WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer, Housing and Employability
Housing and Communities Committee: 22 February 2023
__________________________________________________________________
Subject: More Homes West Dunbartonshire – West Dunbartonshire Council
Affordable Housing Supply Delivery Programme 
1. Purpose
1.1 This purpose of this report is to provide the Housing and Communities
Committee an update on progress with West Dunbartonshire’s More Homes
Programme which oversees the delivery of the Council’s new home building
programme.
2. Recommendations
2.1 It is recommended that the Housing and Communities Committee:
(i) Note the content of the report and the progress made to date in the
delivery of the Council’s More Homes West Dunbartonshire approach
including the practical completion and handover of the latest development
project at Queens Quay (Site B);
(ii) Note the commencement of groundworks at the Clydebank East housing
development in January 2023;
(iii) Note the successful funding application to the Scottish Government’s
Vacant and Derelict Land Fund of £1.25m to support the Pappert housing
development;
(iv) Approve the transfer of the site at Queen Mary Avenue, Clydebank with
vacant possession at the cost of £140,000 from the Council’s General
Fund to the Housing Revenue Account for the delivery of new Council
homes; and
(v) Note the delay in the acquisition of the former Clydebank Health Centre
site at the cost of £707,400 from NHS Greater Glasgow and Clyde for the
delivery of new Council homes.
3. Background
3.1 In West Dunbartonshire the Affordable Housing Supply Programme (AHSP) is
delivered through a More Homes West Dunbartonshire strategic approach
which was initially tasked and has successfully delivered over 1000 new
ITEM 11
(Correct version)

Page 2

affordable homes in West Dunbartonshire by 2022 and includes the Council’s
own ambitious New House Building Programme. 
3.2 The Council’s latest practical completion took place at the Queens Quay
development in September 2022 delivering 29 new Council homes in a key
regeneration area as part of a wider development which has delivered 146
new social rented homes.  These are first residential properties to be heated
from the Council’s Queens Quay District Heating Network.   
3.3 These 29 new homes, are in addition to the completion of the Council’s first
fully dementia designed development at Creveul Court, Alexandria and other
exemplar developments in Haldane, Aitkenbar, Bellmsyre, Dumbarton
Harbour and St Andrews, Clydebank.  The Council have now completed 12
new build developments since 2013 and are the largest developer of social
homes in West Dunbartonshire delivering 496 new homes to date as outlined
in Table 1 below: 
Table 1:  Completed Council New Build
Project No. of
Units
Completion
Date
Granville Street (Phase 1), Clydebank 24 July 2013
Miller Road, Alexandria 15 October 2013
Granville Street (Phase 2), Clydebank 9 February 2014
Central Bellsmyre, Dumbarton 36 December 2014
Hillstreet Square, Dumbarton 37 August 2015
Second Avenue, Clydebank 40 April 2018
Creveul Court, Alexandria 22 April 2021
Aitkenbar Primary School 55 July2021
Haldane Primary School 58 August 2021
St Andrews, Clydebank  126 October 2021
Dumbarton Harbour, Dumbarton 45 December 2021
Queens Quay, Site B, Clydebank 29 August 2022
Totals 496   
3.4 The Strategic Housing Investment Plan (SHIP) 2023-2027, outlining West
Dunbartonshire’s Affordable Housing Supply Programme through the More
Homes West Dunbartonshire approach was approved by the Housing and
Communities Committee in November 2022. The SHIP outline plans to meet
the new Council Administration’s aim of delivering 2500 new affordable and
social rented homes over the next 10 years.  The Council has recently
received positive feedback from the Scottish Government in respect of our
recent SHIP. 
4. Main Issues 
More Homes West Dunbartonshire - Delivery Programme 
4.1 Building new affordable homes has an important role to play in revitalising
local economies and assisting with post-pandemic recovery plans.  It is also
clear that the need for affordable homes has and will increase in the current
economic environment. Our More Homes West Dunbartonshire approach is
an ambitious plan that aims to continue the positive momentum of the delivery

Page 3

of much needed Council homes in West Dunbartonshire and will significantly
assist the Council’s aim to deliver 2500 new social and affordable homes by
2032. 
4.2 As the biggest affordable housing developer in West Dunbartonshire, the
Council has identified a number of future development sites for new council
homes to address existing and new housing need. The design of these homes
will further develop, improve and exceed current best practice, providing
sustainable homes using innovative technology and delivering on our low
carbon ambitions including passivhaus and other net zero carbon
opportunities. 
4.3 The Strategic Housing Investment Plan and HRA Capital Plan outlined the
plans the Council have for meeting their new build ambitions.  Some of the
initial plans were and continue to be impacted as a result of global issues
revised new build targets for the Council are outlined below:   
Table 2: Council New Build Programme 
*Current Planning figures 
4.4 Updates for each site are noted below: 
Clydebank East: 
Site/Developer Number of
Units
Number of
Specialist
Provision 
Est Site
Start
Est Completion
Date
Clydebank East,
Clydebank 88  9 
January
2023
Spring 2025
Mount Pleasant 25 25 March
2023
Summer 2024
Pappert, Bonhill
Alexandria 27  3
October
2023
Autumn 2024 
Dennystoun
Forge
20 20 April 2024  Autumn 2024
Willox Park 17 17 June 2023 Summer 2024
Bonhill Gap Sites* 35 4 July 2023 Winter 2024/25
Bank Street,
Alexandria
20 20 Autumn
2023
Winter 2024/25
Queens Quay
Site C
100 10 Autumn
2023
Spring 2025
Clydebank Health
Centre*
38 5 Autumn
2023
Spring 2025
Clydebank Gap
Sites*
50 10 Spring
2024
Summer 2025
Buyback Scheme
(50 per year)
250 25 2023/24 2027/28
670 units 148 units

Page 4

Works commenced on this development on 23rd January 2023, as reported to
the Housing and Communities Committee in November 2022 the initial
programme will be the remedial works and external drainage, a construction
site start is programmed for May 2023.  The total programme for the works
will be 116 weeks. 
The development at Clydebank East will see the completion of a major
housing led regeneration of a key priority area identified in the Local Housing
Strategy and will be the Council’s first fully zero carbon housing development
and marks a significant milestone in our transition to net zero approved at the
August 2022 meeting of the Housing and Communities Committee. 
Mount Pleasant, Old Kilpatrick 
The demolition of the former care home at the site completed in December
2022 ahead of schedule. 
We have had an initial consultation with the Old Kilpatrick Community Council
where we presented our concept of providing between 25 units of housing in a
similar style to Creveul Court, one and 2 bedroom flats and terraced 1 / 2
bedroom terraced cottages with private gardens. 
An Employers Agent (NBM) have been appointed for this project, they were
previously the EA for the recently completed Queens Quay development.  The
construction procurement strategy is well advance and we intend to appoint a
design and build contractor in the next couple of weeks. 
Pappert, Bonhill 
The development of 27 new homes comprises 7 Passivhaus homes and 20
homes meeting the net zero ready standard. 
House Type Sustainability Standard Number of New
Homes
House 3bed/4 person Passivhaus 4
House 3bed/5 person Passivhaus 3
House 3bed/5 person Net Zero 6
House 4bed/6person Net Zero 4
House 4bed/7person Net Zero 1
Flat 2bed/3person w/c Net Zero 3
Flat 1 bed/2person Net Zero 6 
We have commenced preplanning consultation in advance of submitting a
formal planning application, however we don’t anticipate planning approval
now until October 2023.  This development was also successful in a funding
application to the Scottish Government’s Vacant and Derelict Land Fund and
has been awarded £1.25m funding, this will be additional to grant support
provided through the wider Affordable Housing Supply Programme.  The
additional funding is to be welcomed, however the funding is conditional on

Page 5

the Council fulfilling a number of key project milestones and this will require a
strong collaborative focus across all Council teams involved in the project
delivery to ensure there is no funding clawback and subsequent reputational
damage.   
We have visited the site with housing officers who will assist in some pre
consultation with adjoining residents, schoolchildren and the Bonhill
Community Garden, the focus of the consultation will be the provision of
future play. 
Dennystoun Forge Gypsy/Traveller Site 
A submission was made to the Scottish Government for support funding from
their Gypsy/Traveller Accommodation Fund for significant improvements to
the Dennystoun Forge site, including new energy efficient chalet type
accommodation following a consultation exercise with site residents.
However, we were notified that this submission was unsuccessful at this point.
We have since engaged the Scottish Government following the outcome of
this and are providing more information in terms of our application, this will
allow our proposal to be reassessed and has the potential to achieve the
funding award.  This will be determined over the next few months 
Willox Park, Doveholm, Dumbarton 
All demolition works are now complete with Practical Completion Certificate
issued to contractor. The site has been secured in anticipation of the
construction phase of the development. 
A procurement strategy has been completed to appoint a number of
development consultants to progress the design to a full planning application 
Bonhill Gap Site Strategy 
A pre-planning application on the development of the 4 gap sites has been
made, and a procurement strategy is now in place. 
Bank Street, Alexandria 
The council is currently developing a proposal for 20 sheltered/amenity
housing units in partnership with the HSCP. This will include an options
appraisal in terms of the existing provision within the local area. 
There are a number of infrastructure constraints within the site including a
main sewer which may affect the viability of the site. We are currently working
on pre-planning drawings for submission in early 2023 based on the
conclusion of the discussions with HSCP. 
Queens Quay, Site C, Clydebank

Page 6

The Council is currently developing a design to deliver a projected 20 units on
this site to complement the housing mix within sites A and B.  This
development will also be designed to meet low/zero carbon principles and
linked to the Queens Quay district heating network
.
Pre-planning response was received on the 25th February highlighting
concern of the WDC development proceeding in isolation. We have adopted
a, proactive response to this issue and have developed masterplan diagrams
incorporating the surrounding sites and have instructed the District Valuer to
value these adjacent site to Queens Quay C with a view to purchasing
additional land to deliver more affordable housing in the Queens Quay
regeneration site.  If this is achieved we would seek to develop a mixed tenure
approach to any expanded development site. 
Clydebank Health Centre 
The Council are continuously looking for opportunities to provide additional
new build council homes and this includes through the Scottish Government’s
trawl process which seeks to utilise public sector land sales for the delivery of
key national ambitions which includes the delivery of new homes. The former
Clydebank Health Centre in Kilbowie Road, Clydebank was identified through
this process and approval was granted to acquire the site from NHS Greater
Glasgow and Clyde at the November meeting of the Housing and
Communities Committee for £707,400. 
However, NHS Greater Glasgow and Clyde have informed us that they no
longer wish for accountancy purposes for the transaction to complete in
financial year 2022/23, instead they will only conclude the sale of the land in
financial year 2023/24.  This is disappointing in terms of the Council’s planned
acquisition of the site in this financial year would have enabled an additional
£707,400 from the Scottish Government’s Affordable Housing Supply
Programme funding.  This money is in effect now lost to the wider West
Dunbartonshire economy and to the wider national Affordable Housing Supply
Programme. 
As a result of the above, the Council and NHS Greater Glasgow and Clyde
have instructed the District Valuer to revalue the site to allow the acquisition to
conclude in the next financial year.  We will provide an update and seek
approval to acquire the land for development purposes at the next Housing
and Communities Committee.  We are not anticipating any significant
difference in the valuation, however for Scottish Government grant purposes a
valuation is only valid for a 6 month period (the site was previously valued in
December 2021. 
Potential Additional Sites 
The Council is internally assessing a potential development opportunity at an
area of land in its ownership at Queen Mary Avenue, Clydebank. The site 
approximate site area from Ordnance Survey based digital mapping

Page 7

system indicates the gross site area is approximately 0.90 acres  The site
contains the former Drumry Community Centre which was declared surplus to
requirements in recent years.  If it is approved that this area should be
transferred for a gross value of £140k to the Housing Revenue Account for
the purposes of developing social housing an indicative massing exercise has
established that a development of 16 new homes could be delivered. 
In addition, we are exploring an opportunity to develop a gap site in Council
ownership in Hardgate to provide 2 new homes. 
Buyback Programme 
The Council’s buyback programme which incorporates the Mortgage to Rent
Scheme has purchased 17* new homes to date in 2022/23.  It is the intention
to bring a full annual update report to the next meeting of the Housing and
Communities Committee in May 2023 in relation to the buyback scheme. 
4.5 The Housing Team are continuously looking for opportunities to provide
additional new build council homes and will bring any potential site to the
Housing and Communities Committee with as much information as possible
as part of the regular More Homes update paper. 
5. People Implications 
5.1 There are no people implications from this report. 
6. Financial and Procurement Implications 
Financial 
6.1 In March 2022 Council approved the Housing Capital Programme 2022-2027
which saw significant resources committed to the delivery of new council
homes in West Dunbartonshire.  An expenditure budget of £83.393m for the
affordable housing supply programme is factored into the HRA Capital
Programme this will be updated to reflect the income and expenditure
highlighted within this report.  As it currently stands, it is anticipated that this
programme will complete on project life budget. 
6.2 Influenced by Brexit, the current Covid-19 pandemic, Ukraine and other global
issues, the emergence of supply issues and subsequent cost increases has
begun to be felt across Scotland and the UK.  Whilst the impact of these is still
being examined, it is prudent to mention this as early as possible in order to
provide more detailed information at a future Committee when new tender
prices are known. 
6.3 We are likely to see this impact on all our future development sites. Housing
Development Officers and Finance will continue to assess the impacts in the
context of affordability of developments.

Page 8

Procurement 
6.3 All new development sites will be subject to new detailed procurement
strategies and the opportunities highlighted with 4.4 of this report will continue
to be prioritised. 
6.4 Where the contract award is less than £50,000, authority is delegated to
the Chief Officer in consultation with the Procurement Manager to instruct the
award of contracts for the planned revenue and capital spend detailed in this
report to suppliers providing the most economically advantageous offer to the
Council. 
7. Risk Analysis 
7.1 All Council new build projects have their own Risk Register which highlights
the risk within and out-with the project team’s control.  These are maintained
and adjusted on an on-going basis. 
7.2 With any new build project there is a risk that as the projects develop the cost
increases beyond the estimated contract cost.  Any additional borrowing
requirements, or conversely, cost savings will be reported to future meetings
of the Housing and Communities Committee. However, this is mitigated
through a target cost model approach in our current contract arrangements
within the Scottish Procurement Alliance (SPA) framework and Scotland
Excel. 
8. Equalities Impact Assessment (EIA) 
8.1 The proposal does not alter any existing policy or pattern of service delivery
and so is not considered to require an equalities impact assessment. 
9. Consultation 
9.1 As part of our previous rent consultation exercise, 92% of respondents
indicated their support for the Council’s ambitious plans to deliver the Housing
Revenue Account (HRA) new council house build programme. In addition,
there was positive support for the wider delivery of new build housing as part
of the recent Local Housing Strategy.  Regular updates on new build
development are provided to the West Dunbartonshire Tenants and Residents
Organisation at the bi-monthly liaison meetings. 
10. Strategic Assessment 
10.1 The Local Housing Strategy is the overarching document setting out the
strategic direction for housing across all tenures and informs the future
investment in housing and related services across West Dunbartonshire.
Having considered all the Council’s strategic priorities, this report and the

Page 9

provision of new supply social housing for rent contributes greatly to all
strategic priorities. 
Peter Barry
Chief Officer, Housing and Employability
Date: 9 February 2022 
Person to Contact: John Kerr – Housing Development and Homelessness
Manager, Housing Development and Homelessness
Team, telephone: 07793717981, email: john.kerr@west-
dunbarton.gov.uk   
Appendices: None 
Background Papers: West Dunbartonshire Council’s Local Housing Strategy     
Local Housing Strategy, Health Inequalities Impact
Assessment 
DVS Valuation Report Development Site/s: 
-Clydebank Health Centre  
-Queen Mary Avenue   
Wards Affected: All