 bed/9 person Net Zero 8
Cottage Flat 1 bed/2 person Net Zero 4
Cottage Flat 2 bed/3 person Net Zero 4
Flat 1 bed/2person Net Zero 16
Flat 2 bed/4 person Net Zero 24
Wheelchair Flat 1 bed/2person Net Zero 2
All houses are designed to the Housing for Various Needs Standard (HfVN).
There will be 9 fully Wheelchair (WCH) accessible properties.  The 4 and 5
bedroom homes will all have ground floor double bedrooms.  
The development at Clydebank East will see the completion of a major
housing led regeneration of a key priority area identified in the Local Housing
Strategy and will be the Council’s first fully zero carbon housing development
and marks a significant milestone in our transition to net zero approved at the
August 2022 meeting of the Housing and Communities Committee.  We will
ensure the construction site planned for May/June this year is communicated
to all stakeholders.
Clydebank
Health Centre*
38 5 Winter
2023/24
Spring 2025
Dennystoun
Forge
20 20 Spring 
2024 
Winter 2024
Clydebank
Gap Sites*
(Gilmour
Avenue)
50 10 Spring
2024
Summer 2025
Buyback
Scheme (60
per year)
308 36 2023/24 2027/28
720 units 153 units
Page 114

Page 115

Pappert, Bonhill
We have reviewed the design proposals for the Pappert development and
following an assessment of housing demand information we have maximised
the number of the 3 bedroom homes with a ground floor bedroom.  While this
has the net effect of reducing the number of units in the wider development
from 27 to 26, it does not impact on the number of bedspaces within the
development.
House Type Sustainability Standard Number of New
Homes
House 3bed/5 person Passivhaus 6
House 3bed/5 person Net Zero 6
House 4bed/6person Net Zero 4
House 4bed/7person Net Zero 1
Flat 2bed/3person w/c Net Zero 3
Flat 1 bed/2person Net Zero 6
It is anticipated that a planning approval will be granted in August 2023, and a
site start in late 2023/early 2024.
Willox Park, Doveholm, Dumbarton
The development of the new homes to be delivered at the former care home
site continues within the design phase towards a full planning application. A
landscape architect has been procured for the design team, however the
appointment of engineering consultants (structural, civil, mechanical and
electrical) has been delayed as we were unable to appoint following a recent
tendering exercise.  Our development timescales have been updated as a
result of this setback.
Bonhill Gap Site Strategy
The pre-planning application process has commenced on the development of
the 3 separate gap sites which are contained within this wider development. 
We are in the process of procuring engineering consultants as we move
closer to a full planning application.
We have altered some of the initial design plans to incorporate a number of
adaptable 6/7 bed homes within the development to meet identified housing
need.
Bank Street, Alexandria
The council is currently developing a proposal for 21 sheltered/amenity
housing units in partnership with the HSCP. This will include an options
appraisal in terms of the existing provision within the local area.
Page 115

Page 116

A landscape architect has been procured for the design team and engineering
consultants (structural, civil, mechanical and electrical) will be procured
shortly.
Mount Pleasant, Old Kilpatrick
The demolition of the former care home at the site completed in December
2022 ahead of schedule.
We have had an initial consultation with the Old Kilpatrick Community Council
where we presented our concept of providing housing in a similar style to
Creveul Court, Alexandria. 
An Employers Agent (NBM) have been appointed for this project, they were
previously the EA for the recently completed Queens Quay development.  The
construction procurement strategy is well advanced and will be implemented
following the completion of ongoing site investigations and feasibility studies
for the development. 
Queens Quay, Site C, Clydebank
The Council has been developing a design to deliver a projected 20 units on
this site to complement the housing mix within sites A and B.  This
development will also be designed to meet low/zero carbon principles and
linked to the Queens Quay district heating network
.
Pre-planning response was received on the 25 February highlighting concern
of the WDC development proceeding in isolation. We have adopted a,
proactive response to this issue and have developed masterplan diagrams
incorporating the surrounding sites and have carried out valuations on the
adjacent site to Queens Quay C with a view to purchasing additional land to
deliver more affordable housing in the Queens Quay regeneration site.  If this
is achieved we would seek to develop a mixed tenure approach to any
expanded development site. We anticipate discussions with CRL (Clydeside
Regeneration Limited) in May to progress the possibility of acquiring this
additional land.
Clydebank Health Centre
The Council are continuously looking for opportunities to provide additional
new build council homes and this includes through the Scottish Government’s
trawl process which seeks to utilise public sector land sales for the delivery of
key national ambitions which includes the delivery of new homes. The former
Clydebank Health Centre in Kilbowie Road, Clydebank was identified through
this process and approval was granted to acquire the site from NHS Greater
Glasgow and Clyde at the November meeting of the Housing and
Communities Committee for £707,400.
However, as reported to the February meeting of the Housing and
Communities Committee NHS Greater Glasgow and Clyde chose not to
Page 116

Page 117

complete the transaction in financial year 2022/23, instead choosing to
conclude the sale of the land in financial year 2023/24.  As a result the
Council and NHS Greater Glasgow and Clyde reinstructed the District Valuer
to revalue the site to allow the acquisition to conclude in 2023/24.
A plan of the area is included as Appendix 1 to this report and has a gross site
area which extends to 0.98 ha (2.43 acres).  A valuation carried out by the
District Valuer in March 2023 placed a valuation of £1.5m for the site.
Tripartite discussions involving the Scottish Government, NHS Greater
Glasgow and Clyde have revised the previous agreement on a financial
assessment on the levels of abnormal costs within the site resulting in an offer
of £584,500 subject to Housing and Communities Committee approval.
If approval is granted the transfer will be carried out using the process set out
in the Scottish Public Finance Manual - Guidelines for the Transfer of Property
within the Scottish Public Sector.
Dennystoun Forge Gypsy/Traveller Site
A submission was made to the Scottish Government for support funding from
their Gypsy/Traveller Accommodation Fund for significant improvements to
the Dennystoun Forge site, including new energy efficient chalet type
accommodation following a consultation exercise with site residents. 
However, we were notified that this submission was unsuccessful at this point.
We have since engaged the Scottish Government following the outcome of
this and have provided additional information to the Scottish Government in
support of the application.  
In another positive development the Council’s Housing Development Officer
has been providing support to the tenants within the Dennystoun Forge site to
establish a registered tenants association, the absence of a recognised
tenants group and ongoing site presence was seen as a relative weakness in
terms of the initial submission.  
We anticipate that following the new information provided to support our
application for funding Scottish Government officials will reassess the
application in advanced of the parliamentary recess 
Queen Mary Avenue, Clydebank (Clydebank Gap Sites)
The transfer of the site at Queen Mary Avenue, Clydebank with vacant
possession at the cost of £140,000 from the Council’s General Fund to the
Housing Revenue Account for the delivery of new Council homes was
approved at the February meeting of the Housing and Communities
Committee and has now been concluded.  We are preparing a demolition
programme to allow the site to be cleared as soon as is practically possible. 
Page 117

Page 118

Gilmour Avenue, Hardgate (Clydebank Gap Sites)
As part of the wider development of our Clydebank Gap Site strategy we have
identified a HRA gap site in the Hardgate area at Gilmour Avenue.  The site
was previously the location of timber garages on concrete bases.  These have
long since been demolished and the site has been beset with fly tipping
issues for a number of years.  We are currently undertaking site
investigations, and are proposing to construct 2 semi-detached three bedroom
homes at this location.  As a result of some of the complexities and the scale
of the site we are looking at the potential for a modular construction process. 
This would be the first of this type of construction within our wider More
Homes West Dunbartonshire approach.
Buyback Programme
The Council’s buyback programme which incorporates the Mortgage to Rent
Scheme purchased 16 new homes to date in 2022/23.  A further 4 completed
in early April 2023.
In 2023/24 and following approval of the Strategic Housing Investment Plan
by the Housing and Communities Committee in November 2022 and
subsequently the decision by West Dunbartonshire Council in March 2023 to
deliver an enhanced Housing Capital Investment Programme including
additional funding for buyback purchases we are now scaling up ambition
around our buyback programme.  In 2023/24 and in each of the subsequent
years up to and including 2027/28 we plan to deliver 60 new homes each year
meaning a minimum of 300 new Council homes to meet identified need.  
The additional funding that was approved by the West Dunbartonshire Council
meeting of 1 March 2023 will target larger family homes to meet this specific
need.  To meet these defined targets we will add additional resource within
the Housing team, and we will also refresh our Buyback Policy.  This update
policy will be submitted to the meeting of the Housing and Communities
Committee in November 2023 
4.5 The Housing Development Team are continuously looking for opportunities to
provide additional new build council homes and will bring any potential site to
the Housing and Communities Committee with as much information as
possible as part of the regular More Homes update paper.
5. People Implications
5.1 An additional Senior Housing Development Officer role is required to deliver
the increase and scaling up of the Council’s buyback programme.  This will be
met within the existing resources outlined in Section 6 of this report.  We will
also review surveying resource within the team.
Page 118

Page 119

6. Financial and Procurement Implications
Financial
6.1 On 1 March 2023 Council approved the Housing Capital Programme 2023-
2028 which saw significant resources committed to the delivery of new council
homes in West Dunbartonshire.  An expenditure budget of £155m for the
affordable housing supply programme is factored into the HRA Capital
Programme this will be updated to reflect the income and expenditure
highlighted within this report.  As it currently stands, it is anticipated that this
programme will complete on project life budget.
6.2 The acquisition of the Clydebank Health Centre site will be delivered within
the approved expenditure budget outlined in paragraph 6.1 of this report.  The
addition of the Gilmour Avenue is also incorporated within this expenditure
budget.  
6.3 The anticipated uprated Affordable Housing Supply Programme grant
benchmark assumptions will not be in place from 1 April 2023, and we await
clarification from the Scottish Government as to when these will be published
and implemented.  Notwithstanding the expected increase in benchmark
assumptions Housing and Finance Officers will continue to assess the
ongoing affordability of future developments within the context of the Housing
Revenue Account Business Plan.
Procurement
6.3 All new development sites will be subject to new detailed procurement
strategies and the opportunities highlighted with 4.4 of this report will continue
to be prioritised.
6.4 Where the contract award is less than £213,000, authority is delegated to
the Chief Officer in consultation with the Procurement Manager to instruct the
award of contracts for the planned revenue and capital spend detailed in this
report to suppliers providing the most economically advantageous offer to the
Council.
6.5 All procurement activity carried out by the Council in excess of £2m is
subject to a contract strategy. The contract strategy for new housing
development within the HRA Capital Programme will be developed by the
Corporate Procurement Unit in consultation with Housing Development
Officers. The contract strategy will include, but is not limited to; contract
scope, service forward plan, the market, procurement model and routes –
including existing delivery vehicles, roles and responsibilities, risks, issues
and opportunities and on-going contract management. Opportunities to
maximise the positive social, economic and environmental impact for the
Page 119

Page 120

Council through the relevant procurement processes will be developed in line
with procurement policy.
7. Risk Analysis
7.1 All Council new build projects have their own Risk Register which highlights
the risk within and out-with the project team’s control.  These are maintained
and adjusted on an on-going basis.
7.2 With any new build project there is a risk that as the projects develop the cost
increases beyond the estimated contract cost.  Any additional borrowing
requirements, or conversely, cost savings will be reported to future meetings
of the Housing and Communities Committee. However, this is mitigated
through a target cost model approach in our current contract arrangements
within the Scottish Procurement Alliance (SPA) framework and Scotland
Excel.
8. Equalities Impact Assessment (EIA)
8.1 The proposal does not alter any existing policy or pattern of service delivery
and so is not considered to require an equalities impact assessment.
9. Consultation
9.1 As part of our previous rent consultation exercise, 92% of respondents
indicated their support for the Council’s ambitious plans to deliver the Housing
Revenue Account (HRA) new council house build programme. In addition,
there was positive support for the wider delivery of new build housing as part
of the recent Local Housing Strategy.  Regular updates on new build
development are provided to the West Dunbartonshire Tenants and Residents
Organisation at the bi-monthly liaison meetings.
10. Strategic Assessment
10.1 The Local Housing Strategy is the overarching document setting out the
strategic direction for housing across all tenures and informs the future
investment in housing and related services across West Dunbartonshire.
10.2 Having considered all the Council’s strategic priorities, this report and the
provision of new supply social housing for rent contributes greatly to all
strategic priorities. 
Peter Barry
Chief Officer, Housing and Employability
Date: 18 April 2023
Page 120

Page 121

Person to Contact: John Kerr – Housing Development and Homelessness
Manager, Housing Development and Homelessness
Team, Housing and Employability, telephone:
07793717981, email: john.kerr@west-dunbarton.gov.uk
Appendices: 1. Clydebank Health Centre site plan
Background Papers: West Dunbartonshire Council’s Local Housing Strategy
Local Housing Strategy, Health Inequalities Impact
Assessment
DVS Valuation Report Development Site:
Clydebank Health Centre
Wards Affected: All
Page 121

Page 122

Page 122

Page 123

CLYDEBANK HEALTH CENTRE,KILBOWIE ROAD,CLYDEBANK,DUNBARTONSHIRE,G81 2TQ
Ordnance Survey © Crown Copyright 2020. All Rights Reserved.
Licence number 100022432
Plotted Scale - 1:1250. Paper Size - A4
FIRST SCOTTISH GROUP
St Davids Drive, Dalgety Bay, KY11 9NB
Tel: 01383 826777
PLAN 1
Appendix 1
Page 123

Page 124

Page 124

Page 125

WEST DUNBARTONSHIRE COUNCIL
Report by Chief Officer – Housing and Employability
Housing and Communities Committee: 3 May 2023 
Subject:  Willox Park Sheltered Housing Complex
1 Purpose
1.1 This purpose of this report is to provide the Housing and Communities
Committee an update on the action we are taking to understand the damp and
mould problems experienced by the tenants at Willox Park, Dumbarton and
also the delivery of a wider masterplan approach to the future provision of
sheltered housing within the location. 
2 Recommendations
2.1 It is recommended that the Housing and Communities Committee:
(i) Note the content of the report and the progress made to date in carrying
out initial surveys and approve spend for future surveys and required
works at Willox Park sheltered housing complex; and
(ii) Note that a report will be provided to the November meeting of the
Housing and Communities Committee following consultation with the
tenants on future housing provision within the location.
3 Background
3.1 Willox Park comprises 36 terraced bungalows offering sheltered housing in
Dumbarton. It was built in the 1960s and is typical of the building and space
standards of that time. Whilst the tenants like having their own front doors and
a little outside space the internal layout is not conducive to easy living for
those with limited mobility. 
3.2 The existing homes have received replacement roof and external wall
insulation over the last twenty years alongside investment in kitchens,
bathrooms and windows. 
3.3 However, tenants have complained of dampness and draughts. Following
initial inspections, it was agreed that specialist advice was needed and we
instructed several in-depth specialist surveys at an empty property which
meant we did not need to disrupt or decant any tenants to carry out these
intrusive and detailed surveys.
ITEM 13
Page 125

Page 126

3.4 A number of actions were approved by the February meeting of the Housing
and Communities Committee around steps being taken to investigate the
issues highlighted and an update in progress is provided in Section 4 of this
report. 
4 Main Issues
4.1 Invasive damp surveys
Three tenants within Willox Park have now volunteered to participate in the
more invasive specialist damp surveys.  We have now agreed terms and
conditions with the contractor and these are due to commence in May. The
outcome of these surveys will be known in early June and any required
actions will be undertaken on receipt of the survey report by the appropriate
officers within the Housing Service. 
4.2 Non-invasive damp surveys
In advance of the invasive surveys, the Council had hoped to have carried out
a non-invasive damp survey to all the remaining properties within Willox Park,
these were intended to provide a degree of assurance for all tenants.  While,
we have identified a specialist surveyor contractor to carry out these surveys. 
The formal appointment had been delayed due to terms and conditions being
agreed.  However, these have now been agreed and these intended surveys
will be completed within similar timescales to the more invasive surveys being
carried out as highlighted in 4.1 above.  
4.3 New build update
The development of the new homes to be delivered at the former care home
site continues within the design phase towards a full planning application. A
landscape architect has been procured for the design team, however the
appointment of engineering consultants (structural, civil, mechanical and
electrical) has been delayed as we were unable to appoint following a recent
tendering exercise.  Our development timescales have been updated as a
result of this setback and the development is scheduled to complete in Winter
2024/25.
4.4 Enhanced fire safety
It was highlighted to the February meeting of the Housing and Communities
Committee in February 2023 that following our regular Fire Risk Assessment
of the properties that actions were proposed to improve the
compartmentalisation between the properties, amongst other changes such
as locations of the bin.
4.5 Our appointed consultants have now prepared an option to improve
compartmentalisation but due to complexities and liabilities of providing fire
safety advice we are clarifying with their legal and insurance teams the
required caveats before this will be enacted.  In the meantime, the Housing
Page 126

Page 127

Operation team is identifying more suitable waste solutions for the homes and
these will be agreed with tenants.
4.6 The works identified within this report will support and inform our existing
Housing Asset Management information and this will be used to develop a
future Willox Plan masterplan which will identify future housing investment in
the Willox park sheltered housing complex.  It is intended that following a full
consultative period with the existing tenants a report will be provided to the
Housing and Communities Committee in November 2023. 
5 People Implications
5.1 There are no new people implications for this report.  It should be referenced
however that because of the demographic of the tenant population staff
resource from the Housing Development and Housing Operations Teams will
be required to be prioritised to support this and this may impact on other
functions and priority workstreams.  
6 Financial & Procurement Implications
6.1 The surveys and additional consultancy advice required to build a detailed
picture of the homes have been budgeted for and likewise repairs and
maintenance works will come from the appropriate budgets. However, once
the survey findings and recommendations, including likely some indicative
costings, are received we will carry out an asset management options
analysis to ensure we are achieving value for money for these properties. 
6.2 The suspension of lettings approved in February 2023 will result in lost rental
income and this has been factored into void rent loss assumptions made
within the Housing Revenue Account budget covering 2023/24.  Should any
properties become vacant this may provide a number of benefits namely it will
allow the Council the potential to carry out further surveys or decant existing
tenants into another property in the complex while any required work is
completed to their home. 
Procurement
6.3 We have procured our consultants to date through the appropriate competitive
bids process and will continue to do so to ensure that we get the correct
balance between quality and price to ensure value for money for the Council. 
6.4 Where the contract award is less than £213,000, authority is delegated to
the Chief Officer in consultation with the Procurement Manager to instruct the
award of contracts for the planned revenue and capital spend detailed in this
report to suppliers providing the most economically advantageous offer to the
Council.
6.5 All procurement activity carried out by the Council in excess of £2m is
subject to a contract strategy. The contract strategy for new housing
development within the HRA Capital Programme will be developed by the
Page 127

Page 128

Corporate Procurement Unit in consultation with Housing Development
Officers. The contract strategy will include, but is not limited to; contract
scope, service forward plan, the market, procurement model and routes –
including existing delivery vehicles, roles and responsibilities, risks, issues
and opportunities and on-going contract management. Opportunities to
maximise the positive social, economic and environmental impact for the
Council through the relevant procurement processes will be developed in line
with procurement policy.
7 Risk Analysis
7.1 We maintain risk registers for each project which highlights the risk within and
out-with the project team’s control. These are maintained and adjusted on an
on-going basis.
8 Equalities Impact Assessment
8.1 The proposal does not alter any existing policy or pattern of service delivery
and so is not considered to require an equalities impact assessment.
9 Consultation
9.1 We have worked to keep tenants up-to-date with the survey findings and next
steps utilising newsletters, letters and the housing officer. The Tenants and
Residents Association at Willox Park is actively involved in tracking the
processes and have been heavily involved in the consultation for the new
build element of the complex.
10 Strategic Assessment
10.1  The Local Housing Strategy is the overarching document setting out the
strategic direction for housing across all tenures and informs the future
investment in housing and related services across West Dunbartonshire.
Having considered all the Council’s strategic priorities, this report and the
provision of new supply social housing for rent contributes greatly to all
strategic priorities.
Peter Barry
Chief Officer, Housing and Employability
Date: 18 April 2023
_____________________________________________________________
Person to Contact: John Kerr – Housing Development and Homelessness
Manager, Housing Development and Homelessness
Team, telephone: 07793717981, email: john.kerr@west-
dunbarton.gov.uk
Page 128

Page 129

Appendices: None
Background Papers: None
Wards Affected: Ward 3
Page 129

Page 130

Page 130

Page 131

WEST DUNBARTONSHIRE COUNCIL
Report by Chief Officer –Housing and Employability
Housing and Communities Committee: 3 May 2023 
___________________________________________________________________
Subject: Enhanced Standards for Multi Storey Living – A strategy for
enhancing the experience of living in a multi storey home in West
Dunbartonshire 2023/28
1. Purpose
1.1 The purpose of this report is to provide the Housing and Communities
Committee with an update on the recent resident consultation which gathered
ideas on how to enhance our 19 multi storey homes and seek approval to
implement a strategy to enhance living standards in these homes by
delivering a number of improvement actions.
2. Recommendations
2.1 It is recommended that the Housing and Communities Committee:
(i) note the contents of this report and the feedback received from current and
future tenants regarding their experiences of living in our multi storey flat
homes across the local authority area: and
(ii) approve the strategic approach  outlined with the Strategy
document and improvement action plan developed to address the
findings of the consultative exercise; and
(iii) instruct the Chief Officer Housing and Employability to fully
implement the strategy and associated action plan;
3. Background
3.1 West Dunbartonshire Council have 19 multi storey blocks of flats containing
1,232 homes. The blocks contain one, two and three bedroom flats. The
blocks were built in the 1960s using concrete panels and were insulated and
received new double glazing between 2010 and 2015 to make the homes
more energy efficient.  Apart from the three blocks at Littleholm, which are
connected to the gas network, the remaining blocks use electric storage
heaters as their main form of heating.
3.2 All blocks with the exception of one block are mixed tenure, while the Council
is the majority owner in each of the blocks, the presence of owner occupiers
and private landlords’ means any major works have got to be agreed by all
parties.
3.3 The homes are now around 60 years old and we have committed to review
investment to ensure that we are putting in place the appropriate resource to
enable them to continue to be attractive homes which contribute positively to
our communities.
ITEM 14
Page 131

Page 132

3.4 Indeed, the recent resident survey showed that residents liked the views and
the generous sizes and storage space offered by the flats, however the survey
also offered up numerous areas for improvement which this survey will look
to take forward.  In the appendixes of this paper there is a report detailing the
survey findings in detail. 
4. Main Issues
4.1 Consultation
We surveyed residents using survey monkey for 12 weeks between October
and December 2022.  We received a good response from all blocks and the
residents have provided us with a clear steer in terms of what they would like
to see improved in their home and block.
4.2 A challenge which emerged from the consultation findings is that many of the
improvements people would like do not represent an enhanced living standard
but are planned investment through the Housing Capital Investment
Programme.  For example, similarly to the recent rent consultation exercises
kitchens and bathroom renewals and heating upgrades figured high in terms
of priorities within the responses.
4.3 We also surveyed those on the Council housing waiting list and 40% of those
who responded indicated that they would like to live in a multi storey flat and
provided improvement suggestions, many of which aligned with what tenants
would like to see such as improved estate management of the blocks.
4.4 Identifying priorities and creating an action plan
Taking the survey findings we identified key themes across the blocks which
will form the overarching structure of the wider strategic approach and action
plan. These tackle the common requests from our residents such as
improving heating and hot water and deep cleaning and reimagining the
common areas.
4.5 The wider approach will continue to be developed with tenants and residents
to ensure that they reflect the needs of each block.  As we have also reviewed
findings on a block by block basis to ensure that we are identifying block
specific requests and these can be captured within the wider strategic
approach to enhance the living standards in all our multi story flats across
West Dunbartonshire.
4.6 An improvement action plan has been developed to deliver the enhanced
standards and this is attached as Appendix 1a of this report.
5. People Implications
5.1 A Senior Housing Development Officer will be tasked with effective project
management to deliver the strategic aims contained within the strategy
document and associated action plan. In addition, developing appropriate
Page 132

Page 133

service responses in areas where improvements actions have been identified
will be managed from within existing resources within the Housing Revenue
Account.
6. Financial and Procurement Implications
6.1 Financial
On 1 March 2023 Council approved the Housing Capital Programme 2023-
2028 which committed resources of £4.25m to deliver an enhanced standard
for multi storey living within the HRA Capital Programme. Housing and
Finance Officers will continue to assess the ongoing affordability of future
developments within the context of the Housing Revenue Account Business
Plan.
Procurement
6.2  Where any contract award is less than £213,000 to deliver this strategy,
authority is delegated to the Chief Officer, Housing and Employability in
consultation with the Procurement Manager to instruct the award of contracts
for the planned revenue and capital spend detailed in this report to suppliers
providing the most economically advantageous offer to the Council.
6.5 All procurement activity carried out by the Council in excess of £2m is
subject to a contract strategy. The contract strategy for new housing
development within the HRA Capital Programme will be developed by the
Corporate Procurement Unit in consultation with Housing Development
Officers. The contract strategy will include, but is not limited to; contract
scope, service forward plan, the market, procurement model and routes –
including existing delivery vehicles, roles and responsibilities, risks, issues
and opportunities and on-going contract management. Opportunities to
maximise the positive social, economic and environmental impact for the
Council through the relevant procurement processes will be developed in line
with procurement policy.
7. Risk Analysis
7.1 There is a risk that failure to invest strategically in our multi storey flats will have
a negative impact on their ongoing viability and in turn would lead to a loss of
rental income and could potentially impact on the ongoing sustainability of the
HRA Business Plan.  In addition an ineffective approach to strategic asset
management of our housing stock would attract an adverse reaction from the
Scottish Housing Regulator.
7.2 We maintain risk registers for each project which highlights the risk within and
out-with the project team’s control. These are maintained and adjusted on an
on-going basis.
8. Equalities Impact Assessment (EIA)
Page 133

Page 134

8.1  An EIA screening has been undertaken by officers and no issues were
identified.
9 . Consultation
9.1      As above, we carried out a 12 week consultative exercise and received a
good response from residents and those on the waiting list.  We will
continue to develop the plans in conjunction with tenants and residents as
we further develop a wider investment programme and a monitoring
framework.
10. Strategic Assessment
10.1 The proposals contained in this report directly address all of the Council’s
strategic priorities. The investment in, and provision of attractive affordable
housing will also indirectly support the objective of economic growth and
employability through supporting employment and improving place
attractiveness.
Peter Barry
Chief Officer, Housing and Employability
Date:  18 April 2023
__________________________________________________________________
Person to Contact: John Kerr – Housing Development and Homelessness
Manager, Housing Development and Homelessness,
Housing and Employability, telephone: 07793717981,
email: John.Kerr@west-dunbarton.gov.uk
Appendices: Appendix 1/1a: Enhanced Living Standards Strategy and
Improvement Action Plan 
Background Papers: EIA. March 2023 
Survey findings report, Housing Development 2022
Wards Affected: All
Page 134

Page 135

ENHANCED MULTI
STOREY LIVING
A STRATEGY FOR ENHACING THE
EXPERIENCE OF LIVING IN A MULTI
STOREY FLAT IN WEST DUNBARTONSHIRE
2023/28
ABSTRACT
Our multi storey blocks are now over 50
years old and we want to prepare these
homes for the future to ensure they offer an
attractive place to live where communities
can flourish. 
Housing Development
Spring 2023
Appendix 1
Page 135

Page 136

Contents
Executive Summary ......................................................................................................................... 2
About our multi storey blocks of flats ............................................................................................... 1
Background to the strategy .............................................................................................................. 1
Consultation ..................................................................................................................................... 2
Fire safety......................................................................................................................................... 3
Day to day fire safety .................................................................................................................... 3
Fire Risk Assessments: ................................................................................................................ 3
Asset investment .............................................................................................................................. 4
Surveys ......................................................................................................................................... 4
Energy efficiency improvements .................................................................................................. 4
Lifts ............................................................................................................................................... 5
Breakdown policy ...................................................................................................................... 5
Long term strategy .................................................................................................................... 6
Kitchens and bathrooms ............................................................................................................... 6
Noise insulation pilot ..................................................................................................................... 6
WIFI .............................................................................................................................................. 6
Outcome: ...................................................................................................................................... 6
Common spaces (lobbies, landings and cleaning) .......................................................................... 7
Refurbish common spaces ........................................................................................................... 7
Deep cleaning of closes, landings and foyers .............................................................................. 7
Enhanced CCTV and emergency lighting .................................................................................... 7
Outcome: ...................................................................................................................................... 7
Surrounding green space and amenities ......................................................................................... 8
Waste Strategy ................................................................................................................................. 8
Management .................................................................................................................................... 9
Page 136

Page 137

Executive Summary
Consultation
We surveyed residents using survey
monkey for 12 weeks between
October and December 2022.  We
received a good response from all
blocks and the residents have
provided us with a clear steer in terms
of what they would like to see
improved in their home and block. 
A challenge which emerged from the
consultation findings is that many of
the improvements people would like do
not represent an enhanced living
standard but are planned investment
through the Housing Capital
Investment Programme.  For example,
similarly to the recent rent consultation
exercises kitchens and bathroom
renewals and heating upgrades figured
high in terms of priorities within the
responses.
We also surveyed those on the
Council housing waiting list and 40%
of those who responded indicated that
they would like to live in a multi storey
flat and provided improvement
suggestions, many of which aligned
with what tenants would like to see
such as improved estate management
of the blocks.
Fire Safety
Fire safety is non-negotiable and has
not been subject of community
consultation. We currently have a
tender out to procure refreshed fire risk
assessments and expect to action
some enhanced safety measures as a
result of the findings. This scale of
FRA needs to be completed by
external consultants but the internal
H&S team have been, and will
continue to be, involved in ensuring
our homes are compliant with the
required standards. 
This strategic fire safety investment
will be supported by day to day fire
safety delivered by the Caretaking and
Building Services team which ensure
that there are no obstacles on the
common areas and all fire doors
operate as they should for example. 
Asset Investment
Our multi storey blocks are now over
50 years old and require ongoing
investment to ensure that they remain
fit for the future.  There is a need to
balance in-property investment, which
will continue, such as kitchens and
bathrooms with whole block
investment such as energy efficiency,
heating, roofs, windows and lifts.  
We will as part of the next steps of this
strategy, and in response to survey
findings:
Scope and procure building
fabric surveys for all blocks.
Residents highlighted issues with
dampness, mould and poor ventilation.
We need to understand the cause.
These surveys will also provide a
foundation for future investment for
example in energy efficiency measures
by assessing the performance of the
external wall insulation and windows. 
Install damp and mould
sensors in tenanted properties
as a priority
Page 137

Page 138

Damp and mould and sensors will help
tenants maintain a healthy home whilst
providing us with information about
which homes are experiencing
problems so we can take action to
help.   
This will support the building fabric
surveys by highlighting where
problems are and helping us to target
repairs. 
We will carry out a heating and
hot water options appraisal for
all blocks
Residents, particularly with electric
storage heaters, expressed
dissatisfaction with their heating
systems and it is important that we
review the heating and hot water to
ensure that it complies with our fuel
poverty and climate change ambitions.
Install Connected Response
smart switches in tenanted
properties to improve tenant
experience of electric storage
heaters.
Residents with electric storage heating
told us the heating and hot water was
expensive and was not available when
needed e.g. evenings due to overnight
charging periods. 
These smart switches will give tenants
more control over their heating and hot
water and allow them to access better
off peak tariffs. 
Review asset investment in
kitchens, bathrooms and
windows
Residents expressed a wish for
upgraded kitchens and bathrooms,
including the installation of showers
instead of baths. We will investigate
our asset investment in the flats to
ensure it is meeting cyclical
requirements. 
Pilot noise insulation in homes
(initially void properties)
Whilst some noise is to be expected
we will pilot noise insulation options
either in void properties in partnership
with residents.
Future proofing for our homes
In addition to making homes more
energy efficient we need to prepare
our homes for the future in terms of
technology such a smart home
technology. Some residents
highlighted in the survey that they
struggle to certain internet based tech
such as smart meters and Sky
services.
Improve Wi-Fi choice in the
blocks
We are not responsible for utilities
such as WIFI but we will investigate
means to improve tenant choice and
WIFI connection speed and on
opportunities to become more
involved.  
Common spaces (foyers,
landings and CCTV)
The common areas of a block of flats
represent first impressions but also
receive a lot of traffic from residents
and their friends, family, delivery and
trades people. It is clear from the
survey findings that residents would
like to see these spaces improved.  
Page 138

Page 139

Scope and procure a deep
clean contract for all the
blocks on a 2 year pilot basis
initially
One of the clearest asks from
residents were that closes and
common areas were cleaner.  The
caretakers on site do clean the
buildings daily but they have a number
of other responsibilities and it is
apparent that residents would like this
to be enhanced.  
We will arrange for blocks to be deep
cleaned multiple times per year, and
review to ensure that it is meeting
resident expectations.  
Investigate options to
refurbish foyers and closes
Foyers and closes are high traffic
areas which also provide the vital first
impression of a home and residents
identified refurbishment as a priority
alongside improvements to stores and
laundry.  It was also noted by residents
that signage could be clearer and
improved e.g. block names, flat and
floor numbers.  
Scope works contract for
CCTV and emergency lighting
In addition to refurbishing common
areas, residents expressed ambitions
for improved CCTV coverage and
lighting in their blocks to make them
feel safer and discourage ASB. 
We will also review the intercom
systems, which are an important
means of controlling who is coming
and going in the building.   
Green space and amenity offer
The Covid-19 pandemic has
highlighted how important local green
spaces and amenities such as shops
are to our communities.  Generally, our
residents were happy with the level of
amenity offered by our blocks with
many commenting on the ease of
access to shops and green spaces
were attributes they liked about their
home.  
Develop, in conjunction with
residents, plans to improve the
immediate greenspace/
parking around their blocks.
Residents expressed ambition to
improve their immediate greenspace
or parking but each block has specific
needs so this will need to be
developed in conjunction with
residents.  
Waste & opportunities for
recycling
As the council works to deliver its
Climate Change Strategy and achieve
national targets around reducing waste
sent to landfill, helping all residents but
particularly those living in flats to
reduce their waste and recycle as
much as they can is vitally important. 
Currently all the multi storey blocks of
flats are serviced by a central bin
chute. This does not separate waste
and is instead taken to landfill.
Instigate a working group to
improve waste management
and investigate new solutions
The bin chutes in the flats whilst
convenient were identified in the
Page 139

Page 140

survey as being smelly, noisy and
susceptible to blocking.  We will form a
working group to review waste
management for the multis storey
blocks. 
Supply more recycling bins to
the multi storey blocks
Residents at a number of blocks
expressed a desire for more recycling
facilities.   We will work with the waste
team to supply additional recycling
bins for residents. This may require
investment in bin stores or similar to
ensure they are housed safely.
Management
Multi storey flats offer a comparatively
dense form of housing and whilst this
often brings benefits such as
sustaining demand for local shops and
bus services, it does mean that
everyone is living in quite close
proximity of one another which can
bring complaints for example noise or
smells. 
Review housing management
policies in relation to resident
identified areas of concern
such as laundry etiquette,
ASB, dogs.
The behaviours of other residents
were identified as a major source of
dissatisfaction amongst residents. 
Whilst we cannot control individuals,
we can work to encourage respectful
behaviour through management and
policy. 
We will review our policies and utilise
communication methods to remind
residents of our policies such as how
to report ASB and the lift protocol.
Some reviews may require some
investment such as controlled access
to laundry rooms or the introduction of
additional staff present at all times.
Page 140

Page 141

About our multi storey blocks of flats
• West Dunbartonshire Council have 19 multi storey blocks of flats and
contained within these blocks are 1,232 homes.
• The blocks contain one, two and three bedroom flats, some blocks contain a
mix but some contain only two bedroom homes.
• All bar one of the blocks are mixed tenure meaning that WDC own some,
often the majority, but owner occupiers and private landlords own the
remaining share.
• The blocks were built in the 1960s using concrete panels and were insulated
and received new double glazing between 2010 & 2015 to make the homes
more energy efficient.
• Apart from the three blocks at Littleholm (which are connected to the gas
network) and Mountblow House (which has a communal system) the
remaining blocks use electric storage heaters as their main form of heating.
Background to the strategy
In 2021 we carried out consultation for our current Local Housing Strategy (2022-
2027).  We surveyed residents of West Dunbartonshire and received feedback
unprompted about the multi-storey flats.  
Some people feedback that they thought should be used to house elderly people
some people thought they shouldn’t, some people thought children shouldn’t live in
them meanwhile others thought they should, and some people thought they needed
investment.  West Dunbartonshire Council, acknowledge this feedback and have
committed to reviewing our multi-storey stock and looking to enhance what these
properties offer our current and future residents.  
Using our asset management database we reviewed these properties against a
number of criteria including number of voids, number of refusals and cost of repairs.
This approach highlights that from an asset management perspective these homes
are performing satisfactory but could perform better. Therefore, we also need to
ensure that they represent value for money for our HRA long term. 
We also note that in the period since Grenfell (2017) multi-storey blocks have been
subject to increased scrutiny and concern and it is vital that these homes are as fire
safe as any other home and are known to be so.  
Ultimately, our goal is to ensure that these homes are popular to live in and people
who live there feel and desire to stay there a long time and become part of the
community.  
Page 141

Page 142

Consultation
We surveyed residents using survey monkey for 12 weeks between October and
December 2022.  We received a good response from all blocks, as demonstrated by
the chart below, which shows the number of responses as a percent of the total flats
in each block. The residents have provided us with a clear steer in terms of what
they would like to see improved in their home and block and their constructive
feedback is greatly appreciated. 
Chart 1: Chart showing the percentage of response by block
Source: Enhanced multis living survey 2022
A full summary report of the survey findings are available as an appendix to this
strategy and it highlights that there were a number of positive elements for residents
living in the blocks including the neighbours, the size of flats, their layout and storage
and unsurprisingly for many – the view.  
Residents also put forward a number of suggestions for how to enhance their homes
and these have formed the basis for this strategy and action plan.  However, it
should be noted that a challenge which has emerged from the consultation findings
is that many of the enhancements people do not represent an enhanced living
standard but are planned investment through the Housing Capital Investment
Programme.  
We also surveyed those on the waiting list and whilst some people expressed a
dislike of the multis, 40% said they would like to live there and provided suggestions
for how to improve the books, many of which aligned with what residents would like
to see for example cleaner blocks and improved surrounding.  
0%
5%
10%
15%
20%
25%
Percentage of responses by block:
Page 142

Page 143

Fire safety
Since the Grenfell tragedy in 2017 increased focus has rightly been on fire safety in
taller buildings, particularly those which have been insulated with certain types of
insulation. Therefore it is imperative that we assure our residents and communities
that we have sufficient fire safety policies and protocols in place for these homes. 
We have continued to monitor the recommendations and guidance that has emerged
and worked with the Scottish Government’s specialist team.  The insulation which we
installed in our blocks has been found to be in compliance with building standards at
the time and does not have the same attributes as the insulation which has caused
concern elsewhere. However, we continue to keep it under review because frankly it
is too important not too. 
As a result of this strategy, we intend to review the key protocols and practices that
will help us ensure that these homes are as safe as any other. 
Day to day fire safety
Responsible premises officer: 
This person is the key point of contact within WDC for all aspects of health and
safety within the blocks. They are responsible for ensuring that all checks are
completed and concerns dealt with.  
They are also responsible for liaising with Scottish Fire and Rescue and any
concerns they may raise. Scottish Fire and Rescue visit the blocks regularly and
inspect various elements such as fire doors and report back to WDC as factor and
landlord any actions which need to be taken. 
Caretakers:
Each block has a caretaker who is on site daily, in addition to duties such as
cleaning the caretakers are responsible for ensuring all landings and stairwells are
clear of obstructions and reporting any issues for example broken fire doors to
repairs and maintenance.  
Repairs and maintenance specialist team: 
We are trialling a new specialist team utilising the contractor who supply and
maintain the fire doors, who will survey the blocks and organise repairs.  The trial
started in August 2022 and we will keep this under review. 
Fire Risk Assessments:
Fire risk assessments (FRAs) are standard assessments which are required for
some types of residential accommodation such as multi-storey blocks.  They need to
be undertaken and reviewed regularly. We last had FRAs undertaken on the multi-
storey blocks in 2017. 
Page 143

Page 144

The guidance for FRAs has been updated and we are looking to get refreshed
assessments undertaken, these are currently out for procurement.  We would also
like to supplement this with some fire engineering advice to ensure we have all
required information to support our long term fire safety in the blocks. 
As part of the procurement strategy we considered various options and engagement
with the H&S team found that they did not have the capacity to carry out this scale of
of FRA and thus it was agreed that these would be completed by external
consultants, who can also provide us with the specialist fire engineering advice. 
However, the internal H&S team have been, and will continue to be, involved in
procuring and overseeing the appointment of consultants to complete FRAs and they
will help us maintain our documentation going forward which in turn will help ensure
our homes are compliant with the required standards.  
Action: Carry out refreshed fire risk assessments for all blocks and action any
identified safety enhancements.
Asset investment
Surveys
The blocks were built in the 1960s of concrete panels and are now nearing 60 years
old consequently it is important that we survey the fabric to ensure they are in good
condition.  The need for these building fabric survey was highlight by residents who
complained about dampness, mould and poor ventilation alongside issues with
drainage. 
We need to understand the cause of these problems and target any remediation
works. Having quality building fabric information will also provide a foundation for
future investment, for example by enabling us to enhance the energy efficiency of
the homes which was also identified as a priority by residents. 
Action: Scope and procure building fabric surveys for all blocks.
Action: Install damp and mould sensors in tenanted properties as a priority
In the meantime, we recommend installing damp and mould sensors in all tenanted
multi storey homes.  These sensors will help tenants maintain a healthy home whilst
providing us with information about which homes are experiencing problems so we
can take action to help.  This will support the building fabric survey.  As per the
capital programme paper, we ask that multi storey properties are prioritised.
Energy efficiency improvements
Our multi storey homes have already received external wall insulation (EWI)
between 2010 and 2014 but residents expressed an ambition for this to be
enhanced. However, the heating and hot water systems in the multis were one of the
Page 144

Page 145

resident’s main gripes with many citing the costs of heating their home and the lack
of flexibility due to the current typically overnight charging methods.  This was
applicable to those blocks which have electric storage heaters. 
Action: We will carry out a heating and hot water options appraisal for all
blocks
For some blocks of flats (Littleholm and Dalmuir) the preferred heating replacement
will be connect them to the Queens Quay district heating system. A business case to
establish costs for this is being worked on by the team at WDC responsible for the
district heating. This would offer these residents a low carbon and efficient heating
system. 
For the remaining blocks other options will be investigated, the scale of multi storey
flats offers an opportunity for communal or shared systems and these will be
investigated.   
A heating and hot water options appraisal will take time and technology is evolving
but all options should be considered for example ground source heat pumps, air
source heat pumps and modern electric storage heaters.  
In the meantime we recommend extending the Connected Response pilot to include
all tenanted properties with electric storage heating in the multis.  These smart
heating and hot water controls move users off the radio tele switch and onto a digital
one which gives more control over charging which in turns allows users to access
better tariffs and get smart meters.   This can help residents use their systems more
efficiently with the potential of saving money and energy.  
Action: Install Connected Response smart switches in tenanted properties to
improve tenant experience of electric storage heaters.
Lifts
Lifts are a crucial element of life in a multi storey block and are an attractive feature
compared to tenement blocks which do not have lifts to any floors. However, when
lifts breakdown this is understandably problematic for residents. 
Therefore we are working to ensure that when lifts break they are out of action for as
short a time as possible and all residents are communicated with regarding
timescales as quickly as possible.  Our recent survey highlighted the importance of
communication and speedy repairs for residents. 
Breakdown policy
The Council have recently introduced a new lift breakdown policy for alerting
residents and residents when one or more lift in their block is down.  This policy will
be supplemented with text messages with residents and residents to update them in
real time to timescales regarding repairs. 
Page 145

Page 146

Long term strategy
Lifts in our blocks have a maintenance cycle which sees them checked annually by
our appointed contractor.   The same contractor also responds to and repairs any
issues with the lifts when they breakdown. To assist this contractor, the repairs and
maintenance team have been reviewing frequent repairs to try and identify and keep
in stock commonly needed parts. 
Kitchens and bathrooms
The recent survey highlighted the importance of kitchen and bathroom upgrades for
residents. This is something they have requested to enhance their home and as
such as will review our asset investment programme for kitchens and bathrooms to
make sure these are being updated within appropriate timescales. 
Action: Review asset investment in kitchens, bathrooms and windows
Noise insulation pilot
Whilst some noise is to be expected we will pilot noise insulation options either in
void properties or in partnership with residents. If successful then the pilot could be
extended to more homes in the blocks to help deal with noise transfer between
homes. 
Action: Pilot noise insulation in homes (initially void properties)
WIFI
As our homes become smarter and more systems look to utilise internet it is
important we ensure that our multis have excellent connectivity to enable both
ourselves and residents to utilise smart home devices.  
Our recent survey highlighted that some residents have frustrations with their current
options for Wi-Fi and TV for example not being able to get certain types of Sky or a
smart meter.  Whilst we are not responsible for utilities we will investigate if there are
steps we could take to help improve options for our residents and the possibility of
becoming more involved in the provision.
Action: Investigate improving Wi-Fi choice in the blocks
Outcome:
Ongoing investment in our homes is important and procuring building fabric surveys
will provide the foundation for future investments which our residents have
highlighted as important to them such as heating, hot water and energy efficiency
enhancements. 
In the meantime the installation of damp and mould sensors will empower our
tenants to manage the moisture in their homes whilst providing us with data on
moisture in our homes to help us take targeted action to tackle it. 
Page 146

Page 147

Similarly, the connected response switches offer an opportunity to improve the
storage heaters and hot water systems by changes residents over to digital switches
which unlocks the option of better off peak tariffs and smart meters.  
The pilot of noise insulation options in void properties and in conjunction with
residents will help us trial building fabric measures to improve noise between
properties.  
Common spaces (lobbies, landings and cleaning)
The common areas of a block of flats represent first impressions but also receive a
lot of traffic from residents and their friends, family, delivery and trades people. It is
clear from the survey findings that residents would like to see these spaces
improved.  
Refurbish common spaces
On the biggest asks from residents was to refurbish the common areas alongside
improvement to laundries (where available), store rooms and signage all of which
combine to make a more attractive and welcome first impression.  Ultimately this will
need to be developed with residents but the initial scoping works will seek to
understand possible improvements based upon initial suggestions.
Action: Investigate options to refurbish foyers and closes
Deep cleaning of closes, landings and foyers
Residents expressed an ambition for closes and foyers to be cleaner and suggested
that deep cleans would be beneficial. We will pilot deep cleaning the common areas
of the blocks a couple of times per year and review if this improves satisfaction.
Caretakers will still be responsible for day to day cleaning.
Action: Scope and procure a deep clean contract for all the blocks on a 2 year
pilot basis initially
Enhanced CCTV and emergency lighting
In addition to refurbishing and deep cleaning common areas, residents expressed
ambitions for improved CCTV coverage and lighting in their blocks to make them feel
safer and discourage ASB.  Initial discussions with colleagues in consultancy
services suggests that this will require a specialist design and build contract to
supply and fit these systems safely and thus it may benefit from being tied into other
works such foyer refurbishment.   
Action:  Scope works contract for CCTV and emergency lighting
Outcome:
Page 147

Page 148

Combined these enhancements offer the potential to improve the common spaces in
our blocks which our residents have told us are important to them.  The caretakers
will continue to be responsible for keeping the common areas clean on a day to day
basis alongside reporting any repairs needed to the fire doors and ensuring that any
rubbish is removed but the actions identified here seek to enhance the existing offer.
Surrounding green space and amenities
The recent Covid -19 pandemic has highlighted to many of us the value in our local
green spaces and parks, whilst residents of multi storey flats do not have their own
gardens or balconies many of the blocks have nearby grassed and green spaces or
are nearby sources of water such as canals and the River Clyde.  
Indeed many of those responding to our survey highlighted the amenities near their
flats as one of their top attributes of their homes. Tenants mentioned access to the
shops, transport links, sport facilities and parks as very important to them.
Looking to the immediate area around their homes many of the residents have
suggested that the areas around their homes could be improved for example by
creating spaces to sit,  tidying it up, providing children’s play spaces or increasing, or
improving, parking provision. Each block has specific needs so this will be developed
in conjunction with residents.  
Action: Develop in conjunction with residents plans to improve the immediate
greenspace/ parking around their blocks.
Waste Strategy
As the council works to deliver its Climate Change Strategy and achieve national
targets around reducing waste sent to landfill, helping all residents and particularly
those living in flats to reduce their waste and recycle as much as they can is vitally
important.   Currently all the multi storey blocks of flats are serviced by a central bin
chute. This does not separate waste and is instead taken to landfill.   The bin chutes
in the flats whilst convenient were identified in the survey as being smelly, noisy and
susceptible to blocking.  
We have formed a working group which will consider various options for improving
waste management within the blocks with an emphasis on making it easier to
recycle. For example, we will work with the waste team to supply additional recycling
bins for tenants in the first instance because many residents told us they didn’t have
them or there weren’t enough.  This may require investment in bin stores or similar to
ensure they are housed safely.
Action: Instigate a working group to improve waste management and
investigate new solutions
Action: Supply more recycling bins to the multi storey blocks
Page 148

Page 149

Management
Multi storey flats offer a comparatively dense form of housing and whilst this often
brings benefits such as sustaining demand for local shops and bus services, it does
mean that everyone is living in quite close proximity of one another which can bring
complaints for example noise or smells. 
The behaviours of other residents were identified as the source of dissatisfaction
amongst residents.  Whilst we cannot control individuals, we can work to encourage
respectful behaviour through management and policy. 
We will review our policies and utilise communication methods to remind residents of
our policies such as how to report ASB and the lift protocol. Some reviews may
require some investment such as controlled access to laundry rooms or additional
staff during evenings and weekends.
Action: Review housing management policies in relation to resident identified
areas of concern such as laundry etiquette, ASB, dogs. 
Page 149

Page 150

Page 150

Page 151

APPENDIX 1A– IMPROVEMENT ACTION PLAN 2023/28
Action Reason: Outcome:
Carry out refreshed fire
risk assessments for all
blocks and action any
identified safety
enhancements.
It is vital our homes are compliant with fire
safety standards.  
We will receive the current FRAs this year 2023
and it is important that we action any identified
enhancements, potentially as part of wider works
programme, as soon as possible.  
Scope and procure
building fabric surveys
for all blocks.
Residents complained about dampness,
mould and poor ventilation. We need to
understand the cause. They will also provide
a foundation for future investment. 
The survey will give us detailed information about
the building fabric of our homes and allow us to
target any repairs or remediation.  
Install damp and mould
sensors in tenanted
properties as a priority
Damp and mould and sensors will help
tenants maintain a healthy home whilst
providing us with information about which
homes are experiencing problems so we can
take action to help.  
Tenants will be empowered to manage moisture in
their homes and we will have information about
homes experiencing problems with ventilation.
This will support the building fabric survey.  As per
the capital programme paper, we ask that multi
storey properties are prioritised. 
We will carry out a
heating and hot water
options appraisal for all
blocks
Residents, particularly with electric storage
heaters, expressed dissatisfaction with their
heating systems.  
This will put in place a longer term strategy for
heating and hot water for the blocks.   This will
align with net zero ambitions and may for example
see some blocks connected to the district heating
system at Queens Quay.  Heating and hot water
budgets will require budget to be identified for the
appropriate investments. 
Install Connected
Response smart
switches in tenanted
Residents with electric storage heating told
us the heating and hot water was expensive
The smart switches move tenants off the radio tele
switch which allows them to get smart meters,
access better tariffs and have more control over
Appendix 1a
Page 151

Page 152

APPENDIX 1A– IMPROVEMENT ACTION PLAN 2023/28
Action Reason: Outcome: 
properties to improve
tenant experience of
electric storage heaters.
and was not available when needed due to
charging periods. 
their heating and hot water.  The switches can be
deployed relatively swiftly and offer numerous
benefits. 
Review asset investment
in kitchens, bathrooms
and windows
Residents expressed a wish for upgraded
kitchens and bathrooms, including the
installation of showers instead of baths.  
These are on cyclical programme but we will
review to ensure that homes have kitchens and
bathrooms which meet the required standards.  
Pilot noise insulation in
homes (initially void
properties)
Noise from other residents and whilst some
noise is to be expected we will pilot noise
insulation options either in void properties in
partnership with residents. 
This pilot will see us investigate and pilot noise
reducing insulation in our homes. If successful
then the pilot could be extended to more homes in
the blocks.
Investigate improving
Wi-Fi choice in the
blocks
Residents expressed frustration with their
current Wi-Fi options.
We are not responsible for utilities such as WIFI
but we will investigate means to improve tenant
choice and connection speed and opportunities for
the Council to become more involved in provision. 
Investigate options to
refurbish foyers and
closes
Foyers and closes are high traffic areas
which also provide the vital first impression of
a home and residents identified
refurbishment as a priority alongside
improvements to stores and laundry.  
Ultimately this will need to be developed with
residents but the initial scoping works will seek to
understand possible improvements based upon
initial suggestions e.g. laundry, store rooms,
welcoming.  
Scope and procure a
deep clean contract for
all the blocks on a 2 year
pilot basis initially
Residents expressed an ambition for closes
and foyers to be cleaner and suggested that
deep cleans would be beneficial. 
We will pilot deep cleaning the common areas of
the blocks a couple of times per year and review if
this improves satisfaction. Caretakers will still be
responsible for day to day cleaning. 
Scope works contract for
CCTV and emergency
lighting 
In addition to refurbishing common areas,
residents expressed ambitions for improved
This will require a specialist design and build
contract to supply and fit these systems safely and
Page 152

Page 153

APPENDIX 1A– IMPROVEMENT ACTION PLAN 2023/28
Action Reason: Outcome:
CCTV coverage and lighting in their blocks to
make them feel safer and discourage ASB.
thus it may benefit from being tied into other works
such foyer refurbishment.   
Develop in conjunction
with residents plans to
improve the immediate
greenspace/ parking
around their blocks.
Residents expressed ambition to improve
their immediate greenspace or parking but
each block has specific needs so this will
need to be developed in conjunction with
residents.  
We will work to develop options with tenants per
block identifying appropriate budgets and
outcomes.   
Instigate a working
group to improve waste
management and
investigate new
solutions.
The bin chutes in the flats whilst convenient
were identified in the survey as being smelly,
noisy and susceptible to blocking.  
Working with colleagues across WDC we will
develop a waste options appraisal but as per
below the first steps are to improve recycling at
the blocks. However we will actively look at
alternative solutions to the chute system
Supply more recycling
bins to the multi storey
blocks
Residents at a number of blocks expressed a
desire for more recycling facilities.  
We will work with the waste team to supply
additional recycling bins for tenants.  This may
require investment in bin stores or similar to
ensure they are housed safely. 
Review housing
management policies in
relation to resident
identified areas of
concern such as laundry
etiquette, ASB, dogs.
The behaviours of other residents were
identified as the source of dissatisfaction
amongst residents.  Whilst we cannot control
individuals we can work to encourage
respectful behaviour through management
and policy. 
We will review our policies and utilise
communication methods to remind residents of our
policies such as how to report ASB, the lift
protocol. 
Meanwhile other reviews will be undertaken that
may require additional investment e.g.; controlled
access to laundry rooms or additional staff during
evenings and weekends. 
Page 153

Page 154

Page 154

Page 155

WEST DUNBARTONSHIRE COUNCIL
Report by Chief Officer – Housing and Employability
Housing and Communities Committee: 3 May 2023 
___________________________________________________________________
Subject: Tenant Satisfaction Survey
1. Purpose
1.1 This purpose of this report is to provide members of the Housing and
Communities Committee with the results of a comprehensive Tenant
Satisfaction Survey on Housing and Homelessness Services that has been
carried out and the results of which will be reported to the Scottish Housing
Regulator as part of our 2022/23 Scottish Social Housing Charter
requirements.
2. Recommendations
2.1 It is recommended that the Housing and Communities Committee:
(i) note the contents of this report and recognises the Tenant Satisfaction
levels across all areas of housing and homelessness services since the
introduction of the Scottish Social Housing Charter;
(ii) approve the improvement action plan developed to address the
drivers of dissatisfaction raised by tenants and instruct the Chief
Officer Housing and Employability and the Chief Officer, Supply,
Distribution and Property to fully  implement this action plan;
(iii) note that this satisfaction data will be reported to the Scottish
Housing Regulator (SHR) as part of our Annual Return on the
Charter (ARC); and
(iv) agree that the information and improvement plan contained in this
report is shared with the West Dunbartonshire Tenant Scrutiny
Panel and WDTRO (West Dunbartonshire Tenants and Residents
Organisations) and is distributed more widely to tenants and
housing and homelessness staff.
3. Background
3.1 The Scottish Social Housing Charter (SSHC) requires all social landlords to
have robust and up to date Customer Satisfaction information and to report
this annually to the SHR via the ARC.
3.2 In order to meet this obligation, it was agreed by Housing, Environment and
Economic Development Committee in November 2013 that a
comprehensive tenant satisfaction survey be carried out on an annual basis
for the duration of the first 4 full years of the Charter, when it would then be
reviewed by the Scottish Housing Regulator and Scottish Government.
ITEM 15
Page 155

Page 156

Subsequently, after the review it was agreed in partnership with tenants and
residents organisations that a comprehensive tenant satisfaction survey would
be carried out for our housing and homelessness services every second year.
3.3 However, because of service priorities emanating from the recovery from the
pandemic, the planned survey to be carried out in 2021/22 was delayed until
2022/23. 
4. Main Issues
4.1 The main aim of the Tenant Satisfaction Survey was to seek tenant views of
the housing landlord services provided by the Council and to identify areas
where the service can be improved.
4.2 The survey was designed to meet the guidance provided by the Scottish
Housing Regulator with regard to assessing tenant satisfaction.  As such, the
survey was designed to ensure that:
• the questions asked covered the key tenant satisfaction Charter indicators
in the way which is prescribed.
• the sample was designed to meet the guidance provided by the Scottish
Housing Regulator which states that a minimum of data accurate to +/-5%
should be achieved and the sample should be designed to be
representative of the organisation’s tenant population.
4.3 The IPSOS MORI guidance prepared on behalf of the Regulator debates the
use of a range of different methodologies for carrying out large scale tenant
satisfaction surveys, including postal, online, telephone and face to face
survey methods.
4.4 Given the requirement to achieve data accurate to +/-5% and ensuring a
representative sample of tenants, it was decided that the tenant survey was
carried out utilising a telephone survey. The main benefits of this were:
• utilising an interviewer led methodology allows us to maximise the
response rate;
• this methodology is an inclusive methodology and allows interviewers to
ensure that, for example, elderly or those with a disability or literacy
problems can be included in the process; and
• the methodology facilitates high quality of survey output as it allows the
interviewer to build up a rapport with the participant ensuring that the
questionnaire is answered in full and allowing explanation of the necessity
for asking personal data.
4.5 A total of 600 telephone interviews were carried out between 11 October and
27 November 2022, providing data accurate to +/-4.25%.  Analysis of the
participant profile shows that the survey sample is broadly representative by
geography and property size.  Therefore, there was no requirement for the
survey data to be weighted. 
Page 156

Page 157

4.6 The table below shows the results for the six Charter Indicators that this
survey is used as the source for and assesses performance trends over the
period of the Scottish Social Housing Charter:
West Dunbartonshire Council Tenant Satisfaction Survey 2022
2014 2015 2016 2017 2019 2022
Satisfaction
level since
2014
% of tenants satisfied with
the overall service provided
by their landlord
72% 81% 84% 84% 79% 68% -4%
% of existing tenants satisfied
with the quality of their
home
74% 80% 81% 86% 77% 73% -1%
% of tenants who feel that
their rent represents good
value for money
67% 73% 68% 75% 77% 61% -6%
% of tenants who feel their
landlord is good at keeping
them informed about
services and decisions
72% 76% 87% 84% 86% 76% +4%
% of tenants satisfied with
opportunities to participate
in decision making
52% 59% 67% 79% 84% 69% +17%
% of tenants satisfied with
the management of the
neighbourhood they live in
76% 78% 80% 80% 79% 63% -13%
Overall Satisfaction
4.7 The survey opened by asking respondents how satisfied or dissatisfied they
were with the overall service provided by West Dunbartonshire Council as
their landlord. A majority of tenants (68%) are satisfied with the housing
service overall, whilst 28% are dissatisfied.
4.8 Considering overall tenant satisfaction by property size (as measured by
bed spaces), satisfaction ranges from 69.5% for 1 bed homes, through
69.4% for two bed properties to 55.7% for three or more bed homes.
4.9 Analysis of the responses for overall tenant satisfaction by housing format
illustrates some degree of variation, e.g. 66.7% satisfied for tenants living
in tenements compared to 50.0% satisfied amongst those living in end
terrace homes. 
4.10 In terms of newer homes overall tenant satisfaction was 100% in homes
built after 2021 compared with 60% in older homes.
4.11  In relation to Council areas, the most satisfied tenants overall reside in
Dumbarton (66.2% satisfied) and Alexandria (62.6% satisfied), whilst the
Page 157

Page 158

least satisfied are living in Clydebank (58.5%).
Repairs and maintenance
4.12 The satisfaction data relating to repairs for our ARC submission is sourced via
the existing exit surveys (as per the technical guidance). However, we also
use the opportunity in this representative survey to ask all tenants about their
general satisfaction with repairs and maintenance.
2014 2015 2016 2017 2019 2022
Satisfaction
level since
2014
Generally how satisfied
are you with the way
your landlord deals with
repairs and maintenance
66% 69% 77% 81% 75% 68% +2%
4.13 68% of tenants surveyed were very or fairly satisfied in this respect compared
to 7% who were neither satisfied nor dissatisfied and 25% who were very or
fairly dissatisfied. Satisfaction has decreased since the last survey from 75%
in 2019 to 68% in 2022. However, satisfaction levels are higher than those
recorded in the baseline survey in 2014 after the introduction of the Scottish
Social Housing Charter.  It is evident from the wider responses that the
impacts of the pandemic and the subsequent recovery period have been a
factor in the wider satisfaction levels.
Value for Money
4.14 Respondents were then asked what factors they deem to be important with
regards to value for money.  Respondents were most likely to say
investment in their home and new homes by their landlord (94%) was very
important, followed by how much income they have left after paying their
rent (85%), the quality of service they receive from their landlord (81%)
and how their rent compares with other landlords (80%).
4.15 When asked what they would like to see the Council spending more money
on, tenants were most likely to say more regular maintenance
programmes (93%) followed by a new house build programme (92%) and
an increased budget for external improvements (41%).
4.16 More than six in ten (61%) believed the rent for their home represents very
or fairly good value for money, compared to 24% who said it was neither
good nor poor value for money and 15% who rated it as very or fairly poor
value.
4.17 Over seven in ten tenants (72%) of respondents were in receipt of full or
partial housing benefit, compared with 28% who said they paid full rent.
Those who paid their rent (either fully or partially) were asked how easy
they find it to afford the rent payments for their home.  Only 37% said the
Page 158

Page 159

rent for their home was very or fairly easy to afford, 45% said it was just
about affordable and 18% said it was very or fairly difficult to afford.
4.18 Analysis of rent value by property size shows that tenants living in 1 bed
homes are the most positive on this measure (64.4% say rent is good
value), whilst the least positive are those living in 2 bed properties
(57.1%). 
4.20 In relation to property type, tenants living in semi-detached homes (74.2%
say rent is good value) are the most likely to say that rent is good value for
money. Tenants living in end terrace homes (54.8% say rent is good
value), or other types of property (54.5%), are the least likely to be positive
about rent value.
4.21 Measured by area, the most positive tenants on rent value live in
Dumbarton (75.2% say rent is good value) which compares favourably to
both Clydebank (58.5%) and Alexandria (52.2%). 
Housing quality
4.22 Most tenants (73%) are satisfied with housing quality (27%) are
dissatisfied. The 2022/23 figure for satisfaction is 4% points lower than
2019 (77% satisfied). The 2021/22 sector average for housing quality
satisfaction is 77.2% (based on results submitted since April 2020).
4.23 Housing quality satisfaction is highest for tenants living in 1 bed homes
and lowest for those living in 2 bed homes (only 60.6%).  There is some
degree of variation in satisfaction with housing quality by property type
with the highest satisfaction found amongst tenants living in in semi-
detached homes (88%). 
4.24 Analysis of housing quality satisfaction by area shows that the most
satisfied area in relation to housing quality is Dumbarton (80.6% satisfied)
whilst the least satisfied area is Clydebank (68.9%).
4.25 Only one in three tenants (36.0%) agreed that they can easily afford to
heat their home; 49.2% disagreed. Compared with previous data, it is
notable that the proportion of tenants who cannot afford to easily heat
their home has more than doubled.  This can be easily attributed to the
wider cost of living crisis and the wider impact on the enjoyment our
tenants have of their home as a result.
Tenant Participation and Engagement
4.26 More than 7 in 10 tenants (76%) said their landlord was good at keeping
them informed about services and decisions against 24% who said the
Council was poor on this measure.  The sector average in 2022 was
80.8%.
4.27 69% of tenants were happy with opportunities to participate in decision
making against 25% of tenants who were dissatisfied with these
opportunities. It is noticeable that the level of dissatisfaction has increased
from 12% at the last comprehensive tenant satisfaction survey and this
Page 159

Page 160

might reflect tenants’ views on decision making and responsiveness within
the service. 
4.28 Respondents were asked about the source of information they use to obtain
information about the Council’s housing services.  Written communications
were the most common method used, with 85% stating they use the quarterly
newsletter Housing News, this compares with 18% that use social media
platforms.
Neighbourhood management
4.29 More than six in ten tenants (63%) are satisfied with neighbourhood
management, whilst 27.8% are dissatisfied.  Satisfaction with neighbourhood
management varies by area:-
Dumbarton – 69%
Alexandria – 62%
Clydebank – 61%
Summary and Improvement actions
4.30 Whist a majority of tenants have expressed satisfaction with the housing
services they receive from the Council, a sometimes large minority have
identified some dissatisfaction and based on the tenant feedback in these and
other areas, these are 5 main areas of dissatisfaction which in large have
informed the Improvement plan attached as Appendix 1 of this report.  The
five areas are stated below:-
• Being able to heat the home
• Housing quality
• Repair service
• Management of the neighbourhood
• Rent value for money
4.31 The design of our tenant satisfaction survey meant that any tenants who
expressed dissatisfaction were asked to expand about the reasons for this. 
The feedback has been analysed in some detail and an identified need for
improvement in the following five areas:-
• Better repair service (quality, speed, keep appointments) (19.0% of all
tenants)
• Be more responsive, follow up and resolve issues, reduce delays
(9.7%)
• Be easier to contact, have better communications (7.2%)
• Improve internal parts of the home (5.2%)
• Deal with anti-social behaviour more effectively (neighbours, youths,
pets) (4.7%).
Page 160

Page 161

4.32 Improvement actions have been developed to address areas of
dissatisfaction and is improvement plan is attached as Appendix 1.
5. People Implications
5.1 Developing appropriate service responses in areas where weaknesses are
identified will be managed from within existing staffing resources.
6. Financial and Procurement Implications
6.1 There are no financial and procurement implications.  Any improvement
actions will be resourced within existing resource allocation and budget.
7. Risk Analysis
7.1 There is a risk that failure to have a comprehensive approach toward Customer
Satisfaction and toward benchmarking as part of our wider response to the
Scottish Social Housing Charter, would attract an adverse reaction from the
Scottish Housing Regulator.
8. Equalities Impact Assessment (EIA)
8.1  The proposals do not alter any existing policy or pattern of service delivery
and so is not considered to require an equalities impact assessment.
9 . Consultation
9.1      The findings from the tenant satisfaction survey will be presented to tenant
representatives and we will develop an agreed process for ongoing tenant
involvement in the monitoring of the Improvement Action Plan attached as
Appendix 1 of this report.
10. Strategic Assessment
10.1 The proposals contained in this report directly address all of the Council’s
strategic priorities. The investment in, and provision of attractive affordable
housing will also indirectly support the objective of economic growth and
employability through supporting employment and improving place
attractiveness.
Peter Barry
Chief Officer Housing and Employability
Date:  18 April 2023
__________________________________________________________________
Person to Contact: John Kerr – Housing Development and Homelessness
Manager, Housing Development and Homelessness,
Page 161

Page 162

telephone: 07793717981, email: John.Kerr@west-
dunbarton.gov.uk
Appendices: Appendix 1: Tenant Satisfaction Survey Improvement
Action Plan  
Background Papers: None
Wards Affected: All
Page 162

Page 163

Tenant Satisfaction Survey 2022/23 - Improvement
actions
1. Overall satisfaction
Action Assigned To Due date
Implement improvement plan for Building services – Phase 3 Martin Feeney Mar 2024
Review and update Tenant Communication Strategy John Kerr Mar 2024
Develop and Implement Revised ASB Policy Nicola Pettigrew Mar 2024
Ensure the Council’s Housing stock progresses towards the achievement of the energy efficiency standard
for social housing (EESSH2). Alan Young Mar 2024
Deliver a Greener, Fairer Housing Asset Management Strategy and Investment Plan John Kerr Mar 2024
Conduct follow up tenant satisfaction survey in final quarter 2023/24 John Kerr Mar 2024
2. Repairs and maintenance
Action Assigned To Due date
Review Repairs Policy Martin Feeney Mar 2024
Improve customer satisfaction with Building Services Martin Feeney Mar 2024
Improve maintenance & repairs performance Martin Feeney Mar 2024
3. Value for Money
Action Assigned To Due date
Review Direct Tenant Support Funding Schemes Nicola Pettigrew Mar 2024
Review provision of assistance to tenants in terms of energy efficiency Alan Young Mar 2024
Undertake Rent Affordability Assessment as part of Rent Consultation Exercise John Kerr Mar 2024
4. Housing Quality
Action Assigned To Due date
Implement and monitor process for Dampness and Mould in Tenants Homes Martin Feeney Mar 2024
Deliver the HRA Capital Improvement programme for 2023/24 Alan Young Mar 2024
Improve progress on Electric Installation Condition Reports Martin Feeney Mar 2024
Implement and Review new void relet standard Nicola Pettigrew Mar 2024
Implement Multi Storey Enhanced Living Strategy John Kerr Mar 2024
Deliver the Council’s Affordable Housing Supply Programme John Kerr Mar 2024
Appendix 1
Page 163

Page 164

#
5. Tenant Participation and Customer Engagement
Action Assigned To Due date
Explore new methods to provide information and obtain tenants’ views (social media, IHMS) John Kerr Mar 2024
Review and improve the content on the Housing web pages and use of digital media John Kerr Mar 2024
Maximise the tenant self-serve portal within IHMS John Kerr Mar 2024
6. Neighbourhood management
Action Assigned To Due date
Increase awareness of how to report Anti-Social Behaviour (ASB) Nicola Pettigrew Mar 2024
Deliver new ASB strategy with focus on council properties Nicola Pettigrew Mar 2024
Promote estate walk about programmes to tenants Nicola Pettigrew Mar 2024