Democracy Spraffa

Item 13 - Appendices 3 -7

West Dunbartonshire Council · 22 February 2023
Back to Housing & Communities Committee — 22 February 2023 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

APPENDIX 3
WEST DUNBARTONSHIRE COUNCIL
HRA CAPITAL PROGRAMME
OVERALL PROGRAMME SUMMARY
MONTH END DATE
PERIOD 9
Spend to
Date Spend to Date
£000 £000
Red
12 44.4% 12,763 63.5% 12 44.4% 12,763 63.5%
Amber
0 0.0% 0 0.0% 0 0.0% 0 0.0%
Green
15 55.6% 7,321 36.5% 15 55.6% 7,321 36.5%
27 100% 20,084 100% 27 100% 20,084 100%
Budget Spend to
Date
Forecast
Spend Forecast Variance Budget Spend to Date Forecast
Spend
Forecast
Variance Reprofiled Over/
(Under)
£000 £000 £000 £000 £000 £000 £000 £000 £000 £000
166,246 12,763 170,325 4,079 53,876 12,763 26,285 (27,592) (31,671) 4,079
0 0 0 0 0 0 0 0 0 0
49,874 7,321 49,694 (181) 11,727 7,321 11,547 (181) 0 (181)
216,120 20,084 220,019 3,899 65,604 20,084 37,831 (27,772) (31,671) 3,899
216,120 20,084 220,019 (3,899) 65,604 20,084 37,831 27,772
0 0 0 0 0 0 0 0
Projects are on target both in relation to overall budget and the forecast
stages in the project life cycle and no issues are anticipated at this time
31 December 2022
Project Status Analysis
Project Life Status Analysis Current Year Project Status Analysis
Number of
Projects at
RAG Status
% Projects at
RAG Status
% Project Spend at
RAG Status
Number of
Projects at
RAG Status
% Projects at
RAG Status
% Project
Spend at RAG
Status
Red
Projects are forecast to be overspent and/or experience material delay
to completion
Amber
Projects are either at risk of being overspent and/or delay in completion
(although this is unquantifiable at present) or the project has any issues
that require to be reported at this time
Green
Project Status Analysis
Project Life Financials Current Year Financials
Red
TOTAL RESOURCES
NET EXPENDITURE
Projects are forecast to be overspent and/or significant delay to
completion
Amber
Projects are either at risk of being overspent and/or delay in completion
(although this is unquantifiable at present) or the project has any issues
that require to be reported at this time
Green
Projects are on target both in relation to overall budget and the forecast
stages in the project life cycle and no issues are anticipated at this time
TOTAL EXPENDITURE
ITEM 13

Page 2

WEST DUNBARTONSHIRE COUNCIL APPENDIX 4
HRA CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
MONTH END DATE
PERIOD 9
Budget Forecast Spend
£000 £000 % £000 £000 %
1
Project Life Financials 2,266 703 31% 2,635 369 16%
Current Year Financials 431 703 163% 800 369 86%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
2
Project Life Financials 271 5 2% 271 0 0%
Current Year Financials 185 5 3% 94 (91) -49%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
3
Project Life Financials 192 0 0% 192 0 0%
Current Year Financials 192 0 0% 0 (192) -100%
Project Description
Project Lifecycle 31-Mar-23 31-Mar-24
31 December 2022
Budget Details Project Life Financials
Spend to Date Variance
Main Issues / Reason for Variance
Budget overspend is anticipated due to costs and demand for budget being higher than anticipated at time of budget setting.
Mitigating Action
None available at this time.
Anticipated Outcome
Project to complete over budget.
Capitalised minor works
This is a budget to undertake specific minor ad hoc capital projects that arise on demand 
Planned End Date  Forecast End Date
QL Development
This budget relates to the costs associated with the development of the Integrated Housing
Management System
Anticipated Outcome
Element of budget required to be rephased to 23/24.
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Development of QL system continues through 2022/23.  It was anticipated that two fixed term posts would be appointed to support
the ongoing development, however these posts have not yet been filled and this element of the budget will be required to be
reprofilled to 23/24.
Mitigating Action
None available at this time.
Main Issues / Reason for Variance
The GAA have still to publish their Noise Insulation Scheme which was scheduled for Autumn 2022, the scheme would detail
funding arrangements for those properties both commercial and residential that fall within the scope of the scheme.  The delay to
the publication has negated the opportunity to commence this project in 22/23.  Officers are pressing the GAA for an update in
terms of their timescales, however at this time it is anticipated that the project will be reprofilied to 23/24.
Mitigating Action
Officers liasing with GAA
Anticipated Outcome
Budget to be rephased to 23/24
Airport Noise
Noise Insulation Project 
Planned End Date  Forecast End Date
ITEM 13

Page 3

WEST DUNBARTONSHIRE COUNCIL APPENDIX 4
HRA CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
MONTH END DATE
PERIOD 9
Budget Forecast Spend
£000 £000 % £000 £000 %
31 December 2022
Budget Details Project Life Financials
Spend to Date Variance
4
Project Life Financials 17,607 1,636 9% 17,607 0 0%
Current Year Financials 4,955 1,636 33% 2,700 (2,255) -46%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
5
Project Life Financials 10,963 778 7% 10,963 0 0%
Current Year Financials 2,500 778 31% 1,000 (1,500) -60%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
6
Project Life Financials 566 141 25% 658 92 16%
Current Year Financials 108 141 131% 200 92 86%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
Roof Coverings
Building external component renewals, roofs/chimneys/flashings/fascias/gutters/svp
Anticipated Outcome
Full budget will not be spent and balance to carry into 23-24
Doors/window component renewals
Doors/Windows Component Renewals 
Planned End Date  Forecast End Date 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Currently behind monthly targets, unlikely to meet full spend and targets. Current tiled roof progress is behind cumulative monthly
targets but overall output is anticipated to increase with the new metal and flat roof framework contract coming on board
contributing to a wider range of roof types being completed.
Mitigating Action
Officer and contracts team working to maximise progress where possible to increase completions and spend.
Main Issues / Reason for Variance
Officers working to meet revised targets.  Additional external support has been programmed in from August onwards to assist with
window installs, feedback from officers have highlighted challenges with resource levels from back-up contractor.  This will be
monitored closely, however approximately £1.5m will need to reprofiled into 23/24.
Mitigating Action
Building Services actively redeploying internal resurces to assist with installs and working with external support to maximise
contribution.
Anticipated Outcome
Anticipated to meet reduced forecast spend
Main Issues / Reason for Variance
Projected to exceed budget, this is necessary work to meet demand and comply with legislation.
Mitigating Action
None available.
Anticipated Outcome
Budget to overspend.
Statutory/regulatory compliance works (lifts/electrical/legionnella/fire etc)
This budget will be used to upgrade / replace components / installations in order to comply with
the relevant standards / legislation / health and safety in relation to housing stock. 
Planned End Date  Forecast End Date

Page 4

WEST DUNBARTONSHIRE COUNCIL APPENDIX 4
HRA CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
MONTH END DATE
PERIOD 9
Budget Forecast Spend
£000 £000 % £000 £000 %
31 December 2022
Budget Details Project Life Financials
Spend to Date Variance
7
Project Life Financials 5,092 2,187 43% 6,723 1,631 32%
Current Year Financials 969 2,187 226% 2,600 1,631 168%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
8
Project Life Financials 5,293 1,216 23% 5,707 414 8%
Current Year Financials 1,036 1,216 117% 1,450 414 40%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
9
Project Life Financials 8,384 3,147 38% 9,884 1,500 18%
Current Year Financials 2,000 3,147 157% 3,500 1,500 75%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
10
Project Life Financials 3,637 423 12% 3,637 0 0%
Current Year Financials 887 423 48% 600 (287) -32%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
Mitigating Action
None available since essential spend.
Anticipated Outcome
Budget to overspend.
Heating improvement works
Carry out works to renew inefficient boilers/full systems as identified from the stock condition
survey and renewal of obsolete/damaged boilers. 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
An overspend is anticipated on this budget, as experienced in recent years as demand has exceeded expectations. Current
progress continues this trend. Due to the nature of this project (ensuring heating and hot water availability) there is no option for a
conscious reduction of installs.
Modern facilities and services
New Kitchens, Bathrooms and Showers 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Budget overspend is anticipated due to costs and demand for budget being higher than anticipated at time of budget setting.
Mitigating Action
None available at this time.
Anticipated Outcome
Project to complete over budget.
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Void works to continue into 22/23 to bring void properties up to a lettable standard.  The high number of voids has led to a higher
than expected demand for this budget, resulting in a projected overspend in 22/23. 
Mitigating Action
None available at this time
Void house strategy programme
Spend on Void Properties to bring them up to letting standard
Anticipated Outcome
Void properties to be brought up to lettable standard, budget to overspend.
Mitigating Action
Contracts team working to maximise progress and outturn where able to.
Anticipated Outcome
Full spend unlikely to met and balance to carry forward to 23-24
Defective structures/component renewals
Defective structures 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Slightly behind schedule and anticipated to be under full spend target. Balance to be reprofiled to 23/24.

Page 5

WEST DUNBARTONSHIRE COUNCIL APPENDIX 4
HRA CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
MONTH END DATE
PERIOD 9
Budget Forecast Spend
£000 £000 % £000 £000 %
31 December 2022
Budget Details Project Life Financials
Spend to Date Variance
11
Project Life Financials 5,092 1,105 22% 5,491 399 8%
Current Year Financials 969 1,105 114% 1,368 399 41%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
12
Project Life Financials 106,883 1,422 1% 106,556 (326) 0%
Current Year Financials 39,645 1,422 4% 11,972 (27,673) -70%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
Sites to be reprofiled £m
Aitkenbar Primary School (374)
Clydebank East (13,754)
Queens Quay Site B (629)
Queens Quay Site C (878)
Pappert (4,481)
Bank Street (575)
Willow Park Phase  1 (1,989)
Mount Pleasant (2,420)
Future New build sites (2,246)
TOTAL OF ALL PROJECTS (27,346)
Environmental renewal works, paths/fences/walls/parking area's
Environmental renewal works, paths/fences/walls/parking areas
Anticipated Outcome
Full budget spend, with overspend anticipated.
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
An overspend is anticipated in 22-23 due to level of demand and material costs being higher than expected at time of budget
setting.
Mitigating Action
None available at this time.
Main Issues / Reason for Variance
Progress will continue to be monitored as the year progresses.  The £27.673 variance is made up of £0.326m underspend and a
reprofiling of £27.346m into 2023/24 onwards . Summary of reprofiled sites together with site specific updates as follows:-
Clydebank East -Clydebank East - 88 units to be completed on the site. Project spend now requires to be reprofiled. Anticipated
site start of June 2022 has been delayed as a result of assessing remediation strategy options, while the exercise has proved to
be a lengthy process the options have identified an affordable method which is estimated to be around £9m less costly than the
original proposed method.  We are now in receipt of revised tender costs and a pre start meeting is scheduled for January prior to
works commencing later in January.  The remediation methods will take longer and will be the first phase of the development and
the construction of the new homes will likely commence in April 2023. £13.754m of the £18.754m current year budget will be
required to be reprofiled into 23/24.
Queens Quay Site B - 29 units now completed on the site. Project spend now requires to be reprofiled. Retention figure of
£0.629m budgeted to be paid out in 2022/23 will now be reprofiled to be paid in 2023/24 to allow time to finalise account.
Queens Quay Site C  – 20 units to be completed on site. Project spend now requires to be reprofiled. The budget provision is to
acquire additional land within Queens Quay to enhance the Site C proposals, the discussions with CRL/Rydens have been
protracted but we intend to make an offer shortly subject to the DV valuation being received. This will be reprofiled into 2022/23
(£1.878m).
Affordable Supply Programme
Affordable Housing Supply Programme 
Planned End Date  Forecast End Date
Aitkenbar - Fully complete. Project spend now requires to be reprofiled. Retention figure of £0.374m budgeted to be paid out in
2022/23 will now be reprofiled to be paid in 2023/24 to allow time to finalise account.

Page 6

WEST DUNBARTONSHIRE COUNCIL APPENDIX 4
HRA CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
MONTH END DATE
PERIOD 9
Budget Forecast Spend
£000 £000 % £000 £000 %
31 December 2022
Budget Details Project Life Financials
Spend to Date Variance
TOTAL OF ALL PROJECTS
Project Life Financials 166,246 12,763 8% 170,325 4,079 2%
Current Year Financials 53,876 12,763 24% 26,285 (27,592) -51%
Pappert - 27 units to be completed on site . Projects spend now requires to be reprofiled.  The anticipated site start of October
2022 will not be realised due to a number of factors that have caused the project to miss a number of milestones, notably a longer
than anticipated procurement process and the subsequent delay in developing a contract/tender preparation forced us to miss a
pricing window from the contractor, we anticipate a new cost price in November with a site start of March 23.  It is expected
£0.500m will be paid out in 2022/23 with the remaining £4.481m to be reprofiled into 2023/24
Future New Build gap sites  – Project spend now requires to be reprofiled. Ongoing work to acquire private and Council owned
sites to finalise wider strategy . Expected that there will be  spend of £0.500m this during 2022/23 so £2.246m will be reprofiled
into 2023/24.
Anticipated Outcome
Project will still complete and will meet revised spend profiles .
Bank Street - 20 units to be completed on the site. Project spend needs reprofiled due to wider strategic reasons and potential
reprovisioning of sheltered accommodation which will require consultative exercise . Revised estimated start date July 2023,
estimated completion January 2025.  Project is currently at feasibility stage.  Likely outturn for 22/23 for the Bank Street site is
expected to be circa. £0.420m with £0.575m therefore required to be reprofiled to 23/24.
Willox Park Phase1 - 17 units to be completed on site. Project spend now requires to be reprofiled  . Pre planning discussions
were more involved than anticipated and required some re designing which has resulted in delay to estimated start date from
January 2023 to June 2023 with estimated completion May 2024. Demolition complete, and site investigation under way.  Officers
ready to submit to for full planning.  Tender application expected to go out April 23.  At this stage spend in the current year is
expected to be £0.400m against budget of £2.390m resulting in reprofiling rquirement of £1.989m.
Mount Pleasant - 25 units to be completed on site. Project spend now requires to be reprofiled. Unanticipated longer time frame
for demolition (9 months) has delayed this project by 6 months, now estimating a March 2023 site start, although demolitions are
planned for next month. £0.100m expected costs in 22/23, resulting in reprofiling requirement of £2.420m to 23/24.
Bonhill Gap Site - 32 units to be completed on site.  Estimated start date July 2023 and estimated completion September 2024. 
The project is currently  at design stage with spend of £0.420m expected in 22/23.  No reprofilng required.
Mitigating Action
Staff will work closely with all stakeholders to try and ensure timely resolutions of issues as they arise.

Page 7

WEST DUNBARTONSHIRE COUNCIL APPENDIX 5
HRA CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
MONTH END DATE
PERIOD 9
Budget Forecast Spend
£000 £000 % £000 £000 %
1
Project Life Financials 2,487 396 16% 2,487 0 0%
Current Year Financials 474 396 84% 474 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
2
Project Life Financials 1,557 324 21% 1,557 0 0%
Current Year Financials 664 324 49% 664 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
3
Project Life Financials 170 0 0% 170 0 0%
Current Year Financials 40 0 0% 40 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
4
Project Life Financials 17 0 0% 17 0 0%
Current Year Financials 17 0 0% 17 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
31 December 2022
Budget Details Project Life Financials
Spend to Date Variance
Special needs adaptations
None available at this time
Anticipated Outcome
Full budget spend, possibility of overspend.
Adaptations to Housing for Special Needs 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets. Possibility of overspend due to price increases and demand levels rising.
Mitigating Action
Better Homes Priority Budget
Priority projects as prioritised by the Better Homes Group 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
A number of priority initiatives, supported by the Better Homes Project Board,  are being investigated and are envisaged to have a
positive impact on the current council housing stock and budget, with works expected to progress in 22/23.
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Gypsy Travellers Site
Gypsy/ Traveller Site improvements 
Planned End Date  Forecast End Date
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Community Safety Projects
Community Safety Projects 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.
ITEM 13

Page 8

WEST DUNBARTONSHIRE COUNCIL APPENDIX 5
HRA CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
MONTH END DATE
PERIOD 9
Budget Forecast Spend
£000 £000 % £000 £000 %
31 December 2022
Budget Details Project Life Financials
Spend to Date Variance
5
Project Life Financials 36 0 0% 36 0 0%
Current Year Financials 36 0 0% 36 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
6
Project Life Financials 19,841 3,556 18% 19,841 0 0%
Current Year Financials 4,455 3,556 80% 4,455 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
7
Project Life Financials 257 32 13% 257 0 0%
Current Year Financials 75 32 43% 75 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
Redployable CCTV Cameras
Purchase of 5 redeployable CCTV cameras for Housing use
Anticipated Outcome
Full budget spend
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
5 redeployable cameras to be purchased as planned.  No issues anticipated.
Mitigating Action
None required
Targeted SHQS /EESSH compliance works
This budget is to focus on work required to maintain the SHQS compliance and energy
efficiency  with WDC housing stock. 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets. Current progress is slightly behind cumulative monthly targets, work is
progressing and numbers improving.
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Mitigating Action
None required
Anticipated Outcome
Full budget spend
External stores/garages/bin stores/drainage component renewals
This budget is to focus on external stores/garages/bin stores etc. component renewals as
identified and recommended from the housing stock condition survey. 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.

Page 9

WEST DUNBARTONSHIRE COUNCIL APPENDIX 5
HRA CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
MONTH END DATE
PERIOD 9
Budget Forecast Spend
£000 £000 % £000 £000 %
31 December 2022
Budget Details Project Life Financials
Spend to Date Variance
8
Project Life Financials 273 76 28% 273 0 0%
Current Year Financials 91 76 83% 91 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
9
Project Life Financials 280 0 0% 280 0 0%
Current Year Financials 54 0 0% 54 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
10
Project Life Financials 103 0 0% 103 0 0%
Current Year Financials 103 0 0% 103 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
11
Project Life Financials 581 0 0% 400 (181) -31%
Current Year Financials 181 0 0% 0 (181) -100%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
Secure entry component renewals
This budget is to focus on secure door entry component renewals as identified and
recommended from the housing stock condition survey and appropriate council officer referrals.
Anticipated Outcome
Anticipated not to meet full spend despite best efforts.
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
This programme always presents challenges with owner liaison and reaching agreements to install door entry where none exists,
this contributes directly to achieving SHQS compliance for this element and reducing abeyances. The budget reflects the demand
and number of installs required but it is acknowledged that full uptake is unlikely.
Mitigating Action
Officers continue to liaise with owners to encourage agreement for install.
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.
Mitigating Action
None required
Energy improvements/energy efficiency works
Energy improvements/ efficiency works (e.g. loft insulation, pipe/tank insulation, draught
exclusion)
Anticipated Outcome
Full budget spend
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Improvement works (Risk St)
Risk Street Over clad 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.
Contingencies
This is a contingent budget for unforeseen matters which may arise during the year. 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No Issues, contingent budget for unplanned spend
Mitigating Action
none at this time
Anticipated Outcome
Spend as required

Page 10

WEST DUNBARTONSHIRE COUNCIL APPENDIX 5
HRA CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
MONTH END DATE
PERIOD 9
Budget Forecast Spend
£000 £000 % £000 £000 %
31 December 2022
Budget Details Project Life Financials
Spend to Date Variance
12
Project Life Financials 1,135 126 11% 1,135 0 0%
Current Year Financials 215 126 58% 215 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
13
Project Life Financials 2,378 0 0% 2,378 0 0%
Current Year Financials 800 0 0% 800 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
14
Project Life Financials 7,729 933 12% 7,729 0 0%
Current Year Financials 2,019 933 46% 2,019 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
15
Project Life Financials 13,031 1,878 14% 13,031 0 0%
Current Year Financials 2,504 1,878 75% 2,504 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Asbestos management works
This budget is to fund work associated with the management of current asbestos legislation and 
Planned End Date  Forecast End Date
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Buy Backs
This is a budget to undertake specific projects that will deliver housing policies/strategies,
example: Ex local authority and mortgage to rent buy-back scheme
Multi Story Flats  ( including Fire Risk Assessment Works)
High Rise Fire Safety Measures 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No Issues, anticipated to meet spend and revised targets.
Anticipated Outcome
Budget spend anticipated, should criteria be met.
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
The main objective of the Buy Back Scheme is to bring former council properties that were sold through the RTB scheme, back
into council use.  These properties must assist the council with reducing housing need on the waiting list and where appropriate
assist with external capital works.  For these reasons, any purchase is subject to stringent criteria to ensure accountability and
value for money for existing tenants.  Spend in 22/23 will therefore be dependent on these factors.  So far this year, 15 homes
have been purchased, with the target to deliver an additional 20 homes each year through the buyback scheme.
Mitigating Action
None required.
Main Issues / Reason for Variance
No Issues, budget for salaries and support
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Salaries/central support/offices
Allocation of costs from other WDC services who support the HRA capital programme 
Planned End Date  Forecast End Date

Page 11

WEST DUNBARTONSHIRE COUNCIL APPENDIX 5
HRA CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
MONTH END DATE
PERIOD 9
Budget Forecast Spend
£000 £000 % £000 £000 %
31 December 2022
Budget Details Project Life Financials
Spend to Date Variance
TOTAL OF ALL PROJECTS
Project Life Financials 49,874 7,321 15% 49,694 (181) 0%
Current Year Financials 11,727 7,321 62% 11,547 (181) -2%

Page 12

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
HRA CAPITAL PROGRAMME
ANALYSIS OF RESOURCES
MONTH END DATE
PERIOD 9
Budget Forecast Spend
£000 £000 % £000 £000 %
1
Project Life Financials (48,826) (4) 0% (48,826) 0 0%
Current Year Financials (30,006) 0 0% (10,480) 19,526 -65%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
2
Project Life Financials (42,531) 0 0% (38,702) 3,829 -9%
Current Year Financials (9,215) 0 0% (5,386) 3,829 -42%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
3
Project Life Financials (124,667) (19,723) 16% (124,667) 0 0%
Current Year Financials (26,286) (19,723) 75% (21,548) 4,738 -18%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
Due to spend being later than anticiapted , receipt of grant will also be later than budgeted.
Mitigating Action
Income budget wil be reprofiled to match reprofiled spend
Anticipated Outcome
Income will be received in 2023/24
Main Issues / Reason for Variance
31 December 2022
Budget Details Project Life Financials
Spend to Date Variance
New Build Grant 
Grant to facilitate new build housing 
Planned End Date  Forecast End Date
CFCR
This is capital spend which is funded by revenue budgets
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Income from Revenue reduced to offset adverse varainces in HRA revenue
Mitigating Action
None required
Anticipated Outcome
Reduced CFCR
Prudential Borrowing
Prudential borrowing is long term borrowing from financial institutions that has been approved
for the purposes of funding capital expenditure
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Prudential borrowing is impacted by programme delivery therefore due to reprofiling, the requirement in 2022/23 will be less.
Mitigating Action
None available at this time.
Anticipated Outcome
While prudential borrowing requirement is likely to be less than budgeted in the current financial year this is anticipated to catch
up over the programme life.
ITEM 13

Page 13

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
HRA CAPITAL PROGRAMME
ANALYSIS OF RESOURCES
MONTH END DATE
PERIOD 9
Budget Forecast Spend
£000 £000 % £000 £000 %
31 December 2022
Budget Details Project Life Financials
Spend to Date Variance
New Build Grant
4
Project Life Financials (96) (357) 372% (513) (417) 434%
Current Year Financials (96) (357) 372% (417) (321) 334%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
TOTAL RESOURCES
Project Life Financials (216,120) (20,084) 9% (212,708) 3,412 -2%
Current Year Financials (65,604) (20,080) 31% (37,831) 27,772 -42%
Other Capital Income
Other Income to capital
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
£0.096m estimated income from Glasgow Airport Authority is now not expected to be received in 22/23 as works have not
progressed.  Works and therefore income now expected 23/24.  £0.416m Scottish Governmant Grant income estimated in
relation to buy backs.
Mitigating Action
None available
Anticipated Outcome
Income will be received when due

Page 14

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
HRA CAPITAL PROGRAMME
ANALYSIS OF AFFORDABLE HOUSING SUPPLY PROGRAMME
MONTH END DATE
PERIOD 9
Budget Spend to Date Forecast Spend
£000 £000 £000 £000 %
RAG
Status
St Andrews School 636 129 290 346-   -54% 
Haldane Primary School 148 149 167 20 13% 
Aitkenbar Primary School 652 278 652 - 0% 
Clydebank East 26,474 58 26,474 - 0% 
Creveul Court 58 59 58 - 0% 
Queens Quay Site B 1,259 404 1,259 - 0% 
Queens Quay Site C 6,198 1 6,198 - 0% 
Pappert 7,332 3 7,332 - 0% 
Lilac Avenue 2,676 - 2,676 - 0% 
Bank Street 4,674 - 4,674 - 0% 
Clydebank Health Centre 6,930 6 6,930 - 0% 
Willox Park Phase1 3,817 59 3,817 - 0% 
Willox Park Phase2 6,300 - 6,300 - 0% 
Mount Pleasant 4,200 74 4,200 - 0% 
Silverton 2,100 - 2,100 - 0% 
Fees, Staffing Costs, contingency 4,005 28 4,005 - 0% 
Gap sites
Bonhill Gap Site 420 174 420 - 0% 
Future New build sites 16,824 - 16,824 - 0% 
Total Expenditure 94,703 1,422 94,376 (326) 
31 December 2022
Site
Project Life Financials
Variance
ITEM 13