Appendix 1; SD&P (Housing Asset & Investment and Building Services) Delivery
Plan 2022/23 - Interim Progress
2. Our Environment
Objective 6. Our neighbourhoods are sustainable and attractive
Action Status Progress Due Date Note Owner
Ensure the Council’s Housing stock maintains
compliance with the Scottish Housing Quality
Standard and reduce the number of properties
held in abeyance.
31-Mar-
2023
The main action related to all work streams contributing
to SHQS compliance and in general are progressing well.
However one of the key areas contributing to the drop in
compliance was in relation to Electric Installation
Condition Report (EICR) being valid in all properties.
There has been significant challenges with the EICR
completions in relation to access to properties. Building
Services are working with their specialist contractor in
attempts to improve this. This is currently projected to be
50 % compliant by end of Mar 23 increasing to 70 - 80%
by end of Aug 23.
Alan Young
Deliver the HRA Capital Investment programme
for 2022/23
31-Mar-
2023
Capital programme projects are progressing well, some
meeting or exceeding targets, others were behind mid-
year target position. Efforts to improve these are being
actioned. More detailed reports are provided regularly to
Better Homes and Housing Investment Board (HIB). It is
anticipated this action will be completed by year end.
Alan Young
Ensure the Council’s Housing stock progresses
towards the achievement of the energy
efficiency standard for social housing.
31-Mar-
2023
Energy Efficiency Standard for Social Housing (EESSH)
projects are progressing well, contributing to an increase
in homes meeting the energy efficiency standard. This is
Alan Young
ITEM 10

Page 2

Action Status Progress Due Date Note Owner
reconciled at year end. It is anticipated this action will be
completed by year end.
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Failure to deliver medical
adaptations in agreed
target timescales
This is monitored to ensure target
timescale of 79 days average for
housing medical adaptations is
adhered to ensure satisfaction with
the service and support those in
need of this service.
16-Dec-2022
Good in-year progress and cleared
many legacy applications, however
overall average days number will
still be high due to older jobs
completing.
No change to risk matrix.
Alan Young
Failure to maintain
Housing Stock
The risk that Council’s Housing
Stock are not fully fit for purpose
with consequent adverse impact
on our ability to deliver efficient
and effective housing for Council
tenants.
16-Dec-2022
Full programme of maintenance and
upgrade in place, with regular
monitoring and reporting.
No change to risk matrix.
Alan Young
4. Our Council
Objective 10. Our workforce is resilient and skilled where digital technology supports service delivery for our residents
Action Status Progress Due Date Note Owner
Develop and implement wellbeing,
employee engagement, equality
and training plans to enable
capabilities, improved resilience
31-Mar-2023
Progressing as planned. Regular updates, 121/Be the Best meetings
take place with Housing Asset & Investment Team and Building
Services. Discussions on any training needs or aims are held with
staff and considered where appropriate training or budget is
Alan Young;
Martin Feeney

Page 3

Action Status Progress Due Date Note Owner
and promotion of a diverse
workforce.
available. Scheduled or cyclical training is carried out via iLearn
portal. Building services are focusing on wellbeing in the service to
reduce absence levels and have implemented changes in recruitment
process to build resilience in teams. We will introduce a pilot of
condensed / flexible working in April 2023. It is anticipated this
action will be completed by year end.
Develop and implement employee
life cycle plans in line with the
People First Strategy to attract
and retain the workforce.
31-Mar-2023
Progressing as planned. Periodic review of workforce is undertaken in
consideration of current workload demands. The age profile of the
current staff may present workforce sustainability issues in the
coming years and workforce planning is vital. The current review of
Building Services will provide improved services and employee
satisfaction levels including review of role profiles. It is anticipated
this action will be completed by year end.
Alan Young;
Martin Feeney
Implement service review process
including role design, use of new
technology and new ways of
working to add resilience, address
gaps, and establish opportunities
for efficiencies
31-Mar-2023
Progressing as planned. We continue to review service delivery and
utilise where appropriate flexible working from home/remote/mobile
work styles for service resilience, utilising IT equipment solutions to
deliver their roles effectively and efficient. New technologies
including IHMS are being developed resulting in in-service
improvements. While roles within Building Services are
predominantly front line, flexible working arrangements are in place
across various teams. It is anticipated this action will be completed
by year end.
Alan Young;
Martin Feeney
Develop and implement training
plans and development
opportunities to improve
capabilities and resilience within
the workforce.
31-Mar-2023
Progressing as planned. Discussions on any training needs or aims
are held with staff and considered where appropriate. Scheduled or
cyclical training is carried out via iLearn portal. Statutory training is
being delivered as planned ensuring services meet all regulation and
regulatory obligations. Consultations are ongoing with TUs and
workforce in relation to workforce planning, multi-skilling, operating
hours etc. to improve efficiency, resilience and satisfaction levels. It
is anticipated this action will be completed by year end.
Alan Young;
Martin Feeney
Objective 11. Our Council is adaptable and focused on delivering best value for our residents

Page 4

Action Status Progress Due Date Note Owner
Implement improvement plan for Building
services – Phase 2
31-Mar-
2023
Action is on track. Phase 1 of the restructure of Building
Services is complete and phase 2 is progressing. All craft
role profiles have been reviewed and await review by Job
Evaluation Panel. The stores/ workshop services review is
progressing. A survey has being carried out to gain team
members ideas on service areas for improvement and a
workgroup set up to consider feedback as part of the
phase 2 review. Progress is also being made on ensuring
services gaps are addressed. The new management team
are leading change to improve service and this will be
evidenced by improved performance and increased
customer satisfaction levels. It is anticipated this action
will be completed by year end.
Martin Feeney
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Failure to implement
improvement plan to
ensure Building Services
are fit for purpose
The implementation of the
improvement plan will enhance the
effectiveness, efficiency and best
value of Building Services
20-Jan-2022
Good progress continues to be
made with actions in Building
Services Improvement Plan. Phase
1 of the review of Building Services
structure has been completed and
phase 2 is progressing.
Due to the continued progress the
risk assessment has reduced in both
likelihood and impact. Risk matrix
reduced from 3x3 to 2x2
Martin Feeney
Failure to implement
IHMS system across
building services
The effective implementation of
the IHMS system will delivery
efficiency, improve case tracking,
capture customer satisfaction and
improve service delivery.
20-Jan-2022
Good progress has been made on
Building Services IHMS
improvement action plan. Various
workgroups meetings continue to
review the use of the system
identifying and implementing
changes required. All team
members now have new mobile
devices, various amended and new
processes have been implemented,
Martin Feeney

Page 5

Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
improvements in stock management
processes are in place, new and
amended management information
reports have also developed and
introduced within Building Services
in 2022/2023 year to date. Work
continues on the wider cross
services IHMS improvement plan,
but are not reported within this risk
matrix.
The risk matrix has been changed to
capture improvement. 
Failure to meet citizen
expectation and service
standards
Risk of citizen dissatisfaction due
to us not doing what we say we
will when we say we will or not
completing required works first
time.
20-Jan-2022
Customer satisfaction is showing
gradual improvement year to date.
The service continues to reduce the
number of active repairs and the
percentage of these that are out
with their target times. Tenants /
customers are indicating in their
feedback increased satisfaction.
Improvement actions continue.
No change to risk matrix at this
time.
Martin Feeney
Failure to demonstrate
robust financial and
productivity systems
within building services
The development of new costing
model will mitigate against this
financial risk. Process change and
review will improve the system for
charging of works
20-Jan-2022
Regular finance meetings continue
where the financial processes,
system data management,
performance including effective
work planning and productivity are
monitored, scrutinised and where
necessary improvements actions
agreed. Open Book Recharge (OBR)
has been very successful in
ensuring regular and appropriate
levels of recharges are processed in
Martin Feeney

Page 6

Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
line with work completed and
income projections. OBR allow
improved visibility of service costs
which improves client / contractor
corroboration and scrutiny to
promote improved efficiency and
value for money services.
Due to the continued improvements
the risk assessment has reduced in
impact. Risk matrix reduced from
3x2 to 2x2.
Action Status
Cancelled
Overdue
Not on track
In Progress and on track
Completed
Risk Status
Alert
High risk
Warning
OK
Unknown