Item 14 - Appendices 5 - 6
West Dunbartonshire Council · 22 February 2023
Back to Housing & Communities Committee — 22 February 2023 and its agenda
Text extracted from the council's PDF. Layout and reading order may differ from the original.
Page 1
WEST DUNBARTONSHIRE COUNCIL APPENDIX 5 GENERAL SERVICES CAPITAL PROGRAMME OVERALL PROGRAMME SUMMARY MONTH END DATE PERIOD Spend to Date Spend to Date £000 £000 Red 0 0% 0 0% 0 0% 0 0% Amber 0 0% 0 0% 0 0% 0 0% Green 3 100% 859 100% 3 100% 39 100% 3 100% 859 100% 3 100% 39 100% Budget Spend to Date Forecast Spend Forecast Variance Budget Spend to Date Forecast Spend Forecast Variance Slippage Over/ (Under) £000 £000 £000 £000 £000 £000 £000 £000 £000 £000 PL CY 0 0 0 0 0 0 0 0 0 0 #DIV/0! #DIV/0! 0 0 0 0 0 0 0 0 0 0 #DIV/0! #DIV/0! 1,212 859 1,212 0 147 39 147 0 0 0 0% 0% 1,212 859 1,212 0 147 39 147 0 0 0 31 December 2022 Project Status Analysis Project Life Status Analysis Current Year Project Status Analysis Number of Projects at RAG Status % Projects at RAG Status % Project Spend at RAG Status Number of Projects at RAG Status % Projects at RAG Status % Project Spend at RAG Status Projects are either at risk of being overspent and/or delay in completion (although this is unquantifiable at present) or the project has any issues that require to be reported at this time Green TOTAL EXPENDITURE Project Life Financials Current Year Financials Red Projects are on target both in relation to overall budget and the forecast stages in the project life cycle and no issues are anticipated at this time TOTAL EXPENDITURE 9 Projects are forecast to be overspent and/or significant delay to completion Amber Red Projects are forecast to be overspent and/or experience material delay to completion Amber Projects are either at risk of being overspent and/or delay in completion (although this is unquantifiable at present) or the project has any issues that require to be reported at this time Green Projects are on target both in relation to overall budget and the forecast stages in the project life cycle and no issues are anticipated at this time ITEM 14
Page 2
WEST DUNBARTONSHIRE COUNCIL APPENDIX 6 GENERAL SERVICES CAPITAL PROGRAMME ANALYSIS OF PROJECTS AT GREEN ALERT STATUS PERIOD END DATE PERIOD 9 Budget Forecast Spend £000 £000 % £000 £000 % 1 Project Life Financials 912 832 91% 912 0 0% Current Year Financials 80 35 44% 80 0 0% Project Description Project Manager Elaine Troup Chief Officer Peter Barry Project Lifecycle 31-Mar-23 31-Mar-23 2 Project Life Financials 100 26 26% 100 (0) 0% Current Year Financials 17 4 21% 17 0 0% Project Description Project Manager Graham Watters Chief Officer Peter Barry Project Lifecycle 31-Mar-30 31-Mar-30 3 Project Life Financials 200 0 0% 200 0 0% Current Year Financials 50 0 0% 50 0 0% Project Description Project Manager John Kerr Chief Officer Peter Barry Project Lifecycle 31-Mar-30 31-Mar-30 31 December 2022 Budget Details Project Life Financials Spend to Date Variance Planned End Date Forecast End Date Main Issues / Reason for Variance Development of system progressing, with full budget spend anticipated to be incurred in 2022/23. Mitigating Action None required at this time. Mitigating Action None required at this time. Anticipated Outcome Full spend is anticipated on this year's budget. Integrated Housing Management System Development of IHMS system. Invest in "Your Community Initiative" Capital budget to support the roll out of Your Community, an initiative designed to achieve coordinated service delivery in response to community need. This is complimented by community capacity building, empowering WD citizens to do more for their own communities (leading to less reliance on council). Also included is the implementation of participatory budgeting to support and build capacity in communities. Planned End Date Forecast End Date Main Issues / Reason for Variance Application process is planned for later in this financial year. Main Issues / Reason for Variance The Council is currently trying to secure new funding to provide new accommodation within the Dennystoun Forge site. This may require some redesign of the existing site and has resulted in proposed works to provide additional play and security measures being held until future design proposals are confirmed. Mitigating Action Officers carried out some proactive consultative work to establish the tenant priorities this will allow the work programme to be developed timeously. Anticipated Outcome It is expected the works programme will be completed during 2022/2023. Anticipated Outcome Development of IHMS system. Dennystoun Forge Site Improvements Dennystoun Forge Site Improvements Planned End Date Forecast End Date ITEM 14